P4-1 Harold Grey owns a small farm in the Salinas Valley that grows apricots. The apricots are dried on the premises and sold to a number of large supermarket chains. Based on past experience and committed contracts, he estimates that sales over the next five years in thousands of packages will be as follows: Year Forecasted Demand (thousands of packages) 1 300 2 120 3 200 4 110 5 135 Assume that each worker stays on the job for at least one year, and that Grey currently has three workers on the payroll. He estimates that he will have 20,000 packages on hand at the end of the current year. Assume that, on the average, each worker is paid $25,000 per year and is responsible for producing 30,000 packages. Inventory costs have been estimated to be 4 cents per package per year, and shortages are not allowed. Based on the effort of interviewing and training new workers, Farmer Grey estimates that it costs $500 for each worker hired. Severance pay amounts to $1,000 per worker. a. Assuming that shortages are not allowed, determine the minimum constant workforce that he will need over the next five years. b. Evaluate the cost of the plan found in part (a). P4-2 For the data given in P4-1, graph the cumulative net demand. a. Graphically determine a production plan that changes the production rate exactly once during the five years, and evaluate the cost of that plan. b. Graphically determine a production plan that changes the production rate exactly twice during the five years, and evaluate the cost of that plan. P4-3 An implicit assumption made in P4-1 was that dried apricots unsold at the 'L. end of a year could be sold in subsequent years. Suppose that apricots unsold at the end of any year must be discarded. Assume a disposal cost of $0.20 per package. Resolve Problem 9 under these conditions. P4-4 The personal department of the A&M Corporation wants to know how many workers will be needed each month for the next si5-month production period. The following is a monthly demand forecast for the six-month period. MONTH Forecasted Demand June 1,250 August 1,100 September 950 October 900 November 1,000 December 1,150 The inventory on hand at the end of June was 500 units. The company wants to maintain a minimum inventory of 300 units each month and would like to have 400 units on hand at the end of December. Each unit requires 5 employee-hours to produce, there are 20 working days each month, and each employee works an 8-hour day. The workforce at the end of June was 35 workers. a. Determine a minimum inventory production plan (i.e., one that allows arbitrary hiring and firing). b. Determine the production plan that meets demand but does not hire or fire workers during the six-month period. P4-5 A local semiconductor firm, Superchip, is planning its workforce and production levels over the next year. The firm makes a variety of microprocessors and uses sales dollars as its aggregate production measure. Based on orders received and sales forecasts provided by the marketing department, the estimate of dollar sales for the next year by month is as follows: Month Production days Predicted Demand (in $1 0,000) January February March April May June July August September October November December 22 16 21 19 23 20 24 12 19 22 20 16 340 380 220 100 490 625 375 310 175 145 120 165 Inventory holding costs are based on a 25 percent annual interest charge. It is anticipated that there will be 675 workers on the payroll at the end of the current year and inventories will amount to $120,000. The firm would like to have at least $100,000 of inventory at the end of December next year. It is estimated that each worker accounts for an average of $60,000 of production per year (assume that one year consists of 250 working days). The cost of hiring a new worker is $200, and the cost of laying off a worker is $400. a. Determine the minimum constant workforce that will meet the predicted b. Evaluate the cost of the plan determined in part (a). P4-6 For the data in P4-5, determine the cost of the plan that changes the workforce size each period to most closely match the demand. P4-7 Graph the cumulative net demand for the Superchip data of P4-5. Graphically determine a production plan that changes production levels no more than three times, and determine the total cost of that plan. P4-8. Excelsior Springs, Ltd., schedules production of one end product, Hi-Sulphur, in batches of 80 units whenever the projected ending inventory balance in a quarter falls below 10 units. It takes one quarter to make a batch of 80 units. Excelsior currently has 30 units on hand. The sales forecast for the next four quarters is: Quarter Forecast 1 2 3 4 20 70 70 20 a. Prepare a time-phased MPS record showing the sales forecast and MPS for Hi-Sulphur. b. What are the inventory balances at the end of each quarter? c. During the first quarter, no units were sold. The revised forecast for the rest of the year is: Quarter Forecast 2 3 4 30 50 70 How does the MPS change? P4-9. Neptune Manufacturing Company’s production manager wants a master production schedule covering next year’s business. The company produces a complete line of small fishing boats for both saltwater and freshwater use and manufactures most of the component parts used in assembling the products. The firm uses MRP to coordinate production