2015-11-18-Supplemental2-ASU-Audit-Reports

advertisement
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
This page left blank intentionally.
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
Summary
The audit of the McCord Hall construction contract was included on the Arizona State
University (ASU) FY 2015 annual audit plan approved by the Arizona Board of Regents
(ABOR) Audit Committee and university senior leadership. University construction projects
have been identified as strategic, high-risk areas since charges to the project may not comply
with the negotiated contract, resulting in overcharges, cost overruns, and process
inefficiencies.
Construction administration and project monitoring for ASU is provided by the Capital
Programs Management Group (CPMG). University Audit (Audit) previously completed audits
of construction contracts administered by CPMG in:
• FY2014 - Audit Report Number 14-03 Sun Devil Fitness Complex Polytechnic Campus
Construction Contract issued in November 2013.
• FY2013 - Audit Report Number 13-04 Interdisciplinary Science and Technology Building 4
(ISTB4) Construction issued in January 2013.
• FY2008 - Audit Report Number 09-04 Hassayampa Academic Village Contract
Administration issued in April 2008.
Background: McCord Hall was constructed to help the W. P. Carey School of Business
(school) achieve one of its chief objectives of nurturing a robust graduate community culture
that encompasses all of the W.P. Carey Graduate Programs, reflecting the growth and
prominence of the school. McCord Hall is home to Executive Education programs and
several Master’s programs within the school. The building also accommodates MBA
Administration and Career Management services for graduate students. Although focused on
graduate studies, McCord Hall also is home to the undergraduate Leaders Academy, a
community designed for the school’s top undergraduate students.
McCord Hall was added to the school’s two existing structures, which were renovated during
the construction of McCord Hall. Together, they ease overcrowding for the 10,000-plus
students who attend the school. The facility consists of two four-level sustainable structures
linked by long-span skyways. McCord Hall is approximately 129,000 gross square feet, and
earned a LEED gold certification. Modern architecture with a dramatic facade of corduroy
exterior brick pattern, sloping walls, and an intimate courtyard define this state-of-the-art
building. The project won two awards from the American Concrete Institute Arizona, for Best
Overall Project and Exposing the Best in Concrete. Most recently, the project was
acknowledged by the Arizona Masonry Guild with a Craftsmanship Award and Honor Award,
and at the regional ENR (Engineering News-Record) Southwest Awards as the Best
Education Project in 2014.
Page 1 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
The project was completed using the Construction Manager at Risk (CM@Risk) project
delivery method. The CM@Risk provides technical assistance to the designer during the
design phase, including constructability reviews, cost estimates, and product specifics to aid
in cleaner designs, and provides a fixed price for the contract, called a Guaranteed Maximum
Price, for construction. The majority of construction at ASU uses this method now. The
CM@Risk selected for this project was DPR Construction (DPR). To select the CM@Risk, a
qualified selection committee (committee) was initiated for the request for qualifications, and
a licensed contractor was placed on the committee. Packages that were received were
ranked by the committee. The committee short listed three firms after weighing the criteria
included in the request for qualifications. All of the firms were qualified to perform the required
services for the construction of McCord Hall. The ASU Project Manager served on the
committee; as individuals from the firms were interviewed, the proposals were assessed and
ultimately DPR was selected. The process was in compliance with Arizona Board of Regents
policy and the contract requirements during the selection process. The contract with DPR
(contract) included pre-construction design-phase services as well as construction-phase
management, including coordinating all subcontracted work. Two contracts were used with
the CM@Risk during this project, the “University Standard Form Agreement Between Owner
and CM@Risk on the Basis of a Guaranteed Maximum Price” dated April 19, 2010, for the
design phase of the project, and the “University Standard Form Agreement Between Owner
and CM@Risk on the Basis of a Guaranteed Maximum Price” dated October 31, 2011, for
the construction phase of the project. Audit has made recommendations in previous
construction audits for construction projects that used these contract editions. Because the
construction phase of McCord Hall was 60% complete at the time these recommendations
were made, the recommendations were not implemented for the McCord Hall construction
project.
ASU constructed the facility on the Tempe campus for a final Guaranteed Maximum Price
(GMP) of $41.0 million. The initial scope of work was subject to a ceiling price of $38.4
million as originally fixed in the contract. However, changes in the scope of the construction
project encountered during the Construction Phase necessitated additional work, modified
work or deleted work, all of which added $2.6 million of additional costs documented in
Change Orders to the original GMP, resulting in the final total GMP of $41.0 million (see the
table on page 4). Funding for the project, including funding the Change Orders, was provided
through the sale of ASU System Revenue Bonds and gifts.
ABOR granted Project Implementation Approval for the project in December 2010. The
Capital Committee reviewed the project and ABOR Project Approval was subsequently
granted in September 2011 for $57.1 million.
Page 2 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
The Total Project Budget Amount was $57.1 million (see the table on page 4), which included
GMP construction contract costs of $41.4 million; as well as architectural services, furniture
and equipment, telecommunications equipment and installation, CPMG project management
expenses, state risk management insurance expenses, and other required costs, totaling an
additional $15.7 million.
The CM@Risk performed Design Phase Services during the Pre-Construction Phase of the
project to determine constructability of the facility, including review of the architectural design
and drawings, value management and engineering, preliminary schedule formulation,
subcontractor scope clarification, and development of a Guaranteed Maximum Price. The
responsibilities of the CM@Risk during the Construction Phase of the project included
overseeing construction for conformance to drawings and specifications, reviewing and
certifying amounts due to subcontractors, managing Change Orders, building inspections,
and following Project Closeout procedures.
