Statement of Requirements (for Space Projects) <Project Name> <Location (if applicable)> <Client> National Project Management System Definition Phase Prepared by: Date: File name/EDRM#: SoR Space Projects 10-07-27.doc Statement of Requirements Guidelines Last revised: July 27, 2010 Table of Contents SECTION I 1.0 PURPOSE – Problem Statement ..................................................................... 3 2.0 BACKGROUND ................................................................................................ 3 3.0 PROBLEM/OPPORTUNITY DEFINITION .......................................................... 3 4.0 RISK CONSIDERATIONS ................................................................................. 4 SECTION II 1.0 CLIENT APPROVALS SOUGHT ......................................................................... 5 2.0 PWGSC APPROVALS SOUGHT ......................................................................... 5 3.0 RISK(S) of NOT PROCEEDING ........................................................................ 6 4.0 APPROVAL AUTHORITY .................................................................................. 6 5.0 SOURCE OF SEED FUNDING and Next Steps ................................................... 7 Public Works and Government Services 2 Statement of Requirements Guidelines Last revised: July 27, 2010 SECTION I Statement of Requirements 1.0 PURPOSE – Problem Statement The purpose of Section 1 is to define the “problem or opportunity” in order to seek approval to develop a project up to the Analysis Phase, as per the National Project Management System. Note – If only partial development of project – specify to what phase project is to be developed. Writer's Note – In a brief statement, define the “problem or opportunity” (not the solution or solution requirements) to be presented in this document. E.g. Project to be initiated to address space requirements for X department housed in xxx Street that is a leased facility, with an end of lease date scheduled to occur in XXX. 2.0 BACKGROUND Writer's Notes – Identify whether project is space (accommodation related) or asset (base building) related. Writer is to provide in this section, most up-to-date information available to provide background relevant to the problem statement. Relevant information could include: References to previous related decisions, including related TB minutes (i.e. TB minute regarding approval to expand a client program and accommodations) *Drivers (what is causing problem or opportunity – Strategic considerations, policy requirements, emergency situation); Stakeholders (relevant groups who maybe implicated in the problem/opportunity). If location is known: civic address (town, province), the building name, the tower, the floor(s), the group or tenant occupying the space or adjacent space. Identify: Consistency with Accommodation Plan Potential for non-compliance with space fit-up standards *Sample for drivers: new client program; client space modifications (expansion, reduction, changed use of space, consolidation), temporary storage or office space (swing space), etc. … * Note – Drivers – Refer here only to type of driver, and then define more specifically section 3. 3.0 PROBLEM/OPPORTUNITY DEFINITION Provide a broad description of the following: Nature of the opportunity or problem – Nature of opportunity/what is not working/what is missing? (E.g. current inefficient use of space affording an opportunity for optimization to accommodate growth requirements) Overall timing considerations Highlights of any special issues, which could include the following: Geographic Location Access to public transit, parking Suitability of space Source of funds Timing – duration of occupancy Security Public Works and Government Services 3 Statement of Requirements Guidelines 4.0 Last revised: July 27, 2010 Emergency power Special purpose space Procurement New client program with additional FTEs requiring space Swing Space Strategies-Policies-Regulations-Standards violations Potential for non-compliance with space standards Etc. RISK CONSIDERATIONS Identify key risk issues and potential mitigation strategies associated with the problem. Public Works and Government Services 4 Statement of Requirements Guidelines Last revised: July 27, 2010 SECTION II Approvals 1.0 CLIENT APPROVALS SOUGHT i. Approval of Statement of Requirements ii. Assignment of client representative(s) to the project team: Client Representative(s)? iii. Client funding (where applicable) All fit-up components that exceed the standards must be funded by the client department. In addition, the department is responsible for any client costs associated with this project such as, but not limited to the following: horizontal voice and data, approved non-compliant requests, additional security related to the move and fit-up and all associated consultant fees and PWGSC fees related to the client funded portion fit-up, as well as furniture, fixtures and equipment (FFE). Lastly, client departments are financially responsible for both the rent and fit-up of any additional space that is deemed to be reimbursing. List the items and costs (if known) to be funded by the client in chart below to get to project approval (PPA/LPA). In some cases this could be a percentage or portion of works to be paid by the client. Full client cost will be established when the feasibility assessment has been carried out. FY1 (actual F/Y) Item FY2 TOTAL Client funding total CLIENT SIGNATURE(S) Approved by: (Authorized Client Representative(s) – with Financial Signing Authority) Signature Please print: Name Title Date Comments 2.0 PWGSC APPROVALS SOUGHT i. Approval of Statement of Requirements Public Works and Government Services 5 Statement of Requirements Guidelines Last revised: July 27, 2010 ii. Approval to initiate the documentation related to the development of this project to – specify (normally to PPA) iii. Assignment of a PWGSC project team to consist of: Project Director Leasing Officer Senior Project Leader Client Accommodation Services Advisor (CASA)/Accommodation Manager Senior Project Manager Project Manager Professional and Technical Resources Senior Financial Advisor Property Manager Project OI Analyst Other (specify) ? ? ? ? ? ? ? ? ? ? ? iv. Spending Authority in the amount of $??? (GST included) to gather the client requirements, to prepare the Functional Program (if required), to develop a “Preliminary Project Plan”, to undertake feasibility studies, to assess risks and to finalize the Investment Analysis Report until approval. See section 5. 3.0 RISK(S) of NOT PROCEEDING Briefly identify the impact and associated mitigation strategies of not proceeding with the project. 4.0 APPROVAL AUTHORITY Refer to NPMS Procedure to identify position and obtain the appropriate approval(s) in signature block below. Public Works and Government Services 6 Statement of Requirements Guidelines 5.0 Last revised: July 27, 2010 SOURCE OF SEED FUNDING and Next Steps Identify source of funding (seed money to develop project to PPA) in chart below. E.g. Special Initiatives Building Budget; Capital Vote 12 (Capital Project Briefing Note to be entered into system); Preplanning Leasing Budget; Client; Other, and your Next Steps. # FY1 (actual F/Y) Item 1 Preliminary Plan 2 Functional Program (if required) 3 Consultant Feasibilities Studies 4 PWGSC Feasibility Report 5 Investment Analysis Report 6 Miscellaneous FY2 TOTAL Total Client Funded (as per 1 iii) Total PWGSC Funded Public Works and Government Services 7 Statement of Requirements Guidelines Last revised: July 27, 2010 PWGSC SIGNATURE(S) Prepared by: Prepared by: (PWGSC) Signature (PWGSC) Please print: Signature Please print: Name Position Date Name Project Analyst Date Recommended by: Signature (PWGSC) Please print: Name Title Date Conditions/Comments Approved by: Signature (PWGSC) Please print: Name Title Date Conditions/Comments Public Works and Government Services 8