request for expressions of interest- airport project

advertisement
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
TERRANCE B LETTSOME INTERNATIONAL AIRPORT-BRITISH VIRGIN ISLANDS
AIRPORT & TRANSPORTATION INTERMODAL EXPANSION PROJECT-SPONSORED BY
MINISTRY OF NATURAL RESOURCES & LABOUR
PROJECT HEAD OFFICEMinistry of Natural Resources & Labour
BVI Government,
Central Administration Complex
33Admin Drive
Road Town Tortola BVI
VG1110
Invitation for Expression of Interest (EOI)-cum-Request for Qualification for Design,
Finance & Construction Services for an intermodal transportation center including an
Extension of existing Runway at Terrance B. Lettsome International Airport
1. INTRODUCTION
The Government of the British Virgin Islands (GOBVI)-an overseas Territory of Great
Britain-, the owner and operator of the Terrance B. Lettsome International Airport operates
the airport facility through the BVI Airports Authority (BVIAA).
The BVI Airports Authority was on 15th August 2005 incorporated under the BVI Business
Companies Act, 2004. Its registered Office is situated at Harney Westwood and Riegels,
Craigmuir Chambers, Road Town, Tortola, British Virgin Islands. It is an autonomous body
created by virtue of the Virgin Islands Airports Act, 2003 which was assented to on 2nd
March 2004. The Act provides for the operating of airports in the Virgin Islands as
commercial undertakings and other matters connected therewith.
The Government of the British Virgin Islands (GOBVI) is moving into the next phase of
development to create a unique intermodal transportation center which will be developed as
the first of its kind in the Eastern Caribbean to deliver a memorable, world-class and
environmentally compatible and sustainable development which will include the following
Key Elements/components:
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 1
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
i. Extension of existing Runway into the sea
ii. Passenger Terminal Expansion and upgrade
iii. Aircraft Ramp Expansion (G-5 aircraft, RJ’s; A-320; 737-800; other
private jets)
iv. Sewage Treatment Plant and Fire Fighting system relocation
v. New FBO Facility
vi. Pleasure craft water access-excavated channel
vii. Inter-Island Ferry/Transport service upgrade/relocation
viii. Trellis Bay Welcome and Visitor Center (Transportation Intermodal
Center)
1. Crafts and gift shop
2. Indigenous arts and craft manufacturing & museum
3. Live flora indigenous to Beef Island (lignum vitae stand of trees)
ix. Traffic Reorganization
x. Car-park upgrade
The foundational and key component will be the extension to the existing Runway at Beef
Island and concurrent upgrade/provision of Parallel Taxiways and other airfield systems
expansion/upgrades to meet the airfield infrastructural needs to be generated from direct
long-haul international flights and the consequent and current rapidly growing traffic
demand. The new Runway and taxiway system and corollary airfield improvements and
associated works will be required to be operational by 2015.
The GOBVI has developed a strategy for active participation and involvement of the private
sector in infrastructure development towards national growth, through Public and/or Private
Financing arrangements. In this regard, the Government intends to develop the intermodal
transportation facility including the extension of the airfield facilities at the Terrance B
Lettsome International Airport under a Design, Finance and Construct (DFC) contract.
The Government now invites Expressions of Interest from resourceful, imaginative,
experienced, internationally reputable Airport Planning, Design, Finance and Construction
firms for Planning and Engineering Design Consultancy Services for Runway and Airfield
Expansion and associated works at the Airport.
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 2
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
2. POLITICAL & ECONOMIC OVERVIEW OF THE BVI
Political Overview
Executive authority in the British Virgin Islands is vested in The Queen and is exercised on
her behalf by the Governor. The Governor is appointed by the Queen on the advice of the
British Government. Defense and Foreign Affairs remain the responsibility of the United
Kingdom.
A new constitution was adopted in 2007 (the Virgin Islands Constitution Order, 2007) and
came into force when the Legislative Council was dissolved for the 2007 general elections.
The Head of Government under the new constitution is the Premier (prior to the new
constitution the office was referred to as Chief Minister), who is elected in a general election
along with the other members of the ruling government as well as the members of the
opposition. A Cabinet is nominated by the Premier and appointed by the Governor. The
Legislature consists of the Queen (represented by the Governor) and a House of Assembly
made up of 13 elected members plus the Speaker and the Attorney-General. The current
Governor is His Excellency William Boyd McCleary (since 2010). The current Premier is Dr.
the Honorable Orlando Smith (since 9 November 2011).
