ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK ARTEC Project No. 3760 G. PERFORMANCE QUALITIES & DESCRIPTION OF SYSTEMS ARTEC CONSULTANTS INC Page G 1 ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK NOISE CONTROL AND SOUND ISOLATION INTRODUCTION These guidelines are presented to assist the design team and cost estimators in making performance spaces and other rooms in the facility appropriately quiet, while keeping noise control costs moderate. These recommendations are based on both our wide experience and standard noise control engineering practices. THE NEED FOR LOW NOISE LEVELS Noise is defined as unwanted sound. During a performance, any sound not produced by the performer is, therefore, noise. Absence of noise is a prerequisite for excellent acoustics. Unless background noise is reduced to the appropriate level, all of the other design work and money spent to achieve good acoustics will be in vain. Noise and vibration control must begin at the outset of the project. The purpose of minimizing noise and vibration is not simply to reduce annoyance to the performers or audience; the motivation reaches much further. Very low background noise levels are vital to: Maximize the clarity and richness of the sound Provide ease of concentration and communication among performers Maximize the audible dynamic range Maximize the length and apparent loudness of the reverberant sound as it dies away BACKGROUND NOISE CRITERIA In order to achieve an appropriate acoustical environment, design goals for noise and vibration will be stringent. Criteria will be developed for mechanical/electrical systems as well as for outside noise. Throughout the rest of this report we refer to “noise-critical spaces.” These are spaces where special precautions must be taken in the design of building systems, and in the structural and architectural design to satisfy the appropriate criteria. These “noise-critical spaces” include performance, rehearsal, teaching, and technical spaces many other areas where quiet is required. The criteria for allowable noise levels are presented in terms of Noise Rating (NR) curves according to ISO R 1996 (1971) in octave bands from 63 Hz through 8 KHz. These curves have been extended to include the 31.5 Hz octave band where values are limited to a maximum of 65 dB to prevent possibility of any perceptible vibration in walls or ceilings built from lighter construction. The A-Weighted sound level (dBA) corresponding to each NR curve is also provided for reference only; it is the octave band levels that will need to be met in the finished building. For the Concert Hall, we are recommending a background noise level which approximates NR0, but it is not as stringent in the low band; this criteria is referred to as N-1. The octave band sound pressure levels for the noise criteria are given in the following table. All values are in dB (ref: 20 μPa). Criterion N-1 NR10 NR15 NR20 NR25 NR30 63 36 43 47 51 55 59 ARTEC Project No. 3760 125 22 31 35 39 44 48 OCTAVE BAND CENTER FREQUENCY (HZ) 250 500 1K 2K 4K 13 8 5 3 3 21 15 10 7 4 26 20 15 12 9 31 24 20 17 14 36 29 25 22 20 40 34 30 27 25 8K 3 2 8 13 18 23 dB(A) 19 21 26 30 35 39 2 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK NR35 NR40 63 67 53 57 45 49 39 44 35 40 32 37 30 35 28 33 44 48 BACKGROUND NOISE GOALS The following table presents background noise criteria for each of the “noise critical spaces” on the project. SPACE DESCRIPTION BACKGROUND NOISE GOAL Concert Hall: Concert Hall Sound and Lighting Control Rooms – operable window Sound and Lighting Control Rooms – fixed window Announce/Observation Rooms Broadcast/Recording Room Simultaneous Interpretation Booths Projection and Followspot Rooms Orchestra Assembly Area (backstage) Technical Offices Rehearsal/Recital Hall: Rehearsal/Recital Hall Conference Hall: Conference Hall Sound/Lighting Control / Projection Rooms Simultaneous Interpretation Systems Booths Followspot Rooms Break-Out Conference Rooms Exhibition Area Performer Spaces: Conductor Dressing Room Soloist and Concert Leader Dressing Rooms Musician Rehearsal/Storage Rooms 1-2 person Dressing Rooms Orchestra Dressing Rooms Conference Space Dressing Rooms Administrative Areas: Administrative Offices Conference Rooms Administrative Offices (Open Plan) Common Areas: Lobby & Public Lounges N-1 NR 10 NR 15 NR 15 NR 15 NR 15 NR 20 NR 15 NR 30 NR 15 NR 20 NR 25 NR 15 NR 30 NR 30 NR 35 NR 20 NR 25 NR 25 NR 25 NR 30 NR 30 NR 30 NR 30 NR 35 NR 35 Except for special circumstances, occupied spaces not listed here should meet NR 40, or otherwise fall within the limits of local environmental requirements. The above criteria is intended to guide the design of mechanical systems. Criteria for sound isolation between spaces, from electrical and outside noise will not necessarily be the same as the criteria given for mechanical background noise. Transient, intermittent and tonal noise sources will be addressed with criteria that can more accurately gauge audibility and annoyance. ARTEC Project No. 3760 3 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK ARCHITECTURAL CONSIDERATIONS Sources of Noise