iNtegrate 2 Business Process Redesign: Business Process Recommendations Procurement May 31, 2013 Business Process Recommendations: Introduction Business Process Recommendations SUB-PROCESS RECOMMENDATION CONTENTS Recommendations for a redesigned workflow and supporting materials for each of the sub-processes reviewed as part of the iNtegrate 2 BPR project are detailed in the following section. Each sub-process section includes the following: • Process Overview: A summary narrative of key process steps within the sub-process. • Recommended Future State Process Flow: Detailed process flow of the Future State process steps. • Key Process Changes: For those steps within the Future States that represent primary changes (for one or more NSHE institutions), an explanation, and justification as necessary, for the process change is highlighted • Alternative Process Options: Process Options not recommended in the future state flow are highlighted along with a justification of why this option is NOT recommended or incorporated in the process. • Policy Change Requirements: Instances when either institutional or NSHE policy need to be developed or revised in order to facilitate the recommended process are noted, including recommendations for policy content. • Implementation Challenges: When elements of the recommended future state process were questioned during workshops or noted as significant areas where implementation would be difficult, further discussion and justification is provided along with examples of institutions also utilizing the recommended process. • The examples provided are individual institutions utilizing these recommended practices. NSHE represents a diverse set of 8 institutions and the system office presenting limitations in identifying a comparable system or organization that has broadly implemented “best practice” or recommended processes. • Technology Requirements: Elements of a required technology to enable the process are listed by process step. • Reporting Requirements: Reports, metrics and data points required to monitor and control the process are listed. • NSHE Feedback: Index of comments/feedback provided by NSHE institutions and the Huron response, as needed. © 2012 Huron Consulting Group. All Rights Reserved. Proprietary & Confidential. Draft & Confidential, Not for Distribution. 3 Business Process Recommendations POINTS TO CONSIDER Each sub-process section incorporates some fundamental concepts that should be understood in order to fully consider the recommendations and supporting content. • • Recommendations versus Current State: • These process recommendations represent Huron’s recommendations for a future state business process and are not intended to comment on the current state processes across NSHE. • Some process elements may already be the practice of some or all NSHE institutions. Business Process Swimlanes (horizontal bands): • The business process focuses on the process steps and the work accomplished in these steps and not the process owners/work locations. Therefore, the developed flows include general swim-lanes that are not role/location specific, such as Accounts Payable Administration, Travel Administration, Research Administration, etc. • Flows do include required roles like Vendor, faculty/employee/Investigator, etc. but they do not highlight Administrative Assistant, Vice President of X, etc. The recommended process steps can be applied universally and the steps can be aligned in whatever roles/units are appropriate by institution. © 2012 Huron Consulting Group. All Rights Reserved. Proprietary & Confidential. Draft & Confidential, Not for Distribution. 4 Business Process Recommendations POINTS TO CONSIDER Each sub-process section incorporates some fundamental concepts that should be understood in order to fully consider the recommendations and supporting content. • Existing Supplemental Systems: • • Some NSHE institutions have implemented different “systems” or technologies that are supplemental to the Human Resources or Finance Administration Systems. These process flows assume the existing technologies are integrated into the Future State Business Process. Out of Scope Systems: • Some process flows incorporate Non-Human Resource/Finance Systems that are out of scope for iNtegrate 2 (i.e. a Pre-Award “tracking system”). However, in order to be in line with best practice elements, these out-of-scope technologies were incorporated into the recommended processes. © 2012 Huron Consulting Group. All Rights Reserved. Proprietary & Confidential. Draft & Confidential, Not for Distribution. 5 Business Process Recommendations: Procurement Procurement BPR: Requisitions PROCESS OVERVIEW Requisitions represents the sub-process by which end users request goods or services be procured for either themselves or their department/organization and the subsequent review and approval process. • An individual identifies a need for goods or services, either for their use or on behalf of their department/organization (Purchasing Unit). • The Purchasing Unit executes a search for the goods and services in the eProcurement system and either selects the desired item(s) from the normalized list of items/services or completes a form to request goods or services with custom specifications. • The eProcurement system validates funding availability upon submission of the requisition. • The request is routed to the appropriate Purchasing Unit reviewers for review and approval; the request is then routed to Purchasing Administrator for final review and approval (if required based on the type of request submitted) • The Purchasing Administrator determines what, if any, solicitation requirements exist for the request and takes the appropriate steps. • After all appropriate procurement processes are complete, the requisition is fully approved. Draft & Confidential, Not for Distribution. 7 Requisition, Page 1 1: Identify Need for Goods or Services 2: Execute Keyword Search for Required Goods or Services 3: Procurement Application Returns Search Results 4: Desired Goods or Services in Results? Yes 6: View Item Details and Add to Requisition Yes 8: Access Forms Repository to Determine if PreDefined Form Exists for Need A No Continue Shopping 7: Services Acquisition? Yes Form Search No Department A 11: Continue Shopping? 9: Access Forms Repository to Initiate Free-Form Requisition 10: Populate Form and Add to Requisition 13.1: Funds Checking Executes 13.2: Funds Available? A No 12: Populate the Remaining Requisition Information 13: Submit the Requisition for Processing Yes Requisition Approvals No 13.3: Budget Configured for Warning Only? Yes 13.5: Requestor Notified Requisition Amount Exceeds Available Balance No 13:4: Requisition Returned to Requestor Due to Lack of Available Funds End of Process Requisition, Page 2 Form Search 14: Does Required Form Exist? Yes 16: Populate Require Fields (e.g. Suggested Supplier, Service Dates, Estimated Costs) 15: Select Form from Repository 17: Add the Service Request to the Requisition Department No 18: Continue Shopping? No 19: Access Forms Repository to Initiate Free-Form Requisition 20: Populate Require Fields (e.g. Description, Supplier) 21.1: Funds Checking Executes 21.2: Funds Available? 