CHAPTER 11. SOCIAL IMPACT ASSESSMENT 11.1 INTRODUCTION Social Impact Assessment is carried out to ascertain the impacts, which would occur due to implementation of the project. The exercise facilitates identifying types and extent of impacts and also identifying impacts that can be minimized by good engineering practices. Efforts are made to mitigate impacts, which cannot be minimized during the planning stage. The Impacts Assessment is thus a systematic process of identifying and mitigating impacts on individuals or society in consultation with the individuals or society affected. The National Highways Authority of India (NHAI) has been entrusted with the development, maintenance and management of such of the National Highways as entrusted to it by the Government of India. Under NHDP Phase-III programme, the Government has decided to convert some of the existing two lane highways into four lane/six lane highways. These projects are to be executed by private entrepreneurs as Design, Build, Finance and Operate (DBFO) projects. NHAI has accordingly taken up preparation of Feasibility-cum-Preliminary Design of important NH corridors to be implemented on DBFO pattern. The project under consideration aims at developing the NH-8D from junction of NH 8B and NH 8D near Jetpur town and upto the Somnath temple on the western coast line in Gujarat. The project intends to construct four/six lane divided carriageway. The Total length of the corridor approximately is 127 km. The objective of the study as mentioned in ToR includes the following: To establish the technical, economical, and financial viability of the project and prepare detailed project reports for rehabilitation and upgrading of the existing intermediate 2-lane National Highway (NH) section to 4 to 6 lane divided carriageway configuration. To establish the viability of the project designed as a partially access controlled facility, taking into account the requirements with regards to rehabilitation, upgrading and improvement based on highway design, pavement design, provision of service roads wherever necessary, type of intersections, underpasses / ROB’s, rehabilitation and widening of existing and/ or construction of new bridges and structures, road safety features, quantities of various items of works and cost estimates vis-à-vis the investment and financial return through toll and other revenues. Prepare Feasibility-cum-Preliminary Designs, Social and Environmental action plans as appropriate and documents required for tendering the project on commercial basis for international / local competitive bidding. 11.2 CORRIDOR DESCRIPTION The project corridor Jetpur-Somnath, NH8D, starts at Jetpur in Rajkot district, traverses through only Jetpur Taluka of Rajkot district which further runs across Junagadh district through, Vanthli, Keshod, Veraval and connects the holy place of lord Somnath temple right on the sea coast at Veraval-Somnath. Starting point of the corridor is from junction of NH 8B and NH 8D near Jetpur 11-1 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT town and pass through commercial and residential zone of the town on the both the sides of the road. End point of the corridor is just approach to the Somnath temple on the western coast line. The corridor starts at Km. 0.000 and ends at Km 127.000. The total length of the project corridor is 127Km. The average carriageway width along the entire stretch is 7m with minimum of 1.5m paved shoulder on either side. The urban centres such as Jetpur, Junagadh, Keshod, Vanthali are located along the project corridor. The entire length of corridor under present consideration falls under NH divisions of R&B Department of Government of Gujarat namely Rajkot Divisions. It is understood from the interaction with officials from NH division of R&B department that in general there is a land width of 100 ft available with government for most of the length, even in the proposed Keshod bypass. However, it is not very clear that whether the existing carriageway is centrally placed or eccentrically placed in the available land width. The project corridor passes through several urban & semi urban areas, which have series of developments with residential and commercial activities. There are few major urban sections along the project corridor namely Nawagadh, Jetpur between Km 0.0 and km 5.0, Junagarh between km 25.0 to 42.0 and Kesod between km 66.0 and 79.0. Amongst Junagarh town is biggest amongst all these settlements. The details of all the bypasses are listed in the table 11-1. Table 11-1: Details of Bypass S. No 1 2 3 4 5 6 Existing Chainage (Km) Length From to 0.000 6.400 6.400 25.050 26.300 1.250 34.050 43.050 9.000 46.150 46.950 0.800 60.650 62.700 2.050 65.840 79.450 13.610 Side Name Right Right Right Left Left Right Jetpur Bypass, Start point is at Km 111 of NH-8B Junagadh Bypass-1 Junagadh Bypass-2 Vanthali Realignment Agatrai Realignment Kesod Bypass Junagarh has already been bypassed in the section between Km 26.3 and Km 36.5. The bypass in this section has two lane carriageways with paved shoulders on both sides. In the rest of the urban areas as mentioned above, continuous developments have come up on both sides almost in the entire length. The clear land width available between building lines at these urban settlements is much less than the minimum land required accommodating 4 lanes plus service roads to segregate local traffic. Widening the project corridor through these urban settlements not only cause traffic safety hazards, congestion, delay, but also pose severe environmental and social concerns of resettlement and rehabilitation. As per the recent notification of MoSRTH, all new National Highway-widening projects should acquire land for 60 m width as RoW to cater to future expansion requirements of the roads. Since such a width of land has to be necessarily vacated for the road corridor the impacts shall be of a concentrated nature within this area. Thus this band will be considered as corridor of direct impact for the present assessment. 11-2 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT 11.3 DISTRICTS AND TEHSILS TRAVERSED BY THE PROJECT CORRIDOR The project Corridor passes through seven Talukas in two Districts namely Rajkot and Junagarh. 105 villages would be directly impacted, 9 in Rajkot and remaining in Junagarh District. Details of each of the districts are presented in Table 11-2. Table 11-2: Number of Settlements along the Project Corridor S. No District Taluk Urban Village 1 Rajkot Jetpur 1 3 1 1 0 0 1 7 9 21 16 18 4 17 20 105 2 Junagadh Total Junagadh Vanthali Keshod Mangrol Malia Veraval 7 Source: Census of India 2001 Figure 111-1: Project Corridor 11-3 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT Major part of the project passes through Agricultural area and where ever there are urban settlements areas are with bypasses (Details of all the bypass location are presented in Table 11-1). 11.4 SOCIAL ANALYSIS Social analysis is done on the basis of rapid social assessments carried out in the field and also on the basis of secondary sources of Information collected through Census Surveys. The following aspects of the project corridor and the project affected persons (PAPs) are assessed apart from the identification of potential impacts and minimization of those impacts to the extent possible and formulation of mitigation measures in the case of unavoidable impacts; Occupation profile of PAPs; Poverty scenario along the corridor; Social vulnerability of Population along project corridor; Education Profile of affected population. 11.4.1 Identification of Likely Impacts PAPs are categorized in terms of their extent and nature of impacts. The major likely impacts foreseen in the project would be due to agricultural land acquisition, loss of private buildings and other assets, loss of Common Property Resources (CPRs), religious structures and utilities, etc. Apart from these there would be livelihood losses and losses to people within the ROW in the project. 