2.2 system concept basic requirements

advertisement
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
TABLE OF CONTENTS
1.
INTRODUCTION ......................................................................................................... 3
2.
SYSTEM OVERVIEW ................................................................................................... 4
2.1 LIELVARDE AFB TOTAL SYSTEMS CONCEPT .................................................................. 4
2.1.1
GENERAL ............................................................................................................... 4
2.1.2
SYSTEMS FOR LIELVARDE ...................................................................................... 4
2.2 SYSTEM CONCEPT BASIC REQUIREMENTS ................................................................... 5
2.2.1
NAVIGATION SYSTEM ........................................................................................... 5
2.2.2
COMMUNICATIONS SYSTEM ................................................................................ 5
3.
SERVICES................................................................................................................. 13
3.1 INSTALLATIONS AND TRANSITION OPERATIONAL IMPACT ........................................13
3.1.1
General ...............................................................................................................13
3.2 TRAINING ...................................................................................................................13
3.2.1
Introduction ........................................................................................................13
3.2.2
General ...............................................................................................................14
3.2.3
Training Documentation .....................................................................................14
3.2.4
Training Facilities and Equipment.......................................................................15
3.2.5
Training of Operational Personnel ......................................................................15
3.2.6
Training of Maintenance Personnel....................................................................15
3.2.7
Proposal from the Bidder ....................................................................................16
3.3 QUALITY ASSURANCE .................................................................................................17
3.3.1
General Requirements ........................................................................................17
3.3.2
Quality Control and Verification .........................................................................17
3.4 ACCEPTANCE TESTING ...............................................................................................19
3.4.1
Factory Acceptance Test (FAT)............................................................................19
3.4.2
Site Acceptance Test (SAT) ..................................................................................19
3.4.3
Factory Acceptance Test (FAT)............................................................................19
3.4.4
Site Acceptance Test (SAT) ..................................................................................20
3.5 WARRANTY ................................................................................................................22
3.5.1
General ...............................................................................................................22
3.6 SPARES .......................................................................................................................23
3.6.1
Initial Spares .......................................................................................................23
3.6.2
Sparing Level .......................................................................................................23
3.6.3
Description of Spares ..........................................................................................23
3.6.4
Spares List ...........................................................................................................23
3.6.5
Guarantees .........................................................................................................23
3.7 DOCUMENTATION .....................................................................................................23
3.7.1
General ...............................................................................................................23
3.7.2
Hardware documentation...................................................................................24
3.7.3
Software documentation ....................................................................................25
533576394
07.03.16
Page 1
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.7.4
Miscellaneous documentation ............................................................................25
3.8 HARDWARE AND SOFTWARE REQUIREMENTS ..........................................................26
3.8.1
Software Requirements ......................................................................................26
3.8.2
Hardware Requirements .....................................................................................26
3.9 CIVIL WORKS ..............................................................................................................28
3.9.1
General Requirements ........................................................................................28
3.10 MAINTENANCE REQUIREMENTS ................................................................................28
3.10.1 General ...............................................................................................................28
3.10.2 System design Consideration ..............................................................................28
3.10.3 Maintenance Operation......................................................................................29
3.10.4 Preventive Maintenance .....................................................................................30
3.10.5 Corrective Maintenance......................................................................................30
3.10.6 Maintenance Support .........................................................................................31
533576394
07.03.16
Page 2
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
1.
INTRODUCTION
This document sets forth the operational and technical requirement
specifications for a national Communications, Navigation, and Air Traffic
Management (CNS/ATM) system for the modernization of Lielvarde Air Force
Base (AFB) project. These requirements are mandatory and must be adhered to
by the Bidder. Any significant noncompliance with this fundamental
requirement would result in disqualification from further consideration.
The overall objective of the Lielvarde AFB CNS/ATM/MET system is to provide
the Latvian Air Force (LAF) inter-operability with NATO. Therefore, compliance
with applicable ICAO and NATO standards is mandatory.
The systems proposed must be of modern design, demonstrable and whose
operation has been field-proven in a NATO-member country in Europe. The
Bidder must have upgraded at least three airports in NATO-member countries
essentially to the level specified in this document.
Where possible, the total system will be based on modern, high quality,
commercial off-the-shelf (COTS) technology.
The Bidder will provide a detailed compliance matrix identifying full compliance,
partial compliance (with explanation) or non-compliance based on
requirements identified within this tender document and the attached
specifications.
533576394
07.03.16
Page 3
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.
SYSTEM OVERVIEW
2.1
LIELVARDE AFB TOTAL SYSTEMS CONCEPT
2.1.1
GENERAL
2.1.1.1
The following diagram shows the total CNS/MET System concept for the
modernization of Lielvarde AFB project.
TOWER
VCCS
Printer
AWOS Display
MET OFFICE
Receivers
Site
AWOS Workstation
Transmitters
Site
AWOS Workstation
TECHNICAL HALL
Radio COM
GPS Clock
RCMS
AWOS
AWOS
System
VCCS
System
RCMS
Field Equipment
RCMS(s)
Maintenance
WS
Maintenance
WS
D-VORTAC
Recorder
System
ILS
Lielvarde AFB – Total CNS/ATM/MET System Concept Block Diagram
2.1.1.2
The overall concept for Lielvarde as depicted in the Overall System Diagram
above is based on a requirement for a fully integrated military Communications,
