LIMPOPO COAL COMPANY (PTY) LTD REPLYING SUBMISSION TO THE MINING RIGHT APPEAL PREPARED IN TERMS OF REGULATION 74(7) OF THE MINERALS AND PETROLEUM RESOURCES DEVELOPMENT ACT, 2002 IN RESPECT OF THE APPEALS BROUGHT BY: ENDANGERED WILDLIFE TRUST PEACE PARKS FOUNDATION First Appellant Second Appellant THE ASSOCIATION OF SOUTHERN AFRICAN PROFESSIONAL ARCHAEOLOGISTS Third Appellant THE MAPUNGUBWE ACTION GROUP Fourth Appellant BIRDLIFE SOUTH AFRICA Fifth Appellant BREGJE DAWSON / KNOLL INVESTMENTS Sixth Appellant JM & PD GRAY Seventh Appellant DGR TRUST Eight Appellant MOPANE BUSH LODGE Ninth Appellant PETER FITT / NORTHERN TULI GAME RESERVE Tenth Appellant WILLIAM GILFILLAN MASHATU NATURE RESERVE Eleventh Appellant Twelfth Appellant TOURISM WORKING GROUP, GREATER MAPUNGUBWE TRANSFRONTIER CONSERVATION AREA DJ WESTCOTT / JW TAYLOR TRUST Thirteenth Appellant Fourteenth Appellant Page 2 GA-MACHETE ECONOMIC DEVELOPMENT CORPORATION SOUTHERN CROSS EXPERIENCES (PTY) LTD JOINT VENTURE Fifteenth Appellant THE SOUTH AFRICAN ARCHAEOLOGICAL SOCIETY Sixteenth Appellant JEREMY FITT / NORTHERN TULI GAME RESERVE Seventeenth Appellant WILDERNESS FOUNDATION OF SOUTH AFRICA WORLD WILDLIFE FOUNDATION OF SOUTH AFRICA Eighteenth Appellant Nineteenth Appellant (Collectively referred to as the “Appellants”) REPLYING SUBMISSION I. INTRODUCTION 1. This is the replying submission of Limpopo Coal Company (Pty) Ltd (“Limpopo Coal” or the “Company”) of Coal House, Pine Wood Office Park, 33 Riley Road, Woodmead to the appeals brought by the above named Appellants to the grant a mining right to it for coal in terms of section 22 of Minerals and Petroleum Resources Development Act 28 of 2002 (the “MPRDA”) on 19 March 2010, over Portion 3, 4, 5, 6, 14 and the Remainder of the Farm Overvlakte 125 MS; the Farm Bergen op Zoom 124 MS; the Farm Semple 155 MS; and the Farm Voorspoed 836 MS (the “mining area”). 2. Limpopo Coal was provided the appeal submissions in respect of these appeals on 15 June 2010 by the Department of Mineral Resources (the “DMR”). This was a significant period after they was served on the DMR. While this replying submission was due within 21 days of the date of receipt of the appeal submissions, in an email, dated 23 June 2010, the DMR agreed that the Company’s response could be submitted on 30 July 2010. Page 3 II. PRELIMINARY MATTERS COMMON TO ALL APPEALS 3. It is immediately apparent that the appeals have all been prepared using an identical template, which in certain cases has not been fully completed. 4. As such, there are certain matters common to all the appeals which we deal with at the outset. 5. Most of the issues raised in the Appeals have been raised previously by the Appellants; were responded to by the Company; and were before the decision maker 5.1 Most of the Appellants were participants in the public participation process, undertaken in terms of the MPRDA for the purpose of the mining right application. 5.1.1 The Ga-Machete Economic Development Corporation Southern Cross Experiences (Pty) Ltd Joint Venture; Bregje Dawson/Knoll Investments Ltd; DGR Trust; JM and PD Gray; William Gilfillan; Mopane Bush Lodge; Endangered Wildlife Trust (“EWT”), Association of South African Professional Archaeologists (“ASAPA”), World Wide Fund for Nature South Africa (“WWF”), Birdlife South Africa (“Birdlife”), Peace Parks Foundation (“PPF”) and the South African Archaeological Society were all participants in the Interested and Affected Parties (“I&AP”) process, conducted by the Company for the purpose of preparing the Environmental Impact Assessment (“EIA”) / Environmental Management Programme (“EMP”) during the mining right application. The members of Mapungubwe Action Group (“MAG”) were also participants in this process, as was Northern Tuli Game Reserve from which two Mr Fitt’s have now appealed. These parties furnished detailed comments on the EMP during that process, evident from Annexure “P2” of the EMP, being the Issues and Responses Register (“the Response List”, attached marked “LC1”). 5.1.2 No indication has been given by the Tourism Working Group, Greater Mapungubwe Transfrontier Conservation Area; DJ Westcott/JW Taylor Trust; Wilderness Foundation of Southern Africa (“WFSA”); and Mashatu Nature Reserve why they have chosen now to join an appeal brought by Page 4 participants in the initial I&AP process. They make no effort to distinguish themselves from the majority of the Appellants who were all involved in that process; nor to indicate why there are involved in the Appeal but were not involved in the I&AP process. They have put their appeal submissions on an identical template with the I&AP participants and, as such, have shown themselves to have a common cause with those Appellants. Accordingly, we do not believe there can be any basis to distinguish between the Appellants. 5.2 In accordance with the objects of the relevant legislation, the I&AP process was extensive, rigorous and the views of affected parties were canvassed and given on a number of occasions. Unfortunately, the Appellants appear to have used the opportunity of these appeals simply to restate that which they previously submitted, without considering and referring to the comprehensive and detailed responses contained in the EMP. 5.3 Alternatively, as set out further below, some Appellants while opting out of the I&AP process prior to this point, or choosing to limit their submissions previously, have now introduced new material and allegations for the first time on appeal. This is highly prejudicial to the Company, who has engaged in the statutory process constructively and in good faith. It is also prejudicial to the decisionmaker, who is required to deal with new material for the first time on appeal. 5.4 The I&AP process is set out in detail below. 5.5 I&AP Process July 2008 onwards 5.5.1 A data base of I&APs was compiled. The date base included authorities, landowners and other I&AP that had been registered. It was continually updated as new I&AP were identified throughout the project (see Annexure N1 of the EMP). 5.5.2 A background information document (“BID”) for the project was compiled. The BIDs and a Response Form were distributed via mail, per hand, fax or email to all I&APs from July 2008; and also continuously to all newly Page 5 registered I&APs. The BID provided background to the proposed project; highlighted the legal requirements and EIA process to be followed. A Response Form was attached, inviting I&APs to provide any comments regarding the proposed activities, to identify any further I&APs who should be consulted, and to register on the I&AP data base (see Annexure “N2” of the EMP for a copy of the BID); Friday 22 August – Thursday 28 August 2008 5.5.3 Advertisements for the EIA process appeared in two regional newspapers. Notices were also places on site; at intersections and buildings commonly used by the local community on 15 August 2008 for the duration of the process (full details are provided on pages 4 -5 in Annex-N of the EMP). 31 July 2008 to January 2009 5.5.4 Meetings were held with the Authorities, directly affected landowners, neighbours, land claimants; King Mphephu, the recognised authority of Venda; and other key stakeholders. The main purpose of these meetings was to raise any issues and concerns regarding the project. A background to the EIA process and findings were provided at these meetings. These meetings are set out below. 5.5.4.1 Vhembe District and Musina Local Municipality A meeting was held with these Authorities on 31 July 2008 to present the project; and gather the issues and recommendations on the project, as well as the Social and Labour Plan (“SLP”). (The minutes of the meeting are included as Annexure “N5” of the EMP). 5.5.4.2 5.5.4.2.1 National and Provincial Government A meeting was held with the Authorities on 26 September 2008. (The list of authorities that attended this meeting and the issues that were discussed, as well as the minutes Page 6 of the meeting, are provided in pages 5 – 6 of Annex-N of the EMP and Annexure “N4A” respectively). 5.5.4.2.2 A subsequent meeting was held with the then Department of Environmental Affairs and Tourism (“DEAT”); Limpopo Economic Development, Environment and Tourism (“LEDET”), South African Heritage Resources Agency (“SAHRA)”, South African National Parks (“SANParks”), the Transfrontier Conservation Area (“TFCA”) Coordinator and the PPF on 23 January 2009. (The minutes of the meeting are included as Annexure “N8” of the EMP). 5.5.4.3 5.5.4.3.1 Landowners meeting The landowners of affected farms in an approximately 10km radius of the Vele Colliery (set out in page 7 of Annex-N of the EMP) were consulted on an ongoing basis throughout the project. In particular, they were consulted on 19 September 2008 and 20 November 2008. (The minutes of the meeting are included as Annexure N6 of the EMP). 5.5.4.3.2 Key interviews and focus group discussions were also held all direct neighbours, as well as I&APs in Zimbabwe. 5.5.4.4 5.5.4.4.1 Land Claimants meeting In this period a meeting with the Tshivula Community, who are land claimants of certain properties over the mining area was held on 29 March 2009, once the Land Claims Commissioner had provided the necessary information regarding the claimants. (A copy of the minutes of the meeting is included as Annexure “N7” to the EMP. The minutes of the meeting reflect that it was held on 29August 2009. This is incorrect; the meeting was held on 29 March 2009, as is evident from the attendances register). Page 7 5.5.4.4.2 As indicated in the minutes, the Company undertook to send a formal invitation to the Tshivulu Tribe to attend the Open Day. This invitation was duly sent to the Tshivulu Tribe and several representatives attended the Open Day. 5.5.4.5 Meetings with King Mphephu 5.5.4.5.1 During the course of the public participation process the Company consulted with King Mphephu, the recognised authority of Venda. 5.5.4.5.2 In these meetings between the Company and King Mphephu issues pertaining to land claims and the traditional communities were discussed. 27 November 2008 5.5.5 The DMR accepted the mining right application. 15 December 2008 to 15 January 2009 5.5.6 Comments to the Scoping Report were invited from all registered I&APs. Copies of the documents were made available at the Musina Municipality Offices; Jacana Environmental CC (“Jacana”); and Vhembe District Municipality. 5.5.7 The Scoping Report was also distributed to all registered I&APs through email, delivering and post. 5.5.8 A comment period of 30 days was set from 15 December 2008 to 15 January 2008. Due to the holiday season, the period was extended by an additional 30 days to 16 February 2009. (The comments submitted by I&APs to the Scoping Report are included in the EMP as Annexure “N13”). Page 8 August 2008 – 15 April 2009: Specialist studies 5.5.9 The Company instructed numerous specialists to conduct investigations on the impacts of the mining operations; compile specialist reports and include proposed measures to mitigate any impact. A table is attached as Annexure “LC2”, setting out the specialists’ qualifications and experience in their respective fields. 16 April 2009 5.5.10 A public open day was held at Dongola Ranch. All registered I&APs were invited to the day. Due to the wide scale media attention, more I&APs attended than registered and others were added to the data bases. 5.5.11 Posters and handout documents provided a summary of the findings of specialist reports and mitigation commitments made by the Company. (A copy of the handout is included as Annexure “N11” in the EMP). 5.5.12 The open days allowed for a question and answer session. (Specific details of this session are included as Annexure “N12” in the EMP). 18 May 2009 to 27 July 2010 5.5.13 The registered I&APs were first notified of the availability of the Draft EIA/EMP on 18 May 2010, this was done over a few days due to the size of the I&AP list. The EMP was made available for review at the following locations: 5.5.13.1 Musina Library (hard copy for review on site); 5.5.13.2 Musina Local Municipality (hard copy for review on site); 5.5.13.3 Jacana, 7 Landdros Mare Street, Polokwane (hard copy for review on site, as well as electronic copies of the report); 5.5.13.4 Naledi Development (Pty) Ltd, 142 Blyde Avenue, Sinoville (hard copy for review on site, as well as electronic copies of the Report); Page 9 and 5.5.13.5 download from www.coalofafrica.com/thuli website (from Friday 22 May 2009). 5.5.14 A second notification was done on 1 July 2009, indicating the availability of EMP on the Coal of Africa website. 5.5.15 The draft EIA/EMP included the specialist reports set out below. 5.5.16 I&AP were provided a period of over 60 days to comment of the Draft EIA/EMP on or before 26 July 2009. (26 July fell on a Sunday, so the Company allowed comments to be submitted until Monday 27 July 2009). 3 August 2009 5.5.17 The DMR provided written comments, inclusive of a number of comments from other state departments and I&APs to the Draft EIA/EMP. 20 August 2009 5.5.18 The Company responded in writing to the comments to the EIA/EMP raised by the DMR, the I&APs and the independent reviewer of EWT (being the Response List, attached as Annexure “LC1” hereto). 13 October 2009 5.5.19 Additional comments were received by the Company from the DMR on 13 October 2009. The Company submitted responses to the DMR regarding these comments on 16 October 2009. A copy of the Company’s response is attached as Annexure “LC3”. These issues included: 5.5.19.1 whether Phase 2 Heritage Impact Assessments (“HIA”) had been conducted. The Company confirmed that the EMP and the specialists’ reports were forwarded to SAHRA, with a request to proceed with Phase 2 HIAs. However, SAHRA rejected the request and advised that it would only consider this once the Page 10 mining right had been granted. (The letter from SAHRA is attached to the Company’s response); 5.5.19.2 details on the mitigation measures included in the EMP. The Company referred the DMR to the section of the EMP containing these measures; and repeated the mitigation measures in its response; 5.5.19.3 the total area that would be disturbed. It was confirmed that the area was 8, 663 hectares and the properties included in the application were confirmed; 5.5.19.4 information on any threatened graves. The Company confirmed that two graves had been identified, however they would not be impacted on by the mining or infrastructure development; 5.5.19.5 financial provision. It was conveyed that the guarantee documentation was being prepared and would be delivered once it had been issued; 5.5.19.6 public participation records. The Company confirmed that these records had been included as Annex-N in the EMP. These records were again attached to the Company’s response; 5.5.19.7 rehabilitation plan. Reference was made to the Soil Study and a summary of the rehabilitation plan was included in the Company’s response; 5.5.19.8 distances of the farms from Mapungubwe National Park (“MNP”). These were provided in the Company’s response; and 5.5.19.9 water use licences: the Company provided proof of submission of the integrated water use licence application (“IWULA”). 5.6 Subsequent to this, the Company submitted a final response on 11 November 2010 to the DMR. The covering letter is attached as Annexure “LC4”. This included the comments previously sent to the DMR; proof of submissions of the Page 11 Water Use Licence application and proof of acknowledgement of submission of the Notice of Intent for the bulk diesel facility and mine access road. 5.7 The large majority of the comments raised during the course of the I&AP process have been repeated in these Mining Rights Appeals. For the most part, these relate to alleged deficiencies in the EMP and the environmental impacts of mining. 5.8 In respect of those comments previously made, as is clear from the Response List in Annexure “LC1”, (containing the responses to the I&AP comments), there was no reason why the issues raised by the reviewer needed to be dealt with in the EMP. 5.9 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the Mining Right. 6. 6.1 Irrelevant appeal grounds in respect of the EMP raised As you will be aware, a number of the Appellants in this matter have also Appealed against the decision to approve the EIA/EMP. 1 6.2 A large majority of the Appellants in this matter raise appeal grounds that centre on the EMP and the adequacy of the EMP. For example the following contentions are made, which are responded to in the relevant section: 6.2.1 the mitigation measures in respect of groundwater and surface water impacts are either lacking or inadequate; (See the EWT Appeal Submission, paragraph 9.3.3.1.3 which is answered in paragraphs 22.2 and 23.6 below). 6.2.2 no determination was made with regard to the contribution of the Limpopo River to the primary alluvial aquifer; or from the aquifer to the base flow of the Limpopo River; (See EWT Appeal Submission, paragraph 9.3.3.2.1(iv) which is answered in paragraph 23.3.2 below.) 1 In particular, the following common Appellants have appealed the EMP: the EWT, PPF, WFSA, MAG, WWF, Birdlife SA (“the EMP Appellants”). University of Pretoria is the only Appellant in the EMP Appeal matter that does not appear to have lodged an appeal in respect of the mining right for the Vele Colliery. Page 12 6.2.3 the process of acid mine drainage (“AMD”) has not been quantified; (See EWT Appeal Submission, paragraph 9.3.3.2.2 which is answered in paragraph 23.5 below). 6.2.4 the proposed measures to deal with AMD will lead to further contamination and degradation of the primary aquifer; (See EWT Appeal Submission, paragraph 9.3.3.2.2(iii) which is answered in paragraph 23.5 below). 6.2.5 the proposed mitigation measures for the potential impacts to groundwater do not reflect Best Practice; (See EWT Appeal Submission, paragraph 9.3.3.2.2(vii) which is answered in paragraph 23.8.3 below.) 6.2.6 I&APs in Zimbabwe were not consulted with during the public participation process; (See EWT Appeal Submission, paragraph 9.3.3.2.4(ii) which is answered in paragraph 23.11 below). 6.2.7 the Heritage Impact Assessment (“HIA”) is insufficient and in fact, a full HIA was not undertaken (See ASAPA Appeal Submission, paragraph 9.3.6.1 which is answered in paragraph 26.1.2 to 26.1.16 below). 6.2.8 the discussion in the HIA on the archaeological resources of the ShasheLimpopo confluence area focuses almost exclusively on the Iron Age sequence, making only passing mention of the Stone Age archaeological sequence; and hunter-gatherer and herder art occurring in the region; (See ASAPA Appeal Submission, paragraph 9.3.2.3.1 which is answered in paragraphs 26.7.4 to 26.7.8.3 below.) 6.2.9 there is no evidence that a study has been done on the impact of air pollution and dust on the area; and the impact drawn to the attention of stakeholders, or consideration being given to representatives of the stakeholders in the case of fauna and flora; (See Bregje Dawson Appeal Submission, paragraph 9.3.2 which is answered in paragraph 43.1 below.) 6.2.10 there is no evidence that a study has been done on the impact of disturbance to the water regime in the area; and the impact drawn to the Page 13 attention of stakeholders, or consideration being given to representatives of the stakeholders in the case of fauna and flora; (See Bregje Dawson Appeal Submission, paragraph 9.3.5 which is answered in paragraph 43.4 below.) 6.2.11 there is no evidence that a study has been done on the impact of acidity in the area; and the impact drawn to the attention of stakeholders, or consideration being given to representatives of the stakeholders in the case of fauna and flora; (See Bregje Dawson Appeal Submission, paragraph 9.3.6 which is answered in paragraph 43.5 below.) 6.2.12 there is no evidence that a study has been done on the impact on the land; and the impact drawn to the attention of stakeholders, or consideration being given to representatives of the stakeholders in the case of fauna and flora; (See Bregje Dawson Appeal Submission, paragraph 9.3.7 which is answered in paragraph 43.6 below.) 6.2.13 there is no evidence that a study has been done on noise and vibrations of mining on the area; and the impact drawn to the attention of stakeholders, or consideration being given to representatives of the stakeholders in the case of fauna and flora; (See Bregje Dawson Appeal Submission, paragraph 9.3.8 which is answered in paragraph 43.7 below.) 6.3 These issues are discussed responded to in the individual Appeals lodged. 6.4 The Company instructed several specialists to conduct investigations on the impacts of the mining operations; compile specialist reports and include proposed measures to mitigate any impact. The specialists appointed are set out below. The extent of certain of their investigations is also detailed below, to give examples of the in-depth studies that were undertaken. Furthermore, Annexure “LC2” sets out the specialists’ qualifications and experience in their respective fields. 6.4.1 Description of the Environment: Soil Survey, Land Capability, Land Use and Sensitive Landscapes of the Vele Colliery Project, March 2009 and compiled by BB. McLeroth (the “Soil Study”) (Annex-B to the EMP); Page 14 6.4.1.1 For the purpose of compiling this report, a soil survey was conducted as part of the development of the EMP. To this end, a 150m grid survey and two reconnaissance surveys were conducted, the total area of the study area being 8461, 92 ha. This exercise was conducted in order to quantify the soils, erosion hazard and slope, agricultural potential, land capability, wetland classification, present land use, sensitive landscapes, and give a detailed description of the proposed project. 6.4.1.2 The survey was carried out in three phases from 17 to 31 July, 21 August to 20 September, and 7 to 31 October 2008. 6.4.1.3 Detailed soil, land use and land capability maps were compiled (inclusive of detailed wetland delineation). The information was consolidated in the Soil Utilisation Map, which is indicative of the potential rehabilitation scenarios available for the mine. 6.4.2 Biodiversity Impact Assessment of the Planned Vele Colliery, dated April 2009 and compiled by G.P Nel and E.J Nel of Dubel Integrated Environmental Services (the “Biodiversity Study”) (Annex-C to the EMP); 6.4.2.1 For the purposes of compiling the report, the specialists identified issues that may arise as a result of Vele Colliery, in consultation with the other specialists and I&APs. A desktop baseline study and extensive literature study was undertaken. Broad geological and soil occurrences (land types) and characteristics were identified; and mapping and evaluation of vegetation and habitats on aerial photographs was undertaken. 6.4.2.2 Site visits were undertaken by the specialists from August 2008 to January 2009, to gather and review existing information on geology, soils, fauna and flora that can be expected and do occur in the study area. Potential impacts were identified for each issue and assessed. Where the potential impacts were perceived as having a high risk or significance, alternatives; and preventative and mitigation measures were considered. Page 15 6.4.2.3 Specialist studies and surveys were commissioned to identify: flora species, vegetation communities, fauna and red data species and their potential habitats; evaluate the sensitivity of each plant community and red data species habitat; map vegetation communities and red data species/habitats; and indentify medicinal, invasive and exotic plants that may occur. 6.4.2.4 Other specialist studies conducted as part of the EIA were also consulted and incorporated into this report. 2 6.4.2.5 Additional recent work done within the area was also consulted and incorporated into the report (page 19, Limpopo Valley Herb Project, R van der Walt; and unpublished report, Van Rooyen 2008). 6.4.3 Surface Water Assessment for the Proposed Vele Colliery, dated April 2009 and compiled by WSM Leshika Consulting (Pty) Ltd (“Leshika”) (Annex-D to the EMP) (“the Surface Water Study”): 6.4.3.1 The methodology utilised for the surface water assessment is largely prescribed by legal requirements, as elaborated in best practise guidelines. These requirements are set out on page 4 of the assessment. 6.4.3.2 Based on these requirements, the specialist compiled an estimation of the flood peaks along the affected drainage lines and determined the associated flood widths. She conducted a survey to obtain data at 1 metre contour intervals. With the survey data she modelled the river flow, using specialised software to determine the flood widths. 3 6.4.3.3 By overlapping the proposed Vele Colliery on the site map, the specialist determined the layout and conceptual design of adequate storm water management 2 3 Page 6 of the Biodiversity Study Page 4 of the Surface Water Study Page 16 6.4.4 Environmental Impact Assessment of Groundwater, dated April 2009 and compiled by WSM Leshika Consulting (Pty) Ltd (Annex-E to the EMP) (the “Groundwater Study”); 6.4.4.1 For the purpose of compiling the specialist report, the information was acquired in two phases. During the scoping phase a desk top study and a hydrocensus was undertaken, which evaluated the existing groundwater environment in terms of occurrence, use and quality. The ground proofing phase consisted of drilling, pumping tests, water quality sampling and drill core sampling for acid base accounting. The results of these two phases, in conjunction with the geological information generated by CoAL’s Geological Department, provided input data for the development of a numerical groundwater model, whereby groundwater flow variations with time as a consequence of mining could be quantified. 6.4.4.2 Packer testing was also conducted to determine the in situ permeability of the different hydrogeological models. Water level information was furthermore collected to determine the present status of the piezometric surface; and water samples were collected for macro-chemical analysis to establish the base line water chemistry. Representative samples of diamond drilling core were analysed for sulphide content for use in the AMD impact determination. 4 6.4.5 Air Quality Impact Assessment Report for the Proposed Limpopo Coal Mining Operation; dated 7 May 2009 and compiled by Bohlweki SSI Environmental (Annex-F to the EMP) (“the Air Quality Study”). 6.4.5.1 For the purposes of the compilation of the Air Quality Study, South African ambient air quality standards were used as a base for comparison. Reference was however made to international guidelines to ensure complete compliance. 4 Page 1 of the Groundwater Study Page 17 6.4.5.2 The specialist undertook dispersion modelling within the mining area and its surrounds. The dispersion modelling was conducted using the US – EPA approved Industrial Source Complex Model, version 3. This model is used extensively to assess pollution concentrations and depositions from a wide variety of sources associated with an industrial source complex. 6.4.5.3 The data incorporated into the report when utilizing this model included information on the source and sensitive receptors in the area (such as distances to nature reserves); meteorological parameters (such as wind velocity and direction, ambient temperature, mixing height and atmospheric stability class); and terrain data. 5 6.4.6 Noise Impact Assessment of the Planned Vele Colliery, dated May 2009 and compiled by Jongens Keet Associates (Annex-G to the EMP) (“the Noise Study”), 6.4.6.1 The study area for the Noise Study was that within the area of influence of the Vele Colliery (being longitude 29027’00”E to 29047’00 “E and latitude 2205’00”S to 22018’00”S). 6.4.6.2 For the purposes of the compilation of the report, the specialist compiled with the requirements of Code of Practise SANS 10328: 2003: Methods for Noise Impact. The level of investigation was the equivalent of an EIA. A comprehensive assessment of all noise impact descriptors (standards) was undertaken. The noise impact criteria specifically taken into account were those as specified in the South African National Standard SANS 10103: 2008: The Measurement and Rating of Environmental Noise with respect to Land Use, Health, Annoyance, and Speech Communications, as well as those in the National Noise Control Regulations. 6.4.6.3 5 The investigations comprised of a determination of the existing Pages 5 – 7 of the Air Quality Study Page 18 situation (prior to the development of the mine); an evaluation of the situation during the construction phase and the operational phase; an assessment of the change in noise climate and impacts; and identification of mitigation measures. 6.4.7 Heritage Impact Assessment Report, Proposed Vele Colliery, dated April 2009 and compiled by Frans Roodt from R&R Cultural Resource Consultants (Annex- H to the EMP) (the Heritage Study”); 6.4.7.1 For the purposes of the Heritage Study, various sources were utilised for the baseline information. These included unpublished reports by Archaeological Resource Management of the Archaeological Department of the University of Witwatersrand, the Mapungubwe Cultural Landscape World Heritage Nomination Dossier, academic dissertation, aerial photographs and topocadastral maps. 6.4.7.2 A thorough pedestrian field survey of the mining area was also undertaken by the specialist for detailed site information. 6 6.4.7.3 Additional sites identified and information gathered during the detail soil survey was also incorporated in the assessment. 6.4.7.4 All possible archaeological, cultural and historic remains within the proposed development areas were identified (as far as practicably possible) and a significance rating applied. 6.4.8 Palaeontology Study, dated March 2009 and compiled by Dr. JF Durand (Annex-I to the EMP) (the “Palaeontology Study”); 6.4.8.1 The specialist performed a detailed desktop study, followed by a site visit. 6.4.8.2 The purpose of the desk top study was to detail the probability of finding fossils in the study area and how, if indeed there are 6 Pages 5 – 6 of the Heritage Study Page 19 fossils, the mining activities will impact on the fossils and fossil sites. 6.4.8.3 A surface survey of the rocky outcrops was done on the Farms Overvlakte 125 MS and Newmark 121 MS in Musina District on 79 April 2009. 6.4.9 Visual Impact Assessment for the Proposed Vele Colliery, dated 14 April 2009 and compiled by MetroGIS (Pty) Ltd (Annex-J to the EMP) (“the Visual Study”). For the purposes of the compilation of the report, the specialist conducted several site visits to the mining area. The report was also based on various sources of information, such as the Scoping Report, comments from registered I&APs, the outcomes of project meetings and discussions; GIS data; maps and photographs. 