ATTACHMENT B SCOPE OF WORK ARCHITECT-ENGINEER SERVICES PROJECT: CUF Engineering Services PROJECT NO.: 100-080-040-3520-1900 1. PROJECT DESCRIPTION This project provides for preparation of a Central Utility Facility (CUF) Strategic Development Plan, Steam & Chilled Water Metering Design Project and Future Design Projects to be identified in the Strategic Development Plan. The projects are located at the Central Utility Facility and the Civic Center Campus in Santa Ana, California. Jacobs will provide engineering utility master planning, energy modeling, economic analysis and design services to create a CUF Strategic Development Plan to improve the efficiency, safety and reliability of Civic Center Campus utility services. The circa-1968 original CUF building houses boilers, chillers, absorbers, feed water systems, air compressors, cooling towers, electrical substations and other critical utility infrastructure systems. In 2009 the CUF added two gas fired turbine engines producing a total of 10.4 megawatts of electricity, generating up to 128,000 pounds of steam and 7,000 tons of cooling. The CUF provides utility service on a 24 hour a day, 365 day per year basis serving County and other City, State and Federal buildings in the Civic Center Campus. This project will provide a thorough evaluation of CUF utility services and identify improvements and upgrades aimed at providing the following benefits to the County, in order of priority: 1. Return on Investment (ROI) 2. Reliability and Safety 3. Sustainability 4. Code compliance and risk management In addition to maximizing Cogen’s potential, it will be necessary to upgrade and maintain the CUF’s aging and inefficient infrastructure originally constructed in 1968. Maintenance, repair and upgrades have been completed to portions of the CUF’s system and to buildings served by the CUF in the Civic Center Campus, but many of the systems remain inefficient and are no longer reliable when operating in conjunction with the demands of the Cogen. CUF operations are threatened with equipment failures, pipe ruptures and other problems due to the deteriorating condition of the older equipment. The failure of any of the major systems at the CUF will impact services to the County, City, State, and Federal buildings in the Civic Center Campus. 2. THE DESIGN The design shall include but not be limited to the following: Scope of Work (Board Awarded) Form 3.09 Page 1 of 15 As of 4/28/11 ATTACHMENT B a) All necessary reports, designs, drawings, specifications, equipment and utility documents, construction observation and administration necessary to complete the reports and design and construction of these current and future projects. b) All facility assessments, 10-year strategic development plan preparation, design of specific projects and full construction documents necessary to obtain construction proposals through the public works procurement process on each specific project. c) Review of County energy efficiency plans (Navigant report) incorporation of recommendations and findings as appropriate. d) See additional attached pages for project specific design program 3. REFERENCE INFORMATION Various reports, existing documentation, and as-built plants of County facilities. 4. ARCHITECT-ENGINEER GUIDE Services shall be in accordance with the latest County A-E Guide and Computer Aided Design Guide and other State or federal energy requirements. 5. ENERGY CONSERVATION The design shall fully consider the conservation of energy and water as indicated in the A-E Guide and shall meet the requirements of Title 24 of the California Administrative Code. Furthermore, design(s) shall consider recommendations on energy efficiency systems and optimization of utility systems. 6. CODES AND REGULATIONS The design shall meet all Federal, State, and County applicable codes, State criteria for the physically handicapped, the requirements of Americans with Disabilities Act (ADA), requirements of the State Department of Industrial Safety and local fire department regulations. 7. 8. LEGAL REQUIREMENTS a. EIR Procedures: Prepare initial study report (if applicable). b. Compliance with General Plan. (Verify with County or City as applicable.) ARCHITECT-ENGINEER REVIEWS A-E shall review all drawings for inconsistencies, completion and constructability prior to the 100% submittal to OCPW/OC Facilities/A&E Project Management, and County Building Regulation. 9. PLAN REVIEWS BY ALL COUNTY PERSONNEL Any and all changes in plans due to County review shall be the responsibility of the A-E. Any and all costs for design revisions shall be borne by the A-E, except for those changes made after approval of design to proceed with next phase. Plans for review shall be full size sheets. 10. COORDINATION Coordinate design through the Project Manager of OCPW/OC Facilities Operations/Project Management 11. COMMUNICATIONS, GRAPHICS Not applicable Scope of Work (Board Awarded) Form 3.09 Page 2 of 15 As of 4/28/11 ATTACHMENT B 12. CAD DATA REQUIREMENTS The submission of all CAD data files, in order of preference, must be in AutoCad. The media format must be recordable/rewritable compact discs compatible with the County data system and approved in advance. 13. COST OF CONSTRUCTION Documents prepared to permit construction within a budget to be specified by the County at the time of bidding, between 2012 and 2021, depending on the project. 