Mgmt 120 Technique Review for Materials Management This section contains study problems for the following topics. •Inventory Measures •Bill of Materials Concepts •Independent Demand Inventory Models •Materials Requirements Planning Answers for all the problems are found in the back of this section. Materials Management Problems Materials Management Problems 1. Joan Pontius, the materials manager at Money Enterprises, is beginning to look for ways to reduce inventory. A recent accounting statement shows inventories at the following levels. Raw materials: $2,345,000 Work-in-progress: $5,670,000 Finished Goods: $2,161,000 This year's cost of goods sold should be about $29.4 million. Assuming 52 business weeks per year, express total inventory as: a. weeks of supply b. inventory turns 2. One product line is experiencing 7 turns per year, and its annual sales volume (at cost) is $750,200. How much inventory is being held, on the average? 3. MINC, Inc. keeps 4 items in stock, three machines and a repair kit. The current inventory level and last years demand are shown below along with the value of the items. (Assume 52 weeks per year.) Last year's Currently Value demand on hand of item Model 1 17,000 2500 $200 Model 2 15,000 1500 $300 Model 3 8,500 2000 $150 Repair kits 450 100 $24.00 a. How many weeks of supply do they currently have on hand? b. If the current inventory level is characteristic, how many turns per year does MINC Inc. have? Inventory Measures - 1 Materials Management Problems Inventory Measures - 2 Materials Management Problems 4. A subassembly is produced in lots of 450 units. It is assembled from two components worth $50. The value added (for labor and variable overhead) in manufacturing one unit from its two components is $40, bringing the total cost per completed unit to $90. The typical lead time for the item is 5 weeks and its annual demand is 1872 units. There are 52 business weeks per year. a. How many units of cycle inventory are held, on average, for the subassembly? What is the dollar value of this cycle inventory? b. How many units of pipeline inventory are held, on average, for the subassembly? What is the dollar value of this inventory? (Assume that the typical job in pipeline inventory is 50 percent completed. Thus one half the labor and overhead costs have been added, bringing the total unit cost to $70 (or $50 + $40/2). 5. The bill of materials from item A shows that it is made from two units of B. Item B, in turn is made from two units of purchased item C. The per unit purchase price of item C is $10. The table below gives additional information. No anticipation inventory is held. a. what is the dollar value of inventory held, on average, for each item, broken down by cycle, safety stock, and pipeline inventory? b. How many weeks of supply are held to support demand for item A? Value added ($/unit) Lot size (units) Safety stock (units) Lead time (wk) Item Demand (units/wk ) A 40 50 80 20 1 B 80 20 160 0 2 C 160 - 400 100 1 Inventory Measures - 3 Materials Management Problems 6. Consider the bill of materials diagram below. a. How many immediate parents does item I have? item B item E? b. How many unique components does item A have at all levels? c. How many unique purchased items does item A have at all levels? d. How many of item I are used in each item A? e. How many unique intermediate items does product A have at all levels? f. The items have the following lead times. A: 2 weeks D: 2 weeks G: 5 weeks B: 1 week E: 4 weeks H: 3 weeks C: 3 weeks F: 3 weeks I: 2 weeks What is the customer response time if i. all items are specials (made to order) ii. only items E and I are standard (made to stock) iii. only items