Winfrith Case Study 1 - SGHWR UKAEA, Winfrith. Site Closure Programme, Front End Engineering Contract Project Title SGHWR - Front End Engineering of the Decommissioning. Work Value The value of the Front End Engineering was £2.0 Million. Brief project overview The Winfrith Steam Generating Heavy Water Reactor (SGHWR) was a prototype powerproducing reactor, which operated between 1968 and 1990. Most of the systems associated with the operation of the reactor, other than those providing an ongoing safety function, are no longer operational and the reactor is now in a passive care and maintenance condition. Decommissioning of the reactor is being carried out in two sequential phases. Contract 1 will remove systems, components and equipment principally located in the secondary containment. Contract 2 will address the primary containment components, systems and equipment of the SGHWR. The MWH team provided support services to UKAEA for the Front End Engineering studies. Specific activities undertaken The first phase of work was to carry out an assessment of options for decommissioning of the SGHWR using Value Engineering techniques which led to the determination of the best approach. The team broke the project down to a series of tasks which included: Modification to Safety Case documentation Preparation of a Segmentation report - detailing precisely how the reactor is dismantled and segmented Carrying out Changeroom assessments Carrying out structural and crane assessments of the existing building crane Preparation of Decontamination and Decommissioning report Carrying out a Radioactive Waste Estimates Assessment, Waste Categorization Assessment and Waste Stream Assessments Preparation of Demolition Assessments and Studies Carrying out Activation Analysis work on the SGHWR reactor materials to determine radioactive waste activation levels Preparation of the Concept Design for the Intermediate Level Waste processing plant Preparation of a 3D model and animation package to provide a computerised visualization of the demolition sequence Preparation of a technical specification and then procuring a nuclear rated Industrial Robotic Demolition Machine Preparation of a technical specification for the design and build of a mock up of the SGHWR reactor to demonstrate segmentation approaches and techniques 1 Winfrith Case Study 1 - SGHWR The next phase of the work was to prepare the concept design package. After preparing the maintenance strategy and the detailed cost estimate, a detailed programme (using Primavera P3e planning tool) and an overall assessment of risks to the project were brainstormed and evaluated. An Operations plan was prepared to evaluate the best shift operating plan to employ. Discussions were held with UKAEA to recommend a preferred procurement approach. Timescales for the work Work on the SGHWR project commenced on appointment of MWH in May 2004 and the last task order was completed in December 05. Who the team comprised of The MWH delivery team was made up of the following members: MWH - provision of lead consultant, project management, engineering overview and coordination of the design team Studsvik - provision of radiological design and assessments INBIS - provision mechanical and electrical designs Pell Frishmann - provision of civil and structural designs Electrowatt Ekono - provision of nuclear ventilation and containment engineering design Nuclear Decommissioning Limited - safety case assessment design Gleeds - preparation of cost estimate and cost risk assessment Success factors The work resulted in an overall reduction in the projected work of 5 years - reducing the completion date from 2020 to 2015. The work has also resulted in reduction in risks, keeping costs within UKAEA's overall budget. 2