Page 3 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
Description of the McCord Hall Contract Phases
Initial Pre-Construction Phase Fee
Expenditures
$329,180
Increase in Pre-Construction Phase Fee via Change Order 1
Final Pre-Construction Phase Fee
1,323
$330,503
Initial Construction Phase GMP
$38,400,000
Net Change Orders #1 through #10, as of June 24, 2013
Final Construction Phase GMP
2,619,432
$41,019,432
Total Pre-Construction Phase Fee and GMP as of June 24, 2014
Architect/Engineer, Surveys and Tests
$41,349,935
$5,447,513
Furniture Fixtures Equipment, Telecommunications Equipment
7,860,058
Project Management Expenses and Fees, State Risk Insurance
502,736
Renovation, Special Equipment, Site Development
178,058
Anticipated Costs for additional Project Management Expenses and
Fees, and State Risk Insurance
Uncommitted Budget
1,159,834
51,866
Decrease in Budget Funding
500,000
Total Other Required Project Costs
$15,700,065
Total Budget Amount as of September 30, 2014
$57,050,000
The contract was signed on November 3, 2011, and called for substantial completion of the
facility by June 18, 2013. CPMG indicated satisfaction with the quality of the work and that
the CM@Risk completed work during the required timeframe.
Audit Objectives: To determine that financial transactions relating to construction activity for
the McCord Hall construction project complied with the terms of the contract, including
whether or not:
•
Contractor billings were adequately supported by actual costs plus overhead, profit, and
fees as specified by the construction contract;
Page 4 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
•
•
•
•
Controls over the process were adequate and in accordance with contract provisions;
Change Orders were priced according to the contract terms and were properly approved;
The CM@Risk provided the contracted scope of work; and
Insurance coverage during construction was in compliance with the terms of the contract.
Scope: Our audit included a review of the design phase and all construction-phase
expenses paid to the CM@Risk from the start of the contract in 2010 through the end of
construction in June 2013, including Change Orders #1 through #10 processed through June
2013, and four additional post-construction phase Change Orders #1 to #4 processed from
July 2013 through April 2014. CPMG did not expect any additional Change Orders to be
processed after April 2014.
We relied on CPMG’s expertise for the construction technical aspects, and, therefore, our
scope of work did not include any on-site inspections to assess construction methods,
materials or compliance with design specifications.
Methodology: Our audit objectives were accomplished through:
• Preparing a control schedule of the initial GMP, Change Orders, and payment
applications to ensure payments to the CM@Risk did not exceed the approved GMP;
• Selecting a sample of two out of twenty-five payment applications, one from early in
the project and one from the middle of the project, and comparing the information in
the payment applications to the detail the subcontractors had submitted to the
CM@Risk supporting the amounts approved in the payment applications;
• Reviewing ASU payments to vendors other than CM@Risk to ensure the expenses
were allowable costs and not included in the existing CM@Risk contracted scope of
work;
• Reviewing the payments paid by CM@Risk to subcontractors and vendors for the
actual cost of the work performed, including preparing a control schedule for all
subcontractors under subcontract agreements, to ensure that the CM@Risk billed
ASU for allowable costs;
• Discussing the project with representatives from CPMG including the Executive
Director, Assistant Director, Project Manager Senior, and with representatives from
University Business Services (UBS), including the Manager of Purchasing and Office
Specialist Senior;
• Verifying all required insurance coverage and bonds were maintained during the
project;
• Recalculating the overhead, general conditions and fees charged by the CM@Risk
and the subcontractors on all Owner/ASU Change Orders, ensuring the fees were in
accordance with the Change Order pricing provisions in the contract;
Page 5 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
•
•
•
•
•
•
Preparing a control schedule to facilitate a pricing review of Change Orders (all
Owner/ASU Change Orders with costs totaling $2,619,432 for the Construction Phase
and with costs totaling $68,127 for the Post-Construction Phase were reviewed),
including:
recalculating the bonds, insurance, and taxes charged; reviewing the
supporting documentation to ensure the Change Order amounts agreed to
subcontractor quotes; and checking that the changes were reasonable and properly
approved;
Reviewing Owner/Design Contingency and Contractor Contingency Logs for
approvals, supporting documentation and backcharges;
Ensuring the selection of the Architect was performed in compliance with ABOR and
ASU policies under the “Design Professional Agreement (CM@Risk/Operating
Manual/Multiple Projects Form)” dated February 26, 2010;
Ensuring the cost estimating and bidding process was performed in compliance with
contract provisions under the “University Standard Form Agreement Between Owner
and CM@Risk on the Basis of a Guaranteed Maximum Price” dated October 31, 2011;
Reviewing subcontracts and bid documents for the seven largest subcontractors to
ensure the contract terms were consistent and in compliance with the contract; and
Reviewing for proper application of the Transaction Privilege Tax (TPT).
Conclusion: Based on our audit work, contractor billings were adequately supported by
actual costs plus overhead, profit, and fees as specified by the construction contract. The
financial transactions relating to construction activity, by both CPMG and the CM@Risk,
complied with the terms of the contract. Documentation for payment applications, Owner
Change Orders, and payments by CPMG was in order and complete.
Regarding
Construction General Conditions and cost verification, there are opportunities to improve the
process of determining the cost of the Construction General Conditions and further
strengthen processes for cost control.
