Absorption Costing Absorption costing requires managers to gather information on the direct costs, such as materials, and also the indirect costs or overheads such as admin costs. This method enables us to calculate the cost of production as precisely as possible. If the cost of meeting an order is underestimated, then the business might set the price too low, and make a loss on the order. Or, vice versa, the cost could be too high, and then the business might lose the order to a competitor. Cost centres and cost units We must firstly collect and record the production costs and overheads of running a business. A cost centre is a particular area or point of a business for which costs are collected. In the case of manufacturing businesses, there are two main types of cost centre: Production cost centres (e.g. production departments such as machining or assembly) Service cost centres (e.g. admin or canteen) When we have collected and recorded costs into cost centres, the process of absorption costing involves calculating the cost of each unit of production or Cost Unit. What is absorption costing? It is also known as full or total costing. The key point is that all overheads (indirect costs) are ‘absorbed’ into cost units. Therefore, all costs are included when calculating the cost of producing particular items. The main difficulty of absorption costing is deciding how to divide the cost of overheads (indirect) between these cost centres (more on this later). There are 5 main stages in the absorption costing process: 1.) The first stage is the ALLOCATION of those overhead costs that are ‘directly’ incurred by particular cost centres (remember the above explanation of what a cost centre is), for example, we might be able to pinpoint depreciation of a machine to the production department. 2.) The second stage is to APPORTION, i.e. divide all shared overheads between the production and service cost centres. (For example, sharing the rent of a building between several cost centres contained within that building). 3.) The third stage is to apportion or ‘reapportion’ all service cost centre overheads to the production cost centres. This is also called secondary apportionment (an example might be splitting the cost of running a canteen (service cost centre) up amongst several production cost centres. The reason is that it is only the production cost centres that are directly associated with the manufacture of the cost units. 4.) The fourth stage is to ABSORB the allocated and apportioned overheads into the costs of production of cost units. 5.) Finally include direct costs, which can easily be attributed to individual products (cost units). This stage may have been completed in stage one, so could be ignored depending on the question. Miss Hunter – Absorption Costing Stage 1 – ALLOCATION We must include the direct and indirect costs of production. Most exam questions provide direct costs associated with particular products or cost units, so can easily be charged to the relevant cost centre. For example, wages paid to assembly line workers can be allocated directly to the production department. Note: Sometimes this part is left until the end of the calculation. Some indirect costs that are wholly associated with a particular cost centre can also be charged ‘directly’ to that cost centre. Examples might include the wages of an assembly line supervisor, or depreciation of an assembly line machine. They can be allocated directly to the production department. Not all indirect costs can be charged to production departments. For example, the rent of a sales office might be charged directly to the sales department (service cost centre). Example: Consider Dentons Ltd, a clothing manufacturer. ‘directly’ allocated costs Cutting (production) £ 8,500 Assembly (production) £ 10,500 Canteen (service) £ 4,400 Maintenance (service) £ 6,600 Total £ 30,000 Stage 2 – Apportionment of overheads to cost centres Sometimes overheads are shared between several cost centres. For example, the cost of heating and insurance on a building might be shared amongst several production and service departments. A number of methods can be used to apportion overheads, as shown in the table below. There are no set guidelines to follow, but the basis must be equitable, which means that a fair share of the overheads should be apportioned to the relevant cost centre. Overhead Rent and rates Heating and lighting Personnel costs Buildings insurance Machinery and equipment insurance Depreciation Maintenance Supervisory costs Staff canteen Administration Possible basis of apportionment Floor area of cost centres Floor area, or volume of space of cost centres Number of staff employed by each cost centre Floor area, or book value of buildings in each cost centre Book value of machinery/equipment in each cost centre Book