t s o P The magazine by Putzmeister Concrete Pumps GmbH The world‘s biggest stationary boom on the Bosporus M 6 placing concrete for oil production platform in Russia‘s Far East Hoover Dam Bypass Bridge – concreting at a height of 4 m above the Colorado River 9 Dancing Towers on Hamburg‘s Reeperbahn – three long-reach boom pumps work in perfect coordination PM 4307 GB 1 Content Content / worth knowing 2 3 Title story Hamburg: Dancing Towers Three M 52 long-reach boom pumps used for the concreting of the foundation slab of the new St. Pauli landmark Exhibition dates 4 October – December 2010 On site Hoover Dam Bypass Bridge – the story of a “modern marvel” Concreting at a height of 274 m above the Colorado River Russia: M 62 placing concrete for oil production platform „A single one-way ticket on the Trans-Siberian Railway from Moscow to Vladivostok“ Turkey: The MXKD 50, the world‘s biggest stationary boom Sensational find from ancient Constantinople – Port of Theodosius discovered at the underground station in Yenikapı 04. – 08.10.2010 Elektra Mining, Johannesburg/SA 10 27. – 30.10.2010 SAIE Bologna/Italy 14 18 4 14 On the Reeperbahn at six in the morning… 4 22. – 25.11.2010 50 questions How does Putzmeister manage to be so ubiquitous? In each edition of PM Post we answer one of 50 interesting questions from the last 50 years of Putzmeister 16 Launching of the first dredger in China equipped with a Putzmeister KOS 25100 high-density solids pump Putzmeister at construction sites in India 21 21 22 23. – 26.11.2010 Bauma China, Shanghai/China 5 By the way… Did you know that for many years now, Putzmeister delivery cylinders have been hard chrome plat­ ed? As standard! This is an important quality feature and extends the service life substantially. 6 In brief Putzmeister Academy – Seminar brochure for 2011 Big 5 Show, Dubai/UAE M 62: 9,000 km rail journey to the Sea of Japan 18 History lesson: concreting at the Port of Theodosius 10 Dizzying heights: Hoover Dam Bypass Imprint: Worth knowing Exhibition dates / Interesting facts Editor: Putzmeister Concrete Pumps GmbH Max-Eyth-Str. 10 72631 Aichtal · Germany 3 Photo credits: Photo credits Imprint 2 3 Unless indicated otherwise, all illustrations are copyright Putzmeister Concrete Pumps GmbH. 18: www.datenland.de · 22: hoover_dam_nevada_luftaufnahme, Wikimedia Commons, licensed under CreativeCommons license by-sa-3.0, Florian Arnd · 26: sea_of_okhotsk_map, Wikimedia Commons, licensed under CreativeCommons license by-sa-3.0, Norman Einstein · 27: cape tihii, Wikimedia Commons, Vihljun · 28: nivkh_men, Wikimedia Commons · 29: yuzhno sakhalin museum (5), Wikimedia Commons, licensed under CreativeCommons license by-sa-3.0, Straitgate · 30: zametny island, Wikimedia Commons, Vihljun · 35: istanbul rapid transit map, Wikimedia Commons, licensed under CreativeCommons license by-sa-2.5, Maximilian Dörrbecker PM 4307 GB Editorial department: Volker Wehner, Petra Montag Putzmeister Concrete Pumps GmbH Layout/DTP: Petra Montag Putzmeister Concrete Pumps GmbH Print: Offizin Scheufele GmbH & Co. KG Tränkestr. 17 70597 Stuttgart · Deutschland PM 4307 GB All rights and technical amendments reserved. Although content is checked carefully, we accept no liability for sites to which links are given. The operators of external websites are solely liable for their content. Some of the illustrations show special machine variants and snapshots which do not always comply with the regulations of the Industrial Employers’ Liability Insurance Association. © by Putzmeister Concrete Pumps GmbH 2010 · Printed in Germany (3.51009) worth know ing Title story Title story 7 “Two new dancers on Hamburg‘s Reeperbahn” Following the plans of architects Bothe Richter Teherani, the “Dancing Towers” project was begun in September 009 quite close to the Port of Hamburg. On the approx. 5,400 m² plot at no. 1 Reeperbahn, two pitched high-rise buildings and a hotel complex are being built for around € 150 million. The contractor is Strabag Real Estate GmbH. May 010 saw the second phase of concreting the ground level with a volume of ,650 m³ of concrete. PM has had a look over the shoulders of those involved, who own four Putzmeister long-reach boom pumps (three in use plus one on stand-by) of the BSF 5.0 H type provided by betonlift GmbH & Co. KG. Pump Full support, feeding by two truck mixers at same time Placing such a large amount of concrete on a single day, even for the old hands of construction firm Ed. Züblin AG, requires some preparation in planning and consultation with the contractors. The concrete supplier is Holcim Beton & Zuschlagstoffe GmbH (Hamburg), the pumps are provided by betonlift GmbH & Co. KG and Sociedade de Construções, Lda (Lisbon) is responsible for placing the concrete. On this day, 5th May, work starts with the concreting concept for the bottom plate, which is subdivided into six concreting sections. The following marginal conditions apply: • Max. plant capacity: 200 m³/h (four mobile concrete plants, each with 50 m³/h) • Setting up three concrete pumps • Having three construction crews at the ready The site management prepares the concreting plan for each concreting operation. Concrete Technology In the case of the second phase described here, three different types of C30/37 concrete are used. For the lower part of the floor and the diagonals, the maximum particle size is reduced to 16 mm because of the high density of the reinforcement (see the box). This ensures that the steel is coated with concrete on all sides. In the middle layers, the maximum particle size is 32 mm, and for the top layer, it is reduced to 16 mm again. From the point of view of concrete technology, it is important to place the individual layers in such a way that concreting is always carried out before the bulk concrete of the previously placed layer begins to set. This means that the bottom layer must still be processible when the next layer is being poured. 