general checklist for the inspection of major accident hazards factories

advertisement
Helpline: 0141-2709659, 2709616
List of Documents and Procedure for
Registration and Renewal of Boiler
Registration
Step 1
Step 2
Step 3
Step 4
Step 5
Step 6
Step 7
Step 8
Visit RajFAB web application at www.rajfab.rajasthan.gov.in
Register and make a user ID & get password to use the application.
Keep following scanned documents available
i. Form No. II or Form No. XVII
ii. Form No.III
iii. Form No. IIIA.IIIB,IIIC
iv. Form No. IV or IV A
v. Drawings
vi. Other certificates such as dispatch note, certificate of welders,
certificate of Boiler Attendant/certificate of Boiler Operation Engineer,
test reports etc.
NOTE:- In case of unavailability of any of the certificate at the
time of applying, these can be handed over to Competent Person at
the time of Inspection.
Enter the web application at www.rajfab.rajasthan.gov.in
Click Boiler link as shown below –
Fill in all mandatory fields marked as * in Boiler registration form.
Upload available scanned documents.
You can choose either Departmental Inspecting Officer or Authorized
private person recognized as Competent Person to inspect your boiler
as shown below-
Step 9
Step 10
Step 11
Now click
button to go for payment option.
Make payment. To know about the fees schedule CLICK HERE.
Departmental Inspecting Officer or Authorized private person
recognized as Competent Person shall communicate date of inspection.
Boiler Registration:List of Documents:1.
2.
3.
4.
5.
Form No.II or Form No.XVII
Form No.III
Form No.IIIA.IIIB,IIIC
Form No.IV or IV A
Drawings
6. Test reports, Boiler Attendent’s/ BOE Certicicate copy
Procedure for Submission of Application
and Renewal of Boiler
Step 1
Step 2
Step 3
Step 4
Visit RajFAB web application at www.rajfab.rajasthan.gov.in
Register and make a user ID & get password to use the application.
Enter the web application at www.rajfab.rajasthan.gov.in
Click Boiler link under RENEWAL as shown below –
Step 5
Step 6
Fill in all mandatory fields marked as * in Boiler registration form.
You can choose either Departmental Inspecting Officer or Authorized
private person recognized as Competent Person to inspect your boiler
as shown below-
Step 7
Step 9
Step 10
Now click
button to go for payment option.
Make payment. To know about the fees schedule CLICK HERE.
Departmental Inspecting Officer or Authorized private person
recognized as Competent Person shall communicate date of inspection.
*Note: No document is required for renewal in case of no
change.
Guide for Boiler Registration, Renewal under Boilers Act,
1923
(Application, Procedure, Checklist and Document Required)
www.rajfab.rajasthan.gov.in
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Owner of the boiler may apply to inspector or competent person (Third
Party)
1. Application includes.
a. Basic details of boiler1. Maker’s number
2. Maker’s name and address
3. Year of Make
4. Total Heating surface area
5. Evaporation capacity
6. Intended working pressure
7. Type of boiler
b. Certificates as described below:1. Form No. II or Form No. XVII
2. Form No. III
3. Form No. IIIA, IIIB, III C
4. Form No. IV or IV A
5. Drawings
6. Others (such as dispatch note, certificate of welders,
certificate of Boiler Attendant, certificate of Boiler
Operation Engineer etc)
c. Approved Steam pipe line drawings
1. Submits proposed layout and design of steam
pipe line to CIFB
through boiler section (Clerk)
2. Clerk forwards to officer for technical examination
3. Officer examines and submit recommendation or comments to
CIFB
4. CIFB approves the drawings. (drawings are signed and
returned
to owner)
d. Certificates for steam pipe line
1. Form No. II
2. Form No. III
3. Form No. IIIA, IIIB, III C
4. Form No. IV or IV A
5. Drawings
6. Others
e. Consent letter for erection by a competent firm
f. Fees for boiler and steam pipeline
In case of packaged boiler (Case A)
2. Inspector informs date of inspection and hydraulic test to owner
3. After inspection Inspector prepares boiler inspection report and
steam pipe line Inspection report and submits one copy each to CIFB and
owner.
4. After completion of inspections Owner submits
a. remaining certificates
b. Test reports (if applicable) for steam pipe line1. Radiography
2. Other
5. Inspector prepares MR books (in hard copy)
6. Inspector submits all record, reports and MR book to CIFB
7. CIFB depute other officer for technical examination of all record,
reports and MR book.
8. The other officer recommends after technical examination to CIFB
9. CIFB approves and register the boiler and issues registration number
10. Inspector issues certificate of the boiler to use the boiler for 12
months.
In case of erection of boiler at site (Case B)
11. Inspector informs date of inspection
12. After inspection Inspector submits boiler inspection report and steam
pipe line inspection report one copy each to CIFB and owner.
13. Owner may apply for stage inspection in case of part of the material
received at site.
14.After completion of all inspections Owner submits
a. remaining certificates
b. test reports
b.i. For boiler
b.i.1. Radiography
b.i.2. SR
b.i.3. MPT
b.i.4. UT
b.i.5. Other
b.ii. For steam pipe lineb.
ii.1. Radiography
b.ii.2. SR
b.ii.3. MPT
b.ii.4. UT
b.ii.5. Other
15.Owner may also apply in between for any approval in change of
layout or change in design.
16. Owner applies to inspector after erection and testing (as in point
number 5)
for hydraulic test of
a. complete boiler and steam pipe line
b. part of the boiler
c. steam pipeline
d. other boiler component
17. Inspector informs date for hydraulic test to owner
18. After inspection Inspector prepares boiler inspection report and steam
pipe line inspection report and submits one copy each to CIFB and
owner.
19. Inspector prepares MR books Inspector submits all record, reports and
MR
book to CIFB
20. CIFB depute other officer for technical examination of all record,
reports
and MR book.
21.The other officer recommends after technical examination
22. CIFB approves and register the boiler and issues registration number
23. Inspector issues certificate of the boiler to use the boiler for 12
months.