Navigation, Meteorological, such that Lielvarde can operate autonomously as
well as in harmony with adjacent military and civil aviation authorities.
2.1.2
SYSTEMS FOR LIELVARDE
2.1.2.1
The overall Lielvarde systems concept is as follows:
2.1.2.1.1
The Navigation System will consist of ICAO and NATO compliant Instrument
Landing System, and area navigation systems such as military Tactical Air
Navigation (D-VORTAC);
2.1.2.1.2
The Communications System will consist of HF, VHF and UHF air-ground and
ground-ground radios, voice communications and control system (VCCS) and
ground-ground communications systems to inter-link all the CNS assets to the
Command and Control Center offices in Lielvarde AFB;
533576394
07.03.16
Page 4
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.1.2.1.3
The Meteorological System will consist of an Automatic Weather Observation
System, which will provide current weather observation parameters in
automatic mode, including: wind direction and wind speed, aeronautical
visibility and Runway Visual Range (RVR), height of the cloud base and cloud
amount, some present weather phenomena, atmospheric pressure (QNH, QFE),
temperature and relative humidity (dew point temperature). It will allow
incorporating of visual observations into automated reports, to provide system
operator with complete weather observation data set.
2.2
SYSTEM CONCEPT BASIC REQUIREMENTS
2.2.1
NAVIGATION SYSTEM
2.2.1.1
The Lielvarde AFB navigation system will consist of the following subsystems:
2.2.1.1.1
Cat III ILS Localizer;
2.2.1.1.2
Cat III ILS Glidepath;
2.2.1.1.3
DME;
2.2.1.1.4
Tactical Air Navigation (D-VORTAC).
Refer to Attachment 2 for the detailed Requirement Specifications for the ILS System.
Refer to Attachment 3 for the detailed Requirement Specifications for the DME System.
Refer to Attachment 8 for the detailed Requirement Specifications for the D-VORTAC System.
2.2.2
COMMUNICATIONS SYSTEM
2.2.2.1
The Communication System shall include the following two subsystems:
2.2.2.1.1
Air Traffic Control Tower Communications System
2.2.2.1.2
Communications Information System (CIS)
2.2.2.2
2.2.2.2 Air Traffic Control Tower Communications System
2.2.2.2.1
2.2.2.2.1 The Air Traffic Control Tower (ATC-T) Communications System shall
consist of the following subsystems:
2.2.2.2.1.1 Voice Communication Control System (VCCS);
2.2.2.2.1.2 VHF/UHF Radios (transceivers and receivers);
2.2.2.2.1.3 Voice Logging Recorder System;
2.2.2.2.1.4 GPS Clock System;
2.2.2.2.1.5 Airfield Remote Control and Monitoring System.
The Requirement Specifications for the VCCS are detailed in the Attachment 4
2.2.2.2.2
The following operator workplaces shall be designed and provided:
2.2.2.2.2.1 ATC-T Tower Control
2.2.2.2.2.2 ATC-T Ground Control
2.2.2.2.2.3 ATC-T Auxiliary Position
533576394
07.03.16
Page 5
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.2.2.2.2.4 Approach Control Operator 1
2.2.2.2.2.5 Approach Control Operator 2 (combined with Supervisor)
2.2.2.2.2.6 Technical Maintenance
2.2.2.2.3
The Bidder shall provide three (3) ATC consoles, two (2) APP consoles and one
(1) Technical Maintenance console.
2.2.2.2.4
The design of the consoles shall provide flexible, ergonomic and efficient
operation that eliminate distractions and allow controllers to focus strictly on
the decisions of the moment. For the ATC-T, the consoles shall be designed to
provide the best possible view from a working position towards the outside of
the airfield.
2.2.2.2.5
The consoles shall be provided with the following features:
2.2.2.2.5.1 Internal 19”rack cabinets for mounting equipment
2.2.2.2.5.2 Aluminum rail systems for mounting displays on flexible arms
2.2.2.2.5.3 Vent panels
2.2.2.2.5.4 Removable panels
2.2.2.2.5.5 Individual power distribution system for each cabinet
2.2.2.2.6
Under table rails shall permit mounting of the following equipment accessories:
2.2.2.2.6.1 Jack panels
2.2.2.2.6.2 Microphones
2.2.2.2.6.3 Handsets
2.2.2.2.6.4 Headset plugs
2.2.2.2.6.5 Flight strip tray holders
The Requirement Specifications for the VHF/UHF Radios are detailed in the Attachment 5
2.2.2.2.7
The following radios are requested for the ATC-T:
2.2.2.2.7.1 Five (5) main/standby VHF-UHF transmitters
2.2.2.2.7.2 Five (5) main/standby VHF-UHF receivers
2.2.2.2.7.3 One (1) emergency VHF-UHF transceiver with independent power backup.
2.2.2.2.8
The requested RF filters, antenna, lightning protection, feeders, antenna
towers, and installation materials shall be provided, as a turn-key solution.
2.2.2.2.9
The VHF-UHF transmitters and receivers shall be provided with remote control
and maintenance monitoring system and network management system.
2.2.2.2.10
The detailed Requirement Specifications for the Voice Logging Recorder
System are as follows:
2.2.2.2.10.1 The Voice Logging Recorder shall have the capability to cover all the radio,
telephone and inter operator communications. The recording capability shall be
redundant.
533576394
07.03.16
Page 6
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.2.2.2.10.2 The minimum number of channels installed at the VCCS site shall be forty-eight
(48). Additional recorders with minimum 16 channels shall be available for other
locations upon request.
2.2.2.2.10.3 As a minimum the following features shall be provided:
2.2.2.2.10.3.1 Accurate recording and archiving of calls / radio communications
2.2.2.2.10.3.2 Quick and easy call retrieval
2.2.2.2.10.3.3 Immediate reproduction and availability of the last recorded call
2.2.2.2.10.3.4 Playback without interruption of ongoing recording
2.2.2.2.10.3.5 Reliable archiving of calls on a variety of storage media (HD, DVD, etc.)
2.2.2.2.10.3.6 On-line monitoring
2.2.2.2.10.3.7 Networking capability
2.2.2.2.10.3.8 Expandability
The Requirement Specifications for the Recorder system are detailed in the Attachment 7.
2.2.2.2.11
The detailed Requirement Specifications for the GPS Clock System are as
follows:
2.2.2.2.11.1 The GPS Clock System shall be designed and built to meet or exceed all
specifications recommended in the NENA (National Emergency Number
Association) PSAP (Public Safety Answering Point) Master Clock Standard
(NENA-04-002).
2.2.2.2.11.2 GPS Clock System shall allow other equipment designed to meet NENA
specifications to be synchronized to the time information as received from the
GPS satellites.
2.2.2.2.11.3 The Master Clock shall receive legally traceable time and date information from
Global Positioning System satellites and shall supply UTC (Coordinated
Universal Time) synchronized data to the ATC-T systems in a variety of forms. A
twelve-channel receiver shall be employed, which is capable of tracking up to
twelve (12) satellites simultaneously, although reception of only one is required
for accurate time data to be output.
2.2.2.2.11.4 The Bidder shall be responsible for the provision of the required interfaces for
the following systems:
2.2.2.2.11.4.1 VCCS
2.2.2.2.11.4.2 Voice Logging Recorder
2.2.2.2.11.4.3 RDPS/FDPS
2.2.2.2.11.4.4 Analogue/Digital clocks (minimum 10 interfaces)
2.2.2.2.12
533576394
07.03.16
The Requirement Specifications for the Airfield Remote Control and
Monitoring System are as follows:
Page 7
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.2.2.2.12.1 The RCMS shall provide the remote monitoring and control of the entire
CNS/MET system assets at Lielvarde. The Bidder shall propose his concept such
that the total system can be monitored from a central location.
2.2.2.2.12.2 Both equipment (CNS/MET) and site (Localizer, Glide Path, D-VORTAC, MET)
control and maintenance monitoring information shall be included.
2.2.2.2.12.3 The site monitoring shall consist of, but not limited to the following features:
2.2.2.2.12.3.1 Temperature monitoring
2.2.2.2.12.3.2 Smoke alarm monitoring
2.2.2.2.12.3.3 AC power availability
2.2.2.2.12.3.4 Backup generator on
2.2.2.2.12.3.5 Backup generator alarm
2.2.2.2.12.3.6 Backup generator low fuel
2.2.2.2.12.3.7 Open door alarm
2.2.2.2.12.4 The RCMS shall have the capability of central supervision of the operational
status of all the ground based aviation system elements used by the facility. Its
main purpose is to provide the Air Traffic Management operators with a
comprehensive graphic representation of the equipment interfacing the
system’s alarm conditions.
2.2.2.2.12.5 The RCMS shall be specifically customized for the equipment installed at a given
location. The Graphical User Interface (GUI) shall make the operation of the
software intuitive and interactive.
2.2.2.3