11.4.2 Minimisation of Impacts The inventory gathered during the screening stage formed the baseline for identifying unwarranted impacts. These are minimized during subsequent stages of designing without compromising on the engineering aspects. The new constructions have in most places been accommodated within the existing Right of Way. In most cases, large-scale impacts are relegated by choice of widening options. For instance, when socially sensitive receptors are found to be concentrated on one side, widening is proposed on the other side (Eccentric Widening). In cases, where there are settlements on both sides of the corridor, impacts are minimized by adopting Concentric Widening, that is minimum widening on either side, to save as many structures as possible. The requirement of additional land is assessed after such impact minimization measures are incorporated in the design. The details of land to be acquired along with ownership details are given in the land acquisition plan. This has considered the proposed improvements involving minor changes in alignment adjustments, curve straightening, provision of approaches to the newly constructed bridges, intersection redesign, and other upgradation planned to improve engineering, user safety and traffic flow. 11.4.3 Formulating Mitigation Measures and RAP Residual impacts after minimization have been mitigated within the provision of the entitlement framework for the project. Despite all efforts for minimization of impacts, there are some residual 11-4 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT impacts in the project. Mitigation measures have been developed to address such impacts. Entitlements to the project affected persons who are titleholders and non-titleholders are detailed out in the report. Community Property Resources (CPRs) along the corridor are few in number; however such structures affected have to be rehabilitated. Costs to relocate CPRs and utitlities are also incorporated in the project. An appreciation of the existing government programmes and policy measures are done in view of rehabilitation of PAPs, particularly the vulnerable groups. All these are accounted for in the resettlement budget and a time frame for implementation of the provisions in RAP is given. 11.5 SOCIO-ECONOMIC PROFILE The socio-economic profile along the project corridor includes an overview of the population distribution, density of population, sex ratio, literacy rate, details of scheduled caste/tribe population, work force participation rate, agricultural and industrial scenario. 11.5.1 Population Distribution The growth rate of population in the project influence area is 3.17 percent which is higher than the average growth rate of population in the state (2.06 percent). The highest population growth rate is 4.66 percent which is observed in Veraval Taluka of Junagadh district followed by 4.46 percent in Junagadh Taluka. In rest of the Talukas, growth rate ranges from 1 percent to 2 percent. Jetpur Taluka of Rajkot district has registered the lowest growth rate of 0.77 percent. Taluka wise demographic characteristics in project influence area are presented in Table 11-3. Table 11-3: Population Distribution in Talukas along the Project Corridor, 2001 District Taluka Rajkot Jetpur AAGR (91-01) 1991 2001 122699 132423 0.77 2514122 3169881 2.34 Junagadh 200703 310628 4.46 Vanthali 41976 51987 2.16 Keshod 89905 104251 1.49 Mangrol 9735 11735 1.89 Malia 30778 36941 1.84 Veraval 141014 222458 4.66 2394859 2448173 0.22 636810 870423 3.17 41310000 50671017 2.06 Rajkot District Total Junagadh Population Junagadh District Total Project Influence Area Gujarat State Source: Census of India, 2001 and 1991; *Note: Figures are rounded of to first decimal place 11.5.2 Population Density The project influence area has population density of 741 persons per Sq. Km in 1991 and 1012 persons per Sq. Km in 2001. In 2001 the population density varies from 261 persons per Sq. Km in Mangrol Taluka to 2017 persons per Sq. Km in Junagadh Taluka (Table 11-4). 11-5 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT Table 11-4: Population Distribution and Density in Talukas along Project Corridor, 2001 District Taluka Density (Persons/Sq Km) (Sq. Km) 1991 2001 1991 2001 108.76 122699 132423 1128 1218 11200.00 2514122 3169881 224 283 Junagadh 154.04 200703 310628 1303 2017 Vanthali 143.97 41976 51987 292 361 Keshod 167.72 89905 104251 536 622 Mangrol 44.94 9735 11735 217 261 Malia 123.94 30778 36941 248 298 Rajkot Jetpur Rajkot District Total Junagadh Population Area Veraval 116.48 141014 222458 1211 1910 Junagadh District Total 8800.00 2394859 2448173 272 277 Project Influence Area 859.84 636810 870423 741 1012 196024.00 41310000 50671017 211 258 Gujarat State Source: Population Totals of Gujarat, Census of India, 2001 and 1991 11.5.3 Sex Ratio in the Project Influence Area As per the Census estimates (2001) the sex ratio (females/1000 male) of project influence area is 934 which is higher than the state average of 920. All the districts have shown a decrease in sex ratio from 1991-2001 (Table 11-5). During 2001, amongst all the Talukas, Malia Taluka registered the highest sex ratio (964) followed by Veraval (956). A decline in sex ratio is observed in five Talukas of project influence area during 1991-2001 in accordance with the decline observed at state level. Table 11-5: Gender Ratio of Taluka along the Project Corridor, 1991 – 2001 District Taluka Rajkot Jetpur Rajkot District Total Junagadh Vanthali Keshod Junagadh Mangrol Malia Veraval Junagadh District Total Project Influence Area Gujarat State Sex Ratio 1991 2001 922 946 943 914 929 962 962 961 959 940 934 906 930 931 911 933 938 964 956 955 934 920 Source: Census of India, 2001 *Note: Figures are rounded of to first decimal place 11.5.4 Vulnerable groups in the Influence Area Distribution of scheduled caste and scheduled tribe population is presented in Table 11-6. The percentage distribution of scheduled caste is higher than scheduled tribes in project influence area. About 66846 SC (1.86 percent of the total SC population in the State) and 5398 ST population resides in the project influence area. Mangrol, Vanthali and Keshod Taluka has a 11-6 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT higher percentage of SC population (percentage of SC population to total population in the state), ranging between 13 to 11 percent respectively. Table 11-6: SC &ST Population along the Project Corridor, 2001 District Taluka Rajkot Jetpur Rajkot District Total Junagadh Vanthali Keshod Junagadh Mangrol Malia Veraval Junagadh District Total Project Influence Area Gujarat State Population 2001 Schedule Caste Schedule Tribe 9114 208 244364 13163 22014 2690 6566 101 11203 733 1549 0 3416 107 12984 1559 235624 18832 66846 5398 3592715 7481160 % to Total Population Schedule Caste Schedule Tribe 6.88 0.16 7.71 0.42 7.09 0.87 12.63 0.19 10.75 0.70 13.20 0.00 9.25 0.29 5.84 0.70 9.62 0.77 7.68 0.62 7.09 14.76 Source: Census of India, 2001 and 1991; 11.5.5 Literacy Rate As per the Census estimates (2001), 69 percent of the population are literate in the State, where as the average literacy rate is lower (67 percent) in the project influence area. Within the project influence area, Junagadh Taluka has the highest literacy rate (73 percent) followed by Jetpur (70 percent) and Keshod (68 percent). The lowest literacy rate was observed in Malia (55 percent) and Veraval (59 percent) (Table 11-7). Table 11-7: Literacy Rate of Taluka along the Project Corridor, 1991 – 2001 District Rajkot Taluka Jetpur Rajkot District Total Junagadh Vanthali Keshod Junagadh Mangrol Malia Veraval Junagadh District Total Project Influence Area Gujarat State Literate Population 1991 2001 74341 92772 1419681 2033946 133075 225781 23501 32498 55200 70421 5359 7180 13758 20292 69441 130359 1217725 1408878 374675 579303 21131400 29827750 Literacy Rate (%) 1991 2001 61 70 56 74 66 73 56 63 61 68 55 61 45 55 49 59 51 68 59 67 51 69 Source: Census of India, 2001 and 1991; 11.5.6 Work Participation Rate The given Table 11-8 describes the average annual growth rate and work participation rate at district and Taluka level (within the project influence area). The average WPR in project influence area is 34 percent in 2001. During 2001, Mangrol of Junagadh district has the highest WPR (48 percent) followed by Malia (44 percent) and Vanthali (43 percent). The lowest WPR is recorded in Veraval (31 percent) and Junagadh (32 percent), followed by Jetpur (34 percent). 11-7 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT During the decadal period (1991-2001), the growth rate in the number of workers is observed to be higher (6 percent) in Mangrol, Malia and Veraval Talukas of Junagadh district and lower (3 percent) in Jetpur and Keshod Talukas of Rajkot and Junagadh districts respectively. Table 11-8: Work Participation Rate along the Project Corridor, 2001 District Total Workers 1991 2001 34778 44885 927237 1244806 59991 99231 14957 22414 28126 38116 3251 5631 9552 16432 39170 69970 922375 1000842 189825 296679 16620519 21255521 Taluka Rajkot Jetpur Rajkot District Total Junagadh Vanthali Keshod Junagadh Mangrol Malia Veraval Junagadh District Total Project Influence Area Gujarat State AAGR of Workers (1991-01) 3 3 5 4 3 6 6 6 1 5 2 WPR 1991 28 37 30 36 31 33 31 28 39 30 40 2001 34 39 32 43 37 48 44 31 41 34 42 Source: Population Totals of Gujarat, Census of India, 2001; Note: Figures are rounded of to first decimal place 11.5.7 Type of Workers As per the Census estimates (2001), 91 percent of worker population are main workers in the Jetpur Taluka of Rajkot district. The percentage of main workers in the 6 Talukas of Junagadh district within the project influence areas ranges between 70 percent (in Mangrol) and 91 percent (in Junagadh). About 30 percent of total workers are marginal workers in Mangrol and Malia Talukas of Junagadh district (Table 11-9). Table 11-9: Type of Workers within the Project Influence Area, 2001 District Taluka Rajkot Jetpur Rajkot District Junagadh Vanthali Keshod Junagadh Mangrol Malia Veraval Junagadh District