value of assets in each cost centre Book value of assets in each cost centre No.of staff, or hours worked by supervisor, in each cost centre No.of staff employed in each cost centre No.of staff employed in each cost centre It is important to apportion the overheads fairly because businesses will want to determine as accurately as possible the true cost of operating each cost centre. If they are not apportioned fairly, the business might charge an inappropriate price to its customers. Also, managers (who are responsible for cost centres) might be demotivated, if their centres are charged an unrealistic share of overheads, as it would suggest they are running an expensive department, and seem perhaps inefficient. Miss Hunter – Absorption Costing Example: Consider Dentons Ltd, a clothing manufacturer. They have three overheads, £10,000 for heating, £40,000 in wages for 2 supervisors and £20,000 for insuring equipment. The business is divided into 4 cost centres. Some further information about Dentons Ltd is provided in the table below. Floor area Staff employed Book value of equipment Production cost centres Cutting Assembly 25m2 200m2 15 30 £50,000 £135,000 Service cost centres Canteen Maintenance 100m2 75m2 2 3 £10,000 £5,000 Total 400m2 50 £200,000 We must now apportion the 3 overheads, to the cost centres. The earlier table gave examples of how this can be done. Heating: The heating costs of £10,000 can be apportioned according to the proportion of total floor space each that each cost centre occupies. Cost to be apportioned = floor space occupied by cost centre Total floor space * total heating cost So: Cutting = 25m2 * £ = Assembly = _____ 400m2 * £10,000 = £ Canteen = _____ 400m2 * £10,000 = £ Maintenance = _____ 400m2 * £ = £ Supervision: The supervisory costs of £40,000 can be apportioned according to the proportion of total staff employed in each cost centre. Cost to be apportioned = number of staff employed by cost centre * total supervisor cost Total number of staff So: Cutting = __ * £40,000 = £ Assembly = __ 50 * £ = £ Canteen = __ 50 * £40,000 = £ Maintenance = __ 50 * £40,000 = £ Miss Hunter – Absorption Costing Insurance: The insurance costs of £20,000 can be apportioned according to the total book value of equipment (fixed assets) used in each cost centre. Costs to be apportioned = book value of equipment in cost centre * total insurance cost Total book value So: Cutting = _______ * £20,000 = £ 200,000 Assembly = _______ 200,000 * £ = £ Canteen = ______ 200,000 * £20,000 = £ Maintenance = _____ 200,000 * £20,000 = £ The following table shows the share of overheads apportioned to each cost centre. Sometimes more than one basis for apportionment could be used. For example buildings insurance could be apportioned according to the size of the floor area of each cost centre, OR to the book value of the buildings of each cost centre. It is therefore a subjective judgement. However, it should always be made clear which basis is chosen, and the decision should be consistent and appropriate. Basis of apportionment Heating Supervisory Insurance Total Floor area No.of employees Book value Cutting Assembly Canteen Maintenance Total £ 625 12,000 5,000 17,625 £ 5,000 24,000 13,500 42,500 £ 2,500 1,600 1,000 5,100 £ 1,875 2,400 500 4,775 £ 10,000 40,000 20,000 70,000 Stage 3 – Reapportionment of service centre overheads We now must apportion the service cost centre overheads to the production cost centres. This is called reapportionment or secondary apportionment. Therefore, the costs involved in running service cost centres, such as canteen and maintenance (other examples might include stores and planning), must be shared between the production departments. The reason for this, is that it is only the production cost centres that are directly associated with the manufacture of the cost units. Service cost centre Canteen Maintenance Planning Stores Miss Hunter – Absorption Costing Possible basis for reapportionment Number of staff or meals served to each cost centre Hours of maintenance work carried out for each cost centre Number of hours worked in each cost centre Number of times that materials are requested by each cost centre. We can now illustrate how overheads are apportioned to production cost centres. Firstly we will consider each cost centre as it stands now, and then reapportion the service cost centre overheads to the production cost centres. ‘directly’ allocated costs Apportioned costs Total Cutting (production) £ 8,500 Assembly (production) £ 10,500 Canteen (service) £ 4,400 Maintenance (service) £ 6,600 Total 17,625 42,500 5,100 4,775 70,000 26,125 53,000 9,500 11,375 100,000 £ 30,000 The ‘directly’ allocated costs are those costs such as depreciation of a specific machine that can be associated straight away with a particular cost centre (stage 