The Electric ESP Handbook

advertisement
The Electric ESP Handbook
A G UIDE TO P ACIFIC G AS &E LECTRIC C OMPANY ’ S D IRECT A CCESS
P ROCEDURES FOR E LECTRIC E NERGY S ERVICE P ROVIDERS
Pacific Gas and Electric Company - ESP Services
March 6, 2016
TABLE OF CONTENTS
PREFACE ............................................................................................................................................................................... 1
ABOUT THIS GUIDE ............................................................................................................................................................... 1
Overview ........................................................................................................................................................................... 1
Disclaimer and Warning................................................................................................................................................... 1
Summary of Chapters and Contents ................................................................................................................................. 2
Chapter Organization ....................................................................................................................................................... 2
Overview .......................................................................................................................................................................................... 2
Prerequisites ..................................................................................................................................................................................... 3
Checklist of Key Steps...................................................................................................................................................................... 3
The [Chapter Topic] Process Illustrated ........................................................................................................................................... 3
Procedures ........................................................................................................................................................................................ 3
CHAPTER 1 ............................................................................................................................................................................ 1
ELECTRIC ESP DIRECT ACCESS PRELIMINARY PROCEDURES ................................................................................................ 1
Overview ........................................................................................................................................................................... 1
Prerequisites ..................................................................................................................................................................... 1
Checklist of key steps ........................................................................................................................................................ 2
Electric ESP Direct Access Preliminary Procedures Illustrated ...................................................................................... 3
Procedures ........................................................................................................................................................................ 4
1. Electric ESP obtains required documentation for Direct Access (DA) signup with PG&E......................................................... 4
ESP Service Agreement ............................................................................................................................................................... 6
About Section 22, Billing Options ............................................................................................................................................... 6
About Section 23, Metering and Meter Reading Options ............................................................................................................ 7
Energy Service Provider Information Form ................................................................................................................................. 7
ESP Credit Application and Financial Statements ....................................................................................................................... 8
ESP creditworthiness requirements .............................................................................................................................................. 9
Credit evaluation parameters ........................................................................................................................................................ 9
Primary credit requirements ......................................................................................................................................................... 9
Alternate credit requirements ....................................................................................................................................................... 9
Direct access consolidated billing options worksheet ................................................................................................................ 11
Instructions for completing the Direct Access Consolidated Billing Options Worksheet .......................................................... 12
Required format for the PG&E bill detail page included on Consolidated Electric ESP bills ................................................... 12
EDI Trading Partner Agreement................................................................................................................................................. 12
Main Agreement ......................................................................................................................................................................... 12
Appendix .................................................................................................................................................................................... 13
EDI Setup Form ......................................................................................................................................................................... 15
Meter Data Management Agent (MDMA) qualification/approval ............................................................................................. 16
2. Electric ESP submits completed DA startup documentation to ESP Services ........................................................................... 16
3. ESP Services Representative contacts Electric ESP upon receipt of DA startup documents..................................................... 16
4. PG&E reviews all submitted DA startup documentation ........................................................................................................... 16
DA startup Documentation Review Timeline............................................................................................................................. 17
ESP Service Agreement Processing ........................................................................................................................................... 17
ESP Credit Application processing ............................................................................................................................................ 17
Credit Acceptance ...................................................................................................................................................................... 18
Credit Denial .............................................................................................................................................................................. 18
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Page ii
Direct Access Consolidated Billing Options Worksheet ............................................................................................................ 18
EDI Trading Partner Agreement processing ............................................................................................................................... 18
EDI Setup Form ......................................................................................................................................................................... 18
MDMA Application and Checklist ............................................................................................................................................ 18
5. ESP Services Representative informs the Electric ESP of the type of DA participation for which it is eligible ....................... 18
Information Websites ...................................................................................................................................................... 20
CHAPTER 2 .......................................................................................................................................................................... 21
DIRECT ACCESS SETUP ........................................................................................................................................................ 21
Overview ......................................................................................................................................................................... 21
Prerequisites ................................................................................................................................................................... 21
Checklist of key steps ...................................................................................................................................................... 22
Direct Access Setup Illustrated ....................................................................................................................................... 22
Procedures ...................................................................................................................................................................... 22
Electronic data exchange synopsis.................................................................................................................................................. 23
1. Prepare systems setup for electronic data exchange .................................................................................................................. 23
2. Review electronic transfer procedures and rules as designated by PG&E for DES and EDI (if applicable). ............................ 23
Data transfer specifics: How DES is used to exchange DA information .................................................................................... 24
DES implementation....................................................................................................................................................................... 24
Key DES contacts....................................................................................................................................................................... 24
DES Web site ............................................................................................................................................................................. 25
EDI data transfer ............................................................................................................................................................ 25
EDI contacts ................................................................................................................................................................................... 26
For more information ................................................................................................................................................................. 26
EDI Direct Access transaction sets ................................................................................................................................................. 26
Transaction set 810 - Billing ...................................................................................................................................................... 26
Transaction set 814 - Direct Access Service Request (DASR)................................................................................................... 26
Transaction set 820 - Payment and Remittance Order................................................................................................................ 27
867 - Meter Usage ...................................................................................................................................................................... 27
997 - Functional Acknowledgment ............................................................................................................................................ 27
Test the viability and accuracy of data transferred to PG&E using DES ........................................................................................ 27
CHAPTER 3 .......................................................................................................................................................................... 29
PROCESSING DIRECT ACCESS SERVICE REQUESTS (DASRS)............................................................................................... 29
Overview ......................................................................................................................................................................... 29
Definition of Terms ........................................................................................................................................................................ 29
Prerequisites ................................................................................................................................................................... 30
Checklist of key steps ...................................................................................................................................................... 31
Processing DASRs Illustrated ......................................................................................................................................... 31
Procedures ...................................................................................................................................................................... 33
1.
2.
3.
5.
6.
Electric ESP obtains customer authorization to submit a DASR on its behalf .......................................................................... 33
Electric ESP obtains customer CTC Agreement, if required ..................................................................................................... 33
Electric ESP evaluates customer DA elections and obtains customer information required to complete DASR ...................... 33
Electric ESP submits DASR to PG&E through DES ................................................................................................................ 34
PG&E processes DASR ............................................................................................................................................................. 35
Electronic Validation ................................................................................................................................................................. 35
DASR Validation ....................................................................................................................................................................... 35
Account Validation .................................................................................................................................................................... 35
7. PG&E sends a confirmation, rejection, or pending notification to Electric ESP ....................................................................... 36
Acceptance notices ..................................................................................................................................................................... 36
Rejection DASR ......................................................................................................................................................................... 37
Additional DASR procedures performed by PG&E ....................................................................................................................... 37
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Page iii
DASR for “New” Premises ........................................................................................................................................................ 37
Additional setup transaction procedures .................................................................................................................................... 37
Additional transaction procedures for newly established PG&E account numbers .................................................................... 38
Additional Shut Off (S/O) and Shut-off Non-Payment (SONP) transaction procedures ............................................................ 39
Additional Cancellation transaction procedures ......................................................................................................................... 39
Additional Customer Account Data Change transaction procedures .......................................................................................... 39
Additional procedures for Initial Customer Historical Usage Information................................................................................. 39
Seamless Move........................................................................................................................................................................... 40
Seamless Move Procedures ............................................................................................................................................................ 40
Canceling a Seamless Move ........................................................................................................................................................... 41
Limits to a Seamless Move Option ................................................................................................................................................. 41
CHAPTER 4 .......................................................................................................................................................................... 43
DA ELECTRONIC DATA EXCHANGE CONTINGENCY PLANS ................................................................................................. 43
Overview ......................................................................................................................................................................... 43
Behind the scenes look at the DASR process ................................................................................................................................. 43
DASR Server Communication Illustrated ....................................................................................................................................... 44
Risks ............................................................................................................................................................................................... 44
Event Scenario Back-up Plans ....................................................................................................................................... 44
Electric ESP unable to communicate with DES ............................................................................................................................. 45
Situation ..................................................................................................................................................................................... 45
Back-up Plan .............................................................................................................................................................................. 45
Failure of PG&E equipment (DASR Interface & CIS) ................................................................................................................... 46
Situation ..................................................................................................................................................................................... 46
Back-up Plan .............................................................................................................................................................................. 46
CHAPTER 5 .......................................................................................................................................................................... 47
METERING ........................................................................................................................................................................... 47
Overview ......................................................................................................................................................................... 47
Metering Services ........................................................................................................................................................................... 47
Meter Service Provider Responsibilities .................................................................................................................................... 48
Meter Installation Standards....................................................................................................................................................... 48
Effective Direct Access Date ...................................................................................................................................................... 48
Meter Maintenance..................................................................................................................................................................... 48
Meter Equipment Specifications ................................................................................................................................................ 48
Obtaining Meter Equipment Information for Existing Customer Accounts ................................................................................... 49
Web Site Test ............................................................................................................................................................................. 49
Selection of the Meter Installer .................................................................................................................................................. 49
Scheduling Meter Removal and Installations - PG&E as Meter Installer .................................................................................. 49
Meters Supplied by PG&E ......................................................................................................................................................... 50
Meters Supplied by Electric ESP ............................................................................................................................................... 50
DA Ready Meter ........................................................................................................................................................................ 50
Phone Service Notification - PG&E as Meter Installer .............................................................................................................. 50
Completed Meter Installs ........................................................................................................................................................... 51
Re-scheduling Meter Installations .............................................................................................................................................. 51
Scheduling Meter Removals and Installations - Electric ESP as Meter Installer ............................................................................ 51
Meter Installation/Removal Notification * ................................................................................................................................. 52
Return of PG&E Meters ............................................................................................................................................................. 52
Service Upgrades ............................................................................................................................................................................ 52
Return to Bundled Service from Direct Access and Meter Ownership ........................................................................................... 52
Electric ESP Inquiries..................................................................................................................................................................... 54
Wired Phone Line Requirements ............................................................................................................................................... 55
Wireless Phone Installation Requirements ................................................................................................................................. 56
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Page iv
Responsibility - Phone Service Account Payment .......................................................................................................................... 57
Responsibility - Phone Service Operability and Maintenance ........................................................................................................ 57
Retention of Rights ......................................................................................................................................................................... 58
Meter Data Management Agent (MDMA) Requirements ............................................................................................... 58
MDMA Approval Process and Requirements ................................................................................................................................ 58
Application and Checklist .......................................................................................................................................................... 59
Written Requirements ................................................................................................................................................................ 59
Server Acceptance Test .............................................................................................................................................................. 60
Back-up Reading Process ........................................................................................................................................................... 60
Data Format ................................................................................................................................................................................ 60
Security and Confidentiality ....................................................................................................................................................... 60
Help Desk ................................................................................................................................................................................... 61
Validating and Editing Data ........................................................................................................................................................... 61
Interval Data ............................................................................................................................................................................... 61
Estimating Data .............................................................................................................................................................................. 62
Interval Data Estimation Rules ................................................................................................................................................... 62
Accuracy and Timeliness of Usage Data ........................................................................................................................................ 63
Interval Data ............................................................................................................................................................................... 63
Monthly Data ............................................................................................................................................................................. 63
Data retention period ...................................................................................................................................................................... 63
Electronic exchange of metering data ............................................................................................................................................. 64
Interval and Time-Of-Use (TOU) data ....................................................................................................................................... 64
Meter Reading ................................................................................................................................................................................ 65
Meter reading data obligations ................................................................................................................................................... 65
PG&E meter reading .................................................................................................................................................................. 66
Electric ESP meter reading......................................................................................................................................................... 66
Metered Usage Rates ...................................................................................................................................................... 66
Life Support Customers and Medical Baseline Quantities ............................................................................................................. 66
CHAPTER 6 .......................................................................................................................................................................... 69
DASR PROCESSES FOR METERING DATA ADJUSTMENTS AND CHANGES ............................................................................ 69
Overview ......................................................................................................................................................................... 69
DA Account Commodity Status Changes ........................................................................................................................ 70
DA Account Commodity Shut-Offs................................................................................................................................................ 70
Process ....................................................................................................................................................................................... 70
Matrix of PG&E-initiated Records Related to Shut-offs by Meter Type ................................................................................... 70
Example ..................................................................................................................................................................................... 72
Meter Change ................................................................................................................................................................................. 73
Matrix of PG&E-initiated Records Related to Meter Change .................................................................................................... 73
Example ..................................................................................................................................................................................... 76
New Meter Sets Which are not Concurrent with Old Meter Removals ...................................................................................... 76
Meter Configuration Data .......................................................................................................................................................... 77
Usage Adjustments ......................................................................................................................................................... 77
Usage Adjustments to Monthly Meter Data Due to Additional Validation Checking of Data when PG&E is the MDMA ....... 78
Matrix of PG&E-initiated Records Related to Usage Adjustments ............................................................................................ 78
Example ..................................................................................................................................................................................... 80
Stand Alone Rebate transactions (reversal only adjustment)...................................................................................................... 81
CHAPTER 7 .......................................................................................................................................................................... 83
ELECTRIC ESP ACCOUNT BILLING....................................................................................................................................... 83
Overview ......................................................................................................................................................................... 83
Bill Components and Billing Options ............................................................................................................................. 83
Summary of bill components .......................................................................................................................................................... 83
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Page v
About the California Energy Commission Tax ............................................................................................................................... 84
Billing options ................................................................................................................................................................................ 85
Consolidated UDC billing .......................................................................................................................................................... 85
Consolidated ESP billing ........................................................................................................................................................... 85
Partial Consolidated ESP Billing ............................................................................................................................................... 85
Full Consolidated ESP Billing ................................................................................................................................................... 85
Separate billing .......................................................................................................................................................................... 86
Read and Bill Serial Dates .............................................................................................................................................................. 86
Consolidated UDC Billing .............................................................................................................................................. 86
Pricing options................................................................................................................................................................................ 87
Flat ($/month) ............................................................................................................................................................................ 88
Single-tiered ($/kWh) ................................................................................................................................................................. 88
Double-Tiered ($/kWh, Electric ESP designates tiers) .............................................................................................................. 88
Time-of-Use - TOU ($/kWh, based on PG&E’s tiers) ............................................................................................................... 88
Custom pricing ........................................................................................................................................................................... 89
Submitting Rate-ready data to PG&E ........................................................................................................................................ 89
Deadlines for the submission of rate-ready data ......................................................................................................................... 89
Bill format ...................................................................................................................................................................................... 89
Bill preparation and processing ...................................................................................................................................................... 89
Bill Printing and Delivery............................................................................................................................................................... 90
Reports generated by PG&E ........................................................................................................................................................... 90
Utility User Tax Application .......................................................................................................................................................... 90
How PG&E calculates Electric ESP payments ............................................................................................................................... 91
When PG&E pays the Electric ESP ........................................................................................................................................... 91
I. PG&E payments to Electric ESP and supporting reports: ..................................................................................................... 91
II. When PG&E makes payment to Electric ESP ....................................................................................................................... 91
III. Reserve against collections................................................................................................................................................... 91
Payments from Electric ESP to PG&E ....................................................................................................................................... 91
Consolidated ESP Billing ............................................................................................................................................... 91
Bill format requirements ............................................................................................................................................................ 91
Calculation of charges owed to PG&E ....................................................................................................................................... 92
Payment Processing.................................................................................................................................................................... 92
Electronic Data Interchange (EDI) ............................................................................................................................................. 92
Separate Billing Procedures ........................................................................................................................................... 92
CHAPTER 8 .......................................................................................................................................................................... 93
CUSTOMER INFORMATION RELEASES .................................................................................................................................. 93
Overview ......................................................................................................................................................................... 93
Confidential Customer Information Release .................................................................................................................. 93
GLOSSARY .......................................................................................................................................................................... 95
DIRECT ACCESS TERMS ....................................................................................................................................................... 95
APPENDIX A ...................................................................................................................................................................... 101
SERVICE TERRITORY CITY CODES ..................................................................................................................................... 101
APPENDIX B ...................................................................................................................................................................... 119
SERVICE CITY ZIP CODES .................................................................................................................................................. 119
APPENDIX C ...................................................................................................................................................................... 133
DA APPROVED METERS .................................................................................................................................................... 133
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Page vi
PREFACE
ABOUT THIS GUIDE
Overview
The ESP (Energy Service Provider) Services organization within PG&E, a group dedicated to providing
information and guidance to ESPs, has compiled information in this document which will assist ESPs with
preparing to do business under Direct Access (DA). This information reflects the latest California Public
Utilities Commission (CPUC) decisions on DA. Please note that content of this document is subject to
change over time as the CPUC issues further decisions relevant to DA.
Disclaimer and Warning
PG&E has provided these guidelines for informational purposes only.
In the event of any conflict between the guidelines contained within this handbook and the DA tariffs and
Energy Service Provider Service Agreement approved by the CPUC, the tariff and the Energy Service
Provider Service Agreement shall control.
The procedures adopted for other California utilities may differ from those of PG&E.
Note that the DA Suspension Decision (D.) 02-03-055, dated March 21, 2002, issued by the California
Public Utilities Commission, may have an impact on the qualification of customers for participation in
DA.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Page 1
Summary of Chapters and Contents

Chapter 1: Electric ESP Direct Access Preliminary Procedures - discusses the preliminary
documentation which needs to be signed and sent to PG&E prior to the submission of Direct Access
Service Requests (DASRs).

Chapter 2: Direct Access Setup - covers information about electronic information exchange setup
requirements under DA.

Chapter 3: Processing Direct Access Service Requests (DASRs) - discusses how Electric ESPs
electronically communicate service requests related to DA to PG&E.

Chapter 4: DA Electronic Data Exchange Contingency Plans - discusses contingency plans for
the handling of DASRs should one or more elements of electronic DASR processing fail.

Chapter 5: Metering - covers DA interval metering issues including the prioritization and
forecasting of installation requests; phone service quality and billing requirements; and customer
service for Electric ESPs.

Chapter 6: DASR Processes for Metering Data Adjustments and Changes - provides Electric
ESPs with information on PG&E DASR processes related to metering data adjustments and DA
account commodity status changes.

Chapter 7: Electric ESP Account Billing - contains information on the billing options which
Electric ESPs can offer to their DA customers.

Chapter 8: Customer Information Releases - details the types of customer information which
Electric ESPs can obtain from PG&E.
Chapter Organization
Chapters 1 through 3, which describe sequential, step-by-step procedures, follow a consistent
organizational format as described below.
Overview
This section, which provides an overview of the chapter topic material and related processes, emphasizes
the most important concepts within the chapter.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 2
Prerequisites
The prerequisites to the procedures covered in the chapter are detailed, ensuring that the Electric ESP is
ready for the steps to follow.
Checklist of Key Steps
Key process steps are briefly described within a checklist format which identifies critical elements.
The [Chapter Topic] Process Illustrated
Visuals are an effective way to convey process information. When appropriate conceptual-level flow
diagrams have been included to illustrate main process steps.
Procedures
This section provides a detailed discussion of items identified within the Checklist of Key Steps.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
Page 3
CHAPTER 1
ELECTRIC ESP DIRECT ACCESS
PRELIMINARY PROCEDURES
Overview
This chapter focuses primarily on the types of documents which Electric ESPs will need to submit prior to
participation in Direct Access (DA). The chapter also discusses the timing involved with reviewing and
processing the documentation submitted by Electric ESPs.
Prerequisites
Prior to starting DA preliminary procedures, an Electric ESP must register with the CPUC if it intends to
serve “Small Customers.” Small Customers are defined per revised Rule 1 as customers on demandmetered schedules (A-10 and E-19V), with less than 50kW maximum billing demand per meter for at
least nine (9) billing periods during the most recent twelve (12) month period or any customer on a nondemand metered schedule (A-1 and A-6).
Detailed information regarding registering with the CPUC can be obtained by visiting the CPUC Web site
(see Information Websites at the end of Chapter 1 in this handbook).
Checklist of key steps
#
STEP
1.
Electric ESP obtains required documentation for Direct Access (DA) signup with
PG&E
2.
Electric ESP submits completed DA startup documentation to ESP Services
3.
ESP Services Representative contacts Electric ESP upon receipt of DA startup
documentation
4.
PG&E reviews all submitted DA forms and documentation
5.
ESP Services Representative informs the Electric ESP of the type of DA
participation for which it is eligible
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 2
Electric ESP Direct Access Preliminary Procedures
Illustrated
ESP obtains required
documentation f or Direct Access
(DA) signup w ith PG&E
ESP submits completed DA startup
documentation to ESP Relations
ESP Relations Representative
contacts ESP upon receipt of DA
startup documentation
PG&E processes
Direct Access
Consolidated Billing
Options W orksheet
PG&E review s and executes
ESP Service Agreement and
conducts a quick review of the
ESP Credit Application
PG&E processes
EDI Trading
Partner Agreement
Does ESP plan to of fer
Consolidated ESP billing?
No
ESP is eligible to participate in DA
and of fer Separate billing.
Yes
PG&E review s startup
documentation required f or
Consolidated ESP billing
PG&E processes
EDI Setup Form
PG&E evaluates
ESP Credit
Application
Is ESP's credit
approved?
No
Yes
PG&E informs ESP
that it can off er
ESP-Consolidated
billing option.
Activation pending
ESP's fulf illment of
EDI systems
requirements
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 3
PG&E informs
ESP that it
cannot of fer
Consolidated
ESP billing
Procedures
This section provides a detailed discussion of the process steps outlined within the Checklist of Key Steps.
1. Electric ESP obtains required documentation for Direct Access (DA) signup
with PG&E
Electric ESPs interested in participating in DA with PG&E will need to complete and execute the forms
indicated in the DA Forms Table below. Information on filling out the DA forms is provided in the
sections following the DA Forms Table.
DA startup forms can either be downloaded from the “DA Documents” link on the ESP Resource Center
website (see Information Websites at the end of Chapter 1 in this handbook) or obtained from PG&E’s
ESP Services.
Electric ESPs may also contact ESP Services via the ESP Services hotline at 415-973-1666, should they
have any questions regarding the DA forms.
DA FORMS TABLE
#
DOCUMENT
DESCRIPTION
WHEN REQUIRED
1.
Energy Service
Provider Service
Agreement (the “ESP
Service Agreement”)
This document specifies the roles and
responsibilities of both the Electric ESP
and PG&E with respect to DA business
transactions and interactions which
transpire between the two parties. Note
that the content of the ESP Service
Agreement may be amended from time to
time at the direction of the CPUC.
Always
2.
Energy Service
Provider information
Document which asks for detailed
information about the Electric ESP which
is not included within the ESP Service
Agreement.
Always
3.
ESP Credit Application
and Electric ESP’s
financial statements
PG&E uses the Electric ESP’s Credit
Application and financial statements to
evaluate the credit worthiness of the
Electric ESP.
Always
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 4
#
DOCUMENT
DESCRIPTION
WHEN REQUIRED
4.
Direct Access
Consolidated Billing
Options Worksheet
This form specifies the services and other
information related to the selection of
billing options. The form also serves as
an authorization for PG&E to commence
preparations which are necessary to
establish the billing options selected by
the Electric ESP.
If the Electric ESP plans
to offer Consolidated ESP
and/or Consolidated UDC
billing
5.
EDI Trading Partner
Agreement
The primary purpose of the agreement is
to establish the binding nature of financial
charge and payment data which is
transmitted electronically between the
Electric ESP and PG&E. The agreement
also specifies that data be exchanged in
accordance with the American National
Standards Institute (ANSI) Business
Interchange Standards, which is currently
ANSI X12.
If the Electric ESP plans
to offer the Consolidated
ESP billing option
6.
EDI Setup Form
This form specifies EDI systems details
relevant to the electronic transmission of
financial charge and payment data.
If the Electric ESP plans
to offer the Consolidated
ESP billing option
7.
MDMA Approval
Application and
Checklist
Forms required to apply for approval as
an MDMA.
If the Electric ESP plans
to provide MDMA
services.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 5
ESP SERVICE AGREEMENT
The following exhibit shows the first page of the ESP Service Agreement.
1.1 - ESP SERVICE AGREEMENT (PAGE 1 OF 16)
ABOUT SECTION 22, BILLING OPTIONS
The Electric ESP’s selection of the Consolidated ESP billing option is contingent upon meeting DA tariff
creditworthiness requirements and EDI requirements. EDI requirements include submission of the EDI
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 6
Trading Partner Agreement and EDI Setup Form as well as satisfactory systems capability for EDI
transaction exchange.
Creditworthiness requirements are discussed in the subsequent section, ESP Credit Application and
Financial Statements.
EDI testing procedures and detail on EDI protocol are covered within Chapter 2: Direct Access Setup.
ABOUT SECTION 23, METERING AND METER READING OPTIONS
If the Electric ESP has indicated that it will be offering all or some metering and meter reading services to
its customers, it will need to meet the established requirements for the types of services it plans to offer.
Electric ESPs should consult Chapter 5: Metering of this handbook for a synopsis of guidelines. Failure
to meet established Meter Service Provider (MSP) or Meter Data Management Agent (MDMA)
requirements prior to submitting Direct Access Service Requests (DASRs) can result in delayed DASR
processing or rejection.
ENERGY SERVICE PROVIDER INFORMATION FORM
This form addresses additional information about the Electric ESP which is not specified within the ESP
Service Agreement. Types of information include the Electric ESP’s emergency contact telephone
numbers, business hours, time zone, additional key functional contacts, etc. PG&E’s ESP Services group
in turn uses this information to better tailor the customer services it provides to Electric ESPs.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 7
ESP CREDIT APPLICATION AND FINANCIAL STATEMENTS
The following shows the first page of the ESP Credit Application.
1.2 - ESP CREDIT APPLICATION (PAGE 1 OF 2)
All Electric ESPs interested in participating in DA with PG&E must complete the ESP Credit Application
and submit a set of financial statements pursuant to the specifications of the ESP Credit Application.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 8
ESP CREDITWORTHINESS REQUIREMENTS
Electric ESPs planning to offer Consolidated ESP billing to end-use customers must meet DA tariff
creditworthiness requirements. Electric ESPs who plan to offer either UDC Consolidated or Separate
billing to end-use customers may also be subject to creditworthiness requirements. In some cases, PG&E
will require Separate billing for Electric ESPs who fail to meet creditworthiness requirements.
Additionally, PG&E may require advance payment of authorized service fees for Electric ESPs who offer
either UDC Consolidated or Separate billing.
CREDIT EVALUATION PARAMETERS
Electric ESPs who satisfy primary or alternate creditworthiness requirements as described below may
offer Consolidated ESP billing to end-use customers. The parameters for credit evaluations and security
deposits are summarized below. Electric ESPs should consult PG&E’s DA Rule 22, Section N for
comprehensive details regarding credit evaluation provisions.
PRIMARY CREDIT REQUIREMENTS
PG&E will consider an Electric ESP creditworthy if it has obtained a credit rating of either:

Baa2 or higher from Moody’s

BBB or higher from Standard & Poor’s, Fitch, or Duff & Phelps
The credit evaluation may be conducted by an outside credit analysis agency, as determined by PG&E.
ALTERNATE CREDIT REQUIREMENTS
Electric ESPs may provide credit security in lieu of satisfying the unsecured credit requirements outlined
above. The amount of the security required to establish credit will be twice the estimated maximum
monthly bill for PG&E charges.
With PG&E’s approval, credit security may be in the form of any of the following:
1.
Cash deposit
2.
Letter of credit
3.
Surety bond
4.
Guarantee, with the guarantor having a credit rating of

Baa2 or higher from Moody’s
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 9

BBB or higher from Standard & Poor’s, Fitch, or Duff & Phelps
Electric ESPs can download PG&E’s Guarantee document from the ESP Resource Center website (see
Information Websites at the end of Chapter 1 in this handbook) or can be obtained by calling the ESP
Services hotline at 415-973-1666.
The following exhibit is an example of the first page of PG&E’s Corporate Guarantee document.
1.3 – CORPORATE GUARANTEE (PAGE 1 OF 4)
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 10
DIRECT ACCESS CONSOLIDATED BILLING OPTIONS WORKSHEET
The following shows the first page of the Direct Access Consolidated Billing Options Worksheet.
1.4 - DIRECT ACCESS CONSOLIDATED BILLING OPTIONS W ORKSHEET (PAGE 1 OF 2)
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 11
INSTRUCTIONS FOR COMPLETING THE DIRECT ACCESS CONSOLIDATED BILLING
OPTIONS WORKSHEET
Specifications made by the Electric ESP on this worksheet will determine the bill format that is generated
for Consolidated ESP and Consolidated UDC invoices to end-use customers.
1.
Electric ESPs will need to mark the checkbox(es) for the consolidated billing option(s) that
it plans to provide.
2.
For each consolidated billing option section, the Electric ESP indicates the additional
options that it would like PG&E to provide.
3.
As some services are exclusive of others, the Electric ESP should only select one option
where indicated.
REQUIRED FORMAT FOR THE PG&E BILL DETAIL PAGE INCLUDED ON CONSOLIDATED
ELECTRIC ESP BILLS
Electric ESPs who plan to offer the Consolidated ESP billing option should be aware of PG&E’s
requirements for the format of the PG&E bill detail page. Detailed information and examples of PG&E’s
bill format requirements are addressed within Chapter 7: Billing, under the section heading Consolidated
UDC Billing.
EDI TRADING PARTNER AGREEMENT
The following shows the first page of the EDI Trading Partner Agreement.
The EDI Trading Partner Agreement consists of the main agreement text and an Appendix to the
agreement. The Electric ESP will need to complete sections within both the EDI Trading Partner
Agreement and the Appendix to the agreement as indicated below.
MAIN AGREEMENT
In section 5.0 under Trade Partner, the ESP corporate representative signs on the signature line and
provides their printed name, title, and date on the appropriate lines.
The following shows the first page of the EDI Trading Partner Agreement.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 12
1.5 - ELECTRONIC DATA INTERCHANGE (EDI) TRADING PARTNER AGREEMENT (PAGE 1 OF 7)
APPENDIX
The following shows the first page of the Appendix to the EDI Trading Partner Agreement. The
Appendix is a part of the EDI Trading Partner Agreement document.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 13
1.6 - APPENDIX TO THE EDI TRADING PARTNER AGREEMENT
1.
Under the Documents section, list any electronic transactions which will be performed. For
Consolidated ESP billing, these transactions will include 810 (invoice), 820 (send and remit
payment), and 997 (acknowledgment). Since the 810, 820, and 997 transactions are currently the
most common, they have been included on the Appendix.
2.
Under the Third Party Service Providers section, specify the Electric ESP’s legal, business name,
address, and telephone number.
3.
Under the Security Procedures section, describe any security procedures with respect to the
transmission of documents.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 14
4.
Under the Existing Agreements section, the Electric ESP will need to list any special conditions and
agreements which may impact how the exchange of Consolidated ESP billing information must be
handled.
EDI SETUP FORM
The following shows the EDI Setup Form.
1.7 - EDI SETUP FORM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 15
In order to initiate EDI setup with PG&E, the Electric ESP will need to complete the EDI Setup Form,
indicating EDI contacts, Value Added Network (VAN), version, supported transaction sets, value added
service bank, bank transit routing number, bank account number, etc.
METER DATA MANAGEMENT AGENT (MDMA) QUALIFICATION/APPROVAL
Electric ESPs who wish to provide MDMA services or use the services of an MDMA other than PG&E
will need to have their prospective MDMA complete and submit the PG&E’s Application for MDMA
Approval and MDMA Approval Checklist to ESP Services by fax (415-973-8494) or mail (see next
section). The application and checklist are available through the “DA Documents” link on the ESP
Resource Center website (see Information Websites at the end of Chapter 1 in this handbook). The name
of the document is “MDMA Qualification Instructions”. For detailed information on the MDMA
approval process, see the section Meter Data Management Agent (MDMA) Requirements in Chapter 5:
Metering.
2. Electric ESP submits completed DA startup documentation to ESP Services
Electric ESPs will need to submit two (2) sets of completed and executed DA forms, with original
signatures, as well as one set of financial statements, to PG&E at the following address:
ESP Services
Yolanda Lerma
Pacific Gas and Electric Company
77 Beale Street
P.O. Box 770000
M/C B19C
San Francisco, CA 94177
3. ESP Services Representative contacts Electric ESP upon receipt of DA
startup documents
ESP Services reviews every set of DA startup documentation received from Electric ESPs to ensure that
all information required for the level of service that the Electric ESP intends to offer to its end-use
customers has been provided. An ESP Services Representative will contact the Electric ESP upon receipt
of the DA startup documentation package to discuss the next steps related to DA participation, such as the
submission of DASRs, or to request additional information from the Electric ESP.
4. PG&E reviews all submitted DA startup documentation
The sections below describe PG&E’s role in reviewing the DA forms and documents, which the Electric
ESP has submitted. The first section provides a process timeline and is followed by sections describing
how PG&E handles each type of DA document.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 16
DA STARTUP DOCUMENTATION REVIEW TIMELINE
The timeline below illustrates the amount of time that an Electric ESP should expect for the review of DA
documents submitted to PG&E. Under normal conditions, PG&E will ensure that document processing
takes place within the time allowances indicated below. Electric ESPs should use the timeline to assist
with the planning of their DA roll-out.
Day 1 on the timeline represents the day that ESP Services receives the DA documentation package from
the Electric ESP. Timely processing of the ESP Service Agreement, ESP Credit Application, and EDI
forms is contingent upon PG&E receiving all completed required documents from the Electric ESP.
ESP SERVICE AGREEMENT PROCESSING
1.
Under normal conditions, PG&E will execute the ESP Service Agreement within two business days
of receipt.
2.
PG&E will forward one of the fully executed ESP Service Agreement documents to the Electric ESP
at the address indicated within Section 13.1 of the agreement.
ESP CREDIT APPLICATION PROCESSING
1.
Upon receipt of the Electric ESP’s credit application and financial statements, PG&E’s Credit Risk
Management Unit (CRMU) will review the application and other required financial information (i.e.
Moody’s, D&B, audited financial statements) to determine the credit worthiness of the Electric ESP
in accordance with the provisions under PG&E’s DA Rule 22.
If the CRMU has the completed ESP Credit Application, financial statements, and any other
documentation necessary to conduct its credit evaluation of the Electric ESP, the process normally
will be completed within ten (10) business days.
2.
The CRMU will advise the Electric ESP and PG&E’s ESP Services regarding the outcome of the
Electric ESP’s credit evaluation (i.e. if the Electric ESP’s credit rating is sufficient, or if PG&E will
require additional security).
3.
Once ESP Services has been informed that the Electric ESP’s credit has been either approved or
denied, it will reflect the appropriate information in PG&E’s ESP database, which is used to validate
the DASRs PG&E receives from the Electric ESP.
4.
The original credit documents (for example, credit application, financial statements, surety bond,
letter of credit or guarantee), will be maintained in a file at PG&E’s CRMU.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 17
CREDIT ACCEPTANCE
If the Electric ESP’s credit is approved, the Electric ESP will be eligible to offer Consolidated ESP billing
to end-use customers.
CREDIT DENIAL
If the credit requirements outlined above are not met, the Electric ESP will not be eligible to offer
Consolidated ESP billing to end-use customers until credit is established. PG&E will automatically
establish Separate billing for the Electric ESP, unless the Electric ESP requests Consolidated UDC
billing.
DIRECT ACCESS CONSOLIDATED BILLING OPTIONS WORKSHEET
PG&E will process the Direct Access Consolidated Billing Options Worksheet internally upon receipt.
EDI TRADING PARTNER AGREEMENT PROCESSING
1.
PG&E will normally execute the EDI Trading Partner Agreement within two business days of receipt.
2.
PG&E will forward one of the fully executed EDI Trading Partner Agreement documents to the
Electric ESP at the address provided.
EDI SETUP FORM
PG&E will process the EDI Setup Form internally upon receipt.
MDMA APPLICATION AND CHECKLIST
PG&E will process the Application for MDMA Approval and MDMA Approval Checklist within ten (10)
days of receipt.
5. ESP Services Representative informs the Electric ESP of the type of DA
participation for which it is eligible
An ESP Services Representative will inform the Electric ESP of the type of DA participation for which it
is currently eligible. If the Electric ESP correctly completed and executed the ESP Service Agreement, it
should be able to participate in DA and offer Separate billing to its end-use customers.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 18
The Electric ESP will be eligible to offer Consolidated ESP billing to its customers if it has obtained
credit approval, has submitted a completed Consolidated Billing Options Worksheet, and has submitted
the EDI Trading Partner Agreement and EDI Setup Form. However, the Electric ESP will not be able to
activate Consolidated ESP billing until it has fulfilled the applicable systems requirements for EDI, which
are discussed in Chapter 3: Direct Access Setup.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 19
Information Websites
Electric ESPs may wish to add the following sites as “favorite” links on their web browsers for easy
access to information about PG&E’s Direct Access program.
NAME
ADDRESS
PG&E Corporation
WWW .PGE.COM
Electric ESP (Electric
Energy Service Provider)
Resource Center
WWW .PGE.COM/ESP
Gas ESP (Gas Energy
Service Provider) Resource
Center
WWW .PGE.COM/CTA
EDI
WWW .PGE.COM/EDI
Web Tariff Book
WWW .PGE.COM/TARIFFS
DES
MADS.PGE.COM
CPUC
WWW .CPUC.CA.GOV
California Independent
Systems Operator (CAISO)
WWW .CAISO.COM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 20
CHAPTER 2
DIRECT ACCESS SETUP
Overview
Prior to offering DA to end-use customers through submission of a Direct Access Service Request
(DASR), the Electric ESP must satisfy certain requirements with respect to electronic data exchange and
metering. For instance, the Electric ESP must both establish a systems infrastructure which is capable of
handling the transmission of information in a format acceptable to PG&E and also have the capability to
exchange information with PG&E over the Internet.
Prerequisites
Prior to obtaining proceeding with DA setup, the Electric ESP must fulfill the following:

Register with the CPUC if it intends to serve Small Customers.

Complete, execute, and submit the ESP Service Agreement and ESP Credit Application.
(See Chapter 1)

Complete, execute, and submit the Consolidated Billing Options Worksheet if planning to
offer consolidated billing options. Complete, execute, and submit the EDI Trading Partner
Agreement and EDI Setup Form if planning to offer Consolidated ESP billing. If applicable
documents are not submitted, PG&E will default billing option selection to Separate billing.
(See Chapter 1)

Obtain credit approval from PG&E if planning to offer Consolidated ESP billing. If credit is
not approved, PG&E will default billing option to Separate billing. (See Chapter 1)
Checklist of key steps
#
STEP
1.
Prepare systems setup for electronic data exchange
2.
Review electronic transfer procedures and rules as designated by PG&E for DES
and EDI (if applicable)
3.
Review electronic transfer procedures and rules as designated by PG&E for DES
and EDI (if applicable)
Direct Access Setup Illustrated
Prepare systems
setup for
electronic data
exchange
Review electronic
transfer procedures
and rules as
designated by PG&E
for DES and EDI (if
applicable
Review electronic
transfer procedures
and rules as
designated by PG&E
for DES and EDI (if
applicable
Procedures
This section provides a detailed discussion of the process steps outlined within the Checklist of Key Steps.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 22
Electronic data exchange synopsis
Participation in DA will require that Electric ESPs are capable of exchanging service account information
electronically with PG&E. Currently all DA information is transmitted using data transfer protocol, which
allows Electric ESPs to submit administrative DA transactions (i.e. DA setup, DA service termination,
meter usage, billing service options, customer service account changes, etc.) to PG&E through the
Internet. Data exchange between PG&E and the ESP is accomplished when the ESP retrieves response
data from a data directory that has been established for them. Data entry and Internet connectivity will be
facilitated by the Data Exchange Service (DES), which Electric ESPs can easily install locally on their
systems.
Additionally, the transmission of financial information (i.e. Electric ESP/PG&E charges and payments)
will be required via Electronic Data Interchange (EDI) protocol will also be required for Electric ESPs
who plan to offer the Consolidated ESP billing option to end-use customers.
1. Prepare systems setup for electronic data exchange
The first step involved with electronic data transfer is to establish a systems environment which can
support the processing requirements related to DASRs and Consolidated ESP billing transactions. The
following requirements summarized below are further elaborated upon in Sections C and D of Rule 22:
1.
An Electric ESP will be required to meet electronic data exchange requirements as specified
by PG&E. To commence the process for establishing this requirement, the Electric ESP
must contact PG&E.
2.
PG&E may allow alternative arrangements to electronic data exchange at its discretion for
certain transactions.
3.
An Electric ESP must have the capability to exchange data with PG&E via the Internet.
4.
The Electric ESP must have the capability to communicate to and from Metering and Data
Management Agent (MDMA) servers for the sharing of meter reading and usage data.
5.
The Electric ESP must have the capability to perform Electronic Data Interchange (EDI) if it
will be offering ESP or UDC Consolidated billing options.
6.
To commence the process for establishing EDI, the Electric ESP must contact PG&E and
shall be required to enter into a trading partner agreement in the form by completing and
submitting the EDI Trading Partner Agreement to PG&E.
2. Review electronic transfer procedures and rules as designated by PG&E for
DES and EDI (if applicable).
Electric ESPs who participate in DA with PG&E will need to conform to specific electronic transfer
procedures and rules as discussed below.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 23
DATA TRANSFER SPECIFICS: HOW DES IS USED TO EXCHANGE DA INFORMATION
DES was developed specifically to transmit gas and electricity utility metering, billing, and administrative
information contained within DASRs between Electric ESPs, UDCs, Metering Agents (MA), and Billing
Agents (BA).
Information is transmitted between the Electric ESP and PG&E through DES over the Internet (World
Wide Web). All DASRs that the Electric ESP submits through DES are transmitted to a data repository
external to PG&E’s firewall called the “QUE” and are automatically time stamped upon arrival. The time
stamp determines the priority of the DASR. These DASRs are then forwarded in order of priority to a
server inside PG&E’s firewall called the PG&E DASR Interface (“DASR Interface”), where they are
further processed by priority within PG&E’s Customer Information System (CIS).
DASRs that PG&E transmits to the Electric ESP are initially placed in the DASR Interface and then
forwarded to the QUE, from which the Electric ESP can download or view the DASRs.
The diagram below depicts the information channels used when DASRs are submitted.
ESP
Fire
Que
Wall
PG&E DASR
Interface
ESP
CIS
CS05 Switching Logic
ESP
2.1: DASR SUBMITTAL INFORMATION FLOW CHANNELS
DES implementation
KEY DES CONTACTS
Questions regarding DES protocol or systems implementation requirements related to DES should be
directed to:
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 24
CONTACT
CONTACT INFO
LYNN MCELHATTON, USER ACCESS CONTROL
AND DES ADMINISTRATOR
PHONE: (415) 973-8080
EMAIL: LDMJ@PGE.COM
DES WEB SITE
Electric ESPs can also consult the DES Internet site at for information about using DES to transmit EDI
data. The exhibit below provides an example of the DES index page.
2.2: DES WEBSITE
NOTE: The demos provided serve as tutorials for using DES. As indicated, documentation is
also available through the site and includes the information topics listed below.
EDI data transfer
Electronic Data Interchange, (EDI) is the exchange of business data in a standardized format between
business computer systems. EDI represents a fundamental change in the way companies transact business.
It replaces paper-intensive functions with efficient electronic transactions and eliminates the need for
printing and mailing business information. By using standard formats and languages, the computerized
data can be electronically transmitted between two companies and interpreted automatically.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 25
The process of sending data via EDI requires a series of steps on the part of the sending and receiving
partners (known as Trading Partners). Once the foundation of your EDI message is defined, most of these
steps will be either automated or procedures will be developed.
Pacific Gas and Electric Company presently utilizes Value Added Networks (VAN's) for EDI Outbound
810 billing transactions. We also have the ability to utilize EDI over Internet connectivity for EDI
Outbound 810 billing transactions to Energy Service Providers.
The EDI contacts below can provide valuable guidance and advice. EDI Direct Access transaction sets are
summarized below the contact table.
EDI contacts
Questions regarding EDI protocol or systems implementation requirements related to DES should be
directed to:
CONTACT
FUNCTIONAL AREA
CONTACT INFO
TOM ELDER
BILLING
PHONE: (415) 973-5119
SENIOR PROJECT MANAGER
EMAIL: TXE6@pge.com
FOR MORE INFORMATION
For additional, detailed information on the EDI process, visit the EDI Web site.
EDI Direct Access transaction sets
TRANSACTION SET 810 - BILLING
The 810 Transaction Set is used to provide established PG&E billing data in an electronic format to its
customers. The billing data provided electronically reflects the same information that appears on a
traditional paper bill and is consistent with national standards for EDI.
TRANSACTION SET 814 - DIRECT ACCESS SERVICE REQUEST (DASR)
The 814 Transaction Set or DASR is sent between the Utility and Energy Service Providers (ESPs) for
purposes such as connecting a customer (i.e. Connect Request), updating a significant customer event (i.e.
Update Request/Notification), or disconnecting a customer (i.e. Disconnect Request).
NOTE: that an Electric ESP that exchanges 814 EDI data with PG&E must also be able to
receive 867 EDI. The 867 is used to pass the required 12 months of usage history for the
customer to the Electric ESP.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 26
TRANSACTION SET 820 - PAYMENT AND REMITTANCE ORDER
The 820 Transaction Set is used to make a payment and send a remittance advice. This transaction set can
be an order to a financial institution to make a payment to a payee. It can also be a remittance advice
identifying the detail needed to perform cash application to the payee's accounts receivable system.
PG&E's application requires that the 820 go through a financial institution.
867 - METER USAGE
The 867 Transaction Set is used to transfer meter usage data. Where the Electric ESP is the MDMA the
867 will be sent to PG&E as in inbound file. Where PG&E is the MDMA the 867 will be sent as an
outbound file to the Electric ESP. Refer to the implementation checklists below for both the 867 inbound
and outbound requirements.
997 - FUNCTIONAL ACKNOWLEDGMENT
The “Draft Standard for Trial Use” contains the format and establishes the data contents of the Functional
Acknowledgment Transaction Set (997),. Transaction Set 997 can be used to define the control structures
for a set of acknowledgments to indicate the results of the syntactical analysis of the electronically
encoded documents. The encoded documents are the transaction sets, which are grouped in functional
groups, used in defining transactions for business data interchange. This standard does not cover the
semantic meaning of the information encoded in the transaction sets.
Test the viability and accuracy of data transferred to PG&E using DES
PG&E requires each Electric ESP to conduct electronic data transfer testing. Therefore, the Electric ESP
will need to develop a viable test plan with respect to testing the transfer of DA information to PG&E via
DES. Testing requirements, testing implementation framework, and required downloadable programs are
available to Electric ESPs on the DES Web site.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 27
CHAPTER 3
PROCESSING DIRECT ACCESS
SERVICE REQUESTS (DASRS)
Overview
This chapter discusses the processing cycle associated with Direct Access Service Requests (DASRs) and
the establishment of Electric ESP services to include: DA enrollment, cancellation of DASRs, DA service
termination, and DA account maintenance. The chapter also describes how DASRs are prioritized for
processing once received by PG&E and when DA service will commence after a setup DASR has been
accepted.
Definition of Terms
Direct Access Service Requests (DASRs) are the electronic records used to initiate, update and cancel
Direct Access service options between Electric ESPs and end-use customers. Electric ESPs are
authorized by end-use customers to submit DASRs for service accounts that desire to switch to DA,
change Electric ESPs, cancel DA, etc. An approved DASR will become a part of the ESP Service
Agreement and will be used to define the services that PG&E will be providing to the customer.
Customers with more than one account with PG&E at the same premises may choose DA or full service
for each separate account. However, a customer may not partition the load at a single meter or on a single
account with multiple meters.
In order to establish DA service for end-use customers, Electric ESPs must submit DASRs, which provide
detailed information about the service requirements for a given customer. An end-use customer may not
directly submit a DASR to PG&E unless that customer has agreed to act as an Electric ESP on its own
behalf. The Electric ESP must submit all DASR information electronically through DES using the
protocol discussed previously within the Electronic Data Exchange section of Chapter 2: Direct Access
Setup.
TRANSACTION #
COMMUNICATION
FLOW
DESCRIPTION OF TRANSACTION
1
(ELECTRIC ESP TO
UDC)
setup/establish direct access with customer
2
(ELECTRIC ESP TO
UDC)
discontinue direct access with customer
3
(UDC TO ELECTRIC
ESP)
acknowledge success of direct access request
4
(UDC TO ELECTRIC
ESP)
acknowledge failure of direct access request
5
(UDC TO ELECTRIC
ESP)
acknowledge actual switch of service provider
6
(ELECTRIC ESP TO
UDC)
acknowledge receipt of switch notification
7
(UDC TO ELECTRIC
ESP)
notify of shutoff or turn-on of service
8
(ELECTRIC ESP TO
UDC) OR (UDC TO
SP)
account maintenance (i.e., customer rate schedule
change)
3.1 - FLOW OF DASR TRANSACTION INFORMATION
Prerequisites
Prior to obtaining customer information and submitting DASRs, the Electric ESP must fulfill the
following:

Register with the CPUC if it intends to serve small customers.

Complete, execute, and submit the ESP Service Agreement and ESP Credit Application (See
Chapter 1: Electric ESP Direct Access Preliminary Procedures).

Complete, execute, and submit the Consolidated Billing Options Worksheet if planning to offer
consolidated billing options.

Complete, execute, and submit the EDI Trading Partner Agreement and EDI Setup Form if
planning to offer Consolidated ESP billing. (See Chapter 1: Electric ESP Direct Access
Preliminary Procedures).