21: Submit Requisition for Processing Yes No 21.3: Budget Configured for Warning Only? Yes 21.5: Requestor Notified Requisition Amount Exceeds Available Balance No 21:4: Requisition Returned to Requestor Due to Lack of Available Funds End of Process Requisition Approvals Yes Continue Shopping Requisition, Page 3 Supervisor / Signature Authority Yes Requisition Approvals 21: Requisition Requires Spvsr. Review? Yes 22: Requisition Routed to Appropriate Supervisor / Signature Authority 23: Requires Additiona Spvsr. Reviews? No No 24: Requires Additional Reviews? No A Yes Yes Additional Approvals 25: Requisition Routed to Appropriate Supplemental Reviewer 26: Requires Additional Reviews? No A 26.1: Funds Checking Executes 26.2: Funds Available? No 26:3: Requisition Returned to Requestor Due to Lack of Available Funds Yes Business Center Review A Requisition, Page 4 Business Center Review 27: Receive Requisition 28: Requires Signed Contract? Yes Contract Review A No 29: Review Requisition and Supporting Documentation Procurement Administration A B 33: Competitive Exception Required? 34: Obtain Approval for Competitive Exception Yes No C 38: Is the Supplier Active/ Valid? 30: Invalid Request? Yes 31: Can Req. Proceed with Corrections? No No B End of Process 35: Valid Competitive Exception? Yes No Yes Bid Decision 36: Can RX Proceed with Corrections? No No Supplier Reg. End of Process Yes 37: Business Center Coordinates with Department to Correct Underlying Issue Yes 32: Work with Institution / Department to Revise Requisition C B Procurement Administration Requisition, Page 5 Bid Decision 39: Requires Bidding Event? No Generate PO Yes Competitive Bid Contract Review Procurement Administration Vendor 42: Negotiate agreement’s terms and conditions with institution Contract Review 40: Draft agreement based on requisition details using standard template 41: Send draft contract to vendor for review 43: Negotiate agreement’s terms and conditions with sponsor 49: Accept terms and sign agreement 45: Department impact? Authorized Official Office of General Counsel Department Yes No 46: Validate the terms, impact, etc. 44: Aid in contract review/negotiation/ validation 47: Conduct Final Review 48: Accept terms and sign agreement End Process Procurement BPR: Requisitions KEY PROCESS CHANGES The following table outlines the major process changes (NSHE-wide) incorporated into the recommended process. Process Flow Title: Process Step(s): Requisitions (Page 2) 14 Requisitions (Page 2) 15 Requisitions (Page 2) 26 Contract Review 40 Contract Review 43 Contract Review 48 Requisitions (Page 1) Requisitions (Page 1) 8 11 Explanation and Change Justification: When users are in need of services, they access a list of forms and select the appropriate one for the current need. The eProcurement system allows users to add multiple items into a single cart. A forms repository is formalized which includes standard contract forms. Standard contract forms are developed and loaded into the general repository so a purchasing department can easily access and use the forms, which are submitted with the requisitions. Users pick from a pre-defined list of services. Selecting a service type initiates the appropriate custom form that will display the fields applicable to the service request (e.g., service start date, service end date, insurance requirements, sources of information). With the transition to an automated procurement application, signature validation is an automated process and enforced by the application prior to the requisition progressing through the complete approval process. Pre-approved contacting forms (e.g., “short form”) are readily available in the ERP via eForms, making it easier for NSHE institutions to leverage existing forms and decrease contracting timelines. Tools and training are developed and widely disseminated and reinforced to allow Procurement Administration to manage and negotiate the straight-forward, template contracts. A consistent set of guidelines is established for signatory authority and used to determine who must sing each agreement/contract depending on contract attributes (dollars, time, unit). Draft & Confidential, Not for Distribution. 14 Procurement BPR: Requisitions ALTERNATIVE PROCESS OPTIONS The following table outlines the alternative process options that are not recommended for implementation. Process Step(s): 22 29 Alternative Process Extensively review requisitions submitted by end users with an active PCard. Justification for Non-Recommendation: While the PCard will remain a valued and highly utilized procurement vehicle even with the implementation of an eProcurement system, requiring additional reviews and approvals for a requisition submitted by a user that has an active PCard could provide a disincentive to using the system. Given that end users with active PCards have already been granted the autonomy to procure goods and services with their PCard without prior authorization, consideration should be given to designing workflow rules that reflect that autonomy. By negotiating contracts with defined terms and conditions and pricing and making the items available to end users in the eProcurement system via a list of predefined goods and services, NSHE/Purchasing Administration is removing much of the variability associated with a requisition. Require Purchasing Administration (Central) review of requisitions below a certain dollar threshold where all line items were selected from Therefore, we do not recommend subjecting a requisition containing only the pre-defined list of contracted goods or services. goods or services selected from that same list of predefined goods or services to further review by the Purchasing Administration (Central) provided the requisition total is below a certain threshold. Draft & Confidential, Not for Distribution. 15 Procurement BPR: Requisitions POLICY CHANGE REQUIREMENTS The following table outlines the policy change requirements necessary to facilitate the recommended process. Policy Level: Policy Requirement Type: Policy Development/Addition/Change Requirement: Each NSHE institution has a specific set of rules for competitive exceptions, in some cases varying across institutions. NSHE Change/Develop NSHE should develop consistent policy, at the System level, to be followed by all institutions, outlining what constitutes a valid competitive exception. Policy development should include validation and perspective from all institutions, and their legal representation, to ensure a consistent application of existing competitive exception rules. Change management, with a focus on communication and training, will help with policy implementation, specifically allowing for consistent interpretations of policy across individuals and institutions. Each institution should ensure formal policy is in place defining signature authority for all agreement contracts. Institution/NSHE Reinforce Signature authority varies across institutions, which can result in less sub-optimal contract review / signature processes. Implementing a standardize signature authority policy will not only aid the contract review process, but also streamline the implementation of the associated rules in the future state ERP. We recommend as escalation scheme where depending on dollar value, timeframe, and unit committing funds, signatory authority can be leveraged to the appropriate level within the institution. Draft & Confidential, Not for Distribution. 