7 6.4.10 Impact Evaluation of Blasting for the Vele Colliery Project dated March 2009 and compiled by A J Rourke (Annex-K to the EMP) (“the Blasting Study”). 6.4.10.1 For the purpose of the Blasting Study, the specialist considered other specialists’ reports on the geology, groundwater and predominant winds in the area surrounding the Vele Colliery. He also conducted a site visit to the mining area and surrounding vicinity. 6.4.10.2 The impact assessment was based on international standards on limits for vibration, air blast and fly rock, as outlined in Appendices 1 and 2 of the Blasting Study. 8 6.4.11 Socio-Economic Impact Assessment of the Vele Colliery, dated May 2009 and compiled by Naledi Development (Annex-L to the EMP) (the “SEA Study”). 7 8 Page ii of the Visual Study Page 4 of the Blasting Study Page 20 6.4.11.1 For the purpose of this SEA, the following processes were investigated: demographic; economic; geographic; institutional and legal; emancipatory and empowerment; socio-cultural; and biophysical. 6.4.11.2 The Social Baseline Study made use of existing data, as a starting point. Further, the information in this report was acquired via interviews with key stakeholders; participant observation; published reports (including Integrated Development Plans, Local Economic Development Strategy, Spatial Development Framework); statistical data obtained from Statistics South Africa; and information obtained from social impact assessment literature (set out in section 9 of the SEA Study). 6.4.11.3 Results from the public participation process also informed the study. This enabled local information to be obtained from community members. 6.4.12 Macro Impact Assessment, dated 29 April 2009 and compiled by Naledi Conningarth Economists (the “MEA Study”) (Annex M to the EMP). 6.4.12.1 A Social Accounting Matrix (“SAM”) for South Africa was used as the basis for the general economic equilibrium analysis of the impacts of construction and operation of the coal mining project. In addition, SAM for the Limpopo Province was used to determine the magnitude of the regional impacts that may be experienced by the province as a result of construction and operation of the Vele Colliery. 6.4.12.2 In order to obtain the highest measure of accuracy and realism possible, suitable disaggregation was performed on the SAM to ensure that all sectors that are impacted in a significant manner by the project were taken into account. 6.4.12.3 The analysis took into account the direct, indirect, as well as the induced effects of the opencast and underground mining project. The economic and socio-economic impacts were calculated for both the construction phase of the project, as well as the Page 21 operational phase. 6.4.12.4 In addition, the nature and magnitude of the impact of government revenue generated from the Vele Colliery. was measured. 6.5 The decision to approve the EMP should not be confused with the decision to approve the mining right. 6.6 It is not competent in this appeal to raise an appeal ground that is related to the alleged inadequacy of the EMP. The inadequacy of the EMP on its own is not a valid basis for challenging the mining right. 7. Irrelevant grounds of appeal that are unrelated to section 23(1)(d) of the MPRDA are raised 7.1 In raising the alleged impacts of the Vele Colliery, the Appellants standard form Appeal template relies on section 23(1)(d) of the MPRDA, with each of the Appellants setting out grounds why they believe that the Vele Colliery will result in “unacceptable pollution, ecological degradation or damage to the environment”. 7.2 In the template this is the lead-in to all of the individual comments made by each Appellant. Many of the comments however made by the Appellants do not fall within the scope of this section. Rather, the Appellants have simply used the pretext of an appeal under section 23(1)(d) to restate all of their objections to the granting of the mining right, as well as to introduce a number of new objections. This is an improper use of the appeal process. It has resulted in substantial duplication and repetition in the appeals that have been lodged against the granting of the mining right and the appeals against the approval of the EMP. 7.3 In any event, the appeals fail to engage with the facts and responses that have been forthcoming in the I&AP process prior to the appeal stage. For the most part, the issues raised by the individual Appellants in this standard form part of the template are premised on the following errors, omissions and misunderstandings: 7.3.1 they fail to properly take into account the existing land uses within the area. Most conspicuously, they completely discount the existing intensive Page 22 agriculture taking place in the immediate vicinity of the Vele Colliery and existing mining activities in the area; 7.3.2 they fail to take account of other relevant facts, such as for example, the actual area of the TFCA as presently proposed; and the actual distance of mining operations to MNP, discussed in paragraphs 19.1 and 19.2 below. 7.4 No evidence of pollution for which a mitigation plan has not been made is alleged; no evidence of ecological degradation that does not follow automatically from a mining approval is shown; and no unacceptable damage to the environment is contended. This is discussed in the response to each appeal. 7.5 The following highlights the issues raised which have nothing whatsoever to do with evidence of unacceptable pollution, ecological degradation or damage to the environment, which have been stated to be relevant to this appeal ground: 7.5.1 potential loss of World Heritage Status due to mining adjacent to Mapungubwe National Park (“MNP”) (See MAG Appeal Submission, paragraph 8.3.4(a) – (e), page 8 - 9 which is answered in paragraph 19.4 below); 7.5.2 impact of mining activities on land use wishes of the MAG members (See MAG Appeal Submission, paragraph 8.3.5, page 9 -10, which is answered in paragraph 19.5 below); 7.5.3 failure to compare Vele Colliery’s limited economic benefit with economic losses due to the impacts on food production and eco-tourism ( See EWT Appeal Submission, paragraph 9.3.3.2.4(i), page 13 which is answered in paragraph 23.10 below.); 7.5.4 I&APs in Zimbabwe were not consulted with during the public participation process (See EWT Appeal Submission, paragraph 9.3.3.2.4(ii) which is answered in paragraph 23.11 below) 7.5.5 failure to take into account the impact of mining activities on the Transfrontier Conservation Area (the “TFCA”) (See PPF Appeal Submission, paragraph 9.3.1, page 6-7 which is answered in paragraph Page 23 29.1 below.) and 7.5.6 failure to consider international agreements. (See Jeremy Fitt/Northern Tuli Game Reserve, paragraph 9.3.5, page 6 – 8 which is answered in paragraph 67.4 below.) 8. 8.1 New opposition grounds on appeal As set out above, the extensive statutory I&AP process followed allowed all parties more than sufficient opportunity to make their comments; or to request additional time should this have been needed. In general, during the 60 day period to comment on the Draft EIA / EMP none of the I&AP respondents expressed the view that they had further comments which they wished to make. 8.2 In addition, the South African Institute for Environmental Assessment (“SAIEA”) was commissioned by a number of I&APs, who are also Appellants, to undertake an extensive EMP review. SAIEA also had 60 days to undertake the review. This document is attached to the EWT’s Appeal. At no time did the reviewer indicate that she had insufficient time or opportunity to conduct investigations which may have been deemed necessary to review the EMP. In presenting the SAIEA review, the reviewer does not indicate that she was placed under time pressure or that the review should be considered as a preliminary review. 8.3 Notwithstanding this, the Appellants now for the first time on appeal seek to introduce new material and comments, which were not proffered at the appropriate stage when the I&AP process was underway. The Appellants appear to believe that they should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. They have treated this appeal process effectively as an opportunity to initiate objections for the first time. This undermines the statutory process and is prejudicial both to the Company, which participated in good faith and diligently in the I&AP process in formulating the EMP, as well as to the decision-makers concerned. 8.4 At no time have any of the Appellants given an indication of what actions of the Company prevented them from timeously submitting their reviews in the I&AP process they participated in. They also give no indication of why the comments Page 24 they present now for the first time on appeal were unavailable to them at the time they provided their comments and review of the EMP and participated in the I&AP process conducted. Those Appellants who failed to participate in the process to this point but have now lodged appeals proffer no explanation as to why they did not initially participate, particularly given the fact that this process was well and properly advertised. 8.5 There has been nothing in the Company’s conduct in the course of compiling the EMP or in the I&AP process to explain the failure by these Appellants to participate previously or to introduce comments and criticism prior to the appeal stage, nor is any allegation to that effect. It is common cause that the Company has engaged constructively and properly in the I&AP process. Accordingly, we submit, there is no reason why the Appellants should be afforded an opportunity to introduce new material and criticisms for the first time on appeal. 8.6 It patently unfair to the Company, as well as the decision-makers, for the Appellants to raise, post the mining right being granted, further criticisms of mining in general and the EMP, that they had every opportunity to comment on before the decision to approve was taken. 8.7 Given the opportunities that the majority of the Appellants had and took advantage of prior to the approval of the mining right, the Company submits that the further reasons for appeal set out in these Appeals cannot provide a basis for arguing that the decision to approve the mining right was wrongly taken. 9. 9.1 Contradictions between the EMP Appeal and the Mining Rights Appeal It is also the case that certain criticisms of the EMP made in the SAIEA review have been contradicted by what is stated by the EMP Appeal brought by the EMP Appellants. For example: 9.1.1 The SEA Study: a section of the EMP Appeal is dedicated to a detailed (unjustified) criticism of the SEA Study. In the SAIEA Review this report and the accompanying MEA Study were praised. (See comment 5.4 where it is stated that the SEA Study is “good”. In comment 5.6 the MEA Study was also stated to be “comprehensive”). Page 25 9.1.2 Palaeontology: Ten pages of criticisms of the Palaeontological Study are included in the EMP appeal. In the SAIEA review this was stated to be adequate. (5.3.10). 9.1.3 Biodiversity: In the SAIEA Review it was stated that the Biodiversity Study was good, as it looked beyond lists of flora species and addressed ecosystem functioning (see comment 5.3.10 in Annexure “LC1”). However in paragraph 19.3 of the EMP Appeal the Appellants criticise the Biodiversity Study, stating that the list is not a comprehensive list of flora species in the study area and does not constitute adequate baseline information on which to investigate, assess and evaluate impacts on flora species. 9.1.4 Air Quality: In paragraph 35 of the EMP Appeal the Appellants contend that no substantive reasoning or explanation is given in the EMP as to why no significant adverse impact is anticipated on sensitive receptors. In the SAIEA Review it was found that the description of impacts is adequate. (See comment 5.3.8 in Annexure “LC1”) 9.2 It is extremely difficult for the Company to understand and respond to this type of contradictory criticism which appears to be founded in ideological opposition, rather than reasoned analysis. By way of further example, many of the appeals are internally or mutually contradictory. This is highlighted in more detail below, For example, the EWT appeal criticises the award of the mining right on grounds that it will compromise existing agricultural and farming activities generally in the area. A number of the other appeals (such as that of the PPF) are founded on the proposition that the mining area is hoped to be included in a future transfrontier park. 10. 10.1 Amplification of the grounds of appeal (paragraph 3 of the appeal template) All of the appeals state that the Appellant reserves its rights to amplify the grounds of appeal when it has been provided with certain documents. 10.2 This is not a competent request in terms of the Mineral and Petroleum Resources Page 26 Development Regulations (the “MPRDA Regulations”). 9 10.3 The request for written reasons pursuant to section 6(6) of the MPRDA is a misunderstanding of the intent of this section. In the course of the appeal the Appellants are in any event provided with the record of decision. 10.4 Limpopo Coal reserves the right to respond to any amplified submission once received. 10.5 In addition, if the DMR is minded to allow this request, then we ask that this replying submission not be provided to the Appellants until after they have received the documentation requested; have provided any amplified submission and the Company has been afforded the opportunity to submit a consolidated replying submission to both the initial and amplified appeal submissions. 11. Request that the Minister exercise their power to suspend the grant of the mining right (Paragraph 6) 11.1 All of the Appellants make the same request in this paragraph of their appeal, namely that because of the “serious nature of the appeal which goes to the heart of the decision to grant the mining right” the Minister is requested to suspend the grant of the right. 11.2 It is our contention that the appeals made do not stand any prospects of success. We deal with the substance of each individual appeal below and, as is set out in those sections, the bases upon which the appeals brought should be rejected. 11.3 Limpopo Coal has already mobilised to site and any action at this stage to stop this mobilisation process would cause significant financial and other hardship to Limpopo Coal. In such circumstances, there is no basis to prejudice the valid, lawful and existing rights of Limpopo Coal by suspending the mining right. To do so would unduly disadvantage Limpopo Coal. 11.4 Furthermore, in the course of the next six months the activities to be undertaken on site are to be undertaken within a limited area, in the eastern most area of the mining area. Most of the comments focus on the effect of mining close to MNP, 9 Published under Government Notice R527 in Government Gazette 26275 of 23 April 2004 Page 27 which is approximately 15 to 20km from the existing activities. 11.5 Limpopo Coal has mobilised to site 11.5.1 Limpopo Coal applied for a mining right for coal on 4 November 2008. 11.5.2 At the time of submitting the application for a mining right, Limpopo Coal anticipated that the right would be granted by October/November 2009 and began putting in place the contracts necessary to start mining on this date. (See as an example the Memorandum of Understanding (“MOU”) with MCC Contracts (Pty) Ltd (“MCC”), dated 21 September 2009 and attached as Annexure “LC5”, whereby Limpopo Coal contracted the opencast mining works at Vele Colliery to MCC. In this MOU the parties anticipated that mining would commence in October 2009). 11.5.3 Mobilising the resources necessary to start an operation of this nature is a huge undertaking, which inter alia requires personnel to be found and committed to the project; equipment to be mobilized; and a Wash Plant to be designed and readied for erection. Planning of these activities started once the application was made, so that the mining operations could commence as soon as possible after the mining right was granted. This was necessary to ensure the costs which Limpopo Coal and its parent company, Coal of Africa Ltd (“CoAL”) have incurred in getting the project up and running could start to be recouped as quickly as possible. 11.5.4 A number of activities and contractors have been mobilized to and around the mining area. These include, amongst others, a contractor to undertake the physical activities related to mining coal (which is MCC); ELB Engineering (Pty) Ltd (“ELB”) to undertake the erection and commissioning of the Wash Plant and related facilities; contractors to build roads in the mining area; contractors to ensure accommodation needs for the various short and long term employees; and contractors to transport workers to and from the mining area. 11.5.5 The Mining Contractor, Wash Plant Contractor and other services contractors have mobilised to site and have 201 and 656 personnel on site respectively. Page 28 Mining Contractor 11.5.5.1 MCC is contracted to carry out the opencast mining works at Vele Colliery. MCC will construct and establish the works for the opencast mining operations. Once the necessary works are in place, MCC will thereafter conduct the opencast mining operations to extract the agreed tonnage of coal specified in the Programme of Works. 11.5.5.2 As stated above, the mining operations are scheduled to focus on the East Pit for the next fifteen years. 11.5.5.3 The mining which will take place within the first year is indicated in the grey wedge segment on a map, attached as Annexure “LC6”. Mining will start at the most northerly point for the 12 months (shown in light green) and move southwards for the first 12 months. 11.5.5.4 The mining activities are anticipated to disturb 87.5 hectares in the first twelve months, as follows: 11.5.5.4.1 Opencast Pit: 11.5.5.4.2 Haul Road: 13.4 hectares; 11.5.5.4.3 MCC Area: 11.8 hectares; 11.5.5.4.4 Plant Area: 16.9 hectares; 11.5.5.4.5 New road: 11.5.5.4.6 TOTAL AREA: 11.5.5.5 39 hectares; 6.4 hectares 87.2 hectares Site establishment and mobilisation has been undertaken. This involved obtaining the specialized equipment and people necessary to start mining activities onto site and installed in place. In total, MCC will have 201 personnel on site. 11.5.5.6 MCC is in the process of establishing the box-cut required to start mining. 880,000 Bank Cubic Metres has been removed from the box-cut as at end of June 2010. It is anticipated that MCC will Page 29 commence extracting coal in early August 2010 Wash Plant contractor 11.5.5.7 ELB was contracted for the design, fabrication, installation and commissioning of the initial Wash Plant, that will be utilized in the mining area. ELB is responsible for the complete execution of the works associated with design, construction and commissioning of the Wash Plant. 11.5.5.8 As stated above, ELB was mobilized to the site after the approval of the EMP. The earthworks and civil works required for the Wash Plant Works were finalised between April to June 2010, as well as the electrical hardware. The Wash Plant will be commissioned in mid August 2010. 11.5.5.9 384 employees were mobilized to site to construct the Wash Plant. 11.5.5.10 Once the Wash plant is commissioned, it will be operated by a team from Minopex (Pty) Ltd (“Minopex”), who has been contracted by the Company. The team will consist of 52 employees (it currently consists of 14 of Minopex’s employees and will increase to 28 subsequent to commissioning of the Wash Plant). 11.5.5.11 LCC’s other contractors include, amongst others, contractors to: build a bypass road in Musina and access road in the mining right area; build and operate staff housing; transport workers to and from the mining area; infrastructure contractors; security; accommodation, and related services. There are approximately 272 people currently performing these services. The access road is presently being constructed in the mining area, as well as haul roads within the East Pit. 11.5.5.12 In total there are presently approximately 857 people mobilised to site or to activities associated with the Vele Colliery: Page 30 11.6 Losses to Limpopo Coal or CoAL if the Minister suspends the mining right 11.6.1 To date the costs incurred are in the region of R853 million. 11.6.2 It has been approximately four to five months from the commencement of mining activities before Limpopo Coal is able to generate revenue from its mining operations. During this time Limpopo Coal has incurred a significant amount of capital and operational expenditure. 11.6.3 The funding for this project has been acquired through a combination of equity funding raised through rights issues by CoAL and loan funding, mostly in the form of shareholder loans from CoAL to Limpopo Coal. Interest on these loans is charged at prime plus 2. Any delay in recouping these costs will impact on the share price of CoAL and reduce its potential to raise the capital required for the ongoing funding of the capital expenses related to the Company’s operations. 11.6.4 Limpopo Coal received notice of the grant of the mining right on 2 February 2010. A copy of the letter of grant is attached as Annexure “LC7”. The grant letter indicated that the right would be executed on 24 February 2010. On the grounds of the information contained in the letter of grant, Limpopo Coal and its contractors based their planning schedules and commencement agreements on 24 February 2010 as a starting date. As such, Limpopo Coal became liable to standing time from February 2010. 11.6.5 If the Minister suspends the operation of the Mining Right, pending the determination of the appeal brought by the Appellants in terms of the MPRDA it is likely to stop activities on the mining area for six to twelve months. A delay of this magnitude in exercising its mining right would cause Limpopo Coal and CoAL to suffer potentially devastating losses, these are summarised approximately as follows: 11.6.5.1 MCC contract: Up to R76,6 million 11.6.5.2 Minopex contract Up to R3,7 million Page 31 11.6.5.3 ELB contract: (up to the full EPCM price of R240 million) 11.6.5.4 Raubex contract: (up to the full value of the contract R22.6 million) Plus standing time 11.6.5.5 Transmus contract: (up to the full value of the contract R4.8 million) Plus standing time 11.6.5.6 Envilox contract: (up to the full value of the contract R3 million) Plus standing time 11.6.5.7 Loss in revenue: for 12 months or R46 million for the initial ramp up and steady state production for 3 months R 850 million (12 months steady state) TOTAL: APPROXIMATELY 280.87 million for a 6 month period taking the operation into steady state 11.6.5.8 Reduction in Net present value: Approximately R100 million 11.6.5.9 Leading to a reduction in share price which would impact on the shareholders: Possibly 4.56% reduction in value: (74 percent decrease in the share price or R354, 965,792 reduction in market capitalization) 12. 12.1 Date of knowledge of the grant of the mining right It is disputed that those Appellants who are represented by the Centre for Applied Legal Studies (“CALS”), or who have been obtaining information, from them were first aware of the grant of the mining right on 9 March 2010. 12.2 Despite knowing through the media from 2 February 2010 that the mining right Page 32 had been granted, CALS representing certain of the Appellants wrote, only on Friday 26 February 2010, to Limpopo Coal requesting confirmation of the grant of the right. This confirmation was given to CALS on 5 March 2010. 12.3 The Appellants cannot simply choose to rely on a later date for “fixing” their knowledge of the grant of the right. They knew the right was granted on 2 February 2010. They waited a month to request confirmation of this from Limpopo Coal and received this confirmation in the course of the following week. 13. 13.1 Delay should impact on the relief granted to the Appellants The Appellants assert that they are entitled to the maximum time allowed in the MPRDA for lodging their appeal and should be entitled to condonation beyond this. The Company contends that in the circumstance the Appellants’ failure to pursue this matter urgently impacts in the relief to which they are entitled. 13.2 The Appellants seek, through this appeal, to set aside the decision to approve the mining right for the Vele Colliery. Immediately following the approval of the mining right and EMP, the Company commenced mining preparation on the Vele Colliery site. 13.3 The Appellants threatened repeatedly to pursue an interdict to stop the Company’s operations on the site. In addition, while they requested the Minister to suspend the approval of the EMP pending this appeal and threatened to take further legal steps if this was not suspended they have taken no steps to pursue this suspension. 13.4 On 24 February 2010 the Centre for Applied Legal Studies acting on behalf of the Appellants wrote to the Company. In the letter the Appellants recorded that should the mining right have been granted and the EMP approved, they intended instituting judicial review proceedings or pursuing other statutory remedies regarding these decisions on various grounds inter alia that there were fundamental flaws in the EMP. The Company was requested to provide an undertaking that it would not commence with activities under its mining right. (Letter attached marked “LC8”). 13.5 On 1 March 2010, Bowman Gilfillan Attorneys, acting on behalf of the Company, Page 33 acknowledged receipt of this letter and on 5 March 2010, having taken instructions from the Company, responded to CALS letter. In this response it was explicitly stated that the Company is not in a position to give the undertaking the Appellants required from it. The reasons for this was that the Company had incurred costs of approximately R570 million to date in its preparation, planning and design for the Vele Colliery (including project acquisition costs, exploration costs, capital expenditure, surface rights acquisition and operating costs). It was conveyed in the letter that as soon as the mining right was granted, CoAL began mobilising to begin operations at the Vele Colliery; the process is continuing; and CoAL expected to start operations in the course of April 2010. The letter emphasised that it was necessary for CoAL to commence operations as soon as possible to satisfy investor expectation and honour the contractual obligations it has made. (Letter attached marked “LC9”). 13.6 In this letter it was recorded that the EMP was compiled and the required application processes were undertaken in accordance with all relevant laws and, in particular, the MPRDA. It was however stated that the Company remains willing to discuss all reasonable measures which the Appellants would like to suggest, in addition to those described in the EMP, to mitigate any impact which the Vele Colliery may have on the environment and surrounding communities. It was suggested that the parties meet to constructively discuss such measures. CALS was invited to contact Bowman Gilfillan Attorneys to make arrangements for the proposed discussions. 13.7 No response was received from CALS regarding the proposed meeting. 13.8 Almost a week later, on 11 March 2010, CALS replied to this letter. It noted that the mining right had been granted to the Company and that the DMR had advised that the EMP had not yet been approved. The letter recorded that, as the EMP had not yet been approved the Company’s mining right was not yet effective and mining operations that commenced prior to the approval of the EMP were illegal. An undertaking was required that the Company would not commence mining operations prior to the approval of the EMP. Various documents were also requested from the Company, including a copy of the final EMP, the Mining Work Programme (“MWP”), and a written record of the decision to grant the mining right. A response was required by 15 March 2010. (Letter attached marked “LC10”). Page 34 13.9 On 16 March 2010 Bowman Gilfillan responded to this letter. The letter stated that the Appellants’ concerns that the Company would commence operations before its EMP was approved were unfounded. It was reiterated that the Company intended commencing mining operations within the course of April, being the time period for which it anticipated approval of the EMP. 13.10 In this letter the Company again offered to discuss all reasonable measures which the Appellants would like to suggest, in addition to those in the EMP, to mitigate any impact which the Vele Colliery would have on the environment and communities. The Company confirmed that it was happy to provide the Appellants with a copy of the EMP, which deals with the manner in which all mining activities covered in the MWP will impact on the environment and the mitigation of such impacts. 13.11 It was again proposed that CALS contact Bowman Gilfillan to arrange a meeting and that the final EMP be provided to the Appellants at the first meeting. (Letter attached marked “LC11”). 13.12 On 24 March 2010, CALS addressed a further letter to Bowman Gilfillan. It noted that the Appellants had formally requested the Minister or Director General of Mineral Resources, in terms of section 96(2) of the MPRDA, to suspend the mining right, pending the outcome of an administrative appeal(s) which had been submitted by the Appellants. 13.13 As the appeals had been submitted, it was stated in the letter that the Appellants were of the view that it would “not be appropriate” for them to meet with the Company. 13.14 The letter noted that the Appellants were aware that the EMP had been approved. Again it was required that the Company provide an urgent undertaking that it would not commence with “any action on the land” in execution of the mining right, pending the outcome of the appeal(s). 13.15 It was stated that should the Company refuse to provide such an undertaking by 25 March 2010, the Appellants would have no alternative but to proceed with an urgent interdict, prohibiting the Company from acting on its mining right until such Page 35 time as the appeals against the grant of the mining right and the approval of the EMP, and any judicial review that may arise out of such appeal process, have been made. (Letter attached marked “LC12”). 13.16 Bowman Gilfillan responded on the same date. In the letter it was noted that the Appellants’ request for an undertaking was based on one or more appeal that they had apparently made to the DMR. It was therefore requested that CALS provide a copy of each of the appeals made by the Appellants, to enable it to take instructions from the Company on the Appellants’ latest request for an undertaking. 