Economic Waste: When the Federal Government Is Not Entitled to Strict Compliance by Franci E. Gardner, Associate* In federal government contracting, the principle of “strict compliance with contract specifications” means exactly that; even when the contract specifications are more stringent than industry standards. Consequently, if a federal government contractor does not comply with the government’s specifications and those specifications are express and not ambiguous nor defective, then the government typically has the contractual right to demand strict compliance without additional compensation to the contractor. “Typically,” however, does not means “always”; and the government’s right to insist on strict compliance with its contract specifications is not absolute. Indeed, if the government fails to consider whether the non-conforming work is suitable for its intended purpose but instead insists on strict compliance, the costs of repair or replacement may be chargeable to the government under the doctrine of economic waste. What Is The Doctrine of Economic Waste Defining economic waste can be tricky. Generally speaking it is the unwise use of resources. The doctrine most often comes into play when the market value of a project or property or its usefulness will not increase comparably to the cost of completing or correcting performance. The doctrine has been applied in private construction contract disputes as long ago as 1921 when Justice Cardozo, then of the Court of Appeals of New York reasoned in Jacobs & Young v. Kent that minor deviations from the contract language cannot always be treated as a “breach . . . to be followed by forfeiture.” See, 239 N.Y. 239, 129 N.E. 2d 889 (1921). In federal construction contracts, a similar recognition that non-conforming work shall not always result in forfeiture exists in the standard inspection of construction clause, (FAR 56.246-12); though not in terms of economic waste. Under its standard inspection clause, the federal government has two options in the event of non-conforming construction work before default terminating its contractor; 1) the contracting officer may direct its contractor to repair or replace the nonconforming work, or 2) the contracting officer may accept the non-conforming work with an appropriate adjustment in the contract price when acceptance is in the public interest. Suppose, however, a contracting officer directs its contractor to repair or replace nonconforming work even though the work, as is, is suitable for the intended purposes and the repair or replacement can only be done at great cost. It was not until 1992 that the courts would apply the economic waste doctrine to a federal construction contract. See, Granite Construction Co. v. United States, 962 F.2d 998 (Fed. Cir. 1992) Granite Construction and Economic Waste In Granite Construction, the Corps of Engineers had contracted for the construction of a lock and dam. Waterstop was to be placed in the vertical joints between the walls to prevent leakage. After Granite had installed a portion of the waterstop, the Corps of Engineers declared the waterstop to be non-conforming and ordered removal and replacement with other waterstop. Under protest, Granite performed the replacement and filed a claim for cost of the repair work, which the contracting officer and thereafter the board of contract appeals denied. In the proceedings, Granite’s expert witness had testified that although the originally installed waterstop did not strictly comply with the contract specifications, it was adequate for the project’s ultimate requirements. On appeal to the Federal Circuit Court of Appeals, the court held that while the government usually has the right to require strict compliance with specifications, the public interest provision of the standard inspection clause includes an obligation to consider the nonconforming work relative to the performance requirements, i.e., would it be economically wasteful to repair or replace the non-conforming work. Because the Corps made no such determination, its rejection of the waterstop was “arbitrary and capricious” and Granite was able to recover virtually all its costs for the replacement waterstop. Recent Developments of the Economic Waste Doctrine in Government Contracts The Granite ruling was not an aberration. Since the ruling, the boards of contract appeals have made similar applications of the economic waste doctrine. For instance, in Appeal of George Ledford, ENGBCA No. 6268, 98-2 BCA ¶ 30,016, contractor Ledford entered into a contract with the Corps of Engineers to renovate and pave entrances of four Corps parks at separate locations surrounding Table Rock Lake along the Missouri-Arkansas state line. The contract required Ledford to construct a concrete slab, but this slab had many deficiencies such as being “wavy” and bulging outward. The Corps invoked the contract’s Inspection Clause and ordered Ledford to remove and replace the concrete slab with one that conformed to the contract specifications. Ledford admitted that the deficiencies existed, but characterized them as minor problems which could be repaired. The board of contract appeals found that the Corps was entitled to strict compliance with the contract’s requirements, but the board also recognized the option for the Corps to accept non-conforming work at a downward adjustment of the contract price if within the public interest. The doctrine of economic waste required the Corps to exercise reasonable discretion in ordering the removal and replacement of the concrete slab. Instead, however, as the board found, the Corps did not reasonably consider Ledford’s proposal to repair the slab’s defects or evaluate the work in light of a downward adjustment in the contract price. The Corps’ insistence on strict compliance with the contract’s requirements was arbitrary, and the Contracting Officer was forced to negotiate an equitable adjustment based on the reasonable cost of the remedial work, reduced by the reasonable cost Ledford would have incurred had it been permitted to repair the deficiencies. Although the economic waste doctrine is now an established doctrine in government contracts, the claimant contractor bears the burden of proving that it is entitled to recovery under the doctrine. For example, in order to recover for non-conforming work, the contractor must establish the critical elements that its work though not in strict compliance with the contract is otherwise adequate for its intended purpose, and that the cost of correction is economically wasteful relative to the benefits gained from the correction. In Twigg Corp., GSBCA No. 14,327, 98-2 BCA 29,803, a contractor was under contract with the General Services Administration to install a fire alarm system. A subcontractor used a different wire for the fire alarm circuits than that specified by the contract, and the GSA directed the contractor to replace the wire despite the fact that the wire had been previously approved. The board noted that there had not been enough facts presented to it to make a determination either way. The board did state, however, that the critical element was whether the originally-installed wire was “adequate for its intended purposes,” and it would consider information regarding the reasonable value of the work as-built along with information regarding the acceptability of the originally installed wire. In at least one case, aesthetic shortcomings outweighed application of the economic waste doctrine so as to preclude the contractor’s recovery for repair and replacement. In Appeal of Worcester Brothers Co., Inc., ASBCA No. 49,014, 99-2 BCA ¶ 30,519, the contractor Worcester contracted to perform roofing work at the United States Naval Academy. Under the contract, the roofing tiles were to be “natural red clay in color.” The government found that Worcester had installed tiles that were orange and not a reasonable match to the existing color. The government directed Worcester to replace the riles with those that fit the contract specifications. The board of contract appeals found the government was reasonable in rejecting the non-matching tiles, and noted that the tile specified in the contract needed to match the appearance of the existing tile because the buildings were historical. Conclusion Thanks to Granite, a construction contractor to the federal government can fall back on the economic waste doctrine to seek recovery of costs for economically wasteful remedial work ordered unreasonably. However, it is the contractor who must shoulder the burden of proving why the economic waste doctrine should apply. * Watt, Tieder, Hoffar & Fitzgerald, L.L.P. 8405 Greensboro Drive, Suite 100 McLean Virginia 22102 703-749-1000