E, F, G, H, and I are standard A B(2) E(1) I(1) Bill of Materials - 4 C(1) F(1) E(1) I(1) D(1) G(1) E(1) I(1) H(1) Materials Management Problems 7. Item A is made from components B, C, and D. Item B, in turn, Is made from C. Item D is also an intermediate item, made from B. Usage quantities are all one except that two units of item C are needed to make one unit of B. Draw the bill of materials for item A. 8. Consider the BOM below, which includes lead times. a. What would be the customer response time if every item is a special? b. What would be the customer response time if items D and F are made standards? c. List each item and whether it is an end item, a purchased part, or an intermediate item. d. Are there any subassemblies in this BOM? If so, which item(s)? Bill of Materials - 5 Materials Management Problems A B(2) 2 wk D(1) 2 wk E(1) 3 wk G(1) 1 wk Bill of Materials - 6 1 wk C(1) 5 wk F(1) 4 wk Materials Management Problems 9. A discount appliance store sells combination radio and tape cassette players for only $60 per unit. These hand held units have exceptional sound quality and are in great demand. For these units: • Demand = 80 units/wk • Order cost = $70/order • Annual holding cost rate = 25% of selling price • Desired cycle-service level = 75% • Lead time = 2 wk • standard deviation of weekly demand = 20 units • current on-hand inventory is 183 units, with no open orders or backorders. The store operates 52 weeks per year. It has a continuous inventory review system. a. What is the EOQ? b. What would be the average time between orders (in weeks) using this EOQ? c. What should R be? d. An inventory withdrawal 0f 10 units has just occurred. Is it time to reorder? Independent Demand - 7 10. Suppose that you were in charge of the inventory of an item worth $45 per unit. Every 4 weeks you place an order. To determine the order quantity, you take the current on-hand quantity and subtract it from 400. The result is the amount you order. The weekly demand for this product is 60, with a standard deviation of 8. The cost to place an order is $35, and the holding cost rate is $10 per unit per year. You desire to avoid having a stock out 92% of the time. Assume there are 52 weeks in a year. The lead time is a constant 1 week. a. What is the current annual inventory cost (holding and ordering) for this item? b. If you cannot change the frequency of orders, could you save money by changing your target amount from 400? c. If you could change your frequency of orders, what would be the "optimal" ordering policy (Use periodic review system and round P to nearest week)? How much money would this save over the current strategy? 11. Given the following data, what is the EOQ(optimal Q) and R? • Annual demand is 20,800 units • Ordering cost is $40 per order • Holding cost rate is $2 per unit per year. • Lead time = 2 weeks • Safety stock level, set by company policy, is 1000 units. • Assume 52 weeks in a year. Independent Demand - 8 Materials Management Problems 12. Given the following data, compute the parameters for a periodic review system (P and T) for a P that would provide an average order quantity approximately equal to the EOQ. • Annual demand is 20,800 units • Ordering cost is $40 per order • Holding cost rate is $2 per unit per year. • Lead time = 2 weeks • Safety stock level, set by company policy, is 1000 units. • Assume 52 weeks in a year. Independent Demand - 9 13. a. Complete the record using an FOQ of 45 units Item: Lot size Desc. Lead time Parents: 12 13 14 15 16 17 18 19 Gross requirements 25 25 Scheduled receipts 45 30 40 25 units weeks 4 20 21 30 Projected on hand | 25 Planned receipts Planned order releases b. Complete the record