Project Influence Area Gujarat State Main Workers 2001 No. % Marginal Workers 2001 No. % 40883 1076436 91 86 4002 168370 9 14 90052 18675 31865 3950 11615 62130 785530 259170 17025074 91 83 84 70 71 89 78 87 33.6 9179 3739 6251 1681 4817 7840 215312 37509 4230447 9 17 16 30 29 11 22 13 8.35 Source: Census of India, 2001; *Note: Figures are rounded of to first decimal place 11.5.8 Agriculture Base Agriculture is the backbone of the Rajkot district economy and fisheries related occupation plays a major role in Junagadh district. In Rajkot district, about 34 percent of the total operational land holdings are small (having an area of 1-2 ha) where as in Junagadh district it is 37 percent. At the same time the percentage of small land holding to total land holding is 28 percent at the state level. The percentage of ‘large’ (10 ha and above) land holding to total operational land holding is 11-8 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT less than 2 percent in both Rajkot and Junagadh districts, where as the state average is 2.4 percent (Table 11-10). Table 11-10: Number and Types of Operational Land holdings in Project Districts Operational Land Holding (in HA) 0-1 ha 1-2 ha 2-4ha 4-10 Ha 10 ha & Above Total Marginal Small Semi-medium Medium Large Rajkot % Junagadh % Gujarat % 35835 89539 83456 50609 5250 264689 13.54 33.83 31.53 19.12 1.98 100.00 55050 96203 67008 39737 3611 261609 21.04 36.77 25.61 15.19 1.38 100.00 1033797 1057681 966067 632652 90896 3781093 27.34 27.97 25.55 16.73 2.40 100.00 Source: Statistical Abstract, 2007 11.5.9 Industrial Base Project districts have mainly small- scale industries such as food based industries; followed by the engineering based industries, polymer based industries and cement industries. The boundary walls of some of the industries are likely to be affected. A total number of 43 industries are situated along the project corridor and are likely to be partially affected due to the proposed widening scheme. The occupational pattern in Rajkot district is primarily based on manufacturing and service sector. In the Engineering and Auto-ancillary sector, diesel engine is the leading business with around 105 manufacturing units is operational in the district. Jetpur Taluka of the district is famous for dyeing and printing business. Small and medium industries are dominated by foundries, engineering and automobile works, textile related units, gold and jewellery, handicrafts, spices, medicines and wall-clocks. Fish processing industry is a major sector in Junagadh. Presence of huge reserves of Limestone makes the cement industry a thriving industry sector in the district (Table 11-11). Table 11-11: Medium and Large Scale Industries in Junagadh District Name of the company Agro Marine Export Limited. Creative castings Limited. Gujarat Dairy Development Corporation Limited. Indian rayon and Industries Limited Taluka Junagadh Junagadh Junagadh Veraval Production Marine products Alloy steel castings Pasteurized milk, butter Chemicals Source: Statistical Abstract, 2007 11.5.10 Cultural properties There are about 64 religious structures that exist along the project road; most of them are situated within 30m from the edge of the carriageway. The widening has been designed such that most of these structures remain unaffected or least affected due to the proposed project (Table 11-12 and Table 11-13). Table 11-12: Protected and Conserved Monuments Located in the Project Districts District Taluka Places of Interest / Religious Importance Distance from Junagadh (in KM) ASI protected Monuments Rajkot Junagadh Dhoraji Junagadh Dhoraji Fort Uparkot 16.7 1.21 --Ashokan Rock (Edicts) Distance from NH8D (in KM) 2.15 11-9 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT District Taluka Places of Interest / Religious Importance Distance from Junagadh (in KM) Junagadh Girnar Hill Temple 5.59 Junagadh Mahabat Makbara 0.3 Junagadh Gir Sanctuary 15.48 Junagadh Sakar Bagh Zoo 0.15 Junagadh Swaminarayan Mandir 0.12 Junagadh Damodar Kund 2.87 Manavadar Pipleshwar Mahadev --Vanthali Step well 0.5 Mangrol ----Mangrol ----Mangrol ----Veraval Somnath Temple 1 Source: Google earth, census of India handbook and internet 11.5.11 Distance from NH8D (in KM) ASI protected Monuments Baba Pyare, Khapra Kodia caves --------------Jami Masjid Bibi Masjid Raveli Masjid --- 17.09 Level of Urbanization Out of the 9 urban settlements, three are of Class-I and two settlements are of Class-II. Rajkot district accounts for one and Junagadh accounts for eight urban settlements in the project influence area (Table 11-13 and Table 11-14). Table 11-13: Urban Settlements along the Project Corridor District Rajkot Taluka Jetpur Urban Settlement Jetpur (M) Joshipura Junagadh (M) Timbavad Vanthali (M) Keshod (M) Veraval (M) Bhalpara Patan Junagadh Vanthali Keshod Junagadh Veraval Source: Population Totals of Gujarat, Census of India, 2001 Table 11-14: Category of Urban Areas along the Project Corridor, 2001 District Class I URBAN AGGLOMERATIONS /TOWNS HAVING POPULATION Class II Class III Class IV Class V Class VI Total Rajkot Junagadh 1 2 0 2 0 0 0 1 0 1 0 2 1 8 Project Influence Area 3 2 0 1 1 2 9 Note: Class 1: 1, 00,000+; Class II: 50,000-99,999; Class III: 20,000-49,999; Class IV: 10,000-19,999; Class V: 5,000-9,999; Class VI: Below 5,000 11.6 INFLUENCE AREA OF THE PROJECT CORRIDOR Upgradation of the Jetpur to Somnath section of NH-8D is expected to have both positive and negative impacts on the environment, especially along the Corridor of Direct Impact (CODI). Efforts have been taken to modify the design of the project highway in view of minimizing losses 11-10 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT to the Project Affected People, some of them would be negatively impacted especially due to land acquisition and clearing of illegal habitations within ROW. There would be losses to a few religious and cultural properties and loss of economic opportunities/livelihood and sources of earning as a result of the project. 11.7 IMPACT OF PROJECT ON PEOPLE The impacts are classified into three types, impacts to private land, structures and community properties. The impact to private land has been elucidated from revenue maps and data as collected from the relevant revenue officials and departments. This has been detailed in the Land Acquisition chapter of this report (Chapter 4 of Resettlement Action Plan). The impact on various types of structures is listed in Table 11-15. These are the structures within the Proposed ROW. The respective owners of these structures are titleholders. Table 11-15: Number of Structures Affected along the Project Corridor S. No 1 No. of Affected (Area) in RHS No. of Affected (Area) in LHS Pucca 62 (8057) 32 (4536) 94 (12593) Semi-Pucca 80 (8307) 59 (7329) 139 (15636) Type of Structure Residential Kutcha Sub Total 2 Commercial Mixed (Residential + Commercial) Cattle Shed 153 (8102 97 (15115) 250 (23217) 105 (8357) 230 (13186) Kutcha 12 (98) 7 (34) 19 (132) 290 (13029) 209 (23506) 499 (36535) Pucca 13 (2338) 14 (1433) 27 (3771) Semi-Pucca 8 (594) 12 (766) 20 (1360) Kutcha 0 (0) 1 (4) 1 (4) 21 (2832) 27 (2203) 48 (5035) Pucca 3 (825) 1 (50) 4 (875) Semi-Pucca 7 (355) 4 (365) 11 (720) Kutcha Industrial Sub Total Grand Total Source: Census Survey, LASA 2009 14 (384) 247 (28613) 125 (4829) Sub Total 5 4 (45) 95 (11910) Pucca Sub Total 4 10 (339) 152 (16703) Semi-Pucca Sub Total 3 Total No. of Affected (Area) 0(0) 0(0) 0(0) 10 (1180) 5 (415) 15 (1595) Pucca 11 (3007) 6 (192) 17 (3199) Semi-Pucca 7 (802) 11 (658) 18 (1460) Kutcha 0(0) 0(0) 0(0) 18 (3809) 17 (850) 35 (4659) 491 (37553) 353 (38884) 844(76437) LASA has conducted a preliminary social survey during 21st June 2009 to 10th July 2009. It is observed from the survey that there are some squatters and encroachments along the project corridor. The questionnaire administered to collect socio-economic information is given in Annexure 3.1 and Structure details are listed in Annexure 3.2 of Resettlement Action Plan. 11-11 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT 11.7.1 Impact on Community Properties Among the community property category, 43 tube wells, 95 wells and 11 ponds would be affected (Table 11-16). Considerable impact on the loss of water sources along the project corridor is envisaged. This impact is likely to be significant given the concern about inadequacy of piped water supply along the project corridor. The data also signify that all the people along the project corridor are dependent on underground water sources. Table 11-16: Community Properties Affected in the Project Government 40 Public/Semi Public Structure Bus Tube Educational Stop Well 7 18 43 Religious Structures Well Pond Temple Shrine Masque 95 11 48 15 1 Total 173 Source: Census Survey, LASA 2005 11.7.2 Age and Gender Distribution The age wise distribution and sex ratio of PAP’s are detailed out in 11-18. A major segment of PAPs (517) are in the age group of 20-35 years and the sex-ratio among this group is the second highest (631). Population above 65 years of age constitutes 