Queen Elizabeth Outdoor Pool Redevelopment Project Recommendation: That the September 30, 2008, Community Services Department report 2008CSR029 be received for information. Report Summary This report summarizes the results of a Request for Tender process that was undertaken to determine the scope of the Queen Elizabeth Outdoor Pool Redevelopment Project that can be constructed at the Kinsmen site for $5.5 million. Previous Council/Committee Action At the July 14, 2008, Community Services Committee meeting, the following motion was passed: That Administration tender a Request for Proposals for Construction Management Design Build of a six-lane outdoor pool, including the wading component, at Kinsmen Park for a total project cost of $5.5 million, and return to the October 6, 2008, Community Services Committee meeting. Report 2008 Project Background On January 16, 2008, City Council directed Administration to explore the feasibility of developing an outdoor pool at the Kinsmen Park, and to retain the approved program previously endorsed for the Queen Elizabeth Outdoor Pool Redevelopment Project. This motion was the result of the projected cost of the redevelopment of Queen Elizabeth Outdoor Pool, at the original site (tendered in September 2006 and again in January 2007) coming in significantly over budget ($7.6 million in 2006, and $8.1 million in 2007). The most recent Queen Elizabeth Outdoor Pool program and design was developed in consultation with the Friends of Queen Elizabeth Pool Society (FQEPS), the aquatic community, and the Kinsmen Club of Edmonton. The feasibility report, responding to the January 16, 2008, motion to study the relocation of the Queen Elizabeth Pool program to the Kinsmen Site, was brought forward to Community Services Committee meeting, on July 14, 2008. The report indicated that the estimated cost was $5.3 million in 2008 dollars and with inflation factors of 20% applied, and a design and construction contingency of 30% applied, the funding shortfall could have reached $2.4 million ($7.7 million total). At the July 14, 2008, Community Services Committee meeting, the Committee heard from the FQEPS and Edmonton Springboard Platform Diving Club. They spoke of the need for a six lane pool with recreational diving capabilities. Community Services Committee directed the Administration to issue a Request for Proposal (RFP) to modify the program to reflect a six lane rectangular pool tank, and to remove the zero depth entry, the lazy river, ROUTING – Community Services Committee | Delegation – R. Smyth/C. Ward WRITTEN BY – M. St. Louis/C. Ward | September 30, 2008 – Community Services Department 2008CSR029 Page 1 of 3 E 8 Queen Elizabeth Outdoor Pool Redevelopment Project and the hot tub, as previously recommended by the stakeholder groups. The RFP direction was to determine if the amended program could be built for $5.5 million. Activities resulting from July 14, 2008, Community Services Committee Motion As directed, the RFP documents were prepared with the pool configuration as noted in the July 14, 2008, motion, and with all other minimum program requirements necessary to meet building codes and City policies. The RFP requested total project costing for the scope identified, and the degree of cost accuracy at that level of conceptual design. The minimum acceptable scope identified the following general elements, with the intent to build the program back up to consider increasing the pool depth and additional leisure elements, if this could be achieved within the approved budget: a 25 metre, 6 lane, pool with depth ranging from 1-2.5 metres; adequate deck space, amenities, lighting, mechanical, and security systems to effectively serve the customers; an open change facility with covered family change stalls, and separate male/female change rooms; first aid room and control desk; and, a water play park with a children and family oriented aquatic design. The RFP documents were issued and remained open for submission from July 24 to August 14, 2008. Four bids were received. One bid Page 2 of 3 was disqualified due to noncompliance with the terms of the RFP documents. The remaining submissions were evaluated and the project was awarded to Jen-Col Construction Ltd. on August 29, 2008. A start-up meeting was held immediately after award to discuss the project, the information requirements, and the overall project schedule. The estimated construction schedule has a start date of April 1, 2009, and a completion date of December 15, 2009. Jen-Col Construction Ltd. has responded to the RFP by providing a pre-concept estimate of $5,842,535 (see Attachment 1). This estimate reflects total project cost, is stated in September 2008, dollars, and provides a 9.5% design and construction contingency factor. The estimate is not escalated to match the construction schedule. Risks Based on City forecasts, inflation factors are projected to be 14% annually; therefore a cost escalation allowance of $660,000 is advisable to ensure the completion of this project. Jen-Col Construction Ltd. forecasts design and construction contingency at 9.5% ($393,995). Since the project is at a concept level only, the Administration recommends a 30% contingency be applied to this project. This difference in contingency amounts to an additional $850,000. The estimated total project costs could reach $7,352,535. This does Queen Elizabeth Outdoor Pool Redevelopment Project not include demolition of the existing Queen Elizabeth Outdoor Pool site. 2. Summary of Queen Elizabeth Outdoor Pool Cost Estimates. Jen-Col Estimate City Escalation Additional Design and Construction Contingency $5,842,535 $ 660,000 Others Reviewing this Report M. Koziol, General Manager, Capital Construction Department C. Warnock, Chief Financial Officer TOTAL $7,352,535 $ 850,000 Attachment 2 provides a summary of the Queen Elizabeth Outdoor Pool Redevelopment cost estimates. Policy Approved Policy C534 – Outdoor Aquatics Focus Area Outdoor aquatic experiences contribute to a quality environment and social and cultural key outcomes areas that promote vibrant, inclusive, and safe communities. Budget/Financial Implications There has been no changes to previously approved/submitted budgets, as noted below: - $4.1 million is approved through project 06-75-2515. - The Kin Park Wading Pool redevelopment has $300,000 approved in project 06-28-5223 with an additional $700,000 allocated in the 2009-2011 funded Capital Plan. - The Friends of Queen Elizabeth Pool Society have raised approximately $400,000 for the project through CFEP grants. Attachments 1. Jen-Col Construction Ltd. Feasibility Budget Report Page 3 of 3 Attachment 2 Summary of Queen Elizabeth Outdoor Pool Redevelopment Cost Estimates Original Program (Queen Elizabeth Site) 2006 $7.6 million (tender price) 2007 $8.1 million (tender price) 2008 Original Program (Kinsmen Park Site) Modified Program (Kinsmen Park Site) $7.7 million $7.4 million (July concept estimate) (September concept estimate) Note that these estimated costs do not include demolition and restoration of the existing Queen Elizabeth site. Page 1 of 1 Report: 2008CSR029 Attachment 2