schedules of the component part manufacturing and assembly operations. The production manager has just received the following sales forecast for next year from the marketing division: Sales forecast (standard boats for each series) st Products lines 1 quarter 2nd quarter 3rd quarter 4th quarter FunRay series SunRay series StingRay series 8,000 4,000 9,000 9,000 5,000 10,000 6,000 2,000 6,000 6,000 2,000 7,000 Total 21,000 24,000 14,000 15,000 The sales forecast is stated in terms of ” standard boats,” reflecting total sales volume for each of the firm’s three major product lines.Another item of information supplied by the marketing department is the target ending inventory position for each product line . The marketing department would like the production manager to plan on having the following number of standard boats on hand at the end of each quarter of next year: Product line FunRay series SunRay series StingRay series Quarterly target ending inventory (in standard boats) 3,000 boats 1,000 boats 3,000 boats The inventory position for each product is: Product line FunRay series SunRay series StingRay series Current Inventory level (in standard boats) 3,000 boats 1,000 boats 3,000 boats The master production schedule is to specify the number of boats (in standard units) to be produced for each product line in each quarter of next year on the firm’s single assembly line. The assembly line can produce up to 15,000 standard boats per quarter (250 boats per day during the 60 days in a quarter). Two additional factors are taken into account by the production manager in preparing the master production schedule:the assembly line changeover cost and the inventory carrying cost for the finished goods inventory. Each assembly line changeover costs $5,000, reflecting material handling costs of changing the stocking of component parts on the line, adjusting the layout, and so on. After some discussion with the company comptroller, the production manager concluded that the firm’s inventory carrying cost is 10 percent of standard boat cost per year. The item value for each of the product line standard units is: Product line Standard boats cost FunRay series SunRay series StingRay series $100 150 200 The master production scheduler has calculated the production lot sizes as 5,000, 3,000, and 4,000 units, respectively. a. Develop a master production schedule for next year, by quarter, for each of Neptune’s fishing boat lines. Identify any problems. b. Verify the lot size calculations using the EOQ formula. P4-10. The MPS planner at Murphy Motors uses MPS time-phased records for planning end item production.The planner is currently working on a schedule for the P24, one of Murphy’s top-selling motors.The planner uses a production lot size of 70 and a safety stock of 5 for the P24 motor. Week 1 2 3 4 5 6 7 8 Forecast 30 30 30 40 40 40 45 45 Orders 13 8 4 Available Available to promise MPS On hand = 20 a. Complete the MPS time-phased record for product P24. b. Can Murphy accept the following orders?Update the MPS time-phased record for accepted orders. Order Amount Desired week 1 2 3 4 40 30 30 25 4 6 2 3 P4-11. Nino Spirelli has constructed the following (partial) time-phased MPS record: Week 1 2 3 4 5 6 Forecast 20 30 20 30 20 30 Orders 14 8 6 50 50 Available Available to promise MPS 50 50 On hand = 5 a. Complete the record. b. Are there any problems? c. What's the earliest Nino can promise an order for 44 units? d. Assume that an order for 15 is booked for week 4. Assume the order for 44 units in part c is not booked; recompute the record. P4-12. The Noname Computer Company builds a computer designated model ICU2. It imports the motherboard of the computer from Taiwan, but the company inserts the sockets for the chips and boards in its plant in Lubbock, Texas. Each computer requires a total of 90 64K DRAM (dynamic random access memory) chips. Noname sells the computers with three add-in boards and two disk drives. The company purchases both the DRAM chips and the disk drives from an outside supplier. The product structure diagram for the ICU2 computer is given in Figure 4-1. Suppose that the forecasted demands for the computer for weeks 6 to 11 are 220, 165, 180, 120, 75, and 300. The starting inventory of assembled computers in week 6 will be 75, and the production manager anticipates returns of 30 in week 8 and 10 in week 10. a. Determine the MPS for the computers. b. Determine the planned order release for the motherboards assuming a lot-for-lot scheduling rule. c. Determine the schedule of outside orders for the disk drives. FIGURE 4-1 Product structure diagram for ICU2 computer (for Problem 4-12) P4-13. For the previous problem, suppose that Noname has 23,000 DRAM chips in inventory. It anticipates receiving a lot of 3,000 chips in week 3 from another firm that has gone out of business. At the current time, Noname purchases the chips from two vendors, A and B. A sells the chips for less, but will not fill an order exceeding 10,000 chips per week. a. If Noname has established a policy of inventorying as few chips as possible, what order should it be placing with vendors A and B over the next six weeks? b. Noname has found that not all the DRAM chips purchased function properly. From past experience it estimates an 8 percent failure rate for the chips