Communications Information System (CIS)
2.2.2.3.1
General Description
2.2.2.3.1.1 The configuration of the Communication Information System is specific for each
type of operational environment. Basically the CIS shall provide:
2.2.2.3.1.1.1 Continuous communication-information service to the airport personnel;
2.2.2.3.1.1.2 Links to the communication-information networks of the civilian/military aviation
infrastructure;
2.2.2.3.1.1.3 Technical support for the Automated Information System;
2.2.2.3.1.2 The Communication Information System consists of the following subsystems:
2.2.2.3.1.2.1 Communications Information Center (CIC)
2.2.2.3.1.2.2 Automated Information System (AIS)
2.2.2.3.1.2.3 Telephone Centre (PABX network)
2.2.2.3.1.2.4 Ground – Air – Ground Communications, including
533576394
07.03.16
Page 8
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.2.2.3.1.2.4.1
HF-VHF-UHF Transmitting Center
2.2.2.3.1.2.4.2
HF-VHF-UHF Receiving Center
2.2.2.3.1.2.5 Remote Ground – Air VHF Radio Communications
2.2.2.3.1.2.6 Network equipment (modems, …) to transmit signals from field equipment over
redundant Fiber Optic communications backbone (main) and copper communication
backbone (standby)
2.2.2.3.1.2.7 Local Area Network (LAN) for connecting the CIC and AIS workstations to public and/or
private networks
2.2.2.3.1.2.8 Fiber Optic / Copper Cable / Wireless infrastructure for interconnecting different sites
of the airport to the backbone (e.g. Radio Navigation and Surveillance sites to the
backbone, Radio Transmitting Center and/or Receiving Center to the backbone,
Meteorological System sites to the backbone, local telephone extensions to the PABX,
internal interconnections of the systems at control tower)
2.2.2.3.2
Prerequisites
2.2.2.3.2.1 The CIS will be the responsibility of the bidder to describe in detail in his
proposal after conducting a mandatory site survey. During the site survey, the
Buyer will provide the bidders the opportunity to visit all the locations involved
in this project and their roles. The Buyer will advise all the bidders about the
dates for the Site Surveys.
The Requirement Specifications for the Site Surveys detailed in the Attachment 1.
2.2.2.3.2.2 The Communications Information Center (CIC) shall be equipped with top of the
line Commercial-On-The-Shelf (COTS) workstations, based on specificē
operational configuration.
2.2.2.3.2.3 The standard software shall consist exclusively of the following items:
2.2.2.3.2.3.1 MS Windows Professional (latest edition)
2.2.2.3.2.3.2 MS Office Standard (latest edition)
2.2.2.3.2.3.3 Antivirus software (latest edition)
2.2.2.3.2.4 The Automated Information System (AIS) is an infrastructure that provides
access to information, and means for information processing, storing,
displaying, transferring, and broadcasting. The AIS is structured so that two
different types of networks are available, and completely independent:
2.2.2.3.2.4.1 Private Network (Intranet)
2.2.2.3.2.4.2 Public Network (internet)
2.2.2.3.2.5 AIS shall be equipped with top of the line COTS servers, workstations, switching
and routing equipment based on specific operational configuration.
2.2.2.3.2.6 The standard software shall consist exclusively of the following items:
533576394
07.03.16
Page 9
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.2.2.3.2.6.1 MS Windows Professional (latest edition)
2.2.2.3.2.6.2 MS Office Standard (latest edition)
2.2.2.3.2.6.3 Antivirus software (latest edition)
2.2.2.3.2.7 The Telephone Center consists of a PABX network and corresponding
infrastructure.
2.2.2.3.2.8 The PABX specifications shall be based on the end user provided information
regarding the type and number of trunks, type and number of telephone sets
for extensions, type and number of attendants, number of the nodes within the
network.
2.2.2.3.2.9 The PABX shall be provided with administration terminal(s) based on the
specific project configuration.
2.2.2.3.2.10 The Ground – Air – Ground Communication System is installed in the HFVHFUHF Transmitting Center and HF-VHF-UHF Receiving Center.
2.2.2.3.2.11 The following radios are requested for the Transmitting Center:
2.2.2.3.2.11.1 Two (2) HF Transmitters 125W
2.2.2.3.2.11.2 Two (2) HF Transmitters 500W
2.2.2.3.2.11.3 Five (5) VHF-UHF Transmitters
2.2.2.3.2.12 The following radios are requested for the Receiving Center:
2.2.2.3.2.12.1 Four (4) HF Receivers
2.2.2.3.2.12.2 Five (5) VHF-UHF Receivers
2.2.2.3.2.13 The requested RF filters, antennae, lightning protection, feeders, antena
towers, and installation materials shall be provided, as a turn-key solution.
2.2.2.3.2.14 The VHF-UHF transmitters and receivers shall be provided with remote control
and maintenance monitoring system and network management system.
2.2.2.3.2.15 The radios shall be operated from the VCCS installed in the ATC-T.
The Requirement Specifications for the VHF/UHF Radios are detailed in the Attachment 5.
The Requirement Specifications for the HF Radios are detailed in the Attachment 6.
2.2.2.3.2.16 The Remote Ground – Air Communications (also known as Extended Range VHF
Radio System) is subject of separate specifications.
2.2.2.3.2.17 High capacity communications backbone shall provide the requested links to
the communication-information networks of the civilian/military aviation
infrastructure (e.g. other airports, aviation headquarters, Command and
Control Center, remote ground – air communication system, Air Sovereignty
Operative Center – ASOC, etc.).
2.2.2.3.2.18 A communication backbone to be interconnect all the CNS/MET system
together using modern, high capacity data links (fiber optic, microwave, etc.).
533576394
07.03.16
Page 10
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.2.2.3.2.19 The Bidder shall propose a total communication backbone after conducting a
detailed site survey.
2.2.2.3.2.20 The Fiber Optic infrastructure shall be built with sufficient number of SM (Single
Mode) fiber cables, installed underground in HDPE pipes (one spare pipe to be
included for further development).
2.2.2.3.2.21 The precise number of FO cables shall be determined during the site surveys.
2.2.2.3.2.22 The spare FO cables shall be installed.
2.2.2.3.2.23 The fiber optical cable shall be terminated in Optical Distribution Frames (ODF).
The distribution to the fiber optic line units shall be made with fiber-optic patch
cords.
2.2.2.3.2.24 Each no systems defined above (MW communications, FO terminals and
multiplexors) shall be equipped with remote control terminals, which are
necessary for system administration and remote monitoring.
2.2.2.3.2.25 The Local Area Network (LAN) shall be based on the Ethernet protocol
(IEEE 802.X). The network topology shall be star, with number of nodes and
ports for each node (be defined during the site survey). The central node shall
be assigned to the CIC building.
2.2.2.3.2.26 The links between the nodes shall be provided with fiber optic cables. The fiber
optic infrastructure shall be built with fiber cables, installed underground in
HDPE pipes (one spare pipe to be included for further development).
2.2.2.3.2.27 The fiber optical cable shall be terminated in Optical Distribution Frames (ODF).
The distribution to the fiber optic line units shall be made with fiber-optic patch
cords.
2.2.2.3.2.28 The proper LAN routing equipment shall be used based on the network size.
2.2.2.3.2.29 The Fiber Optic / Copper Cable / Wireless infrastructure consists of the required
cables, distribution frames, and/or communications equipment.
2.2.2.3.2.30 The technology for the PABX distribution network shall be copper pair cables.
2.2.2.3.2.31 The copper pair cables shall be terminated in Main Distribution Frames (MDF)
installed at the entrance in each building. The entrance in the building shall be
properly protected against lightning. The internal distribution to the central
equipment and extension sets shall be made with copper-pair patch cords.
2.2.2.3.2.32 All the other communications between different sites of the airport shall be
made with either fiber optic cables, or wireless transceivers.
2.2.2.3.2.33 In case of fiber optic cables, the fiber optic infrastructure shall be built with
fiber cables, installed underground in HDPE pipes (one spare pipe to be
included for further development). The fiber optical cable shall be terminated in
Optical Distribution Frames (ODF). The distribution to the fiber optic equipment
shall be made with fiber-optic patch cords.
2.2.2.3.2.34 In case of wireless communications between sites, the equipment shall consist