Obtain credit approval from PG&E if planning to offer Consolidated ESP billing. If credit is not
approved, PG&E will default billing option to Separate billing. (See Chapter 1)
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 30

Prepare information systems setup for electronic data exchange. (See Chapter 2)

Confirm the viability and accuracy of information transferred to PG&E by performing data
exchange testing in accordance with PG&E requirements. (See Chapter 2)

Meet the requirements of CPUC Code Section 365(b)(2) (renewable supplier status) if the DASR
indicates that the Customer and Electric ESP claim the status afforded by that code section.
DASRs in which the Electric ESP and the Customer claim the status afforded by Section
365(b)(2) will be given priority in the processing of the DASR in the event of backlog.
Additionally, Electric ESP customers who wish to obtain DA services are subject to the following
requirements and conditions:

A customer must have a service account number assigned by PG&E before the customer
may authorize an Electric ESP to submit a DASR on its behalf. If the customer is new to the
service territory or is moving to a different physical location within the service territory, the
customer must first establish an account with PG&E and receive an account number. This
account number will be used for the submission of the initial DASRs.
Checklist of key steps
#
STEP
1.
Electric ESP obtains customer authorization to submit a DASR on their behalf.
2.
Electric ESP obtains Customer CTC Agreement, if required.
3.
Electric ESP determines DASR transaction and obtains customer information
required to complete DASR.
4.
Electric ESP completes DASR information.
5.
Electric ESP submits DASR to PG&E through DES.
6.
PG&E processes DASR.
7.
PG&E sends a confirmation, rejection, or pending notification to Electric ESP within
two business days.
Processing DASRs Illustrated
The diagram below depicts the primary procedures related to processing DASRs.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 31
ESP obtains
customer
authorization to
submit a DASR
ESP obtains
customer CTC
agreement, if
required
ESP evaluates
customer DA
elections and obtains
appropriate data
ESP completes
DASR
ESP submits DASR
through DES
PG&E evaluates
DASR
PG&E sends rejection
notice to ESP & customer
ESP resolves DASR
issues
No-reject
Yes
Accept DASR
No-pending
Yes
PG&E sends
acceptance notice to
ESP & customer
performs DASR
transaction
PG&E sends pending
notice to ESP & customer
Pending for
more than 11
days?
No
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 32
Procedures
This section provides a detailed discussion of the process steps outlined within the Checklist of Key Steps.
1. Electric ESP obtains customer authorization to submit a DASR on its behalf
An Electric ESP must receive authorization from the end-use customer in order to submit a DASR on its
behalf. The customer can authorize any of the available DASR transactions such as DA setup, DA
termination, and switch of Electric ESP.
2. Electric ESP obtains customer CTC Agreement, if required
As a condition of receiving DA service, DA customers will be responsible for paying for all Competition
Transition Charges (CTC) and other non-bypassable charges authorized by the CPUC for the UDC to
recover from customers in accordance with state law. DA customers are required to confirm this
responsibility in writing provided to the Electric ESP, unless the customer is exempt from the requirement
to provide such a confirmation in writing pursuant to Public Utilities Code Section 370. Where the
customer disputes its obligations to pay CTC for a particular account, the customer may condition its
agreement on resolution of the dispute, provided that the customer has formally requested the CPUC to
grant such relief. However, the existence of such a dispute does not relieve the customer from the
obligation of paying CTC while the dispute is pending. PG&E will continue to bill the customer (either
directly or indirectly through its Electric ESP, depending on the billing option selected) for such charges.
The customer must pay all charges, but may pay any amounts in disputes in accordance with Rule 10,
pending resolution of the dispute.
3. Electric ESP evaluates customer DA elections and obtains customer
information required to complete DASR
Electric ESPs can designate different types of transactions on a given DASR. The table below lists the
transactions, which the Electric ESP can initiate on behalf of an end-use customer. The table also
identifies key customer information that the Electric ESP will need to obtain depending on the type of
transaction. In addition to the customer information outlined below, there are additional field
requirements for each of the transactions. These requirements are available through the DES Web site at
(see Information Websites at the end of Chapter 1 in this handbook).
The designations correspond to those specified in the DASR transaction descriptions.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 33
TRANSACTION #
DESCRIPTION OF
TRANSACTION
REQUIRED CUSTOMER INFORMATION
1
SETUP/ESTABLISH DIRECT
ACCESS WITH CUSTOMER









2
DISCONTINUE DIRECT
ACCESS WITH CUSTOMER




Customer Name
Service Account Address and current service
Zip
UDC Customer Account Number
Service Relationship Provided
Provider (Electric ESP, UTC)
Commodity (i.e. electric, gas)
Billing Option (i.e. UDC-consolidated,
Consolidated ESP, dual)
Renewable Energy Provider Requested
Life Support Customer status*
UDC Customer Account Number
Service Relationship Energy Provided (i.e.
electric, gas)
Customer Name
Service Account Address and current service
Zip
6
ACKNOWLEDGE RECEIPT
OF SWITCH NOTIFICATION

Provide information contained in the
acknowledgment of actual switch of service
provider
10
ACCOUNT MAINTENANCE
(I.E., CUSTOMER RATE
SCHEDULE CHANGE)


UDC Customer Account Number
Service Relationship Energy Provided (i.e.
electric, gas)
Customer Name
Service Account Address
Account information the customer wants to
change



11
ACCOUNT UPDATE (I.E.

Same as #10, Account Maintenance, above
METERING
RELATIONSHIPS, BILLING
OPTIONS)
5. Electric ESP submits DASR to PG&E through DES
Upon entering the required DASR transaction information, the Electric ESP submits the DASR file
through DES by typing the following command at the DOS prompt:
NOTE: Successful implementation of the data exchange test procedure outlined with the
previous chapter required the Electric ESP to install the put.exe and get.exe files locally. If
put.exe and get.exe are not currently installed on the Electric ESP’s local workstation, the
Electric ESP will need to install these programs. Again the files and downloading instructions
are available through the DES Web site.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 34
6. PG&E processes DASR
The illustration below represents the timing associated with processing a DASR.
Day 0
Day 2
PG&E sends
acknowledgment
to ESP that they
have received the
DASR
Day 7
Does PG&E
accept the DASR
No
Yes
Day 18
PG&E sends
DASR
acceptance
confirmation
to ESP &
customer
PG&E will provide, along
with the confirmation
notice, information
regarding when the DA
customer will begin
receiving ESP services,
unless a meter is required
PG&E
notifies ESP
& customer
of error
pending
status or
rejected
DASR
PG&E will confirm or reject
DASRs in error pending
status
3.1 - DASR PROCESSING TIMELINE
ELECTRONIC VALIDATION
All DASRs undergo both transaction level validation, as described in DASR Validation and customer
account validation, as described in the Account Validation section below. All validation rules are covered
within the DES Web site (see Information Websites at the end of Chapter 1 in this handbook).
DASR VALIDATION
PG&E will electronically validate DASRs for accuracy and completeness. DASRs failing the basic
accuracy validation will be rejected back to the Sending ESP. PG&E will communicate the reasons for
rejecting a DASR in the Comments field of the DASR. PG&E will submit a confirmation, rejection or
pending DASR to the Electric ESP within seven (7) business days of receipt.
ACCOUNT VALIDATION
Following successful accuracy validation, PG&E will attempt to electronically match the Receiver
Customer Identifier field of the DASR to PG&E’s computer information system. PG&E’s customer
account number, which is currently printed on the customer’s energy statement, along with the Service ID,
which is printed on the “Details” page of the bill, are the best data available for the Receiver Customer
Identifier field. However, due to the instability of the customer Service ID, PG&E has developed a
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 35
unique non-changing customer-commodity-location specific number called the External Reference ID or
“XREF ID.”1 Once the XREF ID has been assigned to a DA commodity account, it will not change
throughout the life of the account unless DA is cancelled. Essentially, the XREF ID provides a way to
readily identify DA commodity accounts and to reference the history of the commodity even if the
customer switches to different ESPs. PG&E will communicate the customer’s “XREF ID” (rather than
“Service ID”) to the Electric ESP in the acceptance confirmation DASR. The Connect DASR will
validate on the Service ID or XREF ID. The customer’s PG&E XREF ID is intended for use in all future
transactions related to this customer’s service location and commodity. The PG&E account number or
XREF ID is a requirement of all transactions.
When a customer’s commodity account (i.e. electric or gas) undergoes its first DASR transaction, the
current Service ID will be used to populate the XREF ID field and a new Service ID will be assigned to
the commodity account. The Service ID replaces the “account number” on the current DASR form and is
also represented on the “Detail” pages of the customer’s bill.
In the event system validation fails to match the Receiver Customer Identifier supplied in the DASR, or
the account/commodity status is other than open, the DASR will be rejected using the standard DASR
acknowledgment process.
Various PG&E programs and services require additional manual account preparation for certain Direct
Access requests. For this reason, successful DASRs may contain a “memo” status informing the Electric
ESP of additional manual preparation. These DASRs will, however, be accepted by PG&E and a DA
effective date, if applicable, will be established and communicated to the Electric ESP in the confirmation
DASR. The most common reasons for memo status will likely relate to metering installation and setup
issues.
7. PG&E sends a confirmation, rejection, or pending notification to Electric
ESP
Depending upon the results of the validation process, PG&E will electronically send a DASR acceptance
confirmation, rejection, or pending notification to the Electric ESP. A notice will also be sent to the
customer.
ACCEPTANCE NOTICES
An acceptance notice confirms that the DASR has been submitted successfully. If the DASR represented
a DA setup transaction and meter installation is not pending for the service account, a notice
acknowledging the actual switch of service provider and designating when the DA customer will begin
Electric ESP service will also be sent to the Electric ESP and to the customer.
1
Use of the “GEN ID” has been discontinued and replaced by the “XREF ID.”
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 36
REJECTION DASR
A rejection notice provides specific information on why a given DASR was rejected.
The table below provides information on error codes that are generated as a result of a rejected DASR.
[Insert Gary’s Error Code Matrix]
Additional DASR procedures performed by PG&E
Based upon the requested services designated by the Electric ESP, PG&E may be required to perform
additional DASR procedures in order to complete the processing of the DASR transactions as described
below.
DASR FOR “NEW” PREMISES
Although the current DA suspension rule does not allow new accounts to be eligible for DA, there are
certain circumstances under which a DASR can be submitted for premise that may be considered “new”.
DA eligibility, in general, is restricted to the following circumstances:
a)
Service Panel Upgrades
b) Bankruptcies
c)
Assignment of Contract to a new ESP
d) Mergers/Acquisitions/Corporate Reorganizations
When applicable the ESP should contact ESP Services in advance to coordinate the submission of
DASRs.
ADDITIONAL SETUP TRANSACTION PROCEDURES
Billing and Billing Calculation Options. Electric ESPs will state their billing preference in
each DASR. Three billing options are allowed with DA including: 1) UDC (UDC-consolidated
bill for both ESP and UDC charges), 2) SP (Consolidated ESP bill for both ESP and UDC
charges), or 3) DUAL (UDC bills for UDC charges and Electric ESP bills for ESP charges).
PG&E will communicate the enrolled billing option in the confirmation transaction to the
Electric ESP. An example of an invalid billing option is a DASR requesting Consolidated ESP
billing by an Electric ESP that is not authorized to perform Consolidated ESP billing. Once the
account has been prepared for the requested billing option, PG&E will issue a new confirmation
DASR to the Electric ESP informing them of the billing option change and effective date.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 37
Various PG&E programs require manual account preparation for consolidated billing. PG&E
will determine which accounts require manual follow-up and will default those accounts to
Separate billing pending account preparation for consolidated billing. Customer account billing
options which may require manual preparation include:
Balanced Payment Plan (BPP). PG&E’s Balanced Payment Plan (BPP) provides customers
with levelized monthly bills. However, due to the various billing options offered with DA,
PG&E will not be able to offer BPP to DA accounts. Therefore, if a DASR is received and the
account is enrolled in BPP, PG&E will remove the account from BPP and send the customer a
bill for the account’s outstanding balance. This operation will not hinder the account from
becoming a DA account.
Automatic Payment Service (APS). PG&E’s Automatic Payment Service (APS) provides
customers the ability to pay their UDC bill through an automatic debit of their personal bank
account. For those accounts that will be served under the Consolidated ESP billing option, APS
must first be removed from the account before Consolidated ESP billing can be put into effect.
PG&E will flag the account for removal from APS. Following account preparation, PG&E will
place the account on Consolidated ESP billing and issue a confirmation DASR, informing the
Electric ESP of the billing option change and effective date.
Electronic Data Interchange (EDI). EDI provides the customer with the ability to pay their
UDC bill using an EDI interface. EDI is treated similar to APS. DASRs requesting the
Consolidated ESP billing option will require EDI to be removed from the account. PG&E will
follow-up to confirm the customer’s next EDI bank payment clears the account balance.
Following account preparation, PG&E will place the account on Consolidated ESP billing and
issue a new DASR confirmation to the Electric ESP of the billing option change and effective
date.
Balance Due. The Electric ESP must advise its customers that all past due balances owed for
bundled utility service must be paid prior to the start of Consolidated ESP billing service. PG&E
may pursue collection of the balance owing for bundled service from the customer in accordance
with its applicable rules, including if appropriate, termination of the customer’s service.
Rate Schedule Application. DASRs requesting the UDC-consolidated billing option must
include a valid Electric ESP Rate Name (SP Rate Schedule). Electric ESPs may submit account
maintenance DASR transactions to request a change to the SP Rate plan assigned to the account.
ADDITIONAL TRANSACTION PROCEDURES FOR NEWLY ESTABLISHED PG&E ACCOUNT
NUMBERS
Turn On (T/O). A UDC service turn-on (T/O) order is initiated when a customer establishes a
new account with PG&E. Customers must receive an account number from PG&E prior to an
Electric ESP submittal of a DASR for the customer at the new location. The DASR must be
submitted with a UDC account number containing at least nine (9) characters. This partial
account number will alert PG&E to search for a T/O request, allowing the new account to have
DA service on the requested service date.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 38
ADDITIONAL SHUT OFF (S/O) AND SHUT-OFF NON-PAYMENT (SONP) TRANSACTION
PROCEDURES
Shut-Offs initiated by the DA customer. In the event that a customer contacts PG&E to close
its utility service account, PG&E will notify both the servicing and pending Electric ESP with a
termination DASR. PG&E will notify the current Electric ESP by electronic mail in the event of
a shut-off for non-payment.
ADDITIONAL CANCELLATION TRANSACTION PROCEDURES
Cancellation of pending DA service may be requested by the pending Electric ESP. The
pending Electric ESP can cancel a scheduled switch by submitting a DASR transaction, at least
three business days before the scheduled switch date. The request to cancel will be effective
immediately. The existing service provider (ESP or UDC) will remain in effect.
Termination of current DA service may be requested by the current Electric ESP. The
current Electric ESP may terminate service with a customer at any time. The request to terminate
service will be effective according to normal DA switching logic. The switch date will be the
next scheduled meter read date, which occurs fifteen (15) or more days after the DASR has been
received in the DASR Interface. Once the switch occurs, the customer would remain a fullservice customer with PG&E for at least one billing cycle before it could establish DA service
with another Electric ESP. If the current ESP has pending relationships, the UPDATE DASR
will recalculate the earliest possible start date for all relationships.
ADDITIONAL CUSTOMER ACCOUNT DATA CHANGE TRANSACTION PROCEDURES
PG&E will modify its customer account information upon direct customer request only, therefore, DASRs
received by Electric ESPs communicating customer data changes will not be accepted and will reject back
to the initiating Electric ESP.
Electric ESPs may however, request their customer’s account information record from PG&E using the
Customer Information Release Form. Upon request by the current or pending Electric ESP, PG&E will
respond with a standard DASR Customer Account Information record. In the future, PG&E may
implement automatic notification of customer data changes to the Electric ESP.
ADDITIONAL PROCEDURES FOR INITIAL CUSTOMER HISTORICAL USAGE INFORMATION
Upon DASR confirmation, up to 12 months of customer historical usage information will be released
automatically to the pending Electric ESP if PG&E is acting as the energy provider.
NOTE: Historical usage information may be incomplete for some gas and electric services
where a meter change has taken place. In these instances, the ESP will be provided with
supplemental usage history via email.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 39
SEAMLESS MOVE
Direct access customers who move within the service territory can maintain electric DA service with their
electric ESP. It is not necessary to begin with bundled service at the new location.
Seamless Move Procedures
While gathering the necessary information to move the customer’s distribution service, the company’s call
center determines whether the customer wants to continue to use the same Electric ESP. If “yes”, the
company notifies the customer’s Electric ESP by e-mail. The company sends the e-mails once per day in
a batch by noon, Pacific time. The Electric ESP must designate one person (one e-mail address) to
receive the e-mails.
The e-mail to the customer’s Electric ESP includes:

Customer name

Old service address

New service address (including ZIP code)

Old Service ID

New Service ID

New meter number (if required for DASR acceptance)

XREF ID

Requested turn-on date

Billing address (if different than the service address)

Type of move (“new”, “rescheduled”, or “cancel”)
It may also contain, if available:

Rate class

New telephone number

Old Electric ESP customer account number
The Electric ESP may use the data contained in the e-mail to submit a DASR to PG&E for service at the
new location. This DASR must contain a “new customer” designation.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 40
If the DASR was submitted at least three business days before the requested turn-on date, the customer
will receive Direct Access service from that date. If the DASR was submitted less than three business
days before the requested turn-on date, the customer will receive direct access service as of the next meter
read date.
The Electric ESP is responsible for communicating with the customer about their new service start dates
in order to help the customer understand the process. In general, the seamless move procedures involves
the steps indicated below:

Customer contacts their ESP to stop service at the current location and to start service at the
new one

The ESP contacts ESP Services about their customer’s seamless move.

The ESP is sent a Pending service disconnect DASR (SVC DISCONNECT) containing the
future stop date.

The ESP will then receive an acknowledgement DASR (ACK) for the new location, which
will contain the new XREF ID and actual stop date information.

The ESP’s customer identifier will remain unchanged.
Canceling a Seamless Move
If the customer calls back to cancel the move, PG&E will either send a cancellation DASR to the Electric
ESP if the ESP had already submitted a DASR for the new location, or send a cancellation e-mail to the
Electric ESP if the ESP had not already submitted a DASR for the new location.
In the event the customer’s Electric ESP is serving only a geographic subset of PG&E’s service territory,
(a municipal aggregator, for example) and the customer is moving to a new location not served by the
Electric ESP, the ESP will not submit a DASR on behalf of the customer at the new location.
Limits to a Seamless Move Option
To be eligible for a seamless move, a customer must be:

An existing Direct Access customer.

Moving within the service territory.

A residential or small commercial customer who is load-profiled.
All DASR options must remain the same from the existing or old service location to the new service
location; that is, the MSP/MDMA/billing/meter owner options must be the same in both locations.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 41
A change in responsible party, at the time of the move, constitutes a new customer and is not considered
simply a move of distribution service location.
Customers who move first, and notify PG&E after they have moved, will not be eligible for Direct Access
at the time of initial service.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 42
CHAPTER 4
DA ELECTRONIC DATA
EXCHANGE CONTINGENCY
PLANS
Overview
The objective of this chapter is to describe the contingency process for handling DA sign up should one or
more elements of the DASR process fail. Although, failure of the electronic process is not anticipated, we
have put procedures in place which will allow DASRs to be processed in the event of an unplanned
systems-related problem.
Behind the scenes look at the DASR process
DASRs which are submitted by Electric ESPs through DES are transmitted via the Internet to PG&E’s
systems through a mail server called “QUE.” The QUE acts as a data repository for the Electric ESPs and
PG&E to send and retrieve data. The QUE will sort and direct the incoming data by type. Once the data
is in QUE, another system called the PG&E DASR Interface (“DASR Interface”) will retrieve the data for
PG&E. The DASR Interface manages the data from the QUE. DASR Interface is a database that
contains a list of transactions. It takes the data in and stores the transactions, (e.g., to whom we sent
information to) the reasons why, and the data names (e.g. record type, operation type, service relation, SP
identifier). DASR Interface also time-stamps the data, looks for data changes, conducts basic validation
of data, error checks etc. Next, the DASR Interface sends the data to our Customer Information System
(CIS). CIS contains the “CSO5” file--the logic for switching customers to direct access service. CSO5 is
located in the “Master File”. At this point, the customer’s data would be “confirmed” or “rejected” back
to the Electric ESP. This entire process is also know as the DASR or Direct Access Service Request.
DASR Server Communication Illustrated
The diagram below depicts the flow of information between the external data repository QUE, PG&E’s
DASR Interface, which confirms transactions, and the CIS switching logic which establishes DA service
for a given customer.
ESP
Fire
Que
Wall
PG&E DASR
Interface
ESP
CIS
CS05 Switching Logic
ESP
4.1 - INFORMATION FLOW BETWEEN QUE AND DASR INTERFACE
Risks
At any point in this process described above, the electronic down-load or DASR could fail to operate as
planned. Conversely, the Electric ESP’s system may also fail. The impact is that PG&E will be unable to
sign-up customers for Direct Access through electronic means.
Event Scenario Back-up Plans
The following sections describe possible scenarios resulting from Internet failure, Electric ESP/PG&E
system incompatibility, ESP equipment failure or PG&E equipment failure.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 44
Electric ESP unable to communicate with DES
ESP
Fire
DES
Wall
PG&E DASR
Interface
ESP
CIS
CS05 Switching Logic
ESP
4.2 - ELECTRIC ESP UNABLE TO COMMUNICATE WITH THE QUE
SITUATION
The Electric ESP is unable to send information to PG&E’s QUE because of:

Electric ESP equipment failure.

The incompatibility of the Electric ESP’s system with that of PG&E.

Internet failure.

Failure of the QUE/DES.
BACK-UP PLAN
1.
The Electric ESP will notify PG&E’s ESP Services Hotline or PG&E’s ESP Services will notify
Electric ESPs that there is a problem either by fax or phone..
2.
If there is a failure of the QUE but a connection through the Internet is available, the ESP will be
given instructions on sending the data file by email. If an Internet connection is not available, the
Electric ESP will save customer DASR requests on a disk as a comma-delimited .CSV file. The
format should be according to the EDI format as described within Chapter 2: Direct Access Setup in
the section, Review electronic transfer procedures.
3.
The Electric ESP should express mail the disk to the following address, ESP Services, Pacific Gas
and Electric Company, 77 Beale Street, 19th Floor, San Francisco, CA 94105.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 45
4. PG&E will send a confirmation file back to the Electric ESP containing confirmation or rejection
data for each DASR.
Failure of PG&E equipment (DASR Interface & CIS)
ESP
Fire
Que
Wall
ESP
PG&E DASR
Interface
CIS
CS05 Switching Logic
ESP
4.3 - FAILURE OF PG&E EQUIPMENT
SITUATION
The DASR Interface is unable to receive data from the QUE or pass data into CIS or PG&E’s CIS goes
down.
BACK-UP PLAN
1.
This situation will be considered an emergency. ESP Services will notify all Electric ESPs of
emergency conditions.
2.
PG&E will not accept DASRs until the problem has been resolved and the system is stable.
3. The CIS “masterfile” will be responsible for all data validation checks if the DASR Interface goes
down.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 46
CHAPTER 5
METERING
Overview
This chapter focuses on DA (Direct Access) interval metering including meter installation, meter
maintenance obligations, Meter Data Management Agent requirements (including procedures for meter
ownership), meter reading and meter data access.
Within the context of this chapter, the term “meter” refers to an hourly, non-load profile meter, known as
an “interval meter.”
Interval meters are required for DA customers whose maximum electrical demand is equal to or exceeds
50kW. Those DA customers whose demand is between 20-50kW may choose to have an interval data
meter installed; however, meters already in place for customers whose demand is between 20-50kW
already meet the requirements for DA load profile.
If any customer, including those with an electrical demand is 50kW or below, wishes to participate in
PG&E’s hourly PX rate option, that customer is required to have an interval data meter installed.
Similarly, those customers on electric rate schedules A-10 and E19V will be required to have an interval
meter installed if a “spike” of 80kW or over is reflected in their usage within the last 12 months.
PG&E’s Rule 22, Direct Access Service, describes the terms and conditions that apply to both PG&E
customers and Electric Energy Service Providers who participate in Direct Access. Fees for Direct
Access services are described in PG&E Schedules E-DASR, E-ESP and E-EUS. Refer to PG&E’s Web
Tariff Book (see Information Websites at the end of Chapter 1 in this handbook).
Metering Services
While PG&E is hopeful this chapter provides the reader with basic information regarding DA Metering in
PG&E’s service territory, we also strongly suggest contacting your PG&E assigned ESP Services
Representative to arrange a meeting to discuss your metering plans, along with procedures and processes.
METER SERVICE PROVIDER RESPONSIBILITIES
While CPUC decisions refer to meter service providers (MSPs), the industry currently identifies Meter
Installers and Meter Maintainers. ESPs may select approved Meter Installers and Meter Maintainers,
including PG&E, to perform interval meter installations and maintenance.
Responsibilities for Meter Installers and Meter Maintainers include:

meter installation

meter operation and maintenance services

meter testing and certification
METER INSTALLATION STANDARDS
Meter installations will be conducted according to the requirements specified in DASMMD. PG&E shall
have no liability for any damage or injury caused by ESP-installed metering equipment.
EFFECTIVE DIRECT ACCESS DATE
The effective date and time of the switch to direct access are the time and date of the installation, unless
the account is DA Ready (see the “DA Ready Meter” section). If the account is DA Ready, the switch date
is the next meter read date. Also see the “Meter Work Not Completed Within 60 Days” section under the
heading, “Return to Bundled Service from Direct Access and Meter Ownership – Bundled Safe Harbor.”
METER MAINTENANCE
The Meter Maintainer is responsible for the routine maintenance of all DA interval meters, including but
not limited to, DA interval meter testing, record keeping to assure safe and proper operation of the DA
interval meter, and timely repair in accordance with the CPUC’s (California Public Utilities
Commission’s) and other applicable standards.
METER EQUIPMENT SPECIFICATIONS
All meters installed by ESPs or their Meter Installers shall meet all CPUC-approved Direct Access
Standards for Metering and Meter Data (DASMMD) and shall be self-certified by the meter manufacturer
with the CPUC.
PG&E retains the right to replace an existing meter regardless of ownership if that meter fails to meet the
requirements specified in DASMMD. If PG&E replaces the meter, the installation terms, conditions and
procedures below will apply:
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 48

If the ESP does not elect to provide metering services, PG&E will provide those services at fees
specified in PG&E’s rate schedules to the DA customer.