purchased from vendor A and a 4 percent failure rate for the chips purchased from vendor B. What modification in the order schedule would you recommend to compensate for this problem? P4-14. a. Determine the planned order release for the motherboards in Problem 4 assuming that one uses the EOQ formula to schedule production. Use K = $180 and h = 0.40. b. Using the results from part (a), determine the gross requirements schedule for the DRAM chips, which are ordered from an outside supplier. The order cost is $25.00, and the holding cost is $0.01 per chip per week. What order schedule with the vendor results if the EOQ formula is used to determine the lot size? c. Repeat the calculation of part (b) for the add-in boards. Use the same value of the setup cost and a holding cost of 28 cents per board per week. P4-15. The time-phased net requirements for the base assembly in a table lamp over the next six weeks are Week 1 2 3 4 5 6 Requirements 335 200 140 440 300 200 The setup cost for the construction of the base assembly is $200, and the holding cost is $0.30 per assembly per week. a. What lot sizing do you obtain from the EOQ formula? b. Determine the lot sizes using the Silver-Meal heuristic. c. Determine the lot sizes using the least unit cost heuristic. d. Determine the lot sizes using part period balancing. e. Compare the holding and setup costs obtained over the six periods using the policies found in parts (a) through (d) with the cost of a lot-for-lot policy. P4-16. Consider the example presented in Section 2 of this chapter of scheduling the production of the valve casing assembly. a. Suppose that the production capacity in any week is 100 valve casings. Using the algorithm presented in this section, determine the planned order release for the valve casings. b. What gross requirements schedule for the valves does the lot sizing you obtained in part (a) give? c. Suppose that the production capacity for the valves is 200 valves per week. Is the gross requirements schedule from part (b) feasible? If not, suggest a modification in the planned order release computed in part (a) that would result in a feasible gross requirements schedule for the valves. P4-17. A single inventory item is ordered from an outside supplier. The anticipated demand for this item over the next 12 months is 6, 12, 4, 8, 15, 25, 20, 5, 10, 20, 5, and 12. Current inventory of this item is 4, and ending inventory should be 8. Assume a holding cost of $1 per period and a setup cost of $40. Determine the order policy for this item based on a. Silver-Meal. b. Least unit cost. c. Part Period balancing. d. Which lot-sizing method resulted in the lowest cost for the 12 periods? P4-18. Two end products, EP1 and EP2, are produced in the Raleigh, North Carolina, plant of a large manufacturer of furniture products located in the Southeast. The product structure diagrams for these products appear in Figure 4-2. Suppose that the master production schedules for these two products are Week 18 19 20 21 22 23 24 EP1 120 112 76 22 56 90 210 EP2 62 68 90 77 26 30 54 Assuming lot-for-lot production, determine the planned order releases for components F, G, and H. FIGURE 4-2 Product structure diagrams (for Problem 4-18) P4-19. A component used in a manufacturing facility is ordered from an outside supplier. Because the component is used in a variety of end products, the demand is high. Estimated demand (in thousands) over the next 10 weeks is Week 1 2 3 4 5 6 7 8 9 10 Demand 22 34 32 12 8 44 54 16 76 30 The components cost 65 cents each and the interest rate used to compute the holding cost is 0.5 percent per week. The fixed order cost is estimated to be $200. (Hint: Express h as the holding cost per thousand units.) a. What ordering policy is recommended by the Silver-Meal heuristic? b. What ordering policy is recommended by the part period balancing heuristic? c. What ordering policy is recommended by the least unit cost heuristic? d. Which method resulted in the lowest-cost policy for this problem? P4-20. Cosmo's Camping Supplies sells two camping packages designed for hunters: Nomad and Nimrod. It is a two-stage process that involves picking the appropriate items from inventory and then packing them into a hunting knapsack. Cosmo is making his labor estimates for the next four quarters for the picking and packing operations. The Nomad package requires 1.75 hours of labor and the Nimrod requires 2.45 hours. The Picking work center historically uses 55% of the labor resources and the Packing work center uses 45%. The production Schedule for the next four quarters is given below: Calculate the labor hours required in the picking and packing work centers for the next four quarters. Quarter End product 1 2 3 4 Total Nomad 450 500 300 350 1600 Nimrod 350 400 500 550 1800 P4-21. Bisutti Cams has gathered data on labor-hour and machine-hour requirements for producing its Racing Camshaft models RC1 and RC2: 1994 ProductionRC1(units) 1,400 ProductionRC2(units) 700 Labor-hoursRC1 450 Labor-hoursRC2 75 Machine-hoursRC1 125 Machine-hoursRC2 135 1995 1,500 820 580 90 145 160 1996 1,700 940 620 105 180 165 a. What planning factors should it use for 1997? b. What capacity requirements for labor-hours and machine-hours would you project for 1997 if 50 percent of the labor-hours and machine-hours each