14. PHASE 1 – CUF 10-YEAR STRATEGIC DEVELOPMENT PLAN (SDP) SDP Task 1 - Research and review existing CUF operations, facilities, equipment, operational procedures, etc. Perform a facility assessment of CUF, Civic Center Campus buildings served by CUF and potential new CUF customers. a. Jacobs will initiate background research for the preparation of the Development Plan by conducting field walkdowns of the CUF and connected facilities. Data gathering activities within the CUF to include collection of equipment nameplate data (chillers, boilers, cooling towers, combustion turbines, condensers, pumps, etc), review of system connectivity within the plant (piping connections and control system interfaces), review and comparison of system alignments within the plan for comparison to available as-built documentation, and overall review of system age, condition and operability for assessment of remaining useful life. Available service and maintenance logs will be reviewed to assist with useful life determination. Existing CUF system capacities (steam production, chilled water production, electrical generation) and redundancies will be identified, along with operational limitations and restrictions. i. Deliverables associated with this subtask will include an inventory list of existing equipment (in Microsoft Excel format) as well as a list of planned building upgrades. b. Jacobs will conduct walkdowns of individual Civic Center Campus buildings connected to the CUF to collect electrical and thermal utility-side equipment nameplate data, review system connectivity within the building (how building utilities and controls interface with CUF), review and compare system alignments within the plant for comparison to available as-built documentation, and overall review of system age, condition and operability for assessment of remaining useful life. Available service and maintenance logs will be reviewed to assist with useful life determination. This assessment will be limited to the utility systems serving the overall building from the CUF (e.g. pressure reducing stations, heat exchangers, transformers and pumps serving their respective steam, electrical and chilled water systems). Evaluation of dedicated building service systems (e.g. air handler systems and ductwork, etc.) may be evaluated as an additional service (detailed Section 18. Special Services, a. Detailed Building Energy Modeling) if warranted to better understand and define building operational limitations or deficiencies that may impose problems or inefficiencies onto the CUF. i. Deliverables associated with this subtask will include an inventory list of existing equipment (in Microsoft Excel format) as well as a list of planned building upgrades. c. Jacobs will interview plant operators and staff in responsible charge of individual building utilities to better understand operations, persistent problems and service Scope of Work (Board Awarded) Form 3.09 Page 3 of 15 As of 4/28/11 ATTACHMENT B limitations. Estimate includes two days of field time plus one additional day to interview staff in charge of Civic Center Campus buildings. Total estimate for this subtask not to exceed three days. The County will schedule and coordinate interviews with responsible personnel. Interviews will be conducted in parallel with field activities defined in subtasks a and b above. d. Jacobs, with direction and assistance from the County, will identify potential future customers that could be served by the CUF, and assess existing system alignments, thermal utility production equipment and electrical utility services. e. Jacobs will document known and/or calculated building loads (min and max steam load, min and max chilled water load, min and max electrical demand) to assist with analysis and modeling associated with evaluation of master plan improvement alternatives. Where loads are not known or metering data does not exist, Jacobs will work with the County to develop appropriate calculations based on available industry data with similar facility function, construction and climate to develop reasonable approximations of utility loads. f. Task 1 activities will culminate with delivery of a utility system condition assessment report, which will include major equipment inventory lists (featuring nameplate data, age, capacity and other relevant data), descriptions of each utility system alignment, connection and operation, descriptions of building services and operations and a list of deficiencies and operational issues warranting immediate action. Report will also capture institutional knowledge of systems and operations for documentation and record keeping purposes. Report will be submitted in a “live” format, suitable for revision and update through the life of the Strategic Development Plant and for future refinement and update. Report to be included as a section within the overall Strategic Development Plan report, and for use as a standalone utility system assessment report. SDP Task 2 - Develop a CUF 10-year Strategic Development Plan to identify major projects including cost estimates to provide for short and long-term infrastructure improvements to the system. Identify benefits of each improvement to support and establish return on investment goals. Improvements will: Demonstrate a reinvestment of energy savings back into the system infrastructure; demonstrate how existing operating conditions of equipment and current capacities impact operations; provide rationale for repair vs. replacement; provide cost analysis comparisons; identify risks to safety and/or reliability; identify current code and ordinance compliance issues – building and environmental; and provide life cycle cost estimates. Scope of Work (Board Awarded) Form 3.09 Page 4 of 15 As of 4/28/11 ATTACHMENT B a. Jacobs will develop a dynamic utility consumption model for the existing campus connected facilities to serve as a baseline for current energy consumption and utility demand. The model will be calibrated to closely match (within + 5% overall annual consumption) the actual CUF system consumption and demand data as identified with Task 1 activities. Modeling will be accomplished using Trane Trace 700 and other analysis tools as appropriate, to identify the current utility system (chilled water, steam and electrical) load profiles, and to identify capacity