Disc Services 29/11/04 End-cap Disc Services Assembly at RAL – Mon 29 Nov 2004 Colin Dabinett, Stephen Haywood, Ian Wilmut See http://hepwww.rl.ac.uk/atlas-sct/engineering/ec/disc_services/ in particular Progress (just above Mins) and Circuits—progress chart. 1. 1.1 Progress Cooling Circuits Disc Outer Middle Inner Needed 2C 4 4 4 15 Nov 1C 2 wip 4 X 24 Dec UK Spare → 2A 0 1 + 2 wip 4 18 Jan 5A 4 4 4 11 Nov 4A 4 4 4 2 Dec 3A 0 1 +2 wip 4 6 Jan 2A → Spare 2 0 0 1 20 Jan 1A 0 0 X 27 Feb Spare 3 0 0 1 Some bent Pins have been found on 5C Circuits; just seem to be associated with 2nd Point Hi Blocks – origin unclear, but looking at Soldering Jig. Ian 1.2 Inform Liverpool & Nikhef when resolved issues. Disc 6C – Martin Around line 135. Some fraction of front also placed. A Torlon pad is partially detached – will be recorded as nonconformance, even though should be fine when fixed. 1.3 Disc 5C – Geoff Around line 115. Some bent Pins identified – these will be replaced. 1.4 Disc 4C – Graham Around line 111. 1.5 Disc 3C – Mike Around line 111. 1.6 Nikhef (from 22 Nov) ¼ Disc Flushing with Swansolve. 9A Soldered Cooling Circuits. 8A Routing Harnesses. 7A Tapes on; Front Cooling on; doing Opto-pluggins. 6A G&S Foils soldered. 1 Disc Services 29/11/04 5A Hope to add Services (already delivered) around mid-Dec. 4A Would like G&S Foils wb 22 Nov. Need Cooling Circuits 1 Jan. Seem to be problems with contamination of Nikhef Swansolve. Ian 2. Provide advice on Grounding Tab between Disc and Cylinder. Components 2.1 General Paragon seem to have sorted out plating problems. Await more today (29 Nov). We have enough Foils for 2C (F+R) and 4A (R) – we should be careful what we do with Rear Foils in light of RAL & Nikhef requirements. In addition, still need Foils for 6 Discs: 1C, RAL-Spare, 3A, 2A, 1A, Nikhef-Spare. John is making some “dust covers” for the ends of the Cooling Circuits. Need ~400 Clips per Disc. Probably do not have enough for Spare Discs. 2.2 Ian Order more (“banjo”) Clips. Ian Check how many Splice Clips we have and ask Pawel for more. FSI The nominal priority is 6A (need 10 Dec) and then 2C (need 23 Dec). 2.3 Tapes & OptoHarnesses Have all Tapes for 2C and most for 4A and 3A. 2.4 Cooling There were some problems with Connecting Pieces for odd Discs (trying to use common pieces). Colin is getting some test pieces made to resolve issues. We have 209 Main-Lo Blocks – awaiting plating. Sandwiches for 209 Main-Hi Blocks sent to Brite. Stephen 2.5 Clarify plan with John Spencer. Nikhef Hope to send by 2 Dec: Circuits for 4A Replacement Circuit Mid-1002-102#19 G&S Foils for 4A Peek Clips (“Banjo”) – 1000 off Litz Wire Tapes for 4A (except 4W11) & 3A (except 4W11, 2W6), although may have missing Tapes in time Connecting Pieces for 5A 3. Plans for Week 3.1 Cooling Circuits On track. 2 Disc Services 3.2 29/11/04 Daresbury Making good progress. 3.3 Disc 6C – Martin/Paul Precise Placement with Mike’s help. When we are ready to send to Liverpool: Stephen 3.4 Order a high-series Transit van and sort out Insurance. Disc 5C – Geoff Complete soldering of Circuits; then Leak Testing etc. Paul to help. Propose to do DCS later. Replace bent Pins – hope to simply replace Mini-Wiggle Circuit. At least one week’s work before ready for Post-Assembly phase. 3.5 Disc 4C – Graham Soldering of Circuits. At least two weeks’ work before ready for Post-Assembly phase. 3.6 Disc 3C – Mike Emma to retest replaced Tape. Soldering of Circuits. 3.7 Disc 2C Arrived 18 Nov. Can do ~3 days work before need Mini-Cylinder – Tim is making one (or use one from 6C). Hope to start 6 Dec. 3.8 Testing – Emma Retesting 3C. 3.9 Other Martin assembling Flushing Unit – should be finished by 3 Dec. Colin 4. 4.1 Check compressed air with Martin. Matters Arising Spare Discs Discs come with Primary Pads from Nikhef. Propose to add Reflectors, but not Jewels and Harnesses. Stephen 4.2 4.3 From Liverpool Qualification Stephen Ask Tony for logs on CD to be sent up with Disc. Ian Check Fingers are glued down. Ian Follow up location of PPF0 Guides. Safety Stephen 4.4 Check with Pawel. Check Working-alone Risk Assessment. Dbase Ian Think about RAL Dbase for a) Cooling Circuits 3 Disc Services 29/11/04 b) on-Disc components 4.5 Disc Weight Should include glue & solder. 4.6 4.7 Schedule Improvement 1C – would like ~2 Dec as a “spare”, Nikhef plan to ship 17 Dec. Flushing Rig – Martin is assembling this. Non-conformity in Hi-Lo Nature of Circuits Ian 4.8 Spares for Cooling Colin 5. Come up with an ECR. Order spares, including complete set of u and v Pipes (ignore common Pipes). Up-coming Issues for Consideration When all Discs are completed, hold a close-out review. 6. Next Meeting Next: 6 Dec. SH 29/11/04 4