Controls over the design and construction process were adequate and in accordance with
contract provisions, with the project being completed within budget and the CM@Risk
providing the contracted scope of work. Similar to findings in prior construction audits, tThe
architectural fees paid by ASU exceeded the calculated fee from the Arizona Board of
Regent’s Construction Cost Control and Professional Fee Guidelines. University Audit
recommends compiling a historical cost database of architectural services that can be used
to compare against future additional architectural services to help determine fees that are fair
and reasonable to the University per ABOR Policy Number 3-804B.5 Professional Services
and Construction Services Procurement. Determining architectural fees that are fair and
reasonable to the University was also recommended in the Sun Devil Fitness Complex
Polytechnic Campus Construction Contract Audit issued in November 2013, and in the
Page 6 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
Interdisciplinary Science and Technology Building 4 (ISTB4) Construction Audit issued in
January 2013. Per ABOR Policy Number 7-102 Overview of the Capital Development
Process and Phases, article E.1 says that the Regent’s Construction Cost Control and
Professional Fee Guidelines or other industry cost guidelines or internal historical data
(“Guidelines”) are to be considered when estimating architectural fees to ensure the
reasonableness of architectural cost estimates. CPMG is working with the ABOR System
Office to review ABOR Policy Number 7-102 for potential revisions.
The CM@Risk self-performed a portion of the construction work on McCord Hall. When the
CM@Risk self-performs the work, the CM@Risk is functioning as a subcontractor. To verify
the reasonability of the cost of self-performed work, Best Practices dictate receiving at least
three competitive bids for all the work performed. Alternatively, self-performed work could be
competitively priced with a separate pricing and scoping document explicitly defining scope,
labor rates, materials, and pricing method. While three bids were received for a portion of the
materials supplied by the CM@Risk for the self-performed work, since the bids did not
include labor costs, and since the self-performed work was not competitively priced with a
separate pricing and scoping document, there was no independent assurance on the
reasonability of the costs.
In regards to cost verification and similar to findings in prior construction audits, Audit noted
that CPMG did not receive supporting documentation from the CM@Risk sufficient to
complete a detailed review of the amounts paid by the CM@Risk to the subcontractors and
vendors. CPMG also did not receive supporting documentation, including documentation for
Construction Contingency Change Orders, sufficient to perform an in-depth review of the
costs billed to ASU by the CM@Risk to determine whether ASU was only being billed for
allowable costs, but the costs billed were within the contracted total GMP. Because the
university relies on the contracted total GMP to serve as the cost control for construction
projects, it is important that every aspect of the contract cost negotiation process be
researched, negotiated, and documented properly. In addition, reconciling the CM@Risk
payment applications to documentation supporting costs of construction as these progress
payments are paid facilitates the performance of the contract final close-out process. Any
savings due the university, arising from the difference between the GMP and the cost of
construction as required in Section 7.1.2 of the construction contract, can be identified in a
timely manner throughout the construction process.
With this in mind, Audit sought to independently verify insurance costs which had been
separately enumerated in the contract. Audit requested copies of insurance certificates for
insurance payments as proof of actual existence of insurance and bond coverage. The
CM@Risk did not provide insurance certificates for Subguard Insurance. In previous audits,
Audit sought advice from the ASU General Counsel staff, which after reviewing the TriPage 7 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
University construction contract, determined that the CM@Risk was not required to provide
Audit with the original supporting documentation of the CM@Risk’s actual insurance costs
(paid invoices or cancelled checks) under the terms of the current Tri-University standard
construction contract template. The Tri-university construction contract requires the
CM@Risk provide the University with certificates of insurance evidencing coverage. Audit
recommends that ASU Management continue to work with the Tri-University Construction
Contract Committee to review the insurance provisions of the standard construction contract
to seek to reduce potential risk to the Universities.
Page 8 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
The control standards we considered during this audit and the status of the related control
environment are provided in the following table.
General Control Standard
(The bulleted items are internal control objectives that
apply to the general control standards, and will differ
for each audit.)
Reliability and Integrity of Financial
and Operational Information
• Contractor billings were adequately
supported by actual costs incurred by
the CM@Risk, plus fee, tax, and bonds
and insurance charges as specified by
the contract.
• Cost estimating, independent cost
verification, bidding, and pricing of
architectural fees were in accordance
with policies and contract provisions.
Effectiveness and Efficiency of
Operations
Safeguarding of Assets
•
•
Finding
No.
Page
No.
NA
NA
1,2,3
10,11,13
NA
NA
NA
NA
Reasonable to Strong
Controls in Place
NA
NA
Reasonable to Strong
Controls in Place
NA
NA
Reasonable to Strong
Controls in Place
Opportunity for
Improvement
Not Applicable
Reasonable to Strong
Controls in Place
The CM@Risk provided the
contracted scope of work.
Compliance with Laws and Regulations
•
Control
Environment
Owner Change Orders were priced
according to the contract terms and
were properly approved.
Insurance coverage during
construction was in compliance with
the terms of the contract.
We appreciate the assistance of CPMG, UBS and DPR representatives during the audit.
____________________________
Gordon Murphy, CPA, CFE, MAEd
Internal Auditor Senior
_______________________________
Tracy Grunig, CPA, CFE, CISA, MPA
Chief Audit Executive
Page 9 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
Audit Results, Recommendations, and Responses
1. Construction General Conditions Should Be Further Verified for Reasonability
Condition: University Audit noted that Billing Rates charged by the CM@Risk exceeded the
Billing Rates allowed under the contract. Billing Rates for labor costs (Billing Rates) within
Construction General Conditions need to be verified by ASU with the market to ensure the
Billing Rates are not excessive and are competitively market priced. Also, for labor costs and
site support costs within Construction General Conditions, supporting detail for these costs
should be included in all payment applications by the CM@Risk to allow for verification that
amounts paid to the CM@Risk for these costs are correct.
