MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28 TH TO 30TH
AUGUST 2009
AUGUST 2009
The 148th meeting of the Northern Regional Committee (NRC), National Council for Teacher Education (NCTE) was held from 28th
30th August, 2009 at Jaipur. The following members and convener were present:
1 Prof. D.N.Sansanwal
to
Chairperson, NRC-NCTE
2
Prof. M.P. Sharma
Member, NRC-NCTE (29-30 August, 2009)
3
Prof. U. C. Vashishtha
Member, NRC-NCTE (29-30 August, 2009)
4
Prof. S. P. Anand
Member, NRC-NCTE
5
Prof. F. U. Khan
Member, NRC-NCTE (29-30 August, 2009)
6
Prof. M.K. Das
Member , NRC-NCTE
7
Mrs. Usha Bapna
Representative of the State Govt of Rajasthan (28 August, 2009)
8
Mr. S. Kalia
Representative of the State Govt of Haryana
9
Dr. R.S. Barar
Representative of the UT Chandigarh.
10 Dr. Jagdish Prasad
Representative of the Govt. of Uttrakhand
11 Dr. K.S. Yadav
Convener RD, NRC, NCTE
Prof. Bharti Baweja could not attend the meeting.
Dr. K.S. Yadav, Convener RD, NRC, NCTE welcomed the Hon’ble Chairperson and members of Northern Regional
Committee.
With the permission of the Chairperson, Dr. K.S. Yadav (Convener) presented the Agenda before the Committee. Agenda-wise
decisions taken were as follows:S. NO. AGENDA
NO.
1
148.01.
CASES
DECISION OF NRC
CONFIRMATION OF THE MINUTES OF THE 147TH MEETING OF NRC. THE MINUTES OF Minutes are confirmed.
147TH MEETING OF NRC HELD ON 16TH TO 17TH AUGUST 2009 HAVE BEEN UPLOADED ON
THE WEBSITE OF NRC.
-1-
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AGENDA ITEM NO. 148.03.00
CONSIDERATION OF APPEAL ORDERS
S. NO. AGENDA NAME OF THE INSTITUTION
NO.
2
AUGUST 2009
APPEAL ORDER
APPEAL DECISION
DECISION OF NRC
NIMT
B
SCHOOL
FOR F. No. 89-366/2009- The appeal was rejected and NRC’s Decision
of
Appeal
EDUCATION,
VILLAGE
- appeal /99423 dated order
dated
31.3.2009
was Committee is Noted.
AVANTIKA, CHIRANJIV VIHAR, 7.8.2009.
confirmed.
POST- GHAZIABAD, U.P.
COURSE – B.ED. , UP-3295
3
RAMWATI
RAJ
BAHADUR F. No. 89-56/2009- The appeal was rejected and NRC’s Decision
of
Appeal
DEGREE
COLLEGE,
VPO- appeal /100037 dated order
dated
16.6.2009
was Committee is Noted.
PRATHVIPUR, DISTT.-ETAWAH, 7.8.2009.
confirmed.
UP
Course – B.Ed. , UP-3165
4
NIMT
INSTITUTE
OF F. No. 89-573/2009- The appeal was rejected and NRC’s Decision
of
Appeal
EDUCATION GREATER NOIDA, appeal /100033 dated order
dated
4.6.2009
was Committee is Noted.
ADD-UNITED
EDUCATION 7.8.2009.
confirmed.
SOCIETY NIMT,PLOT NO-41 K
P-1, DASNO ROAD NEER PORI
CHOWK,
VIIL-GREATER
NOIDA,
DISTT,
GAUTAM
BUDHA NAGAR
COURSE –B.ED. , U.P.-3434
5
PRAKASH JAN KALYAN AVAM F. No. 89-511/2009- The appeal was rejected and NRC’s Decision
-2-
of
Appeal
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
SIKSHA
U.P.
SAMITI,
HATHRAS, appeal /99803 dated DECISION WAS CONFIRMED.
7.8.2009.
AUGUST 2009
Committee is Noted.
UP-3301, COURSE – B.ED.
6
SUBHARTI
INSTITUTE
OF F. No. 89-535/2009- The appeal was rejected and NRC’s Decision
of
Appeal
MANAGEMENT
& appeal /99819 dated order
dated
5.6.2009
was Committee is Noted.
INFORMATION TECHNOLOGY, 7.8.2009.
confirmed.
KHASRA NO.-1628 & 1629,
SUBHARTI
PURAM,
VP0MALIYANA,
DISTT.-MEERUT,
UP
COURSE – B.ED. , UP-3118
7.
DEEN
DAYAL
COLLEGE, F. No. 89-337/2009MUZAFFARNAGAR, U.P.
appeal /99903 dated
7.8.2009.
UP-1845, COURSE – B.ED.
ADDITIONAL
The appeal was rejected and NRC’s Decision
of
Appeal
order
dated
16.7.2009
was Committee is Noted.
confirmed, in so far it is related to
grant of additional intake to the
existing
B.Ed.
course
of
the
institution.
8.
RAMNATH
DHANANJAYA F. No. 89-469/2009- The appeal was rejected and NRC’s Decision
of
Appeal
SMARAK
MAHILA appeal /99935 dated order
dated
10.6.2009
was Committee is Noted.
MAHAVIDYALAYA,
7.8.2009.
confirmed.
JAGDISHPUR,
ATRAULIYA,
AZAMGARH,
VILLJAGDISHPUR,
POSTDEVRAPATTI,
DISTT.AZAMGARH,
UP-3480, COURSE – B.ED.
9.
SHRI RAM BHAROSEY SINGH F. No. 89-601/2009- The appeal was rejected and NRC’s Decision
of
Appeal
MAHAVIDYALAYA, BAJEHARA, appeal /99951 dated order
dated
19.6.2009
was Committee is Noted.
HARDOI
,
KHASRA
NO- 7.8.2009.
confirmed.
221,413,
VILL-BAJEHARA,
POST-SIRSA, DISTT.-HARDOI,
U.P.
-3-
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
COURSE – B.P.ED., UP-3539
10
SHANTI NIKETAN INSTITUTE F. No. 89-600/2009- The appeal was rejected and NRC’s Decision
of
Appeal
OF TECHNOLOGY, MEERUT, appeal /99523 dated order
dated
10.6.2009
was Committee is Noted.
U.P.
7.8.2009.
confirmed.
UP-3000, COURSE –B.ED.
11
SHREE
BALAJI
DEGREE F. No. 89-341/2009- The appeal was rejected and NRC’s Decision
of
Appeal
COLLEGE, BHAGPAT ROAD, appeal /99587 dated order
dated
12.4.2009
was Committee is Noted.
VILL.-KURALI,
POST.-JANI 7.8.2009.
confirmed.
KHURD, DISTT.-MEERUT, UP
UP-3081, COURSE – B.P.ED.
12
VIMLA
RANI
BHARGAVA F. No. 89-401/2009- The appeal was rejected and NRC’s Decision
of
Appeal
BALIKA
DEGREE
COLLEGE, appeal /99603 dated order
dated
15.5.2009
was Committee is Noted.
VPO-TEWAN,
TEHSIL- 7.8.2009.
confirmed.
MANJHANPUR,
DISTT.KAUSHAMBI, UP
UP-3240, COURSE – B.ED.
13
SHRI RAM INSTITUTE OF F. No. 89-39/2009EDUCATION, VILL.-TIMAKIYA, appeal /99459 dated
BAGHPAT ROAD, POST-JANI 7.8.2009.
KHUD, MEERUT, UP
The council remanded back the case Decision
of
Appeal
to the NRC for inspection of the Committee is Noted and VT
institution
immediately
and be constituted.
thereafter
to
issue
order
accordingly.
COURSE – B.ED. , U.P. –3075
14
KRISHNA GIRLS ACODEMY, F. No. 89-437/2009- THE CASE WAS REMANDED BACK Decision
of
Appeal
KHASRA
NO-313,
VILL- appeal /99791 dated TO THE NRC FOR INSPECTION OF Committee is Noted and VT
LARAMDA, POST-BICH PURI, 7.8.2009.
THE INSTITUITON IMMEDIATELY.
be constituted.
DISTT.-AGRA, U.P.
COURSE – B.ED. , UP-3517
15
VANSA
DEVI
DEGREE F. No. 89-516/2009- REMANDED BACK THE CASE TO Decision
of
Appeal
COLLEGE, JAUNPUR, U.P.
appeal /99955 dated NRC FOR TAKING NECESSARY Committee is Noted and VT
-4-
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
7.8.2009.
ACTION INCLUDING CAUSING OF be constituted.
INSPECTION OF THE INSTITUTION
TO ASCERTAIN THE AVAILABILITY
OF
INFRASTRUCTURE
AND
INSTRUCTIONAL FACILITIES AS PER
NORMS AND THEREAFTER PASS
APPROPRIATE ORDERS.
COURSE – B.ED., UP-2808
16
SHIVLOK
SHRIENET F. No. 89-336/2009MAHAVIDYALAYA, KHASRA NO- appeal /99731 dated
792, 803, GREAT DUCCEN 7.8.2009.
ROAD, VILL.-KAPSAUR, POSTPARARI,
TEHSIL-SADAR,
DISTT.-MIRZAPUR, UP
COURSE – B.ED., UP-3303
17
AUGUST 2009
THE
COUNCIL
REACHED
THE Seek guidance from CP, HQ.
CONCLUSION THAT THERE WAS
ENOUGH GROUND TO ACCEPT THE
APPEAL, THE ORDERS OF NRC
DATED 10.6.2009 WAS SET ASIDE
AND REMANDED BACK THE CASE
TO NRC FOR RECONSIDERATION OF
THE CASE.
PT.TRIPUARI MISHRA ADARSH F. No. 89-488/2009- THE CASE WAS REMANDED BACK Decision
of
Appeal
MAHAVIDYLALAYA,
VILL- appeal /99807 dated TO THE NRC FOR INSPECTION OF Committee is Noted and VT
RAHUA
MUSTAFABAD,
PO- 7.8.2009.
THE INSTITUTION IMMEDIATELY.
be constituted.
GANADIH,
TEHSIL-LALGANJ,
DISTRICT-AZAMGARH, U.P.
COURSE – B.ED., UP-3360
18
17.
PANNA
MAHAVIDAYALAY, F. No. 89-597/2009KHASRA
NO-870,
KUSHAN appeal /99507 dated
BRAHMAN,
VPO-BHIMPURA 7.8.2009.
NO.-1,
BILTHARA
ROAD,
DISTT.-BALLIA, UP
THE CASE WAS REMANDED BACK Decision
of
Appeal
TO
THE
NRC
FOR
FURTHER Committee is Noted and VT
PROCESSING OF THE APPLICATION be constituted.
FOR INSPECTION AND THEREAFTER
ISSUING ORDER.
COURSE – B.ED., UP-3213
19
18.
MOHARMAN SINGH SECHIK F. No. 89-405/2009- THE CASE WAS REMANDED BACK Decision
of
Appeal
AND
SAMAJ
KALYAN appeal /99567 dated TO THE NRC FOR INSPECTION OF Committee is Noted and VT
SANSTHAN, ETAH, U.P.
7.8.2009.
THE INSTITUTION IMMEDIATELY be constituted.
AND
THEREAFTER
TO
ISSUE
ORDER.
COURSE – B.ED., UP-3396
-5-
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
20
19.
DEEN
DAYAL
COLLEGE, F. No. 89-335/2009MUZAFFARNAGAR, U.P.
appeal /99687 dated
7.8.2009.
COURSE – M.Ed., UP-2193
THE REMAND BACK THE CASE TO
NRC FOR EXAMINATION OF THE
STAFF PROFILE SO AS TO ENSURE
THAT THEY HAVE BEEN APPOINTED
AS
PER
NCTE
NORMS
AND
THEREAFTER PASS APPROPRIATE
ORDERS.
AUGUST 2009
Decision
of
Appeal
Committee is Noted. As per
the documents submitted to
the
Appeal
Committee
regarding appointment of
Faculty,
the
committee
observes the following:


Mrs. Bhavana Joshi,
Ms. Deepti Gairola
and
Mr.
Praveen
Kumar
appointed
Lectures
do
have
Ph.D. degree. Hence,
they
are
not
qualified.
Reader has not been
appointed.
Hence,
the
committee
decides to issue Show Cause
Notice on above points and
directs the Institution to
reply within 10 days.
21
20.
RAJESH
MAHAVIDYALAYA,
U.P.
KUMAR F. No. 89-604/2009- THE CASE WAS REMANDED BACK Decision
of
Appeal
JAUNPUR, appeal /99667 dated TO NRC FOR RECONSIDERATION OF Committee is Noted.
7.8.2009.
THE CASE AND TO ISSUE ORDER.
COURSE – B.ED., UP-2318
22
21.
BABA
SARVAJEET
GIRI F. No. 89-543/2009- THE CASE WS REMANDED BACK TO Decision
of
Appeal
MEMORIAL MAHAVIDYALAYA, appeal /99831 dated THE NRC FOR INSPECTION OF THE Committee is Noted.
PRATAPGARH, U.P.
7.8.2009.
INSTITUTION IMMEDIATELY.
Seek guidance from CP, HQ.
COURSE – B.ED., UP-2656
-6-
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
23
22.
INSTITUTE OF PROFESSIONAL F. No. 89-602/2009EXCELLENCE
AND appeal /99443 dated
MANAGEMENT,
GHAZIABAD, 7.8.2009.
U.P.
COURSE – B.ED.ADDITIONAL
INTAKE , UP-2206
AUGUST 2009
THE REMANDED BACK THE CASE Decision
of
Appeal
TO NRC FOR CAUSING INSPECTION Committee is Noted.
OF
THE
INSTITUTION
TO
ASCERTAIN THE AVAILABILITY OF Seek guidance from CP, HQ.
STAFF AS PARTICULAR AND OTHER
FACILITIES AS PER NCTE NORMS
AND
THEREAFTER
PASS
APPROPRIATE
ORDER
ACCORDINGLY THE CASE WAS
REMANDED BACK TO NRC.
24
23.
BEHARI LAL SAMARAK KISAN F. No. 89-562/2009- THE COUNCIL REMANDED BACK Decision
of
Appeal
MAHAVIDYALAYA, AMBEDKAR appeal /99971 dated THE CASE TO THE NRC FOR Committee is Noted.
NAGAR, U.P.
7.8.2009.
FURTHER PROCESSING OF THE
CASE.
Seek guidance from CP, HQ.
COURSE – B.ED. , UP-3148
25
24.
B.N.A.S.
MAHAVIDYALAYA, F. No. 89-496/2009- THE CASE WAS REMANDED BACK Decision
of
Appeal
HARDOI, U.P.
appeal /99775 dated TO THE NRC FOR INSPECTION OF Committee is Noted.
7.8.2009.
THE INSTITUTION IMMEDIATELY.
COURSE – B.ED. , UP-3288
Seek guidance from CP, HQ.
26
25.
MAULANA AZAD INSTITUTE OF F. No. 89-565/2009- THE APPEAL WAS ACCEPTED AND Decision
of
Appeal
HUMANITIES SCIENCE AND appeal /99995 dated NRC’S ORDER DATED 16.7.2009 Committee is Noted.
TECHNOLOGY, SITAPUR, U.P. 7.8.2009.
WAS SET ASIDE WITH DIRECTION
TO
THE
NRC
TO
GRANT Seek guidance from CP, HQ.
RECOGNITION
TO
THE
COURSE – B.P.ED. , UP-2678
INSTIUTTION IMMEDIATELY.
27
26.
ALLAHABAD
AGRICULTURAL F. No. 89-534/2009INSTITUTE, ALLAHABAD, U.P. appeal /99771 dated
7.8.2009.
COURSE – B.P.ED. , UP-1091
28
27.
ALLAHABAD
AGRICULTURAL F. No. 89-464/2009- THE APPEAL WAS ACCEPTED AND Decision
of
Appeal
INSTITUTE, ALLAHABAD, U.P. appeal /99767 dated NRC’S ORDER DATED 17.7.2009 Committee is Noted.
7.8.2009.
WAS SET ASIDE WITH DIRECTION
TO
THE
NRC
TO
GRANT
-7-
THE APPEAL WAS ACCEPTED AND Decision
of
Appeal
NRC’S ORDER DATED 9.7.2009 WAS Committee is Noted.
SET ASIDE WITH DIRECTION TO
THE NRC TO GRANT RECOGNITION Seek guidance from CP, HQ.
TO
THE
INSTIUTTION
IMMEDIATELY.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
RECOGNITION
TO
INSTIUTTION IMMEDIATELY.
COURSE – M.ED. UP-921
AUGUST 2009
THE
Seek guidance from CP, HQ.
29
28.
VEER
BAHADUR
SINGH F. No. 89-527/2009- THE CASE WAS REMANDED BACK Decision
of
Appeal
MAHILA
MAHAVIDYALAYA, appeal /99827 dated TO
THE
NRC
FOR
FURTHER Committee is Noted.
LUCKNOW, U.P.
7.8.2009.
NECESSARY ACTION.
Seek guidance from CP, HQ.
COURSE – B.ED.. , UP-2111
30
29.
VEER
BAHADUR
SINGH F. No. 89-521/2009- THE CASE WAS REMANDED BACK Decision
of
Appeal
MAHILA
MAHAVIDYALAYA, appeal /99759 dated THE
CASE
FOR
FURTHER Committee is Noted.
LUCKNOW, U.P.
7.8.2009.
NECESSARY
ACTION
TO
SCRUTINISE THE LIST OF FACULTY Seek guidance from CP, HQ.
SUBMITTED BY THE INSTITUTION
COURSE – B.P.ED. UP-2110
TO ASCERTAIN THAT IT IS AS PER
NCTE NORMS AND ISSUE FRESH
ORDERS ACCORDINGLY.
31
30.
R.S.M.P. DEGREE
PRATAPGARH, U.P.
COLLEGE, F. No. 89-544/2009appeal /99867 dated
7.8.2009.
COURSE – B.ED. UP-2658
THE APPEAL WAS ACCEPTED AND Decision
of
Appeal
NRC’S ORDER DATED 10.6.2009 Committee is Noted.
WAS SET ASIDE WITH DIRECTION
TO
THE
NRC
TO
GRANT Seek guidance from CP, HQ.
RECOGNITION
TO
THE
INSTITUTION IMMEDIATELY.
32
31.
Sardar Singh Shivraj Singh F. No. 89-544/2009Mahavidyalaya, Raghubir Nagr, appeal /99867 dated
Dhondhi, Sitapur, U.P. COURSE 7.8.2009.
– B.ED.. , UP-946
ACCORDINGLY
THE
COUNCIL Decision
of
Appeal
ACCEPTED
THE
APPEAL
AND Committee is Noted.
REMANDED BACK THE CASE TO THE
NRC FOR INSPECTION OF THE Seek guidance from CP, HQ.
INSTITUTION IMMEDIATELY AND
THEREAFTER ISSUE ORDER.
33
32.
PHOOLA DEVI CHANDRADHR F. No. 89-397/2009- THE CASE WAS REMANDED BACK Decision
of
Appeal
MISHRA
MAHAVIDYALAYA, appeal /99411 dated TO NRC.
Committee is Noted.
AMBEDKAR
NAGAR,
U.P. 7.8.2009.
COURSE – B.ED. UP-3233
34
33.
SHUKDEO PRASAD
MAHAVIDYALAYA,
KUSHINAGAR, U.P.
TRIPATHI F. No. 89-590/2009- THE CASE WAS REMANDED BACK Seek clarification from HQ
appeal /100121 dated TO
THE
NRC
FOR whether order is to be
RECONSIDERATION AND THRERE issued for B.Ed. course or
7.8.2009.
-8-
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AFTER ISSUE
COURSE – B.ED ADDITIONAL THE
COURSE ORDER.
INTAKE , U.P. -2392
MENTIONED IN THE
APPEAL
ORDER
–
B.ED. BUT CASE IS
B.ED. ADDITIONAL
OF
AUGUST 2009
APPROPRIATE B.Ed. Additional intake.
35
34.
K.R.
MANGALAM
GLOBAL F. No. 89-373/2009- THE APPEAL WAS REJECTED AND Decision
of
Appeal
INSTITUE
FOR
TEACHERS, appeal /99435 dated NRC’S ORDER DATED 5.6.2009 WAS Committee is Noted.
NEW DELHI.
7.8.2009.
CONFIRMED.
36
35.
NEHRU
GRAM
ALLAHABAD, U.P.
37
36.
Malwa College of Physical F.No.
89-545/2009- The appeal was rejected and NRC's Decision
of
Appeal
Education,
Goniama
Road, Appeal/99991
dated order
dated
28.05.2009
was Committee is Noted.
Bathinda, Punjab.
07.08.2009
confirmed.
BHARTI, F. No. 89-3551/2009- THE APPEAL WAS REJECTED AND Decision
of
Appeal
appeal /99419 dated NRC’S ORDER DATED 24.3.2009 Committee is Noted.
7.8.2009.
WAS CONFIRMED.
UP-3551 COURSE – B.P.ED.
(PB-634, Course- M.P.Ed.)
38
37.
Shiksha Bharti Institute of F.No.
89-505/2009- The appeal was rejected and NRC's Decision
of
Appeal
Education Training & Research, Appeal/99727
dated order
dated
06.05.2009
was Committee is Noted.
VPO- Samoor Khurd, Distt. - 07.08.2009
confirmed.
Una, HP.
(HP-303, Course- M.ED)
39
38.
Global
College
of
Higher F.No.
89-455/2009Education, Vill- Nangal Khurd, Appeal/99915
dated
P.O- Mansa, Distt- Mansa, 07.08.2009
Punjab
The case was remanded back to the Seek guidance from CP, HQ.
NRC for inspection of the institution
immediately and thereafter, to issue
order.
(PB-672, Course- B.ED)
40
39.
Baba KE College of Education, F.No.
89-592/2009- The appeal was rejected and NRC's Decision
of
Appeal
Vill & Post- Daudhar, Distt- Appeal/99467
dated order
dated
10.06.2009
was Committee is Noted.
Moga, Punjab.
07.08.2009
confirmed.
-9-
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
(PB-668, Course- M.ED)
41
40.
Maharishi Dayanand College of F.No.
89-545/2009- The appeal was rejected and NRC's Decision
of
Appeal
Education, Hanumangarh, Nr. Appeal/99563
dated order
dated
06.05.2009
was Committee is Noted.
BSF,
Azamgarh,
Abohar, 07.08.2009
confirmed.
Punjab
(PB-660, Course- M.ED)
42
41.
Sharan College of Education for F.No.
89-470/2009- The appeal was rejected and NRC's Decision
of
Appeal
Women, Village + Post - Appeal/99943
dated order
dated
02.06.2009
was Committee is Noted.
Ghurkari, Kangra, H.P.
07.08.2009
confirmed.
(HP-200, Course- B.ED ADD)
43
42.
Janak
Raj
Mahajan
College, Kangra, H.P.
44
43.
Shri Guru Ram Dass College of F.No.
89-351/2009- The appeal was rejected and NRC's Decision
of
Appeal
Education, Vill- Halwara, P.O- Appeal/99595
dated order
dated
16.05.2009
was Committee is Noted.
Halwara,
DisttLudhiana, 07.08.2009
confirmed.
Punjab
B.Ed. F.No.
89-328/2009- The appeal was accepted and NRC's Decision
of
Appeal
Appeal/99439
dated order
dated
24.04.2009
was Committee is Noted.
07.08.2009
reversed.
(HP-294, Course- B.ED ADD)
(PB-661, Course- B.ED)
45
44.
Sant Baba Bhag Singh institute F.No.
89-441/2009- The appeal was rejected and NRC's Decision
of
Appeal
of education, Vill- Khiala, P.O, Appeal/100041 dated order
dated
03.06.2009
was Committee is Noted.
Padhiana Jalandhar, Punjab
07.08.2009
confirmed.
(PB-643, Course- ETT)
46
45.
Thakur College of Education, F.No.
89-398/2009- The appeal was rejected and NRC's Decision
of
Appeal
V+PODhaliara,
Tehsil
- Appeal/99679
dated order
dated
16.05.2009
was Committee is Noted.
Dehra, Distt. - Kangra, H.P.
07.08.2009
confirmed.
(HP-299, Course- JBT)
- 10 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
47
46.
AUGUST 2009
Shri Ram E.T.T. College, 142, F.No.
89-574/2009- The appeal was rejected and NRC's Decision
of
Appeal
Kta No-8, VPO-Saru, Chamba, Appeal/99883
dated order
dated
06.05.2009
was Committee is Noted.
H.P.
07.08.2009
confirmed.
(HP-290, Course- ETT)
48
47.
D.A.V
College,
Maharishi F.No.
89-497/2009- The appeal was rejected and NRC's Decision
of
Appeal
Dayanand Marg, Hanumangarh Appeal/
dated order
dated
02.06.2009
was Committee is Noted.
Road,
Abohar,
Ferozepur- 07.08.2009
confirmed.
152116
(PB-675, Course- M.P.ED)
49
48.
Sharan College of Education F.No.
89-471/2009- The case was remanded back to the Seek guidance from CP, HQ.
for Women, VPO- Ghurkari, Appeal/99811
dated NRC for inspection of the institution
Tehsil+
DistrictKangra, 07.08.2009
immediately.
Himachal Pradesh.
(HP-270, Course- M.Ed.)
50
49.
Dr. C. L. Galaxy B.Ed. College, F.No.
89-395/2009- The appeal was rejected and NRC's Decision
of
Appeal
VPO - Nagrota Surian, Distt. - Appeal/99631
dated order
dated
06.05.2009
was Committee is Noted.
Kangra, HP
07.08.2009
confirmed.
(HP-295, Course- B.ED)
AGENDA ITEM NO 148.04.00 CONSIDERATION OF THE COURT CASES.
S.L.
No.
51
AGENDA NAME
OF
NO.
INSTITUTION
1
THE COURSE
Varsha
Teachers B.ED.*
Training
College,
Jhunjhunu-333001,
Rajasthan
FILE NO.
Brief of the case.
RJ-1641
THE ORDER UNDER 7(11) HAS BEEN ISSUED IN Noted
FAVOUR OF THE INSTITUTION IN COMPLIANCE WITH
THE DIRECTION/ORDER OF HON’BLE HIGHT COURT
OF RAJASTHAN AT JAIPUR BENCH PASSED ON
5.3.2009 IN THE C.W.P. NO. 12048/2008 AND
CONFIRMED BY DIVISION BENCH VIDE JUDGEMENT
- 11 -
DECISION
NRC
OF
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
DATED 15.5.2009 AND ALSO AS PER INSTRUCTION
/DIRECTION OF THE NCTE HQRS LETTER DATED
21.8.2009 SUBJECT TO THE OUT COME THE SLP NO.
17165-68/2009 FILED BY THE NCTE IN THE HON’BLE
SUPREME COURT OF INDIA AGAINST THE ORDER
DATED 13.5.2009 PASSED BY THE HON’BLE COURT
OF RAJASTHAN AT JAIPUR BENCH.
52
2
Neelkanth
Teachers B.ED.*
Training College, SikarJaipur Road, Jhunjhunu,
Rajasthan
RJ-1959
THE ORDER UNDER 7(11) HAS BEEN ISSUED IN Noted
FAVOUR OF THE INSTITUTION IN COMPLIANCE WITH
THE DIRECTION/ORDER OF HON’BLE HIGHT COURT
OF RAJASTHAN AT JAIPUR BENCH PASSED ON
5.3.2009 IN THE C.W.P. NO. 12050/2008 AND
CONFIRMED BY DIVISION BENCH VIDE JUDGEMENT
DATED 15.5.2009 AND ALSO AS PER INSTRUCTION
/DIRECTION OF THE NCTE HQRS LETTER DATED
21.8.2009 SUBJECT TO THE OUT COME THE SLP NO.
17165-68/2009 FILED BY THE NCTE IN THE HON’BLE
SUPREME COURT OF INDIA AGAINST THE ORDER
DATED 13.5.2009 PASSED BY THE HON’BLE COURT
OF RAJASTHAN AT JAIPUR BENCH.
53
3
Shri Shyam Shikshak B.ED.*
Prashikshan Sansthan,
Bhadra, Hanumangarh,
Rajasthan.
RJ-2031
THE ORDER UNDER 7(11) HAS BEEN ISSUED IN Noted
FAVOUR OF THE INSTITUTION IN COMPLIANCE WITH
THE DIRECTION/ORDER OF HON’BLE HIGHT COURT
OF RAJASTHAN AT JAIPUR BENCH PASSED ON
5.3.2009 IN THE C.W.P. NO. 11701/2008 AND
CONFIRMED BY DIVISION BENCH VIDE JUDGEMENT
DATED 15.5.2009 AND ALSO AS PER INSTRUCTION
/DIRECTION OF THE NCTE HQRS LETTER DATED
21.8.2009 SUBJECT TO THE OUT COME THE SLP NO.
17165-68/2009 FILED BY THE NCTE IN THE HON’BLE
SUPREME COURT OF INDIA AGAINST THE ORDER
DATED 13.5.2009 PASSED BY THE HON’BLE COURT
OF RAJASTHAN AT JAIPUR BENCH.
54
4
Bhanwar Kanwar Sugan B.ED.*
Singh
Shiksa
RJ-2024
THE ORDER UNDER 7(11) HAS BEEN ISSUED IN Noted