If PG&E removes the DA interval meter, PG&E will properly identify and return the meter to its
owner in the same condition as found within 5 business days.
Obtaining Meter Equipment Information for Existing Customer Accounts
ESPs submit DASRs in accordance with guidelines provided in Chapters 2 and 3 of this handbook,
“Processing Direct Access Service Requests.” Those DASRs which either require or request meter
installations become meter installation orders.
NOTE: No Direct Access metering services may be provided or started by an ESP, its Meter
Installer or MDMA for any customer unless the ESP’s DASR has been accepted by and the
ESP’s work has been scheduled with PG&E.
PG&E’s Meter Equipment Information web site provides authorized and secure access to ESPs and their
designees, generally their Meter Installer, Meter Maintainer or MDMA, for information on existing
metering equipment by customer account. For general information and procedures, see the Meter
Equipment Information Web site.
WEB SITE TEST
ESPs are required to test the Meter Equipment Information web site to ensure their passwords are
operational and meter information is easily downloaded. For further information on the Web Site Test, go
to http://meterinfo.pge.com/3rdparty/login.asp.
SELECTION OF THE METER INSTALLER
As described in the Meter Service Provider Responsibilities paragraph of this chapter, the ESP may select
PG&E as its Meter Installer or Meter Maintainer or select another Meter Installer or Meter Maintainer to
perform metering services. Those services include meter installation, meter operation, maintenance,
testing and calibration. Generally the work also includes the removal of the existing meter.
PG&E metering services fees will be charged to the ESP in accordance with CPUC-filed tariffs. (See the
filed document, E-ESP, located in the Web Tariff Book.)
SCHEDULING METER REMOVALS AND INSTALLATIONS - PG&E AS METER INSTALLER
When PG&E is the meter installer, meter installation scheduling is based upon the following:

Each DASR’s renewable and non-renewable energy supply status
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 49

PG&E’s capacity to install meters which is dependent on its new construction volume, meter
compliance, and meter data recovery work

Date PG&E accepted the DASR on a first-come, first-served basis

Site readiness

Mutually agreed upon date
The ESP is responsible to ensure the meter site is ready for the meter installation. A meter site is
considered ready when PG&E has ESP-provided meters on hand and the meter telecommunications are in
place and working.
PG&E AS METER INSTALLER
If the site is DA Ready with an interval meter in place or PG&E, as Meter Installer, installs a customerowned DA interval meter, the ESP is responsible for the meter cost, local sales tax, Service Base Charge,
meter removal and installation charges and the programming and testing of the DA interval meter in
accordance with the filed rate schedules. (See PG&E’s Web Tariff Book.)
METER SUPPLIED BY ESP
If PG&E, as Meter Installer, installs an ESP-provided DA interval meter, the ESP will be responsible for
the Service Base Charge, the meter removal and the meter installation charges. Additionally, If the ESP
has not performed meter programming and testing, PG&E will charge for that work in accordance with
the provisions of PG&E’s Direct Access Service Rule 22 and its filed rate schedules. (See PG&E’s Web
Tariff Book.)
DA READY METER
A DA ready meter is an installed PG&E interval meter or a customer-owned meter that meets the CPUC’s
interim meter standards and is currently phone line read.
If an account has a PG&E DA ready meter, the ESP may elect to use this meter. Phone service account
payment responsibility is described below in the paragraph entitled, “Responsibility - Phone Service
Account Payment.”
PHONE SERVICE NOTIFICATION - PG&E AS METER INSTALLER
The ESP notifies PG&E’s MEG (Meter Event Group) by sending a “Phone Service Notification.” The
Phone Service Notification can be downloaded from the “DA Documents” link on the ESP Resource
Center Web site.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 50
Upon receipt of the Phone Service Notification, PG&E then schedules the installations in accordance with
its capacity to install meters and posts the scheduled date and order status update to its Meter Equipment
Information Web site.
If the ESPs want to coordinate a field meeting, they must notify the MEG by forwarding a “Field Meeting
Request.” Fees charged to the ESP for the field meeting will be in accordance with PG&E’s rate
schedules.
COMPLETED METER INSTALLS
PG&E will post completed meter removal and installation and maintenance work orders to PG&E’s Meter
Equipment Information Web site.
RE-SCHEDULING METER INSTALLATIONS
Site Not Ready. If at the time of the scheduled installation PG&E determines the site is not
ready, PG&E will notify the ESP.
Metering Equipment Not Available. If at the time of the scheduled installation, the metering
equipment (meter, cellular phone, etc.) is not on hand, PG&E will notify the ESP.
Other Operational Reasons. PG&E will notify the ESP of other operational reasons including,
but not limited to, regulatory compliance work, restoration of service, emergency response, new
business work load and meter repair and data recovery.
Scheduling Meter Removals and Installations - ESP as Meter Installer
The CPUC’s decision, “Opinion Regarding Direct Access Implementation Plans and Related Tariffs - 9710-087,” requires the ESP to provide UDCs with 5 business days advance notice of its meter installations.
As part of PG&E’s implementation process of the CPUC requirement, ESPs are asked to submit install
schedules no later than 3 working days prior to the scheduled date. The statewide accepted form can be
found on the CPUC Web site and includes such data fields as:

UDC order number

Customer Account number

Customer name

Install Date

XREF ID

Install Time - if one of first 20 installations
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 51

Meter Installer - if one of first 20 installations
When an installation does not occur on the scheduled date, the ESP or its designee will notify PG&E’s
Meter Event Group and advise PG&E of the status, i.e., new install date, on hold pending site access,
telecommunications not in place, etc.
Detailed Work Schedule - First Twenty Installations
In accordance with the CPUC’s Decision Regarding Permanent Standards for Metering and Meter Data,
98-12-080, a Meter Installer new to the PG&E service territory is required to provide PG&E with a
schedule of its first 20 installations, including a description of all the procedures it will follow for
removing and installing the meter, and what safety precautions it will take during those procedures.
Additionally, PG&E will exercise its right to meet with the Meter Installer for the first 20 installations
performed.
METER INSTALLATION/REMOVAL NOTIFICATION *
Within 3 business days of the meter removal and installation, the ESP shall return the MIRN (Meter
Installation & Removal Notification) to PG&E. Additionally, PG&E will post all completed MIRNs to
the PG&E Web site.
RETURN OF PG&E METERS
Within 10 business days from meter removal, the ESP must return the meter to:
PG&E Gas & Electric Meter Plant
42100 Boyce Road
Fremont, CA 94538
Attention: Marcia Holloway
Service Upgrades
PG&E highly recommends that ESPs advise their customers to contact the ESPs as soon as customers
know a service upgrade is in the planning stage. Generally, if the transfer of load to the new service is a
gradual one, a new agreement must be set up to maintain DA service. After a DASR is automatically
generated, the ESP is notified through the DASR notification process.
The coordination of a phone line installation (if applicable) and meter install and removal prior to the
service being energized is critical. Please also contact your assigned PG&E Meter Event Group
representative as soon as possible to ensure a smooth transition.
Return to Bundled Service from Direct Access and Meter Ownership
When a customer returns to bundled service from direct access and owns the interval meter, that meter
may remain in service if:
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 52

The meter meets the CPUC’s interval meter design specifications and is compatible with
PG&E’s meter reading systems.

And the customer:

Grants PG&E rights acceptable to PG&E to access, test, maintain and read the interval
meter at any time.

Pays any costs that PG&E incurs in providing metering services using the interval meter to
the extent those costs exceed the costs that PG&E would incur using a standard PG&E meter
for bundled service.

Agrees that PG&E may, at its discretion and at the customer’s expense, replace the interval
meter if it malfunctions with a standard PG&E meter for bundled service.
If the meter is not compatible with PG&E meter reading systems, the meter will be replaced at customer
expense with a standard PG&E meter.
TRANSITIONAL BUNDLED SERVICE (TBS), ALSO KNOWN AS SAFE HARBOR
On May 8, 2003 the CPUC issued Decision, D.03-05-034, the “Switching Order,” in order to adopt rules
to implement what is known as the “Switching Exemption.” The new rules, implemented on February 19,
2004 are outlined as follows:

A customer may return to Transitional Bundled Service (TBS) for a period of 80 days if the
customer’s intent is to find an ESP and continue on Direct Access Service. This period is
also referred to as Safe Harbor. Customers selecting TBS will pay spot market rates for
power for a certain period of time. (??? Aimee, should we refer the reader to the Billing
Chapter 7 or take out this last sentence about spot market rates?)

A customer may return to Bundled Service by providing six months advance notice of their
decision to the utility. During the six months, the customer may switch from one Third Party
ESP to another. Once returned to Bundled Service, the customer will have to remain on
Bundled Service for three years. The three-year minimum Bundled Service Commitment is
known as Bundled Portfolio Service (BPS).

A customer may request to return to Bundled Service without providing six months advance
notice to the utility. The customer will have to remain on Bundled Service for three years.
Customers that return to Bundled Service without six months notice will pay spot market
rates for power for a certain period of time. (??? Aimee, should we refer the reader to the
Billing Chapter 7 or take out this last sentence about spot market rates?)
To summarize, if an ESP elects to discontinue service to a customer or a customer decides to contract with
a different ESP for DA service, the customer enters TBS and then has 80 days to find a new ESP. If the
customer does not find a new ESP within 80 days, they are automatically returned to PG&E Bundled
Service for three years.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 53
The following scenarios describe how customers may switch under the new guidelines.

Direct Access Swith to Transitional Bundled Service. A DA customer returns to TBS
while looking for a new ESP. Either the customer contacts PG&E to enter TBS or the ESP
submits a Disconnect DASR, which automatically puts the customer in TBS for 80 days.

Direct Access Customer Gives Notice to Return to BPS. A DA customer who is not in
TBS wants to return to BPS. The customer gives PG&E six-months notice and remains a
DA customer. During the six-month notice period, the customer can continue to switch
between ESPs. At month 5, PG&E generates a connect DASR for the account to return to
BPS.

Direct Access Customer Requests Switch to BPS ASAP. A DA customer who is not in
TBS requests a return to BPS and the account switches per DA switching rules.

Transitional Bundled Service Defaults to Bundled Portfolio Service. A DA customer
enters TBS while looking for a new ESP. The customer is unable to find a new ESP to
generate a connect DASR within the 80-day TBS period, so the customer defaults to BPS
for three years.

Transitional Bundled Service Switch to Direct Access. A new ESP submits a connect
DASR for a customer in TBS. The account switches to DA per DA switching rules.

Transitional Bundled Service Customer Gives Notice to Return to BPS. A DA
customer switches to TBS to look for a new ESP. While in TBS, the customer decides to
switch back to BPS. When the customer gives 6 months notice, PG&E switches the account
to BPS immediately instead of waiting 6 months to perform the switch.

ESP Wants Its Meter Back. When an account switches from DA to TBS, the ESP may
contact PG&E to request its meter back. PG&E also contacts the ESP to determine whether
or not the ESP wants its meter returned. PG&E then makes arrangements to return the meter
to the ESP.

Meter Work Not Completed Within 60 Days. If meter work is not completed within 60
days of an account switch, PG&E contacts the ESP to find out if the ESP will complete the
meter work. If the ESP has completed or will complete the meter work, PG&E updates its
systems to record the meter work. If the ESP will not complete the meter work, PG&E
schedules and performs the meter change. The account then switches to DA on the meter
change date or the next read date (whichever occurs first).
ESP Inquiries
PG&E’s Meter Event Group works with ESPs to ensure that metering inquiries described below are
answered in a timely manner:

Meter phone number
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 54

Meter installations to include installation job forecasting

Research on the status/tracking of meters

Meter configuration data
To contact a MEG analyst, see DA Contacts on the ESP Web site.
For passwords, contact PG&E’s Telemetering Support Center (TMSC) at 1-800-343-7013, Option 1.
In situations where the ESP intends to use phone-read meter technology and/or selects PG&E as its
MDMA, the ESP is responsible for:

Establishing phone service

Ensuring the phone service billing in its name

Ensuring its telephone service provider installs a phone line for electric meter reading

Or ensuring it provides PG&E with an activated cellular phone upon meter install
“Metering Phone Service Providers,” Appendix B of this handbook includes the names and telephone
numbers of providers within PG&E’s service territory.
When PG&E is the ESP’s MDMA the requirements below for wired phone lines and wireless phones
apply.
WIRED PHONE LINE REQUIREMENTS
The phone line shall be a dedicated phone line. If this is not feasible, the ESP should contact ESP
Relations to discuss other alternatives. (See “DA Contacts.”)
Additionally the phone line shall be:

Installed from the phone minimum point of entry (MPOE) to the meter location. The ESP should
be aware that in some instances, the ESP may be required by the customer or phone service
provider to install a conduit, trench, or penetrate a fire wall in order to accommodate the
installation.

A “measured business” line with blocking on long distance, collect, 900, and 976 calls

Installed in accordance with applicable codes and standards

Labeled to show:

“For Electric Meter Use Only”
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 55

Telephone number

Maintenance and repair telephone number

Telephone service provider’s name
For security reasons, a telephone network interface unit (NIU) shall be installed at the phone line
termination point. A Joslyn telephone network interface model #7550, #7090 or equivalent should be
used, following the requirements below.
Generally, the NIU should not be mounted on the switchboard, meter panels, poles or pedestals. If these
are the only location choices, the mounting must be secure without compromising the safety aspects of the
particular enclosure. In the case of pole mounted terminations, the NIU should be placed below the meter
panel or otherwise not interfering with the pole climbing path.
The NIU should be installed within 5 circuit feet of the meter centerline and from a minimum of 18 inches
to a maximum of 72 inches above finished grade. (A circuit foot is the length of wire or conduit that
needs to be run along walls, etc., from the meter to the NIU. It is not a straight-line distance.)
WIRELESS PHONE INSTALLATION REQUIREMENTS
For situations in which it is not feasible for the telephone company to install a hardwired phone service,
the ESP shall arrange for a cellular telemetry system to be installed and activated.
1.
The cellular telemetry system shall meet the following specifications:

NEMA 3R weatherproof enclosure

Thermal shutoff protection

5% to 95% relative humidity, non-condensing

Cellular radio with antenna connector

Capacity to operate in 120VAC, 50 watts maximum output power

User replaceable fuse

Transient and overcurrent protection for RJ11 connections

External ground lug

One RJ11 jack for data and one RJ45 jack for communications

Two wire, loop start
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 56

Ring voltage, 25Hz, 60 VRMs 150Vp-p

350 Hz/440 Hz square wave dial tone
2.
RJ45 jack for cellular handset programming and testing
3.
The power supply for cellular telemetry system shall be outside any sealed section and on the load
side of the meter. The power supply should further be on a dedicated circuit or otherwise connected
so that it is energized at all times.
4.
Mounting of the cellular telemetry system shall be the same requirement as the installation of NIU as
described above.
5.
The ESP shall ensure that any accessories to the cellular telemetry system, such as an antenna and a
mounting bracket, are properly installed or attached.
6.
The ESP shall have the system activated and functionally tested prior to notifying PG&E that the site
is ready.
7.
The cellular telemetry system unit shall be labeled to read, “For Electric Meter Use Only.”
8.
The unit shall be further labeled to show:

Telephone number

Maintenance and repair telephone number, and

Cellular telephone service provider’s name
The ESP is responsible for the maintenance, repair and replacement of the cellular telemetry unit.
Responsibility - Phone Service Account Payment
If an active phone line exists for a PG&E interval data meter and the ESP chooses to remove the meter
and install its own, PG&E will advise the phone service provider to cancel the account.
Or in those cases where the ESP is installing phone-read technology, PG&E will change billing from
PG&E to the ESP. Some review of phone account responsibility may be required for those sites where
PG&E uses the data for load research.
Responsibility - Phone Service Operability and Maintenance
When PG&E is the ESP’s MDMA, the ESP is ultimately responsible for the on-going phone line
operability.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 57
The ESP must ensure that phone service is not turned off due to late or lack of payments to the phone
service provider. Monthly payments should be made directly to the phone service provider.
Phone lines and phone ancillary devices used for remote meter reading are part of DA meters. Therefore,
the ESP must make certain that the phone line and any ancillary devices are maintained as required. Any
failure caused by phone line or phone ancillary devices shall be considered as meter failure and must be
corrected as required in Rule 22, Section G, Metering Services.
Retention of Rights
PG&E may exercise its right to test its own meters or those owned by customers in accordance with Rule
22, Section G, paragraph 2.
Meter Data Management Agent (MDMA) Requirements
This section addresses the major systems responsibilities and requirements that Meter Data Management
Agents (MDMAs) are required to perform. An MDMA is an entity that takes raw meter outputs, validates
them using validation, editing, and estimating rules, adds corollary information needed to characterize the
customer, and makes complete customer information available to others for use in various applications.
As some of the rules and requirements for interval and monthly (template data) are different, the two
usage types will be addressed separately.
MDMA responsibilities and requirements were established in decision 97-12-048 and the Retail
Settlement and Information Flow (RSIF) Workshops. Decision and workshop reports are available for
those interested in obtaining comprehensive information on MDMA responsibilities at the CPUC Web
site.
MDMA Approval Process and Requirements
The CPUC Decision on the Meter and Data Communication Standards Workshop Report of December 3,
1997, directed the UDCs to develop a MDMA qualification/approval process for ESPs and MDMAs who
wish to offer MDMA services.
The CPUC requires that potential MDMAs comply with current UDC standards in experience, education
and training in order to perform the following functions of an MDMA:

Manage the meter reading schedule

Read and retrieve meter data

Submit meter data to MDMA server using DES protocol

Calculate usage
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 58

Validate, edit and estimate meter data

Format data

Manage data on MDMA server

Meter/device management
If the applicant is found to be compliant, the MDMA may immediately begin to serve accounts for which
the ESP has identified the specific MDMA relationship through the submission of DASRs. Inception of
MDMA service is also contingent upon the coordination between PG&E and the MDMA regarding read
scheduling.
APPLICATION AND CHECKLIST
The potential MDMA must complete the Application for MDMA Approval and checklist which are
available on the DA Documents link on the ESP Resource Center website at (see Information Websites at
the end of Chapter 1 in this handbook). The name of the document is MDMA Qualification Instructions.
The MDMA must forward the application and checklist per the specifications in the section below,
Written Requirements.
WRITTEN REQUIREMENTS
The potential MDMA forwards the completed application, the checklist as well as all written requirements
by mail or fax to:
Pacific Gas and Electric Company
Yolanda Lerma
P.O. Box 770000
M/C B19C
San Francisco, CA 94177
PG&E will review the submitted documentation of this test, determine if the potential MDMA is
compliant with its standards and notify the MDMA via e-mail. PG&E has established a goal of 10
business days to review the documentation and respond to the potential MDMA. Omitted documentation
of the submitted written requirements will result in PG&E requesting that additional information. If it is
deemed after the UDC’s review of the submitted written requirements that the potential MDMAs process
is insufficient, the potential MDMA will fail the written requirements portion and will need to resubmit
for qualification/approval.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 59
SERVER ACCEPTANCE TEST
1.
Subsequent to PG&E receiving the completed qualification documentation, the potential MDMA may
contact PG&E to schedule the acceptance test.
2.
PG&E will work with the applicant to ensure that it meets hardware and software requirements and
will also send a sample test to the applicant prior to the test date.
3.
PG&E will then provide the potential MDMA with data for the server acceptance test. The purpose
of the server acceptance test is for the potential MDMA to demonstrate that it can calculate usage,
validate, estimate and edit usage; format the usage in the Electronic Data Interchange (EDI) format;
post the data to the potential MDMA’s server; and provide the UDC with access to the server.
Detailed steps are outlined in the MDMA Server Acceptance Testing document.
4.
The acceptance test is then performed. The UDC’s have established a 48 hour turn-around time
requirement for the completion of this test.
5.
If the potential MDMA fails the server acceptance test the first time, they can reschedule for re-test.
However, if a failure occurs twice, the potential MDMA must wait three months before re-testing will
be allowed.
6.
In addition, re-testing will be required if new software is installed or if new technology is
implemented by the potential MDMA and their use of the server.
BACK-UP READING PROCESS
If the potential MDMAs primary source of reading meters is a method other than the manual process, the
potential MDMA, in addition to submitting documentation on its primary method must also demonstrate
that it has a capable back-up process in place. Details of the backup process is also outlined on the
checklist.
DATA FORMAT
MDMA data format requirements for each UDC is included with the application and checklist.
SECURITY AND CONFIDENTIALITY
Data security and confidentiality requirements are outlined in more detail by PG&E. However in general,
data must be located in a secure facility and have firewall or equivalent protection.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 60
HELP DESK
The CPUC decision requires that a technical help desk be provided by the UDCs as well as MDMAs.
Each UDC must have toll free numbers available. The potential MDMAs must provide a technical
support number as well. This phone must be answered immediately during normal business hours.
However, after hour calls regarding the server must be returned within one hour. All other after hour calls
can be deferred to the next business day.
Validating and Editing Data
The MDMA will be responsible for performing approved quality checks to the raw data retrieved from the
meters as described in the CA VEE Rules. The quality checks include validating and editing the usage
data. Upon completion of the validation and editing processes, an estimation will be performed on the
data, if necessary. Data estimations are summarized in the subsequent section “Estimating Data”. A
comprehensive description of the rules for validating, editing, and estimating is also addressed within the
CA VEE Rules document.
Below are the basic quality checks for interval and monthly data.
INTERVAL DATA
The interval data validations are summarized below. For a complete description of the rules, refer to the
CA VEE Rules (see Information Websites at the end of Chapter 1 in this handbook).
Spike Check. The highest interval recorded in a 24 hour calendar day cannot exceed the third
highest interval for that day by more than 180%. When a spike is identified, the usage for that
interval is flagged as missing and the estimation rules are used to fill the missing intervals.
High Low Average Daily Usage Check. An average daily total consumption is calculated from
the current month’s usage data and is compared to the average daily consumption calculated
from the previous year’s data for the same billing month, if last years data is not available. If the
current month’s average consumption is outside of plus or minus 50% of the historical average
consumption, then the MDMA must verify the usage (i.e., re-polling, meter test, etc.). If the data
is verified, the usage is flagged as verified and continues on the data flow path.
Sum Check. The energy use recorded by the meter is compared to the energy use recorded by
the pulse recorder. If the difference is greater than two meter multipliers (constant used to
convert meter read to KWh), the data must be verified by the MDMA (i.e., repolling, meter test,
etc.). If the data is verified, the usage is flagged as verified and continues on the data flow path.
Hardware Checks. The MDMA must ensure that the polling device is synchronized to the
national time standard before data collection begins. The MDMA must verify that the time
difference in the meter device is within 180 seconds for a 30-day time period. An interval
tolerance check comparing the number of expected data intervals to the number intervals
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 61
received is performed to ensure the time drift is less than 5 intervals. See the CA VEE Rules for
a complete description of how to correct the time drift.
Kilovolt-Ampere-Reactive hours (KVARH) Checks (if collected). If the kWh channel has
zero consumption and for the corresponding time the kVARh channel has registered
consumption, the kWh data must be treated as missing. The kWh data should be estimated using
the estimation rules described in the CA VEE Rules.
Estimating Data
Following the validation and editing (flagging usage as missing) of the usage data, the estimation routines
are performed to ensure that complete usage data will be provided for the given billing period. Where
raw data is available with incomplete entries, the MDMA will estimate the data gaps using approved and
documented algorithms. After performing the estimation the MDMA will be responsible for providing the
usage to the UDC and ESP. The following are the estimation rules for interval data.
INTERVAL DATA ESTIMATION RULES
Greater than two continuous hours of missing interval data:
1.
Compute the average daily profile by using the days from the current usage period and as
much historical data (up to 90 days) as required to select three complete days (which were
not estimated) corresponding to the day of week or holiday with missing data. See the CA
VEE Rules for additional details on how to select historical data when three complete days
worth of data are not available.
2.
If no historical holidays exist, use Sundays.
3.
The historical data used should be that data immediately preceding the usage period,
regardless of seasonal crossover.
4.
Estimate the missing data by applying the appropriate average daily profile to fill the
missing intervals.
Two hours or less of continuous missing interval data:
1.
Use the point to point linear interpolation method to estimate the missing data where there is
a gap in the data.
2.
If the gap occurs at the beginning of the span, use the last interval from the historical data as
the first point, if the historical data is available and the interval data is not estimated.
Otherwise, use the second point (the nearest good interval data) as the first point (i.e., a flat
load). If the gap occurs at the end of the span, use the first point as the second point (i.e., a
flat load).
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 62
Accuracy and Timeliness of Usage Data
All usage data will be accurate unless otherwise indicated. Data known to be inaccurate or missing will
be estimated and flagged as estimated data. The following accuracy and timeliness standards for interval
and monthly data must be followed by MDMAs. The accuracy and timeliness requirements stated below
were adopted by the CPUC in decision 97-12-048.
INTERVAL DATA
Accuracy. Either no more than 10% of the accounts will contain estimated data, or no more that 1% of
all the data will be estimated.
Timeliness. Assuming that the meter read date is time zero:

80% of all usage data will be made available within 1 calendar day of the scheduled read
date of the meter

90% of all usage data will be made available within 2 calendar days of the scheduled read
date of the meter

99.99% of all usage data will be made available within 5 calendar days of the scheduled read
date of the meter
MONTHLY DATA
Accuracy. Either no more than 10% of the accounts will contain estimated data, or no more than 1% of
the data will be estimated.
Timeliness

85% of all the monthly meter reads will be made available by 6:00 am on the 1 st working day after the
scheduled meter read date.

95% of all the monthly meter reads will be made available by 6:00 am on the 2 nd working day after
the scheduled meter read date.