13.17 Despite the alleged urgency of the Appellants’ request for an undertaking, no response was received to the letter. Bowman Gilfillan therefore sent a further letter on the morning of 26 March 2010 (attached as “LC13”), referring to the letter of 24 March 2010 and requesting acknowledgement of receipt of this letter. Copies of the Appellants’ appeal(s) were also again requested and arrangements for the service of the urgent papers that had been threatened were included in the letter. 13.18 A further undertaking request was requested by the Appellants in a letter from CALS on 20 May 2010, on the basis that the Company was allegedly undertaking unlawful activities. The Appellants demanded various undertakings from the Company, failing which the Appellants would proceed the appropriate action, including approaching a court for the appropriate relief. (A copy of this letter is attached, marked “LC14”). 13.19 It is apparent from the above exchanges that the Appellants have been aware since 2 February 2010 that the Company had been granted a mining right, almost three months before lodging the appeal. 13.20 Since lodging the appeal, they have taken no steps to pursue the suspension of the EMP or mining right, despite threatening this. In the interim, the Company has, as it is required by the MPRDA, commenced with its mining preparation work. At the time of filing this Appeal Response the Company has been on site for four months since 19 March 2010 when the EMP was approved. 13.21 In the circumstances, setting aside the mining right will have a detrimental impact Page 36 on the Company and also potentially on the environment. Operations on site are presently being conducted in accordance with the EMP; environmental monitoring, protection and rehabilitation is undertaken pursuant to this EMP. 13.22 As set out above, a number of activities and contractors have been mobilized to and around the mining area. Implementation of the Social and Labour Plan (“SLP”) has started. Approximately 850 people are presently employed on site. 13.23 There is no basis to prejudice the Company, which on all accounts has properly and responsibly followed the necessary authorisation processes, for inaction on the part of the Appellants. 13.24 The Company has sought throughout this process to engage in a constructive manner with those, including the Appellants, who oppose the granting of this mining right. It still contends that such constructive engagement is the only way that the issues raised by the Appellants will be resolved. 14. Paragraph 8.1.1 of the appeal template – consultation with I&APs An extensive consultative process, as set out in paragraph 5.3 above, was undertaken with I&APs. 15. 15.1 Paragraph 8.1.2 of the appeal template – the EMP had not been finalised As is apparent from the above, an extensive process of engagement with the DMR was followed in respect of the EMP. This process culminated in November 2009. 15.2 As such, the EMP was finalized by the time the mining right was granted on 2 February 2010. 15.3 As is common practice within the DMR, the EMP was formally approved on 19 March 2010, the same day as the mining right was executed with the DMR. 16. 16.1 Paragraph 8.1.3 – significant objections had been raised which had not been addressed This comment contradicts the one made in 8.1.1 of the appeal template. On the Page 37 one hand it is contended I&APs were not consulted, on the other that I&AP comments are alleged not to have been taken into account. 16.2 In respect of those comments previously made, as is clear from the Response List in Annexure “LC1”, there was no reason why the issues raised by I&APs needed to be dealt with in the EMP. But in any event, the decision maker had all of these detailed comments and the Company’s response to all the comments at the time the decision to approve the EMP was made. 16.3 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the mining right approval. 17. 17.1 Other general comments The Appellants conspicuously in their comments and appeals entirely omit the fact that there is existing mining activity closer to the National Park than the Vele Colliery and that the area is under extensive, and in may cases environmentally destructive, agricultural practices. 17.2 These are truly inexplicable omissions. Moreover, there is extensive criticism leveled against the Company for failure to consult communities on the other side of the international border in Botswana and Zimbabwe. Apart from the fact that this criticism (which is dealt with substantively below) is factually incorrect, the claim that the mine will interfere with aspirational cross-border conservation initiatives is undermined by the existence on a colliery on the Zimbabwe side, directly opposite the Vele Colliery. These issues are address in the appropriate places in detail below. III. THE MAPUNGUBWE ACTION GROUP APPEAL SUBMISSION 18. General comments on the Appeal 18.1 18.1.1 I&APs in the Public Participation Process This organization was formed specifically to oppose the grant of a mining right to the Vele Colliery. Many of members of this organization, including Page 38 its Chairperson Mr. Nick Hiltermann, Mr. Paul Hatty and the representatives of the Machete community were I&APs in the public participation process described in paragraph 5.2 above. 18.1.2 Not all of these I&APs provided comments in the public participation process. For those that did provide comments, these were all responded to by the Company in the Response List (Annexure “LC1”). 18.1.3 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the EMP approval. 18.1.4 There are also a number of new comments made by this Appellant. As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. In general, none of the I&APs that responded conveyed that they had additional comments which they wished to make. 18.1.5 Nevertheless, this Appellant appears to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 18.1.6 At no time has this Appellant suggested actions on the part of the Company which may have prevented it from timeously submitting its reviews in the I&AP process. There were no such actions by the Company; it complied with the requirements for public participation conscientiously and properly in the authorisation process. 18.1.7 This Appellant also gives no indication why the comments it presents now were unavailable at the time comments and review of the EMP were provided. We submit that this Appellant should not be permitted to introduce new material in the course of this appeal process but to confine itself to material which already forms part of the record. 18.2 18.2.1 MAG is also an Appellant in the EMP Appeal MAG has also appealed against the decision to approve the EIA/EMP. Page 39 18.2.2 As discussed below, a large majority of issues in this appeal raise grounds that centre on the EMP and the adequacy of the EMP. 18.2.3 It is reiterated that the decision to approve the EMP should not be confused with the decision to approve the mining right. These issues should accordingly be ignored for the purposes of this appeal. 18.3 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 19. Specific responses to the appeal submissions made by the Appellant 19.1 Re 8.3.1: Damage to Sense of Place of Mapungubwe National Park and World Heritage Site 19.1.1 19.1.1.1 EMP has dealt with sense of place Detailed modeling of the potential air/dust, noise and visual impacts of the Vele Colliery has been done. 19.1.1.2 The following specialists reports that were annexed to the EMP are relevant to this assessment: 19.1.1.2.1 the Visual Study; 19.1.1.2.2 the Noise Study 19.1.1.2.3 the Blasting Study; and 19.1.1.2.4 the Air Study. 19.1.1.3 In addition, the following sections of the EMP which summarises the specialists’ reports in respect of the potential visual, noise and Page 40 dust impacts are relevant: 19.1.1.3.1 visual impacts: pages 89 – 90; 126 – 129; 131; and 136 – 137; 19.1.1.3.2 noise impacts: pages 76 – 77; 119 – 120; 123 – 126; 130 – 131; and 135; and 19.1.1.3.3 air quality impacts pages 74; 89 – 90; 115 – 118; 121; 130; and 133. 19.1.1.4 These indicate that in general MNP, located 7km from the most western boundary of the West Pit and 15km from the Wash Plant, will not be impacted by the operations of the Vele Colliery. 19.1.1.5 To the extent that there will be an impact, mitigation measures have been committed to in the EMP. Reference is made to Annexure “LC15” for a summary of the impact assessment and the mitigation measures proposed. 19.1.2 Other potential developments The Company cannot comment on the possibility of other unrelated developments and its application must be considered on its own merits. 19.1.3 19.1.3.1 Existing impact on rural character of the area Mining and intensive agricultural activities has already been undertaken in the area. Conspicuously, as described above, there is not a single reference in this Appeal to the existing mining operations in the area, which are substantially closer to the World Heritage Site and the MNP. 19.1.3.2 Many of the I&APs noted in their comments the existing impact of the Venetia Mine on the sense of place within the area. 19.1.3.3 The following developments in even closer proximity to MNP, Page 41 have already impacted on the sense of place and must be factored in when assessing this comment: 19.1.3.3.1 Venetia Mine, which is one of the world’s largest opencast diamond mines, is situated approximately 5.8km south of the park boundary and is highly visible from MNP. Notably in this regard, as you will be aware from the relevant EIA, Vele Colliery will mostly not be visible in this manner as a result of the topography of the area; 19.1.3.3.2 Tuli Colliery is situated on the Zimbabwean side of the Limpopo River, directly opposite the proposed Vele Colliery; 19.1.3.3.3 mining was being undertaken within the MNP itself at the time of the UNESCO World Heritage Site application and is referred to in the recommendation by the Committee as follows (see pages 56 - 57 and 96 of the application. The entire application is voluminous and only the relevant pages are attached as Annexure “LC16”): “A small portion of the farm Riedel in the eastern part of the Park has been kept on in the hope that it will yield profitable mining operations. This site is in the ancient river course of the Limpopo River. All indications are that it is worked out and unlikely to have an impact on the Mapungubwe Cultural Landscape.” 19.1.3.3.4 In addition to mining activity, there are presently intensive agricultural and related activities located in the Limpopo Valley, which are also visible from MNP. Much of the area covered by the Vele Colliery has previously been under intensive agricultural use, overgrazed and stripped of vegetation through this process. Page 42 19.2 19.2.1 Re 8.3.2: The Greater Mapungubwe TFCA While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 19.2.2 On 23 January 2009 in a meeting with, amongst others, the DEAT, SANParks and PPF, representatives of Limpopo Coal were provided with a Memorandum of Understanding between South Africa, Botswana and Zimbabwe in respect of the Limpopo/Shase Transfrontier Conservation Area. The map attached to the MOU does not include the area of the Vele Colliery (attached marked “LC17”). 19.2.3 The name of this Transfrontier Conservation Area was changed to the Greater Mapungubwe Transfrontier Conservation Area in mid 2009. 19.2.4 In April 2009 Limpopo Coal was provided with a plan for a proposed extension of the Limpopo-Shashe/Greater Mapungubwe Transfrontier Conservation Area. This plan has not been approved through any official channel. None of the mandatory consultative processes have been undertaken in respect of such a plan. This plan showed a desire on the part of the author to further extend the Limpopo-Shashe/Greater Mapungubwe Transfrontier Conservation Area, across privately owned land and to include the area of the Vele Colliery. 19.2.5 Even establishing the initial TFCA area itself is still very much a work in progress. The PPF presents this as though it were already in place, which is highly misleading. This is clearly merely a further aspiration to extend the TFCA in a direction which was never envisaged by the various governments. See the information regarding this downloaded from the SANParks, PPF, and DEAT’s websites in May 2009 when the EMP process was being finalized (attached marked “LC18”). The focus from the South African government’s websites appears to have been on the “core” area of MNP itself. Page 43 19.2.6 The map for the expanded TFCA area notably only has PPF’s logo on it (attached marked “LC19”). PPF is an NGO. It has no authority in respect of declaration or development of new national parks or protected areas. Instead, the PPF seeks to use the occasion of this appeal apparently to pursue its agenda of further extending a TFCA in a manner that was never initially envisaged. This, it is submitted, distorts the existing and real conservation initiatives in the area which the Company is wholly supportive of. 19.2.7 The Company has not been consulted as a private land owner regarding a proposed further expansion of the TFCA. This is further indicative of the lack of substance to this proposed idea. Moreover, the appeal makes no mention of the obvious effect of a proposal to further expand the TFCA in a new direction on the existing coal mining operations on the Zimbabwean side. This was presumably one of the reasons why this area was not initially included in the initial TFCA, which extended in the opposite direction. 19.2.8 The Company has put forward its belief, based on the EIA it has undertaken, that its activities can co-exist with other land uses in the area. It has frequently expressed its willingness to engage regarding this. The Company is extremely mindful and supportive of the existing national park and further meaningful conservation initiatives. It is the Company’s belief, which formed the basis of its application, that the successful balance between conservation measures and much-needed development are at the heart of the legislative and policy framework under which the mining right has been granted. 19.3 19.3.1 Re 8.3.3: Mapungubwe Cultural Landscape While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 19.3.2 A HIA, which meets the criteria set by SAHRA, has been carried out Page 44 (Annex-H of the EMP). . 19.3.3 As such, it is specifically disputed that a “full” HIA has not been carried out. 19.4 19.4.1 Re 8.3.4: Potential Loss of World Heritage Status While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 19.4.2 The Vele Colliery will be located approximately 7 kilometres from the most easterly point of MNP (attached, please see map marked “LC20”). 19.4.3 As described above, and in the EMP, the area surrounding MNP is already characterised by mining activity – notably the Venetia Mine is located 5.8km from the southern border of MNP, which is visible from MNP, and the Tuli Colliery which is directly opposite the Vele Colliery in Zimbabwe. The 2006 Management Plan for MNP acknowledges the mineral wealth within the broader area around MNP; and the need to interface the conservation uses within MNP with the mining activities in the broader area. 19.4.4 In addition to mining activity, there is presently agricultural and related activity located in the Limpopo Valley, which is also visible from MNP. 19.4.5 In the circumstances, any threat to withdraw World Heritage Site status for MNP could not be the result of the Vele Colliery, which is located further away from MNP than the existing mining operations. 19.5 19.5.1 Re 8.3.5: The Land Use wishes of MAG members While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is Page 45 completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 19.5.2 This section focuses mostly on the desires of the Machete Community. Representatives of this community were participants in the I&AP process and did not raise the issues which have subsequently been raised. 19.5.3 The Land Claims Commissioner does not recognize any claim by the Machetes to the farms on which the Vele Colliery is situated. The recognized Land Claimants over some of these farms are the Tshivula Community, who were also participants in the I&AP process and are largely supportive of the Colliery. (We note that in the separate appeal made by the Ga-Machete Economic Development Corporation makes no mention of this alleged land claim, see paragraph 40 below.) 19.5.4 The Company was aware that the Machete Community had claims over 56 farms adjoining the mining area. The Machete Community was therefore registered as an I&AP in the public participation process and consulted with during this process. 19.5.5 It has also more recently become aware that the Machete Community claims that it in fact lodged 103 land claims in the area, including over the mining area. The Land Claims Commissioner however advised the Company that it only has record of 56 land claims by the Machete Community and no claims were submitted by the Machete Community over the mining area. In a letter of 20 October 2009, attorneys representing the Machete Community required that the Company suspend all activities associated with the applications for authorisations to carry on mining activities pending application to the Land Claims. 19.5.6 The Company did not agree to this unreasonable request, which had no legal grounds. It is unlikely that the Machete Community will in fact be successful in its land claim over the mining area. The Land Claims Commissioner has no record of such claims and the period for lodgement of claims in terms of the Restitution of Land Claims Act 22 of 1994 has expired, being 31 December 1998. Secondly, even on the assumption that the Machete Community is successful in having its land claims over Page 46 the mining area registered, they would have been in exactly the same position during the public participation process. The Company was obliged to consult with all I&APs during its mining rights application, regardless of whether they were surface rights holders, land right claimants or neighbours to the mining area. The Machete Community was consulted with and had every opportunity to provide its views during the application. These were considered and responded to by the Company. 19.5.7 Correspondence from the Vhangona National Cultural Movement is included but not specifically dealt with in the Appeal. The Correspondent appears to be under a mistaken apprehension regarding the location of the Vele Colliery in relation to MNP. 19.5.8 With respect to the other land users in the area and their land use wishes expressed in this document, the Company can only point out again that part of the land over which the Vele Colliery will be constructed is presently used for intensive agriculture; there are existing mining uses in the area; and the mineral wealth of the area is acknowledged by the MNP and by the Development Planning documentation for the province. 10 In this regard we attach a spatial development review that was done by Pieterse du Toit & Associates (attached marked “LC21”). 19.5.9 The employment benefits of mining have been shown to far out strip those of tourism and the needs and wishes of all within the community must be balanced. We attach a summary of the Vele Colliery project and the positive impact anticipated from the project (Annexure “LC22”). The following employment will be created, calculated on a national scale: 19.5.9.1 Construction phase – during the 3-year construction period, contractor labour levels will peak at approximately 2,500 employees. A large percentage of employees will be targeted to be drawn during this period from the local area. The macro- economic model in the EIA found that the indirect employment opportunities would amount to 12, 926. Limpopo Employment, Growth & Development Plan 2009 – 2014; Limpopo Province Spatial Development Framework; and Musina Spatial Development Framework Plan (June 2005) 10 Page 47 19.5.9.2 Operational phase – The proposed new development will employ approximately 826 permanent employees with varying skills, implying an impact on the direct livelihood (direct workers and dependents) of approximately 1, 495 people. Indirect employment opportunities amount to 28, 255 during the operational phase. 19.6 19.6.1 Re 8.3.6: Loss of Tourism and Agriculture based jobs While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 19.6.2 The impact of mining on neighbouring farmers will be continuously monitored and mitigation measures are in place to ensure no adverse impacts occur. 19.6.3 The mine has not been “evasive”. The SEA Study and SLP includes details of the jobs to be created and the local skills development programmes to be undertaken. 19.6.4 The Company maintains that its use can coexist with other existing uses in the area. 19.7 19.7.1 Re 8.3.7: Substantive issues raised by NGO’s and independent experts While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 19.7.2 All issues raised in the I&AP process were comprehensively answered in the Response List. (See Annexure “LC1”). Page 48 19.7.3 All issues raised and the Company’s responses were before the decision maker. 19.8 Re 8.3.8 International impacts and international legal obligations 19.8.1 There are existing mines in Zimbabwe that fall within the TFCA. 19.8.2 All potential pollution impacts have been assessed in the course of preparing the EIA/EMP and mitigation measures have been committed to in respect of these. 19.8.3 A number of Botswanan and Zimbabwean I&APs were registered in the process. In particular, Geoff Norris from the Northern Tuli Game Reserve acknowledges in his attached letter this registration. He participated extensively and submitted a number of comments in the process. In addition, Northern Tuli Land Owners Association, Nottingham Estates and Sentinal Ranch were all I&APs in the process 19.8.4 No impact could be discerned in the EIA/EMP on Mozambique, which is situated 189.63 kilometers away, nor is there a plausible basis to suggest such an impact. 19.9 19.9.1 Re 8.3.9 Further issues of concern The issues addressed in this section have all been addressed in the EMP. Impacts on Water Resources 19.9.2 As set out in the Response List, (Annexure “LC1”), 11 Eskom has advised that no dam is being built. The potential impact on water resources was extensively assessed in the Surface Water Study (Annex-D of the EMP) and no impact is anticipated on the Limpopo River and surrounds. 19.9.3 11 There will be no mining on the banks of the Limpopo River or in the 1:100 Page 99 of the Response List Page 49 years floodline. 19.9.4 12 Leshika was appointed to provide response to the water related issues raised by the Appellant (the “Leshika Response”). A copy of this report is attached as Annexure “LC23”. Leshika furnished the following responses in respect of MAG’s contention that the Vele Colliery will result in water usage/ supply stress; and that downstream pollution will result: 19.9.4.1 mining will result in less stress on the Limpopo River, as water demands will be reduced by the reduction of irrigation. Saline irrigation return flows will also be reduced. Saline return flows have already impacted the riverine vegetation; and 19.9.4.2 comparisons with Witbank are not valid since the acid-base relationship of the coal and overburden is not the same, nor are climatic conditions. Witbank is an area of water surplus. In contrast, the Vele Colliery is in area of water deficit with no natural base flow generation. Impacts on Air Quality 19.9.5 The contention that dust modeling was not conducted on the West Pit is incorrect. As indicated in the Air Study, the ISC-ST3 model was used for the dispersion modelling. Source data was obtained for the site and included in the model for use in this assessment. All processes and sources were provided for this project; and included in model runs to determine the potential impacts from the site (this included the information provided for the West Pit). 19.9.6 The Air Study Specialist concluded that the fact that the impacts from the West Pit do not reflect on the isopleths plots is an indication that there are other sources which are responsible for more significant impacts. These impacts from other sources override the impacts expected to result due to the West Pit operations. Attached is a supplementary report from Bohlweki SSI, confirming this (attached marked “LC24”). 12 Page 121 and Figure 1.3.3 of the EIA/EMP . Page 50 Biodiversity 19.9.7 An integrated approach to biodiversity was taken in the EMP, as is best practice, since issues overlap and there are many interdependencies. 13 19.9.8 All fauna, flora and avifauna were assessed comprehensively. No cheetah or wild dogs are expected to be present on the farms on which mining will be undertaken, only within the region or on the surrounding properties. 14 19.9.9 Water uses will be less than the existing agricultural allocation. 15 One of the biodiversity offset programmes the Company has committed to pursue will be to restore riverine forest where this has been damaged by misuse in the past. 16 Permits will be obtained for all protected tree relocations, as part of the Rescue and Relocation Plan. 17 19.9.10 The Company’s experts believe it may be possible to restore Mopane. The Biodiversity Study (Annex-C of the EMP) addresses the difficulties of vegetation restoration in arid areas (see page 67). As stated above, page 69 of the Biodiversity Study refers to the research on vegetation restoration in arid areas, and specifically in the Limpopo River Valley by the Northwest University. The research reflects that mine rehabilitation in Mopani veld in the Limpopo River Valley can be done successfully. 19.9.11 The Company will only recruit from a central location in Musina. No workers will be accommodated on site. 18 20. 20.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. Pages 48 – 57 of the EMP and page 2 of the Response List. See Table 2.1.1.8 on page 56 of the EIA/EMP 15 Pages 61 – 62 and 133 of the EIA/EMP 16 Page 5 of the EIA/EMP 17 Pages 113 – 144; Table 2.2.9 on page 141 and Table 2.6(a) and (b) on pages 157 – 160; and Table 2.6(f) on page 164 of the EIA/EMP 18 Page 28 of the EIA/EMP 13 14 Page 51 20.2 IV. The appeal should accordingly be dismissed. THE ENDANGERED WILDLIFE TRUST APPEAL SUBMISSION PARAGRAPHS 5 AND 8 21. 21.1 21.1.1 General comments on this Appeal I&AP in the Public Participation Process This organization was a registered I&AP in the public participation process. 21.1.2 As stated above, it conducted an independent review of the EMP on behalf of other I&APs. The Reviewer’s comments were all responded to by the Company in the Response List (Annexure “LC1”). 21.1.3 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the EMP approval. 21.2 21.2.1 Additional grounds of appeal not mentioned in I&AP response There are also a number of new comments made by this Appellant. In particular, the EWT now seeks to put forward a completely new specialist review of how water issues are dealt with in the EMP. The brief desk top review by Carin Bosman of Sustainable Solutions is attached to EWT’s appeal as Annexure “B”. 21.2.2 This new water review is submitted despite the fact that the EWT commissioned, on behalf of itself and other I&APs, the SAIEA review of the EMP. Water issues are addressed in detail in the SAIEA review and nowhere does SAIEA mention that they lack water expertise or that they will need additional time to undertake a water review. 21.2.3 As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments and perform such reviews as were Page 52 required. The five page desktop review could hardly have required significant time to perform. Sustainable Solutions mentions at the end this review that it had very limited time to perform the review (which is dated 14 March 2010) so it was obviously not asked to undertake it during the I&AP process. Rather, this was obviously commissioned following recognition by the EWT that the SAIEA review, which was included in the I&AP process, did not deal adequately with water issues. 21.2.4 EWT did not at any stage convey that it had additional comments which it wished to make in respect of water issues or that it did not stand by the water comments made by SAIEA. 21.2.5 Nevertheless, the EWT appears to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 21.2.6 At no time has this Appellant given an indication that any actions of the Company prevented it from timeously submitting its reviews in the I&AP process, nor could there be any such suggestion as the Company properly and diligently followed the authorisation process as described above. It also gives no indication why the comments it presents now were unavailable at the time comments and review of the EMP were provided. 21.2.7 The Company submits that this Appellant should not be given the opportunity to include these new criticisms now. 21.2.8 Notwithstanding this, the Company responds to the new material below within the context of the appeal process. 21.3 EWT is also an Appellant in the EMP Appeal 21.3.1 EWT has also appealed against the decision to approve the EIA/EMP. 21.3.2 As discussed below, a large majority of issues in this appeal raise grounds that centre on the EMP and the adequacy of the EMP. Page 53 21.3.3 It is reiterated that the decision to approve the EMP should not be confused with the decision to approve the mining right and these issues should be ignored for the purposes of this appeal. 21.4 21.4.1 Contradictions between the EMP and Mining Right Appeal As is set out above, the SAIEA review which is attached to the EWT Appeal is contradicted, without any explanation, by the EWT in the EMP Appeal. This review is also seemingly abandoned in the EMP Appeal and is hardly referred to at all. 21.4.2 It is submitted that because of this the SAIEA Review should be ignored entirely for the purposes of this appeal. 21.5 Irrelevant grounds of appeal No evidence is raised in EWT’s appeal of pollution for which a mitigation plan has not been made; no evidence of ecological degradation that does not follow automatically from a mining approval is shown and no unacceptable damage to the environment is alleged. This is discussed in the response to EWT’s grounds of appeal below. 22. 22.1 22.1.1 Summary of main appeal submissions Re 9.3.3.1.1 and 9.3.3.1.2: Summary finding of CBSS Review The Appellant makes a generalised statement that the potential impacts on quality and quantity of surface and groundwater resources have not been adequately identified and some impacts have not been identified at all. It is contended that not all potential receptors of these impacts have been identified. 22.1.2 The Company’s responses in to the Appellant’s specific allegations are discussed below. 