SECTION ONE: CERTIFICATION

1. a) Is a person with an Intermediate Scaffolding Certificate allowed to construct a personnel and materials hoist?

__ No________________________________________________________________ b) Is a person with an Intermediate Scaffolding Certificate allowed to install a cantilevered crane loading platform?

___Yes_______________________________________________________________ c) Is a person with an Intermediate Scaffolding Certificate allowed to carry out all work covered by the Basic Scaffolding Certificate?

___Yes_______________________________________________________________ d) Is a person with an Intermediate Scaffolding Certificate allowed to construct a hung scaffold?

___No________________________________________________________________ e) Is a person with an Intermediate Scaffolding Certificate allowed to construct a barrow ramp?

___Yes_______________________________________________________________ f) Is a person with an Intermediate Scaffolding Certificate allowed to construct a singlepole tube-and-coupler scaffold?

___Yes_______________________________________________________________ g) Is a person with an Intermediate Scaffolding Certificate allowed to construct a boatswain’s chair?

___No________________________________________________________________ h) Is a person with an Intermediate Scaffolding Certificate allowed to construct a tubeand-coupler covered way or gantry?

___Yes_______________________________________________________________ i) Is a person with an Intermediate Scaffolding Certificate allowed to construct a mast climber?

___Yes_______________________________________________________________

APPLICANT'S NAME:_____________________________ SIGNATURE:____________________________

j) Is a person with an Intermediate Scaffolding Certificate allowed to construct a swing stage?

__No________________________________________________________________ k) Is a person with an Intermediate Scaffolding Certificate allowed to construct a cantilevered or spurred scaffold?

_Yes_______________________________________________________________

SECTION TWO: TUBE-AND-COUPLER SCAFFOLD SPECIFICATIONS

2. a) What is the maximum specified height for a tube-and-coupler scaffold?

_45m______________________________________________________________ b) What is the maximum bay width for a light duty independent scaffold?

__2.4m (or planks)___________________________________________________ c) What is the minimum bay width for a medium duty independent scaffold?

__950mm (or 4 planks)________________________________________________ d) What is the maximum bay width for a heavy duty independent scaffold?

__1.275m (or 5 planks)________________________________________________ e) What is the maximum bay length for a light duty independent scaffold?

__3m________________________________________________________________ f) Or a medium duty independent scaffold?

__2.4m_______________________________________________________________ g) What is the maximum bay length for a heavy duty independent scaffold?

__1.8m_______________________________________________________________ h) What is the maximum bay length for a single-pole scaffold?

__1.8m_______________________________________________________________ i) What is the maximum lift height for a normal independent scaffold?

__2m________________________________________________________________

APPLICANT'S NAME:_____________________________ SIGNATURE:____________________________

j) How far from a standard can a ledger be joined?

__300mm_____________________________________________________________ k) How far from a ledger can a standard be joined?

__300mm_____________________________________________________________ l) When putlogs are cantilevered to support extra planks, what is the minimum bay width?

___950mm (or 4 planks)_________________________________________________ m) How many 225mm planks can be supported by the cantilevered portion of putlogs?

___2_________________________________________________________________ n) How many full length working platforms can be carried on a 15m high steel tube scaffold?

___4_________________________________________________________________ o) How many full length working platforms can be carried on a 45m high aluminium tube scaffold?

___1_________________________________________________________________ p) How many full length working platforms can be carried on a 45m high steel tube scaffold?

___2_________________________________________________________________ q) At what lift is the first level of ties fixed on a single-pole scaffold?

___The first lift________________________________________________________ r) What is the maximum height of a mobile scaffold?

___3 times its least base width___________________________________________ s) What is the maximum angle from the vertical for spurs in an access opening?

___45 degrees_________________________________________________________ t) What is the maximum height for puncheons in an access opening?

___30m______________________________________________________________

APPLICANT'S NAME:_____________________________ SIGNATURE:____________________________

u) Where double standards are used, what is the maximum first lift height?

___3m_______________________________________________________________ v) What is the maximum angle for sloping putlogs on a cantilevered catch platform?

___60 degrees (or 30 degrees to the horizontal)_____________________________ w) What is the maximum spacing between intermediate sloping putlogs on a cantilevered catch platform?

____600mm___________________________________________________________ x) What is the maximum width of a cantilevered catch platform?

____1.125m (or 5 planks)________________________________________________ y) How close to the castors is the first lift of ledgers and transoms on a mobile scaffold?

____As close as possible_______________________________________________

SECTION THREE: PARTICULAR SCAFFOLD REQUIREMENTS

3. a) What is the maximum allowable slope of a working platform?

____7 degrees (or 1 in 8)________________________________________________ b) What is the maximum allowable slope of a cleated barrow ramp?

____20 degrees (or 1 in 3)_______________________________________________ c) How far apart would you fix the cleats on the platform of a barrow ramp?

____450mm___________________________________________________________ d) What size gap would you leave for the wheel of a barrow in a barrow ramp cleat?

____100mm___________________________________________________________ e) How many lifts would you support with a single set of spurs?

____5________________________________________________________________ f) What is the minimum width of a steel beam you would use as a needle for a cantilever scaffold?

____75mm____________________________________________________________

APPLICANT'S NAME:_____________________________ SIGNATURE:____________________________

g) How much of a cantilever scaffold needle should be inboard?

____3 times the outboard (or 3 quarters, or 75%)____________________________ h) How would you stop the nuts from loosening on the anchorage bolts of a cantilever scaffold needle?

_____Use lock nuts____________________________________________________ i) What type of baseplate would you use to fix the standards of a cantilever scaffold to the needles?

_____U-Heads (or forkheads)____________________________________________ j) Where would you place the first lift of ledgers and transoms on a cantilever scaffold?

_____As close to the needles as possible__________________________________ k) What is the minimum diameter of bolts you would use to anchor the inboard end of a cantilever scaffold needle?

_____15mm___________________________________________________________ l) Would you use drilled-in anchors to fix the inboard end of a cantilever scaffold needle?

_____No______________________________________________________________ m) When a spur is in compression, what would be its maximum length between node points?

____2m______________________________________________________________ n) What type of coupler would you use to fix a spur to the scaffold framework?

____Right angle (or double or ninety degree) coupler________________________ o) What is the maximum angle from the vertical at which you would fix a spur?

____45 degrees________________________________________________________

APPLICANT'S NAME:_____________________________ SIGNATURE:____________________________