Development of a large-scale wind turbine with a rated power of 4.5 MW Autor: Aloys Wobben, Managing Director ENERCON GmbH Abstract: In the following, the development of the largest wind turbine worldwide with 4.5 MW will be outlined. This pioneering project was very challenging and it produced outstanding insights and new results in the field of large-scale wind turbines. The process from the concept of a wind energy converter to its implementation is very complex and demands a very precise approach. The strategy, to rely on our longtime experience in turbine building, has proved successful. In February this year, the third converter of this power class was erected, three more are under construction, severel others have been planned. Series production is being prepared. In the course of the past years we have come closer to the goal to achieve a proportion of 25 % from wind energy in Germany. Presently, wind energy covers approx. 4 % of the electricity demand. Particularly the district of Papenburg (East Frisia) with a share of 54.2 % of wind energy shows the feasibility of a far higher share. By now, ENERCON has installed more than 6 GW worldwide and more than 6.900 wind turbines respectively. Beginning in 1984 with the first generation of wind energy converters, ENERCON looks back to a longtime experience of nearly 20 years as a developer and manufacturer. The know-how that has grown with it helped to implement larger and larger projects and finally encouraged to build a turbine of a new power class. Foundation and Tower In 2001 the first foundation was built in Egeln (near Magdeburg). Considering the soil conditions and the loads, the flat foundation was constructed with a height of 5 metres and a diameter of 28 m and consumed 1600 m³ concrete and 154 t steel. Furthermore, the tower was erected in a height of 124 m and a diameter from 12 m (at the bottom) to 4 m (at the top). 1000 m³ concrete and 235 t steel were used to build it. Cast Parts Most of the major components, such as the hub, blade adaptors, axle pin and the main carrier, are cast parts which are subject to highest qualitiy standards. Only very few foundries are able to meet these requirements. The material used for the cast parts is spheroidal graphite cast iron. Before it came to their fabrication, the components had been precisely calculated and tested by means of simulation. The production process itself had been very complex concerning its model construction, mould construction, casting, removement from the mould, finishing and extensive quality control (structural investigations, ultrasound and x-ray test). The example of the main carrier gives an idea of the dimension of this complexity: with its height of 3.4 m, length of 5.5 m and width of 4.3 m it consumed 53 t of steel and 850 tons of sand (for the mould). Rotor Blades Because of the hub height and future offshore applications the rotor blades had been designed for wind class 1. The structure has been appropriately adapted to the size and intended use in order to guarantee the stability necessary. All three blades, consisting of epoxy resin and glass fibre, were put through the stress test, and the deformation, resonant frequency and elongation were thoroughly analysed before they were finally assembled to the turbine. With a weight of 20 t, a length of 52 m and a surface of 450 m², these rotor blades needed a purpose-built vehicle to be transported to the construction site in Egeln (near Magdeburg). Assembly The assembly of the 4.5 MW turbine was a challenge on itself. The components of the nacelle were first assembled on-site into modules, none of which weighed more than 110 t. These were then lifted by two cranes, sometimes working in tandem, and were then mounted in position. Afterwards, the generator consisting of the stator and the rotor, the hub, the nacelle cover and finally the three rotor blades were lifted one by one to a height of 124 m where they were fitted together. In Operation By now, the power measurements of the E-112 are finished. Official sound measurements are carried out when wind blows adequately. Internal measurements are already completed. With this large-scale wind turbine, a new dimension in the field of the generation of electricity from wind energy has been entered. Its complexity becomes clear when considering the monitoring system which is comparable to a modern power station. This complete control of sensors as well as the operating status is necessary to guarantee an average technical availability of at least 98 %. All components have to be controlled which means that, in total, more than 2,700 status messages can be generated with respective control measures. Examples are: oscillations, pitch, generator (e.g. temperature, air gap), azimuth components (e.g. currents, voltages), the bearings, the main security circuit (e.g. fuses, electronics), the grid feeding (e.g. phase currents, voltages), etc. Outlook The 4.5 MW turbine has set off a new power class. One E-112 is able to generate 15 mill kWh per year. With this amount, more than 4,000 households (average consumption of 3,500 kWh) can be supplied. This amount saves more than 97,500 tons of CO2 emissions annually. The potential of the E-112 is an interesting example: A share of 25 % wind power in the electricity supply in Germany could be covered by only 7,500 E-112. In other words: distributed to the existing number of villages (approx. 13,200 à < 20,000 inhabitants), every two villages one E-112 would be enough to achieve these 25 %. A fact that one should reconsider.