Criteria: The CM@Risk Tri-University Agreement (Agreement) requires that costs for
Construction General Conditions be paid by ASU to the CM@Risk for allowable costs only,
and for actual costs or negotiated amounts determined to be fair and reasonable to the
University. Labor costs within Construction General Conditions can be based on actual costs
or independently competitively priced with a separate pricing and scoping document explicitly
defining scope (including tiers of CMAR superintendents, engineers, etc.), Billing Rates, and
pricing method. ASU can decompose and benchmark underlying costs before agreeing to
the lump sum terms. In each payment application, the CM@Risk should include supporting
detail including invoices for site support costs.
Cause: A process had not been identified to determine the propriety of labor costs and site
support costs within Construction General Conditions. Regarding this process, in the Sun
Devil Fitness Complex Polytechnic Campus Construction Contract audit issued in November
2013, CPMG stated that the Tri-University Construction Task Force would review these
issues on Construction General Conditions and provide all three universities guidance for
resolution and ratification.
Effect: Following the cost control processes required by contract provisions could help
prevent potential overcharges and cost overruns, prevent unallowable costs and mark-ups on
Construction General Conditions, and help to ensure that the University pays a fair and
reasonable amount for its new facilities.
Recommendation: Billing Rates and site support costs need to be based on actual cost or
verified with the market by ASU to ensure they are not excessive. Supporting detail for labor
costs and site support costs should be included in all payment applications by the CM@Risk
to allow for verification that amounts paid to the CM@Risk for these costs are stated and
disbursed properly.
Page 10 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
Management Response: Concur. Requesting employee payroll information (particularly for
senior project personnel) has been met with resistance from the Contractor community in the
past as it potentially jeopardizes their employee retention leverage with competitor
Contractors. A preferred approach would be to establish an ABOR accredited regional
market rate for the construction industry at 3 AZ University locations which would be updated
annually and include average hourly rates for GC general condition employees, i.e. project
manager, asst. project manager, project superintendent, sight safety manager, which could
be used to ensure billing rates are not excessive. Perhaps the ASU School of Construction
could assist in the development and management of database of average personnel
(overhead) market rates for the construction industry.
2. Supporting Documentation was not provided Substantiating Subcontractor Bidding
Costs and cost of self-performed work.
Condition: The construction phase GMP of $41 million included $31.3 million paid to
subcontractors and for self-performed work, of which $19.2 million was bid appropriately, with
the lowest bid selected from at least three bids for these trades. While the CM@Risk
received three bids for the material portion of the self-performed work, documentation
reflecting the lowest responsive and responsible subcontractor bids from at least three bids
and documentation for independent price reviews for self-performed work for the remaining
amount of $12.1 million paid to subcontractors and for self-performed work, for the purpose of
verifying additional cost savings for ASU, was not provided.
For work self-performed by the CM@Risk (self-performed work), the University was to select
one or more independent qualified persons to review the CM@Risk Price Submission to
ASU. The reviewer was to report to the University and to the CM@Risk whether the reviewer
found the Price Submission to be reasonable and appropriate for the Construction Work to be
performed.
Criteria: The contract requires the use of independent cost verification control procedures
during the various design phases of the building, including obtaining at least three bids for
each subcontracted trade, and price reviews for self-performed work to prevent overcharges
and cost overruns. Sections 2.2.4.7 and 2.2.4.8 of the General Conditions to the contract
state, “If the CM@Risk becomes aware prior to any bid date that less than three (3) prequalified subcontractors plan to bid any portion of any Bid Package, the CM@Risk shall
promptly notify the Owner,” and “A proposal to accept other than a low lump sum bid shall be
justified in writing by the CM@Risk with sufficient detail to satisfy Owner, and be subject to
prior written approval by Owner.”
Page 11 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
When the CM@Risk self-performs the work, the CM@Risk is functioning as a subcontractor.
To verify the reasonability of the cost of self-performed work, Best Practices dictate receiving
competitive bids for the work. Alternatively, self-performed work could be competitively
priced with a separate pricing and scoping document explicitly defining scope, labor rates,
materials, and pricing method.
Cause: CPMG stated that independent cost verification control procedures were followed,
but because CPMG could not find written documentation verifying the completion of financial
control processes and procedures, CPMG does not know if the procedures were fully
documented.
Effect: Following the cost control processes required by ABOR Policies and contract
provisions can help prevent substantial amounts of overcharges and cost overruns, and
demonstrate that the University pays a fair and reasonable amount for its new facilities.
ABOR Policy Number 3-804 B.5 Professional Services and Construction Services
Procurement requires that negotiations for construction services are to include consideration
of compensation to be fair and reasonable to the University.
Recommendation: To ensure compliance with ABOR Policies and contract requirements for
independent cost verification and subcontractor bidding, CPMG should complete all cost
control procedures and maintain written documentation verifying that these procedures have
been completed.
Management Response: Concur, however, do not necessarily agree with $12.1M figure
reported as undocumented sub-Contractor/self-performed work requiring documentation of
minimum of 3 qualified bids (see chart below)
There is approximately $2.6M included in the $12.1M figure which is associated with a preselected vendor for design assist (W&W Design Assist) Although this work was not
competed, it was pre-approved in accordance with contract requirements and should not be
included in the $12.1M figure. There is a line item for construction contingency in the amount
of ~ $1.6M which should also not be included as “subcontractor bidding” requirement, as it is
not specifically assigned to a designated work item or associated with a specific
subcontractor. This allocation augments existing sub-contractors and would not be
competed, validated but not competed.
CPMG is responsible for ensuring proper
documentation and auditability of project execution is in full compliance with contract
requirements. CPMG will implement a standardized project filing format which all CPMG
PMs will adhere to. Project file template will include specific location for filing of all required
bid documentation.