shortfalls that could emerge as new services are provided for planned or existing facilities not currently connected to the CUF. Modeling activities will specifically accomplish the following: i. ii. iii. iv. Verify existing chilled water system load profile, and identify improvements to add capacity and/or improve reliability to meet existing cooling loads and support the addition of other facilities (existing and/or future) for CUF chilled water service. Verify existing steam system load profile and identify improvements to add capacity and/or reliability to meet the existing steam demand and support the addition of other facilities (existing and/or future) for CUF steam service. Verify the existing electrical consumption and demand on the Civic Center Campus, and evaluate the capacity of the existing electrical distribution system for load flow and feeder ampacity (using SKM Tools software) to meet the current electrical loads and support the addition of other County facilities (existing and/or future) for CUF electrical service. Deliverable will include a load model that accurately describes and simulates operation of the CUF as connected to the Civic Center Campus. Model will be depicted with output in form of a load profile graph for electrical, steam and chilled water production in comparison to load over a given simulated year. b. Jacobs will develop chilled water and steam distribution models using hydraulic modeling software (AFT Fathom or Pipe2000) based on the configuration of the existing chilled water and steam distribution system piping. Models be calibrated to match existing operational data where available, creating a baseline scenario model. This baseline model will evaluate the capacity of the piping systems to delivery the full capacity of CUF utility production services to connected facilities. Potential future facility additions will also be evaluated building from the baseline model to determine bottlenecks and operational limitations that would require piping system upgrade or expansion. i. Deliverable will include a distribution model that accurately describes and simulates operation of the CUF thermal distribution utility systems. Model will be depicted with mapped output of nodal piping systems with pipe size, flowrate, velocity and pressure loss for each segment of the system. c. Sustainability Analysis: Jacobs will identify and characterize improvement options with respect to sustainability and carbon emissions. This activity will consider and define the implementation of projects related to energy and water conservation as part of the overall strategies presented for meeting the future utility needs of the Campus (e.g., recovery of blowdown for water reuse on campus, use and/or optimization of plant efficiency measures such as free cooling and heat recovery and utilization of low-carbon energy technologies). i. Deliverables associated with this subtask include a list of preliminary sustainability projects to be evaluated within the Strategic Development Plan. d. Greenhouse Gas Evaluation: Jacobs will develop a CUF-utility related Greenhouse Gas (GHG) Emissions Reduction Program Plan, evaluating individual CUF projects, associated costs and schedules and their individual contribution to overall GHG emissions reduction goals. Scope of Work (Board Awarded) Form 3.09 Page 5 of 15 As of 4/28/11 ATTACHMENT B i. Deliverables associated with this subtask include a list of preliminary projects with GHG-reduction potential to be evaluated within the Strategic Development Plan. e. Building upon the Task 1 condition assessment in conjunction with the previously described production and distribution modeling and load analysis, Jacobs will work with the County to identify potential CUF and campus improvement projects that will improve the operational reliability and safety of provided utility services, increase efficiency of operation or expand the service of the CUF to new facilities. This will identify necessary repairs and upgrades to existing CUF services required to maintain this infrastructure in modern condition and enable future campus service growth. Potential projects that will be evaluated are anticipated to include, but are not limited to, the following: i. Replace and install new steam and chilled water metering and communication system between CUF and Civic Center Campus (design included with Phase 2 Services of this proposal). ii. Complete connection of steam from CUF to 300 and 320 North Flower Street buildings. iii. Demolish three un-used boilers in old CUF. iv. Replace and install new high/low steam headers. v. Design new emergency boiler system. vi. Replace and install six new skid mounted primary loop chiller/absorber supply pumps and all correlated electrical feed equipment and piping systems. vii. Replace four cooling towers and pumps. viii. Replace chillers and branch supply piping. ix. Replace Civic Center Campus chilled water lines. x. Replace surface condensers. xi. Replace air compressors and dryers. xii. Reline condensate and clarifier tanks. xiii. Replace deaerating tank and flash recovery system. xiv. Replace emergency generator. xv. Supervisory Control and Data Acquisition System (SCADA) upgrades. Deliverables associated with this subtask include an updated list of preliminary projects to be evaluated (draft 10-year project plant recommendation). This list will define the projects that will be more fully evaluated within the Strategic Development Plan. Upon County approval of this project list, Jacobs will proceed with detailed economic analysis and cost estimating. SDP Task 3 - Provide recommendations to balance CUF thermal capacity demands by identifying usable outlets within Civic Center Campus (for County facilities currently partially served by the CUF (e.g. served by electrical but not steam or chilled water service)). a. Using the