FAVOUR OF THE INSTITUTION IN COMPLIANCE WITH
- 12 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
Mahvidyalaya,
Inderpura, Jhunjhunu,
Rajasthan.
55
S.
NO.
56
5
1.
THE DIRECTION/ORDER OF HON’BLE HIGHT COURT
OF RAJASTHAN AT JAIPUR BENCH PASSED ON
5.3.2009 IN THE C.W.P. NO. 11700/2008 AND
CONFIRMED BY DIVISION BENCH VIDE JUDGEMENT
DATED 15.5.2009 AND ALSO AS PER INSTRUCTION
/DIRECTION OF THE NCTE HQRS LETTER DATED
21.8.2009 SUBJECT TO THE OUT COME THE SLP NO.
17165-68/2009 FILED BY THE NCTE IN THE HON’BLE
SUPREME COURT OF INDIA AGAINST THE ORDER
DATED 13.5.2009 PASSED BY THE HON’BLE COURT
OF RAJASTHAN AT JAIPUR BENCH.
Shri Ganesh College of B.ED.**
Education, Jhunjhunu,
Rajasthan.
AGEAN
NAME OF
NO. INSTITUTION
THE COURSE
Gautam College of
Education,
Ward
No.10,
UPMohal
Hamirpur,
H.P.
B.Ed.
AUGUST 2009
RJ-1082
FILE
NO.
The institution filed WP no.9739/2009 in the Hon’ble The Decision of
High Court Judicature for Rajasthan at Jaipur Bench , appeal committee
Jaipur. The Court has direct NCTE to decide the is noted.
appeal of the petitioner on or before 28/08/2009 but
not later than 3rd September 2009. The appeal has
been rejected dated 26.08.2009.
CASE No. & Brief
DECISION OF NRC
HP-297 Cont. Pet.(C) No. __ /09 in CWP No. As per the direction of HQ, the decisions
taken in 139th meeting of NRC in respect
2030 of 2009.
of
this
Institution
are
to
be
communicated
to
Hon’ble
High
Court
of
A Contempt petition has been filed by
Himachal
Pradesh
at
Shimla.
Gautam Girls College Management
Committee, Hamirpur, H.P. through its
Secretary, Shri Rajnish Gautam in the
Hon’ble High Court of Himachal
Pradesh at Shimla
The CWP has been disposed of by
observing that petitioner shall submit a
representation along with supporting
documents before RD, NRC within one
- 13 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
week. The Regional Director or
appropriate authority shall consider the
case of the petitioner, if necessary by
hearing the petitioner or representative
of the petitioner and shall dispose of the
same on merits by a speaking order
within two weeks from the date of
receipt of the representation vide order
dated 4.8.2009.
The application of the institution has
already been closed vide order dated
175.2009 as per the decision of NRC
in its 139th meeting.
57
1
Gangadhar
Teacher RJ-2033
Training
College,
Mandrella,
Jhunjhunu-333025,
Raj
B.Ed.
In the 132nd (2nd Sitting) Meeting of
NRC. The NRC decided to issue 7(9).
The institution filed a writ petition no.
13778 / 08 in the Hon’ble High Court
of Judicature for Rajasthan at Jaipur
Bench. The court has allowed the
petition and directed to consider the
case of the petitioner also in the light
thereto and pass appropriate orders in
accordance of law vide order dated
20.05.08.
The
institution
also
submitted the Stamp paper of Rs.
100/- from the Management regarding
appointment of staff and Rs. 10/from the staff in this office on
29.01.2009. The institution has filed a
contempt case in the Hon’ble High
Court of Rajasthan at Jaipur. The case
was listed for hearing on 31.08.09 as
informed by NCTE Hqtrs vide its letter
dated 28.08.2009.
- 14 -
As per the direction of HQ, the decisions
taken in 132nd meeting of NRC in respect
of this Institution along with the
documents submitted by the Institution,
hence the Committee decides to issue
7(11) .
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
58
2
Dhatarwal
Teachers RJ-1658
Training
College,
Manderala,
Jhunjhunu, Rajasthan
59
3
Smt.
Sarla RJ-1654
Parsanouria Shiksha
Sastri Mahavidyalaya,
VPO
–
Dundlod,
Tehsul – Nawalgarh,
Jhunjhunu, Rajasthan
B.Ed.
AUGUST 2009
In the 132nd (2nd Sitting) Meeting of
NRC. The NRC decided to issue show
cause notice. The institution filed a
writ petition no. 14053 / 08 in the
Hon’ble High Court of Judicature for
Rajasthan at Jaipur Bench. The court
has allowed the petition and directed
to consider the case of the petitioner
also in the light thereto and pass
appropriate orders in accordance of
law vide order dated 20.05.08. The
institution submitted to reply to show
cause notice on 30.10.2008. The
institution also submitted the Stamp
paper
Rs.
100/form
the
management regarding appointment
of staff and Rs. 10/- form the staff in
this office on 06.02.2009. The
institution has file a contempt case in
the Hon’ble High Court of Rajasthan at
Jaipur. The case was listed for hearing
on 31.08.09 as informed by NCTE
Hqtrs vide its letter dated 28.08.2009.
As per the direction of HQ, the decisions
taken in 132nd meeting of NRC in respect
of this Institution along with the
documents submitted by the Institution,
the committee decides to issue 7(11)
subject to appointment of Faculty
through
dully
constituted
selection
committee as per NCTE norms for B.Ed.
Shiksha In the 132nd (2nd Sitting) Meeting of
Sastri NRC. The NRC decided to issue 7(9).
The institution filed a writ petition no.
12049 / 08 in the Hon’ble High Court
of Judicature for Rajasthan at Jaipur
Bench. The court has allowed the
petition and directed to consider the
case of the petitioner also in the light
thereto and pass appropriate orders in
accordance of law vide order dated
20.05.08..
The
institution
also
submitted the Stamp paper Rs. 100/form the management regarding
As per the direction of HQ, the decisions
taken in 132nd meeting of NRC in respect
of this Institution along with the
documents submitted by the Institution,
the Committee decides to issue 7(11)
subject to appointment of qualified
Faculty whose Methods of Teaching is
English in place of Shri G. Narayan
Tripathi.
- 15 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
appointment of staff and Rs. 10/form the staff in this office on
19.12.2008. The institution has file a
contempt case in the Hon’ble High
Court of Rajasthan at Jaipur. The case
was listed for hearing on 31.08.09 as
informed by NCTE Hqtrs vide its letter
dated 28.08.2009.
60
4
Ambika
Shikshak RJ-1689
Prashikshan
Mahavidyalaya, Indra
Prastha,
Malsisar,
Jhunjhunu, Rajasthan
61
5
Shree Shyam College
of Education, Villpanhera Kalan, PostFatehpur,
Billoch,
Teh-Ballabgarh,
B.Ed.
B.Ed.
In the 132nd (2nd Sitting) Meeting of As per the direction of HQ, the decisions
NRC. The NRC decided to issue 7(9) – taken in 132nd meeting of NRC in respect
Affidavit Rs. 100/- stamp paper of this Institution along with the
regarding selection of staff. The documents submitted by the Institution,
institution filed a writ petition no. the committee decides to issue 7(11)
13779 / 08 in the Hon’ble High Court subject to submission of affiliating
of Judicature for Rajasthan at Jaipur University letter regarding nomination of
Bench. The court has allowed the Expert on the selection committee of this
petition and directed to consider the Institution.
case of the petitioner also in the light
thereto and pass appropriate orders in
accordance of law vide order dated
20.05.08..
The
institution
also
submitted the Stamp paper Rs. 100/form the management regarding
appointment of staff and Rs. 10/form the staff in this office on
29.01.2009. The institution has file a
contempt case in the Hon’ble High
Court of Rajasthan at Jaipur. The case
was listed for hearing on 31.08.09 as
informed by NCTE Hqtrs vide its letter
dated 28.08.2009.
HR-1632 (A decision has been taken to inspect The judgement of the Hon’ble High court
U/s 17 in the 146th meeting held on is noted.
05th to 07th August. 2009 The
Institution has submitted a stay order
from the Hon’ble subordinate Court,
- 16 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
Distt-Faridabad,
Haryana.
AUGUST 2009
Faridabad, Haryana)
AGENDA ITEM NO 148.05.00 CONSIDERATION OF THE REPLIES RECEIVED FOR CONVERSION FROM 7(9) TO 7(11)
S.L
NO.
AGENDA
NO.
62
1.
DAWARIKADHEESH
RESEARCH B.Ed.
EDUCATION & MANAGEMENT SCHOOL,
JANTA
ROAD,
VPO-MAJA
MUDH,
DISTT.-SAHARANPUR, UP
UP-3274
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
63
2.
SW.
BHAGWANTI
DEVI
DEGREE B.Ed.
COLLEGE, VILL.-BHUSHA, MEJA ROAD,
ALLAHABAD, UP
UP-3087
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
64
3.
SHRI SHANKAR BHAGWAN INSTITUTE B.Ed.
OF TECHNOLOGY, SERA SUBKARA
BABWI ROAD, CHIBBOI, VILLAGE –
MAU, DISTT. – CHITRKOOT, U.P.
UP-2997
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
65
4.
RANI
CHANDRA
PRABHA B.P.Ed.
MAHAVIDYALAYA, KHAGA, FATEHPUR,
U.P.
UP-2668
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
BRIEF DESCRIPTION
COURSE
- 17 -
FILE NO.
DECISION
OF
NRC
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
66
5.
DJBV COLLEGE OF EDUCATION FOR B.Ed.
WOMEN, KHEKRA, BAGHPAT , U.P.
UP-3083
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
67
6.
S.M. EDUCATIONAL INSTITUTE, PL. B.Ed.
NO. 242, VILL.-PALI DUNGRA, POST
SONKH, DISTT.-MATHURA, UP
UP-3111
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
68
7.
SHREE RATIRAM DEGREE COLLEGE, B.Ed.
VILL.-SANKET,
POST.-BARSANA,
TESHIL-CHHATA,
DISTT.-MATHURA,
UP
UP-3089
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
69
8.
LORD SHIVA INSTITUTE FOR HIGHER B.Ed.
STUDIES,
VILL.-KAILAWAN,
POSTSHIKARPUR,
DISTT.-BULANDSHAHR,
UP
UP-3121
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
70
9.
JAI PRAKASH DEGREE
UMRAHA, VARANASI, U.P.
COLLEGE, B.Ed.
UP-2711
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
71
10.
MAA BHAWANI MAHAVIDYALAYA, VPO B.Ed.
– SOGAI, DISTT. – CHANDAULI, U.P.
UP-3110
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
- 18 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
under 7(11).
72
11.
MAA RAMDULARI MAHAVIDYALAYA, B.Ed.
11, NR GARDEN, OLE, DISTT. MATHURA ,U.P.
UP-3383
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
73
12.
PARAMOUNT
INSTITUTE
OF B.Ed.
EDUCATION
&
TECHNOLOGY,
AGRAWAL
MANDI,
TOWN-TATIRI,
DISTT.-BAHGPAT, UP
UP-3113
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
74
13.
CH. BASHIR KHAN MAHAVIDYALAYA, B.Ed.
HARRA, SARDHANA, MEERUT, U.P.
UP-2748
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
75
14.
PT.
TRIYUGI
MAHAVIDYALAYA,
KANPUR, DEHAT, U.P.
NARAYAN B.Ed.
MANGALPUR,
UP-2740
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
76
15.
SHRI
RAM
JANKI
SHIKSHAN B.Ed.
PRARISHAN MAHILA MAHAVIDYALAYA
, VILL-RAM NAGAR , PO-AMOWA SUFI
, DISTRICT-FAIZABAD, U.P.
UP-3375
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
77
16.
PANCHVATI INSTITUTE OF EDUCATION B.Ed.
& TECHNOLOGY, VILL.-GHAAT, POSTPARTAPUR, DISTT.- MEERUT, UP
UP-3072
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
- 19 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
78
17.
SURAJMAL AGRAWAL PRIVATE KIANYA B.Ed.
MAHAVIDYALAYA
B.ED.
COLLEGE,
KISHANPUR, HALDWANI BYE PASS,
KICHHA, UDHAM SINGH NAGAR,
UTTRAKHAND.
79
18.
SHAKTI SMARAK SANSTHAN, VILLAE – B.P.Ed.
DULHINPUR, BALRAMPUR, U.P.
YEARS.
80
19.
81
82
UR-197
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
4 UP-2994
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
J.D.J.B. ANAND DEGREE COLLEGE, B.Ed.
POST
–
KHEMAPUR,
AMBEDKAR
NAGAR,U.P.
UP-2444
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
20.
RAMESHWARMA
INSTITUTE
OF B.Ed.
EDUCATION
&
TRAINING,
VILL.KAMLABAD BADHOLI, TEHSIL-BAKSHI
KA TALAB, DISTT.-LUCKNOW, UP
UP-3107
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
21.
K.S.V. INSTITUTE OF ENGINEERING & B.Ed.
TECHNOLOGY
MARADAPUR
SADAT
GHAZIPUR, KHASRA NO-129 A ,129 B
,
VILL-MARADAPUR,
POSTDAULATHAGARH,
DISTT.-GHAZIPUR,
U.P.
UP-3439
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
- 20 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
83
22.
NATIONAL POST GRADUATE COLLEGE, B.Ed.
KALYANPUR,
BARHALGANJ,
GORAKHPUR, U.P.
UP-2413
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
84
23.
NATIONAL
POST
COLLEGE,
GORAKHPUR, U.P.
UP-2414
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
85
24.
MAJOR SHIV DAYAL SINGH MAHILA M.Ed.
MAHAVIDYALAYA,
VPO
MOHAMMADABAD,
FARRUKHABAD206451, UP
UP-3129
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:
GRADUATE B.P.Ed.
BARHALGANJ,


