Sample Email Messages Dear Name, update the KHH expansion schedule, 1. Time table has been forward to Chinatrust. 2. Eric has confirm the building with Fubun on October,13. 3.KHH call center renovation starting on 10/15. 4. Leasing contract in Chinatrust. I will follow it. 5. Chair will arrive on November 23, and TM will test run on November,24. 6. We will discuss with Tina about the opening day. Over all, everything is on schedule until now. Best Regards, Name Sample 2 Dear all, Good day. Just remind you that you are going to take an assignment on Sep. 28, 2005. Please kindly inform me if you are available or not. If any question, please feel free to contact me! Regards, Name Dear Name, I am so sorry that I can not attend TTY meeting from 9/28 to Feb,2006. Because I need to attend a program of company. Thanks your helpful these days. Best regards, Name 1 Sample 4 Hi Name, I just wanted to drop you a quick note that due to a shift in the CVM strategy, I am no longer with Cigna. It was a pleasure meeting you and I was looking forward to working more deeply on CVM and Chinatrust with you. Overall, I had a good time in Cigna during my nine months, and I enjoyed meeting people like you who are extremely smart in the insurance domain in addition to being highly personable. Do keep in touch. Take care, - Name Dear Name, I heard you leave Cigna from Julie. Thanks your support of Chinatrust project. We are going to second test. Due to your support that we had good performance. Enjoy your new career. Best Regards, Name Dear Name, I am sorry that I am late to send this mail to you. Below is my sample e-mail that I have a discussion with Steve, my coworker who works in HK and he is a Chinese. We were discussing about an enhancement 2 of computer system. If you have any suggestion relates to my wording, grammar...etc, please let me know. Thanks for your understanding. Regards, Name Hi Name, Answer you question…. I prefer to use “Package & Products” excel only. And I have added a field called “face amount” in this file. Please find the attached. So, for “dummy” packages, you can find face amount and real prod code from the excel file. As to S8 Non Dummy Package You can use POL_Product.Prod_product to get real prod code. And you can use PM_BENLVL.blv_level_base_amt to get face amount. If you have any questions, please let me know. Thanks, Name Hi Name, Please find attached the first draft of the Functional Specification for your review. Some questions I would like to post:1) Since the analysis would be on all products (including normal System-6 & CICAP products) should the final "Product & Benefit" Excel contain ALL products and benefits (including normal System-6 & CICAP which are not dummies)? 2) "Package & Products" Excel currently contains only products under "dummy" packages, how do I get the face amount of normal System-6 and CICAP products. In the functional spec., I am assuming the above 1) is true and I get the face amount from the Maximum "Benefit_sch_amt", let 3 me know if this is the case. Best Regards, Name Hi Names, I will communicate with Jerry on the schedule and the details. Best Regards, Name Hi Name, Steve is already working on the function specification. I already allocate his resource for this urgent task. Steve, please also provide a standard schedule and communicate with Jerry. Thanks and Regards Name Dear all: When will you plan to start this modification based on current COE schedule? Jerry may need to inform user about the estimated UAT schedule to allocate the resource for testing. Thanks! Regards, Name Hi Name, In Taiwan, we just need “face amount” so that the 2nd item- package X product (and product face amount) is better. Currently, TW CVM doesn’t include any claim data, there will not be any claim value to support analysis even if we add benefit schedule into CVM. That is the reason why we don’t need “benefit schedule”. BTW, the estimate 5MW means that you will need 5MW working days or you will charge TW 5MW? Thanks, 4 Name Hi Name, coverage "benefit schedule" (4 MW) package X product (and product face amount) - Estimate 5MW; to cater for the different logic needed to handle "Dummy" Product. package X product (and product face amount) plus HK coverage "benefit schedule" - Estimate 6MW; to cater for the different logic to handle "Dummy" Product and Benefit Codes. Best Regards, Name Hi Name, 1. the product modification is no longer address the coverage "benefit schedule", in stead it is addressing the package(dummy) X products (and product face amount) 2. I am thinking to make the best out of the situation, we will give you both the package X product (and product face amount) plus HK coverage "benefit schedule" enhancement (since you will retro fit this anyway) 3. we only need one set of excel files. please provide the final version so that RCS team can populate this info into the testing environment Name, please let us know the following options estimation: coverage "benefit schedule" (4 MW) package X product (and product face amount) package X product (and product face amount) plus HK coverage 5 "benefit schedule" Once I have the estimation, Jerry please discuss with business team. Thanks and Regards Name Dear all, In Taiwan, we thought that every product only has a face amount. Since one product probably owns many benefits, it is difficult to identify which benefit’s “schedule amount” is the face