data and analysis from SDP Tasks 1 and 2, Jacobs will evaluate the current steam and electrical demands on the campus, and identify potential improvement projects or operational changes to provide an improved thermal load match from the cogeneration system. Heat balance analysis will include potential addition of new steam hosts on campus, or new systems within the CUF to more fully leverage the continuous usage of steam in order to improve the overall efficiency of the cogeneration system. Improvement Scope of Work (Board Awarded) Form 3.09 Page 6 of 15 As of 4/28/11 ATTACHMENT B options will be vetted with the County, but could include the usage of steam driven chillers, an additional steam turbine generator or operational strategy changes to more fully leverage steam across a given day’s operation. Potential improvements will be estimated for construction cost and evaluated on a life cycle cost basis. i. Deliverables will include a preliminary list of projects to be evaluated within the context of the Strategic Development Plan. Potential projects will be approved by the County prior to proceeding. SDP Task 4 - Identify immediate and potential County uses for thermal capacity to save County resources, maximize operations and reduce costs by connecting facilities not currently served by the CUF. a. Using the data and analysis from SDP Tasks 1 and 2, Jacobs will evaluate the potential for extending CUF utility services to County buildings currently served by stand alone utility systems. Potential improvements will be estimated for construction cost and evaluated on a life cycle cost basis for comparison between stand alone and CUF service to determine overall cost effectiveness. Factors including reliability, capital avoidance and overall efficiency and sustainability will also be evaluated. i. Deliverables will include a preliminary list of projects to be evaluated within the context of the Strategic Development Plan. Potential projects will be approved by the County prior to proceeding. SDP Task 5 - Identify non-County users as potential customers for electrical capacities for revenue generation. This will require understanding of legal constraints and technical requirements to connect and provide service. a. Using the data and analysis from SDP Tasks 1 and 2, Jacobs will evaluate the potential for extending CUF utility services to non-County buildings. Potential improvements will be estimated for construction cost and evaluated on a life cycle cost basis for comparison between stand alone and CUF service to determine overall cost effectiveness. Jacobs will investigate issues and legal requirements (requirements from CPUC, others) associated with providing a thermal and/or electric utility service to a non-County entity. It is assumed the County will assist with establishing estimates for load demand and relative operating schedules when interacting with non-County agencies. i. Deliverables will include a preliminary list of projects to be evaluated within the context of the Strategic Development Plan. Potential projects will be approved by the County prior to proceeding. SDP Task 6 - Identify future opportunities for Cogen, including potential partnerships with energy providers and expansion of system to further reduce overall costs (e.g. addition of third turbine over time). a. Jacobs will evaluate the potential for existing CUF utility services to non-County buildings. Potential improvements will be estimated for construction cost and evaluated on a life cycle cost basis for comparison between stand alone and CUF service to determine overall cost effectiveness. Jacobs will investigate issues and legal requirements (requirements from CPUC, others) associated with providing a thermal and/or electric utility service to a non-County entity. Phase 1 Completion Using the cumulative input from Tasks 1 through 6 as defined above, Jacobs will develop detailed cost estimates for each mutually agreed upon selected improvement options (defined in Task 2) suitable for establishing confidence in an overall expectation of project construction cost. Scope of Work (Board Awarded) Form 3.09 Page 7 of 15 As of 4/28/11 ATTACHMENT B Identified replacement and improvement projects for chilled water and steam production equipment will be evaluated by comparing up to three different production alternatives and equipment alignments (e.g., chilled water system electric centrifugal versus steam driven chiller options, thermal energy storage, etc.) to determine overall energy consumption, efficiency and capital cost. Potential production improvements will be evaluated on a life cycle cost basis using financial metrics approved by the County to determine the overall option cost and return on investment. Evaluation of improvement alternative reliability, safety, risk, code compliance, sustainability and overall effectiveness in meeting CUF service needs will also be considered as secondary evaluation criteria. Phase 1 services will culminate with delivery of a Strategic Development Plan report, summarizing and documenting the activities associated with SDP Tasks 1 through 6. As part of evaluating different improvement options, Jacobs will evaluate individual projects and groups of “bundled” projects, to determine the combination of project(s) that offer the most favorable ROI. Jacobs will also develop an overall CUF Utility Improvement Plan detailing individual infrastructure projects, their estimated costs and anticipated project schedules. This Improvement Plan will provide a clear roadmap of recommended projects with respective schedules and cost (over time). The SDP report will be tailored to be “live” and suitable for real-time update, dynamically responsive in nature. The plan will accommodate changes in County priorities or potential new project directives to allow dynamic update and responsive output. The analysis and conclusions will demonstrate that the identified recommendations were undertaken using a robust methodology capturing a wide range of options and potential improvements. At the conclusion of the Strategic Development Plan, Jacobs will prepare a report presentation for the Board of Supervisors, and participate in presentation in a minimum of three County meetings. Additional meetings beyond three may be considered as an additional service. Jacobs will not proceed into detailed project design without prior approval from the County. 