Economic Overview
As an offshore financial center the British Virgin Islands enjoys one of the more prosperous
economies of the Caribbean region, with a per capita average income of around $38,500
(2004 est.) The "twin pillars" of the economy are tourism and financial services. Politically,
tourism is the more important of the two, as it employs a greater number of people within
the Territory, and a larger proportion of the businesses in the tourist industry are locally
owned, as are a number of the highly tourism-dependent sole traders (for example, taxi
drivers and street vendors). Economically however, financial services associated with the
territory's status as an offshore financial centre are by far the more important. 51.8% of the
Government's revenue comes directly from license fees for offshore companies, and
considerable further sums are raised directly or indirectly from payroll taxes relating to
salaries paid within the trust industry sector (which tend to be higher on average than those
paid in the tourism sector).
Tourism accounts for 45% of national income. The islands are a popular destination for U.S.
citizens. In 2006 a total of 825,603 people visited the islands (of whom 443,987 were cruise
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 3
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
ship passengers). Tourists frequent the numerous white sand beaches, visit The Baths on
Virgin Gorda, snorkel the coral reefs near Anegada, or experience the well-known bars of
Jost Van Dyke. The BVI are known as one of the world's greatest sailing destinations, and
charter sailboats are a very popular way to visit less accessible islands. Every year since 1972
the BVI has hosted the Spring Regatta, which is a seven-day collection of sailing races
throughout the islands. A substantial number of the tourists who visit the BVI are cruise ship
passengers, although they produce far lower revenue per head than charter boat tourists and
hotel based tourists. They are nonetheless important to the substantial (and politically
important) taxi driving community.
Substantial revenues are also generated by the registration of offshore companies. As of June
2008, 823,502 companies were so registered (of which 445,865 were 'active'). In 2000 KPMG
reported in its survey of offshore jurisdictions for the United Kingdom government that over
41% of the world's offshore companies were formed in the British Virgin Islands. Since 2001,
financial services in the British Virgin Islands have been regulated by the independent
Financial Services Commission.
3. BACKGROUND AND SCOPE
In 2004, the Airport became the first of the Overseas Territories in the Caribbean to be
certificated for the purpose of public transport (passengers or cargo) and instruction in flying.
The Oversees Territory Aviation Regulations (OTAR) became the regulating standards. The
British Virgin Islands Airports Authority (BVIAA) was formed the following year in 2005 as
a separate entity to oversee the efficient and effective operations of all airports in the BVI.
The BVIAA undertook a Strategic Plan and Airport Master Plan for the BVI airports in 2009.
The purpose of this study was to evaluate runway extension alternatives at all BVI airports to
accommodate flights to the continental United States. The proposed design aircraft to reach
these destinations was the Boeing 737-800.
The Strategic Plan concluded that Terrance B. Lettsome Airport was the best candidate for
the required improvements, and an Airport Master Plan was initiated. The Airport Master
Plan was concluded in 2011.
In order to further expand foreign tourism and travel to the British Virgin Islands (BVI) the
government is
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 4
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
actively engaged in making the Islands more accessible to markets such as North America
and Western Europe.
Currently, air travelers from North America choosing to fly commercially cannot fly directly
to the BVI because the length of the runways at island airports is limited to aircraft flying
such long distances. These travelers instead must connect through Puerto Rico or other such
regional airports with longer runways.
In order to accommodate this commercial air service directly and the government of the BVI
has investigated options to extend the available runway length at one of the islands airports.
Previous studies have confirmed that Terrance B. Lettsome International Airport on Beef
Island is the best candidate for a runway extension.
Although the existing runway and taxiways met International Civil Aviation Organization
(ICAO) standards at the time they were built and for the aircraft fleet using the Airport at
that time, design standards and aircraft technologies have evolved, resulting in deficiencies
in the following areas:
• Runway Strip
• Runway End Safety Area
• Runway Centerline to Taxiway Centerline Separation
• Taxiway Shoulders
• Obstacle Limitation Surfaces
The Strategic Plan concluded that Terrance B. Lettsome Airport would be the best candidate
to implement the improvements necessary to accommodate flights to the continental United
States. The Master Plan proposed to upgrade the Airport to an ARC 4C, in order to
accommodate larger aircraft, such as the proposed design aircraft, the Boeing 737-800. This
would require both widening the runway to 45 metres and extending the runway. It
proposes to extend both ends of the existing runway to a total length of 2,134 metres. The
west runway end would be extended approximately 155 metres and the east end
approximately 563 metres. Additional improvements for consideration are upgrading the
approach procedures to precision by installing an Instrument Landing System (ILS) and the
eventual expansion of the terminal area and apron to accommodate the projected increase in
passenger demand.
