THE UNITED REPUBLIC OF TANZANIA MINISTRY OF FINANCE PFMRP IV CASHFLOW FOR FINANCIAL YEAR 2014/15 MAY 2014. 1 CASH FLOW FORECAST FOR FINANCIAL YEAR 2014/15 1. APPROVED ANNUAL WORK PLANS PFMRP approved Annual Work plans and Budget for FY 2014/15 amounts to TZS 49,101,728,561 of which TZS 600,500,000 are Bilateral Project funds, TZS 23,031,120,000 are Government funds and TZS 25,470,108,561 are Basket Funds. 2. SOURCES OF FUNDS (i) Contributions by Development Partners The DPs agreed contribution to Basket Funds for the approved AWP&B for FY 2014/15 is as follows: DPs Local Currency Amount in US $ Amount in TZS DONOR DFID 3,000,000 GBP KFW 600,000 EUR 4,800,000 7,824,000,000 840,000 1,369,200,000 Canada 2,000,000 CAD 1,800,000 2,934,000,000 DANIDA 10,000,000 DKK 1,800,000 2,934,000,000 Ireland 1,000,000 EUR 1,400,000 2,282,000,000 Finland 1,200,000 EUR 1,680,000 2,738,400,000 12,320,000 20,081,600,000 Sub Total Note: Foreign currency transactions have been translated as follows GBP at 1.6USD, CAD at 0.9 USD, EURO at 1.4 USD, DKK at 0.1738 USD and at Ths 1,630 per US $ 2 The amount expected from projects under bilateral arrangements will amount to US$ 363,939 from AfDB (ii)Basket Fund Holding Account balance The closing balance of the Basket fund Holding Account on 30th June 2014 is projected to be US$ 1,592,422. It is also expected that refunds of unspent balances for FY 2013/14 will amount to US$ 1,717,485 being amount expected from the components due to delays in procurement processes and Laws enactments, changes in priorities due to PEFA 2013 and Joint Supervision Mission 2013 and funds from carry over activities. Therefore, the amount available for PFMRP disbursement from Basket Fund Holding Account for FY 2014/15 is expected to be US$ 15,629,907 equivalent to TZS 25,476,748,561. This amount is made up of USD 1,592,422 opening balance, US$ 12,320,000 contribution from BF donors and US$ 1,717,485 refund of unspent balances from components. 2. PROJECTED DISBURSEMENTS FROM BASKET FUNDS TO COMPONENTS Based on cash flow projections by Programme components it is expected that TZS 9,267,042,611 equivalent to US$ 5,685,302 will be required in the 1st Quarter, an estimate of TZS 8,151,978,649 equivalent to US$ 5,001,214 is expected for the 2nd Quarter while TZS 5,967,150,299 equivalent to US$ 3,660,828 is planned for 3rd Quarter and TZS 2,083,937,002 equivalent to US$ 1,278,489 will be required for the last 4th Quarter. A detailed cash flow projection is attached in the following tables; Table 1 Table 2 Table 3 Summary CF for Basket Funds disbursements 2014/15- Semi annually Detailed CF forecast for Basket funds disbursements- Quarterly Detailed CF forecast with all sources of funding (GOT, BF, P) – Quarterly 3