1). The apportioned costs are taken from the workings on the previous page (stage 2). They are those costs which needed apportioning to different cost centres. We now need to reapportion the service cost centre (canteen and maintenance) costs in the following ways: Canteen: according to the number of meals served to staff in each cost centre Maintenance: according to the number of hours that maintenance staff work in each cost centre. Canteen: No of meals (as a % of total) Maintenance: No. of hours (as a % of total) Cutting 3,750 Assembly 7,500 Canteen - Maintenance 1,250 Total 12,500 30% 3,000 60% 3,000 - 10% - 100% 6,000 50% 50% - - 100% The total number of meals served is 12,500. These are split up amongst the three departments. This example presumes that no canteen staff have meals. The 6,000 maintenance hours are split equally between the cutting and assembly departments. Total overheads (from above table) Canteen overheads reapportioned Sub-total Maintenance overheads reapportioned Total overheads apportioned Cutting £ 26,125 Assembly £ 53,000 Canteen £ 9,500 Maintenance Total £ £ 11,375 100,000 2,850 5,700 (9,500) 950 28,975 6,162.50 58,700 6,162.50 - 12,325 (12,325) 100,000 35,137.50 64,862.50 - - 100,000 The £9,500 canteen overheads need to be reapportioned to the two production cost centres. Remember that the Cutting department used 30% of meals so = £_______ (30% of £9,500) The Assembly department used 60% of the meals so = £_______ (60% of £9,500) Miss Hunter – Absorption Costing The Maintenance department used 10% of the meals so = £_____ (10% of £9,500) We can now reapportion the Maintenance overheads to the two production cost centres. Remember the Maintenance overheads now include some reapportioned Canteen overheads. Remember that both the Cutting, and Assembly cost centres used 50% of the Maintenance hours. Therefore we can split the £12,325 Maintenance overheads equally, which = £6,162.50. Stage 4 – ABSORPTION of the allocated and apportioned (and reapportioned!) overheads into the cost units This will ensure that all costs are taken into account when calculating the cost of producing the goods that are to be sold. The rate at which the overheads are charged to cost units is called the overhead absorption rate (OAR). There are several methods available, but we must know only 2 methods for the exam (note: the book has 3 methods, ignore the 3rd!) Machine hour overhead absorption rate: This method is most suitable when production is capital intensive (large investment in fixed assets like machinery compared to labour). Therefore, most of the overheads are related to the cost of using the machinery. They include, for example depreciation, power, insurance, maintenance etc. Machine hour OAR = Total cost centre overheads = Number of machine hours rate per machine hour Imagine that in a machining department, the total annual overheads are estimated to be £250,000. The budgeted annual total of machine hours in this cost centre is 10,000 hours. Machine hour OAR = £______ = £___ per machine hour If a particular cost unit takes 6 hours to produce in the machining department then £150 (6 * £___) overheads will be absorbed to the production of that single unit. Direct labour hour overhead absorption rate: This method is most suitable when production is labour intensive, i.e. when direct labour costs are high relative to capital costs. Direct labour hour OAR = Total cost centre overheads = rate per direct labour hour Total direct labour hours For example, a packaging department has total annual overheads estimated to be £60,000. The budgeted annual total labour hours is 20,000 hours. Direct labour hour OAR = £______ = £__ per direct labour hour If it takes ½ hour to pack a cost unit, then £1.50 (0.5 * £__) overheads will be absorbed to each unit. Miss Hunter – Absorption Costing Step 5: Calculating the total cost unit Firstly add together each production cost centre – from step 4. e.g. £25 + £3 = £28. The final step is to consider any direct costs (materials, labour etc) which would be provided in the exam question (if these have not been dealt with in stage 1). We do not have to do any working out with these direct costs, apart from perhaps working out the direct costs per unit (if only a total is given). We can then add these direct costs to the first bullet point and we have the total cost per unit!!! Example of calculating unit costs using absorption costing: Consider Wrights Ltd, a manufacturer of sailing boats. The business is divided into 4 cost centres: Body shop – produces the fibre glass parts that are needed to construct the boat. Sub-assembly – assembles the bought-in components. Production Packing and dispatch – packs and dispatches the kits to customers. Cost centres Quality control – This department overseas quality control in the 3 production