Page 12 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
McCord Audit Bid Delta
W&W Design Assist Sub
$2,610,789
Pre-selected for design assist, competition not
feasible
DPR Self-perform
3,741,346
$1,174,862 of material bids were competed, labor
not
Construction
Contingency
1,611,667
Competition not required, only validation
Bids not per Contract
3,177,071
CPMG could not provide auditable documentation
1,026,093
Items in this category include electric and utility
bills, small purchases, time sensitive procurements
that are not reasonable to compete.
Pay App Misc. Items
Audit Not Bid Total
$12,166,966
3. Final independent corroborating cost estimate was not provided by the CM@Risk.
Condition: Per ABOR Policy Number: 7-109 Project Approval, to ensure that the University
paid a fair and reasonable amount for the new facility, upon completion of construction
documents an independent corroborating cost estimate was to be completed by an outside
cost estimating consultant and compared against the final CM@Risk Construction Cost
Estimate for the purpose of verifying that the amount charged to the University by the
CM@Risk under the contract was not excessive.
Criteria: The contract requires the use of independent cost verification control procedures
during the various design phases of the building, including outside corroborating cost
estimates. Section 2.2.3.4 of the General Conditions to the contract says, “The CM@Risk
shall prepare an estimate of Construction Cost as soon as major Project requirements have
been identified, and update the estimate for each submittal of the Design Submission
Documents specified in 1.2.12 of the General Conditions.” Cost estimates were required by
the CM@Risk at the Programming, Schematic Design, Design Development, and
Construction Documents phases, and to be independently prepared from cost estimates at
the same phases prepared by the Design Professional. The cost estimates of the CM@Risk
were to be compared to the estimates of the Design Professional. Audit could verify that only
Page 13 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
two of the eight required estimates were completed. ABOR Policy Number 3-804 B.5
Professional Services and Construction Services Procurement requires that negotiations for
construction services are to include consideration of compensation to be fair and reasonable
to the University.
Cause: The required Construction Cost Estimates were not provided by the CM@Risk and
Design Professional at all design phases of the building.
Effect: Completion of cost estimates, as required by ABOR Policy, can help prevent
substantial amounts of overcharges and cost overruns, and demonstrate that the University
pays a fair and reasonable amount for its new facilities.
Recommendation: To ensure compliance with ABOR Policies, the CM@Risk and Design
Professional should complete construction cost estimates.
Management Response: Performing a total of 8 cost estimates during the programming
through construction phase is expensive and does not always provide measurable value
added. Cost estimates associated with future contract requirements should be based on a
project specific basis, i.e. for large, complex projects – ASU should require up to 8 cost
estimates, for smaller, less complex projects – reduce the number of cost estimates
accordingly, not less than 2 (1 from CMAR and 1 independent from DP).
CPMG shall ensure that all cost estimates are performed and documented in accordance
with contract requirements. Leadership within CPMG shall perform internal quality assurance
checks throughout life of a project to ensure contract requirements and administrative policies
are in compliance.
Page 14 of 15
Arizona State University
McCord Hall Construction Contract
Audit Report - Number 15-04
January 30, 2015
Distribution:
Arizona Board of Regents Audit Committee
Michael M. Crow, President
Morgan R. Olsen, Executive Vice President, Treasurer and Chief Financial Officer
José A. Cárdenas, Senior Vice President and General Counsel
Joanne Wamsley, Vice President of Finance
Lisa S. Loo, Deputy General Counsel
Bruce Nevel, Associate Vice President, Facilities Development and Management
Bruce Jensen, Executive Director, Capital Programs Management
Diane Rowley, Associate Director, Capital Programs Management
Pollie Carter, Manager of Purchasing, University Business Services
Todd Raven, Interim Assistant Director, Capital Programs Management
Page 15 of 15
This page left blank intentionally.
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
This page left blank intentionally.
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Summary
The Health Insurance Portability and Accountability Act of 1996 (HIPAA) audit was
included on the Arizona State University (ASU) FY 2015 annual audit plan approved by
the Arizona Board of Regents (ABOR) Audit Committee and university senior
leadership. This audit was conducted to evaluate the efficiency of the HIPAA process
and university adherence to current policies and practices. The audit was requested to
review university compliance with new initiatives created by the U.S. Department of
Health and Human Services (HHS) and Office for Civil Rights (OCR) to more closely
monitor and identify violations.
Background: Arizona State University (ASU) provides health care and performs
research activities that are subject to the Federal Health Insurance Portability and
Accountability Act of 1996 (HIPAA). HIPAA’s purpose is to ensure the confidentiality,
integrity and availability of individuals’ protected health information.
The OCR enforces three rules related to HIPAA:
1. HIPAA Privacy Rule, which protects the privacy of individually identifiable health
information.
2. HIPAA Security Rule, which sets national standards for the security of electronic
protected health information (ePHI).
3. HIPAA Breach Notification Rule, which requires covered entities and business
associates to provide notification following a breach of unsecured protected
health information.
The Standards for Privacy of Individually Identifiable Health Information (Privacy Rule)
establishes, for the first time, a set of national standards for the protection of certain
health information. The HHS issued the Privacy Rule to implement the requirement of
HIPAA. The Privacy Rule standards address the use and disclosure of individuals’
health information called Protected Health Information (PHI) by organizations subject to
the Privacy Rule called covered entities, as well as standards for individuals' privacy
rights to understand and control how their health information is used.
The definition of PHI under HIPAA is broad and includes information maintained by or
for the covered entity relating to a person's health, the care received and payment for
services. Within the university, the covered entity is comprised of its health care
components, clinic components, physicians' offices, self-insured health plans, and
student health services. PHI does not include health information in employment records
maintained by the university in its role as employer.