16 Procurement BPR: Requisitions IMPLEMENTATION CHALLENGES Some recommended process changes may be particularly challenging during the implementation phases. Implementation Challenge Area: Data Acquisition for Workflow • Currently signature authority, where required, is obtained via manual workflows. Capturing the supervisor chain or owners of funding sources and storing the data in a procurement system presents data acquisition considerations that will have to be addressed by NSHE institutions should intradepartmental workflows be captured within the procurement application. • Consensus will need to be gained amount NSHE institutions to determine if goods or services from multiple suppliers can be processed in a single cart. Recommended Process References Institution: Midwestern Public University Ivy League Research Institution Current Process: The University maintains signature authority for funding sources as a part of their organization setup within their ERP (currently Banner). This information is synchronized with their eProcurement system to drive departmental workflows. Any changes made to the “ownership” of the funding source within the ERP are immediately reflected within the procurement system, allowing for a single point of maintenance for this information. The university also allows goods or services from multiple suppliers to be processed in a single cart. This university, characterized by having a highly decentralized procurement process, collected supervisor chain information as a part of the deployment process. Prior to activating an organization’s access to the eProcurement system, the deployment team worked with representatives from the department to document the existing supervisor chain. Supervisor data was stored and maintained in their Oracle ERP system. Draft & Confidential, Not for Distribution. 17 Procurement BPR: Requisitions IMPLEMENTATION CHALLENGES Some recommended process changes may be particularly challenging during the implementation phases. Implementation Challenge Area: Varying interpretations of valid competitive exceptions • There are well defined rules for what constitutes a valid competitive exception and our recommendation is that these rules be integrated into a consistent, NSHE-wide policy. • However, even with consistent policy, differing interpretations can occur across institutions and even across different individuals within institutions. As noted by NSHE, these varying interpretations can also be the result of institutions being pressured to accept exception, even when this represents a less “obvious” interpretation of exceptions. • In order for consistent policy to be effective, and meet the goals of our recommendation, consistent interpretation is also a critical process element. • Close communication between the institutions and NSHE can help ensure even more consistent application of existing competitive exception rules. In addition, all institutions should have a formal process for documenting the exception request, review of the request and end result. • This formal documentation process and a clear policy should empower institutions to only approve exception requests when they truly fit the criteria and if additional validation is required, such as precedents previously set within NSHE, institutions can coordinate to support each other in this effort. Draft & Confidential, Not for Distribution. 18 Procurement BPR: Requisitions TECHNOLOGY REQUIREMENTS The following table lists the system technology requirements necessary to support the recommended process. Process Flow Title: Process Step(s): Requisitions 14 Requisitions 15 Requisitions Requisitions 16 21 Requisitions 25 Requisitions 27 Contract Review 40 Requisitions Requisitions Requisitions Requisitions Requisitions 2 8 9 9 11 Technology Requirement: Provide users access to a listing of goods and services offered by preferred providers reflective of contract prices. Provide users access to predefined forms for the type of service being acquired (e.g., consulting services, sub-award). Allow users to view a predefined list of goods and services offered by preferred providers reflective of contract prices Capture user’s custom requirements on a “blank” form that can be submitted to Purchasing Administration for processing. Allow users to add multiple items into a single cart. Provide institutions with the ability to determine what approvals are required. For example, some routine, low risk transactions might not require additional review. Allow users to pick from a pre-defined list of services. Selecting a service type will initiate the appropriate custom form that will display the fields applicable to the service request (e.g., service start date, service end date, insurance requirements, sources of information). Allows for end users to attach documents required to support the request. Notify approvers electronically of a requisition for review. Automatically route requisitions for approval based on not only the funding source, but also on commodity code and other item attributes. Examples include EH&S review, commodity specific review (e.g., IT equipment), dollar based thresholds, etc. Assign workload via workflow to buyers based on attributes such as commodity, department, dollar value, vendor class and existing “queue” (workload). Allow standard contract templates (Short Forms) to be build into the ERP solution as eForms for easy drafting and dissemination. Draft & Confidential, Not for Distribution. 19 Procurement BPR: Requisitions REPORTING REQUIREMENTS The following table lists the reporting requirements and data points that must be captured to support the recommended process. Process Flow Title: Reporting Requirement: Requisitions Requisition Cycle Time Details • Typically incorporated into service level analysis reviews Requisitions Spend Volume Reports • Aggregate spend across institutions by supplier, commodity, contract, or other combinations Data Points/Metrics: • • • • • • • • • • • • • • Requestor Requesting business unit Requesting department Workflow step count Elapsed time between workflow steps Approver name Initiation date Approval date Approval names Required by/need date Supplier Contract identifier Commodity code Supplier part number Draft & Confidential, Not for Distribution. 20 Procurement BPR: Purchase/Change Orders PROCESS OVERVIEW Purchase/Change Orders represents the sub-process in which a Purchase Order is generated to formally establish an encumbrance and document the commitment in place between the institution to acquire goods or services. • Processing of the requisition is finalized • A determination is made if distribution of the purchase order to the supplier is required, and if so, by what mechanism (e.g., electronic distribution, email, fax) • Modifications are requested to the open encumbrance to reflect changes to the existing agreement (e.g., change in quantity, cancelation of remaining open balance) • The change order request is reviewed by institution and Purchasing Administration representatives • The change order is finalized and the encumbrance is updated to reflect the new amount • A determination is made if distribution of the change order to the supplier is required, and if so, by what mechanism (e.g., electronic distribution, email, fax, verbal communication) Draft & Confidential, Not for Distribution. 