15. PHASE 1B – REVIEW CONDENSER WATER PIPING REPLACEMENT PROJECT Jacobs will review the design drawings that have been prepared for the condenser water supply and return piping replacement project within the CUF. Jacobs will provide review not-only for technical content and sound engineering but also in consideration of the long term Strategic Development Plan approach to ensure that the planned design maintains flexibility and space within the plant to accommodate other future infrastructure improvements. 16. PHASE 2 – STEAM & CHILLED WATER METERING PROJECT Jacobs will design new steam and chilled water metering as well as communication system infrastructure between the CUF and currently connected Civic Center Campus buildings. Design will include replacement of existing Venturi steam and chilled water flow monitoring devices with new utility-grade metering devices calibrated for accuracy across the full range of expected flow, from peak demand to the lowest feed valve inlet setting to allow the County to validate efficiency of CUF operations. Metering will be used to enable the County to establish actual costs of steam and chilled water used in the Civic Center Campus. Design will include new network communication and conductivity to provide communication from each meter to the new Eaton Power Xpert Software and Eaton Power Xpert Reporting System in the CUF (currently being installed under a separate contract). Design services for this package will be provided in accordance with the County Architect-Engineer Guide. Design scope will consist of the following: Scope of Work (Board Awarded) Form 3.09 Page 8 of 15 As of 4/28/11 ATTACHMENT B a. Research and compile metering and control devices available and present recommendations to the County. b. Building walkthrough and documentation: i. Jacobs will confirm any dimensions or details needed to design any necessary piping modifications and meter/instrument devices installation and provide photo documentation. ii. Confirm availability of spare circuits in local electrical panels. c. Revise existing P&ID’s if available to reflect necessary piping/valve modifications and device installation (including meters, pressure/temperature transducers, and transmitters). Installation plans or piping schematics will be additionally be provided to show relative locations of devices or piping/valve modifications for construction purposes. d. Prepare electrical power plans, panel schedules and schematic wiring diagrams. e. Provide instrumentation design, including system architecture and loop sheets. f. Instrumentation programming and building of HMI screens can be provided at an additional cost, but is not currently included in the proposed scope. All engineering and architectural design services will be provided by Jacobs Engineering Group resources. Construction Documents shall be prepared in three separate and distinct submittal packages as defined below, with County review and approval for each package. 1. Schematic Design - Upon Contract approval and official notice to proceed, we will commence with schematic design for the metering project. Schematic design deliverables will include a project manual including narrative project description, design schedule, cost estimate and plan drawings conveying the schematic design scope of work. The Jacobs design team will conduct a meeting early during schematic design with County staff review design intent, control system connectivity requirements, metering options and overall project constraints. This meeting will document key decisions that need to be made during the course of the design. A schematic design review meeting will be held with the County to review and respond to comments originating from the submitted documents. Upon schematic design approval from the County, Jacobs will proceed with detailed design. 2. Construction Documents - The construction document stage will include completion of technical specifications, complete plan drawings, sections and details conveying the full project scope of work associated with each phase of construction. Documents will be packaged and sealed, suitable for bidding and construction purposes. A detailed cost estimate will be provided as well. During construction document design, a 95 percent document package will be delivered for County review and approval. A complete 100 percent construction document package will be issued for approval by the County Planning and Development Services Department prior to project bidding. 