22.1.3 It is reiterated that the Company instructed specialist in both groundwater and surface water, to thoroughly assess the impacts and potential Page 54 receptors of these impacts; and compile an extensive report. These are attached as Annex-D and Annex E to the EMP. 22.2 22.2.1 Re 9.3.3.2.3: Summary finding of CBSS Review The Appellant makes a generalised statement that the mitigation measures in respect of groundwater and surface water impacts are either lacking or inadequate. 22.2.2 The Company’s responses in to the Appellant’s specific allegations are discussed below. 22.2.3 The Company has compiled a detailed EMP, which includes the mitigation measures proposed by the surface water and groundwater specialists to mitigate any potential impacts they identified. This is included in pages 156 – 166 of the EMP. 23. Specific responses to the appeal submissions made by the Appellant WATER QUANTITY, SUPPLY AND FOOD SECURITY 23.1 23.1.1 Re 9.3.3.2.1: Groundwater availability While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 23.1.2 It is completely incorrect that the water quantity required by Vele Colliery will lead to severe damage and loss to irrigation farmers on both sides of the river, due to loss of available groundwater; and dewatering of the primary aquifer at a rate of more than 50 million cubic metres per annum. 23.1.3 Firstly, dewatering the primary aquifer is not physically possible due to its high permeability and hydraulic connection with the Limpopo. This is therefore a completely baseless allegation. Page 55 23.1.4 In addition, the demand for groundwater at Vele Colliery during full production is approximately 4, 200 cubic meters/day, which amounts to 1.533 million cubic metres per annum and not 50 million cubic metres per annum as stated. The current use from the aquifers is estimated to be in the order of 51.874 million cubic metres per annum. 23.1.5 Vele Colliery’s demand is thus in the order of 3% of current use. 23.1.6 The maximum mine water use will be 4, 200 cubic metres per day (average 3, 500 cubic metres per day) and not 5, 000 cubic metres per day as stated. Further, the basic calculation made to convert this daily use to annual use is incorrect. The annual use is only 1. 278 million cubic metres (3, 500 X 365 = 1, 277, 500 cubic metres) which translates to only 116 ha (1, 278 000 / 11, 000 cubic metres per ha = 116 ha) currently under irrigation (at 11 000 cubic metres per hectare per annum) not 6,000 hectares as alleged. 23.1.7 In fact, the current irrigation areas within the Overvlakte and Weipe aquifers do not even amount to 6, 000 hectares (refer to Table 4.3.9.1, page 37 of the Groundwater Study (Annex-E of the EMP). Portion 23.1.8 of Registered Water Use (million m3/a) Overvlakte River Boreholes Total Storage (m3) 5 1.1 3.0262 4.12 24,500 3 1.1 1.9 3 - 4 1.1 0.23 1.33 74,000 TOTAL 3.3 5.1526 8.45 98,500 The existing water rights have been transferred to Harrisia Investment Holdings (Pty) Ltd. 23.1.9 The water use requirements are for the mine and associated processing. This includes requirements for potable use and irrigation of rehabilitated areas. The difference between the registered water use and actual usage on Portions 3, 4 and 5 of the Farm Overvlakte 125 MS amounts to 3, 08 million cubic metres per annum; being double what the mine requires. Page 56 23.1.10 The mining activities will therefore not impact on the current agricultural activities; which leads to a positive scenario of co-existence between the two land uses. The Department of Agriculture Forestry and Fisheries (“DAFF”) has confirmed that it is satisfied that, in the ordinary course, agriculture will not be adversely affected by the mining activities. (See attached letter “LC25”). 23.1.11 This extreme exaggeration demonstrates a real lack of understanding of the EMP and specialist studies and is a patently unfounded allegation. 23.2 Re 9.3.3.2 (i) No assessment of hydrology or geohydrology on Zimbabwe The irrigation on the Zimbabwean side was taken into account (refer to Table 4.3.9.1, page 37 of the Groundwater Study, Annex-E of the EMP). 23.3 23.3.1 Re 9.3.3.2 (ii) to 9.3.3.2(vi): Recharge of primary aquifer Recharge rates have been modelled both with modflow and via calculation of transmission losses to sustain the irrigation. Low recharge rates are substantiated by the calibrated model. River losses are high to the primary aquifer, largely due to irrigation abstraction. The opencast mining does not overlap with current abstraction from the primary irrigation; hence it will not be dewatered. 23.3.2 As stated above, dewatering the primary aquifer is not physically possible due to its high permeability and hydraulic connection with the Limpopo River. It is repeated that this is a completely baseless allegation and there can be no grounds for alleging that the dewatering of the primary aquifer will have a severe effect on landowners on the South African side of the Limpopo River who utilise the aquifer for irrigation. 23.3.3 Figures were confirmed by a water balance (Refer to paragraphs 5.1, 5.2 and 5.3 of the Groundwater Study (Annex-E of the EMP). The Appellant’s contention that no determination was made with regard to the contribution from the Limpopo River to the aquifer; or from the aquifer to the base flow of the Limpopo River is incorrect. River losses to the Page 57 primary aquifer were calculated via modflow and calibrated. There is very little baseflow from the secondary aquifer, due to low recharge and evapotranspiration by riverine vegetation, hence the river is dry for extended periods. This is indicative of lack of baseflow and low recharge. Under natural conditions, baseflow is almost non-existent and river losses are low. Due to high irrigation demands, river losses have become extensive. 23.3.4 The Appellant has not based its conclusions in paragraph 9.3.3.2 v(i) on accurate information. It is therefore in no position to assess the likelihood, duration and magnitude of this impact. 23.3.5 On the grounds of the Company’s specialist report and thorough investigations (see the Groundwater Study (Annex-E of the EMP)) this issue clearly will not result in “unacceptable pollution, ecological degradation and environmental damage” and accordingly should be ignored for the purposes of this appeal. 23.3.6 A recent study by Leshika on the sustainability of the Overvlakte aquifer has shown that the sustainable yield of the aquifer is sufficient to meet the mining and citrus irrigation needs at a high level of assurance, with water available at a lower level of assurance for the cash crops. Reference is made to the Groundwater Study. 19 23.3.7 The impact on food security is that only 116 hectares of arable land will be lost. This is presently used for commercial cash crops and, as such, has little impact on food security in the real sense. The allegation regarding the impact of the Vele Colliery on food security is therefore again a clear exaggeration by the Appellant. WATER QUALITY 23.4 Re 9.3.3.2 (i): Evaluation of impact on Zimbabwe The potential impact on the shared water resource, in terms of both quality and quantity, has been quantified in detail, taking full consideration of the potential 19 Page 46 of the Groundwater Study (Annex-E of the EIA/EMP). Page 58 impact on the irrigation farmers in Zimbabwe. In fact, Tuli Colliery, a Zimbabwean coal mine is situated directly opposite Vele Colliery. This fact is inexplicably repeatedly ignored by this, and other, Appellants. 23.5 23.5.1 Re 9.3.3.2 (ii) – (iii): AMD The EMP indeed did not quantify the potential for pollution through AMD as high. This was based on the extensive specialist studies conducted on this potential impact. 23.5.2 The potential for acid rock drainage was quantified through acid-base accounting. The waste rock as a whole is not acid generating and the small volume of slurry which has high pyrite content will be buried below the water table, preventing acid generation. Waste rock will be buried in the pits INSIDE the Karoo rocks and hence are not in the primary aquifer. 23.5.3 Reference is made to paragraph 2.2.6.2 of the EMP (page 122): “Acid-base accounting results show that the coal samples (and thus the discard / middlings) are likely acid generating, as are the carbonaceous mudstones. The upper 20m of overburden is strongly neutralising. The acid generating material is expected to be a maximum of 10-20% of the total tonnage disposed of in the pit. In addition, this material will be placed in the bottom of the pit, where they will be submerged; hence the acid-generating potential of the material will be restricted. The neutralizing potential of the waste rock will be available, regardless of its presence above or below the water table. For this reason, the specialist concluded that the waste rock is unlikely to generate acid leachate.” 23.5.4 This conclusion is based on the acid-generation potential analysis performed by the groundwater specialist (paragraph 5.5.2 of the Groundwater Study, Annex-E of the EMP). 23.5.5 It must also further be noted that the primary alluvial aquifer does not have exceptional good water quality as claimed, but in fact has poor Page 59 water quality due to salinisation from irrigation return flows. 20 Attached as Annexure “LC26” is Leshika’s water monitoring report for the Vele Colliery, dated February 2010. The report concludes that the groundwater of the area is poor, with all boreholes falling in the Class 4 range (being water quality that has dangerous levels of contaminants). 23.5.6 The Appellant’s allegation that this impact is “downplayed”; and that the overburden and waste rock will cause pollution of the primary aquifer due to AMD clearly has no foundation. As the waste rock will be buried in the pits inside the Karoo rocks and not in the primary aquifer, the Appellant’s contention that this will lead to further contamination and degradation of the primary aquifer also has no basis. 23.5.7 Based on the Company’s specialist report and thorough investigations (see the Groundwater Study), this impact clearly will not result in “unacceptable pollution, ecological degradation and environmental damage” and accordingly should be ignored for the purposes of this appeal. 23.6 23.6.1 Re 9.3.3.2 (iv): Mitigation measures for dirty water dams Dirty water dams will not be built on the primary aquifer for the simple reason that they would not hold water and also as they would be within the 1:100 year floodline. Again, this demonstrates that there would be no way of contaminating the primary aquifer should AMD occur. 23.6.2 Based on the Company’s specialist report and thorough investigations (see the Groundwater Study), this impact clearly will not result in “unacceptable pollution, ecological degradation and environmental damage” and accordingly should be ignored for the purposes of this appeal. 23.7 23.7.1 Re 9.3.3.2 (v): Capacity of dirty water dams A detailed water balance during and beyond the operational phase has been provided in both the Surface Study and Groundwater Study (Annex- 20 Page 32 of the Groundwater Study, Annex-E of the EMP Page 60 D and Annex-E of the EMP respectively); and is inclusive of the “leachate”. 23.7.2 The calculations show that the mine area has a negative water balance, thus no dams to manage dirty water (or leachate) are required. (See the graph on page 31 of the Surface Study (Annex-D of the EMP)). There is therefore no basis to establish, as required by the Appellant, the “proposed capacities of the proposed impoundments” to assess whether they are adequate. 23.7.3 Based on the Company’s specialist report and thorough investigations (see the Groundwater Study and Surface water Study), this impact clearly will not result in “unacceptable pollution, ecological degradation and environmental damage” and accordingly should be ignored for the purposes of this appeal. 23.8 23.8.1 Re 9.3.3.2 (vi) and 9.3.3.2 (vii): Treatment of water and AMD There are dirty water dams which have been designed to cater for the 1:50 year storm event, thus to capture the runoff from the “dirty” or process areas 23.8.2 As stated in paragraph 1.3.4.3 of the EMP, “a closed system is being designed whereby all water is recycled for use in the process”. No dirty water will be discharged into any stream or river during the operational phase and thus no treatment is required. The EMP further states that potential decant (post-closure) must be contained and one of the following measures implemented: 1) treat to an acceptable level before released into the environment, 2) store and evaporate and 3) use for irrigation of crops and rehabilitated areas. These options must be evaluated during the life of mine and included as part of the mine closure plan. 21 23.8.3 It is reiterated that all dirty water will be recycled for reuse within the process. To state that the proposed mitigation measures do not reflect Best Practice, as outlined in the Best Practice Guideline for Water 21 Page 129 of the EIA / EMP Page 61 Management at Mines, 2008 (which is not a legal requirement) or section 22 of the NWA is insupportable. 23.8.4 Based on the Company’s specialist report and thorough investigations (see the Groundwater Study and Surface water Study), this impact clearly will not result in “unacceptable pollution, ecological degradation and environmental damage” and accordingly should be ignored for the purposes of this appeal. SOCIO CULTURAL USE OF WATER 23.9 23.9.1 Re 9.3.3.2.3 There are absolutely no grounds for this contention raised by the Appellant. 23.9.2 The Vele Colliery will not abstract more water from the Limpopo River than was abstracted previously. Furthermore, as a closed system is being designed, whereby all water is recycled for use in the process, the operations will not impact on the water quality of the Limpopo River. 23.9.3 Based on the Company’s specialist report and thorough investigations (see the Surface water Study), this impact clearly will not result in “unacceptable pollution, ecological degradation and environmental damage” and accordingly should be ignored for the purposes of this appeal. GENERAL OBSERVATIONS 23.10 23.10.1 Re 9.3.3.2.4(i): Economic Benefits While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. Page 62 23.10.2 The Appellant has no basis to contend that the Vele Colliery will have “limited economic benefit”. 23.10.3 The MEA Study was compiled by specialists in macro-economics, which concluded that economic benefits will accrue to the Limpopo Province from the Vele Colliery. It is also repeated that the following employment opportunities will arise from the operations: 23.10.3.1 Construction phase – during the 3-year construction period, contractor labour levels will peak at approximately 2,500 employees. The majority of employees will be targeted to be drawn during this period from the local area. The macro- economic model in the EIA found that the indirect employment opportunities would amount to 12, 926. 23.10.3.2 Operational phase – The proposed new development will employ approximately 826 permanent employees, resulting in an impact on the direct livelihood (direct workers and dependents) of approximately 1, 495 people. Indirect employment opportunities amount to 28, 255 during the operational phase. 23.10.4 LCC has also begun with implementation of its SLP, which is part of its Mining Right. This provides for the upliftment of its labour force and community members in the Musina Local Municipal and Vhembe District Municipal Area. In terms of the MPRDA, LCC is obliged to comply with the provisions of the SLP. In particular, discussions have already started with the Musina Municipality regarding two important Local Economic Development projects being the lime project (community project in or close to Musina); and the water infrastructure project (assistance with the upgrading of the water supply and sewage infrastructure in Musina). 23.10.5 As stated above, the Development Planning documentation for the province also supports economic growth through mining. 22 Limpopo Employment, Growth & Development Plan 2009 – 2014; Limpopo Province Spatial Development Framework; and Musina Spatial Development Framework Plan (June 2005) 22 Page 63 23.11 23.11.1 Re 9.3.3.2.4(ii): Consultations with I&AP in Zimbabwe While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 23.11.2 It is incorrect that I&APs in Zimbabwe were not consulted with or that the EMP does not address impacts as a result of the mining in Zimbabwe. In particular: 23.11.2.1 stakeholders from both Botswana and Zimbabwe registered as IAPs and attended the Open Day, where the project was presented. Issues and concerns were recorded on a register and supplied to specialists to incorporate into their specialist studies; 23.11.2.2 all specialist reports identified impacts well beyond the mining right application boundary and also identified sensitive receptors, if the predicted impact models showed an impact beyond these boundaries; 23 and 23.11.2.3 the irrigation on the Zimbabwean side was taken into account. 24 RESPONSES TO SUSTAINABLE SOLUTIONS REPORT 23.12 We set out below the comments in the Leshika Response to the water related issues raised by Sustainable Solutions (which is attached to EWT’s appeal as Annexure “B”), which supports and amplifies the Company’s responses set out above. Some of these comments have already been made above but for the sake of completeness we repeat them in this section. 23.13 This short desk top report is wrong in almost every respect, including in the basic calculations and the understanding of the information contained in the specialists’ report. The Ground and Surface Water Studies undertaken for the EMP were 23 Refer to Figure 2.1.1.12 (p77), Figure 2.1.1.15 (page 90 of the EMP), as well as the specialist reports included as annexures to the EMP 24 Refer to Table 4.3.9.1, page 37 of Annex-E Page 64 comprehensive undertakings by recognised specialists. We submit that for these reasons alone the report Sustainable Solutions Report should be ignored entirely. 23.14 23.14.1 Re 9.3.3.2 (i): Groundwater availability There are no plans to dewater the “primary” alluvial aquifer. Existing irrigation from the alluvial aquifer will be reduced due to the withdrawal from use of land presently under irrigation. The reduction in irrigation is greater than mine water use; hence there will be a net reduction in water use. Dewatering of the poor quality Karoo aquifer is envisaged. The aquifer is not currently used for irrigation due to the high salt content of the water. This low quality water obtained during the dewatering process will be used for mine process water. 23.14.2 The maximum mine water use will be 4, 200 cubic metres per day (average 3, 500 cubic metres per day) and not 5, 000 cubic metres per day as stated. 23.14.3 The basic calculation made to convert this daily use to annual use is incorrect, the annual use is only 1.278 million cubic metres (3, 500 multiplied by 365 = 1, 277, 500 cubic metres), which translates to only 116 hectares (1,278, 000 / 11, 000 cubic metres per hectare = 116 hectares) currently under irrigation (at 11, 000 cubic metres per hectare per annum) not 6, 000 hectares as alleged. 23.14.4 This is a significant error in the report. 23.14.5 The impact of mining has been quantified on both sides of the river. The Limpopo River was considered a constant head boundary thus no impacts will occur across this boundary. 23.14.6 25 It is not correct to say that recharge rates have not been modelled; they have been modelled with both modflow and via calculation of transmission losses to sustain the irrigation. 25 See section 1.4 of the Groundwater Study Page 65 23.14.7 The planned opencast mining will not dewater the primary aquifer and so will not overlap with current abstraction from the primary aquifer by irrigation. In fact, dewatering the primary aquifer is not physically possible due to its high permeability and hydraulic connection with the Limpopo River. It is not dewatered by irrigation. The figures were confirmed by a water balance. 26 23.14.8 The EIA describes the hydrogeological assessment done for the purposes of the mining right application. Further work was undertaken in support of the IWULA application; and concentrates on evaluation of the Overvlakte alluvial aquifer in terms of water abstraction. Modflow is the standard numerical model that was used. 27 Transmission losses are the losses from the Limpopo River. Existing river loses to the primary aquifer were calculated via modflow and calibrated. 23.14.9 There is very little base flow from the secondary aquifer due to low recharge and evapotranspiration by riverine vegetation; hence the river is dry for extended periods. This is indicative of the lack of base flow and low recharge. Under normal conditions, base flow is almost non-existent and the river losses are low. Due to the high irrigation demands, river losses have become extensive. This is to reinforce the fact that recharge is low and that the irrigation water actually comes from the river flow. 23.14.10 The impact on food security is that only 116 hectares of arable land will be lost. 23.14.11 Evaluation shows that the impact will be contained in the pit area and if decant occurs, it will be treated and/or disposed in an environmentally safe way. Thus the impact will only be local. Continued monitoring will also be done to monitor the situation, so that mitigation measures can be implemented where necessary. 23.15 23.15.1 26 27 Re 9.3.3.2: Water Quality The potential for acid rock drainage has been quantified through acid- See sections 5.1,5.2 and 5.3 of the Groundwater Study See section 5.1 of the Groundwater Study Page 66 base accounting and found to be non acid generating. The waste rock at mine as a whole is not acid generating 28 and the small volume of tailings with the high pyrite content will be buried below the water table, preventing acid generation. For acid generation the pyrite needs to be oxidised. If buried below the water table, it is cut off from oxygen and cannot be oxidised. Waste rock will be buried INSIDE the Karoo rocks; hence will not be in the primary aquifer. 29 The pits act as sinks, thus all water will drain towards them. Only once the pits have recovered to the original water level (many years after mining has stopped) could there be a potential of decant. The decant water is not expected to be acidic but will have an increased salt load. The Groundwater Study specifically looked at sulphates and showed how the sulphate load would increase. 30 The background water quality also has a high salt load. The impacts are therefore expected to be minimal. 23.15.2 It is not explained how burying the waste rock in the pits below the level of the primary aquifer could possibly contaminate the primary aquifer. The direction of the seepage is downwards. For upwards flow the tailings would have to be submerged, at which point they are not acid generating. Dirty water dams will not be built on the primary aquifer for the simple reasons that they would not hold water and also that they would be within the 1:100 year floodline. 23.15.3 The primary alluvial aquifer does not have exceptional good water quality as claimed, but in fact has poor water quality due to salinisation from irrigation return flows. 24. 24.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 24.2 28 The appeal should accordingly be dismissed. See section 5.5 of the Groundwater Study See section 5.5 of the Groundwater Study 30 See section 5.5.3 of the Groundwater Study 29 Page 67 V. THE ASSOCIATION OF SOUTHERN AFRICAN PROFESSIONAL ARCHAEOLOGISTS APPEAL SUBMISSION 25. 25.1 25.1.1 General comments on the Appeal I&APs in the Public Participation Process This organization was an I&AP in the public participation process described in paragraph 5.2 above. 25.1.2 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the EMP approval. 25.1.3 There are also a number of new comments made by this Appellant. As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. In general, none of the I&AP respondents expressed the view that they had additional comments which they wished to make. 25.1.4 Nevertheless, this Appellant appears to believe that it should have an unlimited number of opportunities to introduce further material and allegations as to why a mining right should not have been granted to the Company. 25.1.5 At no time has this Appellant given an indication of what actions of the Company prevented it from timeously submitting its reviews in the I&AP process. It also gives no indication why the comments it presents now were unavailable at the time comments and review of the EMP were provided. 25.1.6 We submit that there were no such actions by the Company and, as such, this Appellant should not be given the opportunity to include these criticisms now. The introduction of new material for the first time on appeal undermines the statutory process which is designed to ensure that extensive, and in many cases, technical criticisms are properly ventilated and considered at the initial stage during the I&AP process. The introduction of new material on appeal is prejudicial both to the Company Page 68 and the decision-makers. 25.1.7 Notwithstanding this, the appeal submissions are flawed, as set out below. 25.2 ASAPA is also an Appellant in the EMP Appeal 25.2.1 ASAPA has also appealed against the decision to approve the EIA/EMP. 25.2.2 As discussed below, a large majority of issues in this appeal raise grounds that centre on the EMP and the adequacy of the EMP. 25.2.3 It is reiterated that the decision to approve the EMP should not be confused with the decision to approve the mining right and these issues should be ignored for the purposes of this appeal. 25.3 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 26. Specific responses to the appeal submissions made by the Appellant 26.1 26.1.1 Introduction It is difficult to respond to this submission, as much of it concerns academic and theoretical views. Limpopo Coal and its specialist do not disagree with many of these academic submissions. What they disagree with is the relevance of these submissions to the particular proposed development, which is not in an area which has been set aside exclusively for heritage preservation, and has instead been the subject of intensive agriculture for a number of years. It must be noted that: 26.1.1.1 MNP (and even the existing boundary of the TFCA) represent a huge area set aside for conservation and heritage preservation Page 69 purposes. When MNP was established, its boundaries were demarcated for a reason; 26.1.1.2 there is already mining in the vicinity of the MNP and extensive agriculture in the area, the area is also unlike the MNP area in geology and other characteristics; and 26.1.1.3 a comprehensive HIA Study has been conducted. This met the requirements of the NHRA. 26.1.2 There is specific legislation to deal with heritage impacts, most specifically the National Heritage Resources Act 1999 (“NHRA”). This legislation allows for a range of measures to accommodate heritage artifacts objects and places. Notably the MNP is proclaimed in term of environmental legislation, as there is no equivalent in heritage legislation. 26.1.3 It is impractical to seek to sterilize extensive areas on account of history. A large chunk of the area has been preserved in MNP, 7km to the west of Vele Colliery, and has been given heritage status. Agricultural uses and mining uses have been undertaken in the area for many years – even by inhabitants of Mapungubwe. 26.1.4 The ASAPA Appeal appears to refer interchangeable to the MNP and the broader Mapungubwe cultural landscape. It is only the area of the MNP that has been given World Heritage Status under the name “Mapungubwe Cultural Landscape”. The Mapungubwe cultural landscape is in fact an extensive area and could have stretched as far as Musina in the east. 31 The latter has not been declared a protected area under the Protected Areas Act; the World Heritage Convention Act 49 of 1999 or National Environmental Management: Biodiversity Act, 10 of 2004 (the “Biodiversity Act”). As stated above, it would be clearly inconceivable to prevent development in areas that fall within the Mapungubwe cultural landscape, which in any event already incorporates large towns; widespread agricultural activity and existing mines, including coal mining on the Zimbabwean side directly opposite the Vele Colliery. 31 Page 6 of the HIA Study Page 70 26.1.5 Existing heritage resources within the mining area have been identified during the mining right application in the HIA Study. During the mining operations, further heritage surveys of all areas to be disturbed will be conducted. Areas where there is any doubt regarding the presence of heritage resources, will be disturbed in a slow and systematic manner, with a suitable heritage specialist present. This will in fact assist with documenting and understanding the heritage of the area. 26.1.6 The MPRDA requires a heritage assessment which falls within certain parameters. In particular, an applicant for a mining right must investigate, assess and evaluate the impact of his or her proposed prospecting or mining operations on any national estate referred to in section 3(2) of the NHRA. 32 The MPRDA Regulations 33 provides that an EMP must include the following in respect of heritage resources: 26.1.6.1 a description of the environmental objectives and specific goals for historical and cultural aspects, if applicable; 34 26.1.6.2 an outline of the implementation programme, which must include a description of the appropriate technical and management options chosen for each historical and cultural aspect for each phase of the mining operation; and 35 26.1.6.3 action plans to achieve the objectives and specific goals, which must include a time schedule of actions to be undertaken to implement mitigatory measures for the prevention, management and remediation of each historical and cultural aspect for each phase of the mining operation. 36 26.1.7 This is precisely what has been undertaken. The Appellant’s assertion that a “full HIA” should have been conducted is baseless and it is unclear what is sought here. 32 With the exception of the national estate contemplated in section 3 (2) (i) (vi) and (vii) Published under Government Notice R527 in Government Gazette 26275 of 23 April 2004 34 Regulation 51(a)iv of the MPRDA Regulations 35 Regulation 51(b)i of the MPRDA Regulations 36 Regulation 51(b)ii of the MPRDA Regulations 33 Page 71 26.1.8 Directions for the compilation of HIA are set out in SG 2.2 SAHRA APM Guidelines the: “Minimum Standards for the Archaeological and Palaeontological Components of Impact Assessment Reports”. These Guidelines are attached as (Annexure “LC27”). The relevant sections of these guidelines are set out below. 