The Faculty has not been appointed through
dully constituted selection committee as per
NCTE norms.
Mr. Pravin Kumar Mishra, Mr. Ajeet Kumar and
Mr. Devendra Kumar are not qualified as per
NCTE norms for M.Ed.
Hence, the committee decides to issue Show Cause
Notice on above points and directs the Institution to
submit reply within 21 days.
86
25.
A.B.R.L. DEGREE COLLEGE, VILLAGE B.Ed.
–GITHONI, POT – CHANDHAR, TEHSIL
– KHALILABAD, DISTT. – SANT KABIR
NAGAR, U.P.
UP-2966
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:

- 21 -
There is no Faculty to teach Methods of
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH

AUGUST 2009
Teaching Economics, Commerce, English,
History, Sanskrit, etc.
Mr.Parma Hansh does not possess qualification
as per NCTE norms for B.Ed.
Hence, the committee decides to issue Show Cause
Notice on above points and directs the Institution to
submit reply within 21 days.
87
26.
SUBHI DEVI MAHILA MAHAVIDYALAYA, B.Ed.
VPO-KHALILABAD,
DISTT.-SANT
KABIR NAGAR, UP
UP-3022
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:

There is no Faculty to teach methods of
Teaching
History,
Mathematics,
Physics,
Sanskrit, etc.
Hence, the committee decides to issue Show Cause
Notice on above point and directs the Institution to
submit reply within 21 days.
88
27.
AWADHOOT BHAGWAN RAM POST B.Ed.
GRADUATE COLLEGE, ANPARA DUDHI,
SONEBHADRA, U.P.
UP-2832
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
89
28.
KAUSHAMBI DEGREE COLLEGE, PERAI, B.Ed.
TILHAPUR, MOTH, TILGORI, CHAIL,
KAUSHAMBI, U.P.
UP-2755
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
- 22 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
90
29.
SETH
SRI
NIWAS
AGARWAL B.Ed.
INSTITUTE OF MANAGEMENT, PL. NO.779,
BAGDUDHI
KACCHAR,
G.T.
ROAD,
NARAMAU,
DISTT.-KANPUR
NAGAR, UP
UP-3159
AUGUST 2009
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:

The Faculty has not been appointed through
dully constituted selection committee as per
NCTE norms for B.Ed.
Hence, the committee decides to issue Show Cause
Notice on above point and directs the Institution to
submit reply within 21 days.
91
30.
PT. T. N. MAHAVIDYALAYA, VPO- B.P.Ed.
MANGALPUR, TEHSIL – DERAPUR,
TOWN – JHINJHAK, KANPUR DEHAT,
U.P.
UP-3212
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
92
31.
R.I.E.T.
VIDYAPEETH, VILLAGE – B.Ed.
POHLI, TEHSIL – SARDHANA, DISTT. –
MEERUT, U.P.
UP-3465
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
93
32.
CITY COLLEGE OF MANAGEMENT, B.Ed.
KHASRA
NO-12
AND26,
VILLTIWARIGANJ, POST-CHINHAT, TEHSILSADAR, DISTT.-LUCKNOW, U.P.
UP-3468
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
94
33.
M.I.E.T, VILL-PABALI KHAS, P.O- B.Ed.
PABALI
KHAS,
PLOT
NO161519,1633/2 TEHSIL- SARDHANA,
DISTT- MEERUT U.P.
UP-3069
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
- 23 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
committee and the committee decides to issue letter
under 7(11).
95
34.
SHRI BHOOP SINGH SMRITI MAHILA B.Ed.
MAHAVIDYALAYA,
BHOOP
NAGAR,
MAINPURI, UP
UP-3045
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
Further, the name in the land
documents should be SHRI BHOOP SINGH SMRITI
MAHILA MAHAVIDYALAYA. This correction should be
done within one month.
UP-2742
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
UP-2628
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
UP-2895
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
UP-2972
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
SUBJECT OT 7(11)
96
35.
MAHARASHI
DAYANAND B.Ed.
MAHAVIDYALAYA,
SIRSAGANJ,
SHIKOHABAD, FIROZABAD, U.P.
SUBJECT OT 7(11)
97
36.
CITY
PUBLIC
DEGREE
COLLEGE, B.Ed.
FATEHGARH, FARRUKHABAD, U.P.
SUBJECT OT 7(11)
98
37.
YADU NATH PAL SINGH COLLEGE, B.Ed.
AHAMADPUR, AMOUR, SHIKOHABAD,
FIROZABAD, U.P.
SUBJECT OT 7(11)
99
38.
VIT COLLEGE OF EDUCATION, JATOLI B.Ed.
KANKER KHERA, SARDHANA, MEERUT,
U.P.
SUBJECT OT 7(11)
- 24 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
100
39.
DR.
BHIM
RAO
AMBEDKAR B.Ed.
MAHAVIDYALAYA,
MAU
PARASIN,
MEHAAJPUR, AZAMGARH, U.P.
UP-2793
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
101
40.
RAM
AWADH
SMARAK B.Ed.
MAHAVIDYALAYA,
RAHUL
NAGAR
COLONY, VILLAGE – KASDAHAN,
SHUKLA BAZAR, TEHSIL – AKBARPUR,
AMBEDKAR NAGAR,U.P.
UP-3216
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
102
41.
SHRI
KIRORI
LAL
SHASTRI B.Ed.
MAHAVIDYALAYA, JAGNER, AGRA,U.P.
UP-2024
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
103
42.
SHRI
NATH
ALAKNANDA B.Ed.
MAHAVIDYALAYA, VPO – BHUWARPUR,
TEHSIL – SADPUR, GHAZIPUR, U.P.
UP-3239
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
104
43.
DR.
M.C.SAXENA
COLLEGE
OF B.ED.
EDUCATION, BARAWAN KALA, MALI
ROAD, DISTT.-LUCKNOW, UP
UP-3181
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
105
44.
SHRI
RAM
MAHAVIDYALAQYA,
SIKANDRA, AGRA, U.P.
UP-2841
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
ADARSH B.ED.
PANWARI,
- 25 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
under 7(11) subject to submission
experience certificate of the Principal.
106
45.
Noble College of Education, Vill- Seog, B.Ed.
Post- Pandoh, NH- 21, Tehsil- Sadar,
District- Mandi, H.P.
HP-174
AUGUST 2009
of
teaching
The original file of the institution, reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:

Government of Himachal Pradesh through its’
letter NO. EDN – A – Chha (15)-1 / 2001-Loose
dated 12 August 09 expressed that no more
B.Ed. Colleges are required in the State.
Hence, the committee decides to issue Show Cause
Notice on the above subject and directs the Institution
to reply within 21 days.
107
46.
Aman Bhalla College of Education, B.Ed.
Aman Bhalla Foundation, JammuAmritsar Highway Canal Side Kotli
Pathankot, Post- Jakholari DistrictGurdaspur, Punjab
108
47.
D.A.V.
College,
Chandigarh- 160011
Sector-
PB-379
10, B.P.Ed.
CH-28
(Integrated)
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
The original file of the institution, reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:

The HOD and Faculty has not been selected
through dully constituted selection committee
as per NCTE norms for B.P.Ed.(Integrated)
Hence, the committee decides to issue Show Cause
Notice on the above subject and directs the Institution
to reply within 21 days.
- 26 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
109
48.
Lyallpur Khalsa College of Education B.Ed.
for Women, Jalandhar, Punjab.
PB-361
The original file of the institution, Reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee decides to issue letter
under 7(11).
110
49.
Lyallpur Khalsa College of Education M.Ed.
for Women, Jalandhar, Punjab. (M.ED
needs to be closed on the ground that
its B.ED is not recognized)
PB-488
The original file of the institution, reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:

The Institution is not eligible to apply for M.Ed.
course because its’ B.Ed. course is yet to be
recognized.
Hence, the committee decides to refuse recognition
for M.Ed. course.
111
50.
Government Degree
Daulatpur
Chowk,
District- UNA, H.P.
College,
Tehsil-
VPO- B.Ed. ADD HP-246
AMB, Intake
The original file of the institution, reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:

The deficiency communicated to the college
regarding appointment of Faculty is not
removed within stipulated time.
Hence, the committee decides to refuse recognition
to B.Ed. additional intake.
112
51.
Sardar Rajinder Singh Memorial Mukat B.Ed.
College of Education, Damanheri Road,
Patiala- Rajpura Bye Pass, Rajpura,
PB-356
- 27 -
The original file of the institution, reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
Punjab.
AUGUST 2009
published from time to time were considered by the
committee and the committee observes the following:

The deficiency communicated to the college
regarding appointment of Faculty is not
removed within stipulated time.
Hence, the committee decides to refuse recognition
to B.Ed.
113
52.
S.G.G.S.
Khalsa
College,
VPO- C.P.Ed.
Mahilpur,
TehsilGarh
Shankar,
District- Hosiarpur, Punjab
PB-670
Pending till
completed.
114
53.
Khalsa College of Physical Education, B.P.Ed.
VPO- Heir, Tehsil + dist.: Amritsar,
Punjab
PB-576
The original file of the institution, reply of the
Institution along with all other related documents, Act
of NCTE, 1993, Regulations and Guidelines of NCTE
published from time to time were considered by the
committee and the committee observes the following:


the
inspection
under
section
17
is
The mark-sheets of appointed Faculty have not
been submitted.
Teaching Experience Certificate and certificate
of retirement in respect of Dr. Daljinder Singh
has not been submitted.
Hence, the committee decides to issue Show Cause
Notice on above points and directs the Institution to
reply within 21 days.
- 28 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
AGENDA ITEM NO.148.06.01 CONSIDERATION OF THE REPLY UNDER SECTION 14(3) (B) OF NCTE ACT 1993
Sl. NO. AGENDA
NO.
NAME OF THE INSTITUTIO N
COURSE FILE NO.
DECISION OF NRC
115
1.
S.S. MEMORIAL (P.G) COLLEGE, KHASRA
NO.-457 & 458, VILL.-MAKANPUR, POSTJALESAR
ROAD,
DISTT.-MAHAMAYA
NAGAR, UP
B.Ed.
UP-3221
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(11).
116
2.
DEEN
BANDHU
DEENA
NATH
MAHAVIDYALAYA, KHASRA NO.-453 456 & 461, VILL.-SHIV NAGAR, POSTPANWAR, DISTT.-ETAH, UP
B.Ed.
UP-3266
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
117
3.
SANT BOOLA SATYANAM DAS BIRBAL B.P.Ed. UP-2447
DEGREE COLLEGE, AMARI DULLAHAPUR, ADD.
GHAZIPUR, U.P.
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(9).
118
4.
SHRI
PARAM
PRASHIKSHAN
FAIZABAD, U.P.
HANS
SHIKSHAN
MAHAVIDYALYA,
B.Ed.
UP-2854
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
119
5.
PT.
RAM
CHAARITRA
MISHRA
MAHAVIDYALAYA, VILLAE – PANDELA,
TEHSIL – KADIPUR, SULTANPUR, U.P.
B.Ed.
UP-3204
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(11).
120
6.
KUNWAR
CHANDRAWATI
MAHAVIDYALAYA, PLOT NO.-1, 367, 368,
KHASRA NO.-367, VPO-MUMTAJ NAGAR,
B.Ed.
UP-3223
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
- 29 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
TEHSIL-SOHAWAL,
UP
DISTT.-FAIZABAD,
AUGUST 2009
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
121
7.
JAGDAMBA SARAN SINGH EDUCATIONAL
INSTITUTE, GONDA, U.P.
B.Ed.
UP-2925
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(11).
122
8.
SRI
RAM
TIRTH
CHAUDHARY
MAHAVIDILYA, VILL.-IMILA BANGHUSRA,
POST-REHRA MAFI, TEHSIL-UTRAULA,
DISTT.-BALRAMPUR, UP
B.Ed.
UP-3276
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(9).
123
9.
KASHI
NATH
MAHAVIDYALAYA
NARAYANPUR , KAKARAHI, DOULATPUR,
GHAZIPUR, KHASRA NO-297,299, VILLNARAYANPUR,
POST-DOULATPUR,
DISTT.-GHAZIPUR, U.P.
B.Ed.
UP-3478
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
124
10.
RAM NEWAJ SINGH MAHAVIDYALAYA,
BAWAN KURNAGANJ, FAIZABAD, U.P.
B.Ed.
UP-2815
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(9).
125
11.
SHRI
RAJPATI
SINGH
SMARAK
PRASHIKSHAN
MAHAVIDYALAYA,
DIHDAGUPUR, SULTANPUR, U.P.
B.Ed.
UP-2912
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(9).
126
12.
SHRI R. L. T. SHIKSHA MAHAVIDYALAYA,
KHARSA NO.-748, 369, 44, 464, NH # 2,
BIRARI,
VPO-EKDIL,
TEHSILBHARTHANA, DISTT.-ETAWAH, UP
B.Ed.
UP-3142
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
- 30 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
127
13.
KRISHAK
MAHAVIDYALAYA,
VPO
RAJGARH,
NARHAN,
DISTT.
MIRZAPUR, U.P.
128
14.
SHRI
RAM
SINGH
MAHAVIDYALAYA, VILLAGENAGAR, FAIZBAD,U.P.
129
AUGUST 2009
–
–
B.Ed.
UP-2942
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(9).
GULERIYA
YASWANT
B.Ed.
UP-2991
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(9).
15.
MAYA
COLLEGE
OF
EDUCATION,
VILLAGEJAGNER,
POSTJAGNER,DISTRICT- AGRA, U.P.
B.Ed.
UP-3256
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
130
16.
RAGHU
RAJA
RAM
GOPAL
MAHAVIDYALAYA,
VILL.-BAHURAJMAO,
POST-RAITHANA, DISTT.-UNNAO, UP
B.Ed.
UP-3250
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
131
17.
MAA
PURNAGIRI
COLLEGE
OF
EDUCATION, VILLAGE – BHARTOLI,
BARAKOTE, CHAMPAWAT, UTTRAKHAND.
B.Ed.
UR-180
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
132
18.
BORA INSTITUTE OF MANAGEMENT &
SCIENCE, NH-24, SEWA HOSPITAL,
SITAPUR ROAD, DISTT.-LUCKNOW, UP
B.Ed.
UP-3273
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
- 31 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
133
19.
LAL
BAHADUR
SINGH
SMARAK
MAHAVIDYALAYA,
VPO-GOHAWAR,
TEHSIL-CHANDPUR, DISTT.-BIJNOR, UP
B.Ed.
UP-3085
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
134
20.
CPS COLLEGE OF EDUCATION, VPOSIKANDRA
RAO,
HATHRAS,
MAHAMAYANAGAR, UP
B.Ed.
UP-3008
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
135
21.
GURU
NIRANJANA
NAND
MAHAVIDYALAYA,
VILL-LUHETA,
POIRADAT NAGAR, DISTRICT-AGRA, U.P.
B.Ed.
UP-3312
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
136
22.
SHRI SAI MAHAVIDYALAYA, KHASRA
NO.-55/1, VPO-FATEH PUTHI, DISTT.BAGHPAT, UP
B.Ed.
UP-3247
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee observes the following:

The deficiencies with respect to Faculty and
Multipurpose still exist.
Hence, the committee decides to refuse recognition for
B.Ed. Course.
137
23.
CHAUDHARY CHARAN SINGH COLLEGE
OF EDUCATION & TECHNOLOGY, VILL.SADARPUR, POST-MOD-KHURD, TEHSILMAWANA, DISTT.-MEERUT, UP
B.Ed.
UP-3227
- 32 -
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
138
24.
CH. NATHU SINGH MAHAVIDYALAYA,
KHASRA
NO-850,852,
VILL-DIHULI,
POST-DOHULI, DISTT.-MAINPURI, U.P.
B.Ed.
UP-3456
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
139
25.
BHAGWAN ADARSH MAHAVIDYALAYA,
CHAKRAPANI PUR, AZAMGARH, KHASRA
NO-311 A , VILL-KANAILA KARANHAT,
POST-KANAILA, DISTT.-AZAMGARH, U.P.
B.Ed.
UP-3491
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
140
26.
BABU SINGH MAHAVIDYALAYA, VILL.RAMPUR BAIJU CHHIBRAMU, TEHSILCHIBRAMAU, DISTT.- KANNAUJ, UP
B.Ed.
UP-3210
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee observes the following:

The deficiencies with respect to land, building
plan, laboratories, Language learning facility,
Library, Multipurpose Hall, Black boards, Play
ground, etc. still exist.
Hence, the committee decides to refuse recognition for
B.Ed. Course.
141
27.
KATYAYANI COLLEGE OF EDUCATION,
VILL- BADRUDIN NAGAR NANU,P.ONANU,
PLOT
NO-45,
TEHSILSARDHANA, DISTT- MEERUT,U.P.
B.Ed.
UP-3068
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(9).
142
28.
CHANDRA
PRABHA
MAHAVIDYALAYA
ALAYA, SARAINEEM, JALESAR, ETAH,
KHASRA NO-67, VILL-SARAI NEEM ,
POST-SARAI NEEM , DISTT.-ETAH, U.P.
B.Ed.
UP-3482
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
- 33 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
Institution.
143
29.
CH. BADAN SINGH
ASPUR,
G.T.ROAD,
DISTT.-ETAH, UP
MAHAVIDYALAYA,
VILL.-MANIKPUR,
B.Ed.
UP-3187
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
144
30.
PANDIT LAXMI NARAYAN MEMORIAL
MAHAVIDYALAYA, GHARBARA, TAPPAL,
ALIGARH, U.P.
B.Ed.
UP-3448
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee observes the following:


The bills submitted for purchase of books are
without any date and signature of the book seller.
The deficiencies with respect to Language
learning facility, Website of the Institution and
titles of books still exist.
Hence, the committee decides to refuse recognition for
B.Ed. Course.
145
31.
KABUTRI DEVI RAJESHWARTRIPATHI
SMARAK
MAHILA
MAHAVIDYALAYA,
GORAKHPUR,U.P.
B.Ed.
UP-2864
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(9).
146
32.
SWARN
JAYANTI
MAHILA
MAHAVIDYALAYA, PIPRAICH, DISTT. –
GORAKHPUR, U.P.
B.Ed.
UP-2469
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides for re-inspection of the
Institution.
- 34 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
147
33.
ORNATE INSTITUTE OF TECHNOLOGY,
SAMPLA,
BEGUMPUR,
SARSAWA,
SAHARANPUR, U.P.
B.Ed.
UP-3052
AUGUST 2009
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee observes the following:

The deficiencies as
Institution still exist.
communicated
to
the
Hence, the committee decides to refuse recognition for
B.Ed. course.
148
34.
P.I.E.T. COLLEGE OF EDUCATION, DELHI
ROORKEE BYE PASS, NH-58, GHAAT,
PARTAPUR, MEERUT, U.P.
B.Ed.
UP-3203
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(11).
149
35.
Rattan Professional Education College,
Sohana, Sector- 78, Mohali, S.A.S.
Nagar, Punjab
B.Ed.
PB-640
The original file of the institution, Reply of the Institution
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published
from time to time were considered by the committee and
the committee decides to issue letter under 7(11)
subject to submission of affidavit on stamp paper of Rs.
100 from Management regarding appointment of Ms.
Veena Devi and Ms. Teena Nanchahal.
AGENDA ITEM NO.148.06.02:
S. NO. AGENDA
NO.
150
1.
CONSIDERATION OF THE REPLY UNDER SECTION 15(3) (B) OF NCTE ACT 1993.
NAME OF THE INSTITUTION
COURSE
PRADEEP
MEMORIAL ETE
COMPREHENSIVE COLLEGE OF additional
EDUCATION, PRATAP VIHAR, intake
FILE NO. DECISION OF NRC
DH-385
- 35 -
The original file of the institution, Reply of the Institution along
with all other related documents, Act of NCTE, 1993,
Regulations and Guidelines of NCTE published from time to time
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
KIRARI ETN. NANGLOI, DELHI41.
AUGUST 2009
were considered by the committee and the committee observes
the following:


The deficiency with respect to Language learning facility
still exists.
Twenty-five computers are not enough for students of all
courses run by the Institution.
Hence, the committee decides to refuse recognition for ETT
additional intake.
151
2.
PRADEEP
MEMORIAL M.Ed.
COMPREHENSIVE COLLEGE OF
EDUCATION, PRATAP VIHAR,
KIRARI ETN. NANGLOI, DELHI41.
DH-365
152
3.
P. D. MAHILA DEGREE COLLEGE, M.Ed.
STREET
NO.-MOHAMADABAD
ROAD,
VILL.-FATEHGARH,
DISTT.-FARUKHABAD, UP
UP-3128 The original file of the institution, Reply of the Institution along
with all other related documents, Act of NCTE, 1993,
Regulations and Guidelines of NCTE published from time to time
were considered by the committee and the committee decides
for re-inspection of the Institution.
153
4.
MAJOR SHIV DAYAL SINGH M.Ed.
MAHAVIDYALAYA,
VPO
MOHAMMADABAD,
FARRUKHABAD-206451, UP
UP-3126 The original file of the institution, Reply of the Institution along
with all other related documents, Act of NCTE, 1993,
Regulations and Guidelines of NCTE published from time to time
were considered by the committee and the committee observes
the following:
The original file of the institution, Reply of the Institution along
with all other related documents, Act of NCTE, 1993,
Regulations and Guidelines of NCTE published from time to time
were considered by the committee and the committee decides
to issue letter under 7(9).