99.99% of all monthly meter reads will be made available by 6:00 am on the 5 th working day after the
scheduled meter read date.
Data retention period
On a monthly basis, the MDMA will provide interval data for the billing period in 27 to 33 measured
usage intervals. The interval may or may not be equal to a twenty four hour period depending upon the
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 63
meter read cycle and scheduling. Once the interval data or the monthly usage is posted to the MDMA
server it will remain available for 3 business days. Upon request, this data will be available after the
three-day business period. The MDMA must also store 36 months of historical consumption data.
Electronic exchange of metering data
The diagram below illustrates the flow of metering information from the meter to the ESP.
Meter
MV-90
ESP
VEE
Process
Firewall
Data Exchange Server
Internal
Server
5.1 - METERING CONFIGURATION CHANGES AND METERING CHANGE OUTS
Currently, ESPs submit metering configuration changes and metering change-out requests by fax and not
by DASR. PG&E anticipates that electronic submission of these requests will be feasible by early 1998.
Metering configuration changes and metering change outs should be faxed to the MEG (see the DA
Contacts link on the ESP Resource Center website).
INTERVAL AND TIME-OF-USE (TOU) DATA
Interval data, which represents regular interval energy usage information (i.e. 5 minute, 15 minute,
hourly), is submitted via the DES in EDI 867 record format type. .
Time-Of-Use data, which is characterized by consumption reads at different time periods, is also
represented by using the DES in EDI 867record format type.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 64
Field definitions and requirements for the EDI 867 record format types are provided in the the EDI 867
Guidelines located at PG&E’s EDI website http://www.pge.com/edi .
Meter Reading
METER READING DATA OBLIGATIONS
1.
Meter data for DA Customers shall be read, validated, edited, and transferred pursuant to CPUCapproved standards.
2.
Regardless of whether the ESP or PG&E perform Meter reading services, both PG&E and the ESP
shall have access to the server containing the data, including at a minimum the following data:
a)
Customer account number;
b) Customer location;
c)
Starting and ending read, date and time if available;
d) Usage data (e.g.; kWh, kW, interval use, kVArh if measured);
e)
Estimated usage and adjustment flag or adjustment code;
f)
Meter identification number;
g) ESP identification number;
h) Identity of metering agent, if any, employed by ESP or PG&E;
i)
Load Profile ID (if applicable);
3.
PG&E and the ESP shall provide reasonable and timely access to Meter data to the ISO, Scheduling
Coordinators (or their designated agents), and each other as required to allow the proper performance
of billing, settlement, scheduling, forecasting and other functions.
4.
Until future notice, load point information will need to be communicated manually.
5.
The Party providing Meter reading services is required to keep the most recent 12 months of
Customer consumption data for each DA Customer. Such data must be retained for a period of 36
months. Such data must be released on request to any ESP, or to PG&E, if authorized by the
Customer.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 65
PG&E METER READING
1.
PG&E will read DA interval meters for DA customers on PG&E’s read schedule for each service
account provided that the meter is compatible with PG&E’s meter reading systems and processes.
The ESP will be responsible for any meter reading costs for this service as set forth in DA Rule 22.
2.
PG&E, or its metering and data management agent (MDMA), will be required to install and maintain
a data server in accordance with standards approved by the CPUC.
ELECTRIC ESP METER READING
General Requirements.
1.
No ESP may perform meter reading services for its own or any affiliated entity’s use of DA
Services.
2.
No meter reading service may be provided by theESP until that ESP has been approved by
PG&E.
3.
The ESP must keep PG&E notified at all times of the identity of the ESP’s agent, if any,
conducting Meter reading.
Schedule for ESP Meter reading. If the ESP or it’s agent perform meter reading, it must do so on
PG&E’s meter read schedule for that service account as specified by PG&E, unless a different schedule is
mutually agreed to by PG&E and ESP.
Metered Usage Rates
Metered usage rates are determined by end-use customers’ electric rate schedules. Electric rate schedule
information is available on PG&E’s Web Tariff Book Web site.
Life Support Customers and Medical Baseline Quantities
Life Support customers are residential end-use customers who have a medical disability necessitating the
use of a medical device(s) powered by utility supplied gas and/or electricity. These customers may
qualify for a Standard Medical Baseline Quantity in addition to their regular baseline quantity (i.e., gas
and/or electricity at the lowest Tier 1 residential rate). The Standard Medical Baseline Quantity is 500
kWh of electricity and/or 25 therms of gas per month year-round.
Additional amounts of gas and electricity (Medical Baseline Quantities) are available at the Tier 1 rate to
customers when a full-time member of the household is:
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 66

dependent upon a medical life-support device used in the home.

a paraplegic, hemiplegic, or quadriplegic person or a multiple sclerosis patient with special
heating and/or cooling needs.

a person being treated for a life-threatening illness or a person with a compromised immune
system with special heating and/or cooling needs to sustain the life of the person or prevent
deterioration of the person’s medical condition.

a scleroderma patient with special heating needs.
ESPs who have identified end-use customers which require Standard and/or additional Medical Baseline
Quantities should refer to Electric Rule 14 for information concerning commodity service continuity and
Rule 19 for details on end-use customer qualifications. These rules can be found within PG&E’s Web
Tariff Book.
For information on additional DASR requirements when submitting DASRs for Life Support customers,
see the subsection, “Electric ESP evaluates customer DA elections and obtains customer information” in
Chapter 3: Processing Direct Access Service Requests.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 67
CHAPTER 6
DASR PROCESSES FOR
METERING DATA
ADJUSTMENTS AND CHANGES
Overview
This chapter covers information on PG&E DASR processes that are initiated as a result of metering data
adjustments and changes to DA account commodity status. The purpose of including this information in
the handbook is to foster Electric ESPs’ understanding of the PG&E-initiated transaction records it may
receive when certain account events take place and to make Electric ESPs aware of situations in which
they may need to initiate DASR transactions in response.
The processes and scenarios addressed include those, which occur subsequent to the initial DA customer
account switch. Additional DASR processes related to initial DA account setup and switching are
discussed in Chapter 3: Processing Direct Access Service Requests, under the section heading, Additional
DASR procedures performed by PG&E.
The material addressed includes details which are specific to DES transaction record types MEPAD01
(DASR), MEPMD01, and MEPMD02. Readers may want to familiarize themselves with these record
types and gain an understanding of regular metering data records before proceeding with the material in
this chapter. For detailed information on DES DASR transactions see the DES Transaction Map link on
the DES Web site.
DA Account Commodity Status Changes
DA Account Commodity Shut-Offs
PG&E can initiate the DA account commodity shut-off process if the end-use customer requests this
action or in cases of non-payment. The processes discussed do not apply to situations where the Electric
ESP decides to discontinue service to the end-use customer.
PROCESS
Please note that the following processes apply to both monthly, TOU, demand and interval metered
accounts.
1.
When all meters associated with an account commodity have either been locked or removed, the
account commodity status is considered “Removed” or “Closed” by PG&E. Due to the frequency
with which end-use customers oftentimes change their commodity shut-off dates and also because of
the lack of lead time, PG&E will initiate disconnect notification to the Electric ESP after the final
shut-off meter read is taken and the Commodity Status of the account has been changed to
“REMOVED” or “CLOSED”.
2.
PG&E will then issue an administrative data type record, MEPAD01, to the current, pending, and any
ancillary service providers communicating the date the account commodity was shut-off. This
transaction record will reflect “SVC” within the Operation Type field, “DISCONNECT” within the
Reason field, and the date the commodity was shut-off in the Effective End Date field.
3.
PG&E will also issue the metering data record(s), MEPMD01 and/or MEPMD02 to the current
Electric ESP, and current bill-calculator if PG&E is not the MDMA. These records will include
usage information, but will not indicate that the end-use customer has been shut-off.
PG&E’s system should initiate the relevant administrative and metering data records within two (2)
business days following the account commodity status change.
MATRIX OF PG&E-INITIATED RECORDS RELATED TO SHUT-OFFS BY METER TYPE
The records indicated in the table below are issued by PG&E at the time the DA account commodity is
shut-off.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 70
ACTION
ISSUE RECORD TO
CURRENT ELECTRIC ESP,
PENDING ELECTRIC ESP,
ISSUE RECORD TO CURRENT
ELECTRIC ESP AND BILL
CALCULATOR
ISSUE RECORD TO
CURRENT ELECTRIC
ESP AND BILL
CALCULATOR
AND ALL ASSOCIATED
ELECTRIC ESPS
RECORD TYPE
ISSUED
MEPAD01
MEPMD01
MEPMD02
MONTHLY SINGLEMETERED
One MEPAD01 record:
One MEPMD01 record:
Operation Type field =
“SVC”
Normal start/end read
information record.
One MEPMD02
record:
Reason field =
“DISCONNECT”
Normal totalized
usage information
record.
Effective End Date
Field = date the account
commodity was closed
MONTHLY MULTIMETERED
Same as above
A MEPMD01 record for each
meter:
Normal start/end read
information record
A MEPMD02 record:
Normal totalized
usage information
record.
Meter field = “TOTAL”
INTERVAL SINGLEMETERED
INTERVAL MULTIMETERED
Same as above
Same as above
1.
One or more MEPMD01
record(s), depending
upon interval and period
reported: normal
(monthly, not interval)
start/end read information
record.
2.
One or more MEPMD01
record(s): normal usage
information record by
interval.
1.
One or more MEPMD01
record(s), depending
upon interval and period
reported: normal
(monthly, not interval)
start/end read information
record.
2.
One or more MEPMD01
record(s): normal usage
information record by
interval.
None
None
Meter field = “TOTAL”
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 71
ACTION
ISSUE RECORD TO
CURRENT ELECTRIC ESP,
PENDING ELECTRIC ESP,
ISSUE RECORD TO CURRENT
ELECTRIC ESP AND BILL
CALCULATOR
ISSUE RECORD TO
CURRENT ELECTRIC
ESP AND BILL
CALCULATOR
One MEPMD01 Record:
normal start/end red
information record
1.
One MEPMD02
record: normal
usage
information
record
2.
One MEPMD02
Record: normal
demand usage
information
1.
One MEPMD02
record: normal
start read
information
2.
One MEPMD02
record: normal
end read
information
3.
One MEPMD02
record: normal
usage
information
record
AND ALL ASSOCIATED
ELECTRIC ESPS
DEMAND METERED
TOU METERED
Same as above
Same as above
None
EXAMPLE
Scenario: An interval meter customer has been billed from 5/15 to 6/15. The customer requests a shutoff for 7/28.
Process:
1.
PG&E will issue the metering data record(s), MEPMD01 and/or MEPMD02, to the current Electric
ESP as well as the bill-calculator if PG&E is not the MDMA for the period 6/15 to 7/15.
2.
After the 7/28 shut-off is processed, the current Electric ESP, the pending Electric ESP, and any
ancillary service providers will receive an administrative data record MEPAD01, indicating that the
account commodity service has been disconnected and the effective date of 7/28.
3.
The current Electric ESP, as well as the bill-calculator if PG&E is not the MDMA, will receive a
metering data record MEPMD01 for the period 7/15 to 7/28. This metering record will be initiated
as soon as the shut-off has been processed, it will not be subject to the timing of the customer’s
normal billing cycle.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 72
Exception: If a Lock Pending is issued, this means the account is marked to not bill until the account
commodity is closed (i.e., there will not be a bill for on-cycle bill on 7/15). In this case, the metering
records will be for the period 6/15 to 7/28.
Meter Change
A meter change should not cause an interruption of DA service. Monthly, interval, demand, and time-ofuse (TOU) metered accounts should receive the metering records shown in the table below at the time of
the customer’s normal billing cycle.
MATRIX OF PG&E-INITIATED RECORDS RELATED TO METER CHANGE
The records indicated in the table below are issued by PG&E in correspondence with the customer’s
regular bill cycle.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 73
ACTION
ISSUE RECORD TO CURRENT ELECTRIC
ESP AND BILL CALCULATOR
ISSUE RECORD TO CURRENT ELECTRIC ESP
AND BILL CALCULATOR
RECORD TYPE
ISSUED
MEPMD01
MEPMD02
MONTHLY SINGLEMETERED

One MEPMD02 record:
One MEPMD01 record for the old
meter: normal start/end read
information
Meter field = old meter number

Normal totalized usage information record
for both meters
Meter field = “TOTAL”
One MEPMD01 record for the
new meter: normal start/end read
information
Meter field = new meter number
MONTHLY MULTIMETERED

One MEPMD01 record for each
old meter removed: normal
start/end read information
Meter field = old meter number

One MEPMD02:
Normal usage information record totalizing
usage for all meters.
Meter field = “TOTAL”
One MEPMD01 record for each
new meter installed: normal
start/end read information
Meter field = new meter number
INTERVAL SINGLEMETERED

One MEPMD01 record for the old
meter: normal monthly (not
interval)start/end read
information
None
Meter field = old meter number

One MEPMD01 record for the
new meter: normal monthly (not
interval) start/end read
information
Meter field = new meter number

One MEPMD01 record: normal
totalized usage record
Meter field = “TOTAL”
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 74
ACTION
ISSUE RECORD TO CURRENT ELECTRIC
ESP AND BILL CALCULATOR
ISSUE RECORD TO CURRENT ELECTRIC ESP
AND BILL CALCULATOR
INTERVAL MULTIMETERED

None
One MEPMD01 record for each
old meter: normal start/end read
information
Meter field = old meter number

One MEPMD01 record for each
new meter: normal start/end read
information
Meter field = new meter number

One MEPMD01 record: totalized
usage record
Meter field = “TOTAL”
DEMAND METERED

One MEPMD01 record for the old
meter: normal start/end read
information (kwhreg)

One MEPMD02 record for the old
meter: usage information (kwh)

One MEPMD02 record for the new
meter: usage information (kwh)

One MEPMD02 record for the old
meter: demand usage information (kw)

One MEPMD02 record for the new
meter: demand usage information (kw)
Meter field = old meter number

One MEPMD01 record for the
new meter: normal start/end read
information (kwhreg)
Meter field = new meter number
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 75
ACTION
ISSUE RECORD TO CURRENT ELECTRIC
ESP AND BILL CALCULATOR
ISSUE RECORD TO CURRENT ELECTRIC ESP
AND BILL CALCULATOR
TOU METERED
None

One MEPMD02 records for the old
meter: start reads information
Meter field = old meter number

One MEPMD02 records for the new
meter: start reads information
Meter field = new meter number

One MEPMD02 records for the old
meter: end reads information
Meter field = old meter number

One MEPMD02 records for the new
meter: end reads information
Meter field = new meter number

One MEPMD02 record for the old and
new meters’ totalized usage
information
Meter field = “TOTAL”
EXAMPLE
Scenario: 1/2 was the last on cycle billing read date with a read of 00500. On 1/15 there was a meter
change, and the old meter had an end read of 00550. The new meter had a start read of 00000. On 2/2
the billing cycle end read was 00060. Thus, the billing cycle usage reflects 50 kWh for the old meter and
60 kWh for the new meter for a total of 110 kWh totalized usage.
Process:
1.
PG&E will issue to the Electric ESP, the appropriate metering data type records, (MEPMD01,
MEPMD02) on 2/2. The appropriate metering data type records will show the old meter number
and new meter number start/end reads as described in the above matrix. The metering data record for
usage will indicate “TOTAL” in the Meter Field.
NEW METER SETS WHICH ARE NOT CONCURRENT WITH OLD METER REMOVALS
The example above assumes that the new meter is set on the same day that the old meter is removed. In
reality, there may be situations where the old meter is removed, but the new meter cannot be set on the
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 76
same day. In these cases, the account Commodity Status will be changed to “REMOVED” until the new
meter is set.
If the account is a dual commodity, the Commodity Status for the commodity receiving the new meter will
be changed to “OPEN” after the new meter has been set and the Account number and XREF ID fields will
remain unchanged.
If the account is a single commodity, a new account may be created after the new meter has been set. A
new XREF ID will be created if a new account number is created.
For both dual and single commodity accounts, an account status of CLOSED or REMOVED will require
PG&E’s system to initiate a disconnect notice to the Electric ESP. The Electric ESP will be required to
initiate a SP-REQ/CONNECT MEPMD01 record to re-establish the account once the Commodity Status
changes to “OPEN”.
METER CONFIGURATION DATA
PG&E will communicate the new meter configuration information to Electric ESPs through its Metering
Event Group (MEG).
Usage Adjustments
Usage adjustments occur when previously reported usage for the account requires modification. The
modification can be read and/or usage changes or changes in the reported periods (i.e., billing dates,
interval period). PG&E communicates usage adjustments to ESPs through Electronic Data Interchange
(EDI 867). The EDI 867 Guidelines has a code in the BPT segment that identifies corrected usage as
“CO” located in the BPT01. There is also an adjustment code that is in QTY01 of the EDI 867. This
code is “A5”. The QTY segment is in the PTD loop. The adjusted reads/usage records for an account will
reflect the correct reads/usage for a period which has already been reported. The metering data records
will reflect usage amounts only and not dollar values associated with usage. The initiation of adjustment
records is not dependent upon the timing of the end-use customer’s billing cycle. Therefore, PG&E can
issue adjustment records to the ESP immediately following an adjustment transaction at any time during a
billing cycle.
For more detailed information regarding usage adjustments, please refer to the EDI 867 Guidelines
located at http://www.pge.com/edi.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 77
USAGE ADJUSTMENTS TO MONTHLY METER DATA DUE TO ADDITIONAL VALIDATION
CHECKING OF DATA WHEN PG&E IS THE MDMA
One reason adjustments may occur when PG&E is the MDMA for monthly meter data is because
PG&E continues to perform validation of meter data after that data is sent to ESPs. PG&E uses
several systems to validate meter data. A metering record will sometimes pass initial validation
checks, and fail later checks. Data is sent to the ESP after the initial checks. If potential problems
are identified as the record is passed through additional tests, the information is re-verified to
determine if there is in fact an error. In many cases, the data is not in error and does not have to be
adjusted. However, when there is an error, adjustments need to be made to the data. Adjustments
made in accordance with the processes described in the subsequent sections of this document are then
sent to the ESP.
MATRIX OF PG&E-INITIATED RECORDS RELATED TO USAGE ADJUSTMENTS
The records indicated in the table below are issued by PG&E at the time the adjustment is made.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 78
ACTION
ISSUE RECORD TO CURRENT ELECTRIC
ESP AND BILL CALCULATOR
ISSUE RECORD TO CURRENT ELECTRIC ESP
AND BILL CALCULATOR
RECORD TYPE
ISSUED
MEPMD01
MEPMD02
MONTHLY SINGLEMETERED

One MEPMD02 record for each adjusted
period with the adjusted total usage
One MEPMD01 record with the
adjusted read in the Data field for
each adjusted period
Example for a two months
adjustment:
Example for a two months adjustment:
Eff Start field = “199804150001”
Data field = “199804150001,
,750,199805150001,A,1300”
Eff End field = “199805150001”
Data field =
“199805150001,A,1300,19980615
0001,A ,1650”
Eff Start field = “199805150001”
Data field = “TOTAL,A,550”
Eff End field = “199806150001”
Data field = “TOTAL,A,350”
MONTHLY MULTIMETERED

One MEPMD01 record for the
adjusted meter, with the adjusted
reads in the Data field (similar to
monthly single-metered reads
adjustment record).
One MEPMD02 record for each adjusted
period with the adjusted totalized usage for
all the meters (similar to single-metered
usage adjustment record).
Meter field = “TOTAL”
Meter field = adjusted meter number
INTERVAL SINGLEMETERED

One or more MEPMD01 record(s)
with adjusted start/end reads
information record (similar to
monthly single-metered reads
adjustment record).

One or more MEPMD01 record(s)
with adjusted totalized usage
(similar to monthly single-metered
usage adjustment record).
None
INTERVAL MULTIMETERED
Same as above.
None
DEMAND METERED


One MEPMD02 record with the
adjusted total usage in the Data field
(similar to monthly single-metered
usage adjustment record).

One MEPMD02 with the adjusted
demand usage information (similar to
the monthly single-metered usage
adjustment record).
One MEPMD01 record with the
adjusted reads in the Data field
(similar to monthly single-metered
reads adjustment record).
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 79
ACTION
ISSUE RECORD TO CURRENT ELECTRIC
ESP AND BILL CALCULATOR
ISSUE RECORD TO CURRENT ELECTRIC ESP
AND BILL CALCULATOR
TOU METERED
None

One MEPMD02 record with the
adjusted start reads information

One MEPMD02 record with the
adjusted end reads information

One MEPMD02 record with the
adjusted totalized usage information
EXAMPLE
Scenario: A monthly metered account has been billed in the following manner and the normal
MEPMD01 and MEPMD02 record(s) have already been sent to the Electric ESP when the account was
billed:
ELECTRIC ESP
NAME
DATE
MEPMD02
USAGE
MEPMD01:
START READ
END READ
PG&E
2/15 -3/15
400 KW H
0
400
PG&E
3/15 - 4/15
350 KW H
400
750
ESP
4/15 - 5/15
500 KW H
750
1250
ESP
5/15 - 6/15
400 KW H
1250
1650
On 6/23 a correction is made to the period 4/15 - 5/15. The usage for the period should have been
reported as 550 kWh with an end read of 1300. Then on 6/26 a correction is made to the period 5/15 6/15. The usage should have been 350 kWh with an end read of 1650.
Process:
Under the given scenario PG&E would issue the records shown in the table below when the adjustment is
made to the account.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 80
TIMING ORDER
RECORD TYPE
ISSUED
DATA INCLUDED IN RECORD
1.
MEPMD01
Data field = 199804150001, ,750,199805150001,A,1300
2.
MEPMD02
Eff Start field = 199804150001
Eff Stop field = 199805150001
Data field = TOTAL,A,550
3.
MEPMD01
Data field = 199805150001,A,1300,199806150001,A,1650
4.
MEPMD02
Eff Start field = 199805150001
Eff Stop field = 199806150001
Data field = TOTAL,A,350
Records for items 1 and 2 will be sent on the same day (6/23) when the bill period 4/14 - 5/15 is adjusted.
Then the records for items 3 and 4 will be sent on the same day (6/26) when the bill period 5/15 - 6/15 is
adjusted. The timing between the sending of the two sets of records will be around 3 days and based on
when each adjustment transaction is processed.
STAND ALONE REBATE TRANSACTIONS (REVERSAL ONLY ADJUSTMENT)
Under some circumstances only a rebate transaction will need to be made to the account. A rebate is a
reversal of what was originally billed. This business scenario may occur when PG&E needs to reverse a
bill and then wait for the next on cycle bill to rebill the account. In this situation, PG&E’s system will
wait for three (3) processing days after a rebill transaction is processed by the biller. If the rebill
transaction does not occur within three (3) processing days of the rebate, the system will interpret the
rebill as an reversal only adjustment and send the rebate as a meter adjustment record reversing the reads,
and with 0 usage. When the rebill transaction is eventually processed through the system, then the rebill
transaction will be sent to the Electric ESP’s as adjusted reads/usage records.
Using the same scenario as the previous example, adjust the billing for the bill period of 5/15 - 6/15. The
adjustment is to just reverse the bill and let next month’s on cycle read generate the rebill. So, on 6/20, a
reversal is processed. On 6/23, the system did not receive the rebill for 5/15 to 6/15, so it assumed the
biller wanted to do just a reversal only adjustment. The system will send to the Electric ESP the following
records on 6/23:
MEPMD01 - DATA field = 199805150001,A,1250,199805150001,A,1250
MEPMD02 - Eff Start field = 199805150001 Eff Stop field = 199805150001 DATA field = TOTAL, A,0
On 7/15 - the next on cycle billing, the following records will be sent. Note that since the billing period
includes the bill period that was reversed, the quality code will be A to indicate an adjustment to a
previously sent metering data record.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 81
MEPMD01 - DATA field = 199805150001, ,1250,199807150001,A,1850
MEPMD02 - Eff Start field = 199805150001 Eff Stop field = 199807150001 DATA field =
TOTAL,A,600
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 82
CHAPTER 7
ELECTRIC ESP ACCOUNT
BILLING
Overview
This chapter focuses on ongoing DA billing and credit related issues, which are not a part of the initial
DA setup process. The material covers bill processing; the collection and disbursement of funds for either
PG&E or the Electric ESP with respect to Consolidated UDC billing; Consolidated ESP billing, and
Separate billing.
Bill Components and Billing Options
Summary of bill components
Utility bills which are sent to end-use customers are required to show “unbundled” charges listed on the
bill. These unbundled charges consist of the following components:

Generation

Transmission

Distribution

Public Purpose Programs (PPP)

California Energy Commission Tax (ECT)

CTC

Nuclear Decommissioning

Energy Procurement Surcharge
About the California Energy Commission Tax
In keeping with the developments of electric direct access, the California State Board of Equalization
decided that the Energy Commission Tax (ECT), will be billed and collected by PG&E, for all UDC
Consolidated Billing. The utility distribution company will cease billing of this tax immediately when the
customer’s service is switched to direct access. The customer’s current Electric ESP will assume the
responsibility of billing and collecting this tax from the customer effective with the direct access service
switch date. The Electric ESP is responsible for remitting the ECT to the California State Board of
Equalization.
The ECT, also known as the California Energy Resources Surcharge, applies to the consumption of
electrical energy. It is intended to provide funding for the California Energy Commission. The
regulations for ECT are covered in the California Administrative Code, Title 18, Chapter 2, Subchapter 5,
Article 1, which states:
“Every electric utility making sales of electrical energy to consumers in this state shall collect the
surcharge from each consumer other than a consumer that is an electric utility or is exempt under
Chapter 3, part 19, of the Revenue and Taxation Code, at the time it collects its billing from the
consumer for the electrical energy sold. A consumer is any person receiving electrical energy
furnished by an electric utility and includes a person receiving electrical energy for redistribution
for the use of this tenants.”
The ECT rate, which is subject to revision from time to time, is currently set at two-tenths of a mil
($0.0003) per kilowatt-hour. It is shown as a separate line item on the customer’s bill.
The ECT is based on the consumption of electrical energy and applies to all but the following end-use
customers:
1.
The United States, its unincorporated agencies and instrumentalities
2.
Any incorporated agency or instrumentality of the United States wholly owned by either the United
States or by a corporation wholly owned by the United States
3.
The American National Red Cross, chapters, and branches
4.
Insurance companies, including title insurance companies, subject to taxation under the California
Constitution, Article XIII, Section 28
5.
Indians purchasing and consuming electrical energy on Indian reservations
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 84
6.
Career consular officers and employees of certain foreign governments who are exempt from tax by
treaties and other diplomatic agreements with the United States
7.
Federal credit unions organized in accordance with the provisions of the Federal Credit Union Act.
Questions regarding the tax exemption and remittance timelines should be directed to the State Board of
Equalization. Additional information may be found in the Revenue and Taxation Code.
Billing options
Customer bills will reflect the total amounts charged for each of the bill items described in the table above
regardless of the billing option which the customer chooses at the time of DA sign-up. Again the billing
options available to end-use customers are:
CONSOLIDATED UDC BILLING
Under the Consolidated EDC billing option, the Electric ESP will send its rate schedules to PG&E.
PG&E will then compute the Electric ESP’s charges based upon the Electric ESP’s rate schedules and
customer meter data and send a consolidated invoice to the DA customer which will include both Electric
ESP’s and PG&E’s charge amounts. Rate schedule information is available within PG&E’s Web Tariff
Book Web site.
PG&E will purchase the Electric ESP’s receivables under the terms and conditions set forth in PG&E’s
tariffs.
CONSOLIDATED ESP BILLING
Electric ESPs who elect to offer Consolidated ESP billing may choose Partial Consolidated ESP billing or
Full Consolidated ESP billing pursuant to PG&E’s DA Rule 22. Prior to providing either of these billing
options, the Electric ESP must meet CPUC-specified creditworthiness requirements. The differences
between Partial Consolidated ESP and Full Consolidated ESP billing options are described below.
PARTIAL CONSOLIDATED ESP BILLING
Under Partial Consolidated ESP billing, PG&E will calculate and send its bill to the Electric ESP. The
Electric ESP in turn will then send a consolidated bill to the customer. The Electric ESP is not
responsible for the accuracy of PG&E’s charges.
FULL CONSOLIDATED ESP BILLING
Under the Full Consolidated ESP billing option, the Electric ESP will read the meter, calculate both the
UDC and ESP charges and bill the customer. The Electric ESP will detail PG&E’s charges in
conformance with PG&E’s specifications. The Electric ESP must obtain PG&E’s consent and approval
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 85
prior to offering Full Consolidated ESP billing to its customers, and must also comply with all relevant
provisions under PG&E’s DA Rule 22.
SEPARATE BILLING
Under Separate billing, customers receive two bills, one from the Electric ESP detailing their fees and one
from PG&E detailing PG&E fees.
Although an Electric ESP can select Separate billing as a service option, PG&E may also under certain
circumstances require an Electric ESP to proceed under Separate billing for reasons including but not
limited to the items below.