26.1.9 The process of paleontological assessment (PIA) specialist for the archaeological components of (AIA) heritage or impact assessments usually involves: 26.1.9.1 Initial Pre-Assessment (Scoping) Phase: where the specialist must establish the scope of the project and terms of reference for the developer; 26.1.9.2 Phase 1 Impact Assessment/ Specialist Report: which must 26.1.9.2.1 identify the sites; 26.1.9.2.2 assess their significance; 26.1.9.2.3 comment on the impact of the development; 26.1.9.2.4 make recommendations for their mitigation or conservation, or 26.1.9.3 Letter of Recommendation for Exemption (if there is no likelihood that any sites will be impacted); 26.1.9.4 Phase 2 Mitigation/ Rescue: which involves planning the protection of significant sites; or sampling through excavation or collection (in terms of a permit) at sites that may be lost; 26.1.9.5 Phase 3 Heritage Site Management Plan (for heritage conservation): may be required in rare cases where the site is so important that development will not be allowed. Developers may also choose to, or be encouraged to, enhance the value of the sites retained on their properties with appropriate interpretive Page 72 material or displays; 26.1.9.6 Field survey: Phase 1 AIA generally involve a survey of the proposed development and will include: 26.1.9.6.1 details of the property to be developed and the type of assessment; 26.1.9.6.2 location of the sites that are found; 26.1.9.6.3 a short description of the characteristics of each site; 26.1.9.6.4 a short assessment of the importance of each site, indicating which should be conserved and which mitigated; 26.1.9.6.5 an assessment of the potential impact of the development on the site/s; 26.1.9.6.6 in some cases, a shovel test, to establish the extent of a site, or collection of material to identify the associations of the site. (A pre-arranged permit is required); and 26.1.9.6.7 26.1.9.7 recommendations for conservation or mitigation; Public consultation and assessment of spatial and visual impacts: when a Phase 1 Impact Assessment is part of an EIA, wider issues (such as public consultation and assessment of the spatial and visual impacts of the development) may be undertaken as part of the general study and not be required from the archaeologist. 26.1.10 The HIA Study clearly complied with this Guideline in assessing the impact of the Vele Colliery on heritage resources. 26.1.11 The only other impacts on heritage resources that could arise from the mine would potentially be from dust, other air quality impacts or from blasting vibrations. These wider issues, being the impact of the dust and Page 73 vibrations from the Vele Colliery on MNP were assessed in the EMP, in accordance with the SAHRA guideline, which does not require that these impacts to be assessed by a heritage specialist. 26.1.12 No separate public consultation was undertaken by the heritage specialist, as a comprehensive public consultation process was performed as part of the general study. Discussions were held with landowners, neighbouring farmers, farm workers, land claimants and conservation bodies in the area. 26.1.13 Socio-cultural impacts were not mentioned by any of the local people during the extensive public participation process. 26.1.14 The Company reiterates that is has compiled with the legislative requirements and SAHRA’s guidelines in the compilation of the HIA Study. There is no classification of a “full” HIA in these Guidelines and the Appellant’s comments regarding the nature of this “full” HIA lack any substance. 26.1.15 As stated above, the objective of a HIA is to identify heritage resources affected by proposed operations. For the most part, this involves an identification of the heritage resources themselves within the affected area of the development to ensure these are not impacted on by the development. 26.1.16 Furthermore, in its approval of the EMP the DMR specifically required that Phase 2 permits be obtained from SAHRA where necessary. Accordingly, the issue of heritage was considered by the decision maker in the EMP approval process. 26.1.17 It is submitted that, for these reasons, this discussion of heritage resources does not provide a basis for the mining right to be set aside. 26.1.18 26.2 Nevertheless, we respond to the substance of the contentions made. Re 9.3.1 Industrialization will have a permanent negative impact on the integrity of the heritage and natural landscape Page 74 26.3 In respect of the Appellant’s allegations regarding the impact on the sense of place, reference is made to paragraph 19.1 above. 26.4 Reference is also made to the discussion above regarding the interchangeable manner in which ASAPA refers to the MNP and the Mapungubwe cultural landscape. To date SANParks has not been able to properly incorporate the area of the MNP. Any extension of protected area status to private land requires land owner consent. Reference is also made to the rock art response below, which explains the real differences in landscape and geology between MNP and the Vele Colliery area renders questionable the analysis of the damage that will be done to the “integrity of the landscape”. 26.5 The actual sites that stand to be impacted directly by the mine are discussed below. 26.6 Please refer to paragraph 19.2 above for a discussion of the boundaries of the TFCA. 26.7 Re 9.3.2 A number of archaeological sites from different periods will be destroyed. Re 9.3.2.1. General 26.7.1 The Company sets out below its responses to the Appellants allegations regarding the sites to be destroyed. 26.7.1.1 Sites 1, 2, 23, 24, 25 and 26 are in the location of the East Pit. From the plan it is evident that Sites 2, 24 and 25 are located outside the East Pit and will not be disturbed. The only sites that will be disturbed by the East Pit are Sites 1, 23 and 26 in the longterm; due to a change in the mining plan Sites 1 and 23 will not be immediately disturbed. . 26.7.1.2 Site 21 is in the West Pit. It is correct that it will be disturbed in the long term. Page 75 26.7.1.3 Sites 5, 14, 15, 16, 17, 18 and 19 are within or close to the Wash Plant. None of these Sites will be impacted on; the infrastructure was placed to ensure that these sites are not impacted. 26.7.1.4 Because Sites 5 and 18 are in close proximity to the Wash Plant infrastructure they have been fenced off, it was decided to initiate this immediate action at these Sites in the short-term due to the potential for impact at these Sites. (see the attached photograph marked “LC27.1”) 26.7.1.5 Sites 6 and 7 are within the area of the possible railway line route. Only Site 7 is situated along the course. The route will be deviated to avoid impact. Site 6 is situated to the east of the railway line route and is not in close proximity to it. 26.7.1.6 Site 4 is not close to the head shaft linking the underground infrastructure; this is depicted on the map. It will not be impacted. 26.7.1.7 Site 22 will not be impacted. The final designs and routing of the clean water drains around the West Pit have not been finalized. This site will therefore be avoided. 26.7.1.8 Therefore only 4 of the 26 sites (15%) will be impacted on directly (or removed). 26.7.1.9 Two graves are present on Portion 3 of the Farm Overvlakte, close to the Estelle Esterhuyse farmstead. These graves are far outside the planned mining areas, as they are within the floodplain these will not be impacted. 26.7.2 It is completely untrue that no mitigation has been suggested for non-Iron Age Sites. Comprehensive mitigation measures for all identified sites have been suggested. Please refer to the Heritage Management Plan “LC28”. 26.7.3 Please refer to the response to paragraph 9.3.2.3 below for a detailed discussion of the criticisms of the Stone Age aspects of the HIA. Page 76 Re 9,3,2,2 Rock art – Specialist not involved in Phase 1 assessment 26.7.4 Whether rock art is indeed present in the mining area as alleged by the Appellant is doubtful, for the reasons set out below. 26.7.5 The Company requested specialists to provide supplementary comments on the Appellant’s contention that rock art is present in the mining area. Their responses are set out below. 26.7.6 26.7.6.1 Frans Roodt The Appellants make the assumption that the area where Vele Colliery is located has similar geo-morphological features to the area within the MNP and area to the west of it. Therefore, it is extrapolated by the Appellants that, what is present to the west of the Vele Colliery must also be present at the Vele Colliery. 26.7.6.2 This is a misconception, which clearly reflects the fact that the Appellants have not been to the site. 26.7.6.3 A site visit makes the distinctions between landscape at the mining area and to the west (towards MNP) very clear. The core Mapungubwe area consists largely of flat topped sandstone ridges and a broken topography, while the mining area contains granite outcrops, hills and is more undulating with calcrete outcrops. Furthermore, at the Vele Colliery the fertile floodplains are mostly under cultivation and disturbed while at Mapungubwe the floodplains are mostly intact. 26.7.6.4 The impact of these differences on the potential for rock art within the area of the Vele Colliery is set out below, as confirmed by a specialist in geology. 26.7.6.5 The geology of the area also determined where people preferred to settle. Because crop farming was crucial to the Mapungubwe period, most settlements were likely in close proximity to the Page 77 floodplain. This can be seen at the extensive Site 4, where large numbers of grain bin stands are present. As stated above, within the mining area there has also been widespread cultivation on the floodplain during recent years which has resulted in further destruction of heritage sites. 26.7.6.6 Erosion and a dam have severely impacted on Site 4. Due to reasons discussed above, at the Vele Colliery there is actually a low frequency of preserved sites. 26.7.6.7 This cultivation has also been conducted particularly to the west of the mining area up to the MNP boundary. These areas have already been extensively disturbed and if any heritage areas and/or objects were not identified when this land was first cultivated, this cultivation is likely to have obliterated all trace of these. Destructive natural forces, such as erosion, have also damaged sites to the west of the Vele Colliery. 26.7.7 26.7.7.1 WSM Leshika Consulting (Pty) Ltd A geologist, at Leshika compiled a report regarding the possibility of the rock, which was identified by the heritage specialist as being conducive to rock art, being present on the mining area. The responses to this possibility are set out below. 26.7.7.1.1 From a geological perspective, it is understood that the majority of rock art is found in caves prevalent in the Clarens Sandstone Formation (also known as the cave sandstone). In the area of the mine/the region the Clarens Sandstone Formation is made up of two sub-horizons. In the Tuli Basin these two layers are termed the Red Rocks Member and the overlying Tshipise Member. 26.7.7.1.2 The Red Rocks member comprises very fine to fine grained pinkish to red argillaceous (clayey) sandstones of up to 60 metres in thickness. The overlying Tshipise Member consists of fine to very fine yellowish sandstone, Page 78 varying from 5 to 140m in thickness. 26.7.7.1.3 The Tshipise Member is weathering and erosion resistant, relative to the Red Rocks Member; and has the tendency to form flat-topped “koppies”. Caves are commonly developed along the contact between the Tshipise and the Red Rocks Members. A geological map illustrating the trace of the contact between the two strata and so the probable sites for most of the rock art, as provided in Leshika’s supplementary report (Annexure “LC23”), is included below. The Tshipise /Red Rocks Member contact at its closest juncture is 5, 500 metres to the west of the western limit of the mine. 26.7.7.2 Thus, from a geological perspective, it is highly unlikely that any rock art sites do exist within the mining area. 26.7.8 26.7.8.1 Jeremy Hollmann On the 13th, 14th and 15th July 2010 Mr Jeremy Hollmann of the Page 79 Natal Museum surveyed the affected areas. Mr Hollmann’s credentials in respect of Rock Art are set out in his CV attached marked “LC29”. 26.7.8.2 Mr Hollmann inspected all rock outcrops and other rock features with potential for rock art, including large, free-standing boulders and looked for rock paintings, or traces thereof, as well as rock engravings. However, no traces of rock paintings were found on any surfaces, or any indication of rock engravings. His conclusion was therefore that no rock art occurs on these farms. 26.7.8.3 26.7.8.3.1 As a result of his survey he concluded that: the absence of rock art is a significant finding, given that parts of the Limpopo Shashe Confluence Area (“LSCA”), some 25 km to the west of the mining area, are renowned for rock art. The reasons for this absence are probably complex and will include environmental and cultural factors. More archaeological research is thus required, in order to understand the distribution of rock art in this part of the province; 26.7.8.3.2 the types of rock on the surveyed mining area differ in important respects from the painted and engraved rock surfaces in the LSCA to the west. The ridges on the surveyed farms comprise a variety of quartz and sandstone with large pebbles. The small, rocky hills on the surveyed farms are composed of gneiss. None of these rock types seems suitable for rock art, either painting or engraving. They are coarse-grained, especially when compared with the surfaces to the west, which are a smoother, finer-grained kind of sandstone. Prehistoric artists may therefore have considered these surfaces unsuitable; 26.7.8.3.3 there was very little evidence of Later Stone Age (“LSA”) flakes and other artefacts. There were also no signs that Page 80 any of the ridges and hills was inhabited by people using LSA technology. Whilst it is true that many South African rock art sites do not show any evidence of occupation, the suitability of the rock; lack of any other LSA material culture; and a general absence of water in most of the rocky areas could suggest that the LSA populations did not favour these areas for habitation or making rock art. Rock art in MNP – impact by dust, chemicals, blasting, water Dust 26.7.9 The air quality model took into account the truck and shovel operations and have shown that the level of dust generation falls well within all the SANS standards for air quality, 37 even without any mitigation measures. With mitigation these are reduced substantially. 26.7.10 Excessive blast-related dust is caused by insufficient or ineffective stemming material in each hole. The negative impact significance will be reduced to low with effective stemming controls in place. With these measures, atmospheric dust is mostly contained to within about 200 m of blasting. 38 26.7.11 Based on the distances between the rock art sites listed within MNP and the proposed mining operations, the potential for elevated levels of dust to be generated in these areas is minimal. Vehicle entrained dust and exhaust emissions within the MNP would most probably have a much higher impact than the mine. Similarly, agricultural dust emissions west of Vele Colliery would most probably have a much higher impact. Dust Suppression 26.7.12 As for the dust suppression, the mine has decided to utilize a product called Dustex. See an attached report marked “LC30” for more information. 37 38 Pages 115 – 199 of the EIA/EMP Page 8 of the Blasting Study (Annex-K, of the EIA/EMP) Page 81 26.7.13 Dustex is a calcium lignosulphonate, which is a non toxic by product from the wood-pulping process (King, 2005). Lignin is a natural polymer that binds wood cells together, giving tree bark its flexible properties (King, 2005). Dustex therefore acts as a binder, as it consolidates aggregate to form a durable, hard, dust free surface (King, 2005). At LignoTech SA, spent cooking liquor from Sappi Saiccor is sent through a process to remove wood fibres and the majority of sulphates, leaving behind a product which contains about 5% calcium, 5% sulphur and 25% reducing sugars (mainly pentose) with a pH of around 3.5 (King, 2005). 26.7.14 Lignosulphonate is not corrosive and is also highly water soluble (King, 2005). It is commonly used as animal feed pellet binder and also as an ingredient in micro nutritionist formulations of agricultural products (King, 2005). The only known negative environmental effect associated with the use of lignosulphonate is the depletion of dissolved oxygen levels in water (King, 2005). Water microbes will feed on the wood sugar and consume oxygen in the process (Adams, 1988). This effect, however, will only be detrimental to aquatic biota if an accidental release of a large amount of undiluted lignosulphonate was to be released directly into a watercourse. The normal recommended application rate of 1.3 – 5 tons per acre therefore poses no threat with regards to surface runoff or groundwater contamination (King, 2005). 26.7.15 Upon closer investigation it was found that the majority of dust suppressant products currently available and used in Australia mainly consist of water absorbing chemicals. These chemicals are salts (calcium chloride, magnesium chloride and sodium chloride). As chloride is highly corrosive, it would explain damage to rock art in downstream locations. 26.7.16 Lignin, which is not corrosive, forms cohesive bonds to soils and clay and is very different from chlorides, which is loosely concentrated on the surface of a road from where it is easily dispersible by moving vehicles (Adams, 1988). As such, it should cause no damage to rock art. 26.7.17 Another popular type of dust suppressant, currently used worldwide, is Page 82 organic petroleum based products. These products contain heavy metals, as well as volatile organic compounds (“VOCs”) that may be dispersed into the air when the product is applied (King, 2005). VOC’s pose strong UV absorbance spectra qualities and would therefore be associated with the deterioration of painted surfaces. According to Adams (1988), the manufacture of lignin involves the process of evaporation which drives off all volatile components. Tests carried out by the CSIR on lignosulphonate in its liquid state (to be used at Vele Colliery) showed that it is completely inflammable and would therefore not release gasses like CO2, CO and SO2 into the atmosphere in the event of a fire. Vibrations from blasting 26.7.18 Blasting activities will occur a minimum distance of 5 000 m from any sites containing rock engravings and rock paintings. At these distances, vibration amplitudes from blasting will not exceed 1.0 mm/s at any of these sites at any time during mining. 26.7.19 A vibration of 1 mm/s is very low and generates very low strain on rock. Natural phenomena such as wind, temperature variations and thunderstorms will generate strain on the rock formations higher than the blast induced vibrations. Human traffic visiting the site will generate higher local vibrations than 1.0 mm/s by walking around the area. 26.7.20 Therefore, there is no risk that blasting will pose a higher risk to the sites in question than those that currently exist. Reference is made to the letter from the blasting specialist, Tony Rorke in this regard (Annexure “LC31”). Water 26.7.21 Leshika included in its report, attached as Annexure “LC23”, a response to the water related issues raised by ASAPA as follows: 26.7.21.1 a significant portion of the proposed opencast mining areas are in Page 83 areas already disturbed by present irrigation activities; 39 26.7.21.2 mining does not generate acid rain; rather it is the burning of fossil fuels which generates sulphur dioxide which dissolves in atmospheric water, causing the creation of acid, which falls to earth when it rains. There is no direct link between generation of sulphur dioxide in a particular area and acid rain in that exact area. Weather patterns will determine whether and where acid rain will fall from any particular source of sulphur dioxide. Acid rain is an area problem, not a point source problem, and covers large areas downwind of sulphur generating stacks. As no fossil fuels will be burned for Vele Colliery’s operations, there is no cause for concern regarding acid rain; and 26.7.21.3 the drop in the water table due to dewatering will not affect leaching rates. The existing water table is presently well below the rock shelters in the area. Leaching and recharge are not affected by dewatering, as rainwater will still percolate naturally to the water table. 26.8 26.8.1 Re 9.3.2.2 Stone Age The sites that will be directly impacted by mining activities are discussed above. 26.8.2 The criticism by the Appellant in these paragraphs is focused on the fact that the HIA Study was insufficient in a number of respects, as Stone Age sites may have been overlooked and that a Stone Age specialist was not include in the HIA team. 26.8.3 It is true that Stone Age is not Frans Roodt’s field of specialist study. However, as discussed below, Roodt is a qualified Principal Inspector and, as is set out above, is an experienced heritage practitioner who has undertaken approximately 500 Phase 1 assessments. 39 See Figure 3.2 of the Groundwater Study Page 84 26.8.4 Frans Roodt holds a master degree in archaeology, with specialisation in Iron Age studies. 26.8.5 He has undertaken more than 500 Phase 1 HIAs. His ability to conduct these surveys is derived not from his specialisation in Iron Age sites but also from his wide experience in a range of heritage contexts; and identification of potential heritage sites from a visual inspection of the site. 26.8.6 In this regard, he is registered with ASAPA as a Principal Investigator. According to the ASAPA, the requirements for a Principal Investigator are: “A Masters degree in archaeology and; a) proof of three years full time CRM practice, b) a portfolio of five phase II projects at Field Director level; or (c) a clear, detailed motivation and a portfolio of relevant projects of prior learning or (d) relevant experience of equal value to the above submitted with the application.” (See the Guideline document attached marked “LC27”.) 26.8.7 Based on his years of experience Frans Roodt has the ability to recognise most forms of heritage resources, including spiritual/ritual evidence (even if only derived from environmental evidence). 26.8.8 Frans Roodt has in past surveys noted and recommended further Phase 2 Assessments for recorded Stone Age remains. For example: 26.8.8.1 Mining development on the farm Maandagshoek 254 KT, Tubatse municipal area, Sekhukhune District: March 2006; 26.8.8.2 Phase 1 archaeological impact assessment report (scoping): Anglo Platinum mine – Polokwane sewerage effluent pipeline, Northern Province. 26.8.9 In both cases he recommended further work that was performed by a Stone Age specialist. 26.8.10 In the context of a Phase 1 Assessment, the recognition of Stone Age Page 85 remains and Stone Age bearing gravels is what is important and not their detailed analysis. It is only during a subsequent Phase 2 Assessment that the specialised knowledge of a Stone Age specialist would be required to precisely identify all of the relevant details regarding a site which was demarcated during a Phase 1 assessment. 26.8.11 An archaeological site can generally be identified in terms of man-made features; structures; other cultural material and eco-fact; and deposits resulting from past human activities or induced by past human activities. One Stone Age flake or one pot shard does not constitute a site. At Vele Colliery, Stone Age material was noted where eroded gravels were exposed, as is commonly found all over much of South Africa. During the initial walkover survey no concentration of material was recorded, especially in the opencast mining area or infrastructure area, because the material was scattered over large areas (as was mentioned in the report). 26.8.12 The Appellants’ criticism lies in the fact that only three Stone Age recordings are contained in the report, namely Sites 20, 21 and 22. This is because it was where there were noticeably identifiable objects, in particular: 26.8.12.1 Site 20 is located on a hill and probably constitutes a proper archaeological site; 26.8.12.2 Site 21 records an incomplete Early Stone Age hand axe that was exposed in gravels. As one would naturally expect, it not to be in complete isolation in the gravels, it can therefore be postulated that it constitutes a site; and 26.8.12.3 Site 22 was the location of a complete Early Stone Age cleaver that was found on the surface in an area that is not eroded and was probably transported there in some way. This does not constitute an archaeological site. 26.8.13 As stated above, scattered Stone Age bearing gravels were noted in areas where there will be opencast mining or infrastructure impacts. It is emphasised that the fact that these occur does not necessarily imply that Page 86 it is a “site”. This can only be determined during further assessments and excavations. Because of this, it was recommended that a Stone Age specialist be engaged when topsoils are removed. Should it become apparent that there is sufficient Stone Age material exposed during such monitoring, a Stone Age specialist will conduct a further study in that area. 26.9 26.9.1 Re 9.3.2.3.5 Inadequacy of HIA and mitigation measures The actual sites that will be impacted directly by the Vele Colliery are set out in the response to paragraph 9.3.2.1 above. 26.9.2 It is reiterated that in the context of a Phase 1 Assessment, the recognition of historical remains is what is important and not their detailed analysis. It is only during a subsequent Phase 2 Assessment that the specialised knowledge of for example Stone Age specialist would be required to precisely identify all of the relevant details regarding the site which was demarcated during the Phase 1 assessment. 26.9.3 Chance finds of archaeological sites or remains happen often, even after thorough searching. For this reason, all areas where any mining activity is to take place will be re-inspected before mining commences, to ensure that no undetected site or remains have been missed and to implement heritage resources management measure for any sites/remains. 26.9.4 This recommendation forms part of the Heritage Management Plan submitted to SAHRA. Reference is made to the Heritage Management Plan (Annexure “LC28”). 26.9.5 The Company has committed to the appointment of an archaeologist to monitor all areas to be disturbed on an ongoing basis. In addition, allowance has been made for Phase 2 Assessments, in line with the Heritage Management Plan developed for Vele Colliery (see Annexure “LC28”). 26.9.6 The immediate, short, intermediate and long-term management actions are described below. Page 87 Immediate actions 26.9.7 Protection: During the HIA a number of heritage sites were identified; however, only two sites (Sites 5 and 18) will be affected by the immediate actions at Vele Colliery. As stated above, these sites will be fenced off and enough provision will be made for the subterranean or ‘unseen’ deposits. Short-term actions: Year 1 - 2 26.9.8 Phase 1B Assessment: Phase 1B Assessments will be implemented, in co-operation with SAHRA. These assessments will commence as soon as a permit is obtained from SAHRA. Test pits will be conducted at Sites 5 and 18 to determine the need for Phase 2 Assessments at these sites. 26.9.9 Intangible Heritage: An Indigenous Knowledge Systems specialist will be consulted and allowed the opportunity to gather data from relevant stakeholders. 26.9.10 Recent Historical Background: Information regarding the recent historical period will be researched. The old mining activities on Bergen Op Zoom dates from the 1970’s, but will not be directly affected by the mining. 26.9.11 Iron Age: To ensure that all Iron Age occupation sites or signs of previous land use practises were recorded during the initial survey, additional surveys will be conducted; 26.9.12 Rock Art: Although no signs of rock art were discovered during the initial survey or the additional specialist studies conducted by the Company, attention will again be given to rock faces and shelters, to ensure that none were missed during these surveys. If any are found, a rock art specialist from the Rock Art Institute will be commissioned, to assess these finds and implement mitigation management measures. 26.9.13 Stone Age: A Stone Age specialist will be commissioned to assess the Stone Age bearing gravels. Most of these are not in the area of initial Page 88 development and will be phased in. Intermediate actions: Year 2 - 5 26.9.14 Protection: sites that are not directly threatened by the initial mining will be protected and assessed. 26.9.15 Phase 1B Assessments: Phase 1B Assessments (test pits) will be implemented at sites that may be threatened by the expansion of the mining operations. 26.9.16 Phase 2 Assessments: Phase 2 assessments will be implemented at Sites 5 and 18, if the Phase 1B Assessments indicate the need for further work. Long-term actions (Year 5 onwards): 26.9.17 Protection: Sites that may in the long term be threatened by any activity relating to the mining development will be protected. 26.9.18 Phase 2 Assessments: Phase 2 Assessments will be implemented at sites that may be affected by mining expansions; or where the Phase 1B Assessments indicated the need for further work. 26.9.19 Phase 3 Site Management Plan: A Phase 3 Site Management Plan will be developed and implemented to ensure the protection of sites that will not be affected by mining related activities. 26.9.20 As stated above, The Company has submitted the proposed Heritage Management Plan to SAHRA; however, no feedback has been received from it. 26.9.21 Sufficient budget has been allowed by the Company for environmental and heritage aspects, amounting to R19.1 million per annum. Over the life of the mine this commitment adds up to almost R500 million. Page 89 26.10 Re 9.3.3 and 9.3.4 Intangible heritage resources 26.10.1 The Company is aware and understands that the area has cultural significance; this is dealt with in the HIA Study, as well as the EMP. However, the intangible heritage set out in the EMP Appeal is generic, as it reflects a value appraisal devoted to the entire “Mapungubwe cultural landscape” by affected Communities. There are no specific places within the mining area that they relate to; otherwise it would have been mentioned by the affected Communities during the public participation process. It therefore clearly cannot be contended that the Communities have “deep felt connections” to intangible heritage connected with the mining area. As discussed above, neither the relevant legislation nor SAHRA’s 26.10.2 guidelines require that the heritage specialist should have himself conducted consultations with the Community. These consultations were undertaken during the public participation process. The information obtained through this process was utilised by the heritage specialist for the purposes of his report. Reference is made to paragraph 26.1.12 and 26.1.13 above. The Appellants’ contend that oral traditions and indigenous knowledge 26.10.3 should be utilised to investigate the impact of the mining on intangible heritage. The Company agrees that further information can be obtained to supplement the HIA. Further work in this regard has therefore been proposed in the Heritage Management Plan submitted to SAHRA (See Annexure “LC28”). However, based on the information obtained to date in the public participation process, it cannot be contended that the Vele Colliery will impact on intangible heritage values. 