were worked in departments 101 and 102? Use the quarterly summaries in the following master schedule to do the projections: Quarter 1997 MPS 1 ProductRC1 400 ProductRC2 250 3 2 700 150 4 3 300 450 5 4 400 300 Total 1,800 1,150 P4-22. Determine the capacity requirements in all work centers at erben Fabricators using the MPS, resource profile , product structure, and lead time information given below for product Z and all of its components. (Assume all usages are one, and that a new setup must be made in each week at each work center.) week MPS of Product Z 1 10 2 20 3 15 4 10 5 15 Z M N O P P4-23. Management at the Green Valley Furniture Company has just approved the following master production schedule for its make-to-stock products: End product A B C Week1 30 0 10* Week2 0 40 0 Week3 0 36 0 Week4 10 0 30 *The remaining 10 units from a batch of 30 started last week. a. The production control manager is concerned about capacity requirements for one of the automatic machines in the firm's wood shop--the #10 molder whose fixed capacity is 40 hours per week. Prepare a rough-cut capacity plan for the #I0 molder using the resource profile data below. What suggestions would you make? Hours per unit of end product produced Product #10molder Operation setback A 0.1 1 week B 1.5 1 week C 0.1 1 week The manager has been using the following to estimate capacity requirements: Product A B C Weekly forecast of final product sales Forecast(unit/week) 10 25 15 Product A B C Manager's estimated capacity requirements per week (#I0 molder) Forecast Resources/unit Capacity requirements 10 0.1hour 1.0 hours/week 25 1.5hour 37.5 hours/week 15 0.1hour 1.5 hours/week 40.0 hours/week Evaluate the rough-cut capacity planning procedure used by the production control manager. P4-24. Bisutti Cams has a specialized programmed machining center that produces racing camshafts for Indianapolis 500 race cars. It takes about one day for the firm's programmed machining center to produce a racing camshaft to exact tolerances. Consequently, the firm used a two-week lead time to produce a "batch" of 10 camshafts. The current MRP record for the camshafts is as follows: Week 1 2 3 4 5 6 Gross requirements 2 8 5 8 6 5s Scheduled receipts 0 10 0 0 0 0 0 2 7 9 3 8 10 10 0 10 0 0 Projected available 2 balance Planned order release Q = 10; LT = 2; SS = 2. a. There was real concern whether the programmed machining center's capacity had been managed correctly, especially since the firm was having difficulty meeting customer delivery date promises. The programmed machining center designers had said the machine was capable of producing two usable camshafts a day while operating. Bisutti's engineers had said it wasn't correct to count on the "theoretical" capacity but to use 75 percent as the expected output (1.5 camshafts per day). On the other hand, only over the past few nionths had the company been able to consistently produce one usable camshaft per day. Which capacity value do you think should be used? Why? b. Given the preceding record, what are the capacity requirements over the next five weeks? (You can assume the open order has been in progress for almost a week and has produced five usable camshafts.) How do they compare to the three possible capacity measures? What advice can you give the firm's management? P4-25. The finishing department of the Ragged Edges Company has just upgraded the finishing machlne. The firm hoped the capac~tyw ould now be 20 units a day. The machine has been tested one full day. Output fell two units short of what was planned, while input was exactly as planned. To evaluate the machine's performance, Ragged Edges used a spreadsheet program to create an inputloutput control report five days later, starting with the deviations and backlog (5 units) from the end of the first day. The firm hoped to maintam a 4-unit backlog. a. What would the inputloutput control report look like if the firm planned inputs of 23, 14, 17, 20, and 22 units for each of the five days, and actually did input 22, 15, 21, 23, and 19 units, while output was 22, 20, 20, 18, and 21 units? What observations do you have? b. Suppose the actual input had been 25 units on the last day. What would the report look like (assuming no other changes)? Would your comments change? What if the department reported backlog (Instead of output) and told you that the actual backlog was zero for each of the past four days? c. What would the input/output control report be if the input had actually been 14, 18, and 20 in the past three days? What observations can you make? Consider the example of Noname computers presented in this section. a. What is the minimum cycle time that is possible? What is the minimum number of stations that would theoretically be required to achieve this cycle time? b. Based on the ranked positional weight technique, how many stations are actually required for the cycle time indicated in part (a)? c. Suppose that the owner of the company that sells Noname computers finds that he is receiving orders for approximately 100 computers per day. How many separate assembly lines are required assuming (i) the best five-station balance, (ii) the best six-station balance (both determined in the text), and (iii) the balance you obtained in part (b)? Discuss the trade-offs involved with each choice.