Page 1 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Currently there are six designated covered components at ASU:
1.
2.
3.
4.
5.
6.
ASU Health Services
ASU Counseling Services
Speech and Hearing
College of Nursing and Healthcare Innovations Health Clinics (CONHI)
Center for Health Information and Research (CHiR)
University Technology Office
Effective February 18, 2010, in accordance with the Health Information for Economic
and Clinical Health Act of 2009 (HITECH), a Business Associate Agreement (BAA)
disclosure, handling and use of PHI must comply with HIPAA Security Rule and HIPAA
Privacy Rule mandates. Under the HITECH Act, any HIPAA business associate that
serves a health care provider or institution is now subject to audits by the OCR within
the HHS and can be held accountable for a data breach and penalized for
noncompliance.
Non-compliance with HIPAA regulations can lead to both civil and criminal penalties.
Violations of HIPAA could result in the following penalties:
For violations occurring prior to
2/18/2009
For violations occurring on or after
2/18/2009
Penalty
Amount
Up to $100 per violation
$100 to $50,000 or more per violation
Calendar
Year Cap
$25,000
$1,500,000
The HIPAA Regulations require the university, as a covered entity, to have a BAA
whenever a non-university person or entity provides services to the university involving
the use or disclosure of the university's protected information. HIPAA requires that
agreements with business associates include specific provisions. The university has
standard HIPAA BAA’s that should be used whenever a business associate agreement
is required.
Audit Objectives: The objectives of the audit engagement were to review all six
covered entities at ASU subject to HIPAA regulations and assess the level of
compliance with applicable policies and procedures and state and federal regulations as
it relates to PHI. In addition, perform a review of the controls in place surrounding the
HIPAA process to identify gaps and mitigate risks associated with the PHI.
Page 2 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Scope: The scope of this audit encompassed assessing the purpose and relevancy of
PHI-related data uses, controls and exposures for ASU. University Audit (Audit) gained
an understanding of the process and controls over the designated covered entities
through reviewing supporting documentation and holding interviews with applicable
staff.
Methodology: Audit performed a review of the current controls surrounding HIPAA
regulations as it relates to ASU covered entities. Audit interviewed HIPAA Privacy and
Security Officers from the following covered entities: ASU Health Services, ASU
Counseling Services, Speech and Hearing, CONHI, and CHiR.
During interviews conducted with Privacy and Security Officers, the following topics
were discussed:
• Policies and procedures followed related to the storage and retention of PHI and
ePHI.
• Training provided to staff that contact or interact with PHI and ePHI.
• Required forms to be completed by personnel and staff handling PHI and ePHI.
• Measures taken to ensure the security of ePHI on the system network.
• Requirements needed to be met to gain access to PHI and ePHI information.
• Background check requirements before access to PHI and ePHI are granted.
• Personnel and staff’s level of satisfaction of the current systems in place related
to PHI and ePHI.
• The level of interaction with other covered entities (Privacy and Security Officers
in other covered entities).
Walkthroughs were performed to observe the physical security of PHI files and gain an
understanding of who has access to PHI files.
Page 3 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Conclusion: Audit test work indicated that covered entities are in compliance with
HIPAA regulations but an overall control environment could be strengthened. Recent
changes to HIPAA regulations in 2012 increased the risks related to security of PHI and
ePHI. A strong control environment is mandated; if a breach was to occur, ASU would
have reputational risk as well as monetary fines assessed dependent on the severity of
the breach.
The evolution of the changing environment related to PHI and ePHI requires ASU to
take proactive approaches to ensure all HIPAA standards and regulations are being not
only met but exceeded. ASU is a unique and diverse institution that functions outside
most normal facilities that need to meet HIPAA requirements. The constant evolution of
the HIPAA process and uses of PHI and ePHI requires continual monitoring to assist in
the mitigation of risks.
While many of the requirements stipulated by HIPAA were disseminated across the
university, there did not appear to be uniform consistency of knowledge among Privacy
and Security Officers interviewed. A need was expressed to have a more active
influence from the University Privacy Officer providing direction and guidance to the
covered entities.
It was noted during the audit the University HIPAA Privacy Officer has made multiple
changes to the HIPAA process. With the continual evolvement of the HIPAA
requirements, the university may want to consider providing additional help to the
University Privacy Officer, to assist in the monitoring and functionality of the HIPAA
process.
In the remainder of this report, Audit has identified exceptions to the process and
additional steps that could be taken to mitigate risks associated with HIPAA regulations.
Page 4 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
The control standards we considered during this audit and the status of the related
control environment are provided in the following table.
General Control Standard
(The bulleted items are internal control objectives that
apply to the general control standards, and will differ
for each audit.)
Reliability and Integrity of Financial
and Operational Information
• Business Associate Agreements are
utilized for vendors handling PHI
• Properly monitoring access to PHI and
ePHI
Effectiveness and Efficiency of
Operations
• Proper channels for distribution of
business practices related to PHI
• Regular communication is provided to
covered entities handling PHI
• HIPAA training is properly monitored
and tracked
Safeguarding of Assets
•
•
•
Proper forms and background checks
are being completed
All personnel privy to PHI and ePHI
have completed the HIPAA training
PHI and ePHI is properly secured
Control
Environment
Opportunity for
Improvement
Opportunity for
Improvement
Reasonable to Strong
Controls in place
Opportunity for
Improvement
Reasonable to Strong
Controls in place
Opportunity for
Improvement
Opportunity for
Improvement
Opportunity for
Improvement
Finding
No.