using the L4L lot sizing rule. Item: Lot size Desc. Lead time Parents: 12 13 14 15 16 17 18 19 Gross requirements 25 25 Scheduled receipts 45 30 40 25 units weeks 4 20 21 30 Projected on hand | 25 Planned receipts Planned order releases c. Complete the record using the POQ, with P=3 lot sizing rule Item: Lot size units Desc. Lead time 4 weeks Parents: 12 13 14 15 16 17 18 19 20 21 Gross requirements 25 Scheduled receipts 45 Projected on hand | 25 Planned receipts Planned order releases MRP - 10 30 40 25 25 30 Materials Management Problems 14. The MPS for product A calls for 70 units to be completed in week 4 and 80 units in week 7 (the lead time is one week.) The MPS for product B calls for 150 units in week 7 (the lead time is 2 weeks). Develop the material requirements plan for the next six weeks for items C, D, E, and F. Identify any action notices that will be generated. Data Category Lot-size rule Lead time Scheduled receipts On-hand inventory C FOQ = 100 1 100(week 1) 35 Item D L4L 2 None 0 E F FOQ = 150 POQ (P=3) 3 2 150(week None 3) 125 400 A B C(1) D(1) D(1) E(1) F(1) F(1) E(1) F(1) F(1) E(1) F(1) MRP - 11 Product Lead Time 1 2 MPS 4 3 Item: Desc. Parents: Quantities 5 6 Lot size Lead time 1 2 3 units weeks 4 5 6 Gross requirements Scheduled receipts Projected on hand | Planned receipts Planned order releases Item: Desc. Parents: Lot size Lead time 1 2 3 units weeks 4 5 6 Gross requirements Scheduled receipts Projected on hand | Planned receipts Planned order releases Item: Desc. Parents: Lot size Lead time 1 2 3 units weeks 4 5 6 Gross requirements Scheduled receipts Projected on hand | Planned receipts Planned order releases Item: Desc. Parents: Lot size Lead time 1 Gross requirements Scheduled receipts Projected on hand | Planned receipts Planned order releases MRP - 12 2 3 units weeks 4 5 6 Materials Management Problems Answers: 1. average aggregate inventory value = $10,176,000 29.4 million weekly sales = 52 weeks per year = .565 mill/week 10.176 million weeks of supply = .565million/week = 17.99 ≈ 18 weeks of supply 29.4 million inventory turns = 10.176 million = 2.89 ≈ 2.9 turns per year annual sales 2. turns = ave. aggr. inventory value 750200 7 = ave. aggr. inventory value Thus ave. aggr. inventory value = 750200 = 107,171 ≈ 107,000 7 3. Model 1 Model 2 Model 3 Repair kits Last year's demand Currently on hand Value of item Value on hand 17,000 15,000 8,500 2500 1500 2000 $200 $300 $150 $500,000 $450,000 $300,000 450 100 $24.00 $2400 Yearly value in sales $3.4 mill $4.5 mill $1.275 mill $.0108 mill Ave. aggr. inventory value = $1.2524 mill. Annual sales = $9.185 mill. 9.185 weekly sales = 52 = $.176650 mill 1.2524 weeks of supply = .176650 = 7.09 ≈ 7 weeks of supply 9.1858 turns = 1.2524 = 7.33 turns per year Answers - 13 450 4. cycle inventory = 2 = 225 units $ value = (225)($90) = $20,250 1872 pipeline inventory = dL = 52 (5) = 180 units $ value = (180)($70) = $12,600 5. The inventory items are valued, per unit, as follows: Item Unit value upon Unit value as WIP completion C $10 $10 B 2($10)+$20 = $40 2($10)+$20/2 = $30 A 2($40)+ $50 = $130 2($40)+$50/2 = $105 a. Average inventory in dollars Item cycle safety pipeline A $130(80/2) $130(20) = $105(1)(40 = $5,200 $2,600 )= $4,200 B $40(160/2) 0 $30(2)(80) = $3,200 = $4,800 C $10(400/2) $10(100)= $10(1)(160 = $2,000 $1000 )= $1,600 total $12,000 $8,000 $4,600 Ave. aggr. inventory value = $24,600 $24600 b. weeks of supply = (40 units/week)($130/unit) = 4.7 weeks 6. a. I: 1 ; B: 1 ; E: 3 b. 8 c. 4 d. 4 e. 4: E,B,C,D f. i. 11 ii. 10 iii. 5 Answers - 14 Materials Management Problems 7. A(1) B(1) C(1) D(1) B(1) C(2) C(2) 8. a. 10 b. 7 c. A - end, B - intermediate, C - intermediate, D - purchased, E - intermediate, F - purchased, G - purchased d. B is a subassembly 9. a. d = 80 ; D = (80)(52) = 4160 H = i*price = (.25)(60) = 15 (2)(4160)(70) = 197.04 => 197 15 Q 197 b. Time between orders is = d = 80 = 2.46 ≈ 2.5 weeks EOQ = c. R = d(LT) + zL z, from normal table with cycle service level = 75%, = .67 demand is variable, leadtime is constant: L = L ( d ) = 2 (20) R = (80)(2) + (.67) 2 (20) = 179 units d. 183 - 10 = 173. This is lower that the reorder point figured in part c, so an order should be placed. 