7 percent of the total PAPs (Table 11-18). Table 11-17: Age and Sex wise Distribution of People along the Project Corridor Category Age <20 years 20 to 35 years 35 to 50 years 50 to 65 years Age > 65 years Total Males 205 317 279 131 53 985 Females 105 200 143 49 55 552 Total 310 517 422 180 108 1537 Distribution 20 % 34 % 27 % 12 % 7% 100 % Sex Ratio 512 631 513 374 1038 560 Source: Census Survey, LASA 2009 11.7.3 Vulnerable Population Affected in the Project Population belonging to scheduled caste/tribe, other backward class and those who are below poverty line are categorised as vulnerable population. Accordingly about 607 households (52 percent of the total affected households) will be affected due to the proposed widening (Table 11-19Table 11-18). Among the vulnerable population, ST constitutes 5.6 percent and SC constitutes 2 percent. There are 3 households living below poverty line. Table 11-18: Vulnerable Groups of Affected in the Project SC ST Vulnerable OBC 12 34 558 BPL Non-Vulnerable General Total 3 561 1168 Source: Census Survey, LASA 2009 11-12 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT 11.7.4 Occupational Pattern A major segment of PAPs (44 percent) are engaged in commercial activities and about 36 percent are engaged in agricultural activities Table 11-20. Table 11-19: Occupational Pattern of Project Affected Population S. No. Category of Occupation Number of People % to the total Population 1 Cultivators 407 27 2 Agricultural Labour 139 9 3 Artisans 140 9 4 Commercial 677 44 5 Govt./Public Service 20 1.4 6 Non Agricultural Labour 82 5 7 Private Service 24 1.6 8 Others 48 3 1537 100 Total Source: Census Survey, LASA 2009 11.7.5 Literacy Rate Out of the total number of 1537 PAPs 354 (23 percent) are illiterates and the remaining 1183 (77 percent) are literates. Among the literates, PAPs with secondary level of education constitute 46 percent and with primary level of education constitute 39 percent (Table 11-21). Table 11-20: Literacy Rates of Project Affected People Illiterate Primary Secondary Higher Technical Vocational Total 354 460 540 176 6 1 1157 Source: Census Survey, LASA 2009 11.8 COST OF REPLACEMENT OF STRUCTURES There are generally three major categories of structures that would be acquired due to the proposed project. A description of these categories and their construction costs (on the bases of their plinth areas) are estimated Based on the BSR rates of the Gujarat PWD. The costs of constriction of different types of structures are presented in Table 11-22. Table 11-21: Costing of the Structures S. No 1 2 3 4 Category of Structure Corrugated Asbestos Sheet Roof/tiled, Mud Wall and Flooring Corrugated Asbestos Sheet Roof/tiled, Brick Wall with Cement Mortar, Mud Flooring RCC roof, Brick wall with Cement Mortar, Cement Floor-Single Storey Ground Floor in RCC roof, Brick wall with Cement Mortar, Cement Floor-and First Floor with in RCC roof, Brick wall with Cement Mortar, Cement Floor Double Storey Typology of Structure Construction Cost (Rs/m2) Kutcha 1500 Semi-Pucca 3000 Pucca 4500 Ground and 1st Floor: Pucca 9000 11-13 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT S. No Category of Structure Typology of Structure Construction Cost (Rs/m2) 5 Ground Floor in RCC roof, Brick wall with Cement Mortar, Cement Floor-and First Floor with in Corrugated Asbestos Sheet Roof/tiled, Brick Wall with Cement Mortar Double Storey Ground Floor: Pucca and 1st Floor: Semi-Pucca 7500 Source: Junagarh Schedule of Rates, 2008 11.8.1 Compensation for the community assets lost: The unit costs for the community assets getting affected due to the project are provided in the following Table 11-23. Table 11-22: Unit Rates for Community Assets Community Assets Well Hand pump Place of worship Motor Shed & Bore Well & Pump Shed Unit Rate (Rs) 1,00,000 15,000 30,000 5,000 Community Assets Water Supply tap Water Tank Boundary Wall Iron Gate Unit Rate (Rs) 1000 10,000 500 2,000 Note: * The extent of impacts will be estimated during implementation by the Gujarat State PWD. Presently lump sum amounts have been considered as cost of compensation. 11.9 LAND ACQUISITION IN THE PROJECT The importance of land requirement in development projects needs no introduction. The ownership of such land may vest with the Government or any private person. For linear pattern projects such as the construction of roads, canals, pipelines, etc., minimum horizontal strip of land is required for improvements along the finalized alignment under acquisition. The land acquisition is generally spread over administrative boundaries of different districts. This necessitates co-ordination between the concerned administrative units. Further, another general feature observed is of encroachment along such linear projects. In this project, on examination it has been observed that such encroachment (encroachment here refers to Government Land) has been prominent at settlement stretches along the corridor. Such encroachments will be cleared due to requirement of land for the project corridor improvement. 11.9.1 Requirement for Land In accordance with the stipulated 60 meter RoW and for amenities like rest areas, truck lay byes, and service roads proposed as part of the project development activities, the land requirement is estimated to be to the tune of 416.63 Ha. 11.9.2 Acquisition of Private Land For the proposed project, acquisition of private land (titleholder) will be taken-care of under the aegis of the National Highway Act of 1956. Under the provisions of this act, the Government or any department of the Government can acquire land from the people for public purpose. 11-14 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT 11.9.3 Legal Framework for Land Acquisition With the increase of movement of traffic on account of industrial advancement it was found necessary that important highways of the country be developed and maintained by the Central Government. To achieve this objective The National Highways Bill, 1956 was introduced in the Parliament. The Land Acquisition (LA) for this project is to be undertaken in accordance with the provisions of this act. The following are the major provisions of the act for the land acquisition. Section 3A provides for notification to landowners 4 about the interest of the Government to acquire the notified land; Section 3B&3F provides power and right to the person authorized by the central government to make inspection, survey, measurements, valuation or inquiry; Section 3C permits landowners to express their objections against such land acquisition; Section 3D declaration of acquisition if no objections has been made to the competent authority; Section 3E provides power to take possession of land once the amount determined by the competent authority has been deposited under sub-section (1) of section 3H; Section 3G allows the competent authority to decide on the compensation to be paid; Sections 3H provision for deposit of payment determined under section 3G in the manner as may be laid down by rules made in this behalf of the central government; Under section 3J as per the provision of this section nothing in the Land acquisition act 1894 shall apply to an acquisition under this act. 11.10 METHODOLOGY FOR COLLECTION OF LAND RECORDS In order to determine the extent of private property that will be acquired under the project, the Consultant has requested the respective District Magistrates of the two districts to arrange through the concerned revenue officials to provide the Revenue maps of all the villages through which the corridor traverses. The concerned officers from the Revenue Department of Jetpur Tehsil of Rajkot Disrict and Junagadh, Vanthali, Keshod, Mangrol, Malia, Veraval tehsils of Junagarh District are approached to obtain a copy of the village maps with the demarcated individual plots. The widening plan developed as part of the Feasibility study is superimposed on these village maps to identify the individual plots that are being affected. The plot numbers which are affected are provided to the revenue department for verification of the Khata numbers (plot numbers) and provide the Khataunis (land records) for each of them. All this has been compiled as part of the Land Acquisition Report, an independent document prepared for this project. 4 Notification should be published in two daily newspapers; one in the regional language and the other in English. The same should be published in the Gujarat Government Gazette. 