and Vibration Noise and vibration can arise from sources both inside and outside a building. In the initial stages of design, the architect and design team should be aware of all of the following noise sources: Internal sources Elevators, escalators People and equipment in bars and foyers Scenic construction Loading activities Restaurant activities Electrical transformers Panel and relays Lighting fixtures Mechanical and electrical systems External sources Water Thunder and rain Outdoor events Road, air and boat traffic FACILITY PLANNING AND DESIGN FOR ACOUSTICAL ISOLATION General Requirements for Airborne Noise Isolation: Requirements for airborne noise isolation will be dependent upon the planned uses of any specific space, its corresponding background noise criteria, and specific adjacencies. Specific criteria will be developed during early design phases and stated as R’w values in dB in accordance with ISO 140-4, 140-5 and 717-1. Alternative methods to ensure sufficient airborne sound insulation at lower frequencies, such as C50-5000 according to ISO 717-1, will also be evaluated during design. In general, horizontal airborne sound reduction shall be minimum R’w = 51dBexcept where identified elsewhere in this document. Please note that for certain noise sensitive and/or noisy areas such as plantrooms there will be a demand for significantly higher degree of airborne sound insulation (up to R’w = 70 dB). Particular attention is to be given to low frequency sound transmission and sound flanking paths between adjacent spaces, particularly music performance and rehearsal spaces. In office areas, airborne sound insulation of the partition walls, excluding doors, should generally be minimum R’w = 44 dB between adjacent offices, and R’w = 40 dB between the office and adjacent corridors. No specific acoustical criteria will be given for doors to standard offices. In meeting rooms and executive offices, the airborne sound insulation between adjacent spaces shall be minimum R’w = 48 dB, and R’w = 44 dB between these spaces and adjacent corridors. Doors should achieve minimum R’w = 31 dB for these areas. ARTEC Project No. 3760 4 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK In technical control rooms within performance spaces, airborne sound insulation between the control room and performance space should generally be minimum R’w = 54 dB. Doors leading into these areas should achieve minimum R’w = 35 dB, depending on location. Specific attention to vision glazing will be required in these rooms. General Requirements for Outdoor Noise and Vibration: A complete noise and vibration study of the site will be prepared early in the design phase, and will include expected auto and ship traffic load, as well as other expected noise sources. This will be used to develop sound insulation criteria for facades, exterior glazing, and roof structures. The earliest stages of design allows for considerable opportunity to anticipate and avoid acoustical isolation problems. Some of the required isolation can be achieved by careful planning of the spaces in and around the building. The success of this early planning will have a significant effect on the overall cost of the building. Some General Planning Considerations: Performance/rehearsal spaces should be surrounded, vertically and horizontally, by program spaces like foyers, lobbies, offices, storage spaces, backstage areas, etc so their exposure to the exterior environment is minimized. Place no mechanical or large electrical equipment in these surrounding rooms. Do not attach plumbing fixtures and pipes to the walls, floor or ceilings of any performance or rehearsal space. Locate the noisiest spaces farthest from the performance spaces. Locations of WC The noise caused by water flow from flushing toilets is audible in some existing performance and rehearsal spaces. Avoid locating WC’s directly adjacent to the performance or rehearsal spaces. Across a corridor is acceptable. ARTEC Project No. 3760 5 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK Sound and Light Locks Sound and light locks are essential for all entrances to and exits from performance and rehearsal spaces. This is to provide an appropriate sound (and light) isolation buffer between the performance/rehearsal venue and its surrounding areas. A sound and light lock consists of two sets of doors with at least 1.5 m separation, forming a small vestibule. All walls forming a sound and light lock walls are to extend from floor slab to ceiling slab, and are to be sealed airtight to all surrounding construction. Typical sound and light locks should incorporate heavy doors with a minimum sound class of 35dB; either 55 mm thick solid wood or insulated steel doors fitted properly in frames with full perimeter sound gasket. STRUCTURAL CONSIDERATIONS Structural Design and Acoustical Isolation To ensure maximum viability of the facility, it is important that the major performance venues can operate concurrently with each other and with the conference facilities. To reduce the possibility of noise transmission through the building structure, it is important to