Page
No.
4
8
5, 7
9, 11
N/A
N/A
2
6
N/A
N/A
6
9
3
7
1
6
N/A
N/A
N/A
N/A
Compliance with Laws and Regulations
•
ASU is following HIPAA regulations
•
Following ASU policies and procedures
Reasonable to Strong
Controls in place
Reasonable to Strong
Controls in place
We appreciate the assistance of the University HIPAA Privacy and Security Officers and
the University Privacy Officer.
________________________
Chris Crisci, CPA
Internal Auditor Senior
________________________
Tracy Grunig, MPA, CPA, CISA, CFE
Chief Audit Executive
Page 5 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Audit Results, Recommendations and Responses
1. Electronic Personal Health Information was stored on a local drive.
Condition: Nursing staff at the CONHI improperly stored ePHI on a local server instead
of the secured network. The information was stored on the local server as it related to
the current process for depositing co-pay funds collected from patients at the time
services were rendered. The ePHI was being used for financial and patient account
reconciliation purposes.
Criteria: Covered entities are required to store ePHI in a secure environment.
Cause: Nursing staff were unaware that the local servers were not considered secure. It
was believed that since only they had access, it was considered secure.
Effect: ePHI stored on a local server instead of the secure Citrix server allows for
greater access to the information. This increases the risk of a breach and the possibility
of causing reputational and monetary damages to the university.
Recommendation: Ensure all ePHI is removed from local servers. Review the current
deposit process and modify process to de-identify or not include PHI as it relates to
deposit and patient reconciliation purposes.
Management Response: This recommendation has been initiated. The College of
Nursing Privacy Officer is removing all ePHI from local servers and is revising the
storage process. The university HIPAA Privacy Officer has reinforced university
security practices reminding the department of effective security practices. Deadline for
completion is December 31, 2015.
2. Increase the communication between HIPAA covered entities.
Condition: Currently, no continuous line of communication exists between the HIPAA
Security and Privacy Officers of the covered entities. Group meetings are not being
mandated for the Security and Privacy Officers to encourage sharing and learning
opportunities to increase the knowledge of the entities. Many of the entities are
functioning in a similar manner and exhibiting similar risks and challenges related to
HIPAA compliance regulations.
Page 6 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Criteria: Communication of the entities is significant to gain economies of scale and
increase the knowledge of each entity. Scheduled meetings may improve the
dissemination of new PHI and ePHI requirements as well as provide an open forum to
discuss problems or obstacles the entity may be faced with.
Cause: It has not been the practice of the university to have meetings for all covered
entities.
Effect: Not having a formal channel of distribution and training for departments is
leaving the university in a vulnerable position related to PHI and ePHI requirements
regulated by HIPAA.
Recommendation: Conduct regular meetings with the Privacy or Security Officer
attending. The regular meeting with personnel and staff from the covered entities could
provide training and open forums to discuss obstacles or adversity they may be facing.
Management Response: This recommendation has been implemented. The ASU
HIPAA Privacy Officer and HIPAA Security Officer have implemented an annual
communication plan including regular meetings (likely quarterly) and regular
communications and cross-training opportunities.
3. Contracted janitorial staff cleaning in areas with HIPAA related information are
not properly trained or aware of the regulations surrounding HIPAA information.
Condition: Contracted janitorial staff has access to areas in the clinics and offices
where PHI is stored. The janitorial staff had not completed the HIPAA training mandated
by ASU.
Criteria: Mandating all contracted janitorial staff to perform the HIPAA training course
decreases the liability to the university and ensures having proper recourse if PHI is
improperly shared or breached.
Cause: Contracted janitorial staff with access to PHI was not required to complete the
HIPAA training required by the university.
Effect: Contracted janitorial staff could improperly and unknowingly share PHI, leaving
the university in an unfavorable position by not providing proper documentation for legal
recourse.
Page 7 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Recommendation: The covered entities should review all personnel who have access
or may come in contact with PHI and require them to complete the mandatory HIPAA
training course required by the university and have them sign a document agreeing to
the completion and understanding of PHI information.
Management Response: This recommendation has been initiated in Covered Entities
(CE). A process has been worked out in Health Services that can be mirrored in other
CEs. In addition, every CE engages in general privacy and security practices that limit
exposure of PHI to janitorial staff.
4. No business associate agreement with Canon Inc. copiers exists.
Condition: A business associate performs functions or activities on behalf of a covered
entity that involves access to protected health information or a subcontractor that
creates, receives, maintains, or transmits protected health information on behalf of
another business associate. Cannon Inc. is responsible for performing maintenance
and collection and redistribution of copiers. The copiers contain an internal hard drive
allowing for the PHI to be stored on the copiers. This inadvertently gives Cannon Inc.
access to university PHI. Business associate agreements are required with all partners
that have access to PHI from the university.
Criteria: Canon Inc. is the copy machine provider for the university. Larger copiers have
hard drives stored in the machines and Canon Inc. is responsible for the maintenance
and recollection and redistribution of the machines.
Cause: Canon Inc. did not have a BAA filed with the university when the audit was
conducted.
Effect: BAA’s mandate the business handling PHI adhere to HIPAA rules and can be
held accountable for a data breach and penalized for noncompliance. Without a signed
BAA, the university could have less legal recourse on the company that has improperly
stored, disposed, or shared PHI.
Recommendation: Obtain a BAA from Canon Inc. ensuring they are responsible and
aware of the requirements for proper handling of copiers used with PHI information.
Page 8 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Management Response: ASU agrees with this recommendation. The process for
obtaining a BAA with Canon has been initiated with Sam Wheeler, Executive Director
Business and Auxiliary Services.
