FASTAWAY SERVICES UK LIMITED Method Statement No : RM(MS).< No. > Method Statement Page No 1 of 3 ANNUAL DRAINAGE FLUSH OUT SERVICES Contract: FULL SITE PORTFOLIO Location: AREAS AS REQUIRED Job No: RD/09/PE/KH Issue No: 1 Validity period: This method statement is only valid between 03/04/09 and 03/04/10 inclusive and must be used in conjunction with any another method statement that details the work operation. Key Risks • Slips, trips, fall. • Manual handling. • Electric shock. NOTE Refer to the Risk Assessment for this contract for specific risks and control measures. Supervision • Engineers are competent and responsible for their own supervision. Special training required • Engineers are suitably trained and competent for the task. Personal protection While undertaking this activity: • All relevant PPE will be utilised during this task. General Safety • All works to be carried out in line with specific Risk Assessment LS0010. RM(MS) <No. > - < description > Master document date - < date > Printed -6 April, 2009 FASTAWAY SERVICES UK LIMITED Method Statement No : RM(MS).< No. > Method Statement Page No 2 of 3 Site Preparation • Client site rules to be understood and obeyed. How to do the work To attend the sites in the complete portfolio for the annual drainage flush out services. To carry out all works required by our fully trained service engineers to clear and clean the drainage systems including the Aco systems and all relevant chambers. To carry out the cleaning works with our Super six HPW Jetting machines and also where applicable the Jetchem Bull dog system. All engineers are fully trained with licenses for the Confined Space Entry Requirements and the NRSW act 1991. To lift all relevant chamber lids and to carry out all HPW Jetting services as required with both the Forward and Reverse jetting systems. All working areas to be closed with the safety barrier systems. 2 men on site at all times for the safety regulations. All chambers to be fully cleaned and cleared prior to replacement. All drainage systems to be fully pressure and water tested to show no blockages prior to completion All working areas to be closed off to the general public by our Safety Barriers and the full Chapter 8 Signage around the working areas for the public and the road users information. All working areas to be left in a clean and tidy state upon completion When we arrive on site to ascertain the blocked drainage systems we would install the complete chapter 8 safety signage and barrier systems where required for the safety of the general public and the service engineers. Once we are in a safe working area we would continue to lift all relevant chamber lids. The service engineers would source a good water supply for the jetting machine. The HPW Jetting services would then start with the aid of the insertion tube for the jetting hose safety so no unforeseen spillage and accidents could occur. Upon the clearance of the drainage system a CCTV would be carried out if this service is required to ascertain the condition of the pipe work to check for any defects. Upon the completion of all works the working area would be cleaned and cleared of any debris and all chamber lids re-sealed and tested. All chapter 8 safety signage and barrier systems removed and all areas re-opened to the general public and road users RM(MS) <No. > - < description > Master document date - < date > Printed -6 April, 2009 FASTAWAY SERVICES UK LIMITED Method Statement No : RM(MS).< No. > Method Statement Page No 3 of 3 Waste disposal • All waste will be disposed of in line with our policy. Statement prepared and issued by: PAUL EGGINTON Date:03/04/09 I / we, the undersigned understand the contents of this Method Statement and confirm that we will follow it while carrying out the work that it covers. If a situation arises that represents a serious and immediate danger to my / our health and safety or the health and safety of others or which represents a shortcoming in the health and safety protection arrangements I / we will bring it to the attention of the Company. Name – PRINT Name – PRINT Name – PRINT Name – PRINT Name – PRINT P EGGINTON G ATKINSON K TOAL C SMALLMAN R HAWKSWORTH Signature Signature Signature Signature Signature P C EGGINTON GEOFF ATKINSON KEVIN TOAL CRAIG SMALLMAN RICHARD HAWKSWORTH Date Date Date Date Date 03/04/09 03/04/09 03/04/09 03/04/09 03/04/09 RM(MS) <No. > - < description > Master document date - < date > Printed -6 April, 2009