8 The concreted section has a surface area of 24.5 m x 42 m. For a concreting height of 0.5 m, the concreting volume is approx. 330 m³ per layer with a maximum component thickness of 4.52 m (1.5 m in the boundary areas) for the bottom layers. If one assumes an average output of 150 m³/h, approx. two to three hours will be required for concreting each layer. For the upper area, up to 550 m³ per layer and three to four hours workability time are set aside. This means that the workability time for the concrete supplied for the lower layers must be slowed to four hours, and five hours for the upper layers – even once any change in location of the pumps has been taken into account. Mixture breakdown for the bottom plate bulk concrete bottom area middle area upper area Consistency F5 (58 ± 2 cm) F5 (55 ± 2 cm) F4 (53 ± 2 cm) Workability time up to 6 hrs up to 10 hrs up to 2 hrs Fresh concrete properties Pump OSS (One side support), 180° forwards working area Hardened concrete properties Property class C 30/37 C 30/37 C 30/37 Exposure classes XC2, XC3 XC2, XC3 XC3, XD1 betonlift Service truck with „caboose“ Stand-by pump 9 Pump OSS (One side support), 180° forwards working area 1 4 PM 4307 GB PM 4307 GB 5 10 12 Title story Title story p For some in St. Pauli, this early hour means hometime, but for the workers on the construction site, the day is only just starting: At half past 5 sharp, the first truck mixers arrive. p Keeping an overview: Three booms, moving construction site cranes, constant changing of truck mixers – the construction site requires the utmost attentiveness from the machine operators. Placing concrete - from a practical viewpoint Franz Syrowatka from betonlift Hamburg adds: “To us it was clear that we would be using our Putzmeister 52 m booms; three in action and one as a stand-by pump with one machine operator to relieve colleagues dur­ ing the day. The important thing for pumps 1 and 3 was the one side support, and that we have a working area of 180°. This was the only way that we were able to reach all corners of the area to be concreted. With pump 2, we had somewhat more space. We Laughing when asked what the greatest challenge for placing concrete is, project lead Silke Pförtner from Ed. Züblin AG answers: “When you see the depth of the pit, the type of pit lining and the size of the area set aside for the construction site equipment, it soon becomes clear: There isn‘t actually any space for large machines. In addition, the hours allowed for concreting are clearly delimited because we have to respect our neighbours, and therefore we need as many pumps as possible. So we have teamed up with betonlift to develop a very target-oriented, fair, good and safe solution. Because when placing large amounts of concrete as you see today, we really can‘t leave anything to chance. So, for example, we worked with betonlift to determine first of all the locations of the three pumps (see fig. 7 and 9), restricted as we were by a very small set-up area, the maximum load on the supporting ground at the edge of the pit, and the access options for the truck mixers.” q Don‘t push: Each truck mixer in the convoy is guided to the appropriate pump by the signaller. Pump 2 (far left) has a somewhat larger set-up area and can be fed by two truck mixers at the same time. 11 were able to provide full support there, and were able to load using two truck mixers at the same time. This enabled the P2 to reach a somewhat higher effective pumping rate per hour.” An average pouring rate of 180 m³/h was assumed for the three pumps combined. At 2,650 m³, this meant a pumping duration of approx. 14 hours. Therefore, concreting was set to begin early, at 6:00 am. To save some time, the four concrete pumps were moved into place the evening before, which meant that all that remained to be done was to set up the machine supports and move the boom into its working position anytime from 5:00 am onwards. Around 5:30 am, the first Holcim truck mixer arrived from the plant approx. 15 km away, and shortly after 6:00 am, the first concrete started to flow. In total, there were 45 truck mixers constantly driv­ ing to and fro, transporting the concrete to the “Dancing Towers”. 13 t A fence reduces the street width by half: On one side, traffic can pass by unhindered, and on the other, the truck mixers control the M 52, which is supported on one side. The one side support (OSS) for pumps 1 and 3 was crucial for their use in the tight space available. PM 4307 GB PM 4307 GB Title story Title story 14 18 Concreting within tight reinforcement Because in this area for concreting alone the reinforcement consisted of 776 t of steel, the meshing structure was so dense that specially marked concreting openings (d = 0.2 m) were planned in a 10 m x 10 m grid for inserting the end hoses (see fig. 14). This allowed the boom to be mainly moved from point to point at lengthy intervals. However, the machine operators could not take their eyes off the ball for a moment, because the interruptions caused by the frequent