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 5
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
The Design Finance and Construction Contractor is to plan, Design, develop and construct an
iconic intermodal transportation center which will meet the functional and operational
requirements of GOBVI and the BVIAA. It is expected that the project will be used to train
and transfer technology to the local population and maximize the use of local resources.
The appointed Contractor shall be the main contractor for the project and shall manage &
co-ordinate the Financial Planning, Airport Planning and Design activities of all subconsultants, to ensure an integrated and coordinated plan and design.
Interested contractors who have executed similar works and wishing to qualify to tender for
the Financial Planning, Airport Planning, Design Consultancy and Construction Services for
the Runway Extension Development, are invited to apply for providing the services
satisfying the terms and conditions as stipulated hereunder.
4. PROCUREMENT PROCESS AND SCHEDULE
The procurement process entails two consecutive stages:
The current Expression of Interest and Pre-qualification Stage - June to August 2012
Several appropriate parties will be invited to respond to a Pre-Qualification document in
detail.
Subject to the results of an evaluation process-Pre-qualified Parties will be invited to enter
into a consultative dialogue with the GOBVI after which the RFP will be finalized.
Request-for-Proposal (RFP) Stage. October 2012.
They will then be required to submit final detailed proposals for the Planning, Design,
Financing and Construction of the project. One successful respondent will be selected.
Appointment of Lead Contractor or consortium leader to Plan, Design, Procure Financing
October 2012- December 2012 -Using FIDIC “Yellow Book” as Conditions of Contract.
Construction and Implementation – Phased program January 2013 to December 2015
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 6
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
5. ELIGIBILITY CRITERION
Prequalification is open to suitably qualified and experienced Construction Contractors with
Airport Planning, Finance & Design Consultancy capabilities. The Contractor can lead a
consortium and can appoint Financial, Airport Planning and Engineering sub-consultants as
required to augment his capability where required. Contractors that fulfill all the following
requirements shall be eligible to apply:
i.
Confirmation of the firm’s interest to be considered for short-listing for the
RFP stage
ii.
Achieved as the Main Contractor or consortium leader the Financing,
Planning and Design of at least one similar-sized project commissioned in the
last five (5) years. Technical capacity to design, construct, finance a civil
aviation airport.
iii.
Above such project(s) shall have been executed in the Americas and EuroAsia.
iv.
Achieved a minimum total annual turnover over the last three (3) years on
Design and Construction works of at least US$200 million dollars.
v.
Successful track record of timely completion of projects.
vi.
A signed statement by a duly authorized representative of the firm to the
effect that the firm is in good financial order, is not bankrupt, is not having
their affairs managed by a court, has not entered into an arrangement with its
creditors, or has not suspended its business, or similar or related situations
6. SUBMISSION OF EXPRESSIONS OF INTEREST
Firms may request to be qualified alone, or in consortium with other firms. If the Expression
of Interest is from a consortium of firms, information on all firms making up the consortium
must be provided. It must be clearly indicated which firm is the lead firm of the consortium.
The nature of the consortium arrangement should be specified, including a consortium letter
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 7
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
or agreement signed by all participating firms. Evidence of association will add to the
consortia eligibility
Electronic submissions in PDF format not exceeding 5 MB should be sent to:
Ministry of Natural Resources & Labour- Airport Project Development
Email Address-RSmith-Berkeley@gov.vg
Expression of Interest must be submitted with the above particulars supported by
documentary evidence which should include the following:
i.
Detailed company profile and capability.
ii.
General information on the firm including main business, country(ies) of
establishment and operation and duration of business activities as per attached
Form I: General Information.
iii.
Financial capacity to undertake this transaction. The annual turnover of the
firm in each of the last three financial years should exceed US$ 200 million
(audited financial statements are required for the last three years).
iv.
Annual financial statements for last three (3) financial years as per attached
Form II: Financial Information of the Contractor & Form III: Average Annual
Contracting Turnover.
v.
Auditors’ certificates certifying satisfaction of the financial criteria.
vi.
Detailed project documentation clearly enumerating the projects completed
including but not limited to client certification, description of role and
responsibility and works executed, schedule/ actual start and end date,
budgeted and actual cost of the project etc for airport experience as per
attached Form IV: Statement of Experience on Similar (Airport) Projects as per
attached Form V: Statement of Experience for Design, Financing and
Construction of Similar Magnitude of Work.
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 8
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
vii.
Litigation history, including current material litigation detailed as per attached
Form VI: Litigation History.
viii.
Any other documentary evidence to establish credentials and eligibility.
ix.
Parties short-listed will be issued with a request for proposal (RFP).