of spread spectrum transceivers, using the frequency hopping spread
technology.
2.2.2.3.2.35 The transceivers shall be capable of uncompressed data rates at high speed
over distances of 20 miles or more.
533576394
07.03.16
Page 11
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
2.2.2.3.2.36 The transceivers shall be able to operate point to point or point to multipoint,
mode selectable using an asynchronous terminal program. Up to two repeaters
may be used to extend the range by programming the transceiver to operate as
a store and forward unit, in order to reach distances of 60 miles, or more.
533576394
07.03.16
Page 12
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.
SERVICES
3.1
INSTALLATIONS AND TRANSITION OPERATIONAL IMPACT
3.1.1
General
3.1.1.1
Within about 2(two) weeks of the issuing of the Tender, the Contracting
Authority shall hold a Bidder’s Meeting in Latvia at which time the Buyer shall
brief the Bidder on the LAF Communication concept.
3.1.1.2
Visits of their approximate locations all the relevant LAF CNS assets associated
the Lielvarde project will be facilitated, where the Bidders can conduct detailed
site survey.
3.1.1.3
The Bidders shall submit as a part of their proposals, detailed communication
system to interconnect all the CNS assets within the AirForce Base and to with
other agencies.
3.1.1.4
The Bidder shall perform an in-depth Site Survey within thirty days of Contract
award. Detail drawings along with engineering reports of each site will be given
to the Buyer within 60 days.
3.1.1.5
The Bidder shall propose a Detailed Site Installation Plan that will identify
detailed equipment configuration for each system and describe in details all
areas of work needed to fully install the total system and recommend transition
hardware placement and configuration.
Refer to Attachment 1 for the detailed Requirement Specifications for the Site Surveys.
3.2
TRAINING
3.2.1
Introduction
3.2.1.1
The Bidder shall propose a comprehensive training package as described below:
3.2.1.1.1
System Maintenance (hardware/software) training for 10 electronic technicians
for Navigation and Communication systems and associated subsystems.
3.2.1.1.2
Supervisory training for 10 senior supervisory staff.
533576394
07.03.16
Page 13
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.2.1.2
Training documentation requirements are included here.
3.2.1.3
Detailed training programs for the technical personnel shall be negotiated
3.2.2
General
3.2.2.1
Syllabus, lesson’s plans and lecture notes (handouts) shall be provided for the
each training course.
3.2.2.2
The Training shall be provided separately for every system/equipment, if it was
not specially defined.
3.2.2.3
To ensure efficient training, it is essential that a high standard of
documentation is provided.
3.2.2.4
The documentation shall be in the English (or Latvian) language, provide all
information required, and be presented in a clear, and concise format.
3.2.2.5
All training courses shall:
3.2.2.5.1
be conducted in the English (or Latvian) language;
3.2.2.5.2
involve theoretical and practical training;
3.2.2.5.3
provide simulation of faults;
3.2.2.5.4
use documentation provided for the each system.
3.2.2.6
After training course the Bidder shall give a document (Certificate) which
confirms training completion.
3.2.3
Training Documentation
3.2.3.1
In case final training documentation is not available at the beginning of the
training, preliminary versions of both the information and instructional
documents shall be provided.
3.2.3.2
Descriptions and detailed data included in the documentation shall comply with
the characteristics of the delivered equipment as closely as possible.
3.2.3.3
Any advertising or sales promoting material shall not be included in the training
material.
3.2.3.4
The Bidder shall:
3.2.3.4.1
deliver to the Buyer detailed course programs and documentation at least 1
month before the beginning of the course;
3.2.3.4.2
provide each participant with a complete set of course material at the
beginning of the course;
3.2.3.4.3
at the end of the course deliver a complete set of instructor's training material
(presentations, transparences, films, video tapes etc.) to the Buyer.
533576394
07.03.16
Page 14
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.2.4
Training Facilities and Equipment
3.2.4.1
When training takes place at the Bidder´s factory/training center suitable
classrooms and laboratory facilities shall be provided.
3.2.4.2
Students shall have access to rest areas, and the Bidder shall arrange for
accommodation, transportation, first aid service, etc.
3.2.4.3
All test equipment used under training shall be of the same kind as Contracted.
3.2.4.4
Maintenance of training test equipment is the Bidder´s responsibility.
3.2.5
Training of Operational Personnel
3.2.5.1
Under the Contract, system-related training for operational personnel shall be
provided.
3.2.5.2
The Bidder shall provide the training after the project has been defined and
documented in the Product Specification and prior to, but as close as possible
to the FAT starting date
3.2.5.3
The training course shall include:
3.2.5.3.1
general course on system hardware;
3.2.5.3.2
detailed course on rules of the system operating;
3.2.5.3.3
documentation on the system operation.
3.2.5.4
At the completion of the course each participant shall have:
3.2.5.4.1
clear overview of the system;
3.2.5.4.2
knowledge of the functional design and operation of the system;
3.2.5.4.3
detailed knowledge of operational functions, input functions and their results,
etc. enabling to operate the work station equipment in accordance with the
designer's requirements.
3.2.5.5
This shall include to:
3.2.5.5.1
carry out all the functional operations envisaged by the specifications;
3.2.5.5.2
select any configuration of the system and to be able to accomplish
reconfiguration of the system;
3.2.5.5.3
to operate the workstation equipment in accordance with the designer's
requirements.
3.2.6
Training of Maintenance Personnel
3.2.6.1
Under the Contract, system-related training shall be provided for maintenance
personnel and system engineers.
3.2.6.2
The Bidder shall provide the training after the project has been defined and
documented in the Product Specification and prior to, but as close as possible
to the FAT starting date
3.2.6.3
The training course shall include:
3.2.6.3.1
detailed system hardware course;
3.2.6.3.2
system operating course;
533576394
07.03.16
Page 15
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.2.6.3.3
installation, maintenance and technical parameter changes.
3.2.6.4
At the completion of the course each participant shall have:
3.2.6.4.1
clear overview of the complete system;
3.2.6.4.2
a sound understanding of individual sub-systems;
3.2.6.4.3
knowledge of the functional design and operation of the system down to board
level;
3.2.6.4.4
detailed knowledge of operational functions, input functions and their results,
etc. enabling the operation of all sub-systems and work station equipment;
3.2.6.4.5
detailed knowledge of how to perform preventive and corrective maintenance.
3.2.6.5
This shall include to:
3.2.6.5.1
check performance parameters;
3.2.6.5.2
interpret fault conditions;
3.2.6.5.3
select and apply maintenance aids such as fault finding procedures, test
programs, control and monitoring test equipment;
3.2.6.5.4
carry out adjustments allowable for maintenance personnel;
3.2.6.5.5
perform necessary restoration of service.
3.2.7
Proposal from the Bidder
3.2.7.1
The Bidder shall, based on the guidelines given above, compose an adapted
technical training course program.
3.2.7.2
Each course shall have a description, duration, location and an allowed
maximum number of participants.
3.2.7.3
The Bidder shall state the price for each of the courses in his proposal which
shall also form a part of the Contract.
3.2.7.4
When training takes place at the Contractor´s factory/training center travel
cost, accommodation and daily expenses for trainees shall be provided by the
Contractor.
533576394
07.03.16
Page 16
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.3
QUALITY ASSURANCE
3.3.1
General Requirements
3.3.1.1
The Bidder shall provide its Quality Assurance Plan to the Buyer. The QAP shall
conform to the following guidelines
3.3.1.2
Quality System Requirements
3.3.1.2.1
To prevent nonconformity at all stages of the project, Bidder shall have
established a quality system in accordance with the requirements in the