3. Construction Administration Services - Construction administration services will be provided to assist the County in monitoring project construction and observing the quality and timely completion of construction. Proposed construction administration services include: a. Attendance at project pre-bid meeting, responding to questions from bidders, issuing addenda to prospective bidders if necessary, analyzing bids and recommending contract award by the County. Scope of Work (Board Awarded) Form 3.09 Page 9 of 15 As of 4/28/11 ATTACHMENT B b. Attendance at project preconstruction meeting. c. Attendance at on-site construction meetings, to assist the County and contractor during construction, as well as preparation of field reports documenting the observed progress and design conformance. d. Collect, track and review submittals and contractor shop drawings, managed through a Jacobs internal database and project controls department. e. Respond to contractor questions through a formally tracked Request for Information process, to support the project through construction completion, managed through a Jacobs internal database and project controls department. f. Provide site visits for final punch list creation and review at substantial completion. g. Review test reports as required by the specifications. h. Review Operation & Maintenance Manuals as required by the specifications. i. Review of substitutions to equipment and systems specified, as well as alterations to Construction Documents for substitutions. Material changes to project scope requiring significant additional design will be considered an additional service. j. Prepare final as-built drawings based on contractor-provided electronic drawing updates of modifications, delivered at project completion, as well as preparation of asbuilt drawing CAD updates based on completed construction conditions, for record document purposes, based on contractor markups. k. Review contractor progress payment requests. 17. FUTURE PHASES – PROJECTS TO BE DETERMINED Design by A-E of projects identified in the CUF Strategic Development Plan. It the County’s intent with this Agreement to retain an A-E to provide full design services, prepare construction documents and provide construction support services for all projects identified in the CUF Strategic Development Plan. A-E will be required to negotiate fees for each project and the County will retain the option to not award the work to the A-E. Work on future phases is anticipated to occur between 2012 and 2021. 18. SPECIAL SERVICES The following additional engineering consulting services are anticipated beyond the above Basic Consulting, Design and Construction Administration Services for the CUF Strategic Development Plan. These potential services are outlined below and may be activated if the scope or overall direction of the project warrant. It is anticipated that a more exact scope and fee will be developed and negotiated specific to each service if and when activated, but prior to commencing work. a. Detailed Building Energy Modeling: The initial Strategic Development Plan scope is limited to evaluating the connectivity of CUF-supplied utility services to each building on the Civic Center Campus. It is anticipated that during the Phase 1 Strategic Development Plan activities, field observations and data collection may uncover building operational anomalies which warrant further investigation. Detailed energy modeling of building-side systems may be provided as an additional service to help determine improvement opportunities within individual buildings that could enhance operations or efficiency. b. Civil Utilities Master Planning: Utility master planning for civil utilities and infrastructure (storm sewer, sanitary sewer, domestic water and natural gas) may be provided for the Civic Center Campus in conjunction with activities associated with the Strategic Development Plan. Planning activities would include evaluation of existing system Scope of Work (Board Awarded) Form 3.09 Page 10 of 15 As of 4/28/11 ATTACHMENT B capacities, projection of load increases due to new or added facilities, identification of improvement projects needed to increase capacity or reliability of service, along with cost estimates of proposed improvement recommendations. c. Funding Assistance – SGIP Application : The following services may be provided in support of the additional design scope required to support the SCE Self Generation Incentive Program Application process. i. Prepare reservation request including: 1. Gather and complete the required documents 2. Complete Waste Heat Emission Worksheet 3. Download, complete and mail the Reservation Request Form with all required documents above ii. Prepare the Project Advancement Milestone Report and Checklist with input from facilities personnel. Gather and complete the required documents, including: 1. Equipment Specifications 2. Proof of Utility Service 3. 12-month Electric Load Documentation 4. Proof of Power Factor Eligibility (for conventional CHP projects) 5. Proof of NOx Emissions Qualifications (for conventional CHP projects) 6. Application Fee – 1% of the requested incentive amount shall be provided by the County. 7. Proof of Non-Profit Status 8. Preliminary Monitoring Plan 9. Copy of RFP for Public Entities 10. Copy of Executed Contract or Agreement for Installation 11. Completed Air Pollution Permit Application (Internal Combustion Engines & Gas Turbines) iii. Prepare the Incentive Claim Form with input from County Personnel, including: 1. Gather and complete the required documents 2. Final Project Cost Breakdown Worksheet 3. Final Project Cost Affidavit 4. Revised Waste Heat Emission Worksheet 5. Electric Load Documentation 6. Energy Efficiency Audit 7. Proposed Monitoring Plan 8. Proof of Authorization to Interconnect 9. Substantiation of Load (for new construction or expansion) 10. Revised Sizing Calculation (if applicable) 11. Download, complete and mail the Incentive Claim Form with all required documents above 12. Incentive Claim Form and Checklist d. Funding Assistance – State and Federal: In conjunction with the strategic planning effort, Jacobs is available to conduct an exhaustive review of potential federal, state and local funding incentives that may be available to support the design and implementation of recommended project improvements. Additionally, Jacobs will immediately engage with its contacts at the U.S. Department of Energy (DOE) and state and local sources to identify potential funding sources for the front-end planning effort. Potential funding sources will be investigated at the local, state and federal levels. A representative sampling of