If the Electric ESP selected Consolidated UDC billing but the ESP’s rate schedule was not properly
received when the DASR was transmitted, PG&E will establish Separate billing for the corresponding
end-use customers. Consolidated UDC billing, in this case would be established once the Electric
ESP resubmitted the rate schedule and the schedule data was entered into PG&E’s systems.

If the current Electric ESP has defaulted on the terms and conditions of ESP Consolidated billing
under either PG&E’s ESP Service Agreement or DA Rule 22, PG&E will establish separate billing
for that end-use customer.

If an Electric ESP has indicated that it would like to offer Consolidated ESP billing but has not
fulfilled creditworthiness and/or EDI requirements, PG&E will require the Electric ESP to proceed
under Separate billing.
Read and Bill Serial Dates
Because multiple services may be represented on one bill, the meter Read Date will not always be equal to
the Bill Date. PG&E will retain the serial system currently in use and apply it towards the Read and Bill
cycles. Both Read and Bill serials will be communicated to the ESP via the acknowledgement (ACK)
DASR.
Consolidated UDC Billing
The Electric ESP and PG&E will work together to establish the ESP’s billing information in PG&E’s
billing system. For a fee, PG&E can generate Consolidated UDC bills for Electric ESPs and serve as the
collection agent as well. Set up fees are based upon PG&E rate schedule E-ESP.
When DA begins, PG&E will offer Electric ESPs Rate Ready pricing options. In order to calculate the
Electric ESPs charges for Rate Ready options, PG&E will need the rate structure(s) and rate schedules
that the Electric ESP has selected. The Electric ESP may have up to 100 rate schedules. The Electric
ESP will then populate the rate schedules with their respective rates and prices.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 86
Pricing options
Electric ESPs communicate Rate-ready pricing options by completing the PG&E Consolidated Billing
Pricing Worksheet. The following exhibit is an example of the worksheet.
7.1 - PG&E CONSOLIDATED BILLING PRICING W ORKSHEET
The Electric ESP must complete and submit the PG&EConsolidated Billing Pricing Worksheet for every
pricing change that it wants to make. The worksheet can be downloaded from the “DA Documents” link
on the PG&E’s ESP Resource Center Web site or obtained by contacting ESP Services at 415-973-1666.
Completed worksheets should be faxed to ESP Services at 415-973-2194.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 87
The following Rate Ready pricing options will be available in on the DA implementation date:
FLAT ($/MONTH)
Also referred to as fixed price, a flat rate structure is a non-volumetric set cost that is billed per month
regardless of the amount of the customer’s usage.
An additional flat rate to cover monthly Electric ESP administrative customer charges may be combined
with this rate structure.
SINGLE-TIERED ($/KWH)
A single-tiered rate structure is a set cost billed per usage unit (kilowatt-hour or therm). The customer’s
energy charge will vary according to the amount of electricity consumption per month.
A flat rate to cover monthly Electric ESP administrative customer charges may be combined with this rate
structure.
DOUBLE-TIERED ($/KWH, ELECTRIC ESP DESIGNATES TIERS)
A double-tiered rate structure has two set costs billed per usage unit (kilowatt-hour or therm) which is
charged whenever a usage baseline or threshold is designated. The first-tier price will apply until the
usage threshold is exceeded. The second-tier price will apply to any usage above the designated
threshold. The customer’s energy charge will vary according to the amount of electricity consumption per
month.
A flat rate to cover monthly Electric ESP administrative customer charges may be combined with this rate
structure.
TIME-OF-USE - TOU ($/KWH, BASED ON PG&E’S TIERS)
A TOU structure is a combination of set costs billed per usage unit (kilowatt-hour or therm) based on
consumption during a particular period of the day. Depending on the customer class and the installed
metering device, TOU pricing may have up to three different rates for three different peak periods. The
TOU periods are on-peak, partial-peak, and off-peak. Rates are more expensive during the on-peak
periods, when more customers demand energy. Customers may tailor their energy consumption during the
off-peak hours to take advantage of the low off-peak rates. The customer’s energy charge will vary
according to the amount of electricity consumed during a particular time of the day.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 88
CUSTOM PRICING
A rate plan that does not fit with any of the above four pricing structures is considered custom pricing.
On an individual case basis, PG&E will evaluate an Electric ESP’s customized pricing structure to
determine whether it can be accommodated and implemented by PG&E.
SUBMITTING RATE-READY DATA TO PG&E
Electric ESPs should contact PG&E’s ESP Billing Services (ESPBS - see the “DA Contacts" link on
PG&E’s ESP Resource Center Web site) to discuss transmission requirements prior to submitting rateready data.
DEADLINES FOR THE SUBMISSION OF RATE-READY DATA
In order for PG&E to send out consolidated bills which include Electric ESP billing information for a
given DA billing cycle, the Electric ESP must provide the following information to ESPBS by the dates
specified:

Electric ESP billing rates and structures at least thirty (30) days prior to the billing cycle end date.

Customer list with associated Electric ESP billing rates at least fifteen (15) days before the billing
cycle end date.
There is a fee for a rate change based on PG&E’s rate schedule E-ESP. If the Electric ESP should require
custom programming, ESPBS will make a concerted effort to fulfill the requirements specified within the
time frame above but cannot guarantee billing implementation for that billing cycle period.
Bill format
PG&E will include the Electric ESP’s logo on the page of the customer’s bill which details Electric ESP
charges. However, the Electric ESP must provide ESPBS with the company information that must appear
on the bill (i.e. Electric ESP’s name, address, telephone number) as well as the Electric ESP’s company
logo. The logo should be provided in the form of a bitmap image file. All details regarding the Electric
ESP bill page format are addressed in the Direct Access Consolidated Billing Options Worksheet which
can be located and downloaded from the “DA Documents” link on the ESP Resource Center Web site.
Bill preparation and processing
PG&E will prepare the consolidated bill according to the procedures outlined below.
1.
PG&E will calculate the Electric ESP’s energy cost charges. The Electric ESP’s rate schedule is used
to calculate the energy cost component. Information regarding the submission of rate schedule
information by the Electric ESP is covered within Chapter 3: Processing DASRs.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 89
2.
PG&E’s charges for transmission, delivery, PPPs, CTC, and other charges that may apply to a given
customer, are calculated separately using the customer’s PG&E rate schedule.
3.
The Electric ESP’s charges are then combined with PG&E’s charges onto one bill.
4.
Utility user taxes, if applicable, are calculated on the total of the PG&E and Electric ESP combined
charges.
5.
Other processing functions such as the update of receivables, payments, credits, debits, and other
adjustments are performed by PG&E to generate the Consolidated UDC bill.
Bill Printing and Delivery
1.
Bills will follow the format designated by the Electric ESP in the Direct Access Consolidated Billing
Options Worksheet, to include the layout, logos, and other enclosures specified.
2.
A printed copy of the bill is mailed to end-use customers on Summary Billing and to those end-use
customer not on Electronic Data Interchange (EDI).
3.
If the customer has an EDI Trading Partner Agreement in place with PG&E and has followed the
requirements for implementing EDI as outlined in Chapter 2: DA Setup, PG&E can submit invoices
to the end-use customer electronically.
Reports generated by PG&E
Since the billing process is a collaborative effort, it requires constant communication between the Electric
ESP and PG&E. Reports are the method by which PG&E and the Electric ESP coordinate their
consolidated billing effort. Reports are sent manually by PG&E in an electronic format, to the Electric
ESP. Contents of the report include data relating to rate schedule changes and billed data and revenue.
Reports are created daily.
Daily Billing File
The daily billing file consists of two sections. The first section includes the billing data. He second
section includes any adjustments made to a particular bill.
Utility User Tax Application
Under the rate-ready billing type, PG&E will calculate any applicable utility user taxes on the total of the
PG&E and Electric ESP combined charges. PG&E will apply the utility user tax, including exemptions
and caps based on PG&E’s agreement with the governing cities and counties in PG&E’s service territory.
Under the bill-ready billing type, PG&E, will apply utility user taxes on the Electric ESP’s charges.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 90
Remittance of utility user tax is the responsibility of each party, PG&E, and Electric ESP for their
respective taxable charges. PG&E will report the taxes billed on the Electric ESP charges to the Electric
ESP. PG&E will only remit the utility user tax collected to the Electric ESP. The Electric ESP is
responsible for remitting the utility user tax to the governing authority.
How PG&E calculates Electric ESP payments
WHEN A CUSTOMER MAKES PAYMENT TO PG&E
The portion due to the ESP is then forwarded on the the ESPs financial institution. This is done via ACH
wire fund transfer, using banking data provided by the ESP.
Because the amount deposited to the bank is one lump sum, PG&E then sends to the ESP an electronic
file which lists the detail for that deposit (customers’ names, account ID’s and associated remittance
amounts) since this payment file is sent automatically, the ESP must provide PG&E with one e-mail
address where the report is to be sent.
PAYMENTS FROM ELECTRIC ESP TO PG&E
Payments from the Electric ESP to PG&E encompass service charges for billing services, which PG&E
provides on behalf of the Electric ESP. The Electric ESP will be responsible for the payment of PG&E’s
charges on an ongoing basis while Consolidated UDC billing is in effect. Charges are dependent upon the
transactions incurred during a given month, and Electric ESPs are billed once a month for these charges
by PG&E. Service charge amounts billed can vary for each account specified under the Consolidated
UDC billing option. Charges associated with Consolidated UDC billing are specified on PG&E’s Web
Tariff Book Web site. PG&E, upon ten (10) days written notice, may net any past due payment for
associated Consolidated UDC billing services, as outlined in Rate Schedule E-ESP (see PG&E’s Web
Tariff Book Web site), against payments by PG&E on the Electric ESP’s accounts receivable.
Consolidated ESP Billing
Consolidated ESP billing involves the transmission of charges for transmission, distribution, PPP, and
CTC from PG&E to the Electric ESP.
BILL FORMAT REQUIREMENTS
PG&E requires that Electric ESPs provide detailed page showing PG&E related charges according to a
standardized format. Electric ESPs should consult the PG&E Bill Format for Consolidated ESP Billing
document for detailed requirements on the representation and transmission of PG&E billing information.
The document can be downloaded from the “DA Documents” link on the ESP Resource Center.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 91
CALCULATION OF CHARGES OWED TO PG&E
PG&E calculates charges for a given service account’s electric transmission and distribution services.
Transmission and distribution charge information is then sent electronically to the Electric ESP for
inclusion in the Electric ESP’s bill.
PAYMENT PROCESSING
Once PG&E’s charges are calculated, these charges are transmitted to the Electric ESP through Electronic
Data Interchange (EDI). The Electric ESP is responsible for payment to PG&E regardless of whether or
not it receives payment from the end-use customer. The Electric ESP must submit payments to PG&E via
EDI as discussed below.
ELECTRONIC DATA INTERCHANGE (EDI)
Electric ESPs wishing to provide billing services for PG&E must meet EDI requirements (see Chapter 2:
DA Setup for detailed information). EDI is the adopted standard for the transmission of charge
information from PG&E to the Electric ESP and for PG&E’s subsequent receipt of payments from the
Electric ESP. Service accounts that are billed through Consolidated ESP billing must be added to the list
of EDI customers for a given Electric ESP.
Separate Billing Procedures
Under the Separate billing option, both PG&E and the Electric ESP will bill the end-use customer
individually for their respective charges. Neither billing nor payment information is exchanged between
the Electric ESP and PG&E since each entity is responsible for the billing and collection of payments
associated with Separate billing service accounts.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 92
CHAPTER 8
CUSTOMER INFORMATION
RELEASES
Overview
This chapter provides information on how Electric ESPs participating in DA with PG&E can obtain
certain types of customer information.
Confidential Customer Information Release
Electric ESPs have the opportunity to request customer specific information that includes energy usage for
the last 12 billing transactions.. In order to request information for a customer, the Electric ESP will be
required to obtain and provide ESP Services with a signed Customer Information Release form and
indicate the specific customer account number(s). The form can be obtained from the “DA Documents”
link on the ESP Resource Center website. The signed form should be faxed to Robert Reeder at (415)
973-2194 or e-mailed to rwr6@pge.com.
The following data will be provided in the customer information release:

Service ID

Meter Number

Customer Name

Meter Read Date (current/prior)

Service Address

Billing Cycle Days

Billing Address

TOU Split (Demand & Energy)

SIC 2

Total revenue for last 12 billing periods

Rate Schedule

Total kWh for last 12 billing periods
Note: Load research sample data will not be included in the release of customer
information.
PG&E will forward the information described above within 10 working days of its receipt of the Electric
ESP’s request. PG&E will provide DA customer data free of charge for up to two times a year. However,
a charge of $40.00 per data set will apply to subsequent requests. Data format options include hard copy
report, floppy disk or e-mail file.
Regarding a request status contact Robert Reeder at (415) 973-5480 or e-mail rwr6@pge.com.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 94
GLOSSARY
DIRECT ACCESS TERMS
APPLICANT
A person or agency requesting PG&E to supply electric service or for charges in electric
service. Electric service may consist of both energy and energy related services.
APPLICATION
An oral, electronic, or a written request to PG&E for electric service; not an inquiry as to the
availability or charges for such service. The form of the request shall be at PG&E’s discretion.
BASELINE
A rate structure mandated by the California Legislative and implemented at PG&E in 1984 that
insures all residential customers are provided a minimum necessary quantity of electricity at the
lowest possible cost.
BILLING AGENT
The billing agent prepares and submits bills to end-use customers; collects and processes
payments; and remits aggregate funds and records to its clients.
BILLING CYCLE
The regular interval at which a bill for electric service is rendered; typically spans a 27 to 33 day
period.
BILLING DEMAND
The demand on which the customer is to be billed in accordance with the terms and conditions
of their applicable rate schedule.
BILLING FACTOR
Factor used to calculate a bill on a daily basis as opposed to monthly, when the billing period is
other than 27 to 33 days. All rate schedules assume monthly billings of 27 to 33, and the Billing
Factor for these billings is equal to 1. The factor is used to adjust flat monthly charges (such as
fixed usage accounts), monthly customer, monthly meter, and minimum service charges to
monthly parity when an account is billed for fewer than 27 days (Billing Factor is less than 1), or
when billed for more than 33 days (Billing Factor is greater than 1). The factor is based on 365
days divided by 12 months, which is 30.4166, the number of average days in an average
month. The billing Factor formula is:
Billing Factor = Number of Billing Days divided by 30.4166
BILLING MONTH
The period of time over which a customer is billed for services rendered during a particular
billing cycle.
BILLING SERVICE DATE
The effective date for commencement of either of the direct Access Consolidated Billing
options.
BUSINESS DAY
A day on which PG&E offices are open to conduct general business in California.
COMMISSION
The Public Utilities Commission of the State of California, sometimes referred to as the Public
Utilities Commission (PUC) or the CPUC.
COMPETITIVE TRANSITION
CHARGE (CTC)
Defined in Public Utilities Code Section 840 and by the Commission.
CONNECTED LOAD
The sum of the rated capacities of all the customer’s equipment that can be connected to
PG&E’s lines at any one time as more completely described in the rate schedules.
CPUC (CALIFORNIA PUBLIC
UTILITIES COMMISSION)
The Public Utilities Commission of the State of California.
CURTAILMENT
The temporary reduction or interruption of service to customers because of projected or actual
supply or capacity constraints, as further defined in Rule 14 and PG&E’s Electrical Emergency
Plan. PG&E may also request such load reduction under the provisions of its nonfirm
programs.
CUSTOMER
The person, group of persons, firm, corporation, institution, municipality, or other civic body, in
whose name service is rendered, as evidenced by the signature on the application, contract, or
agreement for that service, or in the absence of a signed instrument, by the receipt and
payment of bills regularly issued in that name, regardless of the identity of the actual user of the
service. a customer may take Full Service or Direct Access Service, but must take final
delivery of electrical power, and not resell that power.
DEMAND
The amount of energy drawn by a Customer at a specific time. Typically expressed in kilowatts
or kW.
DEMAND CHARGE
One component of an electric customer’s bill (along with, but not limited to, the customer
charge, meter charge, and the energy charge). This charge recovers some of the costs PG&E
incurs in providing sufficient operating capacity to meet that customer’s maximum demand.
The demand charge is based on the highest level of kW required by the customer during a
billing period.
DIRECT ACCESS METER
A meter meeting the Commission’s requirements to support Direct Access Service to a Direct
Access Customer not eligible for a Load Profile.
DIRECT ACCESS SERVICE
Defined in Rule 22.
DIRECT ACCESS SERVICE
REQUEST (DASR)
An application for Direct Access Service submitted to PG&E on behalf of a Customer by an
Electric ESP, as described in Rule 22.
DISTRIBUTION LOSS FACTORS
The loss of energy over distribution lines are categorized into two distinct loss factor types:
Distribution Line Losses and Total Distribution System Losses.
Distribution Line Losses consist of:


losses due to resistance in the distribution lines
transformer core losses
Total Distribution System Losses consist of:



DISTRIBUTION SERVICES
distribution line losses
metering error - the difference between the actual electric usage at the meter
and the recorded meter read plus any differences due to malfunctioning meters
energy theft - the deliberate and unauthorized use of energy
The delivery of electrical supply and related services by PG&E to a customer over PG&E’s
Distribution System.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 96
DISTRIBUTION SYSTEM
Those non-ISO transmission and distribution facilities owned, controlled, and operated by
PG&E that are used to provide Distribution Service under these tariffs.
ELECTRIC SUPPLY OR
PROCUREMENT SERVICES
Includes, but is not limited to, procurement of electric energy; all scheduling; settlement, and
other interactions with Scheduling Coordinators, the ISO and the PX; all ancillary services and
congestion management.
ELECTRONIC DATA INTERCHANGE
(EDI)
The electronic transmission and receipt of data and/or funds in agreed upon formats in
accordance with PG&E’s specifications.
ENERGY SERVICE PROVIDER
(ESP)
An entity who provides electric supply services to DA Customers within PG&E’s service
territory. An ESP may also provide certain metering and billing services to its DA Customers as
provided for within these tariffs.
FIXED TRANSITION AMOUNT (FTA)
CHARGE
A non-bypassable, separate charge that is authorized by the Commission to be charged to
residential and small commercial customers to allow PG&E to recover financed transition costs
and the costs of providing, recovering, financing or refinancing transition costs, including the
costs of issuing, servicing, and retiring Rate Reduction Bonds.
FULL SERVICE
As defined in Rule 22.
GENERATION CUSTOMER
Any PG&E electric customer with electric generation facilities (including back-up generation in
parallel with PG&E) on the customer’s side of the interconnection point.
INDEPENDENT SYSTEM OPERATOR
(ISO)
The California Independent System Operator Corporation, a state chartered, non-profit
corporation that controls the transmission facilities of all participating transmission owners and
dispatches certain generating units and loads. The ISO is responsible for the operation and
control of the statewide transmission grid.
KILOWATT
1,000 watts; a watt is a unit of electrical power equal to a current of one ampere under one volt
of pressure.
KILOWATT-HOUR
1,000 watts, or one (1) kilowatt of electricity used for one hour.
LOAD PROFILES
An approximation of a Customer’s electric usage pattern as approved by the Commission for
certain purposes set forth in PG&E’s tariffs.
MASTER-METERED CUSTOMER
A PG&E Customer who takes Full or Direct Access Service at a single “master meter” and
distributes electric supply, by its own means, to tenants within its own premises. The
availability of master metering is limited by Rule 18 and the P.U. Code.
MASTER-METERING
Where PG&E installs one service and meter supply more than one residence, apartment
dwelling unit, mobile home space, store, office, etc.
METER
The instrument that is used for measuring the electricity delivered to the Customer. In certain
circumstances, the terms “meter” or “metering” also include related metering facilities or
equipment.
METER DATA MANAGEMENT
AGENT (MDMA)
the entity that takes raw meter outputs, validates them using validation, editing, and estimating
rules, adds corollary information needed to characterize the customer, and makes complete
customer information available to others for use in various applications.
METER SERVICE PROVIDER
(MSP)
The entity that installs, validates, registers, and maintains the physical meter required on a
premise to measure the required variables.
METERING FACILITIES OR
A meter, its associated current and potential transformers, test facilities, communication
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 97
METERING EQUIPMENT
interfaces, and other associated metering equipment required for the measurement of supply
deliveries to a Customer’s Account.
OPTIONAL RATE SCHEDULES
Commission-approved rate schedules for a customer class from which any customer in that
class may choose. Optional rate schedules do not include experimental schedules or
schedules available at the sole option of PG&E.
PAID OR PAYMENT
Funds received by PG&E through the postal service, PG&E payment office, PG&E authorized
agent, or deposited in PG&E’s bank account by Electronic Data Interchange.
PERSON
Any individual, partnership, corporation, public agency, or other organization operating as a
single entity.
POWER EXCHANGE (PX)
The California Power Exchange Corporation, a state chartered, non-profit organization charged
with establishing a competitive spot market for electric power through day and hour ahead
auction of generation and demand bids, in accordance with the PX Tariff.
POWER EXCHANGE SUPPLY COST
PX supply costs will be shown as either the cost of PX energy purchased by PG&E for a full
Service Customer’s use, or the credit for a Direct Access Customer.
POWER FACTOR
The percent of total power delivery (kV) which does useful work. for billing purposes, average
power factor is calculated from a trigonometric function of the ratio of reactive kilovolt-amperehours to the kilowatt-hours consumed during the billing month.
PREMISES
All of the real property and apparatus employed in a single enterprise on an integral parcel of
land undivided, excepting, in the case of industrial, agricultural, oil field, resort enterprises, and
public or quasi-public institutions, by a dedicated street, highway or public thoroughfare or
railway. Automobile parking lots constituting part of land adjacent to a single enterprise may be
separated by an alley from the remainder of the Premises served.
PUBLIC PURPOSE PROGRAMS
CHARGES
A non-bypassable surcharge imposed on all retail sales of electricity and electrical services to
fund public goods research, development and demonstration, energy efficient activities, and low
income assistance programs.
PUBLIC UTILITIES COMMISSION
The Public Utilities Commission of the State of California.
QUALIFIED CONTRACTOR/
SUBCONTRACTOR (QC/S)
An applicant’s contractor or subcontractor who:

is licensed in California for the appropriate type of work such as, but not limited
to, electrical and general;

employs electric workmen properly qualified (Qualified Electrical Worker,
Qualified Person, etc.) as defined in State of California High Voltage Safety
Orders (Title 8, Chapter 4, Subchapter 5, Group 2); and