26.11 Re 9.3.5 Sense of place Please refer to the General discussion and the response to paragraph 9.3.1 above. Page 90 26.12 Re 9.3.6 Destruction of heritage resources 26.12.1 Please refer to the response in respect of paragraphs 9.3.1 and 9.3.2.1 above. 26.12.2 With respect to the allegation that a “piecemeal approach” we repeat that the HIA Study fulfilled the requirements of a Phase 1 Assessment, as stipulated in the SG 2.2 SAHRA APM Guidelines: “Minimum Standards for the Archaeological & Palaeontological Components of Impact Assessment Reports”. 27. 27.1 This appeal should be dismissed For the reasons set out above, this appellant has not set out grounds for the mining right to be set aside. 27.2 The appeal should accordingly be dismissed. VI. PEACE PARKS FOUNDATION APPEAL SUBMISSION 28. General comments on the Appeal 28.1 28.1.1 I&APs in the Public Participation Process This organization was an I&AP in the public participation process described in paragraph 5.2 above. 28.1.2 All comments provided in the I&AP process were responded to. 28.1.3 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the EMP approval. 28.2 28.2.1 PPF is also an Appellant in the EMP Appeal PPF has also appealed against the decision to approve the EMP. Page 91 28.2.2 As discussed below, a large majority of issues in this appeal raise grounds that centre on the EMP and the adequacy of the EMP. 28.2.3 It is reiterated that the decision to approve the EMP should not be confused with the decision to approve the mining right and these issues should be ignored for the purposes of this appeal. 28.3 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 28.4 28.4.1 TFCA The PPF premises its submission on a purported TFCA, which it says would be impacted by the Vele Colliery. As described above, this is extremely misleading. The TFCA which has been envisaged, known as the Greater Mapungubwe TFCA, did not incorporate the area in which the Vele Colliery is situated. 28.4.2 The supposed new TFCA, upon which the PPF now relies, would incorporate land on which the Vele Colliery, not to mention other mining and agricultural activities are currently undertaken. This new vision of the TFCA is at best highly aspirational. No key role players have consented to it and no steps have been taken to bring it into being. 28.4.3 Accordingly, it is unfortunate that the PPF should use the notion of this new TFCA to attempt to block the Vele Colliery, when the true challenges lie in bringing the initial TFCA into being, a task which is itself only in its early stages. We refer further in this regard to what is set out in paragraph 19.2 above, and to the maps which indicate the envisaged Greater Mapungubwe TFCA. Page 92 29. 29.1 29.1.1 Specific responses to the appeal submissions made by the Appellant Re paragraph 9.3.1 Impact on Transfrontier Conservation Area Please see the response in the MAG response in paragraph 19.2 above, as well as the response in paragraph 19.1 regarding the sense of place. 29.1.2 In addition, it is denied that the mine is located on the “Main Entrance” to the proposed TFCA. 29.1.3 It is denied that the approval of the mine should have any international implications. The mine is not located in the TFCA; and there is a coal mine directly opposite the Vele Colliery in Zimbabwe. Conspicuously, the Appellant’s submission entirely omits reference to these fundamental facts. It is submitted that these omissions of crucial facts cast doubt on the balance of the appeal. 29.1.4 South Africa’s international treaty obligations are given effect to through national legislation and other similar acts of domestication. South Africa’s environmental and mining legislation requires extensive environmental assessment. Legislation such as the Biodiversity Act go a lot further to domesticate South Africa’s international treaty obligations regarding the environment than is found in neighbouring countries or even in most developed countries. 29.2 Re paragraph 9.3.2: Direct impact on water availability Detailed specialist studies have been undertaken to study any potential impacts and ensure mitigation of such impacts. The impact on neighbouring states has been considered in these assessments. Please refer to Surface Water Study and Groundwater Study (submitted with the EMP as Annex-D and Annex-E respectively). Page 93 29.3 Re paragraph 9.3.3: Cumulative impact on water availability Cumulative impacts have been referred to in the EMP. 40 The difficulties with undertaking an assessment of developments that are not yet even planned have been discussed in the EMP. The Company’s application must be considered on its own merits. 29.4 Re paragraph 9.3.4; Impact on water quality Leshika provided the following comments to the contentions raised by PPF in this paragraph, the mine will: 29.4.1 use less water than the existing irrigation; and 29.4.2 not impact on quality, as it will act as a sink during mining, containing all potential pollutants. Only many years after mining stops is there a possibility of decant. This decant will need to be monitored and treated in an environmentally friendly way before being discharged. The decant is not expected to be acidic but will have an increased salt load. The natural salt content of the Karoo aquifer in the area is also very high; thus the impact is expected to be minimal. 30. 30.1 This appeal should be dismissed For the reasons set out above, this appellant has not set out grounds for the mining right to be set aside. 30.2 40 The appeal should accordingly be dismissed. Page 146 of the EMP Page 94 VII. BIRDLIFE SOUTH AFRICA APPEAL SUBMISSION 31. General comments on the Appeal 31.1 31.1.1 I&AP in the Public Participation Process This organization was an I&AP in the public participation process described in paragraph 5.2 above. 31.1.2 Birdlife however appears to have chosen not to submit any comments in this process. 31.1.3 It has chosen instead to now submit an extensive submission, in which it sets out its perspective on avifauna in the area. 31.1.4 As set out above, the I&AP process followed allowed all parties more than sufficient time and opportunity to make their comments. Birdlife did not express any need in that process for more time to make its comments. 31.1.5 Nevertheless, Birdlife appears to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 31.1.6 At no time has this Appellant suggested actions on the part of the Company which may have prevented it from timeously submitting its reviews in the I&AP process. There were no such actions by the Company which reflect that it did not comply conscientiously and properly in the authorisation process. 31.1.7 We submit that there were no such actions by the Company and, as such, this Appellant should not be given the opportunity to include these criticisms now. The introduction of new allegations for the first time on appeal is highly prejudicial to the Company and the decision-makers; and undermines the statutory process which is intended to ensure that all relevant material is ventilated during the I&AP process. Page 95 31.2 Birdlife is also an Appellant in the EMP Appeal 31.2.1 Birdlife has also appealed against the decision to approve the EIA/EMP. 31.2.2 As discussed below, a large majority of issues in this appeal raise grounds that centre on the EMP and the adequacy of the EMP. 31.2.3 It is reiterated that the decision to approve the EMP should not be confused with the decision to approve the mining right and these issues should be ignored for the purposes of this appeal. 31.3 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 32. 32.1 Response to the appeal submissions made by the Appellant The issues raised in this section do not relate to “unacceptable pollution, ecological degradation and environmental damage” and accordingly should be ignored for the purposes of this appeal. 32.2 In this Appeal and supporting report by Tembele Ecological Services annexed to the Appeal, no reference is made to the mining right application or to the actual studies done for the EMP or any deficiencies in these. It contains interesting information on birdlife in the area around Vele Colliery but is not directly relevant to the EMP Appeal. 32.3 While Birdlife states that it was an I&AP, it was obviously represented through individuals who did not state their affiliation to Birdlife. Birdlife did not make any comments on the EMP. 32.4 Furthermore, this section comprises almost entirely new comments that have not previously been made. Accordingly, they should be dismissed for the purposes of the appeal. Page 96 32.5 The large number of bird species set out in this Appeal is acknowledged. That a total of 470 bird species frequent MNP is, however, not unexpected because of the range of habitat provided through the interface of the western and eastern sub-regions; migratory routes; the importance of riverine (canopy) habitat along the Limpopo and alluvial zones; and the provision of large man-made impoundments. It is a relatively large area of 25 km radius from the main entrance to the MNP and the area is an interface of southern and northern subregions and forms. With the range of habitat provided by MNP and its geographical position, it would be unusual for it to record fewer species. Checklists of bird species are built up over many years; the list presented by Birdlife is obviously a list that has been documented over many years by many birding enthusiasts. 32.6 It must however be noted that only part of the westernmost reach of the mine is located within 25km from the main entrance to MNP, a lot of this western area is presently intensively cultivated and the mine is not included in the Birdlife South Africa Important Bird Area (SA 001 Vhembe Nature Reserve) as is alleged in paragraph 9.3.1 of the Appeal. As is discussed below, there is a real difference in terrain and habitat in the mine area as opposed to the MNP area. There is no indication of how many of the named species have been seen in the area of the Vele Colliery itself; or the cultivated lands that will be mined to the west of the Colliery. 32.7 The occasional records of rare vagrant species over the past number of years are not unexpected. The provision of large man-made impoundments is attractive to the named species, and many records of vagrants have been recorded in numerous areas, as a result of weather patterns and fluctuating food levels. 32.8 The Vele Colliery area does not offer the same range of habitat as MNP. In comparison, the rock-faces (koppies) at the Vele Colliery and the extent of riverine vegetation are insignificant compared to MNP. Similarly, there are no comparable wetlands. It would be highly unlikely that the same number of species would be recorded at the Vele Colliery. . 32.9 This riparian forest and associated plant communities on the Farm Overvlakte Page 97 has been already degraded, as have most of the farms west and east of MNP. (In this regard we refer to the report of Gerhard De Beer attached marked “LC32”). As rehabilitation at Vele is progressed and less water is abstracted from the boreholes (than is presently abstracted for farming) an increase in bird activity will be expected. 32.10 In view of the fact that the Venetia Mine is situated where it is, it is interesting that a total of 470 bird species have been recorded in the area. The impact of that mine, despite its lights, noise and habitat destruction, has obviously not had a significant negative impact on avifauna. 32.11 Venetia is a diamond mine which has much greater lighting needs than a coal mine. Vele Colliery will have a much smaller area working face at any one time than Venetia and its lighting will be minimal compared to Venetia. 32.12 The Company has implemented a programme of monitoring of bird species recorded at Vele. Surveys are conducted by knowledgeable bird enthusiasts in different areas of varying habitat, which represent the entire range of habitat of the area. To maintain consistency, the same observers are used. Results, as recorded per “pentad”, are forwarded to the Avian Demographic Unit, as part of the Bird Atlas Programme. Dubious or unlikely records are omitted until confirmed by further observation. 32.13 It seems highly unlikely that the Vele Colliery will have any noticeable effect on the number of bird species occurring in the area, or on population numbers. On the contrary, the reclamation of riverine habitat and the potential of artificial water impoundment 41 will likely increase local records of bird numbers and species. 32.14 Mitigation measures as committed to in the EMP will further reduce the impact on birdlife. These include: 32.14.1 development of air blast control measures; 32.14.2 implementation of noise reduction measures; 32.14.3 use of directional or cut-off type luminaries to mitigate light pollution; 32.14.4 limiting speed of truck haulers; 32.14.5 ongoing rehabilitation of disturbed areas; 41 See section 21.6 of the EIA/EMP. Page 98 32.14.6 development of a biodiversity management plan; 32.14.7 closed system for recycling of dirty water to prevent any water quality impacts; 32.14.8 rehabilitation of riverine forest and floodplain as part of off-set programme; and 32.14.9 32.15 ongoing environmental monitoring programme. It is further important to note that the area in question is not pristine as implied. The impact of water abstraction, agriculture, security fence and elephants has impacted on the biodiversity, which also would have had a large impact on the natural bird population prior to 1979. This is also applicable on any other development in the area (We again refer to the De Beer report attached marked “LC32”). 32.16 The impacts of habitat destruction on birdlife were addressed in the EMP. Detailed species lists have been provided in the Biodiversity Study. 33. 33.1 This appeal should be dismissed For the reasons set out above, this appellant has not set out grounds for the mining right to be set aside. 33.2 The appeal should accordingly be dismissed. VIII. WORLD WILDLIFE FOUNDATION OF SOUTH AFRICA 34. General comments 34.1 No indication has been given by WWF why it has chosen now to join an appeal brought by participants in the initial I&AP process. It makes no effort to distinguish itself from the majority of the Appellants who were all involved in that process nor to indicate why it is involved in the Appeal but was not involved in the I&AP process. It has put its appeal submissions on an identical template with the I&AP participants and, as such, has shown itself to have a common cause with those Appellants. Accordingly, we do not believe there can be any basis to distinguish between the Appellants. Page 99 34.2 As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. 34.3 Nevertheless, the WWF appear to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 34.4 At no time have WWF given an indication of what actions of the Company prevented it from timeously submitting a review in the I&AP process. They also give no indication why the comments they present now were unavailable to them at the time they could have provided their comments and review of the EMP and participated in the I&AP process conducted. Nor why they did not initially participate. 34.5 We submit that there were no such actions by the Company and, as such, the Appellants should not be given the opportunity to include these criticisms now. 34.6 WWF is also an Appellant in the EMP Appeal 34.6.1 WWF has also appealed against the decision to approve the EIA/EMP. 34.6.2 As discussed below, a large majority of issues in this appeal raise grounds that centre on the EMP and the adequacy of the EMP. 34.6.3 It is reiterated that the decision to approve the EMP should not be confused with the decision to approve the mining right and these issues should be ignored for the purposes of this appeal. 35. 35.1 35.1.1 Specific responses to the appeal submissions made by the Appellant Re 8.3.1: Contamination of water resources Detailed specialist studies have been undertaken to study any potential impacts and ensure mitigation of such impacts. The impact on Page 100 neighbouring states has been considered in these assessments. 35.1.2 42 It is reiterated, as stated in paragraph 1.3.4.3 of the EMP, “a closed system is being designed whereby all water is recycled for use in the process”. No dirty water will be discharged into any stream or river during the operational phase and thus no treatment is required. 35.1.3 Reference is also made to the response to the EWT contention that the Vele Colliery will impact on the water quality, as set out paragraphs 23.4 to 23.8 above. 35.1.4 The Leshika Response (Annexure “LC23”) included comments to the contentions raised by WWF. In particular the following was stated: 35.1.4.1 the potential for contamination was investigated and the concern was found to be unfounded; 35.1.4.2 tailings, that could generate sulphates and acidity, will be disposed in the bottom of the pits; hence leachate will not be able to enter surface water courses. 35.1.4.3 further, during mining the mining areas will act as sinks with flow towards the pits; thus preventing flow downstream and thus potential contamination; and 35.1.4.4 post mining, these tailings will be submerged below the water table, hence will not be oxidized. It is only when rock containing sulphates is exposed to oxygen that acid can arise. Submerging such rock is an accepted method for avoiding acid mine drainage. 43 35.2 35.2.1 42 43 Re 8.3.2: Impact on the tourism in the area While we do not believe that there is any evidence of “unacceptable Pages 7 – 63 of the EIA/EMP and the Surface Water Study. Refer to section 5.5 of the Groundwater Study Page 101 pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 35.2.2 The potential impact on tourism has been considered in the MEA Study. It is reiterated that the employment benefits of mining have been shown to far out strip those of tourism and the needs and wishes of all within the community must be balanced. 35.2.3 The Company repeats the response to EWT’s Appeal, set out in paragraph 23.10 above. 35.3 Re 8.3.3 Desecration of World Heritage Site and the cultural landscape of Greater Mapungubwe 35.3.1 While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 35.3.2 The Vele Colliery will be located approximately 7 kilometres from the most easterly point of MNP (attached, please see map marked “LC20”). 35.3.3 The area surrounding MNP is already characterised by mining activity – notably the Venetia Mine is located 5.8km from the southern border of MNP, which is visible from MNP, and the Tuli Colliery which is directly opposite the Vele Colliery in Zimbabwe. The 2006 Management Plan for MNP acknowledges the mineral wealth within the broader area around MNP and the need to interface the conservation uses within MNP, with the mining activities in the broader area. 35.3.4 In addition to mining activity, there is presently agricultural and related activity located in the Limpopo Valley which is also visible from MNP. Page 102 36. 36.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 36.2 The appeal should accordingly be dismissed. IX. WILDERNESS FOUNDATION OF SOUTH AFRICA 37. General comments 37.1 No indication has been given by WFSA why it has chosen now to join an appeal brought by participants in the initial I&AP process. It makes no effort to distinguish itself from the majority of the Appellants who were all involved in that process nor to indicate why it is involved in the Appeal but was not involved in the I&AP process. It has put its appeal submissions on an identical template with the I&AP participants and, as such, has shown itself to have a common cause with those Appellants. Accordingly we do not believe there can be any basis to distinguish between the Appellants. 37.2 As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. 37.3 Nevertheless, the WFSA appear to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 37.4 At no time have WFSA given an indication of what actions of the Company prevented it from timeously submitting a review in the I&AP process. It also give no indication why the comments it presents now were unavailable to it at the time it could have provided its comments and review of the EMP and participated in the I&AP process conducted. Nor why it did not initially participate. 37.5 We submit that there were no such actions by the Company and, as such, the Appellant should not be given the opportunity to include these criticisms now. Page 103 37.6 WFSA is also an Appellant in the EMP Appeal 37.6.1 WFSA has also appealed against the decision to approve the EMP. 37.6.2 As discussed below, a large majority of issues in this appeal raise grounds that centre on the EMP and the adequacy of the EMP. 37.6.3 It is reiterated that the decision to approve the EMP should not be confused with the decision to approve the mining right and these issues should be ignored for the purposes of this appeal. 38. 38.1 Specific responses to the appeal submissions made by the Appellant Re 8.3.1: Potential loss of biodiversity A Biodiversity Study was undertaken (Annex-C to the EMP). The area is not one of the areas protected in terms of the Biodiversity Act, nor is it located in one nine broad priority areas for conservation action, which were identified in the National Spatial Biodiversity Assessment (“the NSBA”) published in 2005 by the South African National Biodiversity Institute (“SANBI”) and supported by DEAT. These Priority Areas are now included in the National Biodiversity Framework (“NBF”) which was published in 2009 in terms of section 39 of the Biodiversity Act. 44 A number of biodiversity offset programmes are included in the EMP to mitigate any impact on biodiversity. 45 38.2 Re 8.3.1: Loss of wilderness character of protected areas Please see the response on sense of place in the MAG response in paragraph 19.1 above. 38.3 38.3.1 Re 8.3.1: Impact on World Heritage Site While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is 44 45 Government Gazette No 32474 in Government Notice 813 dated 03 August 2009. Page 5 of the EMP. Page 104 completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 38.3.2 38.4 38.4.1 Please see the response to MAG in paragraph 19.1 above. 8.3.1: Potential Impact on other World Heritage Sites around the country While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 38.4.2 No justification is given for this fairly farfetched concern. No such impact is foreseeable. XI. THE GA-MACHETE ECONOMIC DEVELOPMENT CORPORATION /SOUTHERN CROSS EXPERIENCES (PTY) LTD 39. 39.1 39.1.1 General comments on this Appeal I&APs in the Public Participation Process This organization was an I&AP in the public participation process described in paragraph 5.2 above. 39.1.2 All comments provided in the I&AP process were responded to. 39.1.3 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the EMP approval. 39.2 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to Page 105 this ground and accordingly should be ignored for the purposes of this appeal. 40. 40.1 Specific responses to the appeal submissions made by the Appellant General We note that in this submission the Machete representatives do not mention the allege land claim that has been lodged over the Vele Colliery area which is dealt with in the MAG submission (see paragraph 19.5.3 above). We must assume that this land claim, which was brought outside of the statutory time period and which appeared baseless, is no longer being pursued. 40.2 40.2.1 Re 9.3.1: Threat to Mega Eco Cultural Tourism Initiative While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 40.2.2 Please see the response in the MAG response in paragraph 19.2 regarding the impact on the TFCA and the reply to the EWT’s Appeal, set out in paragraph 23.10 above. 40.3 Re 9.3.2: Noise pollution and Visual Destruction Please see the response in the MAG response above regarding the Sense of Place in paragraph 19.1.1.above. 41. 41.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 41.2 The appeal should accordingly be dismissed. Page 106 XI. BREGJE DAWSON/KNOLL INVESTMENTS LTD 42. General comments on this Appeal 42.1 42.1.1 I&APs in the Public Participation Process This organization was an I&AP in the public participation process described in paragraph 5.2 above. 42.1.2 All comments provided in the I&AP process were responded to. 42.1.3 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the mining right. 42.2 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 43. 43.1 Specific responses to the appeal submissions made by the Appellant Re 9.3.2: Impact of Mining on Air Quality A detailed Air Quality Study has been done. Reference is made to the Air Quality Study (included in the EMP as Annex-F). 43.2 Re 9.3.3 Problem with greenhouse gases, acid rain and ground level ozone The impacts which are discussed in this section are associated with industries that utilize coal, rather than coal mines. 43.3 43.3.1 Re 9.3.4 Impact of Coal Fires Spontaneous combustion normally goes with old, abandoned mine sites and dumps. The Company has applied normal process and mitigation Page 107 planning in the EMP so as not to cause this. 43.3.2 It is in the Company’s interests to get the coal to market as soon as possible after being mined and washed. The coking qualities reduce if exposed for a period of time. The coal will therefore not remain on the mining area for an extended time period and the risk of spontaneous combustion is low. 43.3.3 Mitigation measures such as cladding of stockpiles have been considered during the engineering design of the mine. In the unlikely event that spontaneous combustion does occur, the necessary mitigation measures will be implemented in accordance with the emergency plans. 43.4 Re 9.3.5: Impact of Mining on Water regime and disturbance to hydrologic regime 43.4.1 A detailed study of groundwater has been done. Reference is made to the Groundwater Study (included in the EMP as Annex-E). 43.4.2 Reference is also made to the response to EWT contention that the Vele Colliery will impact on the water quality and quantity, as set out paragraphs 23.1 to 23.8 above. 43.5 Acid Mine Drainage The Company refers to what is stated in response to the EWT appeal in respect of AMD in paragraph 23.5 above 43.6 Impact of Mining on Land Existing land use and land capability was addressed in detail in the Soil Study (Annex-B to the EMP). The impact of mining on land use and fauna and flora was extensively addressed in the Soil Study and Biodiversity Study (Annex-C to the EMP) and the EMP. 46 46 Section 2.2.6.1, page 113 of the EIA/ EMP Page 108 43.7 Impact of Noise and Vibrations from Mining A detailed Noise Study and Blasting Study have been done. . Reference is made to the Noise Study and the Blasting Study (included in the EMP, as AnnexG and Annex K respectively). 44. 44.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 44.2 The appeal should accordingly be dismissed. XII. DGR TRUST 45. General comments on this Appeal 45.1 I&APs in the Public Participation Process 45.1.1 This organization was an I&AP in the public participation process described in paragraph 5.2 above however did not submit comments. 45.1.2 All comments provided in the I&AP process were responded to. 45.1.3 Accordingly, these comments already made and responded to do not provide any grounds for setting aside the EMP approval. 46. Specific responses to the appeal submissions made by the Appellant No substantiation is given for the impacts listed and nothing has been done to substantiate a claim of “unacceptable pollution, ecological degradation and environmental damage” and accordingly this appeal should be ignored. 46.1 Re 9.3.1: Avifauna While the heading is “Avifauna” the issue appears to relate to animal and plant Page 109 life in general. In this regard, reference is made to the detailed Biodiversity Study which has been undertaken (included in the EMP, as Annex-C). In addition, a number of biodiversity offset programmes are included in the EMP to mitigate any impact on biodiversity. 47 46.2 Re 9.3.2: Archeological resources Archeological resources are alleged to be eliminated forever. In this regard reference is made to the HIA Study (included in the EMP as Annex-H), which has been undertaken to identify all affected heritage resources and to mitigate any impact. Presently only 4 sites will be directly impacted by mining activities over the whole life of mine. 46.3 Re 9.3.3: Cultural Resources 46.3.1 An allegation is made regarding cultural resources - that the opportunity to study relics will be lost forever. Again reference is made to the HIA Study (included in the EMP as Annex-H). 46.3.2 A lack of respect for the process laid down in law is alleged but no details of the basis for this allegation are provided and it is denied. 47. 47.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 47.2 The appeal should accordingly be dismissed. XIII. JM AND PD GRAY 48. General comments on this Appeal 48.1 I&APs in the Public Participation Process 48.1.1 47 Page 5 of the EMP. These parties were I&APs in the public participation process described in Page 110 paragraph 5.2 above. 48.1.2 The Appellants raises no new comments and only refers to two submissions that were made as part of the EMP process, namely: 48.1.2.1 the South African Archeological Society comments dated 9 July 2009 – these were addressed in the Issues & Response Register submitted to the DMR on 20 August 2009. Thus the authority had this during decision-making. 48.1.2.2 individual comments by Mrs. and Mr. Gray dated 13 August 2009. This was received by Naledi Development on approximately 24 August 2009. This was well beyond the deadline of 30 July 2009 for the processing of comments and after the Responses List had been provided to the DMR. As such, no consideration could be given to this late submission. In addition, upon considering the submission, it was apparent that no new issues were raised that were not addressed previously. This was communicated by telephone to the Appellants by Naledi Development at the time. 49. 