21 Purchase Orders Generate PO 1: Finalize Requisition 1.1: Funds Checking Executes Yes 2: Establish Encumbrance Procurement Administration No 1:3: Requisition Returned to Department Due to Lack of Available Funds A Department 1.2: Funds Available? 7: Open Encumbrance Reporting 8: Year End Reporting 5: Distribute Purchase Order to Supplier 6: System Notifies Requestor of Purchase Order Creation End of Process 3: PO to Be Automatically Distributed? No End of Process 4: Generate Encumbrance (Do Not Distribute Order) Yes A Department Change Orders, Page 1 1: Identify Need for Change to Existing Order 3: Initiate a “V2” of the Existing Purchase Order 2: Access Order in System 5: Allowable Changes? 4: Revise Order Yes 7: Submit Order for Review A No A 8: Receive Request for Change to Existing Order 9: Valid Request? Yes No 11: Can Request Proceed with Corrections? Yes 12: Work with Requesting Dept. to Revise Request Approvals No 13: Cancel Change Request B 10.2: Funds Available? Yes Change Request Review No 10:3: Requisition Returned to Department Due to Lack of Available Funds End of Process End of Process 10: Approve Change Request 10.1: Funds Checking Executes B Change Orders, Page 2 Change Request Review 14: Review Change Request 15: Valid Request? Yes 16: Finalize Change Request 16.1: Funds Checking Executes A No Procurement Administration 18: Can Request Proceed with Corrections? Yes 19: Work with Requesting Institution to Revise Request No A 16.2: Funds Available? Yes 20: Notify Institution of Issues. Reject Change Request End of Process 16.4: Encumbrance Updated 16.5: Institutions Notified of Modification of Order No 16:3: Requisition Returned to Department Due to Lack of Available Funds 21: Supplier Requires Updated Order? No End of Process End of Process Yes 22: Distribute Revised Order to Supplier End of Process Procurement BPR: Purchase/Change Orders KEY PROCESS CHANGES The following table outlines the major process changes (NSHE-wide) incorporated into the recommended process. Process Flow Title: Process Step(s): Purchase Orders 5 Purchase Orders 16.1 Change Orders 3 Change Orders 10 Explanation and Change Justification: One of the primary benefits of many leading eProcurement applications is the ability to electronically route purchase orders to a subset of suppliers, eliminating the need to manually print and fax documentation. This distribution option usually only applies to suppliers that with the technological capability to accept and process orders via EDI, XML, or other electronic communication methods. In addition, eProcurement applications can also be configured to automatically fax or email purchase orders directly to suppliers when this fulfillment related information is known and stored in the vendor record. Signature authority is validated within the eProcurement application rather than through manual validation means (e.g., signature book). The issuing department requests a new version of the order that is electronically reviewed by both the institution's Finance Office as well as the Procurement Administration(as required). Change order requests are approved electronically utilizing electronic workflow. Signature authority for change orders, where required, is obtained via manual workflows and capturing the supervisor chain or owners of funding sources and storing the data in a procurement system Draft & Confidential, Not for Distribution. 25 Procurement BPR: Purchase/Change Orders ALTERNATIVE PROCESS OPTIONS The following table outlines the alternative process options that are not recommended for implementation. Process Step(s): Alternative Process Justification for Non-Recommendation: Limitations in the reporting capabilities of procurement systems can lead to organizations building and maintaining shadow systems to track open encumbrances and associated activity. All Utilize “shadow” systems to record and track open encumbrances. Institutions should be incented to utilize the selected software and reporting capabilities need to be robust enough to provide quick and efficient access to data. Draft & Confidential, Not for Distribution. 26 Procurement BPR: Purchase/Change Orders IMPLEMENTATION CHALLENGES/PAIN POINTS Some recommended process changes may be particularly challenging during the implementation phases. Implementation Challenge Area: Manually Maintaining Change Order Workflow • Similar to the point raised in regards to the requisition process, signature authority for change orders is obtained via manual workflows and stored and maintained in the procurement system • This presents data acquisition and technical configuration considerations, specifically the challenge will be designing and maintaining a second approval flow for change orders from requisitions. Consideration should be given when designing workflows and the associated queues to capture not only the required approvers for requisitions, but also those for change orders. Recommended Process References Institution: Midwestern Research Institute Current Process: While this institution has not yet fully addressed the challenge presented by change order workflows from a systematic perspective, they have implemented online forms to streamline the change order process. In the case where an existing encumbrance needs to be changed, an online form is submitted, detailing the request. The form is routed for approvals and terminates with the purchasing department, who is responsible for reviewing and implementing the requested changes. As data was being gathered to support the unique routing of change order requests, this institution leveraged their existing workflow rules to route the form and will transition to custom routings once the data collection effort is complete. Draft & Confidential, Not for Distribution. 27 Procurement BPR: Purchase/Change Orders TECHNOLOGY REQUIREMENTS The following table lists the system technology requirements necessary to support the recommended process. Process Flow Title: Process Step(s): Purchase Orders 1 Purchase Orders 5 Change Orders 22 Change Orders 22 Change Orders 22 Technology Requirement: Encumbrances are systematically recorded with the release of a purchase order. Allow for the automatic routing for purchase orders to suppliers that have provided fax/email/automated fulfillment information; however Purchasing Administration can elect to not automatically distribute the order as appropriate. Allow for the automatic routing for change orders to suppliers that have provided fax/email/automated fulfillment information; however Purchasing Administration can elect to not automatically distribute the order as appropriate. Allow for signature authority (for change orders) to be obtained via manual workflows. Capture the supervisor chain or owners of funding sources and store the data in within the procurement system. Allow for configuration of the procurement application to be able to accommodate unique approval chains for requisitions and subsequent change orders, as approving parties on the two transactions can differ. Draft & Confidential, Not for Distribution. 