7. OTHER CONDITIONS
(a) GOBVI reserves the right to accept or reject any or all EOI without assigning any
reasons and is not obliged to correspond with the Applicants in this regard. Further,
GOBVI reserves the right to change and/or cancel the pre-qualification and tender
process or review/revise the pre-qualification criteria at any time without prior notice
or without assigning any reasons whatsoever and without prejudice to its right to retender at any time in the future and in such case no bidder/intending bidder shall
have any claim arising out of such action.
(b) GOBVI reserves the right to invite revised responses from the Applicants by issue
of an addendum, at any stage, without liability or any obligation for such invitation
and without assigning any reason. This request for EOI does not give rise to any rights
and is not an offer or an invitation to offer.
(c) The Government, by this process, does not intend to assume any legal obligation
whatsoever, including any binding relationship of any kind, with any Applicant, nor
will the Government accept any liability howsoever arising, in relation thereto. By
this document Applicants are so informed, and unconditionally acknowledge that
they are fully aware that through an expression of interest, no entitlement
whatsoever vests, or will vest in them.
(d)Participation by any party in this EOI pursuant to the invitation by GOBVI shall
be considered to be an acceptance of all the terms and conditions of this invitation by
such party and no claims or disputes raised by it during or subsequent to the award
process shall be entertained by GOBVI.
(e) All documents and other information supplied by GOBVI or submitted by an
Applicant to GOBVI shall remain or become the property of GOBVI. GOBVI will not
return any application or any information provided along therewith.
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 9
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
(f) Scope of the requirement and qualification criteria may be modified at Request for
Proposal (RFP) Stage.
(g) The applicants shall bear all costs associated with the preparation and submission
of its EOI. GOBVI will in no case be responsible or liable for these costs, regardless of
the conduct or outcome of EOI process.
Expression of Interest must be delivered in a sealed envelope to the following address
latest by 3:00 pm EST, on 25TH July, 2012 and be clearly marked “Expression of
Interest for Planning, Design and Financing Consultancy Services for Runway and
Airfield Expansion of Terrance B Lettsome International Airport”. GOBVI shall not
be responsible for the loss or non-receipt or delay in the receipt of any Expression of
Interest application sent by post or courier.
Address for Communication:
MINISTRY OF NATURAL RESOURCES & LABOUR.
Central Administration Complex
33Admin Drive
Road Town Tortola, BVI
VG1110
-----
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 10
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
FORMS FOR EXPRESSION OF INTEREST
FORM I- GENERAL INFORMATION
ITEM
BIDDER’S INFORMATION
Bidder’s registered name:
Bidder’s country of constitution
Bidder’s year of constitution
Bidder’s registered address in the country of
constitution
Bidder’s authorized representative
(name, address, telephone numbers, fax numbers,
e-mail address)
Note:
him/her to submit the EOI.
FORM II- FINIANCIAL INFORMATION OF THE CONTRACTOR
FINANCIAL
INFORMATION IN USD
YEAR
FINANCIAL INFORMATION FOR PREVIOUS 3 (THREE) FINANCIAL YEARS
2011-2012
2010-2011
2009-2010
Information from Balance sheet
Total Assets
Total Liabilities
Net Worth
Liquid Resources (Cash
in hand)
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 11
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
Current Liabilities
Information from Income Statement
Total Revenue
Profit Before Taxes
Note:
Contents of this form should be certified by the statutory auditor of the applicant.
FORM III - AVERAGE ANNUAL PROJECT TURNOVER
Financial Information in USD
Annual Turnover data (Consultancy only)
2011-2012
2010-2011
2009-2010
Total Revenue
Average Annual Project Turnover
2011-2012
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 12
REQUEST FOR EXPRESSIONS OF INTEREST- AIRPORT PROJECT
FORM IV –STATEMENT OF EXPERIENCE ON SIMILAR (AIRPORT) PROJECTS
Item
No.
Customer Name,
Address,
Representative and
Phone No.
Project
Description
Scope
of
Work
Location
Runway
length
Value
Start/
Stop
dates
Schedule
Budget
(On
schedule
/
delayed)
(On
budget/overrun
FORM V – STATEMENT OF EXPERIENCE FOR CONTRACTING SERVICES OF SIMILAR MAGNITUDE OF WORK
Item
No.
Customer Name,
Address,
Representative and
Phone No.
Project
Description
Scope
of
Work
Location
Runway
length
Value
Start/
Stop
dates
Schedule
Budget
(On
schedule
/
delayed)
(On
budget/overrun
FORM VI – LITIGATION HISTORY
YEAR
Award For or AGAINST Applicant
Name of client, cause of
litigation, and matter in dispute
Disputed amount
(current value)
MINISTRY OF NATURAL RESOURCES AND LABOUR
Page 13
Download