these sources includes: i. Federal investment tax credits for HVAC, CHP and renewable energy projects ii. Federal grant programs related to CHP and district/campus energy projects iii. Federal grant programs related to building energy efficiency improvements Scope of Work (Board Awarded) Form 3.09 Page 11 of 15 As of 4/28/11 ATTACHMENT B iv. State energy program funding related community energy efficiency and energy conservation projects v. State energy program funding related to community renewable energy projects vi. Local utility rebate programs vii. Local utility ancillary services programs viii. Private third party performance contracting options e. Review of Design Standards: Based on the recommendations associated with the Strategic Development Plan, Jacobs can provide review of the County A-E design guidelines and provide recommendations for opportunities for long term operational, maintenance and energy improvements in keeping with the purpose and intent of the Development Plan. f. Piping Testing Services: Distribution piping inspection and testing services are not included with the basic scope of work. Non-destructive testing services for existing campus distribution piping may be added as an additional service at a later date if requested to determine piping system integrity. g. Board of Supervisor Presentations: As needed to support implementation of the overall Strategic Development Plan or its individual elements, Jacobs will conduct meetings and prepare summary presentations of our planning and evaluation work and progress suitable for executive level presentation and review for individuals on the Board of Supervisors or other relevant County officials (beyond the presentations included in the base scope of services at the culmination of Phase 1 Strategic Development Plan services). Presentation content and approach to be developed based on actual support needs as indicated by the County. h. Development of Conceptual Design Sketches: Jacobs will develop conceptual sketches for potential utility infrastructure improvement projects associated with Strategic Development Plan recommendations. The project(s) selected for development into concept sketches will be based on the findings and recommendations of the Development Plan, and would be used for initial project planning, scoping and budgeting purposes prior to actual detailed design. Concept design would include drawings depicting major equipment locations, flow diagrams demonstrating system connectivity and preliminary single-line electrical drawings, along with a narrative project description and cost estimate. i. Detailed Project Design: Detailed design for individual project recommendations originating from the Strategic Development Plan are anticipated at a future time. Individual design projects will be developed and proposed at a later time, consistent with the County A-E guidelines. (See Future Phases) j. Site Survey: As needed to accomplish project design, Jacobs can provide land surveying services, consisting of survey of Civic Center Campus and ground mapping of certain utilities. k. Utility Locating: Potholing or sub-surface utility locate services needed to determine underground utility locations for design of site piping distribution or other design improvements are not included in the proposed fee, but may be subcontracted as an additional reimbursable expense if requested and/or required. Scope of Work (Board Awarded) Form 3.09 Page 12 of 15 As of 4/28/11 ATTACHMENT B l. Geotechnical Subsurface Investigation: Subsurface investigation needed to complete project design may be included as an additional future service. Analysis type, number and depths of borings and other investigation requirements will be negotiated at a future date based on project type. m. Arc Flash Hazard Analysis and Labeling: Jacobs will create an Arc Flash Hazard analysis model for the CUF to fulfill the requirements of NFPA 70E. This study will incorporate the relay and protective device settings and will be used to develop equipment labels for the electrical equipment in the new plant. The labels would be installed in the field by the installation contractor. n. CEQA Environmental Impact Report: Preparation of Environmental Impact Reports associated with CUF design projects will be provided as an additional service, with exact scope and fee to be negotiated based on project type and size. o. Environmental Testing Services: Environmental testing services, including but not limited to flow and temperature measurements, air balance readings, as needed to complete Strategic Development Plan evaluations due to incomplete or missing data, may be requested and performed as an additional service, with exact scope and fee to be negotiated based on testing service type and size. p. Dynamic Airflow Modeling: Jacobs will sub-contract to provide wind engineering and computational airflow analysis to evaluate cooling tower drift discharge and new boiler stack designs associated with new design projects. This airflow analysis can be used to help determine air quality impacts due CUF emissions on adjacent building ventilation system air intakes. This analysis will aid in the evaluation of the stack elevations and configuration options, and will identify risk and mitigation strategies, if needed, to prevent operational and possible health related problems associated with emissions entrainment into adjacent building ventilation systems. Computational modeling of the stacks and cooling towers will also provide analysis of expected localized relative humidity levels during cooling tower operation, helping predict when fogging problems may occur. q. Equipment Procurement Package Preparation: Jacobs may prepare equipment procurement packages to allow the County and/or its designated Construction Manager to proceed with early procurement of equipment to