28 Procurement BPR: Purchase/Change Orders REPORTING REQUIREMENTS The following table lists the reporting requirements and data points that must be captured to support the recommended process. Process Flow Title: Purchase Orders Reporting Requirement: Open Encumbrance Details Purchase Orders / Order Distribution Status Change Orders Data Points/Metrics: • • • • • • • • • • • • • • Departments Institution Associated buyer(s) PO Number/Identifier PO Status Remaining balances Funding source Date change order was distributed Status of distribution (if electronic) Departments Institution Associated buyer(s) PO Number/Identifier Order status Draft & Confidential, Not for Distribution. 29 Procurement BPR: Competitive Bid/RFP PROCESS OVERVIEW A Competitive Bid / Request for Proposal represents the sub-process in which a Purchasing Unit coordinates with Purchasing Administration to solicit, collect and review competitive bids and proposals. • An institution identifies a need for goods or services, either for their use or on behalf of their department/organization. • A purchasing agent is assigned to support the acquisition of goods or services. • Suppliers are notified of the opportunity to offer their goods or services to the institution. • Supplier proposals/bids are evaluated by the institution and Purchasing Administration. • An intent to award is made to the selected supplier. • A contract between the supplier and institution is negotiated. • The goods or services are obtained. Draft & Confidential, Not for Distribution. 30 Proponent Request for Proposal Process, Page 1 Start Process 1: Need Identified for Goods or Services 2: Proponent Organization Submits Request for Goods or Services to Purchasing Center Procurement Administration 3: Valid Request? 5: Assign Request to Purchasing Agent 6: Analyze Proponent Provided Requirements 11: Finalize RFP Document 12: Distribute RFP Opportunity Notifications to Suppliers 4: Work with Proponent on Revising Parameters of Request 7: Work with Proponent to Finalize Specifications and Scope of Work 8: Assemble RFP Proposal Evaluation Committee (PEC) 9: Work with Proponent to identify Proposal Evaluation Criteria and communicate to PEC 10: Draft RFP Document and Review/Revise with Proponent and PEC as Required Notify Supplier Procurement Administration Proposal Evaluation Committee Supplier Request for Proposal Process, Page 2 Notify Supplier 16: Evaluate Proposals based on RFP Criteria and Specifications 22: Coordinate Required Contract Reviews 13: Supplier Receives Notification of RFP Posting 14: Supplier Is Notified of Addendums 15: Supplier Provides Proposal 18: Support the PEC by Assisting in Negotiations with Downselected Supplier(s) 19: Identify Most Qualified Supplier as Based on RFP Evaluation Criteria / Scoring 24: Modify Encumbrance to Match Awarded Amount 24.1: Purchase Order Required? 17: Conduct Supplier Presentations / Interviews as Required by RFP Specifications 23: Award Contract Yes 20: Notify Supplier of Intent to Award 21: Finalize Contractual Terms 24.2: Distribute Purchase Order End of Process No Proponent Competitive Bid Process, Page 1 Start Process 1: Need Identified for Goods or Services 2: Proponent Organization Submits Request for Goods or Services to Purchasing Center Procurement Administration 3: Valid Request? 4: Work with Proponent on Revising Parameters of Request 7: Work with Proponent to Finalize Specifications / Scope of Work 8: Distribute Notification of Bidding Opportunity to Suppliers Notify Supplier 5: Assign Request to Purchasing Agent 6: Analyze Proponent Provided Requirements Supplier Competitive Bid Process, Page 2 Notify Supplier 10: Supplier Is Notified of Addendums (if Generated) 11: Supplier Provides Bid Proposal 13: Evaluate Bid Response(s) 14: Award Bid to Best Value Supplier 15: Notify Supplier of Intent to Award Procurement Administration 12: Receive Bid 9: Supplier Receives Notification of Bidding Opportunity and Related Specifications 15.1: Did Supplier Accept Standard T&Cs? Yes No 16: Finalize Contractual Terms A 18: Award Contract 19: Generate Encumbrance for Awarded Amount End of Process 17: Coordinate Required Contract Reviews A Procurement BPR: Competitive Bid/RFP KEY PROCESS CHANGES The following table outlines the major process changes (NSHE-wide) incorporated into the recommended process. Process Flow Title: Process Step(s): Request for Proposal 9 Request for Proposal 12 Request for Proposal 16 Competitive Bid 8 Competitive Bid 13 Explanation and Change Justification: Proponent works with Procurement Administration to establish the Proposal Evaluation Criteria (PEC) and then Procurement Administration assists in communicating this criteria to the committee and ensuring understanding. Data stored in the supplier registration system is leveraged to generate bid notifications for suppliers who have registered to be notified of opportunities for the commodity or service areas associated with the solicitation. Institutions and Purchasing Administration evaluate supplier proposals accordingly based on regions of service , especially for those suppliers who are limited in scope to one of the two regions. The geographic realities of the state also provides an opportunity to work with other close by entities (e.g., municipalities, independent school districts) on bidding opportunities; incorporating these entities into a more highly automated solicitation management system could prove challenging. Data stored in the supplier registration system is leveraged to generate bid notifications for suppliers who have registered to be notified of opportunities for the commodity or service areas associated with the solicitation. Institutions and Purchasing Administration evaluate supplier proposals accordingly based on regions of service , especially for those suppliers who are limited in scope to one of the two regions. The geographic realities of the state also provides an opportunity to work with other close by entities (e.g., municipalities, independent school districts) on bidding opportunities; incorporating these entities into a more highly automated solicitation management system could prove challenging. Draft & Confidential, Not for Distribution. 35 Procurement BPR: Competitive Bid/RFP IMPLEMENTATION CHALLENGES Some recommended process changes may be particularly challenging during the implementation phases. Implementation Challenge Area: Geographic Distribution of Suppliers • Given that Nevada’s population is predominantly located in the northern and southern regions of the state, the sources of supply share this same geographic distribution. Systems used to support the competitive bid and request for proposal processes will need to be able to allow institutions to identify what region the supplier primarily serves. This will allow institutions and Purchasing Administration to evaluate supplier proposals accordingly, especially for those suppliers who are limited in scope to one of the two regions. • The geographic realities of the state also provides an opportunity to work with other close by entities (e.g., municipalities, independent school districts) on bidding opportunities; incorporating these entities into a more highly automated solicitation management system could prove challenging. Draft & Confidential, Not for Distribution. 