structurally separate the concert hall, recital hall, and conference hall from each other and the rest of the facility with a 50mm wide structural separation. This break will occur from foundations up through the roof. Artec will work with the design team as facility massing is being planned to develop these structural breaks in the most cost effective manner – often in cooperation with necessary building structural movement joints. Locations for the Mechanical & Electrical Equipment Buildings To keep air-borne and structure-borne noise out of noise-critical areas, major mechanical and electrical equipment should be centralized in locations remote from noise-critical spaces. ARTEC Project No. 3760 6 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK Plan for a structurally separate physical plant that will house the heaviest, noisiest equipment, such as chillers, pumps, and large fans. This physical plant should also be planned to house major electrical equipment such as distribution switchgear and transformers. All this equipment should be located on grade. Satellite mechanical and electrical plantrooms should be minimized in quantity, located remote from noise critical areas, and should only contain fan units (not contain large machinery such as chillers or large pumps or large transformers). Isolating construction of walls and slabs will depend largely on the location of these spaces, so it is advisable to keep these areas remote from sensitive areas, surrounded by similar spaces where noisy activities occur, and on grade where possible to avoid expensive sound isolating constructions. Mechanical and electrical duct shafts and duct zones can be used as acoustical “buffer zones” around the mechanical equipment room. Each duct or shaft that penetrates the plantroom enclosure must be sealed appropriately. Doors to and from plantrooms should lead only to acoustically non-critical building areas. In some special cases sound locks or special acoustical doors may be required at access doors to the plant rooms. Fresh air intakes and exhaust air discharges should be planned to not lead onto noise sensitive outdoor areas or onto locations where noise can re-enter the building through walls, windows, doors or vents. MECHANICAL SYSTEMS CONSIDERATIONS Air Handling Systems Serving Noise-Critical Spaces The degree of noise control materials and methods used to properly attenuate noise produced by the air delivery systems will depend on a number of factors, but among the most important is the length of acoustically lined duct between the fan and the nearest terminal in the noisecritical space. Significant savings can be had if the system is laid out so that there are no particularly short duct lengths. We therefore advise that air handling units serving noisecritical spaces be located as remote from the spaces they serve as possible to facilitate these long duct runs. A combination of vibration isolators, duct silencers, insulated acoustical plenums, insulated fan casings, and careful duct routing will also be used to attenuate the noise from these systems. The Need for Separate Air Handling Systems It is strongly advised that all main performance/rehearsal spaces be served from dedicated constant volume air handling systems to achieve consistency in background noise levels and to allow flexibility and cost-efficiency in the operation of the facility. In addition, there are several areas where, because of operating schedules and load variations, air handling systems must be operated (not just controlled) independently of the systems serving the performance areas. These include: Rehearsal spaces Box office(s) Technical control rooms, followspot rooms, projection rooms (these several spaces may be separate zones on one system, but not on the audience chamber or lobby systems) Instrument storage rooms ARTEC Project No. 3760 7 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK These rooms should be served by air handling units located in the mechanical plantroom, independent of the halls. This arrangement will allow the technicians, staff and artists to work in the control rooms during “off”-hours without the necessity of running the main mechanical systems for the halls. In most cases, one or more of these rooms can be served by one air handling unit, if feasible from an engineering standpoint. Systems can be VAV if feasible. Lighting, sound and communications equipment can sometimes remain on 24 hours a day and can generate a lot of heat. Therefore a separate, dedicated air-handling unit(s) for the spaces housing this equipment is advised. The air handling unit can be located in the equipment rooms in most cases. Some areas may require separate air handling systems for health reasons as well as time of use. These include: The receiving dock, where toxic fumes are encountered (for exhaust of truck fumes as well as for dust reclamation) Film Projection Rooms (depending on specific code requirements) Follow spot rooms (certain types of follow spots emit toxic fumes) Treat this equipment as discussed above to keep noise and vibration from noise-critical spaces. Spaces with