11-15 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT 11.11 LAND REQUIREMENT FOR THE PROJECT The available RoW along the project corridor varies from 14 m to 45 m in revenue villages where as in forest areas the available RoW is in between 10 m to 15 m. The proposed project requires land to be acquired for up to 60 meters. In the revenue villages the total area of land to be acquired is 416.63 Ha. This includes the land required for geometric improvements and the development of amenities along the proposed project corridor. Village-wise land to be acquired is presented in Table 11-24. Table 11-23: Number of Plots Affected and Land Rate (Market Rate) along the Project Corridor S. No Village Taluka District 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 29 28 30 33 34 31 32 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 Nawagarh Padala Jetalsar Jetalsar Navisankdi Juni Sankadi Choki Kathrota Bhiyal Wadal-1 Wadal-2 Sukhpur Sukhpur Sabalpur Saragwada Khamdhron Khalipur Joshipara Jhajharda Jhajharda Chobari Koyli Sahpur-3 Sahpur-1 Sahpur-2 Sahpur-2 Vanthali-1 Vanthali-4 Vanthali-1 Vanthali-4 Kanjha Khokharda Vanthali-3 Kanjha Khokharda Godoi Tinmas Manakwada Agatrai-1 Agatrai-2 Agatrai-2 Mawana Keshod-3 Keshod-1 Keshod-1 Keshod-4 Kevadra Sondarda Sondarda Koylana Revadra Jetpur Jetpur Jetpur Jetpur Jetpur Jetpur Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Vanthli Keshod Keshod Keshod Keshod Keshod Keshod Keshod Keshod Keshod Keshod Keshod Keshod Keshod Keshod Rajkot Rajkot Rajkot Rajkot Rajkot Rajkot Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Junagarh Chainage From 0+000 1+400 2+314 6+250 9+363 11+700 12+780 16+734 17+427 18+800 21+536 23+572 23+600 24+400 26+317 29+186 31+300 31+630 32+936 32+600 33+347 35+400 35+521 37+750 39+575 42+800 44+371 44+370 43+750 43+750 49+443 49+610 46+884 50+200 52+445 53+211 56+018 56+250 60+018 60+017 58+100 64+936 64+936 63+700 66+450 66+450 70+550 72+375 79+400 80+669 84+241 To 1+400 2+314 4+600 9+363 11+700 12+780 17+400 18+800 18+800 21+536 23+572 25+242 24+400 24+706 29+186 31+300 31+630 32+936 34+200 33+347 35+400 38+382 36+116 39+575 40+300 44+371 46+250 50+200 44+100 44+325 49+610 49+880 50+200 52+000 53+211 56+018 56+250 60+018 64+936 64+936 60+200 66+065 66+065 66+450 70+550 70+550 72+375 74+900 80+669 84+241 84+615 Area to be Acquired (Sq. M) 73574.581 65292.313 137363.858 93425.245 69733.381 32530.798 132142.957 22449.249 29206.076 81905.494 61031.715 50372.553 24468.83 8876.66 85975.30 63199.03 10156.90 39341.17 37349.72 44286.18 122844.86 113409.94 35682.83 100845.33 43922.23 47201.00 17244.88 40053.42 20570.51 30694.19 9355.44 14400.01 67115.25 53950.60 22694.48 84302.87 7433.17 116982.45 35330.97 58421.95 120004.08 12065.43 21627.95 82375.02 66883.54 56426.95 54580.78 76102.22 37760.410 107122.215 3488.393 Land Rate (Rs/Sq. m.) 2000 1500 1000 750 675 550 510 450 330 450 450 525 525 750 650 450 600 950 1200 950 750 585 675 675 675 675 750 950 850 850 450 450 750 450 450 360 450 375 375 375 375 330 750 1200 1200 750 375 645 645 405 240 Total Amount 147149162 97938470 137363858 70068934 47070032 17891939 67392908 10102162 9638005.1 36857472 27464272 26445590 12846136 6657495 55883945 28439564 6094140 37374112 44819664 42071871 92133645 66344815 24085910 68070598 29647505 31860675 12933660 38050749 17484934 26090062 4209948 6480005 50336438 24277770 10212516 30349033 3344927 43868419 13249114 21908231 45001530 3981592 16220963 98850024 80260248 42320213 20467793 49085932 24355464 43384497 837214.32 Remarks Jetpur Bypass Widening along Existing Alignment (EA) Junagarh Bypass 1 Widening along (EA) Junagarh Bypass 2 Widening along (EA) Vanthali Realignment Widening along (EA) Agatrai Realignment Widening along (EA) Keshod Bypass Widening along (EA) 11-16 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT S. No Village Taluka District 52 Panidhra Malia Junagarh 53 Jhuthad Malia Junagarh 54 Gadodar Malia Junagarh 55 Bhanduri Malia Junagarh 56 Jhadka Malia Junagarh 57 Gadu Malia Junagarh 58 Vshanvel Malia Junagarh 59 Sukhpur Malia Junagarh 60 Mohabatpura Malia Junagarh 61 Simar Malia Junagarh 62 Kindarwa Malia Junagarh 63 Sidokar Malia Junagarh 64 Supasi Malia Junagarh 65 Chanduway Malia Junagarh 66 Dari Malia Junagarh 67 Chatroda Malia Junagarh 68 Veraval-4 Malia Junagarh 69 Veraval-4 Malia Junagarh 70 Patan Malia Junagarh 71 Bhalpara Malia Junagarh Source: Land Acquisition Plan, LASA 2009. Chainage From 84+241 86+764 89+243 93+423 98+400 99+755 102+824 104+200 105+880 105+880 107+700 109+200 109+469 111+823 113+358 115+165 115+850 111+541 117+850 120+835 To 86+764 89+243 93+423 98+400 99+755 103+722 104+200 105+880 107+700 107+700 109+200 109+469 111+823 113+358 115+850 115+650 116+050 112+600 127+600 122+571 Area to be Acquired (Sq. M) 64658.837 81970.821 121793.146 148905.609 40886.911 117407.810 15414.626 49800.341 16165.243 38686.523 44885.394 8437.417 69906.859 46136.210 63436.721 11787.312 29812.889 63107.414 237320.962 52190.724 Land Rate (Rs/Sq. m.) 360 375 450 600 375 600 375 375 420 450 330 450 330 450 525 300 600 1200 600 300 Total Amount 23277181 30739058 54806916 89343365 15332592 70444686 5780484.8 18675128 6789402.1 17408935 14812180 3796837.7 23069263 20761295 33304279 3536193.6 17887733 75728897 142392577 15657217 Remarks Veraval Realignment Widening along (EA 11.12 COMPENSATION VALUES 11.12.1 Value of Land The value of the land for the purpose of calculating the compensation has been based on the village wise market rate. For the purpose, the registry rates of the plot are collected from the concerned revenue offices at the district level for each Development Block. The registry rates for each village are presented in Table 11-25. The land that shall be acquired from any government agency has also been estimated based on the market rates. In case there is no cost incurred in transferring such land the budget estimated for land acquisition will be adjusted accordingly. It is observed that the ribbon development along the project corridor has affected the traditional land use in the region. The barren/agricultural land has been converted for commercial purpose. The consultants have considered the market values of commercial land for calculating the cost estimates of land being acquired. 11.13 SUMMARY OF PROCEDURE ADOPTED FOR PREPARATION OF LAP The following steps are adopted for the preparation of detailed land acquisition plan; Step 1: Project Initiation - The NHAI has directed the consultant for preparing Land Acquisition Plan. Simultaneously, NHAI has issued letters to concern district collectors, acknowledging them about the project and also to provide necessary documents to consultants. District Collectors issued letters to Block Development Officers, who consecutively directed Amin’s to provide respective village maps, revenue records and cost of land to the consultant for preparation of lap. Step 2: Identification of Villages - The consultant has identified the villages through which the corridor passes. 11-17 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT Step 3: Collection of Revenue Maps - after the identification of villages, the consultant has approached respective Amin’s for collecting revenue maps. Step 4: Overlapping on Revenue Maps - Once after gathering revenue maps, the proposed widening plan are overlapped on the maps with the help of software packages. Step 5: Identification of Affected Plots - The exercise of overlapping could bring out specifically the affected plots. Such affected plots have been market out. Step 6: Demarcation - After identification of affected plots, the specific area of the affected plot could be demarcated. Step 7: Collection of Land Records - On demarcating the affected area, land records would be collected from Amin. This could fulfil the requirements of 3a. Step 8: Compilation - After collecting land records for all the plots from respective Amin, the same has been sorted out for affected plots. Step 9: Final Land Acquisition Plan - All the information collected from Amin has been worked out with respect to proposed widening plan. Finally this forms the lap for submission to NHAI. 11.14 R&R IMPLEMENTATION AND ARRANGMENTS Efficient implementation of Resettlement Action Plan (RAP) prior to handing over the site for civil construction works is a prerequisite. Implementation of RAP is designed and the entitlements for the project affected persons are estimated as per the guidelines of National Rehabilitation and Resettlement Policy, 2007. This would expedite the overall implementation of the project and will also provide adequate support to the population affected/displaced due to the proposed project. 