changes of truck mixers had to be agreed with the concreting team. In addition, the machine operators also had to keep the other placing booms and cranes within view, as they were moving at the same time. Not an easy job, when you consider that on this particular day, work started around 4:00 am in the depot at betonlift, and that the construction site had special permission to work until 11:00 pm, to be on the safe side. 15 for the next round of work. And because every construction site worker is welcome, we have a good reputation. It helps us particularly when, being far from home, there are problems from time to time. For example, a locksmith can be on hand quickly if necessary, or people who can help to clear out a pipe fast if there is a blockage. In my opinion, we get back many times what we‘ve put in.” Guten Appetit, or is that Bom Apetite? The same must surely apply to the men from Zucotec, mostly Portuguese, who were responsible for placing the concrete inside the reinforcements, spreading it, venting and smoothing it. As a spicy aroma begins to waft across the pit around the middle of the day, we cram into one of the site containers in search of the chef, who proudly presents two trays of fried chicken for his fellow Portuguese countrymen (see fig. 16). At around 9:30 pm, the last Holcim truck mixer has been emptied, and even all 2,650 m³ of the top layer of floor concrete, with its target consistency of F5, has been successfully placed. All that remained was smoothing, tidying up and cleaning. And when PM asked again the following day how the collaboration went, project lead Silke Pförtner and Franz Syrowatka from betonlift agreed: “The work was hard but was shared equally and ran smoothly.” ■ © www.datenland.de ‚ The Dancing Towers of St. Pauli Soon to reach up to 85 m in height, the pitched “Dancing Towers” have already become the new symbol of the St. Pauli district. Combined with the inclinations in the buildings‘ structure, nocturnal illumination is meant to make it look as though the towers are dancing. Top planning combined with a good working atmosphere produces a high level of efficiency In addition to offices and a hotel, the “Mojo Club” will return to its former address of No.1 Reeperbahn. From 1993 it was an internationally renowned attention in the nightlife scene of St. Pauli. 16 The working atmosphere and level of cooperation on the construction site were remarkably good. Contributing to this are very good organisation of processes and certainly the mobile combination of workshop and “caboose”, which Jürgen Bitsch from betonlift Hamburg sends to the construction site to supply the team for such large-scale operations (see fig. 17). His explanation sounds quite simple: “When you require a lot from your team, you also have to provide some relief for them. And when you experience what the machine operators and many others have to put up with on the construction site, in cold and wet weather, then it quickly becomes clear that they really value a cup of coffee or a bowl of hot stew. It motivates them and refuels them The towers are due for completion in summer 2012. Webcam at the No.1 Reeperbahn construction site: ‚ http://baustelle.strabag.at (various construction sites can be viewed) 17 Spectacular construction projects by architects Bothe Richter Teherani: ‚ www.brt.de Always worth a visit – the Hanseatic city of Hamburg ‚ www.hamburg.de p Because of the extremely dense network of reinforcements, the workers can only feed in the end hose at the specially marked points. t An army marches on its stomach: A hearty stew with sausages from the “betonlift canteen” and Portuguese fried chicken “à la Zucotec” provide new strength. t Working in the supporting ground: Zucotec workers are inside the reinforcements while the bottom layer is being concreted. 8 PM 4307 GB PM 4307 GB 9 On site On site 19 The making of a “Modern Marvel” [Putzmeister America, October 2009] The Mike O‘Callaghan-Pat Tillman Memorial Bridge – better known as the Hoover Dam Bypass Bridge – is one of the most ambitious construction projects in the USA. With a span of 323 m between the twin concrete arches, once complete, it will be the longest in North America and the fifth longest concrete arch bridge in the world. Its apex reaches a height of 274 m over the Colorado River. Stationary concrete pumps and placing booms from Putzmeister mastered the high demands of concrete pumping in this Colorado River bridge construction project. As was done 76 years ago, the Hoover Dam is again making its mark in history books. Crews are conquering an engineering feat of constructing the most technically challeng­ ing bridge ever to be built in North America, the Colorado River Bridge. To help place concrete for this one-of-a-kind project, two Putzmeister placing booms and BSA trailer pumps are taking on the obstacles presented by the Hoover Dam surroundings. The bridge is part of the Hoover Dam Bypass project, will hover around 274 m above the Colorado River and run parallel to the dam. The bridge, with two lanes in each direction, is being built in an effort to alleviate traffic on U.S. Highway 93, which currently crosses the Hoover Dam to pass over the Colorado River. Because the highway is the major commercial corridor between Arizona, Nevada and Utah as well as on the North American Free Trade Agreement (NAFTA) route between approach, helping us from the beginning of the project. The placing system they chose to maximize their concrete placement