49.1 Specific responses to the appeal submissions made by the Appellant The letter of the South African Archaeological Society 49.1.1 The essential allegation is that a “full” HIA has not been undertaken. 49.1.2 A Phase 1 Heritage Assessment was performed in line with the Directions for the compilation of HIA are set out in SG 2.2 SAHRA APM Guidelines the: “Minimum Standards for the Archaeological and Palaeontological Components of Impact Assessment Reports”. These Guidelines are attached as (Annexure “LC27”). The HIA Study clearly complied with this Guideline in assessing the impact of the Vele Colliery on heritage resources. 49.1.3 The report refers interchangeably to the MNP and the broader Mapungubwe cultural landscape. It is only the area of the MNP that has been given World Heritage Status under the name “Mapungubwe Cultural Page 111 Landscape”. The Mapungubwe cultural landscape is in fact an extensive area and could have stretched as far as Musina in the east. 48 The latter has not been declared a protected area under the Protected Areas Act; the World Heritage Convention Act 49 of 1999 or Biodiversity Act. It would be clearly inconceivable to prevent development in areas that fall within the Mapungubwe cultural landscape, which in any event already incorporates large towns, widespread agricultural activity, as well as existing mines, including coal mining on the Zimbabwean side directly opposite Vele. 49.1.4 Heritage resources have been identified during the mining right application in the HIA Study. None will be disturbed without the requisite permits. Only 4 of the sites identified are likely to require removal for mining operations to proceed. 49.1.5 During the mining operations, further heritage surveys of all areas to be disturbed will be conducted. Areas where there is any doubt regarding the presence of heritage resources, will be disturbed in a slow and systematic manner, with a suitable heritage specialist present. This will in fact assist with documenting and understanding the heritage of the area. 49.1.6 This recommendation forms part of the Heritage Management Plan submitted to SAHRA. Reference is made to the Heritage Management Plan (Annexure “LC28”). 49.1.7 The Company has committed to the appointment of an archaeologist to monitor all areas to be disturbed on an ongoing basis. In addition, allowance has been made for Phase 2 Assessments, in line with the Heritage Management Plan developed for Vele Colliery (see Annexure “LC28”). 49.2 49.2.1 The letter of 13 August 2009 Heritage (Reasons 1, 2, 5, Observations 2, 4, 5) See the response above. 48 Page 6 of the HIA Study Page 112 49.2.2 49.2.2.1 Greater Mapungubwe TFCA (Reason 4) On 23 January 2009 in a meeting with, amongst others, the DEAT, SANParks and PPF, representatives of Limpopo Coal were provided with a MOU between South Africa, Botswana and Zimbabwe in respect of the Limpopo/Shase Transfrontier Conservation Area. The map attached to the MOU does not include the area of the Vele Colliery. 49.2.2.2 The Company has put forward its belief, based on the EIA it has undertaken, that its activities can co-exist with other land uses in the area and has frequently expressed its willingness to engage regarding this. 49.2.3 Impact on biodiversity and land use / Vhembe Biosphere (Reasons 3, 6, 7, 9 Observation 13) 49.2.3.1 A Biodiversity Study has been undertaken (Annex-C to the EMP). The area is not one of the areas protected in terms of the Biodiversity Act, nor is it located in one nine broad priority areas for conservation action, which were identified in the NSBA published in 2005 by SANBI and supported by DEA. These Priority Areas are now included in the NBF, which was published in 2009 in terms of section 39 of the Biodiversity Act. 49 A number of biodiversity offset programmes are included in the EMP to mitigate any impact on biodiversity. 50 49.2.3.2 The Company’s experts believe it may be possible to restore Mopane. The Biodiversity Study (Annex-C of the EMP) addresses the difficulties of vegetation restoration in arid areas (see page 67). As stated above, page 69 of the Biodiversity Study refers to the research on vegetation restoration in arid areas, and specifically in the Limpopo River Valley by the Northwest University. 49 50 The research reflects that mine rehabilitation in Government Gazette No 32474 in Government Notice 813 dated 03 August 2009. Page 5 of the EIA/EMP. Page 113 Mopani veld in the Limpopo River Valley can be done successfully. 49.2.3.3 A number of biodiversity offset programmes are included in the EMP to mitigate any impact on biodiversity. 51 One of the biodiversity offset programmes the Company will pursue will be to restore riverine forest where this has been damaged by misuse in the past. 52 49.2.3.4 It is further important to note that the area in question is not pristine as implied - see the impact of water abstraction, agriculture, security fence and elephants on the biodiversity in the larger area. This is also applicable on any other development in the area. (Please refer to the attached De Beer Report marked “LC32”) 49.2.3.5 The Company committed that a detailed rehabilitation plan will be developed for the mine at the commencement of mining. The rehabilitation plan will undergo an annual review, or whenever there is a major change in mine scheduling. The prolonged rehabilitation measures will be designed to ensure this impact is as brief as possible. 49.2.3.6 Commitments were made by the mine for the establishment of animal corridors; and for management agreements with adjacent landowners to limit these impacts. .53 The rescue plan further not only addressed the flora in the area, but also looks at the relocation of fauna, to limit the impact of mining. 49.2.3.7 Sufficient budget has been allowed by the Company for environmental and heritage aspects, amounting to R19.1 million per annum. Over the life of the mine this commitment adds up to almost R500 million. 51 Page 5 of the EIA/EMP. Page 5 of the EIA/EMP. 53 Page 115 of EIA/EMP 52 Page 114 49.2.4 49.2.4.1 Impact on agriculture (Observation 3) Due to the combined mining method of opencast and underground mining, the mining activities will have a limited impact on the current agricultural activities, which lead to a positive scenario of co-existence between the two land uses. Only approximately 8% of the existing agricultural lands will be impacted over the life of mine as mining progresses. 49.2.4.2 The impact of mining on neighbouring farmers will be continuously monitored and mitigation measures are in place to ensure no adverse impacts occur. 49.2.4.3 The Company maintains that its use can co-exist with other existing uses in the area. 49.2.5 Impact on water (Observations 6, 7, 8, 12, 21) 49.2.5.1 Water uses will be less than the existing agricultural allocation. 54 49.2.5.2 Detailed specialist studies have been undertaken to study any potential impacts and ensure mitigation of such impacts. The impact on neighbouring states has been considered in these assessments. 49.2.5.3 55 . It is reiterated, as stated in paragraph 1.3.4.3 of the EMP, “a closed system is being designed whereby all water is recycled for use in the process”. No dirty water will be discharged into any stream or river during the operational phase and thus no treatment is required. 49.2.5.4 The mine will not impact on groundwater quality, as it will act as a sink during mining, containing all potential pollutants. Only many years after mining stops is there a possibility of decant. decant 54 55 will need to Page 61 – 62 and 133 of the EIA/EMP Pages 7 – 63 of the EIA/EMP and the Surface Water Study be monitored and treated in This an Page 115 environmentally friendly way before being discharged. The decant is not expected to be acidic but will have an increased salt load. The natural salt content of the Karoo aquifer in the area is also very high; thus the impact is expected to be minimal. 49.2.6 Air, dust, noise, lighting impacts (Observations 9, 10, 11, 14, 20) The impacts associated with dust, noise, lighting has been dealt with in paragraph 19.1 above in detail and is not repeated here. 49.2.7 49.2.7.1 Skyline reports of infrastructure (Observation 15-19) It is completely untrue that “skyline” reports have not been performed during the EIA. 49.2.7.2 A detailed Visual Study was performed (Annex-J of the EMP), which included viewshed analyses of mining at different stages and the mining plant infrastructure. All infrastructure was included in this analyses, including the stockpiles, waste dumps, overburden dumps, washing plant, etc. 49.2.7.3 Vegetation mapping were also performed to determine the visual absorption capacity of vegetation. . 56 49.2.7.4 A photographic simulation of the possible exposure to a waste rock dump of the west pit was also done. 57 49.2.8 49.2.8.1 Impact on Palaeontology (Observation 23) Clear reference is made to the Palaeontology Study (Annex-I of the EMP), as well as the fact that previous studies confirmed the presence of vertebrate fossils in the area. 58 49.2.8.2 56 As mentioned in the Palaeontology Study, it was determined Section 6.5 of the Visual Study, page 17. Figure 16 of the Visual Study, page 1) 58 Also refer to section 2.4 (page 152) and Table 2.6(e) (page 163) of the EIA/EMP. 57 Page 116 during the site visit that the bulk of the Solitude and Klopperfontein Formations in the study area are covered by alluvium and nonfossiliferous formations. Although no vertebrate fossils were found in the area investigated at the time, it does not mean that there are no fossils in the layers covered by alluvium as mentioned in the Specialist Report. These layers will only be exposed when construction and mining commences. 49.2.8.3 A detailed paleontological study of the terrain would be done at a later stage. Given that no fossiliferous material was found, as the fossiliferous layers are covered by alluvium and non-fossiliferous geological strata, this will be a superfluous exercise at his stage. 49.2.8.4 Thousands of tons of material containing plant fossils are destroyed annually in the coal mines in South Africa, without SAHRA or anyone else for that matter doing anything about it. Vele Colliery could make a difference by involving a palaeontologist to salvage at least some of the plant fossils, as per the specialist’s suggestions. The commitment for the appointment of a palaeontologist has been made and the necessary funds made available. 59 49.2.9 49.2.9.1 Impact on tourism (Observation 24) The employment benefits of mining have been shown to far out strip those of tourism and the needs and wishes of all within the community must be balanced. A summary of the Vele Colliery project and the positive impact anticipated from the project is attached as Annexure “LC22”. The following employment will be created, calculated on a national scale: 49.2.9.1.1 Construction phase – during the 3-year construction period, contractor labour levels will peak at approximately 2,500 employees. A large percentage of employees will be targeted to be drawn during this period from the local 59 Refer to Table 2.6(e) on page 163 of the EIA/EMP. Page 117 area. The macro-economic model in the EIA found that the indirect employment opportunities would amount to 12 926. 49.2.9.1.2 Operational phase – The proposed new development will employ approximately 826 permanent employees with varying skills, implying an impact on the direct livelihood (direct workers and dependents) of approximately 1 495 people. Indirect employment opportunities amount to 28, 255 during the operational phase. 49.2.9.2 A MEA Study was performed to determine the impact on the economic activity: tourism. The results showed that there will be some impact on tourism in the direct vicinity of the mining development, but further showed a higher positive impact by the mine on employment and GDP in relation to that of tourism. 49.2.9.3 CoAL will be a major contributor to South Africa’s GDP – R2.1billion during construction and R9.7bn during operational phase. The initial capital investment in the mine will be R3 billion. Letters of intent have been signed with prospective customers for off-take agreements. It is anticipated that sales of coking coal could replace coal currently imported from Australia, benefitting South Africa’s balance of payments. 49.2.9.4 In addition to providing employment opportunities, CoAL is committed to spending R85 million over a five-year period for Local Economic Development i.e. infrastructure projects, social investment, health and welfare projects and environmental projects. 49.2.9.5 The company will contribute R70 million over an eight year period towards Human Resources Development Programmes i.e. skills development, Career Progression Plan, a mentorship plan and internship and bursary plans and local community CSI projects. 49.2.9.6 The Company believes that it is possible for the various Page 118 ecotourism projects, the communities and the mine to co-exist in a way that benefits all. Local conservation initiatives will also be supported. 50. 50.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 50.2 The appeal should accordingly be dismissed. XIV. WILLIAM GILFILLAN 51. General comments on this Appeal 51.1 51.1.1 I&APs in the Public Participation Process This person was an I&AP in the public participation process described in paragraph 5.2 above. 51.1.2 51.2 All comments provided in the I&AP process were responded to. Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 52. 52.1 Specific responses to the appeal submissions made by the Appellant The Appellant refers to the SAIEA EMP Review. This was considered and responded to in the I&AP process conducted for the purposes of the EMP. In this regard please see the response to the EWT in paragraph IV above. 52.2 The Appellants also alleges a potential loss of World Heritage Status for Page 119 Mapungubwe. In this regard please see the response to MAG in paragraph 19.2 above. 53. 53.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 53.2 The appeal should accordingly be dismissed. XV. MOPANE BUSH LODGE 54. General comments on this Appeal 54.1 54.1.1 I&APs in the Public Participation Process This organization was an I&AP in the public participation process described in paragraph 5.2 above. 54.1.2 54.2 All comments provided in the I&AP process were responded to. Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 55. 55.1 55.1.1 Specific responses to the appeal submissions made by the Appellant Re 9.3.1: Groundwater Availability While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for Page 120 the purposes of this appeal. 55.1.2 The Vele Colliery will not abstract more water from the Limpopo River than was abstracted previously. Furthermore, as a closed system is being designed, whereby all water is recycled for use in the process, the operations will not impact on the water quality of the Limpopo River. 55.1.3 A detailed study of groundwater has been done, including the regarding the availability. Reference is made to the Groundwater Study (included in the EMP as Annex-E). 55.1.4 Reference is also made to the response to EWT’s contention that the Vele Colliery will impact on the water quantity, as set out paragraphs 23.1 to 23.3 above. Further reference is made to the Leshika Response in reply to the Sustainable Solutions comments on groundwater (attached as Annexure B to the EWT Report), set out in paragraph 23.14 above. 55.1.5 An Integrated Water Use License Application has been submitted for the water uses that require authorisation under the NWA. 55.2 55.2.1 Re 9.3.2: AMD It is incorrect that the planned operations will be conducted below the Limpopo River. 55.2.2 It is reiterated, as stated in paragraph 1.3.4.3 of the EMP, “a closed system is being designed whereby all water is recycled for use in the process”. No dirty water will be discharged into any stream or river during the operational phase and thus no treatment is required. Reference is made to the Surface water Study (included in the EMP as Annex-D). 55.2.3 The Groundwater Study also included a detailed analysis of the potential of AMD. Reference is made to the Groundwater Study (included in the EMP as Annex-E). 55.2.4 The Company repeats what is stated in response to the EWT appeal in respect of AMD in paragraph 23.5 above. It further refers to the Leshika Page 121 Response in reply to the Sustainable Solutions comments on groundwater (attached as Annexure B to the EWT Report), set out in paragraph 23.15 above. 55.2.5 There is no basis for the Appellant’s allegation that the Company will pollute the Limpopo River, thereby impacting on the livelihoods of farmers in the region or the people of Mozambique who live along the banks of this river. 55.3 55.3.1 Re 9.3.3: Dust Pollution The Air Quality Study (Annex-F to the EMP) included dispersion simulations to reflect the combined impacts from the sources of inhalable particulate and nuisance dust deposition rates from all the activities at the Vele Colliery. Comparison with the predicted daily and annual average ground level concentrations to the current South African standards reflected that there was no exceedance at or within the Vele Colliery boundary area. 60 55.3.2 No exceedances were noted for inhalable particulates over the adjacent areas when comparisons are made to the stricter SANS 1929 daily and annual limits. They only exceeded the stricter SANS 1929 daily limits for residential areas which is 600 mg/m²/day but not for the industrial limit of 1200 mg/m²/day. With the implementation of mitigation measures, the concentrations would however be significantly reduced. 61 55.3.3 It is recognised in the EMP that excessive blast-related dust is caused by insufficient or ineffective stemming materials in each hole. As stated above, the negative impact significance will however be reduced to low with effective stemming controls in place, resulting in atmospheric dust mostly being contained to within 200 metres of the blasting. Air blast monitoring will also be conducted for all blasts to ensure that the limits are being achieved; and to provide an indication of when modifications are needed to the blasting method, for increased vibrations and air blast 60 61 Page 29 of the EIA/EMP Page 29 of the EIA/EMP Page 122 levels. 62 55.3.4 Mitigation measures for potential dust pollution, during both the construction and operational phase, will inter alia include regular watering on the haul and in pit road, as well as application of chemical dust suppressants on the main haul road; tarring of the access road; vegetation of permanent stockpiles and berms; use of water spray systems at the stockpiles; sprays of all transfer points; cladding of the run of mine and product stockpile; limitation of vehicle speed on unpaved roads; and developing air blast control measures to limit dust from blasting. 63 55.3.5 Figures 5-4 to 5-6 of the Air Quality Study shows the maximum predicted ground level concentrations with planned mitigation measures in place. The specialist concluded that, as a result of these mitigation measures, all predicted emissions (including dust fallout and PM concentrations) fall below the South Africa Standards of 180μg/m³ and 60μg/m³, as well as the stricter SANS limits of 75μg/m³ and 40 μg/m³ for daily and annual limits respectively. 64 55.3.6 This is with the exception of the residential dust fallout limit of 600mg/m²/day which is exceeded for a short distance outside of the southernmost border of the mine lease area. As is noted in Figure 5.6 this exceedance will only be for a distance of approximately 1km. The relevant property is the farm Erfrust. This property has no residents or agriculture; and is not pristine, consisting of restored grazing land which also belongs to Harrisia. It will not impact on for example Dongola Ranch, which is further than 1km south. 55.3.7 With the implementation of mitigation measures, the concentrations would however fall well below the SANS maximum levels. 55.3.8 As set out in Annexure “LC15”, the Company has included extensive mitigation measures to mitigate any impacts on air quality. 62 Pages 125 - 126 of the EIA/EMP Pages 115 – 119 of the EIA/EMP 64 Pages 26 – 28 of the Air Quality Study 63 Page 123 55.3.9 As specialist studies have concluded that dust pollution will not impact on areas outside the mining area there are patently no grounds for the Appellant to state that “all surfaces of Mopane Bush Lodge and Mapungubwe World Heritage Site and the environment will be covered in dust” or that dust pollution will have a detrimental effect on the agricultural production of the area. 55.4 55.4.1 Re 9.3.4: Smell Smog, Smell and Pollution are related to the control of spontaneous combustion. 55.4.2 Spontaneous combustion normally goes with old, abandoned mine sites and dumps. The Company has applied normal process and mitigation planning here so as not to cause this. 55.4.3 It is in the Company’s interests to get the coal to market as soon as possible after being mined and washed. The coking qualities reduce if exposed for a period of time. The coal will therefore not remain on the mining area for an extended time period and the risk of spontaneous combustion is low. 55.4.4 Mitigation measures such as cladding of stockpiles have been considered during the engineering design of the mine. In the unlikely event that spontaneous combustion does occur, the necessary mitigation measures will be implemented in accordance with the emergency plans. 55.5 55.5.1 Re 9.3.5 Noise The Company instructed a specialist to compile the detailed Noise Study, which is attached as Annex-G to the EMP. 55.5.2 Reference is made to Annexure “LC15”, where the potential noise impacts and the mitigation measures that will be implemented are discussed. Page 124 55.6 55.6.1 Re 9.3.6 Light The Company instructed a specialist to compile the detailed Visual Study, (attached as Annex-J to the EMP). 55.6.2 Reference is made to Annexure “LC15”, where the potential light impacts and the mitigation measures that will be implemented are discussed. 55.7 55.7.1 Re 9.3.7 Transport The Appellant states that the Vele Colliery will transport 1 million tonnes of coal per year over a local road. It is not clear which road the Appellant is referring to, as no specific information is given. 55.7.2 A detailed assessment was undertaken of transport and road infrastructure for the purposes of the EMP. 55.7.3 The Company plans to construct an access road off the R572. Initially the road will be gravel but will be upgraded to tar once the mine is in full production. A by-pass road has been constructed by the Company (the new Venetia – Harper Link Road) to the MAC Siding. The construction of this road will alleviate any traffic congestion. 65 55.7.4 There is absolutely no basis for the Appellant to state that the vehicles travelling to Vele Colliery will “destroy the road”. 55.7.5 Mitigation measures have been included in the EMP to ensure that coal is not spilled off the trucks and exhaust fumes are controlled. 66 55.8 55.8.1 Re 9.3.8: Visual The Company has instructed a specialist to compile the detailed Visual Study (attached as Annex-J to the EMP). 55.8.2 65 66 Reference is made to Annexure “LC15”, where the potential light impacts Page 22 – 23 of the EMP Page 156 – 166 of the EMP Page 125 and the mitigation measures that will be implemented are discussed. 55.9 55.9.1 Re 9.3.9 Environment The residential limits / standards used in the Air Quality Assessment are of course the most stringent South African standards. There are no standards for sensitive landscapes but one would imagine that the potential impact of any emissions on humans, particularly children, in a residential context would result in the highest possible standards and that it would be unusual to find an impact standard allowed for a sensitive landscape that is higher than the impact standard allowed for a child. 55.9.2 Mitigation measures suggested for implementation at the mining area were based on best available technology approaches for the reduction of impacts associated with mining activities. The implementation of these suggested measures at the mining area aim to ensure the reduction of impacts to within the prescribed health risk standards, set by the South African National Department of Environmental Affairs. These standards are set to manage impacts on human settlements, as well as sensitive vegetation. 55.10 55.10.1 Re 9.3.10 Cultural Heritage While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 55.10.2 The Appellant has no basis for its exaggerated claim that the Vele Colliery will place at risk the opportunity of Zimbabwe and Botswana also gaining World Heritage status for their areas of the ancient Kingdom of Mapungubwe. 55.10.3 The Company repeats paragraph 19.1 above regarding the allegation that the Vele Colliery will have an impact on the status of MNP. Page 126 55.11 55.11.1 Re 9.3.11 People While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 55.11.2 It is incorrect that there is no plan regarding the accommodation of employees of Vele Colliery. 55.11.3 There will be no onsite housing. The issue of employee housing and service delivery in Musina was assessed thoroughly in the SEA Study. 55.11.4 Vele Colliery will provide a range of accommodation options to employees and will promote home ownership through various mine-sponsored initiatives. 55.11.5 67 In respect of service delivery, the following conclusions were set out in the SEA Study: 55.11.5.1 water: Musina Local Municipality has a bulk water scheme, abstracting water from the Limpopo River for purification and distribution. The system does require upgrading and expansion to be able to address current needs of the Musina town. This is however a problem common in most Municipal areas in South Africa; 55.11.5.2 sewerage: a water-borne sewage works exists in the town of Musina; 55.11.5.3 electricity: four electrical sub-stations are located within the Musina Local Municipality; and 55.11.5.4 67 Page 18 of the SEA Study refuse: the Musina Local Municipality has access to three general Page 127 disposal landfill sites, excluding those privately operated by mining.68 55.12 55.12.1 Re 9.3.12: Sense of Place In respect of the Appellant’s allegations regarding the impact on the sense of place, reference is made to paragraph 19.1 above. 55.12.2 It is denied that there are no possible mitigation measures for the potential impact on the sense of place. The specialists have identified measures to mitigate any potential impact on the sense of place. This is set out in Annexure “LC15”. 55.13 55.13.1 Re 9.3.13 TFCA It is denied that the Vele Colliery falls “well within the planning domain of the TFCA”, in terms of the MOU for the TFCA. 55.13.2 The Company repeats the contents of paragraph 19.2 above regarding the alleged impacts on the TFCA. 55.13.3 With respect to the addition of Vhembe, including the Mapungubwe Landscape to the UNESCO World Network of Biosphere Reserves, South Africa does not have legislation or any other instrument in which it domesticates the UNESCO Framework. The only statutory instrument which refers to Biosphere reserves is the National Biodiversity Framework (NBF) which states that the implementation of the Biosphere Reserve concept is relatively new to South Africa, with the first South African Biosphere Reserve designated by UNESCO in 1998. 55.13.4 The NBF says a Biosphere reserve usually includes one or more formal protected areas, but is more than just protected areas. Those parts of the Biosphere Reserve which do not constitute a protected area have no legal status. 68 Page 38 of the SEA Study Page 128 55.13.5 The area of the Vele Colliery includes a number of areas subject to intensive agriculture. 55.14 Re 9.3.14: Alternative site While we do not believe that there is any evidence of “unacceptable 55.14.1 pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 55.14.2 The coal in this area is predominantly a blend coking coal, which South Africa has very limited remaining resources of. This deposit is one of the few remaining economically viable Southern African resources of this coal type. 55.15 Re 9.3.15: Constitutional Right 55.15.1 It is correct that the Appellants have a constitutional environmental right. 55.15.2 Section 24(b) of the Constitution of the Republic of South Africa 1996 provides that everyone has a right to have the environment protected, for the benefit of present and future generations, through reasonable legislative and other measures that prevents pollution and ecological degradation; promotes conservation; and secures ecologically sustainable development and use of natural resources while promoting justifiable economic and social development. 55.15.3 The principle of sustainable development requires that the environment, economic development and human development must be balanced. The principles of sustainable development are included in NEMA. 69 55.15.4 It is submitted that the approval of the mining right is in accordance with the doctrine of sustainable development and the Appellant’s constitutional environmental right has not been infringed. 69 Sections 3 of NEMA. Page 129 56. 56.1 This appeal should be dismissed For the reasons set out above, this appellant has not set out grounds for the mining right to be set aside. 56.2 The appeal should accordingly be dismissed. XVI. PETER FITT/NORTHERN TULI GAME RESERVE; 57. General comments on this Appeal 57.1 57.1.1 I&APs in the Public Participation Process This organization was an I&APs in the public participation process described in paragraph 5.2 above. 57.1.2 57.2 All comments provided in the I&AP process were responded to. Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 58. 58.1 58.1.1 Specific responses to the appeal submissions made by the Appellant Impact on the TFCA While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 58.1.2 Please refer to paragraph 19 of the MAG response regarding the impact Page 130 on Mapungubwe; paragraph 19.4 regarding the loss of World Heritage Status of MNP and paragraph 19.2 regarding impact on TFCA. 58.1.3 The Company has a dual listing on the JSE and a number of South African shareholders, including its black economic empowerment partners amongst others. It clearly will act with due regard to its corporate responsibilities and in compliance with local law. 58.2 58.2.1 Culture While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 58.2.2 A HIA Study has been undertaken and included in the EMP to identify all heritage resources which will be affected by the Vele Colliery. (See Annex-H of the EMP). 