11.15 ENTITLEMENT FRAMEWORK IN THE PROJECT The project requires approximately 416.63 Ha of land to be acquired. Households adversely affected by the project due to land acquisition, would be compensated for the loss of land and structures. Project Affected Households (PAHs) losing livelihoods would be assisted through income restoration measures. Residents of squatter settlements belonging to vulnerable groups would be provided with one-time shifting allowance. All non-title holders within RoW would be allowed to salvage material assets belonging to them. In the context of entitlements the following relevant definitions have been adopted in the project. Resettlement and rehabilitation measures would be provided following these definitions. “Affected Family” means a family whose primary place of residence or other property or source of livelihood is adversely affected by the acquisition of land for a project or involuntary displacement for any other reason; or any tenure holder, tenant, lessee or owner of other property, who on account of acquisition of land 11-18 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT (including plot in the abadi or other property) in the affected area or otherwise, has been involuntarily displaced from such land or other property; or any agricultural or non-agricultural labourer, landless person (not having homestead land, agricultural land, or either homestead or agricultural land), rural artisan, small trader or selfemployed person; who has been residing or engaged in any trade, business, occupation or vocation continuously for a period of not less than three years preceding the date of declaration of the affected area, and who has been deprived of earning his livelihood or alienated wholly or substantially from the main source of his trade, business, occupation or vocation because of the acquisition of land in the affected area or being involuntarily displaced or any other reason; “Affected Area” means area of village or locality notified by the appropriate Government as part of this Policy. “Agricultural Labourer” means a person primarily resident in the affected area for a period of not less than three years immediately before the declaration of the affected area who does not hold any land in the affected area but who earns his livelihood principally by manual labour on agricultural land therein immediately before such declaration and who has been deprived of his livelihood. “Agricultural Land” includes land being used for the purpose of – agriculture or horticulture; dairy farming, poultry farming pisci-culture, breeding of livestock or nursery growing medical herbs; raising of crops, grass or garden produce; and land used by an agriculturist for the grazing of cattle, but does not include land used for cutting of wood only; “Appropriate Government” means in relation to the acquisition of land for the purpose of the Union, the Central Government; in relation to a project which is executed by the Central Government agency or undertaking or by any other agency on the orders or directions of the Central Government, the Central Government; in relation to the acquisition of land for purposes other than (i) and (ii) above, the State Government; and in relation to the rehabilitation and resettlement of persons involuntarily displaced due to any other reason, the State Government; “BPL Family”: the below poverty line (BPL) families shall be those as defined by the Planning Commission of India from time to time and included in a BPL list for the time being in force; “Commissioner for Rehabilitation and Resettlement” means the Commissioner for Rehabilitation and Resettlement appointed by the State Government not below the rank of Commissioner or of equivalent rank of that Government; “Family” includes a person, his or her spouse, minor sons, unmarried daughters, minor brothers, unmarried sisters, father, mother and other relatives residing with him or her and dependent on him or her for their livelihood; and includes “nuclear family” consisting of a person, his or her spouse and minor children; “Holding” means the total land held by a person as an occupant or tenant or as both; “Khatedar” means a person whose name is included in the revenue records of the parcel of land under reference; “Land Acquisition” or “Acquisition of Land” means acquisition of land under the National Highway Act, 1956. “Marginal Farmer” means a cultivator with an un-irrigated land holding up to one hectare or irrigated 11-19 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT land holding up to half hectare; “Non-Agricultural Labourer” means a person who is not an agricultural labourer but is primarily residing in the affected area for a period of not less than three years immediately before the declaration of the affected area and who does not hold any land under the affected area but who earns his livelihood principally by manual labour or as a rural artisan immediately before such declaration and show has been deprived of earning his livelihood principally by manual labour or as such artisan in the affected area; “Occupiers” means members of the Scheduled Tribes in possession of forest land prior to the 13th day of December 2005; “Small Farmer” means a cultivator with an un-irrigated land holding upto two hectares or with an irrigated land holding up to one hectare, but more than the holding of a marginal farmer. “Vulnerable Group” includes persons such as the disabled, destitute, orphans, widows, unmarried girls, abandoned women, or persons above fifty years of age; who are not provided or cannot immediately be provided with alternative livelihood, and who are not otherwise covered as part of a family; Community Property: A community property is a structure or a piece of land that embodies a public utility, facility or a cultural / religious entity that belongs to a community or a group. For example a shrine, temple, mosque, church, school, well or a tube well is a community property. Compensation: Compensation refers to restitution made to property under the National Highway Act, 1956. In this context it refers to payment made by the Government exercising ‘Eminent Domain’. Right of Way (RoW): Means the entire strip of land traversed by any highway, street, county road or roadway easement including (longitudinal drains, service roads and embankment) for the purpose of vehicle travel, and includes the entire width of the land dedicated or acquired by law for right-of-way purposes. All along the proposed corridor available RoW is not enough to contract road so additional land upto 60 meters of PRoW will be acquired. Cut-off Date: Cut-off date is established to identify and enumerate the Entitled Persons. For titleholders / legal owners, the cut-off date will be the notification by the PIU declaring the intention to acquire the property. The date of serving the notice u/s 3A of National Highway Act of 1956 will be established as the cut-off date. Encroacher: Any person illegally occupying public property by extending their land boundary or a portion of their building onto the RoW is an encroacher. Entitled Person (EP): Entitled Person includes all PAPs who qualify for, or are entitled to, compensation / assistance since being impacted by the project. The basis for identification of Entitled Persons (EP) in the project will be the cut-off date. Project Affected Household (PAH): Any household living, cultivating land or carrying on business, trade or any other occupation within the Corridor of Impact (CoI) who are impacted by the project is a Project Affected Household. All the members of a PAH in the project will be treated as PAPs. Project Affected Person (PAP): Any individual (part of the PAHs) living, cultivating land or carrying on business, trade or any other occupation within the Corridor of Impact (CoI) who are impacted by the project is a Project Affected Person (PAP). Present Market Rate: Present market rate in the project refers to the valuation of a project-affected property as per the up-dated Circle Rate or BSR Rate respectively for land and structures. Titleholder / Private Property Owners: Private property owners are persons who have legal title to structures, land or other assets. These property owners are entitled to compensation under the National Highway Act of 1956. 11-20 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT Non-titleholder: Squatters and encroachers are non-titleholders, as they do not have any legal title of the parcel of land they occupy. However, some of the non-titleholders are found to pay certain taxes regularly to local self governments for present occupancy for their housing/commercial establishment. The NH Act 1956 for Land Acquisition does not recognize the usufruct right so they are not eligible to any compensation or assistance as per the statues. The R&R Policy for the project also does not specify any assistance for non-titleholders. Encroachment: Private structures, which extend from private land to government land, are classified as encroachment. The portion of the structure in government land is considered illegal occupancy and is not eligible for any compensation for assistance as per the R&R Policy for the project. Squatter: Any person having structures entirely within the public RoW for residential and/or commercial purposes is a squatter. The Entitlement Framework for Project Affected Persons (PAP) in this project has been presented in Table 11-25. PAPs are entitled for various types of rehabilitation and resettlement benefits depending upon the type of loss due to the project. The entitlements as per the National Rehabilitation and Resettlement Policy, 2007 is detailed out in Table 11-25. Table 11-24: Entitlement Matrix for Project Affected Persons S. No A 1 Category/Target Details Group Homestead land / House Building Assistance Each affected family 2 Each affected below poverty line family B Agricultural Land 1 Each displaced family owning agricultural land 2 C 1 D 1 E 1 F 1 G Any affected family owning house and whose house has been