document: STANDARD ISO 9000 SERIES (the latest version available, but not
lower than ISO9001:2008).
3.3.1.2.2
If the Bidder uses a standard other than stated above compliance with it shall be
stated in the compliance table and a correspondence with the ISO 9000 series
standards shall be stated.
3.3.1.2.3
All of the offered equipment shall be produced in accordance with the
European Union Directives to obtain the CE symbol (including the standards for
electromagnetic compliance (EMC) as well as the safety regulations, which
ensure the protection of personnel and equipment).
3.3.2
Quality Control and Verification
3.3.2.1
Introduction
3.3.2.1.1
Although the objective of the prescribed quality system is to prevent
nonconformity to materialize, verification shall be an important activity.
3.3.2.1.2
The verification activities shall be an on-going process that extends from the
conception of the system up to and including its acceptance by the Buyer.
3.3.2.1.3
The verification process shall include design reviews, inspections, and relevant
tests. As the realization of the system progresses, tests shall be performed at
increasingly higher levels of items. Test procedures shall be worked out for
assemblies, units, sub-systems and other equipment.
3.3.2.2
Design Reviews
3.3.2.2.1
Design reviews shall be held at appropriate points in the design and
development phase in order to verify compliance with the requirements in the
Specification.
3.3.2.2.2
Completion of the design reviews shall result in the release of preliminary
acceptance test procedures.
3.3.2.2.3
Design reviews shall be performed by the Bidders own organization.
3.3.2.2.4
Preliminary acceptance test procedures shall be made available to the Buyer.
3.3.2.3
Quality Inspection
3.3.2.3.1
The Bidder shall have the full responsibility for a proper and thorough
supervision of the manufacturing process.
533576394
07.03.16
Page 17
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.3.2.3.2
The Bidder shall have full responsibility for quality of the equipment under the
Contract even if the Buyer has made use of his right to verify the manufacturing
process through inspection activities.
3.3.2.3.3
The Buyer's representative shall be given complete insight in the Bidder's and
any Sub-Supplier's manufacturing and QA activities.
3.3.2.3.4
Should the Buyer's representative so wish, he shall be entitled to carry out his
own verification tests and reviews. In such cases he shall be given full assistance
from the Bidder's staff.
3.3.2.3.5
All approvals shall be in written form and signed by the Buyer's Project
Manager or his authorized representative.
3.3.2.4
Testing
3.3.2.4.1
A formal stability verification test before commissioning of the contracted
equipment is part of the Buyer's requirements.
3.3.2.4.2
The objective of the Buyer's testing requirements is a full verification that the
equipment, when completed and installed on site, meets the contractual
specifications, as laid down in the Specification.
3.3.2.4.3
Tests are divided into two categories:
3.3.2.4.3.1 production tests, which shall be performed by the Bidder in order to verify
compliance to specifications of items at lower levels;
3.3.2.4.3.2 acceptance tests, which shall be performed by the Bidder in order to verify
compliance to specifications of items at lower levels.
3.3.2.4.4
Acceptance tests shall be performed on items at sub-system level and higher, in
order to demonstrate that the item concerned meets the specified functional
performance.
3.3.2.4.5
The Buyer shall be prepared to accept such tests being applied to units if the
performance or capabilities of such units cannot be demonstrated properly
under higher level tests, or if testing of units will give a better verification of
compliance.
3.3.2.4.6
Acceptance tests are of important significance for the Buyer. Every acceptance
test shall be performed in the presence of the Buyer, who will sign the
acceptance documentation upon successful completion of the tests.
3.3.2.4.7
All Acceptance tests shall be further divided into 2 categories:
3.3.2.4.7.1 Factory Acceptance Tests (FAT)
3.3.2.4.7.2 Site Acceptance Tests (SAT).
533576394
07.03.16
Page 18
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.4
ACCEPTANCE TESTING
3.4.1
Factory Acceptance Test (FAT)
3.4.1.1
Before the actual Factory Acceptance test a full-scale internal preliminary test
shall be arranged according to the specification. The Buyer reserves the right to
attend this test as an observer. The Bidder shall notice in due time the start of
this preliminary test, however not later than one month in advance.
3.4.1.2
FAT is a test in the Bidder's facilities, which is conducted in accordance with the
agreed FAT specification.
3.4.1.3
The Buyer shall be entitled to witness the test and shall be notified about the
FAT in due time (at least 3 months in advance). Upon successful completion of
the FAT the Buyer will sign the test protocol.
3.4.2
Site Acceptance Test (SAT)
3.4.2.1
A test at the Buyer's premises which is conducted in accordance with the
agreed SAT specification. The Buyer shall witness the test and will sign the test
protocol upon successful completion of the test.
3.4.3
Factory Acceptance Test (FAT)
3.4.3.1
A selection of the required documentation shall be approved by the Buyer, as
indicated below. The following documentation is relevant for the FAT:
3.4.3.1.1
TEST PLAN, which shall contain the general conditions and definitions, a test
work flow which defines the test sequence and identifies the related test
specifications and test procedures, and a general description of the tests. The
Test Plan shall be worked out by the Bidder and shall be made available for the
Buyer for review and approval latest three months prior to the expected start
of the FAT.
3.4.3.1.2
TEST SPECIFICATION, which shall include detailed descriptions of the various
tests and also include criteria for acceptance/rejection, conditions and
interfaces. In addition, requirements for test provisions such as test tools, test
equipment and test software shall be included. The Test Specification shall be
worked out by the Bidder and sent, together with the Test Plan, to the Buyer
for review latest two months prior to the expected start of the FAT.
3.4.3.1.3
CERTIFICATION RECORD, which shall indicate the type of test, the items tested
and test result, including possible remarks. After completion of each
acceptance test an equipment certification record shall be filled in. Remarks
may include agreed deviations from the test procedure. The Certification
Record shall be the formal document for recording of approval of the relevant
test. Both the Employer and the Supplier shall sign the Certification Record.
3.4.3.1.4
LIST OF DELIVERY. The list of delivery shall contain information about the
configuration of the equipment down to sub-assembly level.
533576394
07.03.16
Page 19
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.4.3.2
The Bidder shall accomplish the agreed Factory Acceptance Test (FAT) program
in the presence of the Buyer's appointed representatives.
3.4.3.3
The FAT shall be run to verify whether the equipment, before delivery, satisfies
the functional requirements and technical specifications defined in the
Contract.
3.4.3.4
It is accepted that factory acceptance tests are performed under the
environmental conditions that prevail in the Bidder's test department at the
time of the test.
3.4.3.5
The FAT shall be performed following the Test Plan, successively checking the
items for compliance with the Test Specification.
3.4.3.6
The Bidder shall provide all instruments, equipment, materials, facilities and
services required for an appropriate realization of the FAT.
3.4.3.7
During the FAT the Certification Record shall be completed. The configuration of
the equipment during the FAT shall correspond to the one requested by the
Buyer.
3.4.3.8
Should problems arise during the FAT or should the FAT test results be deemed
unsatisfactory in any major way by the Buyer, the problems shall be corrected
and the status shall be mutually verified and agreed. The Bidder shall take full
economic responsibility for any required re-testing program.
3.4.3.9
The following set of documentation shall be handed over to the Buyer as
evidence of a successfully completed FAT:
3.4.3.9.1
the Certification Record, signed by the Buyer or their representatives upon
completion of the test,
3.4.3.9.2
the List of Delivery
3.4.3.10
These Factory Acceptance Test documents, properly signed by the Bidder and