noise criteria of NR 25 and higher can be served through variable air volume (VAV) systems. Care must be taken to locate VAV boxes serving each room to achieve the desired criteria in the particular room. Acoustical Lining Mineral wool or glass fiber duct lining insulation (density 24–48 kg/m3) with integral protective facing will need to be installed in all ductwork systems serving noise-critical spaces. Acoustical duct lining insulation typically should be 25 mm thick installed in all ductwork serving noise critical areas. Final lining requirements will be developed when duct layout and equipment selections have been made. Additional thermal insulation is not usually required for acoustically lined ducts. Acoustical Plenums and Duct Silencers Control of low-frequency fan noise is often best achieved through a combination of duct silencers and acoustical plenums. Plenums can be built on site from concrete, block, or prefabricated insulated steel panels. Assume all acoustical plenums will be internally lined with duct liner insulation (100 mm thick, typical). For initial pricing, planning and mechanical room layout assume that each of the supply and return systems serving any space with a noise criteria of less than NR 20 will require a plenum on the order of 2.0m × 3.0m× 3.7 m. Duct silencers may be required for noise attenuation when the noise reduction from acoustically lined duct is not sufficient. For initial pricing, planning, and layout, assume that each supply and return system for spaces with criteria of NR 15 or less will each need a 3 m long silencer. Each system serving spaces with criteria of NR 20 will require a 2m silencer, ARTEC Project No. 3760 8 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK and each system serving spaces with criteria between NR 20 – NR 30 will require a 1 m silencer. It is recommended to install silencers where the ducts exit the mechanical plantroom. The heavier gauge steel from which silencers are built acts to reduce mechanical room noise breakout. Also, regenerated noise from silencers, even when the silencers are correctly located, means that they should be located as far from the terminals as possible. Duct Materials and Duct Geometry Rectangular sheet metal duct should be used for most applications. Avoid duct dimensions with aspect ratios exceeding 4:1, as they have a tendency to drum. If exposed ductwork is required inside a noise-critical space (quiet or noisy), use internally lined circular duct, since this shape allows less noise to break into or out of the duct. Do not use circular ducts for general use since they do not attenuate low frequencies sufficiently. Transitions in duct geometry should be gradual; none greater than 1 in 7. Elbows Use full radius elbows in systems serving noise-critical spaces in order to minimize generation of low frequency turbulence. Where full radius elbows are not possible, small radius elbows are still preferable to mitered elbows. Do not use turning vanes, except where required within the mechanical room or far away from the terminal outlets as they generate turbulence noise. Control Systems in the Critical Spaces Control systems located in noise-critical spaces must be electronic and must operate silently. Direct location of these devices within the space should be avoided if possible. Routing of Ducts and Pipes Routing of ducts and pipes should be carefully considered early in the design. Avoid service penetrations in sound isolating constructions wherever possible. Ducts and pipes should not enter noise critical spaces directly from another occupied program space, but rather from an enclosed, quiet duct space or shaft. Do not route ductwork serving noise-critical spaces through noisy spaces or through other noise-critical spaces. Noise can enter the duct in one space and be transmitted down the duct to another. Piping and Noise-Critical Spaces Hot water, chilled water, domestic water, steam, sanitary, or roof drain piping should in general not be run within or through noise-critical spaces. Hot water and steam pipes can generate noise as the pipes expand and contract in the pipe clamps and as valves constrict the flow. Pipes connected to pumps will vibrate and radiate low frequency pump noise as well as flow noise. Such vibration can easily be transmitted through the building structure. Flow noise can be a problem in all pipes, including domestic hot and cold water. This can be minimized by sizing pipes for a maximum velocity of 1.2m/s for pipes 50mm in diameter or less and 3m/s for larger pipe sizes using a pressure drop limitation of 400 Pa/m. Flow noise and vibration can also be introduced by turbulent flow, sharp pressure losses and trapped air. Care should be taken to avoid these conditions. Sprinkler pipes pose no acoustical problem in quiet spaces, but the points where they penetrate the envelope of any noise- critical space must be carefully sealed. ARTEC Project No. 3760 9 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK Roof drain pipes transmit noise from outside and also radiate flow noise in storms. ARTEC Project No. 3760 10 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK Controlling Air Flow Noise Noise is generated by the flow of air through or past diffusers, grilles, dampers, turning vanes, and duct fittings. The sound power generated at any one location depends on both the air velocity and the local geometry. The greater the air turbulence, the greater the sound power generated; higher velocities in the presence of local obstructions result in greater turbulence and therefore higher noise levels. Air Supply From Underfloor Plenum One method of air delivery in the Concert Hall is to supply air through a plenum under the concrete slab(s) supporting the seating and delivering the air through holes/outlets in the floor coordinated with the audience seating. This approach will require coordination with seating, structural considerations, and careful design of duct distribution and terminal outlets to ensure even distribution of air to all areas of the auditorium. Underfloor Plenum For initial pricing purposes, assume all walls and ceiling of the distribution plenum under the floor slab are lined with glass or mineral fiber duct lining insulation (50 mm, typical). Air Velocities in the Ducts Leading to the Plenum When providing air supply through a large underfloor plenum, the following air velocities guidelines are recommended: SUPPLY AIR VELOCITY – UNDERFLOOR SYSTEM ONLY at face of terminal device† 0.3 m/s to 0.5 m/s or approx. 9 to 12 L/s per seat Distribution duct in plenum (if necessary) 1.3 m/s - 2.5 m/s riser duct outside of plenum 3 m/s to 4.6 m/s depending on location †Note: Velocity through hole in floor slab may be higher than at face of pedestal. Conventional “Top Down” Systems For Performance Spaces If an underfloor air supply system is not desirable, then delivering the air from the ceiling and returning at low level is the other common approach. To deliver air quietly and minimize very low air velocities throughout the system with this approach, it is important to remove the noise-generating obstructions and provide gradual transitions in velocity. For this type of system to operate silently, the duct termination must be free from all obstructions. With no obstructions at the terminal outlet, smooth velocity transitions, and sufficient length of lined ductwork to attenuate turbulence noise, we can allow the velocities to be higher throughout the system. The following air velocity guidelines are recommended for the design of the air distribution systems throughout the facility. ARTEC Project No. 3760 11 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK Table 4 Air Velocity Guidelines Location at terminal outlet to 7 diameters distribution ductwork in room Main header ducts in space maximum outside room In Plantroom Location Inlet condition to 7 diameters distribution ductwork in room Main header ducts in space maximum outside room In Plantroom Guidelines for Supply Air Velocity in fpm (m/s) Design Noise Goal for Space N-1 NR 10 NR 15 NR 20 400 (2.0) 500 (2.5) 550 (2.8) 600 (3.0) 450 (2.25) 550 (2.8) 600 (2.8) 650 (3.3) 600 (3.0) 700 (3.5) 750 (3.8) 800 (4.0) NR 25 650 (3.3) 700 (3.6) 850 (4.25) NR 30 700 (3.5) 750 (3.8) 900 (4.5) 850 (4.25) 850 (4.3) 900 (4.5) 1000 (5.0) 1100 (5.5) 1100 (5.5) 1200 (6.0) 1250 (6.3) 1300 (6.5) 1400 (7.0) 1400 (7.0) 1500 (7.5) 1800 (9.0) 1800 (9.0) NR 25 500 (2.5) 550 (2.8) 800 (4.0) NR 30 600 (3.0) 650 (3.3) 900 (5.0) 1800 (9.0) 1800 (9.0) 1800 (9.0) 1800 (9.0) Guidelines for Return Air Velocity in fpm (m/s) Design Noise Goal for Space N-1 NR 10 NR 15 NR 20 300 (1.5m/s) 350 (1.7) 400 (2.0) 450 (2.3) 350 (1.75) 400 (2.0) 450 (2.3) 500 (2.5) 600 (3.0) 650 (3.3) 700 (3.5) 750 (3.8) 850 (4.3) 850 (4.3) 900 (4.5) 1000 (5.0) 1100 (5.5) 1100 (5.5) 1200 (6.0) 1250 (6.3) 1300 (6.5) 1400 (7.0) 1400 (7.0) 1500 (7.5) 1800 (9.0) 1800 (9.0) 1800 (9.0) 1800 (9.0) 1800 (9.0) 1800 (9.0) Controlling Mechanical Systems Vibration It will be necessary to install mechanical equipment on vibration isolators, since structural discontinuities cannot provide sufficient vibration attenuation at low frequencies. General guidelines for space requirements are discussed in the following sections. Equipment Location and Support All major equipment should be located on grade. When it is necessary to install smaller equipment on elevated levels, it must be positioned near or directly above supporting columns or major beams. Suspended equipment should be supported from beams, joists, or other relatively heavy structural members—members not connected to the structure of the performance space. Please note that it may be necessary to frame between major beams for additional support as it is vital to make the supporting structure as stiff as possible. Locate vibration isolation mounts directly on the building structure where possible. Avoid direct support from lightweight slabs or roof decks, and avoid seating isolation mounts on steel frame sub-structures. Space Requirements Sufficient space is to be provided for mechanical equipment vibration isolation bases: generally 50 mm minimum horizontal clearance between any vibrating equipment and nearby building structure; and generally 50 mm between