acquired or lost Free of cost house site to the extent of actual loss of area of the acquired house but not more than 250 sq.m of land in rural areas / 150 sq.m of land in urban areas for each nuclear family In urban areas, a house of up to 100 sq.m carpet area. Such house may be offered in a multi-storied building complex. Affected families without homestead land and which has been residing in the affected area continuously for a period of 3 years preceding the date of declaration of the affected area and which has been involuntarily displaced from such area A house of minimum 100 sq.m carpet area in rural areas, or 50 sq.m carpet area in urban areas (which may be offered, wherever applicable, in a multi-storied building complex), as the case may be in the resettlement area Affected families owning agricultural land in the affected area and whose entire land has been acquired or lost Agricultural land or cultivable wasteland to the extent of actual land loss, subject to a maximum of 1 ha of irrigated land or 2 ha of un-irrigated land or cultivable wasteland Each affected family who have been reduced to the status of marginal farmers Land Development In case of allotment of wasteland or degraded land in lieu of the acquired land Agricultural Production In case of allotment of Each Khatedar in agricultural land in lieu of the the affected family acquired land Construction of Cattle Shed Each displaced family which is having cattle Shifting Allowance Allowance for shifting of family, Each displaced building materials, belongings family and cattle Construction of Working Shed or Shop Each Khatedar in the affected family Entitlement Agricultural land or cultivable wasteland to the extent of actual land loss, subject to a maximum of 1 ha of irrigated land or 2 ha of un-irrigated land or cultivable wasteland One-time financial assistance of such amount as the appropriate Government may decide but not less than Rs.15000/- per hectare One-time financial assistance of such amount as the appropriate Government may decide but not less than Rs.10000/- Financial assistance of such amount as the appropriate Government may decide but not less than Rs.15000/- One-time financial assistance of such amount as the appropriate Government may decide but not less than Rs.10000/- 11-21 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT S. No 1 H Category/Target Group Each displaced person who is a rural artisan, small trader or selfemployed person Employment Assistance Details Entitlement One-time financial assistance of such amount as the appropriate Government may decide but not less than Rs.25000/- The requiring body shall give preference in providing employment in the project, subject to the availability of vacancies and suitability of the affected person for employment Arrange for training of the affected persons, so as to enable such persons to take on suitable jobs 1 At least one person per affected family 2 Affected persons I 1 J 1 K 1 L 1 M 1 2 3 11.16 Offer scholarships and other skill development opportunities to the eligible persons from the affected families as per the criteria as may be fixed by the appropriate Government Give preference to the affected persons or their groups or cooperatives in the allotment of outsourced contracts, shops or other economic opportunities coming up in or around the project site Give preference to willing landless labourers and unemployed affected persons while engaging labour in the project during the construction phase Necessary training facilities shall be offered for development of entrepreneurship, technical and professional skills for self employment. Rehabilitation Grant Affected families who have not been provided agricultural land or employment Subsistence Allowance Each affected family 750 days minimum agricultural wages Each affected family 25 days minimum agricultural wages per month for a period of one year from date of displacement Annuity Policies Vulnerable affected persons (as per Para 6.4(v) of the Policy) Ex-Gratia Project authorities shall, at their cost, arrange for annuity policies that will pay a pension for life to the vulnerable affected persons In case of linear acquisitions, in projects relating to railway lines, highways, transmission lines, laying of pipelines and other Each Khatedar in such projects wherein only the affected family narrow stretch of land is acquired for the purpose of the project or is utilised for right of way Assistance to Vulnerable Groups Additional one-time financial Each scheduled assistance for loss of customary tribe affected rights or usages of forest family produce Each scheduled tribe affected Those resettled out of the district family Affected families of scheduled tribe Minimum of Rs.500 per month Rs.20000 in addition to the compensation or any other benefits due under the Act or programme or scheme under which the land, house or other property is acquired 500 days minimum agricultural wages 25% higher rehabilitation and resettlement benefits in monetary terms (in respect of items specified in paragraphs 7.9 to 7.12 of the Policy) Land free of cost for community and religious gathering LIVELIHOOD RESTORATION OF VULNERABLE SQUATTERS WITHIN CODI Since the project is to be implemented on a commercial format, there are no inherent funds devoted to restoration of livelihoods of non-title holder occupants within the CoI / public RoW, who would be evicted due to the project. However, the Consultants feel that since there would be substantial losses to livelihoods due to such eviction, it would be worthwhile on the part of the 11-22 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT project authorities to integrate at least the vulnerable squatter and the PAPs in various development / welfare programmes of the State and Central Governments. To this end, the Consultants suggest in the following a range of Government aided programmes undertaken through the District Rural Development Authority (DRDA) in the State of Gujarat in which vulnerable squatter and the PAPs losing livelihoods may be integrated with. Pradhan Mantri Gram Sadak Yojana (PMGSY) Swarnjayanti Gram Swarozgar Yojana (SGSY) Sampoorna Gramin Rozgar Yojana (SGRY) Indira Awas Yojana Credit-cum-Subsidy Scheme for Rural Housing Innovative Stream for Rural Housing and Habitat Development Rural building Centres Samagra Awas Yojana National Social Assistance Programme Council for advancement of People’s Action and Rural Technology Rajiv Gandhi National Drinking Water Mission Centrally sponsored Rural Sanitation Programme Drought Prone Area Programme Wastelands Development 11.17 RELOCATION AND PRESERVATION OF COMMUNITY / CULTURAL PROPERTY The detail of the community/cultural properties has been provided in the Environmental Impact Assessment Report. The construction costs for community/cultural properties have been presented in the Environmental Management Plan of the project. 11.17.1 Implementation Arrangements Implementation of RAP is one of the major tasks that need to be carried out during the project implementation. The PAPs would receive adequate notice, counselling and assistance before handing over their assets. The implementation of RAP begins with land acquisition, payment of compensation, identifying the relocation sites for community /cultural property in consultation with the affected people and assisting them for enrolling them in Governmental welfare programmes. The R&R activities are a part of the RAP. 11.17.2 Institutional Arrangements The NHAI is responsible for implementation of the complete resettlement and rehabilitation of all those affected by the project. For implementation of RAP, the NHAI should focus on four critical aspects. Establish a Project Implementation Unit (PIU) exclusive to this Project. It is suggested that NHAI may designate the State Level H& RW (National Highway Division) to act as PIU for this Project; Appointment of NGOs to assist in implementation of RAP. This is essential to carry out implementation activities of RAP inclusive of issuing and distribution of Photo Identity Cards, counseling, disbursement of compensation money, etc. to the PAPs. Establish a District Level Committee (DLC) in the project District, where acquisition of land for the project will take place; and 11-23 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT Establish a Grievance Redressal Committee (GRC). Project Implementation Unit The PIU will be headed by a Project Director. The NHAI Project Implementation Unit (PIU) will be responsible for implementation of the R & R component of the project. It is responsible for planning of the entire R & R activities, implementing in consultation with the PAPs, considering R&R as a process of development. While land acquisition is the responsibility of the State Government on behalf of the NHAI, (land acquisition is the responsibility of the State/District Administration) the responsibility of the Project Implementation Unit (PIU) is to ensure that the delays between the date of notification and the date of award are reduced to eliminate the hardship caused to the affected people, are minimized. This is possible if the PIU works in coordination with the District Level Committee set up to review the progress of land acquisition. For the implementation of the Resettlement Action Plan and to address the grievances of the PAPs owing to the project, a Manager has to be designated as Resettlement and Rehabilitation Officer (RRO), and shall oversee the implementation of R & R activities. The responsibilities and duties performed / to be performed during the implementation of the project is presented in Table 11-26. 