the Buyer, shall imply that the equipment is accepted by the Buyer for delivery
to the site.
3.4.4
Site Acceptance Test (SAT)
3.4.4.1
A selection of the required documentation shall be approved by the Buyer, as
indicated below. Upon approval by the Buyer these documents shall be binding
on both parties. The following documentation is relevant for the SAT:
3.4.4.1.1
TEST PLAN, which shall contain the general conditions and definitions, a test
work flow which defines the test sequence and identifies the related test
specifications and test procedures, and a general description of the tests. The
Test Plan shall be worked out by the Bidder and shall be made available for the
Buyer for review and approval latest three month prior to the expected start of
the SAT or after completion of the FAT, whichever is the latest.
3.4.4.1.2
TEST SPECIFICATION, which shall include detailed descriptions of the various
tests and also include criteria for acceptance/rejection, conditions and
interfaces. In addition, requirements for test provisions such as test tools, test
equipment and test software shall be included. The Test Specification shall be
worked out by the Bidder and sent, together with the Test Plan, to the Buyer
for review latest two months prior to the expected start of the SAT or after
completion of the FAT, whichever is the latest.
533576394
07.03.16
Page 20
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.4.4.1.3
CERTIFICATION RECORD, which shall indicate the type of test, the item tested
and the test result, including possible remarks. After completion of each
acceptance test, an equipment certification record shall be filled in. Remarks
may include agreed deviations from the test procedure. The Certification
Record shall be the formal document for recording the approval of the relevant
test. Both the Buyer and the Bidder shall sign the Certification Record.
3.4.4.1.4
LIST OF DELIVERY. The list of delivery shall contain information about the
configuration of the equipment down to sub-assembly level.
3.4.4.2
The objective of the Site Acceptance Test is to confirm that the system, after
installation on site, is compliant with all the specifications.
3.4.4.3
A complete Site Acceptance Test shall include verification of all items delivered
in accordance with the Bidder including training and documentation
3.4.4.4
The Site Acceptance Tests will be performed under the environmental
conditions that will exist under normal operation for the equipment contracted.
3.4.4.5
It shall be the responsibility of the Bidder to provide required documentation,
test equipment, measuring instruments, tools etc. prior to the start of the SAT.
3.4.4.6
The SAT shall be performed following the Test Plan and the Test Specification.
3.4.4.7
Flight Inspection (Check) for navigation systems (ILS and D-VORTAC) shall be
considered as a part of SAT and shall be the responsibility of Bidder to order
necessary Installation and Commissioning Flight Check from neutral Provider.
3.4.4.8
Equipment under SAT shall consist of the complete system in accordance with
the Contract.
3.4.4.9
The final phase of the SAT shall include a long term STABILITY TEST, lasting for
minimum 30 days, during which the system shall run under continuous relevant
operation without any signs of anomalous function. The procedures of the
stability test and the criteria and conditions to be granted acceptance shall be
mutually agreed.
3.4.4.10
The configuration of the equipment, as it is during the SAT shall be laid down in
the List of Delivery.
3.4.4.11
Should problems arise during the SAT or should the SAT test results be deemed
unsatisfactory in any major way by the Buyer, the problems shall be corrected
and the status shall be mutually verified and agreed.
3.4.4.12
The following set of documentation shall be handed over to the Buyer as
evidence of a successfully completed SAT:
3.4.4.12.1
the certification record, signed by the Buyer or their representative upon
completion of the test,
3.4.4.12.2
the list of delivery.
533576394
07.03.16
Page 21
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.5
WARRANTY
3.5.1
General
3.5.1.1
The warranty period for the entire system shall commence after Buyer
acceptance and last for 2 year.
3.5.1.2
The Bidder shall be responsible to provide system maintenance support during
the warranty period.
3.5.1.3
The Bidder shall propose a maintenance concept for the on-going management
of the installed systems after acceptance.
3.5.1.4
A fully covered contractor maintenance proposal shall be provided within 4
months after contract award.
533576394
07.03.16
Page 22
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.6
SPARES
3.6.1
Initial Spares
3.6.1.1
Initial spare parts shall be provided by the Bidder and shall be sufficient for
maintaining all hardware items for a three-year period, including the warranty
period.
3.6.1.2
The spare parts will be for all delivered systems and equipment including test
and ancillary equipment.
3.6.2
Sparing Level
3.6.2.1
The recommended sparing level shall be based upon the Bidder’s reliability data
for the system being provided and reflect the reliability expected in the Buyer’s
operational environment.
3.6.2.2
The Bidder shall provide these reliability data as part of the response to this
tender.
3.6.3
Description of Spares
3.6.3.1
Spares will consist of LRM and LRU spares, as well as consumable items
required for system operation, including, but not limited to, fuses, lamps,
printer supplies, and specialized print medium.
3.6.4
Spares List
3.6.4.1
The recommended spares list shall be fully itemized and individually priced and
shall be included as part of the tender documentation.
3.6.5
Guarantees
3.6.5.1
The Bidder shall guarantee the availability of all spare parts and modules for the
COTS equipment offered for a period of at least 5 years.
3.6.5.2
The Bidder shall guarantee the availability of all spare parts and modules for the
special equipment offered for a period of at least 10 years.
3.6.5.3
The equipment vendor shall, for a period of 20 years, monitor the availability of
repair parts, and shall provide the Buyer at least 3 months’ notice in writing of
supplier(s) intending to terminate their manufacture and the date by which the
Buyer may place orders for the final production run.
3.7
DOCUMENTATION
3.7.1
General
3.7.1.1
The documentation shall make it possible to the Buyer to:
3.7.1.1.1
Perform fault detection and repairing on a routine basis
3.7.1.1.2
Estimate how functions in hardware may be changed and completed without
tedious studying of details
533576394
07.03.16
Page 23
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.7.1.2
The design of documentation shall be such that the Buyer's staff in appropriate
length of time and by themselves shall be able to:
3.7.1.2.1
Reach good knowledge of principles of hardware structure and way of
operation
3.7.1.2.2
Understand how certain hardware parts cooperate to perform certain functions
3.7.1.2.3
Understand interfaces between different units
3.7.1.2.4
Locate erroneous units and make corrections
3.7.1.3
The system documentation shall include complete technical manuals for each
equipment and part of the system consisting at least the System description
and Software description
3.7.1.4
Documentation data must be recorded to the CD/DVD media in common
software like (Excel, Word, Acrobat, Auto-Cad, etc.)
3.7.1.5
The Buyer shall have the right up to mutually agreed level to copy and use
delivered documentation.
3.7.1.6
To assist any further modification and use of the documentation it should be
available also in electronic data form with suitable media.
3.7.1.7
The Bidder shall provide 3 complete sets of system operations and maintenance
manuals for each subsystem
3.7.2
Hardware documentation
The documentation of hardware shall include:
3.7.2.1
Technical manuals:
3.7.2.1.1
General description
3.7.2.1.2
Technical functions
3.7.2.1.3
Mechanical lay-out
3.7.2.1.4
Maintenance instructions
3.7.2.2
Technical data:
3.7.2.2.1
Parts lists (List of used components with serial numbers)
3.7.2.2.2
Communication settings
3.7.2.2.3
Logic and circuit schematics
3.7.2.2.4
Cabling documentation
3.7.2.3
Installation description:
3.7.2.3.1
Distribution plan
3.7.2.3.2
Cable runs
3.7.2.3.3
Interconnection schematics
533576394
07.03.16
Page 24
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.7.3
Software documentation
3.7.3.1
The documentation shall make it possible for the Buyer to:
3.7.3.1.1
To find out easily version of software