complies with applicable laws such as but not limited to, Equal Opportunity
Regulations, OSHA, and EPA
RATE SCHEDULE
One or more tariff sheet(s) setting forth the charges and conditions for a particular class or type
of service in a given area or location. A rate schedule includes all of the wording on the
applicable tariff sheet(s), such as Schedule number, title, class of service, applicability, territory,
rates, conditions, and references to rules.
RULES
Tariff sheets which cover the application of all rates, charges, and services when such
applicability is not set forth in and as part of the rate schedules.
SCHEDULED METER READING
The date PG&E has scheduled a Customer’s meter to be read for the purposes of ending the
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 98
DATE
current billing cycle and beginning a new one. PG&E’s meter reading schedule is published
annually, but is subject to periodic change.
SCHEDULING COORDINATOR
An entity meeting requirements as set forth by the Commission, FERC, and these tariffs.
SERVICE ID
A PG&E-specific identifier for tracking energy service deliveries for a specific load through one
or more meters at a customer premises or location. one customer may have several accounts
within a premises or throughout PG&E’s service territory.
SETTLEMENT QUALITY DATA
With respect to metering, validated or estimated interval data that is formatted into hourly usage
data. This data includes monthly cumulative data that has been converted to an hourly format
by the application of an approved load profile.
SETTLEMENT READY DATA
With respect to metering, settlement quality data that has had the appropriate distribution loss
factors applied and is aggregated for delivery to the scheduling coordinator.
SUBMETERING
Where the master-metered customer installs, owns, maintains, and reads the meters for billing
the tenants in accordance with Rule 18.
TARIFF SHEET
An individual sheet of tariff schedules.
TARIFFS
The entire body of effective rates, rentals, charges, and rules, collectively, of PG&E, including
title page, preliminary statement, rate schedules, rules, sample forms, service area maps, and a
list of contracts and deviations.
TIME-OF-USE
Rate option that prices electricity according to the season or time of day that it is used. Such
usage is aggregated into discrete time periods, which are called “TOU” periods and are as
specified in the PG&E rate schedules.
TRANSMISSION LOAD CUSTOMER
A PG&E electric customer, interconnected to PG&E’s power system at a transmission level
voltage, who has no generation of its own paralleled with the PG&E system and is not
interconnected with any generation source other than PG&E.
UTILITY
Pacific Gas and Electric Company (PG&E).
UTILITY USERS TAX
A tax imposed by local governments on PG&E’s customers. PG&E is required to bill customers
within the city or county for the taxes due, collect the taxes from customers, and then pay the
taxes to the city or county. The tax is calculated as a percentage of the charges billed by PG&E
for energy use.
XREF ID
A unique non-changing customer-commodity-location specific number. Once the XREF ID has
been assigned to a DA commodity account, it will not change throughout the life of the account
unless DA is cancelled. Essentially, the XREF ID provides a way to readily identify DA
commodity accounts and to reference the history of the commodity even if the customer
switches to different ESPs.
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 99
APPENDIX A
SERVICE TERRITORY CITY
CODES
CITY CODE LETTERS CORRESPOND TO THE SECOND AND THIRD CHARACTERS OF THE CUSTOMER ACCOUNT NUMBER.
CITY NAME
CITY
CODE
ACADEMY
TK
ACAMPO
AK
ADAMS SPRINGS
ZH
AGNEW
VP
AGUA CALIENTE
NV
AHWAHNEE
AE
ALAMEDA
JP
ALAMO
AL
ALBANY
AB
ALBION
QA
ALDER SPRINGS
FJ
ALDER SPRINGS
TK
ALDERPOINT
G4
ALEXANDER VALLEY
NH
ALLEGHANY
IU
ANDRUS ISLAND
PP
ALLENSWORTH
AF
ANGELS CAMP
XB
ALMANOR
Q1
ANGWIN
N2
ALPAUGH
AF
ANNAPOLIS
1N
ALTA
H1
ANNAPOLIS
1N
ALTAVILLE
XB
ANTELOPE
AN
ALTO
NK
ANTIOCH
JC
ALTON
KT
APPLEGATE
H2
ALVISO
AV
APTOS
AP
AMADOR CITY
QB
ARBUCKLE
DB
AMBOY
T3
ARCATA
AC
AMERICAN CANYON
NY
ARGUS
TD
ANCHOR BAY
P2
ARNOLD
XA
ANDERSON
AS
AROMAS
XK
ANDERSON SPRINGS
ZM
AROMAS
XK
ARROYO GRANDE
AG
BANTA
X2
BETHANY
XV
ARROYO GRANDE
AG
BASS LAKE
LD
BETHEL ISLAND
BI
ARROYO SECO
GF
BAXTER
H3
BETTERAVIA
BX
ARTOIS
9A
BAY POINT
DP
BIEBER
UQ
ARVIN
AR
BAYLISS
FJ
BIG BEND
UD
ASTI
2N
BAYSIDE
YS
BIG BEND
H8
BAYWOOD PARK
LG
BIG BEND VILLAGE
DS
ATASCADERO
WW
ATHERTON
AT
BEALE AFB
BY
BIG LAGOON
LF
ATWATER
AW
BEAR VALLEY
9S
BIG MEADOW
TJ
AUBERRY
AU
BEAR VALLEY
ZS
BIG OAK FLAT
EF
AUBURN
HB
BEAR VALLEY
2T
BIG SPRINGS
FP
AUBURN
HB
BEAR VALLEY
SPRING
TR
BIG SUR
ME
AUCKLAND
TJ
BIGGS
JM
BELDEN
Q9
BIOLA
BA
BELL SPRINGS
LM
BIRCHVILLE
HM
BELLA VISTA
VH
BIRDS LANDING
P7
BELLA VISTA
VH
BIRDS LANDING
PP
BELMONT
RN
BITTERWATER
BJ
BELVEDERE
NU
BLACK POINT
NM
BEN LOMOND
BP
LM
BLACKWELLS
CORNER
TX
BENBOW
BEND
FN
BLAKES LANDING
MM
BENICIA
BE
BLOCKSBURG
KD
BERENDA
TN
BLOOMFIELD
NN
BERKELEY
JR
BLUE CANYON
H5
BERKELEY
JR
BLUE LAKE
CQ
BERRY CREEK
IY
BLUE LAKE
CQ
AUKUM
AVENAL
AVERY
AVILA BEACH
AVON
BACHELOR VALLEY
BADGER
XD
AZ
XY
AA
JG
ZU
AD
BAKER RANCH
GE
BAKERSFIELD
TC
BAKERSFIELD
TC
BAKERSFIELD
TC
BALLARD
B7
BALLICO
BQ
BANGOR
YB
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 102
BODEGA
BB
BROWNS VALLEY
BL
CALWA
TK
BODEGA BAY
BB
BROWNSVILLE
IV
CAMANCHE
XD
BODEGA BAY
BB
BRUSH CREEK
IH
CAMBRIA
KA
BOGARD STATION
FF
BRYTE
WS
CAMDEN
TT
BOLINAS
BZ
BUCKINGHAM PARK
ZK
CAMERON PARK
GS
BONNY DOON
VT
BUCKS LAKE
FP
CAMINO
GP
BOONVILLE
UF
BUELLTON
B9
CAMP CONNELL
XA
BOOTJACK
TS
BUMBLEBEE
XR
CAMP MEEKER
CR
BORON
BO
BURLINGAME
BS
CAMP MONTECITO
TJ
BOULDER CREEK
BC
BURNEY
FF
CAMP SACRAMENTO
HT
BOWLES
TT
BURNT RANCH
L3
CAMPBELL
CM
BOWMAN
HB
BURREL
BF
CAMPBELL
CM
BOYES HOT
SPRINGS
7N
BURREL
BF
CAMPO SECO
XE
BURSON
XI
CAMPO SECO
VS
BRADLEY
DC
BURSON
XI
CAMPTONVILLE
IQ
BRADLEY
DC
BUTTE CITY
ET
CANTUA CREEK
KK
BRANNAN ISLAND
PP
BUTTE MEADOWS
F1
CANYON
J2
BRANSCOMB
W9
BUTTONWILLOW
BU
CANYON DAM
Q4
BRENTWOOD
BW
BYRON
BN
CAPAY
FJ
BRICELAND
LM
CACHAGUA
CY
CAPAY
3P
BRIDGEPORT
HM
CACHUMA
3B
CAPITOLA
CP
BRIDGEVILLE
KE
CADIZ
2C
CARBONA
XV
BRIGHTON
PS
CARIBOU
FP
AH
CALAVERAS BIG
TREES
XA
BRISBANE
CARLOTTA
KH
BROOKDALE
BD
CALIFORNIA VALLEY
3C
CARMEL
CE
BROOKS
2P
CALISTOGA
N3
CARMEL HIGHLAND
CE
BROWNS FLAT
XR
CALPELLA
UG
CARMEL VALLEY
CY
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 103
CARMEL VALLEY
CE
CHALLENGE
YQ
CLINTON
XD
CARMICHAEL
CA
CHAMBLESS
TD
CLIPPER GAP
HB
CARRISA PLAINS
T4
CHEROKEE
FM
CLIPPER MILLS
IM
CARSON HILL
XB
CHESTER
Y8
CLOVERDALE
ND
CARUTHERS
CB
CHICAGO PARK
JF
CLOVIS
CI
CARUTHERS
CB
CHICO
FB
CLYDE
CD
CASMALIA
B6
CHILES VALLEY
N3
COALINGA
TF
CASPAR
QC
CHINESE CAMP
EJ
COARSEGOLD
GO
CASSEL
UR
CHOLAME
DG
COBB
ZH
CASTLE GARDENS
TR
CHOWCHILLA
TP
COHASSET
FB
CASTRO VALLEY
CV
CHOWCHILLA
TP
COLD CREEK
NX
CASTROVILLE
CT
CHRISTIAN VALLEY
HB
COLD SPRINGS
YU
CATHEYS VALLEY
CZ
CHROME
FJ
COLFAX
HF
CAWELO
TX
CHUALAR
CF
COLLEGE CITY
CC
CAYTON VALLEY
FF
CISCO GROVE
H8
COLLINSVILLE
PP
CAYUCOS
KY
CITRUS HEIGHTS
CH
COLMA
AI
CAZADERO
4N
CLARKSBURG
CG
COLOMA
GQ
CEDAR FLAT
LW
CLARKSVILLE
HT
COLUMBIA
YW
CEDAR GROVE
TJ
CLAY
XF
COLUSA
PX
CEDAR RIDGE
JE
CLAYTON
CL
COMPTCHE
UH
CEDARBROOK
TJ
CLEAR CREEK
Q7
CONCORD
JG
CENTERVILLE
FB
CLEARLAKE
ZC
CONCOW
FM
CENTERVILLE
KQ
CLEARLAKE OAKS
ZE
CONEJO
TT
CENTERVILLE
TK
CLEARLAKE PARK
ZP
CONFIDENCE
XR
CENTRAL VALLEY
VE
CLEMENTS
KM
COOL
GD
CERES
AJ
CLEONE
NF
COPPEROPOLIS
XC
CERES
AJ
CLINGANS JUNCTION
TJ
CORCORAN
TG
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 104
CORDELIA
PK
CUYAMA VALLEY
CJ
DIGIORGIO
TC
CORDELIA
PJ
DAGGETT
TD
DILLON BEACH
ZD
CORNING
WF
DAIRYVILLE
FN
DINSMORE
KE
CORRAL DE TIERRA
BT
DALY CITY
RB
DINUBA
TJ
CORRALITOS
VX
DANA
DY
DINUBA
TJ
CORTE MADERA
CN
DANVILLE
DD
DIXON
PF
COTATI
CO
DAVENPORT
DN
DIXON
PF
COTTONWOOD
KO
DAVIS
PY
DOBBINS
DO
COTTONWOOD
KO
DAYTON
FB
DONNER SUMMITT
H8
COULTERVILLE
CX
DE SABLA
FM
DORRINGTON
XA
COULTERVILLE
CX
DEER PARK
N4
DOS PALOS
DZ
COVELO
W7
DEHAVEN
QW
DOS PALOS (SOUTH)
DT
COW CREEK
SR
DEL LOMA
L1
DOS PALOS (SOUTH)
TM
COYOTE
VR
DEL PASO HEIGHTS
PS
DOS PALOS Y
TM
CRESCENT MILLS
EY
DEL REY
DR
DOS RIOS
W6
CRESSEY
CS
DEL REY
DR
DOUGLAS FLAT
XG
CRESSMAN
AU
DEL REY OAKS
BT
DOWNIEVILLE
HJ
CRESTON
DQ
DELEVAN
PX
DRUM VALLEY
TJ
CROCKETT
CK
DELFT COLONY
TJ
DRYTOWN
QD
CROWS LANDING
X6
DELHI
1X
DUBLIN
DU
CUMMINGS
G5
DENAIR
DK
DUNCAN MILLS
M1
CUNNINGHAM
NR
DENAIR
DK
DUNLAP
DI
CUPERTINO
VV
DENVERTON
FS
DUNNIGAN
DB
CUSHENBURY
SPRINGS
TD
DERBY ACRES
DE
DUNNIGAN
DB
DIABLO
DL
DURHAM
DH
CUTLER
CW
DIAMOND SPRINGS
GT
DUSTIN ACRES
DA
CUTTEN
LF
DIBBLE CREEK
FN
DUTCH FLAT
H4
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 105
EARLIMART
EA
ELK RIVER
LF
FEATHER FALLS
EAST NICOLAUS
HP
ELKHORN
BT
FELLOWS
FW
EAST NICOLAUS
NO
ELMIRA
EI
FELTON
FE
EAST OAKLAND
JQ
ELVERTA
EV
FERNBRIDGE
KJ
EAST PALO ALTO
EP
ELVERTA
EV
FERNDALE
KQ
EASTON
TK
ELVERTA
EV
FETTERS HOT
SPRINGS
NV
ECHO LAKE
HT
EMERYVILLE
EM
FIDDLETOWN
QE
EDISON
TC
EMIGRANT GAP
H5
FIELDBROOK
OX
EDWARDS
ED
EMMET
B6
FIELDS LANDING
YL
EDWARDS (NORTH)
ED
EMPIRE
ER
FINLEY
ZF
EDWARDS AFB
ED
ENTERPRISE
FQ
FIREBAUGH
FG
EEL ROCK
LM
ESCALON
X5
FISH CAMP
YF
EL CAMINO
WF
ESCALON
X5
FITCH MOUNTAIN
NH
EL CERRITO
EC
ESHOM VALLEY
TJ
FIVE POINTS
FT
EL DORADO
GV
ESPARTO
4P
FLORIN
PS
EL DORADO HILLS
GW
ETTERSBURG
1G
FLOURNOY
OF
EL GRANADA
VG
EUREKA
LF
FOLSOM
FL
EL MACERO
EO
FAIR OAKS
FO
FORBESTOWN
IT
EL NIDO
EN
FAIR PLAY
HT
FORD CITY
TV
EL PORTAL
EL
FAIRFAX
FX
FOREST
IX
EL SOBRANTE
ES
FAIRFIELD
PJ
FOREST GLEN
8F
EL VERANO
NV
FAIRHAVEN
AM
FOREST KNOLLS
FK
ELDERWOOD
WJ
FAIRMEAD
TP
FOREST RANCH
F9
ELDRIDGE
NV
FALL RIVER MILLS
UE
FORESTHILL
GE
ELK
P3
FALLON
ZB
FORESTVILLE
FV
ELK CREEK
9E
FAMOSO
TX
FORESTVILLE
FV
ELK GROVE
EG
FARMINGTON
FA
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 106
IF
FORT BRAGG
NF
FRUITLAND
LM
GONZALES
GZ
FORT ORD
SS
FRUITVALE
TC
GOODYEARS BAR
JD
FORT ORD
MA
FULTON
FU
GRAND ISLAND
PP
FORT ROSS
5N
GALT
GA
GRANITE BAY
HS
FORT SEWARD
2G
GALT
GA
GRANITE BAY
KR
FORTUNA
LJ
GANNS MEADOW
XA
GRANITE STATION
TC
FOSTER CITY
FC
GARBERVILLE
LM
GRAPEVINE
TC
FOUR COURNERS
TD
GARDEN VALLEY
GG
GRASS VALLEY
HM
FOWLER
FI
GARDENLAND
PS
GRATON
GR
FRANKLIN
PS
GAREY
BX
GRAYSON
X7
FRANZ VALLEY
NL
GENERAL GRANT
GROVE
TJ
GREELEY HILL
7G
FREEDOM
XM
GREENACRES
TC
GENESEE
EZ
GREENBRAE
LK
GEORGETOWN
GH
GREENFIELD
GF
GERBER
GB
GREENFIELD
TC
GEYSERS
ND
GREENVILLE
YG
GEYSERVILLE
NC
GREENWOOD
GI
GILROY
VF
GRIDLEY
FD
GLEN ELLEN
6N
GRIMES
ZA
GLENBURN
DX
GRIMES
ZA
GLENCOE
QV
GRIZZLEY BLUFF
LJ
GLENHAVEN
ZJ
GRIZZLY FLATS
GX
GLENN
9G
GRIZZLY ISLAND
FS
GOLD HILL
HT
GROVELAND
YY
GOLD LAKE
IG
GROVER BEACH
GC
GOLD RIVER
RA
GUADALUPE
B8
GOLD RUN
H6
GUALALA
P4
FREEPORT
FREESTONE
FREMONT
FRENCH CAMP
FRENCH CAMP
FRENCH CORRAL
FRENCH CORRAL
FRENCH GULCH
FRESH POND
FRESHWATER
FRESNO
FRESNO
FRIANT
FRIANT
FRIANT
PS
NR
JJ
FH
FH
JO
IJ
ZG
HT
LF
TK
TK
FR
FR
FR
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 107
GUERNEVILLE
NG
HAYWARD
JK
HORSE CORAL FLAT
TJ
GUERNSEY
TG
HEALDSBURG
NH
HUB
TT
GUINDA
5P
HEART MEADOW
TJ
HUGHSON
HG
GUSTINE
GU
HELM
HE
HUGHSON
HG
GUSTINE
GU
HENLEYVILLE
WF
HUMBOLDT HILL
LF
HACIENDA
FV
HERCULES
HR
HUME LAKE
HK
HALCYON
AG
HERITAGE RANCH
BR
HUMPHREYS
STATION
TK
HALES GROVE
LM
HERNDON
TK
HUNTER LIG RES
JO
HALF MOON BAY
RH
HICKMAN
HC
HURLETON
FQ
HAMES VALLEY
DC
HIGHWAY CITY
TK
HURON
HU
HAMILTON CITY
9H
HILLCREST
FF
HYDESVILLE
KV
HAMILTON FIELD
NM
HILLSBOROUGH
HL
IGNACIO
NM
HAMLET
NN
HILMAR
HQ
IGO
W1
HAMMONTON
HP
HILTON
NG
INDIAN FALLS
FP
HANFORD
HA
HOBERGS
ZH
INVERNESS
IN
HANFORD
HA
HOLLISTER
BG
INYOKERN
C9
HANFORD
HA
HOLLYDALE PARK
NR
IONE
QF
HARDON FLAT
XR
HOLMES
LJ
IOOF PARK
NG
HARDWICK
TT
HOLY CITY
VJ
IRWIN
XX
HARMONY
T7
HOLY CITY
VJ
ISLAND MOUNTAIN
3G
HARRIS
4G
HONCUT
FQ
ISLETON
P8
HARTLAND
TJ
HONEYDEW
KU
JACKASS HILL
XR
HASTINGS ISLAND
PP
HONEYDEW
KU
JACKSON
XD
HAT CREEK
US
HOOPA
L1
JACKSONVILLE
XR
HATHAWAY PINES
XO
HOPETON
TR
JACOBY CREEK
LF
HAUSNA
AG
HOPLAND
UI
JAMESTOWN
YZ
HAWKINS BAR
L8
HORNITOS
HN
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 108
JARBO GAP
FM
KIRKWOOD
WF
LANARE
TT
JEFFERSONVILLE
XR
KNEELAND
KL
LARGO
UI
JENNER
5N
KNIGHTS FERRY
XN
LARKFIELD
NR
JENNY LIND
XT
KNIGHTS LANDING
KS
LARKSPUR
LK
JOHNSON PARK
TU
KNIGHTSEN
K3
LAS CRUCES
2B
JOLON
JO
KNOWLES
TN
LAS DELTA
TM
JONESVILLE
FB
KORBEL
KB
LASSEN CAMP
MW
JOYCE ISLAND
FS
KRAMER JUNCTION
TD
LATHROP
LP
KEDDIE
Y3
KYBURZ
GY
LATHROP
LP
KELSEY
G1
LA GRANGE
LR
LATHROP
LP
KELSEYVILLE
ZK
LA HONDA
LH
LATON
LX
KENSINGTON
KN
LA HONDA
LH
LATON
LX
KENTFIELD
KF
LA PORTE
IL
LATROBE
HT
KENWOOD
KW
LA PURISMA
2B
LAYTONVILLE
W8
KERMAN
TH
LA SELVA BEACH
VX
LAYTONVILLE
W8
KETTENPOM
LM
LAFAYETTE
LY
LE GRAND
LQ
KETTLEMAN CITY
KC
LAGUNITAS
LU
LEBEC
LE
KEYES
2X
LAKE ALMANOR
Q2
LEESVILLE
9S
KEYES
2X
LAKE BERRYESSA
N7
LEGGETT
5G
KEYSTONE
XR
LAKE DON PEDRO
SX
LEMOORE
TL
KING CITY
BJ
LAKE DON PEDRO
CX
LIBERTY FARMS
PK
KING SALMON
LF
LAKE DON PEDRO
LR
LINCOLN
HD
KINGS CANYON
NATIONAL PARK
KG
LAKE MADRONE
FQ
LINCOLN
HD
LAKE OF THE PINES
HM
LINDA
HP
KINGSBURG
KI
LAKEHEAD
LB
LINDEN
LI
KINGSBURG
KI
LAKEPORT
NJ
H8
LITTLE GRASS
VALLEY
IL
KINGVALE
LAMONT
LT
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 109
LITTLE NORWAY
8R
LOS ALTOS HILLS
LA
MANTON
MQ
LITTLE RIVER
QL
LOS BANOS
TM
MAPLE CREEK
LF
LITTLE VALLEY
W5
LOS BERROS
AG
MARICOPA
MF
LIVE OAK
LO
LOS GATOS
VJ
MARICOPA HEIGHTS
TV
LIVE OAK
LO
LOS GATOS
VJ
MARINA
MA
LIVERMORE
JN
LOS MOLINOS
OM
MARINWOOD
NQ
LIVINGSTON
LV
LOS OLIVOS
B5
MARIPOSA
TS
LOCH LOMOND
ZO
LOS OSOS
LG
MARSHALL
MM
LOCKEFORD
LC
LOST HILLS
LL
MARSHALL
MM
LOCKWOOD
VW
LOTUS
8S
MARSHALL STATION
TK
LODI
XF
LOVELOCK
FM
MARTELL
QP
LODOGA
FJ
LOWER LAKE
ZL
MARTINEZ
MR
LOLETA
KX
LUCERNE
ZI
MARTINS BEACH
RH
LOLETA
KX
LUCERNE VALLEY
T8
MARYSVILLE
HP
LOMA MAR
VM
LYONSVILLE
PC
MATHER AFB
MN
LOMA RICA
HP
LYTTON
NC
MAXWELL
EU
LOMPICO
FE
MAD RIVER
KZ
MC ARTHUR
UU
LOMPOC
2B
MADERA
TN
MC CANN
LM
LONDON
TJ
MADERA
TN
MC CLELLAN FIELD
PS
LONE STAR
TK
MADISON
6P
MC FARLAND
MC
LONG BARN
EB
MAGALIA
F3
MC KINLEYVILLE
MV
LONGVALE
NZ
MAGUNDEN
TC
MC KITTRICK
MK
LONOAK
BJ
MALAGA
TK
MEADOW LAKES
TK
LOOMIS
LZ
MANCHESTER
P1
MEADOW VALLEY
EX
LOOMIS
LZ
MANILA
LF
MEADOW VISTA
GJ
LOS ALAMOS
B4
MANTECA
XH
MEADOWMONT
XB
LOS ALTOS
LA
MANTECA
XH
MENDOCINO
QM
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 110
MENDOTA
MY
MODESTO
XJ
MOUNT BULLION
TS
MENLO PARK
MP
MOJAVE
T5
MOUNT HAMILTON
VP
MERCED
TR
MOKELUMNE HILL
QT
MOUNT HERMON
MT
MERCED FALLS
TR
MOKELUMNE HILL
QT
MOUNTAIN RANCH
XQ
MERIDIAN
EK
MOLINO
NR
MOUNTAIN REST
TK
MERRITT ISLAND
PP
MONMOUTH
TT
MOUNTAIN VIEW
VL
METTLER STATION
MZ
MONO PINES
XR
MUIR BEACH
OW
MI WUK VILLAGE
UW
MONO VISTA
XR
MUROC
TD
MICHIGAN BLUFF
GE
MONSON
TJ
MURPHYS
XU
MIDDLETOWN
ZM
MONTA VISTA
VV
MYERS FLAT
G6
MIDPINES
TS
MONTARA
VD
NAPA
NL
MILL CREEK
MX
MONTE RIO
ZR
NASHVILLE
HT
MILL VALLEY
NK
MONTE SERENO
MS
NAVARRO
UJ
MILLBRAE
MI
MONTEREY
BM
NAVELENCIA
RV
MILLVILLE
MJ
MONTGOMERY
CREEK
UT
NELSON
NA
MILPITAS
ML
NEVADA CITY
HH
MOONSTONE BEACH
LF
NEW CUYAMA
3N
MOOSE CAMP
FF
NEW IDRIA
AY
MORAGA
MG
NEWARK
NE
MORGAN HILL
MH
MH
NEWBERRY
SPRINGS
C4
MORGAN HILL
MORRO BAY
MB
NEWCASTLE
GK
MOSS BEACH
VK
NEWMAN
XL
MOSS LANDING
MD
NEWVILLE
FJ
MOUNT AUKUM
GP
NICASIO
N8
MOUNT AUKUM
8P
NICE
ZN
MOUNT AUKUM
(NORTH)
8P
NICOLAUS
NO
MINERAL
MINKLER
MINTURN
MIRABLE PARK
MW
SR
TN
FV
MIRAMONTE
MU
MIRANDA