58.3 58.3.1 Flora and Fauna A Biodiversity Study has been undertaken and included in the EMP, as Annex-C. 58.3.2 The area is not one of the areas protected in terms of the Biodiversity Act, nor is it located in one nine broad priority areas for conservation action which were identified in the NSBA. These Priority Areas are now included in the NBF which was published in 2009 in terms of section 39 of the Biodiversity Act. 70 58.3.3 A number of biodiversity offset programmes are included in the EMP to mitigate any impact on biodiversity. 70 71 71 Government Gazette No 32474 in Government Notice 813 dated 03 August 2009. Page 5 of the EMP. Page 131 58.4 End of Eco Tourism While we do not believe that there is any evidence of “unacceptable 58.4.1 pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 58.4.2 These comments are based on other developments occurring in the area, which are unrelated to the Vele Colliery. 59. 59.1 This appeal should be dismissed For the reasons set out above, this appellant has not set out grounds for the mining right to be set aside. 59.2 XVII. The appeal should accordingly be dismissed. TOURISM WORKING GROUP OF THE GREATER MAPUNGUBWE TRANSFRONTIER CONSERVATION AREA; 60. 60.1 General comments No indication has been given by this Appellant why it has chosen now to join an appeal brought by participants in the initial I&AP process. It makes no effort to distinguish itself from the majority of the Appellants who were all involved in that process nor to indicate why it is involved in the Appeal but was not involved in the I&AP process. It has put their appeal submissions on an identical template with the I&AP participants and, as such, has shown itself to have a common cause with those Appellants. Accordingly we do not believe there can be any basis to distinguish between the Appellants. 60.2 As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. 60.3 Nevertheless, this Appellant appears to believe that it should have an unlimited Page 132 number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 60.4 At no time has this Appellant given an indication of what actions of the Company prevented it from timeously submitting their reviews in the I&AP process. It also gives no indication why the comments it presents now were unavailable to it at the time it provided its comments and review of the EMP and participated in the I&AP process conducted. Nor why it did not initially participate. 60.5 We submit that there were no such actions by the Company and, as such, the Appellant should not be given the opportunity to include these criticisms now. 60.6 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 61. 61.1 61.1.1 Specific responses to the appeal submissions made by the Appellant Re 8.4.1: TFCA While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 61.1.2 The Company repeats the contents of paragraph 19.2 regarding the alleged impact of the Vele Colliery on the proposed TFCA. 61.2 61.2.1 Re 8.4.1 Tourism While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is Page 133 completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 61.2.2 The potential impact on tourism has been considered in the MEA Study. It is reiterated that the employment benefits of mining have been shown to far out strip those of tourism and the needs and wishes of all within the community must be balanced. 61.2.3 It is completely incorrect that the Vele Colliery will only create 650 jobs. As set out above and included in the EMP, Vele Colliery will create 2, 500 and 1, 495 jobs in the construction and operational phases respectively. It is further estimated to potentially create 12, 926 and 28, 255 jobs indirectly in the construction and operational phases respectively. In addition, its SLP will lead to the upliftment of the local community. 61.2.4 The Company repeats the response to EWT’s Appeal regarding the impact on tourism, set out in paragraph 23.10 above. It further repeats paragraphs 19.5.9 and 23.10, being its responses the comments of MAG and EWT on the employment created by the Vele Colliery. 62. 62.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 62.2 The appeal should accordingly be dismissed. XVIII. DJ WESTCOTT/JW TAYLOR TRUST 63. 63.1 General comments No indication has been given by this Appellant why it has chosen now to join an appeal brought by participants in the initial I&AP process. It makes no effort to distinguish itself from the majority of the Appellants who were all involved in that process nor to indicate why it is involved in the Appeal but was not involved in the I&AP process. It has put their appeal submissions on an identical template Page 134 with the I&AP participants and, as such, has shown itself to have a common cause with those Appellants. Accordingly we do not believe there can be any basis to distinguish between the Appellants. 63.2 As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. 63.3 Nevertheless, this Appellant appears to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 63.4 At no time has this Appellant given an indication of what actions of the Company prevented it from timeously submitting their reviews in the I&AP process. It also gives no indication why the comments it presents now were unavailable to it at the time it provided its comments and review of the EMP and participated in the I&AP process conducted. Nor why it did not initially participate. 63.5 We submit that there were no such actions by the Company and, as such, the Appellant should not be given the opportunity to include these criticisms now. 63.6 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 64. 64.1 Specific responses to the appeal submissions made by the Appellant Re 8.3.1 A general concern is raised regarding the region and the waterfall and vegetation within the region and the pollution of these. A detailed Biodiversity Study, Groundwater Study and Surface water Study was undertaken for the purposes of the EIA/EMP. These studies are included in the EMP, as Annex-E Annex- D and Annex-C respectively. Page 135 64.2 64.2.1 Re 8.3.2: TFCA While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 64.2.2 The Vele Colliery does not form part of the area of the TFCA included in the MOU referred to in this paragraph. The Company has put forward its belief, based on the EIA it has undertaken, that its activities can co-exist with other land uses in the area and has frequently expressed its willingness to engage regarding this. 64.3 64.3.1 Re 8.3.3 While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 64.3.2 The Appellant makes a general statement that it is questionable that the Company compiled a full and comprehensive EIA / EMP by responsible and involved parties, and whether proper consultations with all I&AP took place. No grounds are given to substantiate this general statement. 64.3.3 As is set out in paragraph 5.5 above, the Company conducted an extensive public participation process. It has compiled its EIA / EMP in compliance with all the provisions of the MPRDA. In addition, it expended significant resources in ensuring that a wide range of specialists, in all relevant fields, thoroughly investigated and assessed the potential impacts of the Vele Colliery. 65. 65.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the Page 136 mining right to be set aside. 65.2 The appeal should accordingly be dismissed. XIX. JEREMY FITT/NORTHERN TULI GAME RESERVE; 66. General comments 66.1 No indication has been given by this Appellant why it has chosen now to join an appeal brought by participants in the initial I&AP process. It makes no effort to distinguish itself from the majority of the Appellants who were all involved in that process nor to indicate why it is involved in the Appeal but was not involved in the I&AP process. It has put their appeal submissions on an identical template with the I&AP participants and as such has shown itself to have a common cause with those Appellants. Accordingly, we do not believe there can be any basis to distinguish between the Appellants. 66.2 As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. 66.3 Nevertheless, this Appellant appears to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 66.4 At no time has this Appellant given an indication of what actions of the Company prevented it from timeously submitting their reviews in the I&AP process. It also gives no indication why the comments it presents now were unavailable to it at the time it provided its comments and review of the EMP and participated in the I&AP process conducted. Nor why it did not initially participate. 66.5 We submit that there were no such actions by the Company and, as such, the Appellant should not be given the opportunity to include these criticisms now. 66.6 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, Page 137 ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 67. Specific responses to the appeal submissions made by the Appellant 67.1 Re 9.3.2: Vegetation 67.1.1 No power station is “required” for the Vele Colliery. 67.1.2 No decision has yet been made on the construction of a railway access. 67.1.3 AMD is not “inevitable”. The Company refers to what is stated in response to the EWT appeal in respect of AMD in paragraph 23.5 above 67.1.4 Topsoil will be preserved and rehabilitation will be undertaken on an ongoing basis to restore vegetation in rehabilitated areas. The studies undertaken for the purposes of the EIA and EMP have identified all potential negative impacts and provided mitigation for these. 67.2 67.2.1 Re 9.3.3: Fauna The Company committed that a detailed rehabilitation plan will be developed for the mine at the commencement of mining. The rehabilitation plan will undergo an annual review, or whenever there is a major change in mine scheduling. 67.2.2 67.2.2.1 The following minimum standards will apply: vegetation will be left intact in areas not earmarked for immediate excavation for as long as possible, to assist in prevention of soil erosion and mitigation of noise and particle pollution; 67.2.2.2 the above-ground vegetation layer will be stripped (cut down) prior to topsoil stripping and stockpiled. This organic material will be mulched and used with the topsoil as compost in the restoration and rehabilitation program; Page 138 67.2.2.3 all available topsoil will be stripped and utilised for rehabilitation. Direct placement will be implemented as far as possible, limiting the stockpiling of topsoil; 67.2.2.4 rehabilitation (levelling & topsoiling) will be initiated within 5 strips of active pit; 67.2.2.5 restoration of the vegetative layers will take place immediately thereafter using the mulch, harvested seeds and plants from the indigenous plant nursery. Ongoing research will be conducted to improve on the sustainable restoration of the natural veldt; 67.2.2.6 soil analysis, to provide corrective fertilisation regimes, will be an ongoing procedure to facilitate vigorous plant growth. 67.2.2.7 until the herbaceous (shorter period) and woody (longer period) vegetation layer is established, artificial watering of reclaimed areas will be applied; 67.2.2.8 erosion control measures will be implemented where necessary; 67.2.2.9 the final profile will be free-draining. Ponding will be prevented as far as practically possible; 67.2.2.10 the final end land use will reflect the initial land capability as far as possible. As a minimum, the final end land use should be grazing (topsoil depth = 0.25m); and 67.2.2.11 all rehabilitation programmes will be properly monitored and documented for future referencing on the impacts, restoration and rehabilitation programs within semi-arid areas. 67.2.3 The implementation of the rehabilitation plan will be coordinated and supervised by a suitably qualified rehabilitation officer. 67.2.4 The prolonged rehabilitation measures will be designed to ensure this Page 139 impact is as brief as possible. 67.2.5 Commitments were made by Vele Colliery for the establishment of animal corridors; and for management agreements with adjacent landowners to limit these impacts. .72 The rescue plan further not only addressed the flora in the area, but also looks at the relocation of fauna, to limit the impact of mining. 67.2.6 All other mitigation measures committed to reduce the impact of noise, blasting and traffic management will also assist with minimising the stress on the animals. 67.3 Re 9.3.4 Pollution Please refer to the MAG response in paragraphs 19.1 and 19.4 above regarding the impact on Mapungubwe National Park and the sense of place. 67.4 Re 9.3.5 International Agreements While we do not believe that there is any evidence of “unacceptable 67.4.1 pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 67.4.2 The Vele Colliery does not form part of the area of the TFCA included in the MOU referred to in this paragraph. 67.4.3 The Company has not been consulted as a private land owner regarding the proposed further expansion of the TFCA. 67.4.4 The Company has put forward its belief, based on the EIA it has undertaken, that its activities can co-exist with other land uses in the area and has frequently expressed its willingness to engage regarding this. 68. 72 This appeal should be dismissed Page 115 of EIA/EMP Page 140 68.1 For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 68.2 The appeal should accordingly be dismissed. XX. MASHATU NATURE RESERVE 69. General comments 69.1 No indication has been given by this Appellant why it has chosen now to join an appeal brought by participants in the initial I&AP process. It makes no effort to distinguish itself from the majority of the Appellants who were all involved in that process nor to indicate why it is involved in the Appeal but was not involved in the I&AP process. It has put its appeal submissions on an identical template with the I&AP participants and as such has shown itself to have a common cause with those Appellants. Accordingly we do not believe there can be any basis to distinguish between the Appellants. 69.2 As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. 69.3 Nevertheless, this Appellant appears to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 69.4 At no time has this Appellant given an indication of what actions of the Company prevented it from timeously submitting their reviews in the I&AP process. It also gives no indication why the comments it presents now were unavailable to it at the time it provided its comments and review of the EMP and participated in the I&AP process conducted. Nor why it did not initially participate. 69.5 We submit that there were no such actions by the Company and, as such, the Appellant should not be given the opportunity to include these criticisms now. Page 141 69.6 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 70. 70.1 70.1.1 Specific responses to the appeal submissions made by the Appellant Re 8.3.1: TFCA While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 70.1.2 The Vele Colliery falls outside the area of the TFCA in the MOU referred to in this paragraph. 70.2 Re 8.3.2 and 8.3.3: Environmental Legislation 70.3 The DMR is the decision maker in the approval of the mining right and the EIA/EMP required for mining. 70.4 70.4.1 Re 8.3.4: Employment While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, this appeal submission in particular is completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 70.4.2 A MEA Study was performed, to determine the impact on the economic activity: tourism. The results showed that there will be some impact on tourism in the direct vicinity of the mining development, but further showed a higher positive impact by the mine on employment and GDP in Page 142 relation to that of tourism. 70.4.3 CoAL will be a major contributor to South Africa’s GDP – R2.1 billion during construction and R9.7 billion during operational phase. The initial capital investment in the mine will be R3 billion. Letters of intent have been signed with prospective customers for off-take agreements. It is anticipated that sales of coking coal could replace coal currently imported from Australia, benefitting South Africa’s balance of payments. 70.4.4 The contribution to employment means that both directly and indirectly, 12 926 people will be advantaged during construction and 28 255 will be advantaged when the mine is operating. 70.4.5 In addition to providing employment opportunities, Coal of Africa is committed to spending R85 million over a five-year period for Local Economic Development i.e. infrastructure projects, social investment, health and welfare projects and environmental projects. 70.4.6 The company will contribute R70 million over an eight year period towards Human Resources Development Programmes i.e. skills development, Career Progression Plan, mentorship plan and internship and bursary plans and local community CSI projects. 70.4.7 The Company believes that it is possible for the various ecotourism projects, the communities and the mine to co-exist in a way that benefits all. .Local conservation initiatives will also be supported. 70.5 Re 8.3.5 Prevailing wind The Air Quality Study, included as Annex-F in the EMP has modelled the wind directions; and the potential pollution plume and mitigation measures have been put in place to reduce any impact. 70.6 70.6.1 8.3.6 Dark Nights It was recognised in the main report of the EMP and the Visual Study that the sense of place in the areas surrounding the Vele Colliery is quiet and Page 143 peaceful, especially at night time when there is complete darkness against moonless nights with excellent star gazing. 70.6.2 The impact of lighting and associated glow in the absence of any other light source; and the possibility of a direct line of sight of the Vele Colliery to visitors at MNP was raised particularly by the private lodge owners and tourist safaris that commented during the public participation processes. 70.6.3 Initially the lighting in the wash plant area was designed to be a height of 30 metres high-intensity masts; however, to mitigate any potential light pollution impacts the lighting within the plant will be directional or cut-off type luminaries, below the maximum stipulated height of 20m. No high masts will be erected. 70.6.4 No light impact is anticipated to arise from the opencast pits. Movable directional lights will be used by employees, which will not be visible outside the pits. 70.6.5 The natural topography and vegetation in the area will assist in mitigating any light pollution. The Vele Colliery is situated in a low lying area. 73 70.6.6 Due to the potential impacts of the Wash Plant causing light pollution in the construction and operational phase, various mitigation measures will be implemented by Limpopo Coal in both phases. The Wash Plant has been designed to be constructed below a maximum height of 20 metres. Directional or cut-off type luminaries will also be utilized in both the construction and operational phase of the Wash Plant, to mitigate any light pollution caused by the Wash Plant. These luminaries will be set to focus beams downwards to mitigate light pollution. 74 The luminaries will be directed away from MNP 70.6.7 Vegetation screens along the western edge of the Wash Plant area will also be used, which will also assist in the absorption of light. It was proposed that Baobab trees could be relocated from the opencast area 73 74 See page 17 of Annex -J to the EIA/EMP Pages 158 and 161 of the EIA/EMP Page 144 for this purpose, provided that the habitat is suitable. 75 Similarly, as much vegetation as possible will be retained in the opencast pits and revegetation will occur to create screening against lighting from this area. 70.6.8 It is noted that, even though the Vele Colliery is on a low lying area, the reflection of the light from the Wash Plant area may create sky glow, which will be visible as a dome above the horizon. 76 However, as the Wash Plant is on a low lying area, as opposed to Venetia Mine which is located on a relatively high area, the Wash Plant will have less exposure with an associated lesser degree of glare. 70.6.9 At MNP, the overnight areas are furthermore not on top of the mountain and the lighting from the Wash Plant should not be visible from these overnight areas of Mapungubwe. 71. 71.1 This appeal should be dismissed For the reasons set out above, this Appellant has not set out grounds for the mining right to be set aside. 71.2 The appeal should accordingly be dismissed. XX. SOUTH AFRICA ARCHAEOLOGICAL SOCIETY 72. General comments 72.1 No indication has been given by this Appellant why it has chosen now to join an appeal brought by participants in the initial I&AP process. It makes no effort to distinguish itself from the majority of the Appellants who were all involved in that process nor to indicate why it is involved in the Appeal but was not involved in the I&AP process. It has put their appeal submissions on an identical template with the I&AP participants and, as such, has shown itself to have a common cause with those Appellants. Accordingly, we do not believe there can be any basis to distinguish between the Appellants. 75 76 Pages 158 and 161 of the EIA/EMP Page 20 of Annex-J to the EIA/EMP Page 145 72.2 As set out above, the I&AP process followed allowed all parties more than sufficient time to make their comments. 72.3 Nevertheless, this Appellant appears to believe that it should have an unlimited number of opportunities to provide further reasons why a mining right should not have been granted to the Company. 72.4 At no time has this Appellant given an indication of what actions of the Company prevented it from timeously submitting their reviews in the I&AP process. It also gives no indication why the comments it presents now were unavailable to it at the time it provided its comments and review of the EMP and participated in the I&AP process conducted. Nor why it did not initially participate. 72.5 We submit that there were no such actions by the Company and, as such, the Appellant should not be given the opportunity to include these criticisms now. 72.6 Irrelevant grounds of appeal While we do not believe that there is any evidence of “unacceptable pollution, ecological degradation and environmental damage” following from the grant of the mining right, certain of these appeal submissions are completely unrelated to this ground and accordingly should be ignored for the purposes of this appeal. 73. 73.1 Specific responses to the appeal submissions made by the Appellant Re 8.3.1: Impact of mining on MNP is permanent and irrevocable Impact on MNP, Mapungubwe Cultural Landscape and archaeological heritage “The MNP and World Heritage Site was declared to preserve and protected the Mapungubwe Cultural Landscape….” “Mining and the associated activities will damage this landscape (the Mapungubwe Cultural Landscape) and alter the sense of place permanently and forever” Page 146 Impact of the Vele Colliery on MNP 73.1.1 The comments in this paragraph are largely academic, illustrating the importance of MNP and the Mapungubwe Cultural Landscape. 73.1.2 Whilst the Company does not respond to these academic comments, it has always recognised that MNP and the broader Mapungubwe cultural landscape are an important part of South Africa’s heritage. It was for this reason that the Company instructed a heritage specialist and a palaeontology specialist to conduct thorough investigations and compile comprehensive reports. 73.1.3 As stated above, MNP itself has been declared a World Heritage Site under the name “Mapungubwe Cultural Landscape”. The area of the World Heritage Site does not extend beyond the area of the MNP. 73.1.4 A thorough HIA Study was undertaken to investigate the potential impacts on heritage resources and propose mitigation measures to avoid such potential impacts. 73.1.5 None of the sites identified in the HIA Report was accorded a high significance rating. “A phase 1 heritage survey was undertaken of the demarcated area during which archaeological sites relating to the Mapungubwe cultural landscape were recorded. These are socalled commoner sites and most have been degraded by natural forces. None of the sites have been assigned to a high significance grading and it is recommended that phase 2 assessments be undertaken in line with the provisions of section 38 of the National Heritage Resources Act (25 of 1999) should mining be implemented. It is argued that this work will add value to and further understanding of the existing information about the Mapungubwe cultural landscape. In addition, Stone Age material was observed and these must be assessed once Page 147 mining operation commence due to their obscured subterranean occurrence.” 77 73.1.6 The map attached as “LC6” plots the heritage sites identified on the site as against the activities to be undertaken. 73.1.7 The areas with the potential to be impacted in the next year of operations have been fenced off. Attached as Annexure “LC28” is the Draft Heritage Management Plan for Vele Colliery, setting out this information. 73.1.8 It is therefore denied that the Vele Colliery will damage this landscape (the Mapungubwe Cultural Landscape) permanently and forever”. Impact on the sense of place 73.1.9 In respect of the Appellant’s allegations regarding the impact on the sense of place, reference is made to paragraph 19.1 above. 73.1.10 Based on its specialist reports and the mitigation measures, recommended by the specialists, which it is obliged to implement, the Company believes that the sense of place of MNP will not be impacted on. 73.2 73.2.1 Re 8.3.2: A “full HIA” was not carried out The Appellants contend that due to the range of different sites, inputs from specialists in paleontology, archaeology and Stone Age should have been included in the EIA. It is alleged that this was not done and a “full HIA” should have been carried out. 73.2.2 The Appellant’s requirement that a “full HIA” should have been conducted is baseless and unclear. It has complied with the provisions of the MPRDA in the compilation of the HIA Study. As set out above, the HIA Study also complies with SAHRA’s directions for the compilation of HIA are set out in SG 2.2 SAHRA APM Guidelines the: “Minimum Standards 77 Page 3 of the Vele Heritage Impact Assessment Report. Page 148 for the Archaeological and Palaeontological Components of Impact Assessment Reports”. (Annexure “LC27”). The relevant sections of these guidelines and the provisions of the MPRDA have been set out in paragraph 26.1.9 and 26.1.6 above respectively, in response to the Appeal by ASAPA. 73.2.3 The Company reiterates that is has compiled with the legislative requirements and SAHRA’s guidelines in the compilation of the HIA Study and repeats the contents of paragraph 26.1.6 to 26.1.13 above. There is no classification of a “full” HIA in these Guidelines and the Appellants’ comments regarding the nature of this “full” HIA lack any substance. 73.2.4 As stated above, the objective of a Phase 1 HIA is to identify heritage resources affected by proposed operations. For the most part, this involves an identification of the heritage resources themselves within the affected area of the development to ensure these are not impacted on by the development. 73.2.5 The EMP consisted of reports from Frans Roodt, who holds a master degree in archaeology, with specialisation in Iron Age studies. It also consisted on a report from Dr. Durant, a specialist in palaeontology. 73.2.6 As set out in paragraph 26.8.3 above, Roodt is not a specialist in Stone Age. He is however a qualified Principal Inspector and is an experienced heritage practitioner who has undertaken approximately 500 Phase 1 assessments. His ability to conduct these surveys is derived not from his specialisation in Iron Age sites but also from his wide experience in a range of heritage contexts and identification of potential heritage sites from a visual inspection of the site. 73.2.7 In the context of a Phase 1 Assessment, the recognition of Stone Age remains and Stone Age bearing gravels is what is important and not their detailed analysis. It is only during a subsequent Phase 2 Assessment that the specialised knowledge of a Stone Age specialist would be required to precisely identify all of the relevant details regarding the site which was demarcated during the Phase 1 assessment. Page 149 73.3 Re 8.3.3: Many heritage resources have not been excavated and the mining will result in permanent damage 73.3.1 Whilst many heritage resources have not been excavated in the area to date, there can be no guarantees that funding will actually be obtained for such excavations. 73.3.2 The Company has committed to the appointment of an archaeologist to monitor all areas to be disturbed on an ongoing basis. In addition, allowance has been made for Phase 2 Assessments, in line with the Heritage Management Plan developed for Vele Colliery (see Annexure “LC28”). Therefore, if any heritage resources are excavated, the Company will deal with them in accordance with this plan. 73.3.3 The immediate, short, intermediate and long-term management actions are described in paragraphs 26.9.7 to 26.9.19. It is therefore incorrect that mining will result in permanent damage to heritage resources. 73.3.4 Sufficient budget has been allowed by the Company for environmental and heritage aspects, amounting to R19.1 million per annum. Over the life of the mine this commitment adds up to almost R500 million. 73.3.5 Furthermore, if fossils or archaeological heritage resources remain underground for thousands or millions of years, the information will also be lost to humankind. It is neither in the interest of science nor humankind not to study nature. 73.3.6 Many thousands of fossils and heritage resources have been salvaged successfully from mines (both abandoned and functioning) in South Africa. 73.3.7 Although not all of these fossils were undamaged, the storerooms at the Council for Geoscience, Bernard Price Institute for Palaeontology and the Transvaal Museum contain hundreds of thousands of such fossils from mines in the Cradle of Humankind, Makapan’s Valley and Collieries. 73.3.8 Thousands of tons of material containing fossils or archaeological Page 150 heritage resources are destroyed annually in the coal mines in South Africa, without SAHRA or anyone else for that matter doing anything about it. Vele Colliery could make a difference by involving a specialist to salvage at least some of heritage resources, as per the specialist’s suggestions. The commitment for the appointment of a palaeontologist has been made and the necessary funds made available. 78 73.3.9 It is therefore denied that the Vele Colliery will cause permanent damage to the archaeological and paeleoontological remains 74. 74.1 This appeal should be dismissed For the reasons set out above, this appellant has not set out grounds for the mining right to be set aside. 74.2 The appeal should accordingly be dismissed. ------------------------------------------------------------------Riaan van der Merwe Director Limpopo Coal Company (Pty) Ltd 30 July 2010 78 Refer to Table 2.6(e) on page 163 of the EIA/EMP.