5. Perform more thorough self-monitoring audit steps on access to PHI at the
covered entries.
Condition: Currently clinic staff are randomly selecting patients and reviewing who has
accessed the patient’s information to see if there has been improper access to a
patient’s record.
Criteria: The sampling method does provide a level of assurance. However, a more
judgmental sampling method should be used when performing self-monitoring audit
steps.
Cause: The clinics have always performed the review in this manner and the process
has not been reviewed to identify a more efficient way of performing the review prior to
this audit.
Effect: By using a random selection of patients, clinic staff is not effectively gaining
insight into who is accessing patient’s records. Limiting the review to a random sample
is not conducive to identify the improper viewing of PHI by someone other than the
intended person.
Recommendation: Perform a more thorough review of PHI accessed. For example,
obtain a list of physician’s known patients, and then review which patient files the
physician have accessed outside of their known patients and determine the reason(s)
for access to those patients.
Management Response: ASU agrees with this recommendation. All CEs will be asked
to provide the University Privacy Officer and Security Officer a more thorough and
specific process for reviewing access to PHI. The scheduled deadline for submitting a
plan is December 31, 2015 and the scheduled deadline for implementation is June 30,
2016.
6. Confidentiality agreements signed by all personnel using PHI.
Condition: Currently it is not a requirement of the university to have all personnel
handling or dealing with PHI sign a confidentiality agreement. Confidentiality
Page 9 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
agreements provide legal documentation requiring an employee to sign a consent
stating they understand general rules of PHI.
Criteria: Mandating all employees handling PHI and ePHI to complete a confidentiality
agreement may decrease the liability to the university and ensure proper legal recourse
if PHI is improperly communicated or shared.
Cause: It has not been the practice of the university to have staff and personnel sign
confidentiality agreements in previous years.
Effect: Without a signed confidentiality agreement the university could reduce the legal
consequences of an employee found who has improperly shared or discussed PHI.
With a confidentiality agreement, the university would have legal recourse and reduce
the chances of being in an unfavorable position.
Recommendation: Require all staff and personnel to sign a confidentiality agreement
coinciding with the HIPAA training that is being mandated. Include this as part of the onboarding process and annual certifications. Confidentiality agreements could include
information such as the following:
• Protected Health Information (PHI) is considered confidential and should not be
used for purposes other than its intended use.
• Ethical and legal obligation to protect PHI used or obtained in the course of
performing duties and understand that all policies on confidentiality apply equally
to data stored on the computer and on paper records as well as information
discussed.
• Authorization to disclose PHI is made only by owners of the PHI and only on a
need to know basis.
• Unauthorized use of, or access to, PHI may result in discipline up to and
including termination. Violation or breach of confidentiality, with regards to PHI,
may also create civil or criminal liability.
Management Response: ASU agrees with this recommendation. The HIPAA training
module was revised. A “certification statement” will be added to the end of the training
that will specifically state the above points in recommendation. Participants in the
training are not be able to complete the training without certifying an understanding the
general rules of PHI and University practice. This was added and part of the training
released in summer 2015.
Page 10 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
7. Roles and responsibilities of individuals utilizing and using PHI and ePHI are
not documented and communicated to the entire organization.
Condition: A document with the responsibilities (e.g., job description) including
information related to the specific roles and responsibilities of individuals utilizing PHI
and ePHI should be maintained to reinforce the security standards issued by the HHS.
Criteria: Requesting departments to document the roles and responsibilities of
individuals with access to PHI and ePHI will assist the covered entities and the
University HIPAA Privacy Officer to clearly identify job duties and needs. In addition,
provide a road map of who may be using PHI and ePHI allowing for reviews to be
performed ensuring proper access.
Cause: The data needed to provide this information to the University HIPAA Privacy
Officer had not been considered or developed prior to this audit.
Effect: Having a formal description of roles and responsibilities reported to the
University HIPAA Privacy Officer could decrease the risk of staff and personnel
improperly viewing or accessing PHI and ePHI. Roles and responsibilities documented
can assist the University HIPAA Privacy Officer in identifying areas of concern within the
organization. This could identify people accessing PHI and ePHI without a valid
purpose.
Recommendation: Mandate all covered entities create organizational charts including
job descriptions, roles, and responsibilities for individuals utilizing PHI and ePHI. The
data should be provided to the University HIPAA Privacy Officer and regularly reviewed
to determine if the responsibilities of individuals utilizing PHI and ePHI have been
clearly defined.
Management Response: ASU agrees with this recommendation. As part of the annual
communication plan, all Covered Entities will be asked to send an organization chart
with roles and responsibilities related to PHI to the University Privacy Officer and
Security Officer. Updates will be requested on an annual basis.
Page 11 of 12
Arizona State University
HIPAA Compliance
Audit Report – Number 15-08
May 7, 2015
Distribution:
Arizona Board of Regents Audit Committee
Michael M. Crow, President
Morgan R. Olsen, Executive Vice President, Treasurer and Chief Financial Officer
Mark Searle, Deputy Provost, Chief of Staff and Professor
José A. Cárdenas, Senior Vice President and General Counsel
Lisa Loo, Deputy General Counsel
Joanne Wamsley, Vice President for Finance
Gordon Wishon, Chief Information Officer
Tina Thorstenson, Assistant Vice President and Chief Information Security Officer,
HIPAA Security Officer
Aaron D. Krasnow, Assistant Vice President and Director, ASU Counseling Services,
HIPAA Privacy Officer
Benjamin Mitsuda, Associate General Counsel, General Counsel for HIPAA Compliance
Page 12 of 12
Download