Automatic Sprinkler Plan Submittal

advertisement
NEVADA STATE FIRE MARSHAL
AUTOMATIC SPRINKLER PLAN SUBMITTAL
NFPA 13/13R 2002 EDITION
1. Company Submitting
2. Project Title
3. Project Address
Fire Marshal License #
4. Water Supply (provide as required for your submittal)
15.1.1 Municipal System
flow
GPM
Residual
15.2.2 Pumps
flow
GPM
Residual
15.2.3 Pressure Tank
storage
gallons, flow
gallons, Residual
storage
gallons, flow
gallons, Residual
15.2.4 Gravity Tanks
16.1 Private Fire Service Mains
flow
GPM
Residual
15.2.5 Other: Explain
11.1.1 Required water supply
psi @
available water supply
psi @
(Available must exceed the required by 10 psi.)
Static pressure
Residual pressure
Test location
5. Flow
Test date
Test time
(Current water supply information shall be provided and tested during peak hours.)
(Water supply information must have been taken from tests within 90 days)
6. Hazard Classification (11.2.1.3)
Total area:
(sq ft)
Ordinary group 3:
(sq ft)
Light Hazard area:
(sq ft)
Extra Hazard group 1:
(sq ft)
Ordinary group 1:
(sq ft)
Extra Hazard group 2:
(sq ft)
(sq ft)
High Piled storage
(sq ft)
Ordinary group 2:
7. Type system (coverage) (3.4)
Area wet (3.4.9)
Area dry pipe (3.4.5)
Area dry pendant
Area looped (3.4.7)
(sq ft)
(sq ft)
(sq ft)
(sq ft)
8. Quality of risers (3.5.8)
Light (5.2)/Ordinary (5.3): sum of areas=
52,000 sq ft
Extra Hazard (5.4): sum of area=
40,000 sq ft
9. System is: Pipe schedule (11.2.2)
Area pre-action (3.4.8)
Area deluge (3.4.4)
Area anti-freeze (3.4.1)
psi.
psi.
psi.
psi.
psi.
GPM
(sq ft)
(sq ft)
(sq ft)
High piled (3.3.12): sum of areas=
40,000 sq ft
Pipe schedule: sum of area=
25,000 sq ft
Hydraulically calculated: (11.2.3)
10. Sprinkler area coverage per head is: Maximum distance between sprinklers:
(not to exceed 15 sq ft (4.6m))
Light hazard area
Ordinary hazard area
(not to exceed 15 sq ft (4.6m))
Extra hazard area
(not to exceed 12 sq ft (3.7m) with a density of .25 or
greater) or (15 sq ft (4.6m) with a density of less than .25)
11. Side wall sprinkler (3.6.3.5) coverage per head is: (8.7.2.2)
(sq ft)
12. Piping materials are: Welded seamless
Copper pipe
Steel
CPVC
ECR (3.6.2.2)
LDS (3.6.2.3)
QRES (3.6.2.7)
13. Number of sprinkler heads: ESFR (3.6.2.1)
QR (3.6.2.9)
Special sprinkler (3.6.2.1)
SACMS (3.6.2.12)
Spray (A.3.6.2.12)
Standard (3.6.2.14)
Quantity of spare sprinkler heads
Total Quantity:
14. System has:
(a) Anti-Freeze:
YES
NO
less than 40 gallons
YES
YES
NO
less than 1,000 sprinkler heads
(b) Pre-action system:
(c) Deluge system
YES
NO
(d) Dry system
YES
NO (see note1)
(e) High Piled Storage: NFPA 231
231C
231D
231F
(f) Combination Standpipe/Sprinkler system
YES
NO
NO
YES
NO
15. Cross connection control (7.5.3.1) Back flow protection for potable water systems.
TYPE
MFG
MODEL
Listed/Approved by:
Location:
Installed by:
Health Approval
(Name & Office)
16. Pipe schedule classification (14.5)
Light Hazard (14.5.2)
residual pressure
riser flow
Ordinary Hazard (14.5.3)
residual pressure
riser flow
Extra Hazard (14.5.4). Shall be hydraulically calculated
17. Hydraulic calculated system. (11.2.3)
Area of sprinkler operation
Density- gpm/square foot
Hose Allowance
Static head loss
(sq ft)
18. A complete and accurate submittal shall include the following:
(a) Riser diagram with all trim
(b) Fire department connection detail
(c) Material specifications for all materials including listing and/or approval
(d) Piping elevations
(e) Calculations
(f) The sprinkler system shall include underground piping drawing and specifications
(g) Full height cross section of building
(h) Occupancy of each room
(i) Graph sheet
(j) Cross connection control (backflow prevention) detail. See note #8
Notes:
1. NFPA 13 indicates in section (3.4.6) that a Gridded dry pipe system shall not be installed.
2. Need away brace and earthquake coupling location.
3. R-1 occupancies (hotel, motel, apartments, condominiums) must have residential or quick response standard sprinkler heads.
NFPA 13 (8.4.5)
4. Certificate of Registration holder must be on the job site at all times when the work is being performed.
5. When job is completed it must be approved, a tag hung, and a letter certifying that it meets code and NAC 477 submitted to the
AHJ.
6. Additional and/or relocated sprinkler heads (10 or less) do not need to be submitted to this office.
7. Approval of plan contingent on acceptable cross connection control (backflow prevention) valving to protect the drinking
water supply. (Check with Health Authorities)
8. Above ground/underground test certificates must be supplied to this office.
9. An R-1 occupancy that has more than two stories must have an NFPA 13 system installed. An R-1 occupancy that has less than
two stores must have and NFPA 13-R or NFPA 13 system installed.
SUBMITTED BY:
(SIGNATURE REQUIRED TO INITIATE REVIEW, UNSIGNED SUBMITTALS WILL BE RETURNED.
REPRESENTING
Download