for the arch was MX 32-4 Multi and MX 36-4 Multi placing booms and BSA 2107 HP-E and BSA 2109 H-E trailer pumps.” Mexico and Canada, the traffic congestion (an average of 14,000 vehicles a day) caused by the existing highway across the dam, imposes a serious economic burden to the country. In addition, the traffic volumes, combined with the sharp curves of the highway near the Hoover Dam, create a potentially dangerous situation for Hoover Dam visitors and dam facilities. Once the Colorado River Bridge is complete, no through or truck traffic will be allowed on the existing roadway; only Hoover Dam visitors will be permitted. Overcoming the extreme To date, Obayashi/PSM JV has pumped and placed about 10,000 cubic yards (7,646 m3) of concrete for the Colorado River Bridge. Jeff St. John, project manager of Obayashi/ PSM JV, says the pump manufacturer helped their team determine how and where to mount the placing booms and position the trailer pumps for all portions of the project. “For construction of the twin arches, we positioned one trailer pump near the base of the Nevada arches and one on top of the arch footing in Arizona,” comments St. John. “A placing boom was also positioned on each the Nevada and Arizona side of the twin arches.” The separate placing booms and their pedes­ tals were flown via crane to each of the twin arches for mounting on their specially-de­ signed platforms. As a result of the blazing heat, and to prevent traffic problems, most of the concreting was carried out at night. 20 Choosing the right system Obayashi/PSM JV, a joint venture of Obayashi Corporation and PSM Construction USA, Inc., the general contractor, began construction on the 579 m long open spandrel deck arch bridge in early 2005. Obayashi/PSM JV had its work cut out for them; the project included the pre-casting and erection of pier columns up to 91 m tall; construction of the twin, cast-in-place segmental concrete arch spans; and the installation of temporary twin cable stays that have a 762 m span and are 101 m tall to support the arches during construction. “We called Putzmeister right away to discuss the project and what our possible concrete placing solutions for this complicated project would be,” says Wes Pollnow, construction manager of Obayashi/PSM JV. “We needed to know which solution would make the most sense and which would be most efficient; they have a true complete systems Planned amounts of concrete and steel for bridge construction 69 N/mm2 concrete in the arches 6,499 m3 41 N/mm2 concrete in the pier columns and caps 6,395 m3 31 N/mm concrete in the bridge deck 4,193 m3 28 N/mm2 concrete in the footings and abutments 5,106 m3 21 N/mm concrete for column infill 1,575 m3 2 2 Reinforcing steel 3,765 t Structural steel 3,084 t Post-tensioning steel (permanent) 384 t Post-tensioning steel (temporary) 680 t 10 PM 4307 GB PM 4307 GB 11 21 On site On site 23 In order to avoid the intense heat and avoid traffic congestion, most of the concrete placements occurred at night. Once the placing booms and trailer pumps were in position, they were ready to step up to overcome the 38 °C weather, while pumping and placing the notorious, harsh Nevada concrete mix up 85 m and out 162 m. “All of the concrete mixes used for the arch were advanced concrete mix designs using harsh aggregates,” says St. John. “Liquid nitrogen has been used extensively for precooling of the concrete in order to reduce the temperature the concrete reaches during curing.” For the arches, a high-strength 69 N/mm2 concrete mix was used, and for the columns and pier caps a high-strength 41 N/mm2 mix was used. Early in the project the concrete mixes were provided by Casino Ready Mix and Silver State Materials (now a part of the CalPortland Company), however in late 2007 Obayashi/PSM JV began operating their own concrete batch plant for the arch and deck concrete, and will continue to make their own until the project is complete. “Even with the combination of the heat and the harsh mix, the trailer pumps were able to easily maintain a continuous concrete flow, at a timely pace, up to the placing booms so it would not clog the pipe system in the extreme conditions,” comments Pollnow. “In addition, the S-valves on the pumps had no problem gulping down the tough concrete mixes.” The trailer pumps are able to provide a smooth, more controllable output of concrete because of each pump’s free flow hydraulic technology. Both pumps have a fully adjustable volume control to allow very slow pumping while retaining full concrete pressure. The pumps have been outputting around 12 m3/h due to the job site’s extraordinary environment conditions. “The pumps really provided that extra muscle we needed to push the concrete up and out to its final destination, and in fact, both trailer pumps have the capability to pump concrete up to 244 m high. Also, the capabilities of the placing booms helped immensely to reach the exact point of concrete placement for each segment of the twin arches. Again, because of the unconventional setup, we really needed dependable booms, and they did not disappoint.” t The airy workplace for the placing booms 1 PM 4307 GB Quinn Concrete Pumping, Las Vegas Quinn Concrete Pumping, Inc. (Quinn) of Las Vegas has also lent its services to the Colorado River Bridge project. Quinn has supplied both pump operators and has provided their own Putzmeister equipment. “Quinn was on site quite early on in the project for the footing and arch foundation