the underside of a loaded concrete inertia base or structural base and the top of the concrete housekeeping pad or floor slab. ARTEC Project No. 3760 12 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK The vertical requirements for vibration isolator hangers range from 100–300 mm, depending on the size of the unit or pipe. Take isolator dimensions into account when considering piping layout. Housekeeping Pads Provide reinforced concrete housekeeping pads (100 mm thick typically) below all large floorsupported mechanical and electrical equipment. Size this pad to extend beyond the supported mechanical unit plus its vibration isolators. The pads provide local mass and stiffness below mechanical equipment, and prevents debris from accumulating beneath the inertia base, which would short out the isolators. Inertia Bases Spring-supported concrete inertia bases below mechanical equipment units are necessary for the stability of most pumps; for equipment with a high center of gravity or with high unbalanced forces during normal operation or starts and stops; and for some very noisy equipment. Typical applications are large fans, medium to large base-mounted pumps, and air compressors. Inertia bases should be generally 150 mm thick and should weigh one to two times as much as the equipment they support (including any associated piping, fluid, and/or dynamic loads). Specific inertia base requirements will be determined on an individual basis after equipment is selected. Electrical Connections to Mechanical Equipment Electrical connections to all vibration-isolated equipment including pumps, fans, and transformers should be made with flexible conduit installed in a slack “U-shape”. Duct Connections Connect all ductwork to fans, fan casings or fan plenums with flexible sleeves. Pipe Connections Mechanical and plumbing pipes are to be supported on spring-and-neoprene hangers having the same static deflection as the equipment to which the pipes are connected. These hangers are required within the mechanical room. Outside the mechanical plantroom, chilled water/glycol piping smaller than 50 mm should be supported on neoprene hangers or supports. Support piping that is 50 mm and larger on spring and neoprene isolators. Do not hang large diameter chilled water piping from structure common to the performance spaces. Run these large, noisy pipes only in spaces that are inherently noisy i.e. mechanical rooms, garage, and loading dock. Isolators alone do not provide adequate protection against the high vibrational energy in such pipes. Suspend pipes with outside diameters over 13 mm connected to fan coils with spring hangers. This should allow the isolated fan unit to “float” freely on its mounts, avoiding strain on any pipe connections. Use flexible pipe couplings at or near connections to mechanical equipment. Such couplings facilitate pipe alignment as well as providing some isolation. Use flexible couplings where pipes cross vibration joints between separate structures. This applies to all piping except sprinkler pipes. Details of the approach will be developed with the engineers as the design progresses. ARTEC Project No. 3760 13 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK All large pipes connecting the chilled water pumps, the cooling tower, and the chiller must be fully isolated over their entire lengths with combination steel spring/neoprene isolators. Fan Selection Criteria We recommend Class I built-up centrifugal fans with backward-inclined airfoil blades for all noise-critical systems. Selection and final balancing of fans for maximum efficiency is critical, since a fan operating at a higher efficiency will be quieter. Axial and forward-curved centrifugal fans are acceptable in some circumstances. Pump Selection For similar reasons, select and balance centrifugal pumps for maximum efficiency. Low pump efficiency and small impeller-cutwater clearance tend to cause high pump noise and energy transmission to the fluid and piping. Chillers and Cooling Tower Selection To minimize noise, hermetically sealed centrifugal chillers are recommended. Cooling towers must not be mounted on structure that is common to noise-critical spaces. Mounting cooling towers on a grade slab, structurally separate from the rest of the facility is preferred. If the cooling tower is mounted on building structure, large spring isolators must be used. Noise emission to surrounding neighbors will need to be considered, and mitigating measures (enclosures) may be required. ELECTRICAL SYSTEMS CONSIDERATIONS Power Distribution & Transformer Location Since electrical transformers of all sizes and electromechanical transducers are capable of inducing vibration into the supporting structure and generating airborne noise, it is strongly advised to plan for a main electrical equipment room or rooms where all power distribution equipment will be located. This room (or rooms) should be in a part of the facility that is, like the main mechanical equipment room, structurally separate from noise critical spaces. Also, all main electrical equipment should be located on grade. Transformers larger