amount of this product. That is the reason why I add a new column called “Face amount”. In Taiwan, I can make sure that we don’t create any new dummy package anymore. Name, this new column will be a part of the RCS but we don’t use it in RCS, just only for CVM. In RCS, we use schedule amount but in CVM, we use face amount. I have no idea how to separate this table, if you have any suggestion that will be welcome. Thanks, Name Hi Name, Please find the attachment about Package & Product mapping table revised version. I add a new column called “Face Amount” in this table. (1) S6 Dummy Package, You can use this table to find real prod code and face amount. (2) S6 Non Dummy Package You can use POL_Product.Prod_product to get real prod code. Ming, how do you think about that I add a new column in this table, but the usage is only for CVM enhancement not for RCS? Name 6 Jerry and Steve, we need to talk, this does not seems to be utilizing the enhancement from HK coverage. Jerry, the new columns, will this be part of the RCS Steve, setup up a time for discussion once you have digest the content. Thanks and Regards Name Hi Name, OK, so some product, if they exist in the "Package & Product.xls" then it is a Dummy Package and I look up the associated "real product codes" in this Excel. Regarding Face amount of the "Real Product", this will be the sum of all the face amount of the Benefits under that Product? I'm assuming this to be "Benefit_sch_amt" in the "Product & Benefit.xls", is this what users want to analyze? Best Regards, Name Hi Name, I hope that you can understand that there are two usages about prod code in TW S6 now. If you have any question or my explanation is not clear, please let me know. Regards, Name Hi Name, Could you give us some real examples of how a Policy is related to the "real product code"? We need to have common understanding of this before we can move along. What we have on hand at this moment are 7 the 2 Excel's attached, it would be necessary to know how these are related to the Taiwan requirements of "product", many thanks. E.g. Does "real product code" refer to GPE030 Jack, OK to settle claim as recommended. Name Name Note: Again, we are being hit by these large claims which we sold one after the other--first, NT$3M and then 8 months later, NT$7M. Paul, what was the coverage/income ratio for the deceased a) coverage with CIGNA; b) all coverage including Prudential and Zurich? Thanks. Name Dear Name, Here is a jumble accidental death claim. The total insurance is high to NT$ 10,000,000 (US$ 292,890.00), The insured owned 2 policies, the policies details are as follows: Insured: Su Shih-Tsung, Male, Age 46, and Occupation: Worker in a winery The insured is a worker in a winery but he also helped his father running a betel nut stall when he was free from work at winery. At around 7:40 pm, Nov. 18, 2004, the insured was delivering a bag of betel nuts and drink to a customer across the road. When he was crossing the road 8 through a crosswalk, a turn-right truck appeared suddenly and hit him. The accident caused the insured serious injuries and fractures. He was sent to a hospital for first aid, but unfortunately, he passed away at 8:50 pm, the same day. According to the traffic accident paper, we confirm the accident with the policeman in charge. The policeman makes sure that the insured was a walker hit by a truck when he was crossing the road. There is no alcohol measurement to the insured because he was not a driver. In addition, the insured was covered by another 2 policy issued by Prudential Life and Zurich Non-life. The details of the 2 policies are as follows: Prudential Life has paid the insurance at Dec. 14, 2004. Zurich Non-life received the claim application at Dec. 22, 2004. This claim is still under examining process and will be closed at Jan. 3, 2005. The accident is clear and no exclusion involved, I suggest paying this claim. Because the insurance exceeds US$100,000, I need your approval. If you have any questions or comments, please don't hesitate to advise me. Thanks! Attached please find the LLR. Best Regards, Name Dear Name: You bet. Would you mind inform me time and place to meet (better not to early! )? Meanwhile, We will attend the 2 days trip for mountain hiking also. 9 Best wishes. Name Dear All, Attached please find the file of revised claim work manual for your reference. Thanks! Regards, Name Dear Name and Name, Attached please find the file of revised claim work manual. A new item asked by FSC auditor, Name, has been added at claim administrative section (page 70). If you need a hard copy, please let me know. I'll prepare one for you. Thanks! Regards, Name Dear all, 2005 English Training Program will be launched in Oct, 2005. We have 38 staffs participate this program. Detail information is listed on the attached memo. Pls find it for your reference. If you have any question, pls feel free to contact to me (#1720) , Wish you enjoy your learning!!! Best regards, Name Dear Miss Name, Please explain in more detail what was going on. How did Mr. Wang come back to TWN? Any assistance SOS provided to him? Did SOS know the arrangement? Name Dear Name, 10 Here is a jumble accidental total disability claim. The insurance is high to NT$ 5,000,000 (US$1…..). You may find this claim is similar to the one of Kuo PeiHong, with the same product and the similar course of event. However, they