concrete,” notes St. John. “They are a great team to work with, very dependable. We expect they’ll also be involved with placing the deck concrete as well.” Most notably, Quinn’s M 42 and M 58 truckmounted concrete boom pumps were on site back in 2005 to pump and place concrete for the Colorado River Bridge’s pier. The pier provides foundation for the vertical columns needed to support the arch of the bridge. “The 58-meter boom pump was positioned atop a cliff’s edge on site, and used its full boom length to place concrete into the hopper of the M 42 which was situated in a gorge below on another cliff,” says Pollnow. “The M 42 then stretched its boom to pump and place the concrete to its final destination. The equipment setup and performance was truly remarkable.” As of October 2009, Quinn has placed about 3,823 m3 for the Colorado River Bridge project and about 80 percent of the bridge was complete. The remaining work on the project includes erecting the precast spandrel columns, installing tub girders, casting the pier caps, the deck, then the barrier walls and approach slabs. Concrete placement is anticipated to be complete during summer 2010, with the bridge opening for public use in November 2010. ■ p Each state had a stationary concrete pump: one in Nevada and one on the Arizona-side of the Colorado River. 22 Hoover Dam Bypass Bridge Boulder Dam? Hoover Dam? Originally started as the “Boulder Dam” project, the dam was renamed to “Hoover Dam” at the beginning of the official construction phase. At this time, Herbert C. Hoover was standing for re-election as president. Despite linking his name to this construction project, which created many thousands of jobs during the Great Depression, Hoover lost the election. In 1933, the dam was again called Boulder Dam, but 14 years later, and ever since, the dam was again called Hoover Dam. Owner/Developer: Federal Highway Administration/Washington, D.C. · Arizona Department of Transportation/Phoenix, Arizona · Nevada Department of Transportation/Carson City, Nevada · U.S. Bureau of Reclamation · National Park Service · Western Area Power Administration/Lakewood, Colorado Design Team: T.Y. Lin International/San Francisco, California · HDR Engineering · Sverdrup Civil, Inc. General Contractor, Concrete pump supplier and concrete ready mix supplier: Obayashi/PSM JV, a Joint Venture of Obayashi Corporation and PSM Construction USA, Inc./Boulder City, Nevada Concrete pump sub-contractor: Quinn Concrete Pumping, Inc./Las Vegas, Nevada Additional concrete ready mix suppliers: Casino Ready Mix/Las Vegas, Nevada · Silver State Materials/Las Vegas, Nevada Equipment: Obayashi/PSM JV: Stationary concrete pumps BSA 2107 HP-E and BSA 2109 HE, placing booms MX 32-4 Multi and MX 36-4 Multi Quinn Concrete Pumping: M 42 and M 52 truck-mounted concrete pumps PM 4307 GB ‚ The Hoover Dam – interesting and intriguing Concrete on a huge scale The Hoover Dam was constructed as an arch gravity dam between 1931 and 1935 with a height of 221 m and a crest width of about 14 m. The base width is 201 m. Approximately 2.6 million m3 of concrete was used in the construction of the dam. The dam was not cast as a single piece but, instead, was created from a large number of individual trapezoidal concrete blocks that were 1.5 m in height. Each block contained a series of pipelines through which the cool water circulated. As a result, the heat that is produced as the concrete sets is conducted away at a considerably quicker rate. Without this measure, the concrete would have taken approximately 105 years to cool! The metropolis of gambling grew as the dam grew The town of Boulder City was built specifically to house workers involved in the construction along with their families. However, gambling and alcohol were prohibited in Boulder City. It was therefore only logical for workers to use their free time to make the pilgrimage to the small desert settlement of Las Vegas, 50 km away. Bars and Casinos started to emerge in no time. Las Vegas without electricity? Unimaginable! However, a curious fact is that at the time when the electricity purchasing rights from the hydroelectric power station at the Hoover Dam were being negotiated, the desert city‘s mayor at that time rejected any purchase, saying “Las Vegas will never have more than 5,000 inhabitants”. As a result, Las Vegas currently only receives about three percent of its annual electricity demand from the nearby Hoover Dam hydroelectric station. 1 On site On site 24 26 In March of this year, a brand new M 6-6 travelled over 9,000 kilometres on the Trans-Siberian Railway from Moscow to Vladivostok. The customer – Stroitel’nyi Aljans – is currently using this long-reach boom pump 180 km away in Nakhodka, a port city on the Pacific coast of the Russian Far East. Together with its older brother – an M 44-5 that was manufactured in 1996 and that Stroitel’nyi Aljans acquired second-hand from Japan in 2004 – the M 62-6 is concreting the base of a large oil platform. t Well lashed – in Moscow, the M 6-6 commences its long journey to the far east with the Trans-Siberian Railway. Russia – vast country, long journey: 9,000 km by train to the site This GBS – Gravity Based Structure – consists of a concrete slab that has an area of approximately 100 x 127 m and is 13 m thick and on which four shaft towers – 25 m in diameter and 41 m high – will be erected. The complete structure will be concreted on land and will then be towed by ship to an oil field just off the