Chapter 3: The Project Management Process Groups: A Case Study

advertisement
CIS 486 Managing Information
Systems Projects
Fall 2003
(Chapter 3)
Jongwook Woo, PhD
jwoo5@calstatela.edu
California State University, LA
Computer and Information System Department
Jongwook Woo
Chapter 3:
The Project Management
Process Groups: A Case Study
Jongwook Woo
1
Learning Objectives
„ Describe the five project management process groups,
 the typical level of activity for each,
 and the interactions among them
„ Understand how the project management process groups
relate
 to the project management knowledge areas
„ Discuss how organizations develop
 information technology project management methodologies to meet
their needs
Jongwook Woo
Learning Objectives
„
Review a case study of an organization

„
applying the project management process groups to manage an
information technology project
Understand the contribution that

effective project initiation, project planning, project execution,
project control, and project closing
–
makes to project success
Jongwook Woo
2
Project Management Process Groups
„ Project management can be viewed
 as a number of interlinked processes
„ The project management process groups include
 initiating processes
– Define the business need for the project
– Need sponsors and project manager
– Initiates to end a project
• Document lessons
• Reassign project resources
• Ensure that the customer accepts the work
 planning processes
–
–
–
–
To define the scope of the project
Estimate costs
Decide what resources to procure
Often revise project plans during project life cycle
Jongwook Woo
Project Management Process Groups
„ The project management process groups include (Cont’d)
 executing processes
–
–
–
–
–
–
Developing project team
Providing leadership
Assuring project quality
Disseminating information
Procure necessary resources
Deliver the actual work
 controlling processes
– Monitor progress against the project plan
– Take corrective action when necessary
 closing processes
– Archiving project files
– Document lessons learned
– Receive the formal acceptance of the delivered work
Jongwook Woo
3
Project Management Process Groups
(Fig 3-1)
„ The process groups are not isolated events
 Occurs at varying levels of intensity through out each project phase
 The level and length varies for each project
„ Executing Processes
 Normally requires the most resources and time
„ Initiating and closing
 Normally requires the least resources and time
„ The process groups can be applied to each phase of a
project
 Concept, Development, Implementation, Close-out
Jongwook Woo
Figure 3-1. Overlap of Process Groups in a Phase
(PMBOK® Guide, 2000, p. 31)
Jongwook Woo
4
Table 3-1. Relationships Among Process Groups and
Knowledge Areas (PMBOK® Guide 2000, p. 38)
Jongwook Woo
Table 3-1. Relationships Among Process Groups and Knowledge Areas
(PMBOK® Guide 2000, p. 38)
Jongwook Woo
5
Developing an IT Project Management
Methodology
„ Just as projects are unique,
 so are approaches to project management
„ Many organizations develop their own project management
methodologies,
 especially for IT projects
„ Blue Cross Blue Shield of Michigan used the PMBOK as a
guide
 in developing their IT project management methodology
Jongwook Woo
Figure 3-2. ITPM Methodology
See figure in text. Note that
many parts of this approach
map to the PMBOK, but
some activities have been
changed to meet the needs
of the organization.
Jongwook Woo
6
IT Project Management Methodology
of Blue Cross Blue Shield
„ Contrast to PMBOK Guide 2000
 The overriding financial investment in S/W development
– Mainly Salaries not materials
 Most of the procure functions
– Scope Planning and Definition
– Resource Planning
 Add a project workbook
– Keep track of the large amount of document necessary
– Serve as an information resource for team members
• A hard-copy record of project activities
 Add issue control
– Handle the inherent complexity of IS and rapidly changing technology
 Work Plan Development
– Combine the PMBOK processes
• Activity sequencing, definition, duration estimating, and Schedule
Devlopement
Jongwook Woo
Case Study: JWD Consulting’s Project
Management Intranet Site
„ This case study provides an example of
 what’s involved in initiating, planning, executing, controlling, and closing
an IT project
 Uses some ideas from the PMBOK Guide 2000, Blue Cross Blue shield of
Michigan methodology, and its own unique project needs
„ You can download templates for creating your own project
management documents from the companion Web site for this
text
„ Note: This case study provides a big picture view of managing a
project.
 Later chapters provide detailed information on each knowledge area.
Jongwook Woo
7
Project Initiation
„ Initiating a project includes
 recognizing and starting a new project or project phase
„ Some organizations use a pre-initiation phase,
 Project Scope Management
 while others include items like developing a business case as part of
initiation
„ The main goal is to formally select and start off projects
„ Key outputs include:




Assigning the project manager
Identifying key stakeholders
Completing a business case
Completing a project charter and getting signatures on it
Jongwook Woo
Project Initiation Documents
„ Business case: See pages 74-76
 Document during or before project initiation
 Introduction/background
– JWD’s CEO believes that its intranet with project management information and
service to current and potential clients can increase its business
 Business objectives
– JWD’s goal is to continue growth and profitability
– The intranet project will support these goals by the visibility of its expertise
– It will also reduce the internal costs by providing standards from the intranet to
internal consultants








