Method statement for site handling of concrete made with Ecocem GGBS cement Introduction Ecocem Ground Granulated Blastfurnace Slag (GGBS) cement is a by-product of iron-making. It replaces up to 70% ordinary cement in concrete on a one for one basis, giving superior concrete performance. Health and safety (H & S) Ecocem GGBS is a non-hazardous cementitious powder certified to I.S. EN 15167-1 that has no classification under the REACH directive. When used in concrete, normal health and safety considerations for handling fresh concrete apply. See Ecocem’s MSDS for full H&S information. Quality Assurance (QA) Concrete with Ecocem GGBS shall be supplied by independently certified concrete suppliers to I.S. EN 206 and sampling and testing shall be in strict accordance to EN 12350-1&2 and EN 12390-2&3. Where higher than 50% GGBS is specified, it is advisable to take extra cubes for 56-day strength testing. Pre–ordering arrangements 1. Confirm the percentage of Ecocem GGBS required, typically between 30-70%, most commonly at 50%. 2. Plan the pour to commence as early as possible in the day 3.Confirm that the pour time allows sufficient time for finishing/power-floating and optimal striking of concrete. When Ecocem GGBS percentages exceed 50%, or in colder weather, concrete setting times will be prolonged by a number of hours. TIP: Keep time and date stamped photos as a record that good practice is being followed on site. 4.Arrange meeting on site with Ecocem, to discuss best practice for working with concrete incorporating GGBS. Taking delivery of concrete with Ecocem GGBS 1. Check the mix design on the delivery docket prior to discharge to ensure the specified concrete has been supplied. TIP: Ecocem GGBS cement is white in colour, and concrete with Ecocem GGBS is paler in colour than ordinary concrete. 2. Water should not be added to concrete as it will reduce the strength and durability of the concrete. Concrete made with Ecocem GGBS has more fluidity and stays workable for longer than concrete without Ecocem GGBS. Any addition of water on site is to be in accordance with clause 7.5 of EN 206. Placing and compacting concrete with Ecocem GGBS 1. The usual methods of placing concrete (and selfcompacting concrete) apply for concrete with Ecocem GGBS. 2.Do not drop concrete from more than a height of 1m as the concrete may segregate. For deep pours use tremie pipes or pumps to place the concrete. 3.Concrete with Ecocem GGBS stays workable for longer, allowing more time to place and compact, and reduces the risk of cold joints forming. TIP: Concrete with Ecocem GGBS is easier to pump due to its improved workability. 4. Place poker to ensure vibrated areas overlap. 5.For subsequent layers the poker should be allowed to sink under its own weight about 100mm into the underlying layer, and the concrete vibrated from the underlying layer upwards. Failure to do this can lead to air bubbles being trapped, leaving blowholes. 6.Remove vibrator when air bubbles stop rising. Overvibration will lead to segregation. 7.Avoid poker burn by keeping the poker 75-100mm away from the formwork. Avoid poker contact with the reinforcing. 8. If plastic settlement occurs re-vibrate the top 75100mm of the concrete to ensure the concrete is levelled. ECOCEM Contact Details: Tel: 00353 1 6781800 Fax: 00353 1 6781816 Email: technical@ecocem.ie Web: www.ecocem.ie This is a guidance note and should be supplemented with the users requirements. october 2012 - rev 1.0 Finishing and curing concrete with Ecocem GGBS 1. The usual finishing techniques of using screeds, floats, trowels, power floating, etc. apply to concrete with Ecocem GGBS. 2.Flat surfaces of concrete with Ecocem GGBS are to be finished only when bleed water has fully evaporated, and not before. 3.For higher percentages of Ecocem GGBS (+ 50%) and/or in cold weather, setting times and duration TIP: Longer setting of bleed time may need times allow concrete to to be extended. Consult be worked for longer with Ecocem for further periods so that time delays guidance. 4.Concrete is to be cured in accordance with EN13670. 5.Cure concrete for a minimum of three days, but ideally seven days. between mixing and using concrete are less critical. This can also enable power floating to be completed on the morning after a pour, rather than late at night. 6.The two principle methods of curing are: a)Keep the surface of the concrete wet by ponding, mist spraying or covering with damp hessian. b)Retain the moisture in the concrete by using polythene sheeting, sprayed curing compounds, leaving formwork in place or use of frost blankets. (Curing compound should be compatible with end use of concrete). TIP: Finishing concrete prior to evaporation of bleed water can lead to remixing of the surface layer of concrete and weakening of the concrete surface. This can lead to cracking, dusting, delamination, abrasion, frost or chemical damage. 7.Failure to cure concrete adequately can result in loss of up to 50% of the concrete design strength; increased risk of cracking; dusty surfaces with low abrasion resistance; reduced frost resistance and porous concrete that will be susceptible to water ingress and chemical attack. 8. In quick drying conditions or when concrete with > 50% Ecocem GGBS is used, greater attention is required. Striking formwork 1. Formwork shall not be removed until the concrete has gained sufficient strength. 2.Determine the required in-situ concrete strength for striking formwork from the Engineer’s Specification or using guidance from EN 13670 or The UK’s Concrete Society publication “Formwork – A guide to good practice”. TIP: Secure polythene sheeting to prevent wind tunnel effect and keep hessian damp for the duration of its use. 3.To optimize striking time, determine the insitu strength of the concrete, rather than working to a fixed striking time, as the early age strength gain of concrete with Ecocem GGBS can vary according to variables such as ambient temperature, mix design, the percentage of Ecocem GGBS and the section size. 4. Standard 20oC cured cubes do not give an accurate measure of early age in-situ strength. 5.To determine early-age in-situ strength of concrete for optimum striking times use techniques such as Temperature Matched Curing, Maturity Meters and Maturity Functions, LOK Test or Capo Test. 6.Contact Ecocem to discuss formwork striking times and to implement a site testing program to determine the in-situ strength of concrete and determine the optimal time to safely strike formwork. 7.After removing formwork, a blue/green colour may temporarily appear on concrete with Ecocem GGBS. This is due to iron and manganese sulphides. However, these oxidise on exposure to air, returning the colour to normal after several days. The desired concrete properties such as strength, durability or final appearance are not affected by this colouration. Cold and Warm Weather concrete with Ecocem GGBS 1. Normal precautions are to be taken in cold and warm weather, when concreting with Ecocem GGBS. 2.Cold weather will extend setting time which can lead to increased formwork pressures and delays in striking and finishing. 3. Warm weather can lead to excessive drying out or the formation of cold joints. Consider modifications to the concrete mix design, e.g. increase Ecocem GGBS content and/or use chemical retarders. ECOCEM Contact Details: Tel: 00353 1 6781800 Fax: 00353 1 6781816 Email: technical@ecocem.ie Web: www.ecocem.ie This is a guidance note and should be supplemented with the users requirements. october 2012 - rev 1.0