Thirty-two computers are not enough for students of all
courses, that is, BA, B.Sc., B.P.Ed, B.Ed.
The deficiency with respect to Language learning facility
still exists as old bills dated 18. 6. 2009, 20.6.2007, etc.
have been submitted.
For purchase of books old bills dated 17.8.2009,
16.6.2009, etc. have been submitted.
Hence, the committee decides to refuse recognition for M.Ed.
- 36 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
course.
154
5.
J.N.
KAUL
INSTITUTE
OF B.Ed. ADD. UR-212
EDUCATION, DUNGSIL TALLA,
BHIMTAL,
SOS
COMPLEX,
NAINITAL, UTTRAKHAND.
The original file of the institution, Reply of the Institution along
with all other related documents, Act of NCTE, 1993,
Regulations and Guidelines of NCTE published from time to time
were considered by the committee and the committee observes
the following:



The deficiency with respect to NAAC certificate still
exists.
The school is still being run from the building.
The deficiencies with respect to Language learning
facility, total number of titles, common rooms for males
and females, etc. still exist.
Hence, the committee decides to refuse recognition for B.Ed.
additional intake.
155
6.
Govt.
College,
Sector-11, M.P.Ed.
Madhyam Marg, Chandigarh
156
7.
Sukhdeva Krishna College of B.Ed
Add PB-658
Education for Girls, G.T. Road, Intake
VPOGhall
Kalan,
Tehsil+
District- Moga, Punjab
The original file of the institution, Reply of the Institution along
with all other related documents, Act of NCTE, 1993,
Regulations and Guidelines of NCTE published from time to time
were considered by the committee and the committee decides
to issue letter under 7(11).
157
8.
Kenway College of Education, M.Ed.
Vill- Azimgarh, Post+ TehsilAbohar,
DistrictFerozepur,
Punjab
The original file of the institution, Reply of the Institution along
with all other related documents, Act of NCTE, 1993,
Regulations and Guidelines of NCTE published from time to time
were considered by the committee and the committee observes
the following:
CH-32
PB-687
- 37 -
The original file of the institution, Reply of the Institution along
with all other related documents, Act of NCTE, 1993,
Regulations and Guidelines of NCTE published from time to time
were considered by the committee and the committee decides
to issue letter under 7(11) subject to appointment of two
Faculty members on Full time Regular basis.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH

AUGUST 2009
(Ms) Sushila Devi does not have teaching experience as
per NCTE norms for M.Ed.
Hence, the committee decides to issue Show Cause Notice on
above point and directs the Institution to reply within 21 days.
AGENDA ITEM NO.148.07.00
S. NO. AGEAN NO. NAME
OF
INSTITUTION
158
1.
CONSIDERATION OF THE VTR UNDER SECTION 14
THE COURSE
SHIVANAND
ANAND B.Ed.
MADHAV
MAHILA
MAHAVIDYALAYA,
NAGALA BALL, POST –
JAYMAI,
SIRSAGANJ,
DISTT. – FIROZABAD,
U.P.
FILE NO.
DECISION OF NRC
UP-2779
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:









As per CD, the building is incomplete.
The building completion certificate is not from competent
authority.
Proper Science, ET and Psychology labs do not exist.
Play grounds do not exist.
Identified Faculty was not available at the time of
inspection.
As per CD, toilets are poorly maintained.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
- 38 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
159
2.
CH.
MAHKAR
COLLEGE
EDUCATION,
PABARSA,
DAURALA,
SARAHANA,
MEERUT, UP
SINGH B.Ed.
OF
VILL.POSTTEHSILDISTT.-
UP-3084
AUGUST 2009
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:









The constructed building is not as per approved building
plan.
The Multipurpose Hall does not exist.
Teaching of Arts and work experience facilities has not
been created.
Office does not appropriate furniture.
All labs are ill equipped.
Play grounds do not exist.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
160
3.
MALI
LAL
RAMNATH B.Ed.
MAHAVIDYALAYA , VILLBHADARAULI,
DISTT.AGRA, U.P.
UP-3459
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:





- 39 -
As per CD, the building has not yet been finished.
Adequate equipments are not available in Science, ET and
Psychology labs.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
161
4.
RAJAT
MAHILA B.Ed.
MAHAVIDYALAYA,
KHASRANO-414,416,417,
VILL-SINGHPUR,GOHILA,
PO-SEMRANA SEERPUR,
DISTRICTAMBEDKAR
NAGAR, U.P.
UP-3311
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:






ET and Science labs are ill equipped.
There is no proper furniture in labs.
Playgrounds are underdeveloped.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The College does not have Website as per NCTE Regulation,
2007.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
162
5.
ACHARY
BALDEV B.Ed.
COLLEGE
KOPA
PATARAHI,
JAUNPUR,
KHASRA NO-1063, VILLKOPA,
POST-KERAKAT,
DISTT.-JAUNPUR, u.p.
UP-3438
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:










- 40 -
2500 books are not as per NCTE norms for B.Ed.
The Multipurpose Hall does not exist.
Eight computers are not enough for 100 students.
Internet facility does not exist.
Furniture is of poor quality.
All labs are ill equipped.
Play grounds do not exist.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
163
6.
JAGANNATH
PRASAD B.Ed.
SMARAK COLLEGE OF
EDUCATION,
VILL.BUNDHAWA,
POSTGHOORPUR,
TEHSIL.BARA,
DISTTALLAHABAD, UP
UP-3246
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:







The built up area is not as per NCTE norms for B.Ed.
The size of Multipurpose Hall is small.
Science, ET and Psychology labs are ill equipped.
Seminar room is without proper furniture.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
164
7.
SHYAM NARAYAN URMILA B.Ed.
GIRLS
TEACHER
TRAINING
COLLEGE,
KHASRA NO.-210, 215,
VILL.-SARAI
MUGHAL,
POST-AIHAR,
TEHSILRUDAULI,
DISTT.FAIZABAD, UP
UP-3263
The original file of the institution, along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee decides to issue letter under 7(11).
165
8.
MOTHER
HOOD B.Ed.
INSTITUTE
OF
TECHNOLOGY,
KHASRANO-1132,
TEHSIL-SARDHANA
DISTRICT-MEERUT, U.P.
UP-3401
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:

- 41 -
All labs are ill equipped.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH


AUGUST 2009
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
166
9.
NALANDA COLLEGE OF B.Ed.
EDUCATION,
DEFENCE
COLONY,
DEHRADUN,
UTTRAKHAND.
UR-208
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:








As per CD, the building is under construction.
The VT members were shown residential building which is
not appropriate for running teacher training programme.
The built up area is not as per NCTE norms.
Proper Science, ET and Psychology labs do not exist.
Play grounds do not exist.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
167
10.
SRI GIRRAJ MAHARAJ B.Ed.
INSTITUTE
OF
MANAGEMENT,
VILL.MUNDESI,
DISTT.MATHURA, UP
UP-3186
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:


- 42 -
As per CD, the outer portion and inner portion do not
match.
The number of computers as per Management is 30 but VT
members reported 35. So there is a discrepancy.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH






AUGUST 2009
The built up area is not as per NCTE norms.
As per CD, Play grounds do not exist.
Multipurpose Hall is small in size.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The college does not have a college website as required per
NCTE Regulation, 2007.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
168
11.
SHRI KRISHNA JANKA B.Ed.
DEVI
MAHAVIDYALAYA,
VILLAGE & POST- RURA,
TEHSILAKBARPUR,
DISTRICTKANPUR
DEHAT, U.P.
UP-3289
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:







As per CD, the building is not as per approved building
plan.
As per building plan there should be two floors. The Ground
Floor for B.Ed. and First Floor for BA and other courses has
been earmarked. But as per CD, there is only one floor.
Thus, Ground Floor is proposed to be shared with BA and
other courses. This is not permissible as per Regulation
2007.
The built up area is not as per NCTE norms for B.Ed.
Science, ET and Psychology labs need up-gradation.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
- 43 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
169
12.
DRON B.ED. COLLEGE B.Ed.
FOR WOMEN, UDHAM
SINGH
NAGAR,
UTTRAKHAND.
UK-170
AUGUST 2009
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:







All labs are ill equipped.
Five computers are not enough for 100 students.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The college does not have website as required per NCTE
Regulation, 2007.
The building completion certificate is not issued by
competent authority.
Land is not in the name of the Institution.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
170
13.
PT.
OM
PRAKASH B.Ed.
SHARMA
MAHAVIDYALAY,
ADDRURA KANPUR DEHAT,
PO-PURA,
DISTRICTKANPUR, U.P
UP-3364
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:






As per CD, the building is not as per approved building
plan.
Different labs meant for B.Sc. are proposed to be used for
B.Ed. It is not permitted as per NCTE Regulation 2007.
Language learning facilities are not available.
Playgrounds are yet to be developed.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
- 44 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
above points and directs the Institution to reply within 21 days.
171
14.
BABU
RAM
RUKMANI B.Ed.
DEVI
MAHAVIDYALAYA,
VILL-RASODPUR,
POMUSANAGAR,
DITRICTKANPUR, U.P.
UP-3361
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:








Flooring is incomplete.
All labs are ill equipped.
Language learning facilities are not available.
Playgrounds are not developed.
The same building is being used to run other course. It is
not permitted as per NCTE Regulation 2007.
Science labs meant for B.Sc. courses are proposed to be
used for B.Ed.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
172
15.
SHRI
RAM
PRAKASH B.Ed.
PORWAL
MAHAVIDYALAYA,
VPORAJPUR,
TEHSILSIKANDRA,
DISTT.KANPUR DEHAT, UP
UP-3143
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:






- 45 -
As per approved building plan, first floor is earmarked for
B.Ed. which does not have classrooms.
Multipurpose Hall is small in size.
All labs are ill equipped.
Laboratories do not have adequate furniture.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH

AUGUST 2009
As per CD, playground does not exist.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
173
16.
PT.
MANISH
SHARMA B.Ed.
DEGREE
COLLEGE,
SEMARI KA TAAL, KOTLI
BAGICHI, DEORI ROAD,
SADAR, AGRA, U.P.
UP-2700
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:











As per CD, the building is under construction.
The building completion certificate submitted is not from
competent authority.
The multipurpose Hall is under construction.
All labs are ill equipped.
Four computers are not enough for 100 students.
Books shown to the VT members are not entered in the
accession registered.
Playgrounds do not exist.
Toilets facilities for males and females do not exist as per
CD.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The College does not have Website as per NCTE Regulation,
2007.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
174
17.
HIMALAYAN INSITUTE OF B.Ed.
EDUCATION
AND
TECHNOLOGY, VILLAGE –
JILASU, PATWARI BIRTGIRSA, POST – JILASU,
VIA – LANGASU, DISTT.
–
CHAMOLI,
UR-204
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:


- 46 -
As per CD, the building is under construction.
The books in the library are not as per NCTE norms for
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
UTTRAKHAND.






AUGUST 2009
B.Ed.
All materials are displayed on the table in one room. So
proper labs do not exist.
Five computers are not enough for 100 students.
Playgrounds do not exist.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The College does not have Website as per NCTE Regulation,
2007.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
175
18.
BHEL EMB COLLEGE OF B.Ed.
EDUCATION, SECTOR -1,
HARIDWAR,
UTTRAKHAND.
UR-203
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:










As per CD, the building meant for B.Ed. is being used for
running school.
There is no material in Psychology lab.
All material in ET lab belongs to school.
Ten computers are not enough for 100 students.
The Internet facility is not available in Computer lab.
The library has school level books. It means that there is
no separate library for B.Ed. This sharing of library with
school is not permitted as per NCTE Regulation 2007.
As per CD, play grounds do not exist.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
- 47 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
above points and directs the Institution to reply within 21 days.
176
19.
BHARTI
VIDYAPEETH, B.Ed.
VILL-RALI
CHAUHAN,
POST-ABDULLAPUR,
DISTT.-MEERUT, U.P.
UP-3470
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:











The land is not in the name of the Institution.
Old building is being renovated although a piece of land has
been purchased adjoining this building.
The building shown to VT members is not a part of sale
deal.
Playgrounds do not exist.
Built up area is not as per NCTE norms for B.Ed.
Multipurpose Hall is small in size.
All labs are ill equipped.
Ten computers are not enough for 100 students.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
177
20.
MIT BUSINESS SCHOOL, B.Ed.
POST-SARDANA, DISTT.MEERUT, U.P.
UP-3423
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:





- 48 -
As per VT report, the built up area is not as per NCTE
norms for B.Ed.
No room for Arts and Work-experience.
There are no common rooms for Males and Females.
Playgrounds are not developed.
Language learning facilities are not available.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH


AUGUST 2009
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
178
21.
MAA
SHEETALA
DEVI B.Ed.
TAIJUGI
NAREYAN
MAHILA MAHAVIDYALAYA
,
KHASRA
NO-A29K,
PO&VILL-BARANDA,
DISTRICT-KANPUR
NAGAR, U.P.
UP-3357
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:





Playgrounds need to be improved.
Science lab needs improvement.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The College does not have Website as per NCTE Regulation,
2007.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
179
22.
RITURAJ
DEGREE B.Ed.
COLLEGE, JANIHA ROAD,
VPO-ASTEE BAJAYAPATI,
DISTT.-FATEHAPUR, UP
UP-3135
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:







- 49 -
As per CD, the building is under construction.
The building is not plastered.
Science Lab and Psychology lab are shared and
equipped.
The flooring is incomplete.
Part of the ceiling is of asbestos sheets.
There are no common rooms for Males and Females.
Playgrounds are not developed.
ill
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH




AUGUST 2009
The Multipurpose hall is small in size.
Language learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The information as required per NCTE Regulation, 2007 is
not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
180
23.
RAJA
DEVI
DEGREE B.Ed.
COLLEGE,
VILL.BADOKHAR
KHURD,
DISTT.-BANDA, UP
UP-3156
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:





Twenty computers are not enough for students of all
courses run by the College.
There are no common rooms for Males and Females.
Playgrounds are not developed properly.
The number of titles in the library is not as per NCTE
norms.
The College does not have website as required per NCTE
Regulation, 2007 is not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
181
24.
KUNDAN INSTITUTE OF B.Ed.
PROFESSIONAL
STUDIES,
VILLAGE
–
JYORA,
POST
–
NAVALGANJ,
KANPUR
NAGAR, U.P.
UP-3356
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:

The Management refused to have inspection.
Hence, the committee decides to issue Show Cause Notice as why
the further processing of the file be not stopped and directs the
Institution to reply within 21 days.
- 50 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
182
25.
PATHIK INSTITUTE OF B.Ed.
EDUCATION
AND
TECHNOLOGY,
KHASRA
NO-1733, VILL-DAURALA
,
POST-DAURALA
,
DISTT.-MEERUT, U.P.
UP-3453
AUGUST 2009
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:

The Management refused to have inspection.
Hence, the committee decides to issue Show Cause Notice as why
the further processing of the file be not stopped and directs the
Institution to reply within 21 days.
183
26.
SAVITA DEVI COLLEGE, B.Ed.
VILLAGE
–
KAYASTH
GAWARI,
POST
–
MOHIUDDINPUR, DELHI
ROAD, DISTT. – MEERUT,
U.P.
UP-3112
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:










As per CD and VTR, the building is under construction.
Library does not have books as per NCTE norms for B.Ed.
Six computers are not enough for 100 students.
ET and psychology labs are in one room and ill equipped.
There are no common rooms for Males and Females.
Playgrounds do not exist.
Language learning facilities are not available.
There is no room for Arts, craft and work-experience.
The number of titles in the library is not as per NCTE
norms.
The College does not have website as required per NCTE
Regulation, 2007 is not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
184
27.
GYAN BHARTI INSTITUTE B.ED.
OF
MANAGEMENT
STUDIES,
KHASRA
NO.937,
VILL.-JAWERI,
MEERUT CANTT., TEHSIL-
UP-3242
- 51 -
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
SDARDHNA,
MEERUT, UP
AUGUST 2009
DISTT.









As per CD, the building is not yet ready for running B.Ed.
course.
Course-wise demarcated built up area is not given in the
building plan.
Flooring is incomplete.
All labs are ill equipped.
Proper furniture does not available in the classrooms.
Playgrounds are not developed.
Language learning facilities are not available in the college.
E-learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The College does not have website as required per NCTE
Regulation, 2007 is not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
185
28.
J.P.VERMA
SCIENCE B.ED.
MAHAVIDYALAYA
TERWAGAUS
GANJ
HARDOI , VILL-TERWA ,
PO-GAUSGANJ
,
DISTRICT-HARDOI
UP-3379
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:












- 52 -
Three computers are not sufficient for 100 students.
There are only 461 books as against 3000 books.
Only twenty chairs in Multipurpose Hall.
Flooring is incomplete.
Unpolished furniture in classrooms.
All labs are ill equipped.
Labs are without any furniture.
No demarcated space in the building for B.Ed. course.
Blackboards are of poor quality.
Playgrounds are not developed.
Language learning facilities are not available in the college.
E-learning facilities are not available.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH


AUGUST 2009
The number of titles in the library is not as per NCTE
norms.
The College does not have website as required per NCTE
Regulation, 2007 is not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
186
29.
S.T.J.M.
B.ED.
MAHAVIDYALAYA,
KHASRA
NO493,495,496,
VILLHERWAL,
POSTPURBOWON,
DISTT.HARDOI,
UP-3535
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee observes the following:









Course-wise detailed demarcated area is not given in the
building plan.
As per CD, Labs and library are common for all courses run
by the Institution.
Total built-up area for B.Ed. course is not given in the
building plan.
Playgrounds do not exist.
Toilets facilities are inadequate.
Language learning facilities are not available in the college.
E-learning facilities are not available.
The number of titles in the library is not as per NCTE
norms.
The College does not have website as required per NCTE
Regulation, 2007 is not available on the College Website.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
187
30
Sidana
Institute
of B.Ed.
Education, Vill- Khiala
Khurd,
Sub
TehsilLopoke, Tehsil- Ajnala,
District- Amritsar, Punjab
PB-468
The original file of the institution, VTR along with all other related
documents, Act of NCTE, 1993, Regulations and Guidelines of
NCTE published from time to time were considered by the
committee and the committee decides to issue letter under
7(11).
188
31
Tara
HP-263
The original file of the institution, VTR under section 14 of the
College
of B.Ed.
- 53 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
Education, Vill- Bassa
Waziran, Post- Bhugnara,
Tehsil- Nurpur, DistrictKangra, H.P.
AUGUST 2009
Institution along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from time to
time were considered by the committee and the committee
observes the following:





The address of the Institution is different from that on the
land document.
The Multipurpose Hall is not appropriate.
All labs are ill equipped and not proper.
VT members could not open the College website.
Government of Himachal Pradesh through its’ letter NO.
EDN – A – Chha (7)-2 / 2007- dated 13 August 08
expressed that no more B.Ed. Colleges are required in the
State.
Hence, the committee decides to issue Show Cause Notice on the
above subject and directs the Institution to reply within 21 days.
189
32
Sai- A- One College of ETT
Education, Vill- Baduhi
(Raja Ka Bagh), PostNagabari, Tehsil- Nurpur,
District- Kangra, H.P.
HP-293
The original file of the institution, VTR under section 14 of the
Institution along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from time to
time were considered by the committee and the committee
observes the following:








- 54 -
Total constructed area is not more than 750 sq. m which is
not as per NCTE norms for ETT / D.Ed.
Actual space is not as per approved building plan.
The land is not in the name of the Institution.
All books available in the library are for B.Ed. course but
not D.Ed. / ETT.
The physical and instructional facilities indicate that the
Institute is not ready to start ETT / D.Ed. course.
Eleven computers are not enough for students of all
courses.
E-learning facilities are not available.
Different labs are ill equipped.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH


AUGUST 2009
The Management suppressed the information regarding
running B.Ed. Course.
The titles of books in the library are not as per NCTE norms
for D.Ed. / ETT.
Hence, the committee decides to issue Show Cause Notice on the
above points and directs the Institution to reply within 21 days.
190
33
B.B.N.
College
of B.Ed.
Education, VPO- Baroa,
Tehsil- Jawalaji, DistrictKangra, H.P.
HP-289
The original file of the institution, VTR under section 14 of the
Institution along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from time to
time were considered by the committee and the committee
observes the following:

Government of Himachal Pradesh through its’ letter NO.
EDN – A – Chha (15)-1 / 2001-Loose dated 12 August 09
expressed that no more B.Ed. Colleges are required in the
State.
Hence, the committee decides to issue Show Cause Notice on the
above subject and directs the Institution to reply within 21 days.
191
34
Awasthi Memorial School D.Ed.
of Teacher Education,
Vill- Dharamshala, Sham
Nagar, Kangra, HP.
HP-312
The original file of the institution, VTR under section 14 of the
Institution along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from time to
time were considered by the committee and the committee
observes the following:

The land has not been registered in the name of Institution
within stipulated time as communicated to it. There is no
reply of the Institution regarding registration of land in the
name of Institution till date.
Hence, the committee decides to refuse recognition to D.Ed.
course.
192
35
Asra
College
of B.Ed.
PB-665
- 55 -
The original file of the institution, VTR under section 14 of the
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
Education, VPO- Rajpura,
Street
No.
NH-22,
PatialaSangrur
Highway,
TehsilBhawanigarh,
DistrictSangrur, Punjab.
AUGUST 2009
Institution along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from time to
time were considered by the committee and the committee
observes the following:





As per CD, the building is under construction.
Proper Science lab does not exist.
Building completion certificate is not submitted.
The number of titles in the library is not as per NCTE
norms.
It appears that the Institution is running many AICTE
approved courses on the same premise. The Physical and
Instructional facilities meant for AICTE approved courses
are being proposed to be used for B.Ed. course.
Hence, the committee decides to issue Show Cause Notice on the
above subject and directs the Institution to reply within 21 days.
193
36
Malwa
College
of B.Ed.
Education,
VPOSardulewala,
TehsilSardulgarh,
DistrictMansa, Punjab
PB-587
The original file of the institution, VTR under section 14 of the
Institution along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from time to
time were considered by the committee and the committee
observes the following:





The building is unfinished.
The number of titles in the library is not as per NCTE
norms.
As per CD, it appears that the building is being used to run
some other programmes.
E-learning facilities are not available.
Language learning facilities are not available.
Hence, the committee decides to issue Show Cause Notice on the
above subject and directs the Institution to reply within 21 days.
194
37
Bhagwati
College
of B.Ed.
PB-639
- 56 -
The original file of the institution, VTR under section 14 of the
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
Education,
VillSom
Hospital, Post- Bhikhi,
District- Mansa, Punjab.
AUGUST 2009
Institution along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from time to
time were considered by the committee and the committee
observes the following:



Three computers are not sufficient for 100 students.
Language learning facilities are still not adequate.
The number of titles in the library is not as per NCTE
norms.
Hence, the committee decides to issue Show Cause Notice on the
above subject and directs the Institution to reply within 21 days.
AGENDA ITEM NO.148.08.00 CONSIDERATION OF THE VTR UNDER SECTION 15
S. NO. AGEAN
NO.
195
1.
NAME OF THE INSTITUTION
COURSE
PT.
KUNDAN
LAL
SHUKLA B.P.Ed.
MAHAVIDYALAYA,
VILLPRARIDDHPUR, PO-RAMIA, TEHSILAKBARPUR, DISTRICT-KANPUR, U.P.
FILE NO. DECISION OF NRC
UP-3345
The original file of the institution, VTR along with all other
related documents, Act of NCTE, 1993, Regulations and
Guidelines of NCTE published from time to time were
considered by the committee and the committee observes
the following:




Playgrounds are not well developed.
As per CD, playgrounds are under water.
The number of titles in the library is not as per
NCTE norms.
The College does not have Website as per NCTE
Regulation, 2007.
Hence, the committee decides to issue Show Cause Notice
- 57 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
on above points and directs the Institution to reply within
21 days.
196
2.
INNOVATIVE
INSTITUTE
OF M.Ed.
EDUCATION AND TECHNOLOGY, PLOT
NO. -6. KNOWLEDGE PARK -2,
GREATER NOIDA, U.P.
UP-2732
Decision is to be taken after the report of inspection under
section 17 is considered.
197
3.
KANCHAN
SINGH
BHOOLI
DEVI M.P.Ed.
MAHAVIDYALYA,
VILLL.BHIKIHANAPUR,
SHAJAHANPUR,
VINAYA,
POST-SARWAN
KHERA,
AKBARPUR, KANPUR, U.P.
UP-3114
The original file of the institution, VTR along with all other
related documents, Act of NCTE, 1993, Regulations and
Guidelines of NCTE published from time to time were
considered by the committee and the committee observes
the following:



Course-wise detailed building plan is not submitted.
The number of titles in the library is not as per
NCTE norms.
The College does not have Website as per NCTE
Regulation, 2007.
Hence, the committee decides to issue Show Cause Notice
on above points and directs the Institution to reply within
21 days.
198
4.
NEHRU
GRAM
BHARTI B.Ed.
VISHAWVIDYALAYA, ALLAHABAD, U.P. ADD.
UP-3548
The original file of the institution, VTR along with all other
related documents, Act of NCTE, 1993, Regulations and
Guidelines of NCTE published from time to time were
considered by the committee and the committee observes
the following:





- 58 -
Additional Physical and Instructional facilities for
proposed B.Ed. additional intake are not in place.
Playgrounds are not well developed.
The number of titles in the library is not as per
NCTE norms.
Language learning facilities do not exist.
The College does not have Website as per NCTE
Regulation, 2007.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH

AUGUST 2009
The Video during VT has not been made and
submitted.
Hence, the committee decides to issue Show Cause Notice
on above points and directs the Institution to reply within
21 days.
199
5.
RAJ
NARAYAN
PANDEY
DEGREE B.P.Ed.
COLLEGE,
KHASRANO-PHAPHAMAU
ROAD, VILL-BERUI, PO-GARAPUR,
TEHSIL-PHOOLPUR,
DISTRICTALLAHABAD,U.P.
UP-3326
The original file of the institution, VTR along with all other
related documents, Act of NCTE, 1993, Regulations and
Guidelines of NCTE published from time to time were
considered by the committee and the committee observes
the following:






Sports Medicine Lab and Educational Technology lab
are ill equipped.
As per CD, there is no Multipurpose Hall.
There is no common room for Males and Females.
The playgrounds are under developed.
The number of titles in the library is not as per
NCTE norms.
The information as required per NCTE Regulation,
2007 is not available on the College Website.
Hence, the committee decides to issue Show Cause Notice
on above points and directs the Institution to reply within
21 days.
200
6.
SHIV
SHANKAR
CHATURVEDI BTC.
MAHAVIDYALAYA,
TUMPAR,
KHALILABAD , SANT KABIR NAGAR,
U.P.
UP-2541
The original file of the institution, VTR along with all other
related documents, Act of NCTE, 1993, Regulations and
Guidelines of NCTE published from time to time were
considered by the committee and the committee observes
the following:



- 59 -
The building plan is not approved.
The course-wise earmarked built up area is not
shown in the building plan.
All labs are ill equipped.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH






AUGUST 2009
Multipurpose hall is common for B.Ed. and BTC
students and that too is small.
Five computers are not enough for students of all
courses run by the Institution.
Playgrounds do not exist.
The number of titles in the library is not as per
NCTE norms.
Language learning facilities do not exist.
The College does not have Website as per NCTE
Regulation, 2007.
Hence, the committee decides to issue Show Cause Notice
on above points and directs the Institution to reply within
21 days.
201
7.
SUBHASH CHANDRA BOSE DEGREE B.ED.
UP-3534
COLLEGE KAHLI, VILL-KHALI TERWA , Additional
POST-GAUSGANJ,
DISTT.-HARDOI,
U.P.
The original file of the institution, VTR along with all other
related documents, Act of NCTE, 1993, Regulations and
Guidelines of NCTE published from time to time were
considered by the committee and the committee decides to
issue letter under 7(9).
202
8.
Swami
Sarvanand
College
of ETT
Education, Vill- Talwandi G.T. Road,
Dinanagar- 143531, Punjab
The original file of the institution, VTR under section 15
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from
time to time were considered by the committee and the
committee observes the following:
PB-513

The land has not been registered in the name of the
Institution within stipulated time as communicated
through letter dated 12 May 2009.
Hence, the committee decides to refuse recognition to
ETT.
203
9.
Anand College of Education, VPO- M.Ed.
Jethuwal,
Batala
Road,
DistrictAmritsar, Punjab
PB-464
- 60 -
The original file of the institution, VTR under section 15
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from
time to time were considered by the committee and the
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
committee observes the following:






As per CD, multipurpose Hall does not exist.
E-learning facilities are not available.
Titles of books in the library are not as per NCTE
norms for M.Ed.
Psychology and ET labs have not been upgraded to
meet the requirement of M.Ed. course.
Twenty Computers are not enough for students of
all courses run by the Institution.
FDR for Reserve fund as per NCTE norms for M.Ed.
is not submitted.
Hence, the committee decides to issue Show Cause Notice
and directs the Institution to reply within 21 days. Further,
the land is to be registered in the name of the Institution
within 90 days.
204
10. Kenway College of Education, VPO- ETT
PB-567
Abohar, District- Ferozepur, Punjab.
The original file of the institution, VTR under section 15
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from
time to time were considered by the committee and the
committee observes the following:


Total titles of books in the library are not as per
NCTE norms for ETT / D.Ed.
Arts Craft and Work-experience facilities do not
exist.
Hence, the committee decides to issue Show Cause Notice
and directs the Institution to reply within 21 days.
205
11. Colonel P.G. College Of Education, M.Ed.
PB-489
VPO- Chural Kalan Distt- Sangrur148031, Punjab
- 61 -
The original file of the institution, VTR under section 15
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from
time to time were considered by the committee and the
committee observes the following:
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH







AUGUST 2009
The land has not yet been registered in the name of
the Institution as communicated through letter
dated 29 April 2009 and 2 June 2009.
There is no earmarked built up area for M.Ed.
course.
E-learning material is not available.
All labs are ill equipped.
The titles in the library are not as per NCTE norms
for M.Ed.
Playgrounds are not developed.
The Institution does have website as per NCTE
Regulation 2007.
Hence, the committee decides to issue Show Cause Notice
and directs the Institution to reply within 10 days.
206
12. Namdhari College of Education, Vill- M.Ed.
HP-275
Bhojpur, Post – Sunder Garh, District
- Mandi, HP.
The original file of the institution, VTR under section 15
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from
time to time were considered by the committee and the
committee observes the following:







- 62 -
ET Lab and psychology lab are ill equipped.
Twenty computers are not enough for B.Ed. and
M.Ed. students.
E-learning material is not available.
The Multipurpose Hall has to be common for both
B.Ed. and M.Ed. The existing Multipurpose Hall is
too small.
The titles in the library are not as per NCTE norms
for M.Ed.
As per CD, there is no toilet facility neither for
males nor females.
As per CD, there is no drinking water facility in the
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
college.
Hence, the committee decides to issue Show Cause Notice
and directs the Institution to reply within 21 days.
207
13. Shanti College Of Education, Vill- M.Ed.
HP-260
Kailash Nagar, Post- Nakroh, TehsilAMB, District- UNA, H.P.
The original file of the institution, VTR under section 15
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from
time to time were considered by the committee and the
committee observes the following:




The land has not been registered in the name of
Institution within 90 days as communicated to the
Institution.
The Multipurpose Hall is small in size.
Twenty computers are not enough for B.Ed. and
M.Ed. students.
The titles in the library are not as per NCTE norms
for M.Ed.
Hence, the committee decides to refuse recognition to
M.Ed. course.
208
14. Baba
209
15. Gaur Brahaman College of Education, B.Ed.
Mangal Singh Institute of B.Ed. ADD PB-688
Education, Barnala Road, Bughipura,
District- Moga, Punjab.
Gau Karan Road, VPO - Rohtak, Distt additional
- Rohtak, Haryana
Decision is kept pending till the Inspection under section 17
is done.
HR-1591 The original file of the institution, VTR under section 15
along with all other related documents, Act of NCTE,
1993, Regulations and Guidelines of NCTE published from
time to time were considered by the committee and the
committee observes the following:


- 63 -
ET and Psychology labs are ill equipped and tests &
equipments are not in proportion to B.Ed. additional
intake.
There is no course-wise demarcation of building
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH








AUGUST 2009
plan.
The size of Multipurpose Hall and classrooms are not
as per NCTE norms.
The library has not been updated.
The building is still under construction and alteration
is in progress.
There is no play ground.
The titles of books are not as per NCTE norms for
B.Ed.
The information as required per NCTE Regulation,
2007 is not available on the College Website.
Fourteen computers are not sufficient for students
of all courses.
Two different land documents were shown to VT
members.
Hence, the committee decides to issue Show Cause Notice
on above points and directs the Institution to reply within
21 days.
AGENDA ITEM NO.148.09.00
CONSIDERATION OF THE VTR UNDER SECTION 17
S. NO. AGEAN NAME OF THE INSTITUTION
NO.
210
1
COURSE
FILE NO. DECISION OF NRC
INNOVATIVE
INSTITUTE
OF All courses UP-2156
EDUCATION AND TECHNOLOGY,
PLOT NO. -6. KNOWLEDGE PARK 2, GREATER NOIDA, U.P.
The original file of the institution, VTR under section 17 along with
all other related documents, Act of NCTE, 1993, Regulations and
Guidelines of NCTE published from time to time were considered
by the committee and the committee observes the following:

- 64 -
The courses being run from the same premise are: BA,
B.Ed. BCA (Proposed), LLB (Three years), LLB (Five Years),
B.Pharma, D.Pharma (Applied), B.Ed. Additional (Applied),
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH














- 65 -
AUGUST 2009
M.Ed. (proposed), B.Sc. (Biotech), B.Sc.(Microbiology),
and M.Sc. (Biotech) (proposed).
The building in which all courses are being run has not
been issued building completion certificate till date.
The building map is for Institute of Engineering and
Technology but not for Innovative Institute of Education
and Technology.
The built up area has not been mentioned on the Building
plan.
The Faculty was appointed after the commencement of
B.Ed. course in contravention of the NRC / NCTE order No.
10199 – 10200 dated Dec. 29, 2006.
Another building shown to VT members for B.Ed., B.Ed.
Additional (proposed) and M.Ed. (proposed) is still under
construction.
The built up area earmarked for B.Ed. in the upcoming
building is not as per NCTE norms for B.Ed. Not to talk of
B.Ed. additional (proposed) and M.Ed. (proposed), the built
up space is not sufficient even to run the present B.Ed.
course.
Out of 1161.2 Sq.m, two rooms measuring 1303 sq. ft.
were found locked and told to be dumped with all sort of
construction material.
None of the appointed Principal and eight B.Ed. lecturers
was present during inspection.
As per affidavit, original mark sheets were not made
available to the VT members.
Mr. Kanhaya Kumar Yadav, being not PG and B.Ed., is not
qualified as per NCTE norms for B.Ed.
All rooms and other classrooms have school furniture.
There is no Multipurpose Hall, Work-experience room, Arts
and craft room, seminar room, and separate rooms for
Faculty.
Science lab does not have multiple sets of apparatus and
material required to perform practical as per syllabus.
Three computers are not sufficient for 100 students.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH



AUGUST 2009
Computer lab has got only slabs, no fittings, no computers
or furniture of any kind.
The titles of books in the library are not as per NCTE
norms for B.Ed.
No play ground for Hockey, football. Volley-ball or
badminton is available on the campus.
Hence, the committee decides to issue Show Cause Notice on
above points and directs the Institution to reply within 21 days.
AGENDA ITEM NO.148.10
S.L.
No.
211
AGENDA NAME OF THE INSTITUTION
NO.
1
212
COURSE FILE NO. DECISION OF NRC
Laxmi Shikshak Prashikshan Mahavidyalaya, B.ED.
Merana Road, Bayana, Bharatpur, Rajasthan.
AGENDA ITEM NO.
S.L.
CONSIDERATION OF THE REPLY RECEIVED FROM THE INSTITUTION WHERE LOI WAS
ISSUED SUBJECT TO CERTAIN CONDITIONS AND AWAITED FOR VISITING TEAM
CONSTITUTION FOR SHIFTING OF PREMISES
AGENDA
NO.
1.
RJ-503
Before taking final decision, the committee decides to
conduct inspection on the new premise of the
Institution.
148.11.00 MISC. CASES.
NAME OF THE INSTITUTION
COURSE
SYMBOYZIA COLLEGE, MAHARANI BAGH, BODLA, AGRA, B.Ed.
U.P.
DECISION OF NRC
UP-2030
Permitted to change
education to Girls.
from
co-
CO- EDUCATION TO GRILS
213
2.
DEV COLLEGE, BARHAN, ETMADPUR, AGRA,U.P.
- 66 -
All courses
Inspection under Section 17 is to
be conducted.
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
214
3.
DEV COLLEGE OF EDUCATION, BARHAN, ETMADPUR, All courses
AGRA, U.P.
Inspection under Section 17 is to
be conducted.
215
4.
Academy of Business Management, Vill: Shakoorpur, All courses
Mohiuddinpur, Modinagar, Ghaziabad, UP
Inspection under Section 17 is to
be conducted.
216
5.
Academy of Business Management, Gyan Sthali, Hapur All courses
Road, Modinagar, Ghaziabad, UP
Inspection under Section 17 is to
be conducted.
217
6.
Rao Mulchand Education College, Vill: Khatori Khrud, All courses
The: Narnol, Jila: mahindergarh, haryana
Inspection under Section 17 is to
be conducted.
218
7.
R.K. College of Education, Vill:
Farunagar, Jila: Gurgaon, H aryana
Inspection under Section 17 is to
be conducted.
219
8.
Venkateshwar Institute of
Technology, Jatoli, Meerut
220
9.
Bhora
Computer
Kala, The: All courses
Science
and All Courses
Inspection under Section 17 is to
be conducted.
Venkateshwar Institute of Technology, Meerut
All courses
Inspection under Section 17 is to
be conducted.
221
10.
Ch: Narendra Singh College, Meerut
All courses
Inspection under Section 17 is to
be conducted.
222
11.
S.R. College of Education, Meerut
All courses
Inspection under Section 17 is to
be conducted.
223
12.
Padmavati Bal Vidyapeeth, Meerut
All courses
Inspection under Section 17 is to
be conducted.
224
13.
Venkateshwar College of Education, Meerut
All courses
Inspection under Section 17 is to
be conducted.
225
14.
Gandhi Institute of professional & Technical Studies, All courses
Hapur Bye Pass, Meerut
Inspection under Section 17 is to
be conducted.
226
15.
Gandhi Institute of Perfect Teaching, Meerut
All courses
Inspection under Section 17 is to
be conducted.
227
16.
Gandhi Institute of professional & Technical Studies for All courses
Girls, Meerut
Inspection under Section 17 is to
be conducted.
- 67 -
MINUTES OF 148TH MEETING OF NORTHERN REGIONAL COMMITTEE HELD FROM 28TH TO 30TH
AUGUST 2009
228
17.
R.N College of Education, Hastinapur, UP
All courses
Inspection under Section 17 is to
be conducted.
229
18.
Department of Education, Amity University, Lucknow
All courses
Inspection under Section 17 is to
be conducted.
230
19.
NANCY COLLEGE OF EDUCATION, PATIALA, PUNJAB.
All courses
Inspection under Section 17 is to
be conducted.
231
20.
S.G.G.S. Khalsa College, VPO- Mahilpur, Tehsil- Garh All courses
Shankar, District- Hosiarpur, Punjab
Inspection under Section 17 is to
be conducted.
(K.S.YADAV)
(D.N. Sansanwal)
CHAIRMAN, NRC,NCTE, JAIPUR
Convener RD,NRC, NCTE, JAIPUR
- 68 -