Current situation and problem/opportunity statement
Critical Assumptions and constraints
Analysis of options and recommendations
Preliminary project requirements
Budget estimate and financial analysis
Schedule estimate
Potential Risks
Exhibits
Jongwook Woo
8
Project Initiation Documents
„ Charter: See pages 77-78, also shown on next two slides
 A project manager drafted a project charter
 The project manager had the project team members reviews it
 A stakeholder made a few minor change
– and all stakeholders signed it
 A stakeholder – for example, a senior consultant – put a comment
section about his concern
„ Note: Every organization has its own variations of what
documents are required for project initiation.
 It’s important to identify the need for projects,
 who the stakeholders are,
 and what the main goals are for the project
Jongwook Woo
JWD’s Project Charter
Jongwook Woo
9
JWD’s Project Charter
Jongwook Woo
Project Planning
„ The main purpose of project planning is
 to guide execution
„ Every knowledge area includes planning information (see Table
3-5 on pages 79-80)
 knowledge area
 Process
 Outputs
„ Each organization has the different planning outputs
 Based on its particular needs
Jongwook Woo
10
Project Planning
„ Key outputs include:




A team contract (Not listed in Table 3-5)
A scope statement
A work breakdown structure (WBS)
A project schedule,
– in the form of a Gantt chart with all dependencies and resources entered
 A list of prioritized risks
„ See sample documents on pages 83-90,
 and refer to them later in the course
Jongwook Woo
A team contract
„ For all projects to help promote teamwork
 And clarify the team communications
„ The project manager organizes a kick-off meeting for the Project
Management Intranet Site Project
 After the project charter signed
 Helps the project team get to know each other
– Everyone would be more relaxed
 Explains that a team contract will be the most important tool to help a
project team to work together
 A consultant, a IT member, and a client representative form one project
team contract (Table 3-6)
– Code of conduct
– Particiopation
– Communication etc.
Jongwook Woo
11
A Scope Statement
„ Need to keep in mind for the budget and schedule goals
„ Create a draft scope statement





The number of hours available for each member per month
Any unclearness of the scope of this project?
Any question or issue about the scope of this project?
List the main deliverables for this project
Which deliverables you can help create or review?
„ Scope Statement after a few discussions (Table 3-7)





Project title
Project Justification
Product Characteristics and Requirements
Summary of Project Deliverables
Project Success Criteria
Jongwook Woo
WBS with the Scope Statement
„ Provides the basis for
 Deciding how to do the work
 Creating the project schedule
 Performing earned value management for measuring and forecasting
project performance
„ JWD uses the project management process groups as the main
categories of WBS (Fig 3-3 p87)
„ More about WBS at chapter 5
Jongwook Woo
12
Gantt Chart
„ Provides the project schedule
 Schedules are dependent
„ Gantt Chart (Fig 3-4) for the JWD project
 Understand the dependencies
 Understand what to do and when
 Measure workloads and cost constraints during developing the duration
estimates
 Use, for example, Microsoft Project 2002 to enter all of the information
„ Network diagram (Fig 3-5) for the JWD project
 Emphasize the executing tasks and critical paths
 WBS information, the duration estimates and dependencies, the cost and
resource information
 Detail at Chapter 6
Jongwook Woo
JWD’s Project Gantt Chart
Jongwook Woo
13
A List of Prioritized Risks
„ The project manager reviews the risks
 In the business case
 The comments of the project charter
„ Special meeting
 To discuss and brainstorm potential risks
 List a probability/impact matrix (Table 3.1 p90)
Jongwook Woo
JWD’s List of Prioritized Risks
Jongwook Woo
14
Project Executing
„ It usually takes the most time and resources
 to perform project execution
– since the products of the project are produced here
„ work results
 The most important output of execution
 Table 3-9 (p91) lists
– Knowledge area, processes, outputs of project executions
„ leadership skills needed
 Project managers must use their leadership skills
– to handle the many challenges that occur during project execution
– To produce the desired work results
– Get input from external sources at no additional cost
Jongwook Woo
Project Executing
„ Need to show a milestone report
 CEO and sponsors want to see progress on projects
 Want to see if any potential issues or problems
 Table 3-10 p92
„ Human Resource issues often occur
 Some member may be efficient for his own specific needs
– For example, meeting with clients to ask the expert
 May need to buy S/Ws instead of developed by a member
 May need additional funds from sponsors
 Project manage offers a free family vacations etc for the persons
who provided the best productivity
Jongwook Woo
15
Project Controlling
„ Controlling involves
 measuring progress toward project objectives,
 monitoring deviation from the plan,
 and taking corrective actions
„ Controlling affects all other process groups
 and occurs during all phases of the project life cycle
– Table 3-11 p94, Knowledge area, process, outputs of project controlling
– Affects project scope, schedule, and budget
„ Status and progress reports
 are important outputs of controlling
 Table 3-12 p95 Weekly status report
– With tool such as Microsoft Project 2002
Jongwook Woo
Project Closing
„ The closing process involves
 gaining stakeholder and customer acceptance of the final product
 and bringing the project, or project phase, to an orderly end
 Table 3-13 p97
– Knowledge area, process, and outputs of project closing
„ Even if projects are not completed,
 they should be closed out to learn from the past
„ Project archives and lessons learned
 are important outputs.
 Table 3-14 p98
„ Most projects include a final report and presentations
 Table 3-15 p99
Jongwook Woo
16
Post-Project Follow-up
„ Many organizations have realized that
 it’s important to review the results of projects a year or so
– after they have been completed
„ Many projects project potential savings,
 so it’s important to review the financial estimates and help
– learn from the past in preparing new estimates
Jongwook Woo
17
Download