coast of the island of Sakhalin and, from there, it will be lowered to the seabed at a depth of 35 m. The client is the Norwegian company Aker Solutions. In total, the two Putzmeister pumps will place 55,000 cubic metres of concrete before the end of 2011. ■ ‚ www.sakhalin.ru/engl/ Information about Russia‘s largest island (engl.) ‚ www.sakhalin1.com/en/ An area just off the coast of the island of Sakhalin in the far north-east of Russia is said to contain the largest untapped reserves of oil and gas in the world. In oil alone, it is estimated that there are 13 billion barrels in this area. The Arkutun-Dagi field – part of the Sakhalin-1 project and the future site of use for the GBS that is currently under construction in Nakhodka – is located only a few kilometres off the coast of Sakhalin. The US oil company Exxon-Mobil is investing about 12 billion US dollars in the development of the three oil and gas fields (in total), amounting to the largest direct investment by a foreign company in Russia to date. Approximately 13,000 jobs have been created (directly and indi- China Information about the oil and gas development of Sakhalin-1 (engl.) Written and researched by the locals, “Way to Russia” is a very popular independent guide to Russia online (engl.) rectly) from the development of these raw material reserves and the tax revenue for the region has doubled. The island has the highest proportion of foreign nationals of all the Russian regions and an above-average share of English-speaking Russians. Russia Kamchatka Peninsula Sea of Okhotsk Arkutun-Dagi oil and natural gas field Sakhalin ‚ www.waytorussia.net q In the port city of Nakhodka, the M 6-6 and M 44-5 together are pumping a total of 55,000 cubic metres of concrete for an oil platform. Arctic Ocean Vast oil and gas reserves in the Russian Far East r Ku Nakhodka North Korea Hokkaido il ds an Isl Pazific Ocean 25 Sakhalin – affectionately named “the wild dishevelled animal” in the language of the indigenous people – is 948 km long and between 27 and 160 km wide and is situated to the north of the Japanese island of Hokkaido in the Pacific. With 650,000 inhabitants, this is Russia‘s biggest island and only 3,150 of these inhabitants belong to the indigenous groups of the Nivkh, Nani, Orok and Evenki. They live selfsufficiently, as fishermen, as herdsmen or by collecting wild plants. Ceded to the Russian Empire in 1875, the south of the island was ruled by Japan from 1905 until 1945. The few remaining indige- nous people were forced to leave their homeland and travel in the direction of Hokkaido. Since the 19th century, the island had been used as a penal colony for Russian prisoners. The inhabitants who live there today – except for those who immigrated as a result of the raw materials boom – are descendants of the former forced labourers. With approximately 175,000 inhabitants, the island‘s capital Yuzhno-Sakhalinsk is the largest city on the island. However, most of Sakhalin is made up of largely untouched boreal forest or mountains and has a population density of 6.2 inhabitants per square metre – half as much as in Norway. Sakhalin – Сахалин 27 14 PM 4307 GB PM 4307 GB 28 Sakhalin is currently trying to find a balance between becoming an ambitious economic region and nature resort, between tourism ambitions and the threat of damage to the environment. q (from left to right) Cape Tihii (“Quiet Cape”) in the Sea of Okhotsk · Nivkh hunters in their traditional dress · The state museum in Yuzhno-Sakhalinsk provides evidence of the former Japanese reign · The island of Zametny in the Tihaya Bay 29 30 15 50 questions The company · Question 9 How does Putzmeister manage to be such a global presence? Putzmeister promises “Competence near you”. This is a bold claim for a company whose customers are dispersed all around the world. It‘s a claim that Putzmeister lives up to with modern communications technologies, a dense service network and the best possible relationships with distribution partners in every corner of the globe. Since Putzmeister sold its first machine abroad, the company has gradually opened up one world market after another. Peter Dörr was an instrumental part of this process. Since 1984, the 67-year-old has travelled the Near East and the countries of Asia in order to sell machines made in Aichtal. And his record is a successful one. “In Vietnam, we started out as a tiny operation. We sold our first machine at an agricultural trade fair,” recalls Dörr. Hoang Minh Hung turned out to be a born entrepreneur. In 2001, he employed a technician for the after-sales service and set up a small spare parts warehouse in Hanoi. His company, Minh Hoang & Co, now has 20 employees and two offices in Hanoi and Ho Chi Minh City. Many Putzmeister distribution partners all over the world can tell a similar story. “These partners have grown with us. This results in very close and resilient relationships,” says Dörr. A close network of specialists 50 questions 9 32 subsidiaries and dealers is now present in more than 100 countries. The headquarters in Aichtal and the regional subsidiaries offer support in the form of service engineers, training specialists and a team of service technicians. Together, they ensure that Putzmeister customers always receive competent advice, are efficiently supplied with spare parts and can depend on a speedy and reliable after-sales service, no matter where in the world their machines are put to use. In many cases, Putzmeister service