are indeed two independent claims. The policy details are as follows: Insured: Hong Lie, Male, Age 55, and Occupation: Fishmonger in Market Policy Number: ……………. The accident was happened at 13:30, Saturday, Mar. 6, 2004. The insured went hiking and visiting his brother at law. After the visitation, he walked down the hill along the road. Due to the road is wet and slippery, he slipped down and his head was hurt, then, he fell into the valley. As a minibus passed through, the driver found the insured lay on the side of road and reported the event to the police. The insured was sent to the hospital for first aid. It is clear that there is not traffic accident happened. The insured was a walker and fell by himself. Due to there is no opposite party, the police just kept the event record but didn’t have a further investigation. After check the scene and the records of police and hospital, we may eliminate the possibility of suicide. After 6 months of waiting period, the insured raised a formal disability certificate to apply disability insurance. We send an investigator to examine the insured’s body. Our medical consultant, according to the disability certificate, medical report and investigating report, identify that the insured’s condition has met the total disability standard. In addition to our policy, the insured owned another one issued by Cathay Life, 11 Life NT$600,000(US$17,573.40) PA NT$2,000,000(US$58,578.00), effective from Nov. 23, 1998. Cathay Life has paid the disability insurance, NT$2,600,000(US$76,151.40), at Dec. 7, 2004 The accident is not so clear but we can’t prove any exclusion was involved, I suggest paying this claim. Because the insurance exceeds US$100,000, I need your approval. If you have any questions or comments, please don't hesitate to advise me. Thanks! Attached please find the LLR. Name Dear all: We have few colleagues sign up for today's semninar. Welcome! And see you 30 minutes later. This is a reminder for today afternoon's product seminar (Sept. 6, 4:30 5:30pm at Jupitor). Thanks for your sign up of New product seminar. For your reference only, please see attached attendees list for three sessions. <Product Seminar - one year group surgery2.xls>> Best Regards, Name Hi Name, Can you please provide me more details on your issue. From past experience, there can be a few different error messages after setting up ADI that have different 12 causes. Did you recently upgrade PC's to XP and had to reinstall ADI? If you did, please tell me what version of ADI you installed. It would be very helpful if you could provide details of your error including screenshots to give us an idea of how you got this error and what the appropriate solution would be. From your brief description of the problem, it sounds like it may be either an issue with the TNSNAMES.ORA files or the database connection. To test this theory, please follow the attached document to setup the database connection. If the setup does not fix the error, we will proceed with further tests and actions. Does this issue relate to the ADI issue that Penny has resolved? Regards, Name My name is Name. Taiwan Company Name leader. These days, We have get some trouble in Oracle ADI setup process.Now we can setup Oracle ADI completed , but can't reached the Database. Now the finance department want to use this tools. Would you please give us the SOP about Oracle ADI's setup process or some advice about this? Thanks for your cooperation!! Name Dear Name, At first I am sorry for my late answer because of our national holiday. I am Young Min, Ha and manage welcome 13 call centre. If you don't mind, could I arrange it on Thursday afternoon start from about 3:00 pm korea time(2:00 pm Taipei time)?. I am also looking forward to being helpful and useful conference call each other. Regards, Name Hi, Name, Please let me introduce myself first, I am Kelly Lu in charge of Taiwan Reconfirm Team (Welcome call). Regarding the time of experience sharing as I have not receive any information from you, so can we have a conference call on 9/20, Tuesday OR 9/21 Wednesday morning start from 10:30 (Taipei time)? If you prefer another day and time, please do not hesitated to let me know. I am looking forward to have this kind of experience exchange, talk to you soon. Best Regards, Name Hi Name, I heard from Derek that we had a duplicate Token ID of JINYEH(Jinn-Wen Yeh), so would you give a list about the Token owner of Taiwan that as soon as you can , Thank you very much. Bye the way , about last week I could not enable 3 Tokens in Taiwan , I will try again at tomorrow ,hope this time will be work. And The Monday of next week is our popular holiday , we will take one day off, Thanks~ Regards, Name Name, 14 I am in office today. I had checked both TPIFS001 & HKIAPP09 (HK Websense). It seems the TPIFS001 can communicate with HKIAPP09. I will suggest a reboot for TPIFS001 during lunch hours. Name Hi Name, Alan has take one day off , so would you help us ? Hi Name, We can’t logon any web site now, I have already restart below two services on Tpifs001, but still can’t access any web site, would u help us to find out what’s going on ? Thank you very much ~ Hi Name, OK, I will restart Tpifs001 during lunch break , Thanks~ And we have already prepare another server for programmer testing, so about the IIS on the Tpifs001 will be only provide for Websense soon, Name 15