36 Procurement BPR: Competitive Bid/RFP TECHNOLOGY REQUIREMENTS The following table lists the system technology requirements necessary to support the recommended process. Process Flow Title: Process Step(s): Competitive Bid 2 Competitive Bid 7 Competitive Bid 8 Competitive Bid Competitive Bid Request for Proposal 8 10 2 Request for Proposal 10 Request for Proposal 12 Request for Proposal Request for Proposal 14 16 Request for Proposal 19 Technology Requirement: Utilize electronic forms to request goods or services. Allow for embedded collaboration tools within the solicitation management functionality such as document sharing, clause libraries, and online editing. Utilize a supplier registration system to automatically generate bidder lists and distribute notifications alerting suppliers to the opportunity. Allow institutions to identify what geographic areas the supplier primarily serves. Automate the distribution of addendum notifications to prospective suppliers. Utilize electronic forms to request goods or services. Allow for embedded collaboration tools within the solicitation management functionality such as document sharing, clause libraries, and online editing. Utilize a supplier registration system to automatically generate bidder lists and distribute notifications alerting suppliers to the opportunity. All for configuration to automatically post the RFP notification at a certain date/time. Automate the distribution of addendum notifications to prospective suppliers. Allow institutions to identify what geographic areas the supplier primarily serves. Aid the evaluation of RFP responses (via solicitation management functionality), e.g., automate the scoring process, apply weighted averages to scoring criteria, provide tabulation summaries. Draft & Confidential, Not for Distribution. 37 Procurement BPR: Competitive Bid/RFP REPORTING REQUIREMENTS The following table lists the reporting requirements and data points that must be captured to support the recommended process. Process Flow Title: Reporting Requirement: Request for Proposal / Supplier Response Status Competitive Bid Request for Proposal / Competitive Bid Supplier Bid Notification Report • Suppliers receiving notification of RFP/Competitive Bid posting Request for Proposal / Bid/proposal Scoring Summary Competitive Bid Data Points/Metrics: • • • • • • Supplier name Date of bid notification Date of response (if applicable) Completeness of response Bid list recipient diversity status Respondent diversity status • Supplier name • Assigned categories • Supplier name • Weighted averages of bid scoring categories • Summary of subjective responses (as appropriate) Draft & Confidential, Not for Distribution. 38 Procurement BPR: Supplier Registration PROCESS OVERVIEW Supplier registration represents the sub-process in which suppliers and vendors are registered and entered into the electronic procurement system. • An NSHE institution identifies the need to do business with a selected supplier OR a supplier expresses interest in doing business with an institution • The supplier accesses the online vendor portal and initiates the registration process • The supplier completes the registration process, accepts the required terms and conditions, uploaded the appropriate certifications, etc. • Purchasing Administration is notified of the registration request and reviews the supplier provided information • The supplier is activated an available to receive purchase orders, solicitations, etc. from NSHE institutions Draft & Confidential, Not for Distribution. 39 Supplier Registration 1: Supplier Receives Request to Register as a Supplier of NSHE Institutions 2: Supplier Accesses Registration Portal 3: Supplier Initiates Registration Process 4: Supplier Provides High Level Company Information 5: Supplier Indicates if there are any Existing Conflicts of Interest 6: Supplier Provides Company Address Information 7: Supplier Provides Contact Information for Addresses 8: Supplier Indicates if their Insurance Meets NSHE / Institution Requirements 9: Supplier has Ability to Add Insurance Information and Certificates 10: Supplier Uploads Tax Form Appropriate for the Entity’s Registration Type and all other required information 10.1: Supplier Reviews and Accepts Terms and Conditions of Software Use 10.2: Supplier Reviews and Accepts NSHE Business Terms and Conditions 11: Supplier Attests to Accuracy of Information and Completes Form A A 12: Business Center is Notified of New Registration Request/Update 13: Request is Reviewed for Accuracy Procurement Administration Supplier Start Process 14: Do Tax Forms Support Reg. Type? Yes 15: Ins. Cert. Equal Indicated Coverage? Yes 16: Valid Order From/Remit To Locations? No No 15: Contact Supplier to Request Updates to Account 17: Activate Supplier Record 18: Notify Departments as Required of the Addition of the Supplier End of Process No Yes Procurement BPR: Supplier Registration KEY PROCESS CHANGES The following table outlines the major process changes (NSHE-wide) incorporated into the recommended process. Process Flow Title: Process Step(s): Supplier Registration 1 Supplier Registration 12 Supplier Registration 13 Explanation and Change Justification: Responsibility for managing supplier information is transitioned to the supplier (from NSHE institution). This is a key change for institutions (outside of UNLV who has an SR system currently in place). Interactions with suppliers are that of requesting action on the supplier’s part, as opposed to requesting information. Registration of suppliers is currently initiated at both Business Center locations. With the adoption of a centralized registration system, a centralized supplier registration team will be needed to support the end to end process for Purchasing Administration. While the adoption of a centralized vendor registration system will automate much of the registration process, the human element will still play a critical roll in the overall process, especially in the review and approval of supplier registration requests. Draft & Confidential, Not for Distribution. 41 Procurement BPR: Supplier Registration ALTERNATIVE PROCESS OPTIONS The following table outlines the alternative process options that are not recommended for implementation. Process Step(s): Alternative Process Justification for Non-Recommendation: Best practice calls for a single system to house both potential suppliers (those receiving solicitation notifications) as well as validated suppliers. 1 9 Only store validated suppliers and manage bid opportunities outside of the supplier registration system. Supplier record attributes will allow for institutions to separate potential suppliers from validated suppliers for reporting purposes while still having a single view of the entire supply chain within a single vendor file. The embedded control lies within the requisition approval flow; requisitions to Preventing suppliers of services from completing the registration suppliers that have not yet provided valid insurance certificates are routed for process without providing insurance information. review and approval prior to purchase order generation so that the supplier can be prompted to update their profile as appropriate. Draft & Confidential, Not for Distribution. 