than 45kVA capacity should not be located above grade or suspended. No major or minor transformers should be located outside an isolated mechanical structure. High voltage distribution to multiple step-down transformers within the building is not acoustically acceptable. Dimmer Room Dimmer racks for house and production lighting produce considerable noise and vibration and will need to be located in an acoustically isolated dimmer room. Locate the dimmer room to conserve electrical wiring while ensuring appropriate reduction of noise and vibration. Do not position it directly over, under, or beside noise-critical spaces. Separate rooms housing electrical equipment of this kind from critical spaces by heavy masonry walls, intervening corridors, and storage rooms. If such buffer spaces cannot be properly located, then multiple layers of built-up constructions may be necessary. Do not locate the transformer serving the dimmers in the dimmer room (unless it is in the basement in an isolated structure). Ballasts for Fluorescent Fixtures Fluorescent fixtures may be used for worklights (only) in the performance and connected spaces. Use electronic ballasts for these fixtures. ARTEC Project No. 3760 14 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK Fluorescent fixtures may be used in dedicated rehearsal spaces, but the ballasts for them must be remotely located. In control rooms and observation rooms, fluorescent fixtures may be acceptable with electronic ballasts, or remote ballasts. Low-Noise Dimmers Artec will specify dimmers used with performance lighting, concert lighting, house lighting, and rehearsal room lighting to minimize noise generated by the filaments. House Light fixtures Fluorescent and neon fixtures are unacceptably noisy for house light applications in the performance space. In general, incandescent fixtures connected to high rise-time dimmers will result in acceptably quiet conditions. Cable Routing and Sound Isolation Sound isolating walls can be compromised severely by chases or penetrations for electrical trunking or conduit. Cable routes should not pass directly between noise-critical spaces or from noisy to noise-critical spaces. Many problems can be avoided if the design team carefully consider the cable routes at an early design stage. The cable routes to and from the dimmer room must be considered with particular care. Emergency Power Do not locate contactors for emergency lighting fixtures in noise-critical spaces. Such relays are normally on and can generate disturbing hum. Exit signs in performance and rehearsal spaces should not contain relays, transformers or contactors, and must not be fluorescent. Incandescent line-voltage fixtures are acceptable. Low voltage fixtures may be acceptable if all are fed by transformers located outside of the noise-critical space. Aisle Lights We recommend incandescent line-voltage fixtures. Low voltage fixtures may be acceptable if fed by transformers located outside of the noise-critical space. ELEVATOR/ESCALATOR NOISE AND VIBRATION Wherever possible, hydraulic elevators should be used as they operate quieter than their traction drive equivalent. Electric traction drive elevator machines impart transient vibrations to the structure, which must then be isolated from surrounding structure, whereas hydraulic equipment can be supported on vibration isolators: Locate machine rooms on grade. Walls of equipment room should achieve minimum Rw’ = 55 dB to surrounding areas. If the elevator machine room is on structure that is common with any noise-critical space, the floor slab must be isolated from the surrounding structure. The equipment room floor slab should be isolated from the walls and footings by a 50 mm wide acoustical expansion joint. For electrical elevators, since the floor cannot be tied into the building structure, the weight of the floor slab itself must counterbalance the weight of the cab, the load, and the counterweight. This must be addressed in the structural/architectural design. ARTEC Project No. 3760 15 ARTEC CON ICELANDIC NATIONAL CONCERT & CONFERENCE CENTRE IN REYKJAVÍK Mount motor generators and other equipment on vibration isolators. Pipe and conduit penetrations in the equipment room should be sleeved, packed and caulked as with other penetrations of noise-critical walls. Use manufacturer's standard polyurethane roller guides on the cab guide system to reduce noise generated by cab movement. For electrical elevators, isolate the head sheave from shaft structure with 2-direction isolators. Artec will suggest a guideline detail, if necessary. Make room in the basement for elevator machine rooms, and plan for underslung and/or hydraulic equipment in the budget. Artec will advise on particular acoustical details later in the project. OTHER NOISE SOURCES Interior activities such as kitchen commotion, set-ups for catered events, scenery handling, and scenery construction can be significant sources of noise. Consideration must be given to the locations and logistics of these activities so that they will not negatively impact the noisecritical spaces. ARTEC Project No. 3760 16 ARTEC CON