3.7.3.1.2
Perform fault detection and repairing on a routine basis
3.7.3.1.3
Estimate how functions and software may be changed and completed without
tedious studying of the details and making excessive summaries
3.7.3.2
The design of the documentation shall be such that the members of the Buyer's
staff in appropriate length of time and by themselves shall be able to:
3.7.3.2.1
Reach good knowledge of the principles of software structures and way of
operation
3.7.3.2.2
Understand how certain software parts cooperate to perform certain functions
3.7.3.2.3
Understand interfaces between different programs and interfaces between
hardware and software
3.7.3.2.4
Understand how every single program and program module operate
3.7.3.2.5
Understand organization and meaning of data in the system
3.7.3.2.6
Understand all error signals from the system
3.7.3.2.7
Estimate computer capacity, how it is used and determine reserve capacity
3.7.3.3
The documentation of the software shall at least include:
3.7.3.3.1
An overall system description
3.7.3.3.2
All necessary manuals to meet the requirements of software production and
maintenance
3.7.3.3.3
The complete linked system, including the bootstrap loader for initial system
loading, stored on media acceptable to the Buyer.
3.7.3.3.4
It shall be possible to restore the system from scratch using the provided
installation media.
3.7.3.3.5
System and workstation images on a CD/DVD media
3.7.4
Miscellaneous documentation
3.7.4.1
Test procedure and test report documentation for Factory Acceptance Test.
3.7.4.2
Test procedure and test report documentation for Site Acceptance Test
3.7.4.3
Training documentation
3.7.4.4
Reliability analysis
3.7.4.5
Maintenance plan
3.7.4.6
Risk analysis
533576394
07.03.16
Page 25
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.8
HARDWARE AND SOFTWARE REQUIREMENTS
In case if it is not specially defined in the current document or its attachments,
the Bidder should provide the hardware and software, which fulfils the
following requirements:
3.8.1
Software Requirements
3.8.1.1
System-level software for servers shall be one of the commercially available
multi-tasking, multi-user Operating System (OS). One of the OS UNIX™ versions
or their clones (such as Linux), which supports Intel® hardware platform are
preferred.
3.8.1.2
System-level software for Working Positions shall be one of the commercially
available multi-tasking, multi-user Operating System (OS). One of the OS UNIX™
versions or their clones (such as Linux), which supports Intel® hardware
platform are preferred, however Microsoft® Windows™ 7 or later version will
be considered as a suitable OS
3.8.1.3
Off-the-shelf (COTS) database software shall be provided for servers.
3.8.1.4
System and application software shall support dual server architecture and
allow automatic and manual switching of the primary/standby server, in case of
failure or for the maintenance purposes.
3.8.2
Hardware Requirements
3.8.2.1
Off-the-shelf (COTS) equipment shall be provided for server and workstations
equipment. Solutions, based on Intel® Pentium™ platform (Dell, HP, FUJITSU)
are preferred.
3.8.2.2
The server and communication equipment should reside in standard 19” rack
(the dimension should be at least: 2000mm height, 600mm width, 1000mm
depth). Rack shall be equipped with rack-mounted console including LCD
monitor, keyboard and mouse.
3.8.2.3
All the server equipment, including computers, display, keyboard, etc., should
be rack-mounted.
3.8.2.4
In case of several servers, it shall be necessary to provide an Off-the-shelf
(COTS) KVM switch with correspondent number of KVM ports.
3.8.2.5
Each server should have the configuration, not worse that:
3.8.2.5.1
Processor: X86 architecture with 4 cores (64 bit support). 2 processors with 8
cores total. Min. 185 point benchmark by SPECint_rate2006 test
(http://www.spec.org);
3.8.2.5.2
Memory: At least 32 GB DDR3 with Advanced ECC with possibility to extend till
128 Gb;
3.8.2.5.3
HDD: 4x300 GB 15000 RPM, Hot Swap(SAS or SCSI interface);
3.8.2.5.4
Optical equipment: CD-RW/DVD-RW drive (EIDE or SCSI interface);
3.8.2.5.5
Network Interface Card(s), Base-T Dual Gigabit Ethernet with RJ-45 socket;
3.8.2.5.6
Rack-mount (19”) case with the redundant power supply of sufficient
characteristics and appropriate cooling;
533576394
07.03.16
Page 26
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.8.2.5.7
USB 2.0: 2 USB 2.0
3.8.2.5.8
Video card, which supports resolution of 1280x1024,
3.8.2.5.9
17” High Resolution LCD display;
3.8.2.5.10
Additional components, like multi-port serial interfaces, magneto optical or
tape
3.8.2.5.11
storage device for long-term data archiving or DVD/CD-writer, modems, etc.,
shall be provided.
3.8.2.6
The servers shall be provided with embedded redundancy functionality
including dual power supplies, mirrored hard drives (RAID 0/1/5), etc.
3.8.2.7
Each CWP should have the configuration, not worse that:
3.8.2.7.1
Processor: Processor: X86 architecture with min. 2550 point benchmark by
PassMark CPU test (http://www.cpubenchmark.net) with possibility extend for
2 processors;
3.8.2.7.2
Memory: At least 4 GB DDR3 expandable till 8 GB;
3.8.2.7.3
HDD: 160 GB (PATA/SATA or SCSI interface);
3.8.2.7.4
CD/DVD drive (PATA/SATA or SCSI interface);
3.8.2.7.5
Network Interface Card(s), Ethernet 10/100/1000 Base-T with RJ-45 socket;
3.8.2.7.6
Video card, which supports resolution of 1920x1080 min (for Tower positions
2K x 2K);
3.8.2.7.7
24” LCD display (for Tower positions with daylight settings). The other displays
could have another parameters, but not worse than described above
3.8.2.7.8
Additional components, like multi-port serial interfaces, magneto optical
storage device for long-term data archiving or DVD/CD-writer, modems, etc.,
shall be provided as necessary.
3.8.2.8
The workstations shall be provided with mirrored hard drives (RAID 0/1/5)
3.8.2.9
Every workstation shall be equipped with all necessary power cables,
communication cables, input\output devices (mouse/trackball, keyboard, etc.).
3.8.2.10
Sufficient number of short-range modems shall be provided for the systems,
which requires serial asynchronous connection.
3.8.2.11
The system should be equipped with one or more network packet switches to
allow network communication between system components (servers,
workstations) and external equipment.
3.8.2.12
Network switches should allow connection of the equipment by means of
1000BaseT Category 6 twisted pair cabling or higher.
3.8.2.13
The system should be equipped with number of printers. It should be network
or local printers depending on the configuration.
3.8.2.14
The laser printers are preferable, however in special cases and for special
purposes the matrix printers will be considered as suitable solution.
533576394
07.03.16
Page 27
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.9
CIVIL WORKS
3.9.1
General Requirements
3.9.1.1
The Bidder shall evaluate existing situation at the Lielvarde AFB as well as the
works performed during the reconstruction and review all available information
(design, surveys of performed works etc.).
3.9.1.2
If the information is insufficient the Bidder shall obtain additional data that is
required for installation of proposed equipment (topographical survey,
geological survey etc.).
3.9.1.3
The Bidder shall provide all the required construction works for installation of
proposed equipment including construction of foundations, access roads,
communication networks and providing the water drainage.
3.9.1.4
The Bidder shall provide development of appropriate design to perform the civil
works.
3.10
MAINTENANCE REQUIREMENTS
3.10.1
General
3.10.1.1
The ILS/DME and DVORTAC systems shall include maintenance features, which
provide system operators and maintenance personnel with full information
about system status all the time. Moreover, to satisfy availability requirements,
outage time shall be minimised by functions and facilities, which enable rapid
diagnosis of malfunction, identification and replacement of the failed unit.
3.10.1.2
The Bidder shall present complete set of maintenance documentation include
list of all required maintenance procedures and all measurement equipment’s
and tools required to carry out those maintenance.
3.10.1.3
The maintenance philosophy and planned operations herein after are the basis
for the Contract, but however, if the Bidder thinks he can evaluate and state a
corresponding or better solution, he shall do so.
3.10.1.4
Following items are considered:

system design considerations;

maintenance concept;

system management;

preventive maintenance;

corrective maintenance;

maintenance supports;

technical monitoring and control.
3.10.2
System design Consideration
3.10.2.1
Design considerations shall include at least, but not be limited to:

533576394
07.03.16
maximum reliability of equipment;
Page 28
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION

maximum availability of equipment;

redundancy of equipment and/or modules.
3.10.2.2
Features that will allow internal on-line diagnostics for isolating failed modules
and effect system restoration by reconfiguring the system by using redundant
modules.
3.10.2.3
Modular design that permits an easy access to and simple replacement of
defective modules and subassemblies.
3.10.2.4
Standardisation of modules or units, to the extent practicable, to reduce life
cycle costs including training, spare-keeping, etc.
3.10.2.5
The maintenance design features shall include on-line and off-line diagnostics,
which together with built-in test equipment, test points and fault indicators,
should quickly detect the existence of pinpoint and the source of a failure.
3.10.2.6
Diagnostics, status information and control of system are required to be
handled via terminals, which should be located in the Technical Monitoring &
Control (TMC) facility.
3.10.2.7
Special tools to remove, repair, replace and adjust units shall be minimum for
using.
3.10.2.8
All Lowest Replaceable Modules (LRM), subassemblies, parts, test points and
terminals shall be readily accessible for adjustment and maintenance. Each unit
shall be so mounted as to permit its replacement without the partial or
complete removal of any other.
3.10.2.9
The Bidders shall describe the method of the main LRM replacement. The hot
swap of LRM is preferable.
3.10.2.10
Adjustments and routine servicing such as lubrication, screwdriver adjustments,
etc., for rack mounted equipment, shall be possible without removing the
equipment from the rack in which it is installed.
3.10.2.11
The hardware shall be designed to minimise the effects of individual part
failures. The design shall prevent the propagation of the effects of an error.
3.10.2.12
The Bidders shall present to the Buyer the equipment failure detection ratio
and MTBF for DVORTAC, ILS, DME and it components.
3.10.3
Maintenance Operation
3.10.3.1
General
3.10.3.1.1
The maintenance operation is based on the premise of a highly reliable
hardware design with a reasonable amount of redundancy at the system level.
Therefore necessary design features to keep maintenance requirements to a
minimum shall be incorporated.
3.10.3.1.2
Maintenance activities are classified into five items:
533576394
07.03.16

system management;

certification;

preventive maintenance;

corrective maintenance;
Page 29
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION

technical support.
3.10.3.1.3
The Bidder shall present to the Buyer the list off all measurement devices,
accessories, tools and etc., required for site survey, installation, commissioning
and all kind of maintenance. All items of this list shall be included to offer as
separate items, but the list of units, which cost presented shall be present
inside proposal. All delivered measurement devices shall be calibrated and
include calibration certificate (valid at least 1 year at the delivery date) with list
and data of performed tests, as well as with list of devices utilised during
calibration and it calibration dates. All required sets of cables, adapters,
connectors and etc. shall be delivered together with DVORTAC and ILS/DME
beacons.
3.10.3.1.4
All supplied tool, measurement instruments, as well as extension boards shall
be delivered with manufactures calibration certificates and within hard cases
(metallic cases are preferable) for safety transportation and storage. The wellknown device manufacture such as Tektronix, Rochde&Schwarz, Agilent, IFR,
Radial, Spinner or equivalents shall be preferred.
3.10.3.2
Spares
3.10.3.2.1
The Bidder shall suggest the two lists of LRM: first one based on own
experience and second – one of each unique board for DVORTAC, ILS, DME and
RCMS. The Bidder offer shall include cost for both spares sets as separate items.
The list of both spares set shall be specified within technical specification. The
Buyer could extend this list after Bidder offer analysis and later during of
warranty time.
3.10.3.2.2
The Bidder shall propose routines for repairing the LRM.
3.10.3.2.3
The Bidder shall guarantee the correct operation of delivered spares.
3.10.3.2.4
Each delivered lowest replaceable module (LRM) spares shall be supplied inside
separate protection packing for successful transportation and storage.
3.10.4
Preventive Maintenance
3.10.4.1
The Bidder shall propose a program and detailed instructions for preventive
maintenance, taking into account this chapter and operational as well as
reliability and availability requirements.
3.10.4.2
The Bidder shall propose all necessary resources to be needed to carry out the
proposed preventive maintenance.
3.10.5
Corrective Maintenance
3.10.5.1
Level 1
3.10.5.1.1
The redundancy of the equipment together with the on-line diagnostic
capability shall permit automatic reconfiguration of a defective unit to a
redundant one.
3.10.5.1.2
Fault isolation to the defective lowest replaceable module (LRM) will be
accomplished using built-in test equipment (BITE) and/or off-line diagnostic
programs.
3.10.5.1.3
The time consumption of removal and replacement to accomplish of an LRM
shall be determined by the Bidder and presented within offer.
533576394
07.03.16
Page 30
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.10.5.1.4
The Bidder is requested to submit predicted Mean Time To Repair (MTTR) on
maintenance level 1 for all the LRM-units contained in the proposed system and
to calculate on this basis and on the Contract previous experience the MTTR.
3.10.5.1.5
Compliance with the predicted MTTR figures will be evaluated during the
equipment guarantee period.
3.10.5.1.6
Considerable negative deviations from predicted values affecting the expected
magnitude of the life cycle cost of the equipment should be considered as an
acceptable guarantee claim.
3.10.6
Maintenance Support
3.10.6.1
On-line Diagnostics
3.10.6.1.1
General
3.10.6.1.1.1 The purpose of the on-line diagnostic task is to check the system hardware for
correct operation and to initiate a malfunction report when an error occurs.
3.10.6.1.1.2 On-line diagnostics should provide a very high level of confidence for
operational use of the system, a sound basis for automatic and manual
reconfiguration decisions, and an indication to maintenance personnel of the
nature and location of the malfunction.
3.10.6.1.2
Design Considerations
3.10.6.1.2.1 Design emphasis should be placed on fault detection primarily and on fault
location secondly. The design should take advantage of all available
supplementary and status information which is to be included in the
malfunction report.
3.10.6.1.2.2 In addition, this information should be easily accessible from different system
blocks by maintenance personnel.
3.10.6.1.2.3 The on-line diagnostic tasks should form an integral part of the system design,
and should be executed on a regular basis by means of a clock call.
3.10.6.1.2.4 Diagnostic routines should be repeated within adjusted time depending upon
the criticality of the individual equipment. Diagnostic routines should be
provided for each hardware functional element, such as processing elements,
memory/storage elements, interfaces, communication links and user interfaces
and should be properly tailored to the hardware architecture and interface
configurations.
3.10.6.1.3
Hardware Error Detection
3.10.6.1.3.1 All features for hardware error detection should be exercised by the on-line
diagnostics to the extent that they do not degrade the operational system
integrity.
3.10.6.1.4
Watch-dog-function
3.10.6.1.4.1 The design should include the capability of verifying that the diagnostic and
operative routines have been executed at the specified rate.
3.10.6.1.5
Documentation
3.10.6.1.5.1 Explanatory documentation for on-line diagnostic programs should be supplied.
533576394
07.03.16
Page 31
Request for proposal
TECHNICAL REQUIREMENTS SPECIFICATION
3.10.6.1.6
Built-in test equipment (BITE)
3.10.6.1.6.1 BITE should be designed for rapid assessment of test results and isolation of
faults down to LRM or component level.
3.10.6.1.6.2 Built-in test equipment or diagnostic programs should be utilised also in
peripheral equipment to localise faults down to LRM level. Facilities for
calibration, fault detection, fault location and performance monitoring
functions should be included where applicable.
3.10.6.1.6.3 BITE should not cause system failures or false alarms and should be extensively
self-tested to ensure the validity of the BITE output. There should be a
possibility to block off the BITE function.
3.10.6.1.6.4 A local summary signal for pass/fail should be indicated, for instance by an LED
on the front edge of each major unit or PWB.
3.10.6.1.6.5 A subset of the internal diagnostic routines should be activated automatically
on power up. In this case the execution time of diagnostics should be stated for
each major unit. The associated routines should include a check of all LRM's in
the chassis and present the results in a manner similar to that described in the
previous paragraph.
3.10.6.1.6.6 When BITE is activated, reports should be output to the corresponding display
and log file.
3.10.6.1.7
Off-line Diagnostics
3.10.6.1.7.1 Off-line diagnostics should be available for downloading to the defective
equipment.
3.10.6.1.7.2 It should be possible to run the diagnostics either in a chained mode with
default parameter values or by individual selection to permit detailed fault
analysis in specific areas. Parameter values should be easily modified and
diagnostic loops easily inserted.
533576394
07.03.16
Page 32
Download