technicians do not even need to visit the site. Thanks to modern telecommunication technologies, they can often diagnose and rectify fault causes easily from their PC. Our Putzmeister Partner in Vietnam: This is how Putzmeister continues to guarantee “Competence near you” worldwide. ■ Minh Hoang & Co. 4 Pham Huy Thong · Hanoi Asked about the secret of his success, Dörr doesn‘t take long to find a response: “You have to be interested in people. Of course, you also need a good product. But interpersonal relationships are crucial. If you want to be successful in a foreign country, you need to have distribution partners there who are prepared to nurture these relationships and will be there for their customers 100 percent.” Putzmeister has mostly been blessed with a lucky touch when it comes to the selection of distribution partners. The worldwide service and distribution network of Putzmeister Hoang Minh Hung is one of these distribution partners. The 47-year-old represents Putzmeister in Vietnam. “He‘ll bend over backwards for us and his customers whenever it‘s necessary,” says Peter Dörr. When Dörr first met Hung back in 1993, Hung had no capital. What he did have, however, were intimate and trusted ties with many potential customers, and he was convinced by Putzmeister products. Dörr gave Hung a moped. They would dash through Hanoi and Ho Chi Minh City, sometimes even side by side, to visit customers and deliver spare parts. q Hoang Minh Hung (nd from left) with his family and the partners of Putzmeister: Friedemann Bornträger (rd from left), Peter Dörr (nd from right) and Johnson Ong (far right) Mr. Hoang Minh Hung Tel: +84-4-1950 Fax: +84-4-195 E-mail: mhc-hanoi@hn.vnn.vn p Since the 1990s, Putzmeister concrete pumps have even serviced Vietnamese construction sites. 31 q A Putzmeister stationary concrete pump on the way through the streets of Hanoi. 33 q In Vietnam, the motto is “even the smallest moped has room”. 34 ? We‘ve picked 50 questions from over 50 years of Putzmeister and given the answers some serious thought. From now on, we‘ll be featuring one question in each new edition. 16 PM 4307 GB PM 4307 GB 1 On site On site MXKD 50 and BSA 110 HP D concreting the underground rail station in Yenikapı / Istanbul In February 010, the time had finally come: an MXKD 50 on a 15 m lattice tower and a BSA 110 HP D stationary concrete pump began concreting the Yenikapı railway station. 35 I STA N B U L 36 This is the only station of the new Marmaray tunnel line being constructed using the cutand-cover method. Its bottom surface mea- sures approximately 300 m long and 35 m wide. For the concreting of the foundations, it was divided into a total of 29 sections. Each section – approximately 10 x 35 m and 2 m thick – is being concreted monolithically in multiple layers of 40 cm. Each layer contains some 120 m3 concrete, which produces an average of 650 m3 for each of the 29 sections. . Technical data BSA 110 HP D Output up to Concrete pressure up to Engine Delivery cylinder Ø Stroke 102 m3/h 220 bar 330 kW Diesel 200 mm 2100 mm rus o osp B 38 Historic city center aray on m r a ti M l sec e n n tu Yenikapı t Pipeline fastenings in the horizontal section ZX 15/5”-10 bar Sea of Marmara MXKD 50 at the centre of an archaeological sensation The construction of a new, state-of-the-art transport interchange is supposed to be underway here, in Yenikapı, on the European side of the Bosporus: a major rail transit station to serve the 15-million metropolis of Istanbul. When the ground was broken back in 2004, nobody thought that the project would be set back by the discovery of an important transport hub from Constantinople‘s past. What was a great moment for archaeology (Yenikapı is the largest urban excavation and one of the most significant finds in Turkey) has caused developers to suffer serious time delays and, of course, to incur enormous costs. Yenikapı is situated on the southern shore of Istanbul‘s old town on the Sea of Marmara. With the future construction of its major rail transit station serving the “Marmaray” undersea tunnel under the Bosporus strait, Yenikapı is intended to offer passengers a means of changing from overground to un- q While some go to work with heavy machinery, others require rather more delicate tools, such as a trowels and brushes. In the foreground are unearthed fragments of the ancient harbour wall. derground trains. Originally, a new regional train station had also been planned in order to connect suburban commuter traffic to the East-West network. However, this aspect of the project had to be changed: such is the importance of the ancient port, the local heritage trust decided that it would have to remain exactly where it is. q Discovery site of one of the wooden ships 39 37 First of all, the excavation of the pit for the new, 21st century subway station on the Marmaray tunnel line unearthed a series of ancient walls. As it turned out, these belonged to an important Byzantine trading port, a transport hub of the “global world” dating back to around 400 AD. The “Port of Theodosius” – named after the last ruler of the Eastern Roman and Byzantine Empire – contained the remains of, to date, more than 30 ships, the largest single discovery of ship relics anywhere in the world. Among them were four Byzantine dromons, the oldest warships ever to have been discovered. They must have been sunk around 1000 AD. 18 PM 4307 GB PM 4307 GB 19 On site In brief 40 41 43 Putzmeister Academy Seminars 010/011 p Hydraulic