42 Procurement BPR: Supplier Registration IMPLEMENTATION CHALLENGES Some recommended process changes may be particularly challenging during the implementation phases. Implementation Challenge Area: Converting to a centralized vendor registration process • • • • A full compliment of supplier data must be available and current in the online supplier registration system. Given the large volume of suppliers with Advantage and UNLV’s existing online supplier registration system, it will be a challenge to replicate those records in the new system considering the burden for updating and maintaining information will be shifted to the supplier. During the Implementation Phase, NSHE will make a conversion decision to either pre-seeding the registration system with minimal data so that when suppliers access the system they have a starting point or to scrub the existing vendor record and convert all existing records using as much clean data as possible. Suppliers accessing the system will then validate the existing record and make updates where needed. With the move to a centralized supplier registration system, the terms and conditions presented to suppliers as a part of the registration process will be standardized across NSHE. NSHE will need to perform a review and reconciliation process of the terms and conditions currently employed by the three purchasing locations. Recommended Process References Institution: West Coast Public University System Current Process: Currently manages a central supplier registration system for solicitation opportunities. They will soon be expanding the utilization of the system to include all trade vendors utilized by the ten System campuses. University pre-populated the supplier registration system with minimal data (e.g., name, email) and requested participating suppliers provide the remaining pieces of information. Draft & Confidential, Not for Distribution. 43 Procurement BPR: Supplier Registration TECHNOLOGY REQUIREMENTS The following table lists the system technology requirements necessary to support the recommended process. Process Flow Title: Process Step(s): Supplier Registration 2 Supplier Registration 5 Supplier Registration 6 Supplier Registration 10 Supplier Registration 17 Technology Requirement: Allow the supplier registration portal to be accessible via the web and open to all potential suppliers of goods and services to NSHE institutions. Provide ability to search for and filter on physical supplier location and service areas. Allow for the acknowledgement of a potential conflict of interest via the online form, and depending on the information provided, route the application request to the Purchasing Administrator for further review prior to the request being fully approved. Require suppliers to provide the following address information: physical location, PO receipt location, and remit to location. Automatically prompt the supplier to populate the appropriate Tax Form (e.g., W9) and all other required forms/information based on their entity type and attributes (e.g., C Corp, partnership). Provide institutions ability to search across all vendor records, including those records containing comments generated as a part of the registration process. Draft & Confidential, Not for Distribution. 44 Procurement BPR: Supplier Registration REPORTING REQUIREMENTS The following table lists the reporting requirements and data points that must be captured to support the recommended process. Process Flow Title: Reporting Requirement: Supplier Registration Supplier registration status Supplier Registration Abandoned registrations Supplier Registration Suppliers by category Supplier Registration Duplicate supplier records Data Points/Metrics: • • • • • • • • • • • • • • • • • • • • • • • • • Supplier name Corporate Status TIN Diversity status Registration status (e.g., in process, completed, approved) Insurance coverage Last updated date Supplier name TIN Corporate Status Supplier contact information Missing registration components Acceptance of terms and conditions Last updated date Category (e.g., lawn services, scientific supplies) Supplier name Corporate Status TIN Diversity status Supplier contact Registration date Registration status Licensing status Supplier name TIN Draft & Confidential, Not for Distribution. 45 Business Process Recommendations: NSHE Feedback NSHE Feedback: Procurement ROUND 1: MARCH – APRIL 2013 The following table outlines the NSHE feedback and commentary, as well as Huron response when applicable. SubProcess/ Institution Topical Area Requisitions UNLV Requisitions UNLV Purchase/ Change Orders UNLV Competitive UNLV Bid/RFP Competitive UNLV Bid/RFP Competitive UNLV Bid/RFP Comments/Feedback Huron Response PCard purchases are not typically on a requisition. Not sure what the point is The text has been updated to more clearly state what process here. we are trying not to encourage. The goal was to encourage NSHE/institutions to incent the use of an eProcurement system (where appropriate) by streamlining the approval process for active PCard holders and didn't capture that sentiment in my original text. The system must be able to assign workload to buyers by commodity; We have added a Technology Requirement to this end. Other department; dollar limits, from supervising positions to subordinates, etc. assignment variables could include vendor class, existing workload. What is V2 (just a term for request for modification to PO?) We modified the step to display: "3: Modify the PO by Initiating a “V2” of the Existing Order" referencing a Version 2. Is the vehicle to submit requests a requisition so we can determine if there is adequate funding and approval to start the process? In regards to the form, yes, either a requisition or a customized solicitation form would be submitted. Regarding the question about funding, there was a good debate at the workshops around this point. We agreed to reflect the funding decision point in the process after contract signing. The Proposal Evaluation Committee does not set the evaluation criteria. This is establish as part of step 7. There should be a step for selecting a supplier (bidders) list based on This is more clearly articulated as a requirement via a callout to the flow chart to better illustrate how the notifications are content/requirement of request (commodity or service) this needs to tie to supplier section that allows a search for appropriate suppliers (including their distributed. diversity status, licensing certificates, bond/insurance limits) Draft & Confidential, Not for Distribution. 47 NSHE Feedback: Procurement ROUND 1: MARCH – APRIL 2013 The following table outlines the NSHE feedback and commentary, as well as Huron response when applicable. SubProcess/ Institution Topical Area Competitive UNLV Bid/RFP Competitive UNLV Bid/RFP Supplier UNLV Registration Supplier UNLV Registration Supplier UNLV Registration Supplier UNLV Registration Comments/Feedback Huron Response A step should be added for how the RFP is advertised, posted to web. Is there A callout has been added to the flows to include this step a way to automate a pre-form notification from the ERP system to notify to within Step 12 of the RFP process. The ERP can be post? Insert step before 12 or include as simultaneously with 12. configured to automatically post the RFP notification at a certain date/time, and there are commercial systems that can accommodate this requirement. This has been added as a Technology Requirement. Would suggest we list that due to the geography of the state it is important to We have added text and content to address this challenge. consider that the purchasing centers often work with other public agencies