facilitate an efficient design and construction schedule for selected CUF projects, prior to the completion of detailed design. Pre-purchase will allow detailed design completion to be focused on the actual equipment to be installed, ensuring coordination of relevant design details. The procurement packages will consist of equipment schedules, specifications and necessary supplemental documentation to facilitate bidding as distinct stand-alone procurement packages. Proposed services include bid evaluation and recommendations for purchase of the equipment. r. Enhanced Engineering Support Services: The following support services are not included in the base proposed scope of services; i. Commissioning Services. ii. Preparation of documents or attendance in the capacity of an expert witness. iii. Provide revisions to completed design work as a result of Owner-directed changes to the original design scope or criteria. iv. Amendment of Existing Air Permitting: Jacobs can assist the County with developing the necessary technical supporting data and paperwork to complete the Scope of Work (Board Awarded) Form 3.09 Page 13 of 15 As of 4/28/11 ATTACHMENT B v. vi. vii. viii. 19. revision of the existing air permit based upon new equipment or operational changes. Development of Plant Operation & Maintenance Manuals: The O&M manuals would incorporate the manufacturer’s equipment data and O&M procedures for the chillers, boilers, combustion turbine engines and generators, HRSGs, control systems, cooling tower and balance of plant equipment. Procedures would include normal startup, operation, and shut-down procedures for each component as well as the combined systems. The procedures would also include emergency upset procedures for shut-down and operation. Startup Assistance: Startup assistance under this scope would include field and office support of the startup and field commissioning for the new equipment to be installed as part of the Strategic Development Plan recommendations. This would include development of performance and safety verification procedures, wiring verification and troubleshooting assistance. Witnessing of Factory Testing of Equipment: Factory witness testing to be performed at the location of manufacture or third party testing location. Tests to be performed will be determined during equipment procurement, but will generally serve to verify performance and specification conformance of the equipment as well as to minimize construction complications prior to it leaving the factory. Detailed Control System Drawings: Jacobs can provide the following detailed controls drawings for the Phase 2 Metering Project, if requested: 1. Point-to-Point Interconnection Wiring Diagrams: Electrical, instrumentation, and controls point-to-point interconnection wiring diagrams will be provided as a supplement to the Construction Documents packages. Terminal blocks, wire and cable designation, and routing are included in this scope. 2. Logic and Function Diagrams: Jacobs will provide loop diagrams, functional diagrams, and logic diagrams further depicting control system functionality for the balance of plant systems. These controls will be implemented in the balance of plant control systems by the control systems integrator. CONDITIONS OF DESIGN WORK - ASSUMPTIONS The following assumptions apply to work in Phase 1 and Phase 2 of this Agreement and may apply to future Phases. a. CADWorks 3D computer aided design software will be used for the preparation of engineering production drawings (AutoCAD compatible). b. Jacobs will have access to all drawings, specifications, surveys, geotechnical reports and other information previously prepared for the County, and other pertinent documentation available and necessary to complete the scope of work for the new CUF Strategic Development Plan. c. Jacobs reserves the right to modify or initiate contracting of sub-consultants for the execution of this work, in order to improve work product or schedule performance. d. Identification of environmental hazards and/or contamination remediation at the existing site (cleanup of existing fuel oil leaks, asbestos, lead paint, etc.), if discovered during the course of field survey, design or construction, is not included in this scope of work. e. The preparation of detailed engineering design packages for identified and accepted Strategic Development Plan infrastructure improvements is not included in basic services, but may be included as additional services. f. Power distribution analysis of future buildings will be based on estimated watts per square foot by building type. Scope of Work (Board Awarded) Form 3.09 Page 14 of 15 As of 4/28/11 ATTACHMENT B g. Number of improvement options to be analyzed per system (chilled water, steam and electrical) will be limited to three, unless noted otherwise. h. Effort includes detailed modeling of chilled water, steam, cogeneration production and electricity distribution systems. Detailed modeling of individual buildings can be included as an enhanced engineering service. i. Life cycle sensitivity analysis is included for up to 5 variables of economic nature only. Sensitivity analysis related to significant load changes can be included as an additional service. j. Chilled water, steam, and electric system condition assessments will be developed based on prior assessments completed by the County, staff interviews, O&M data reviews and visual inspection at the CUF. k. Jacobs will be provided two weeks advanced notice of on-site meetings to reduce travel costs. l. Jacobs will provide video conferencing software for use by the County to accommodate meetings between the County and the SDP project team. It is assumed as meeting meetings as possible will be accommodated using video and/or internet-based conferencing technology. Scope of Work (Board Awarded) Form 3.09 Page 15 of 15 As of 4/28/11