cost centres. This is therefore a service cost centre. A machine hours OAR is used in the body shop to charge overheads. A direct labour hours OAR is used in the other 2 production departments. Floor space Book value of assets No. of employees Quality control hours Overheads Rent Heat & light Depreciation Administration Total Body shop 8,000m2 £600,000 Sub-assembly Packing 4,000m2 2,000m2 £200,000 £200,000 Quality control 2,000m2 - Total 16,000m2 £1,000,000 10 40 20 10 80 2,000 8,000 4,000 - 14,000 £ 1,600,000 400,000 200,000 800,000 3,000,000 Annual budgeted machine hours in the body shop Annual budgeted direct labour hours in the sub-assembly dept Annual budgeted direct labour hours in the packing department Cost of direct materials per boat Cost of direct labour per boat £500 £2,500 Time taken to produce one boat kit in each department Body shop 10 hours Sub-assembly 15 hours Packing 8 hours Miss Hunter – Absorption Costing 50,000 40,000 20,000 We now need to calculate the cost of producing one boat: Step 1: Firstly we must apportion the £3m overheads to the 4 cost centres. Basis for apportionment Body Shop £ Subassembly £ Packing £ Quality Control £ Rent Heat & Light Depreciation Administration Total Total £ 1,600,000 400,000 200,000 800,000 3,000,000 Step 2: Reapportion the overheads of the service department to the production departments. In this example, the quality control department is a service cost centre, so needs to be reapportioned to the other 3 production cost centres. The basis for reapportionment in this case is the number of hours the quality control department works for each other department. Body shop £ Sub-assembly Packing £ £ Quality control £ Total overheads Quality control reapportioned Total Total £ 3,000,000 3,000,000 Step 3: When all the overheads have been apportioned to the production cost centres, the next step is to calculate the overhead absorption rates. (Remember either the machine or direct labour hour OAR can be used). In the exam, if you are not sure which OAR to use, then just decide if the department in question is capital or labour intensive, and this will tell you which OAR to use! The body shop uses the machine hour OAR. The sub-assembly department uses the direct labour OAR. The packing department uses the direct labour OAR. Therefore: Body shop: Machine hour OAR = = Sub-assembly dept: Direct labour hour OAR = = Packing dept: Direct labour hour OAR = = Step 4: We can now calculate the number of overheads that can be charged to each cost unit, i.e. boat. We just multiply the relevant OAR by the length of time it takes to process a single cost unit in each department. Department OAR Multiplied by Number of hours Cost per unit Miss Hunter – Absorption Costing £ £ * * * Body shop Sub-assembly Packing Total 917.50 Step 5: The final step is to calculate the total cost of each boat (cost unit) by adding the total overheads (£917.50 from above) charged per cost unit to the direct costs per unit (labour and materials – provided in the question). £ Direct material cost per unit Direct labour cost per unit Overheads per cost unit Total 3,917.50 And the selling price should be? Now that we have worked out that the cost of the boat is £3,917.50 we can decide the selling price accurately. Obviously it needs to be higher than this figure, so that the business can make money. And if the calculations are inaccurate? Obviously, all these calculations are budgeted figures. They are just predictions, usually based on historical data, which might not accurately reflect the future. If they are inaccurate, then the selling price might be set too high, or too low. This could either put off customers, or result in less profit being made, than was perhaps possible. Advantages of absorption costing Ensures all costs are fully covered so is a widely used method. Business will cover their costs (assuming actual costs are similar to budgeted costs) Conforms to SSAP9 Valuing stocks. SSAP9 states that absorption costing should be used, rather than marginal costing. This is because absorption costing reflects all costs involved, including fixed costs. Disadvantages of absorption costing Is based on budgeted figures, which may prove inaccurate. If they are inaccurate then businesses might set the selling price too high or too low. It is a complex, time consuming and expensive process. Key definitions: Allocation Apportionment Reapportionment Absorption Costs assigned to one individual cost centre Costs assigned to two or more cost centres Charging all service cost centre overheads to production cost centres. This is because at the end of the day it is the production cost centres that are directly associated with the finished products (cost units) The allocation of all production direct and indirect expenses to cost units Miss Hunter – Absorption Costing