gate valve GVHM / converted for installation in a vertical line p The hopper of the stationary concrete pump is cleaned under high pressure, and cleansing water is then pumped through forwards. Five set-up sites are planned for the MXKD 50, which will all enable it to reach each point of the foundation area. This means that it will have to be relocated four times. The boom anchor set is located in the centre of the reinforcement of one of the foundation sections. As the boom foundation needs to have a certain amount of strength before subsequent anchoring can take place, a defined workflow has been planned for the concreting of the individual positions. When each section gets its turn is absolutely crucial to avoiding unnecessary waiting times in the re-siting of the lattice tower. The concrete mix is particularly challenging. Despite a strength class of “only” C40, the high additives content makes it awkward to pump. These additives are necessary because the concrete must be able to withstand a high groundwater pressure. Our seminar brochures for 2010/2011 (German language), containing dates and information about courses and training, will be sent out by post in October. Find out about the current dates for the next “season”, sign up in good time and reserve your customised company seminar. In our seminar brochures for different target groups, we demonstrate what is important: preventing accidents, increasing efficiency and lowering costs. If you have not yet received your copy, then please contact us by e-mail: akademie@pmw.de In total, the concreting time of the subway station (foundations, walls, shafts, etc.) is estimated to take 15 months to complete. ■ q The huge stationary boom at the start of foundation concreting. In the background are the tunnels of the future underground line. 42 Launch of the first dredging boat in China with solids pump KOS 5100 q Many representatives from the Chinese regional government and industry representatives took part in the official naming ceremony of the “Guohai I”. (4th from the right) Gerhard Schäffer from PSP 44 At exactly 9:09 am on 6th June, 2010, the ship “Guohai I” (Chinese Sea) was named and launched at the port of Rongcheng (in the province of Shandong) in an official ceremony. This dredger from the Chinese manufacturer Guohai Meister (a co-operation partner of Putzmeister Solid Pumps GmbH) is the first dredger that has integrated a KOS 25100 piston pump and transports the sludge in a closed pipeline. The dredging sludge can be pumped across longer distances using a lower water content and this accelerates the process of land reclamation considerably. 0 PM 4307 GB PM 4307 GB 1 In brief In brief Putzmeister at construction sites in India 45 Climbing booms and stationary pumps at the Ruby Mill Tower in Mumbai At the Ruby Mill construction site in Mumbai, two MX 32-4T self-climbing stationary booms and two pumps of the type BSA 1408 HD are being used. In total, 50,000 cubic metres of concrete has to be placed. The pumps are cleaned using sponge balls and wash-out pigs by simply pumping them with water. There is no need for any separate cleaning station. 1,100 m of concrete is used for each level, including the ceilings, columns and inner walls. Two levels are completed each month. 3 Concreting data Concrete type Compressive strength Slab M 40 > 40 N/mm2 Column M 50 > 50 N/mm2 Inner wall M 50 > 50 N/mm2 Slump measure (ø) 140 mm Concrete delivery pressure 200 – 220 bar 46 Ruby Mill Tower Once complete, the Ruby Mill Tower will be 185 m in height and have 34 levels (four of which are parking areas). The total usable area of 78,000 m2 will mostly be used as office space. The building was designed by the New York architects FxFowle, analysis and design was carried out by LERA and the Indian company Vascon Engineers undertook the construction of the building. Construction commenced in 2007 and the building should be complete by the end of 2010. 48 Essar Oil Refinery in Jamnagar: Four truck-mounted concrete pumps in action Essar is using the first Putzmeister M 42-5 in India to concrete one of the largest refineries in the world at Jamnagar in West India. Together with three of the eight M 36 pumps from the fleet, the “new” edition pumps reliably throughout the day and night. The Putzmeister India After Sales & Parts Service is regarded highly by the people at Essar, but the message from Deepak Kumar Singh, Managing Director of Essar HED, is clear: “For me, the machines by Putzmeister are simply the best for concreting.” 47 p Teamwork: Three M 6 and the new M 4-5 are placing 1,400 m of concrete Essar Oil The Essar Oil Refinery in Vadinar/Jamnagar in the state of Gujarat lies on India‘s west coast, ideally located close to the oil-rich Gulf states. It is one of the largest refineries in the world. The Indian conglomerate, Essar Group, is active in the fields of steel, oil and gas, energy, communication, transport/logistics, construction and raw materials. PM 4307 GB PM 4307 GB Safe. Clean. Simple. The new Pin Pour 50 49 Work safely and cleanly! • Stop dangerous goosenecks! • The boom is steadier – constant flow of concrete, even at low output • No risk of injury from concrete splatters Reduce your operating costs! • Quick and easy assembly • Less wear of delivery line pipe and end elbow • Economic • Affordable 51 for all end hoses with Ø 125 mm Order now: Phone +49 (0) 173 3 09 26 63 · spareparts@putzmeister.de Hotline for technical questions: +49 (0) 7127 599-297 PM 4307 GB