11.17.3 District Level Committee (DLC) RAP implementation will be coordinated through District Level Committee. The District Level Committee (DLC) is an ad hoc committee and will be dissolved later once the R & R implementation is complete. The committee will comprise of the District Collector and officially deputed Land Acquisition Officer (LAO), Tehsildars of affected Tehsils, Pradhans of Block Development Offices of affected Blocks, Project Director, RRO, representative of the NonGovernment Organization (NGO) and representatives of the PAPs. The DLC will play a coordinating role in land acquisition and compensation, assistance and so forth. Table 11-25: Roles and Responsibilities of PIU and NGOs Implementation Staff Project Director at Project Implementation Unit (PIU) Manager as RRO at PIU Non Organization Government Roles and Responsibilities Overall responsibilities for land acquisition and R&R activities in the field. Make budgetary provisions for land acquisition and R&R activities. Liaison with district administration for land acquisition and implementation of R&R. Participate in the district level committee. Co-ordinate with district administration and NGOs responsible for land acquisition and R&R. Print Policy and Identity Cards for the PAPs. Ensure that the land acquisition plans as per the alignments are submitted to the district administration for acquisition. Liaison with the District Administration for dovetailing Government's schemes for income generation and development programs for the PAPs. Co-ordinate with the NGOs appointed for implementation of the R&R. Monitor physical and financial progress on land acquisition and R&R implementation activities including shifting of people. Organize regular meetings with the NGOs to review the progress of R&R. Co-ordinate with the RRO to implement R&R activities. Verification of PAFs listed out in the RAP. Issue Identity Card to the PAFs Facilitate the RRO in organising the public information campaign at the commencement of the R&R activities. Assist the PAPs in receiving the payment of compensation, opening of the Bank accounts and facilitates the vulnerable PAPs in ensuring that they get their dues on time and are not left out to deteriorate to the stages of impoverishment. Ensure that the PAPs receive their entitlements on time. Participate in the meetings organized by the PIU. Submit monthly progress report. 11-24 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT 11.18 IMPLEMENTATION PROCEDURE The RAP is implemented through the following five stages: Issue of legal notification for land acquisition and the cut-off date; Verification of Eligible Persons (EPs) and estimation of their types and category of losses; Preparation of Photo Identity Card, issue and distribution to EPs; Disbursing Compensation Money; Monitoring Physical and Financial Progress of Resettlement Action Plan . 11.19 GENERAL ACTIVITIES In order to carry out the above activities, the NHAI has to carry out institutional strengthening and certain administrative responsibilities in terms of: Contracting of NGOs; Setting up of District Level Committees (DLC) and the Grievance Redressal Cell (GRC); Verification of EPs; Updating of the census data to include the disputed cases or left out cases to be included in the list of PAPs; Distribution of Identity Cards (see at the end of the chapter, a format for ID Card); Opening of joint accounts in the name of the EPs, representatives of the NGOs and RRO; Special emphasis on the vulnerable groups for helping enroll the PAPs from this group in Governmental welfare schemes operating in the region; Monitoring physical and financial progress; and Prepare monthly reports of the progress made. 11.20 SPECIFIC ACTIVITIES 11.20.1 Permanent Land Acquisition: It will be carried out under National Highway Act of 1956. The following steps will have to be carried out for land acquisition: Appointment of the competent authority; Identification of Villages Along the Project Corridor; Preparing land plans for acquisition with details about the total land holdings and the area affected; Issue of notices as per the National Highway Act 1956 for the purpose of acquisition; Announcement of compensation awards as per the NH Act; Issue of cheques in public places prior to taking of possessions: PAPs will be allowed to salvage their materials from the demolished structures. 11.21 PAYMENT OF COMPENSATION Ensure the amount of compensation is appropriate to PAPs; Verification of EPs for compensation; Ensure the receipt of cheques by owner of the affected unit; Ensure that cheques are issued in public during meetings; Inform about acquisition or transfer of land to other authorities whose land is being taken (Forest; Defense etc). 11-25 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT 11.22 GRIEVANCE REDRESSAL MECHANISM The objective of the mechanism is to provide a platform to the affected people to address their grievance that are sought by meaningful solutions. Thus, reflecting continued participation and justification to design, economic returns and the PAPs themselves. The grievances addressed in this manner have community approval and the redressal is appropriated through stakeholders’ participation. The committee thus formed for this purpose will continue to function for the benefit of the PAPs during the entire life of the project so that the PAPs grievances are redressed at the right time. The GRC will have to be formed at every District Head Quarter consisting of the following members. The Project Director; RRO; District Collector; NGO; and Monitoring Implementation of Resettlement Action Plan It is important to consider setting up an early system for monitoring project objectives and social accountability. Monitoring involves tracking the progress of process and implementation (as measured by indicators on inputs, outputs and outcomes) associated with the project. This is done to ensure that the desired targets are achieved. Indicators for monitoring will be designed to capture physical and financial progress of the project. Promote Social Accountability Monitoring and evaluation system can also be implemented to promote social accountability during the process of implementation of the project leading to sustainability. Participatory public review and perception surveys would be used for social accountability in the monitoring and evaluation process. 11.23 THE RAP BUDGET The RAP budget includes the cost of land and compensation for private structures. The details are listed in the Table 11-27. Table 11-26: Preliminary Social Cost Details S. No Details of Affected Structures Area in Sq. M/No/Mts Unit Rate/Sq. M Amount (Rs) 384 1500 576000 1 Residential Kutcha 2 Residential Semi-Pucca 15636 3000 46908000 3 Residential Pucca 12593 4500 56668500 4 Commercial Kutcha 132 1500 198000 5 6 Commercial Semi-Pucca Commercial Pucca 12747 22119 3000 4500 38241000 99535500 7 Mixed Kutcha 4 1500 6000 8 Mixed Semi-Pucca 1360 3000 4080000 9 Mixed Pucca 3771 4500 16969500 10 1 Pucca Ground Floor with Semi-Pucca 1st Floor (Commercial) 439 7500 3292500 11 12 1 Pucca Ground Floor with Pucca 1st Floor (Commercial) Industrial Semi-Pucca 1098 1460 9000 3000 9882000 4380000 11-26 Final Feasibility-cum-Preliminary Design Report VOLUME I: Preparation of Feasibility– cum-Preliminary Design for 4/6 Laning of JetpurSomnath section of NH 8D, Package No: NHAI/DBFOII/DPR/02 MAIN REPORT S. No Area in Sq. M/No/Mts Details of Affected Structures Unit Rate/Sq. M Amount (Rs) 13 Industrial Pucca 3199 4500 14395500 14 Wells 95 Nos. 1,00,000/Well 9500000 15 Temple/Mosque/Church 49 Nos. 30000/Structure 1470000 16 17 Pump House with Tube Well Tap 43 Nos. 38 Nos. 5000/Structure 1000/Tap 215000 38000 18 Water Tank 19 Compound Wall 20 Iron Gate 21 A Proposed Affected Land in Sq. m for Acquisition 148 Nos. 10000/Tank 1480000 25184 Mts 500/ Running Mts 12592000 209 Nos. 2000/Gate 418000 2652818376 2973663876 Total Rehabilitation And Resettlement Assistance 22 Construction of Cattle Shed 67 15000 23 Shifting Allowance 299 10000 2990000 24 Construction of Working Shed 763 25000 19075000 25 26 Subsistence Allowance Annuity Policies 1157 809 24000 6000 27768000 4854000 27 Ex-Gratia 1157 20000 23140000 28 B Assistance to Vulnerable Groups 607 40000 Total TOTAL SOCIAL COST (A+B) 1005000 24280000 103112000 3076775876 The Social Cost (Including Land Acquisition cost, Structure Cost and resettlement and Rehabilitation Cost) has been estimated at Rs. 307, 67, 75, 876 11-27