10. a. Current approach: P = 4, T = 400 Safety stock = T - d(P+L) = 400 - (60)(4+1) = 100 (4)(60) 52 C = 2 + 100 (10) + 4 (35) = $2,655 b. With a service level desired of 92%, the safety stock can be reduced. z = 1.41 Answers - 15 The new target inventory would be: T = d(P+L) + zd P L = (60)(4+1) + 1.41(8) 4+1 = 300 + 25.2 = 325.2 Safety stock would be: = T - d(P+L) = 325.2 - (60)(4+1) ≈ 25 units (4)(60) 52 C = 2 + 25 (10) + 4 (35) = $1,905 Savings = $2,655 - $1,905 = $750 c. D = (d)(ppy) = (60)(52) = 3120 per year 1 optimal P = d (ppy = period per year) (2)(3120)(35) = 2.46 weeks ≈ 2 weeks (10) new T = (60)(2+1) + 1.41(8) 2+1 = 180 + 19.5 = 199.5 ≈ 200 safety stock = 200 - (60)(2+1) = 20 units. (2)(60) 52 new C = 2 + 20 (10) + 2 (35) = $1,710 for a savings of $945. (2)(20800)(40) = 912 2 Usually, R = d(L) + zL , but in this case safety stock is set at 1000. 20800 That means R = d(L) + safety stock or R = 52 (2) + 1000 = 1800 11. EOQ = D 20800 12. d = ppy = 52 = 400 1 P = 400 (2)(20800)(40) = 2.28 ≈ 2.3 weeks 2 As in problem 11, safety stock is given, thus the revised formula for T is T = d(OI + LT) + safety stock = (400)(2.3 + 2) + 1000 = 2720 Answers - 16 Materials Management Problems 13. a. Item: Desc. Parents: Lot size Lead time 12 Gross requirements 25 Scheduled receipts 45 Projected on hand | 25 45 13 14 15 30 45 15 15 16 17 40 25 2 4 0 Planned receipts 4 5 Planned order releases 45 45 0 18 45 4 19 units weeks 20 25 4 0 21 30 1 1 5 5 4 3 0 4 5 5 4 5 b. Item: Desc. Parents: Lot size Lead time 12 Gross requirements 25 Scheduled receipts 45 Projected on hand | 25 45 13 14 15 30 45 15 15 Planned receipts 16 17 40 25 0 0 2 2 5 Planned order releases 25 25 25 18 19 L4L units 4 weeks 20 25 0 0 30 0 2 5 21 0 3 5 0 3 0 c. Complete the record using the P=3 lot sizing rule Item: Lot size Desc. Lead time Parents: 12 13 14 15 16 17 18 19 Gross requirements 25 25 Scheduled receipts 45 Projected on hand | 25 45 30 45 15 15 40 25 2 0 5 Planned receipts 5 0 Planned order releases 50 0 P = 3 units 4 weeks 3 0 20 21 30 3 0 0 5 5 55 Answers - 17 Answers - 18 Materials Management Problems 14. Item: C Desc. Parents: Lot size Lead time 1 1 per A, 3 4 1 per B, 100 135 135 65 6 80 65 65 85 100 100 1 per B 1 2 3 4 70 0 0 70 0 70 150 0 1 per D 1 2 70 55 55 150 150 1 per E 1 2 L4L 2 units weeks 5 6 150 80 0 150 150 3 units weeks 6 3 4 5 150 150 55 80 150 3 0 80 80 125 150 Lot size Lead time 1 per D, 5 70 Lot size Lead time Gross requirements Scheduled receipts Projected on hand | 125 Planned receipts Planned order releases Item: F Desc. Parents: 2 Lot size Lead time Gross requirements Scheduled receipts Projected on hand | 0 Planned receipts Planned order releases Item: E Desc. Parents: units weeks 1 per A Gross requirements Scheduled receipts Projected on hand | 35 Planned receipts Planned order releases Item: D Desc. Parents: 100 1 4 125 150 125 P=3 2 units weeks 5 6 Gross requirements 220 150 150 80 Scheduled receipts Projected on hand | 400 180 30 80 0 0 0 Planned receipts 200 Planned order releases 200 Action notices: Order 70 Ds now, order 150 Es now, order 200 Fs now Delay shipment of 100 Cs until period 3, if possible. Answers - 19