that are in the same proximity (such as CCSD and Clark County in the South) for better pricing and available supplier base. We often participate or tie on to their solicitations or they with ours. Not all suppliers are notified to register; they may decide without any We have revised the narrative and flows to better capture this notification from NSHE. process variation. Not sure why we would not accept suppliers without insurance. Insurance The Alternative Process Option was unclear and has been requirements are not the same for every procurement situation that a supplier updated to state "Preventing suppliers of services from may be requested to perform. It would not make sense to have someone completing the registration process without providing providing bonding etc. until they are actually awarded a contract/PO to do insurance information." business with us. Not one size fits all approach will work. Why would we not consider sending out notices to suppliers to register in This (valid) point is an Implementation Decision and should be UNLV's supplier registration system as we start implementing our new ERP? addressed as a part of the conversion process once a system We could then use that data to populate our new system. This would help has been selected. avoid uploading all of the inaccurate data currently in all of the Advantage instances. We are not sure the first Alternative Process Option is a good idea. (But it is better than a data dump of "garbage " from Advantage.) Draft & Confidential, Not for Distribution. 48 NSHE Feedback: Procurement ROUND 2: MAY 2013 The following table outlines the NSHE feedback and commentary, as well as Huron response when applicable. SubProcess/ Institution Topical Area Supplier UNLV Registration Supplier UNLV Registration Supplier UNLV Registration Supplier UNLV Registration Comments/Feedback Huron Response If we intend to use one data base for suppliers the system must allow for the We have updated the comments for step #2 to indicate the suppliers to note that they only service certain institutions or regions, etc.. requirement to allow institutions to search for and filter on There will have to be filters to avoid misleading assumptions on suppliers physical supplier location and service areas. capabilities. Conflicts of Interest be covered during the review of the applicant's data before We have added clarifying language that the review would they are activated and uploaded into the system. This would be considered occur prior to approval of the registration request. having the supplier's application in a "pending review" type status. This validation would be part of the other validations to be done such as checking insurance certificates, etc.. Each individual item to be submitted to NSHE doesn't need to be listed as separate process points (if they do then there are several missing). We just need to list that information needs to be submitted by supplier, reviewed/accepted by system administrator, and then accepted/approved as a supplier in the system. Not sure why Tax Forms would be listed only for this data point. Information Agreed that Tax Form requirement seems specific in light of a submission could apply throughout the application process (e.g. insurance general need for a system that would direct certificates) . The system could prompt the applicant throughout the suppliers/institutions to complete all required fields based on submission if that functionality is available and those rules are set up in the the characteristics of the registration. This specific point was system. included to make sure we captured this specific point around the entity type and its impact on the registration forms. Draft & Confidential, Not for Distribution. 49 NSHE Feedback: Procurement ROUND 2: MAY 2013 The following table outlines the NSHE feedback and commentary, as well as Huron response when applicable. SubProcess/ Institution Topical Area General UNLV Competitive UNLV Bid/RFP Comments/Feedback Huron Response It does not appear that the issue of contracting/legal review of contracts for We have added a flow diagram under requisitions specifically any/all purchases that are outside the norm of standard agreements is outlining the high-level flow for Contract Review, including clearly/specifically addressed. This is what is the largest hold up on associated Policy Change Requirements and Technology processing time and I did not really see this addressed much in here. Where is Requirements. it specifically addressed? Why would there not be specific recommendations on use of standard contracts and bringing general risk factors into how much time is needed for formal agreement review? (Page 6. (slide titled ‘Requisition, Page 4’) there is a connector in the first row to a process ‘Contract Review’, but there is no corresponding process flow or other recommendations/discussion points documented?) This page indicates specific policy needs to be established, but there already We have further built out the Implementation Slide to talk is consistent policy in place, it is just that the interpretation varies depending about these challenges and how, aside from communication, on who is completing the review of the exception request. This can happen NSHE institutions can move towards a consistent with any policy such as this where some degree of flexibility appropriately interpretation. exists within the policy. Page 13 (implementation challenges) summarizes this point, but suggests the answer is closer communication between the institutions and NSHE. I think the issue with competitive exceptions with some of the institutions is not communication but that they feel pressured to accepting exception and not all institutions have a formal process for documenting the request and review process. Draft & Confidential, Not for Distribution. 50 NSHE Feedback: Procurement ROUND 2: MAY 2013 The following table outlines the NSHE feedback and commentary, as well as Huron response when applicable. SubProcess/ Institution Topical Area Competitive UNLV Bid/RFP Requisitions UNLV Comments/Feedback Contract review can be time consuming. The amount of review and the time taken for executing contracts often over shadows the actual risk assessment for contract driven procurements. General Counsel's, Purchasing's and individual Department's views of particular terms and conditions contained in contracts are often times in conflict. This conflict can negatively impact the processing times for documents required for services in particular. Huron Response We have added a Key Process Change under Contract Review that specifically speaks to the need for tools and training (that are widely disseminated) to ensure Procurement Administration(across the institutions and NSHE) are consistently managing contracts and balancing risk with review time in a manner that is consistent with NSHE/institutional priorities. Requisition Step 14/15 should indicate that forms repository would need to include standard contract forms. With the transition to automation consideration should be given to developing and loading standard form contracts in the requisition form repository for use by the departments. These forms could be available and submitted with the requisitions. We have updated the materials accordingly. Draft & Confidential, Not for Distribution. 51