6G
MISSION DISTRICT
SL
MISSION HILLS
2B
MO TRIANGLE
TV
MOCCASIN
YY
MODESTO
XJ
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 111
NIMSHEW
FM
OCCIDENTAL
OC
OROVILLE
FQ
NIPINNAWASEE
TQ
OCEANO
OO
ORRS HOT SPRINGS
NX
NIPOMO
B2
ODD FELLOWS
EB
OSWALD
HP
NIPOMO
B2
OIL CENTER
TC
OUTINGDALE
HT
NORD
FB
OILDALE
TC
PACHECO
PA
NORDEN
H8
OLD CUYAMA
TV
PACIFIC GROVE
PG
NORTH COLUMBIA
HM
OLD RIVER
TC
PACIFIC HOUSE
HV
NORTH FORK
NT
OLD STATION
UX
PACIFICA
RP
NORTH HIGHLANDS
HI
OLEANDER
TK
PAGES CORNER
TK
NORTH SAN JUAN
IO
OLEMA
OA
PAICINES
AY
NORTHWOOD
ZR
OLIVEHURST
OL
PALERMO
IP
NOVATO
NM
OMO RANCH
HX
PALO CEDRO
AO
NOYO
NF
ONO
V3
PANOCHE VALLEY
AY
NUBIEBER
UV
OPHIR
HB
PARADISE
FM
O'BRIEN
LB
ORA VISTA
FQ
PARADISE PINES
FM
O'NEALS
ON
ORANGE COVE
OE
PARKFIELD
KP
OAK RUN
OU
ORANGEVALE
OV
PARLIER
PE
OAK RUN
OU
ORCUTT
4B
PASKENTA
XP
OAK SHORES
BR
ORD BEND
FJ
PASO ROBLES
BK
OAK SHORES
DC
OREGON CITY
FM
PATTERSON
X8
OAKDALE
XN
OREGON HOUSE
OH
PAYNES CREEK
PC
OAKHURST
TQ
ORICK
OI
PEACH TREE
BJ
OAKLAND
JQ
ORINDA
OR
PEARDALE
HM
OAKLAND
JQ
ORLAND
FJ
PEBBLE BEACH
PB
OAKLEY
OK
ORLEANS
L2
PENN VALLEY
IJ
OAKVILLE
OQ
OROSI
OS
PENNGROVE
9P
OCCIDENTAL
OC
OROVILLE
FQ
PENNINGTON
FQ
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 112
PENRYN
GL
PIONEER POINT
TD
PRATHER
PR
PEPPERWOOD
LF
PISMO BEACH
PW
PRATTVILLE
Q1
PESCADERO
VO
PITTSBURG
JH
PRESIDIO
PT
PETALUMA
NN
PITTVILLE
FF
PRESTON
NC
PETALUMA
NN
PLACERVILLE
HT
PRINCETON
EQ
PETALUMA
NN
PLANADA
PM
PRINCETON
VG
PETERS
XT
PLATINA
8A
PROBERTA
RW
PETROLIA
JV
PLEASANT GROVE
PO
PROJECT CITY
WO
PETROLIA
JV
PLEASANT GROVE
PO
PRUNEDALE
BT
PHILLIPSVILLE
G9
PLEASANT HILL
PH
PULGA
F6
PHILO
UK
PLEASANT VALLEY
HT
PUMPKIN CENTER
TC
PIEDMONT
PD
PLEASANTON
PL
QUAIL FLAT
TJ
PIEDRA
SR
PLEASANTON
PL
QUINCY
FP
PIERCY
G7
PLYMOUTH
QS
RACKERBY
IK
PIKE CITY
IZ
POINT ARENA
NP
RAILROAD FLAT
QX
PILOT HILL
GN
POINT REYES
PQ
RAINBOW TAVERN
H8
PINE FLAT
SR
POINT REYES
STATION
PQ
RAISIN CITY
RR
PINE GROVE
QJ
RANCHO CORDOVA
RA
POLLOCK PINES
HW
RANCHO MURIETA
RF
POND
TX
RANCHO TEHAMA
WF
PONDEROSA SKY
RANCH
PC
RAYMOND
RY
PONDOSA
1W
RAYMOND
RY
POPE VALLEY
N5
RAYMOND
RY
PORT COSTA
DF
RED BANK
FN
PORTOLA VALLEY
PV
RED BANK
WJ
POTTER VALLEY
UM
RED BLUFF
FN
PRAIRIE CREEK
LF
RED MOUNTAIN
TD
PINE MOUNTAIN
LAKE
XR
PINE RIDGE
AU
PINECREST
YU
PINEDALE
PI
PINEHURST
PU
PINNACLES
AY
PINOLE
PN
PIONEER
QK
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 113
RED TOP
C8
RIO LINDA
RL
RUTH
JY
REDCREST
JW
RIO NIDO
9N
RUTHERFORD
N6
REDDING
FY
RIO OSO
RO
RYDE
PP
REDWAY
G2
RIO VISTA
PP
RYER ISLAND
PP
REDWOOD CITY
RC
RIPON
X4
SACRAMENTO
PS
REDWOOD CREEK
LW
RIVER PINES
QG
SALIDA
ID
REDWOOD ESTATES
RE
RIVERBANK
RI
SALINAS
BT
REDWOOD ESTATES
RE
RIVERBANK
RI
SALMON CREEK
BB
REDWOOD VALLEY
UN
RIVERDALE
RZ
SALYER
L4
REDWOOD VALY
L3
RIVERDALE
RZ
SAMOA
AM
REEDLEY
RV
RIVERTON
HT
SAN ANDREAS
ZT
REEDLEY
RV
ROBBINS
ZQ
SAN ANSELMO
SW
RESCUE
HY
ROCKLIN
RT
SAN ARDO
AQ
RHEEM
RM
ROCKPORT
QR
SAN BENANCIO
CANYON
BT
RICHARDSON
GROVE
LM
RODEO
RQ
SAN BENITO
BG
ROHNERT PARK
RK
SAN BRUNO
RD
ROHNERT PARK
(SOUTH)
RK
SAN CARLOS
SC
ROHNERVILLE
LF
SAN FRANCISCO
RG
ROLINDA
TK
SAN GERONIMO
GM
ROSEDALE
TC
SAN GREGORIO
VQ
ROSEVILLE
HS
SAN JOAQUIN
SJ
ROSEVILLE
HS
SAN JOSE
VP
ROSS
RS
SAN JOSE
VP
ROUGH & READY
IW
SAN JOSE
VP
ROUND MOUNTAIN
UB
SAN JUAN BAUTISTA
B1
RUMSEY
7P
SAN JUAN BAUTISTA
B1
RICHARDSON
SPRINGS
FB
RICHFIELD
WF
RICHMOND
JT
RICHVALE
IR
RIDGECREST
TD
RIEGO
HP
RIO BRAVO
TC
RIO DELL
NR
RIO DELL
NR
RIO DELL
JX
RIO DELL
JX
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 114
SAN LEANDRO
SO
SANTA YNEZ
3B
SHEEP RANCH
XS
SAN LORENZO
SZ
SARATOGA
SG
SHELL BEACH
PW
SAN LUCAS
AX
SARATOGA
SG
SHERIDAN
SH
SAN LUIS OBISPO
BV
SARATOGA
SG
SHERMAN ISLAND
PP
SAN MARTIN
UA
SAUSALITO
NS
SHINGLE SPRINGS
HZ
SAN MATEO
SM
SAWMILL FLAT
XR
SHINGLETOWN
WQ
SAN MIGUEL
KP
SCHELLVILLE
NV
SHIVELY
LF
SAN PABLO
SB
SCIOTS CAMP
HT
SIEGLER SPRINGS
ZH
SAN QUENTIN
QU
SCOTIA
JU
SIERRA CITY
IG
SAN RAFAEL
NQ
SCOTTS VALLEY
SY
SIERRA CITY
HM
SAN RAMON
SN
SEACLIFF
AP
SIERRA VILLAGE
UW
SAN SIMEON
SP
SEA RANCH
P5
SILVER FORK
HT
SAND CITY
EW
SEASIDE
SS
SISQUOC
B3
SANGER
SR
SEAVIEW
NG
SITES
PX
SANGER
SR
SEBASTOPOL
SE
SKAGGS SPRINGS
NC
SANGER
SR
SEBASTOPOL
SE
SKY LONDA
LH
SANTA BARBARA
5B
SELBY
JT
SLOUGHHOUSE
QQ
SANTA CLARA
SA
SELMA
TT
SLY PARK
HT
SANTA CLARA
SA
SEQUOIA
TJ
SMARTVILLE
SV
SANTA CRUZ
VT
SEVILLE
VE
SMARTVILLE
SV
SANTA MARGARITA
WZ
SHAFTER
TE
SMITH CAMP
FF
SANTA MARGARITA
WZ
SHANDON
WY
SNELLING
SX
SANTA MARIA
BX
SHASTA
W2
SO BEIRIDGE
TV
SANTA NELLA
GU
SHASTA LAKE
VE
SODA SPRINGS
H8
SANTA RITA PARK
TM
SHASTA LAKE CITY
VE
SOLEDAD
SL
SANTA ROSA
NR
SHAVER LAKE
SK
SOLEDAD
SL
SANTA VENTIA
NQ
SHAWS FLAT
XR
SOLVANG
1B
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 115
SOMERSET
IC
STONE CORRAL
WJ
SYCAMORE
PX
SOMES BAR
L6
STONE LAGOON
LF
TAFT
TV
SONOMA
NV
STONYFORD
9S
TAFT
TV
SONOMA
NV
STORRIE
F7
TAFT (SOUTH)
TV
SONORA
XR
STOUT
XR
TAFT HEIGHTS
TV
SOQUEL
SQ
STRATFORD
RX
TALMAGE
UO
SOULSBYVILLE
YR
STRAWBERRY
HT
TAMARACK
XA
SOUTH FORK
TQ
STRAWBERRY
X1
TAMARACK PINES
HT
SOUTH SAN
FRANCISCO
RJ
STRAWBERRY POINT
NQ
TAYLORSVILLE
EZ
TEHACHAPI
2T
N7
STRAWBERRY
VALLEY
IS
SPANISH FLAT
TEHAMA
YT
SPANISH RANCH
EX
SUGAR PINE
TQ
TEMPLETON
BR
SPRECKELS
SF
SUGAR PINE
UW
TEPUSQUET
BX
SPRINGVILLE
VU
SUISUN
FS
TERMINOUS
XF
SPRUCE POINT
LF
SUISUN
FS
TERRA LINDA
NQ
SQUAW VALLEY
VY
SULTANA
UL
THERMALITO
FQ
SAINT HELENA
NW
SUMMERHOME PARK
NR
THORNTON
TW
STANDARD
YR
SUMMIT CITY
FY
THREE ROCKS
KK
STANFORD
UNIVERSITY
ST
SUNNYBRAE
LF
TIBURON
OT
SUNNYVALE
VB
TIERRA BUENA
HP
SUNOL
SU
TIVY VALLEY
SR
SUTTER
SD
TOADTOWN
FM
SUTTER
SD
TOBIN
F8
SUTTER CREEK
QI
TOCOLOMA
LU
SUTTER HILL
XD
TODD VALLEY
GE
SUTTER ISLAND
PP
TOLLHOUSE
T1
SWAINS FLAT
LF
TOMALES
N1
STENT
STEVINSON
STEWARTS POINT
STINSON BEACH
STIRLING CITY
STOCKTON
STOCKTON
STOCKTON
XR
SI
P6
BH
F2
XT
XT
XT
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 116
TRACY
XV
VALLECITO
XZ
WASHINGTON
II
TRANQUILLITY
TI
VALLEJO
NY
WATERFORD
WT
TRAVER
TZ
VALLEJO
NY
WATERLOO
XT
TRAVIS AFB
EE
VALLEY ACRES
VA
WATSONVILLE
VX
TRES PINOS
6B
VALLEY FORD
BB
WATSONVILLE
VX
TRIMMER
TK
VALLEY HOME
XN
WAUKENA
WG
TRINIDAD
TB
VALLEY SPRINGS
VS
WAWONA
C6
TRONA
TO
VALLEY SPRINGS
VS
WEIMAR
HF
TRONA (SOUTH)
TO
VAN ARSDALE
VM
WEIMAR
H9
TUDOR
HP
VANDENBURG AFB
2B
WEITCHPEC
L7
TULARE
TY
VERNALIS
X3
WEOTT
JZ
TUOLUMNE
YX
VERONA
HP
WEST POINT
QY
TUPMAN
TA
VICHY SPRINGS
NX
WEST SACRAMENTO
WS
TURLOCK
XX
VICTOR
VC
WESTEND
TD
TUTTLETOWN
XR
VICTORVILLE
C5
WESTHAVEN
LF
TWAIN
Y6
VILLA GRANDE
N9
WESTLEY
X9
TWAIN HARTE
YV
VINA
IA
WESTPORT
QW
TWIN BRIDGES
IE
VINEBURG
8N
WESTWOOD
Q7
TWITCHELL ISLAND
PP
VIRGILIA
FP
WHEATLAND
WE
TWO ROCK
NN
VISALIA
VI
WHEELER RIDGE
TV
TYLER
HH
VOLCANO
QN
WHISKEYTOWN
WB
TYLER ISLAND
PP
VOLTA
TM
WHISPERING PINE
ZH
UKIAH
NX
WALLACE
WL
WHITE HALL
NN
UNION CITY
UC
WALNUT CREEK
WC
WHITE PINES
XW
UPPER LAKE
ZU
WALNUT GROVE
WV
WHITETHORN
G3
VACATION BEACH
NG
WALNUT GROVE
WV
WHITMORE
W3
VACAVILLE
PK
WASCO
TX
WHITTAKER FOREST
TJ
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 117
WILDWOOD
8W
WINTON
WN
YOLO
YO
WILLIAMS
DV
WISHON
WU
YORKVILLE
UP
WILLITS
NZ
WITTER SPRINGS
ZW
YOSEMITE
YX
WILLOW CREEK
LW
WONDER VALLEY
SR
YOSEMITE (WEST)
T2
WILLOW SPRINGS
XD
WOODACRE
WA
YOUNTVILLE
YN
WILLOW SPRINGS
YR
WOODBRIDGE
WR
YUBA CITY
YC
WILLOWS
9W
WOODEN VALLEY
NL
YUBA GAP
HB
WILLOWS
9W
WOODLAKE
WJ
YUBA GAP
H5
WILSEYVILLE
QZ
WOODLAND
PZ
ZACA LAKE
3B
WILSONIA
TJ
WOODLEAF
FQ
ZAMORA
PZ
WINDSOR
WI
WOODSIDE
WD
ZENIA
G8
WINDSOR
WI
WYANDOTTE
FQ
WINTERS
7W
YANKEE HILL
FM
WINTERS
7W
YETTEM
YE
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 118
APPENDIX B
SERVICE CITY ZIP CODES
City
ACAMPO
AHWAHNEE
AHWAHNEE
ALAMEDA
ALAMEDA
ALAMO
ALBANY
ALBANY
ALBANY
ALBION
ALDERPOINT
ALLEGHANY
ALLENSWORTH
ALLENSWORTH
ALLENSWORTH
ALMANOR
ALPAUGH
ALTA
ALTAVILLE
ALTON
ALVISO
AMADOR CITY
AMBOY
AMERICAN CANYON
AMERICAN CANYON
AMERICAN CANYON
AMERICAN CANYON
ANDERSON
Zip Code
95220
93601
93601
94501
94502
94507
94706
94707
94710
95410
95511
95910
93201
93219
93219
95947
93201
95701
95221
95540
95002
95601
92304
94503
94503
94588
94590
96007
ANDERSON
ANGELS CAMP
ANGELS CAMP
ANGWIN
ANNAPOLIS
ANTELOPE
ANTIOCH
ANTIOCH
ANTIOCH
ANTIOCH
ANTIOCH
ANTIOCH
ANTIOCH
ANTIOCH
ANTIOCH
ANTIOCH
ANTIOCH
APPLEGATE
APTOS
APTOS
ARBUCKLE
ARBUCKLE
ARCATA
ARCATA
ARCATA
ARNOLD
ARNOLD
AROMAS
AROMAS
96007
95221
95222
94508
95412
95843
90212
90406
92626
92806
94507
94509
94509
94523
94531
94566
97478
95703
95001
95003
95912
95932
95518
95519
95521
95223
95223
95004
95004
ARROYO GRANDE
ARROYO GRANDE
ARROYO GRANDE
ARROYO GRANDE
ARROYO GRANDE
ARTOIS
ARTOIS
ARVIN
ATASCADERO
ATASCADERO
ATASCADERO
ATASCADERO
ATHERTON
ATWATER
AUBERRY
AUBURN
AUBURN
AUBURN
AUBURN
AUBURN
AUBURN
AVENAL
AVENAL
AVERY
AVILA BEACH
AVILA BEACH
BADGER
BADGER
BAKERSFIELD
93401
93420
93421
93444
93445
95913
95913
93203
93422
93423
93442
93446
94027
95301
93602
95602
95602
95603
95603
95603
95604
93204
93204
95224
93424
93449
93603
93603
90404
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BAKERSFIELD
BALLARD
BALLICO
BANGOR
BANGOR
BANTA
BASS LAKE
BASS LAKE
BAXTER
BAXTER
BAY POINT
BAYSIDE
BEALE AFB
BEAR VALLEY
BEAR VALLEY
90503
91210
92658
92887
93203
93206
93220
93280
93301
93302
93303
93303
93304
93305
93306
93307
93308
93309
93309
93311
93312
93313
93314
93380
93381
93383
93384
93387
93388
93389
93390
93463
95303
95914
95914
95304
93604
93669
95701
95722
94565
95524
95903
95222
95222
BEAR VALLEY
BEAR VALLEY
BELDEN
BELLA VISTA
BELMONT
BELMONT
BELVEDERE
BEN LOMOND
BENICIA
BENICIA
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERKELEY
BERRY CREEK
BETHEL ISLAND
BETHEL ISLAND
BIEBER
BIEBER
BIG BEND
BIG SUR
BIGGS
BIOLA
BIRDS LANDING
BLOCKSBURG
BLUE LAKE
BLUE LAKE
BODEGA
BODEGA BAY
BOLINAS
BOONVILLE
BORON
BORON
BOULDER CREEK
95223
95223
95915
96008
94002
94002
94920
95005
94510
94553
94618
94701
94702
94703
94704
94704
94705
94706
94707
94707
94708
94708
94709
94710
94720
95916
94511
94513
96009
96130
96011
93920
95917
93606
94512
95514
95524
95525
94922
94923
94924
95415
93516
93516
95006
BRADLEY
BRADLEY
BRADLEY
BRANSCOMB
BRENTWOOD
BRENTWOOD
BRENTWOOD
BRENTWOOD
BRENTWOOD
BRENTWOOD
BRENTWOOD
BRENTWOOD
BRENTWOOD
BRIDGEVILLE
BRIDGEVILLE
BRISBANE
BROOKDALE
BROOKS
BROWNS VALLEY
BROWNSVILLE
BRUSH CREEK
BUELLTON
BUELLTON
BURLINGAME
BURLINGAME
BURNEY
BURNEY
BURNT RANCH
BURNT RANCH
BURREL
BURSON
BURSON
BUTTE CITY
BUTTE CITY
BUTTE MEADOWS
BUTTONWILLOW
BUTTONWILLOW
BYRON
BYRON
BYRON
BYRON
BYRON
BYRON
CALIFORNIA VALLEY
CALIFORNIA VALLEY
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 120
93426
93426
93426
95417
94513
94513
94513
94513
94513
94514
94561
94566
94588
95526
95526
94005
95007
95606
95918
95919
95916
93101
93427
94010
94011
96013
96130
95527
95546
93607
95225
95225
95920
95920
95942
93206
93260
92626
94513
94514
94514
94514
94514
93453
93453
CALISTOGA
CALISTOGA
CALPELLA
CAMBRIA
CAMERON PARK
CAMINO
CAMP CONNELL
CAMP MEEKER
CAMPBELL
CAMPBELL
CAMPBELL
CAMPBELL
CAMPBELL
CAMPBELL
CAMPBELL
CAMPO SECO
CAMPTONVILLE
CAMPTONVILLE
CANTUA CREEK
CANYON
CANYON DAM
CAPAY
CAPAY
CAPITOLA
CARLOTTA
CARMEL
CARMEL
CARMEL
CARMEL
CARMEL VALLEY
CARMICHAEL
CARMICHAEL
CARRISA PLAINS
CARRISA PLAINS
CARRISA PLAINS
CARUTHERS
CASMALIA
CASPAR
CASSEL
CASTRO VALLEY
CASTRO VALLEY
CASTRO VALLEY
CASTRO VALLEY
CASTRO VALLEY
CASTROVILLE
94515
94515
95418
93428
95682
95709
95223
95419
95008
95008
95008
95008
95009
95009
95009
95226
95922
95922
93608
94516
95923
95607
95607
95010
95528
93921
93922
93923
93924
93924
95608
95609
93276
93453
93453
93609
93429
95420
96016
94541
94544
94546
94546
94552
95012
CATHEYS VALLEY
CATHEYS VALLEY
CAYUCOS
CAZADERO
CEDAR RIDGE
CERES
CERES
CHALLENGE
CHALLENGE
CHESTER
CHICO
CHICO
CHICO
CHICO
CHICO
CHICO
CHINESE CAMP
CHOLAME
CHOLAME
CHOWCHILLA
CHOWCHILLA
CHUALAR
CITRUS HEIGHTS
CITRUS HEIGHTS
CLARKSBURG
CLAYTON
CLAYTON
CLEARLAKE
CLEARLAKE OAKS
CLEARLAKE PARK
CLEMENTS
CLEMENTS
CLIPPER MILLS
CLOVERDALE
CLOVERDALE
CLOVIS
CLOVIS
CLOVIS
CLOVIS
CLOVIS
CLOVIS
CLOVIS
CLOVIS
CLYDE
COALINGA
95306
95338
93430
95421
95924
95307
95351
95925
95925
96020
95926
95927
95928
95929
95973
95973
95309
93431
93461
93610
93610
93925
95610
95621
95612
94517
94566
95422
95423
95424
95220
95227
95930
95425
95425
93611
93612
93613
93619
93706
93720
93725
95834
94520
93210
COALINGA
COALINGA
COARSEGOLD
COBB
COHASSET
COLFAX
COLFAX
COLLEGE CITY
COLMA
COLMA
COLOMA
COLUMBIA
COLUSA
COMPTCHE
CONCORD
CONCORD
CONCORD
CONCORD
CONCORD
CONCORD
CONCORD
CONCORD
COOL
COPPEROPOLIS
CORCORAN
CORCORAN
CORCORAN
CORCORAN
CORCORAN
CORNING
CORNING
CORNING
CORTE MADERA
CORTE MADERA
CORTE MADERA
COSTA MESA
COTATI
COTATI
COTTONWOOD
COTTONWOOD
COULTERVILLE
COULTERVILLE
COURTLAND
COVELO
COYOTE
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 121
93210
93210
93614
95426
95973
95713
95736
95912
94014
94015
95613
95310
95932
95427
94518
94519
94520
94520
94521
94522
94523
94524
95614
95228
93212
93212
93212
93221
93230
96021
96021
96022
94925
94948
94976
92626
94928
94931
96022
96022
95311
95311
95615
95428
95013
CRESCENT CITY
CRESCENT MILLS
CRESSEY
CRESTON
CROCKETT
CROWS LANDING
CUMMINGS
CUPERTINO
CUPERTINO
CUPERTNIO
CUTLER
CUTTEN
CUYAMA
CUYAMA
DAGGETT
DALY CITY
DALY CITY
DANVILLE
DANVILLE
DANVILLE
DANVILLE
DANVILLE
DANVILLE
DAVENPORT
DAVIS
DAVIS
DAVIS
DAVIS
DEER PARK
DEL REY
DEL REY
DELEVAN
DELHI
DENAIR
DENAIR
DERBY ACRES
DERBY ACRES
DIABLO
DIABLO
DIABLO
DIAMOND SPRINGS
DIAMOND SPRINGS
DILLON BEACH
DILLON BEACH
DINUBA
95531
95934
95312
93432
94525
95313
95585
95014
95015
95014
93615
95534
93252
93254
92327
94014
94015
94005
94506
94526
94526
94526
94526
95017
91789
95616
95616
95617
94576
93616
93657
95988
95315
95316
95316
93224
93268
94520
94526
94528
95619
95675
94929
94929
93271
DINUBA
DINUBA
DINUBA
DISCOVERY BAY
DIXON
DIXON
DIXON
DIXON
DIXON
DOBBINS
DOBBINS
DORRINGTON
DOS PALOS
DOS PALOS
DOS PALOS
DOS RIOS
DOUGLAS FLAT
DOWNIEVILLE
DRYTOWN
DUBLIN
DUBLIN
DUBLIN
DUBLIN
DUBLIN
DUNCANS MILLS
DUNLAP
DUNNIGAN
DURHAM
DURHAM
DUSTIN ACRES
DUTCH FLAT
EARLIMART
EAST NICOLAUS
EAST PALO ALTO
EAST PALO ALTO
EDISON
EDWARDS
EL CERRITO
EL DORADO
EL DORADO HILLS
EL DORADO HILLS
EL GRANADA
EL MACERO
EL NIDO
EL PORTAL
93618
93618
93662
94514
95615
95620
95620
95662
95694
95935
95962
95223
93620
93620
95340
95429
95229
95936
95699
94566
94568
94568
94568
94568
95430
93621
95937
95926
95938
93268
95714
93219
95659
94303
94303
93220
93523
94530
95623
95762
95762
94018
95618
95317
95318
EL SOBRANTE
EL SOBRANTE
ELK
ELK CREEK
ELK GROVE
ELK GROVE
ELK GROVE
ELK GROVE
ELK GROVE
ELMIRA
ELVERTA
ELVERTA
ELVERTA
EMERALD HILLS
EMERYVILLE
EMERYVILLE
EMIGRANT GAP
EMIGRANT GAP
EMPIRE
ESCALON
ESPARTO
ESPARTO
EUREKA
EUREKA
EUREKA
EUREKA
EUREKA
EUREKA
FAIR OAKS
FAIRFAX
FAIRFIELD
FAIRFIELD
FAIRFIELD
FAIRFIELD
FAIRFIELD
FAIRFIELD
FALL RIVER MILLS
FALLON
FARMINGTON
FARMINGTON
FEATHER FALLS
FELLOWS
FELTON
FERNBRIDGE
FERNDALE
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 122
94803
94806
95432
95939
95624
95757
95758
95828
95829
95625
95626
95626
95626
94062
94601
94608
95715
95715
95319
95320
95607
95627
90274
95501
95502
95503
95521
98101
95628
94930
94533
94534
94534
94535
94585
95687
96028
94952
95230
95230
95940
93224
95018
95540
95536
FIDDLETOWN
FIDDLETOWN
FIELDBROOK
FIELDBROOK
FIELDBROOK
FIELDS LANDING
FINLEY
FIREBAUGH
FIREBAUGH
FIREBAUGH
FISH CAMP
FISH CAMP
FIVE POINTS
FLOURNOY
FOLSOM
FOLSOM
FOLSOM
FORBESTOWN
FORBESTOWN
FOREST GLEN
FOREST KNOLLS
FOREST RANCH
FORESTHILL
FORESTVILLE
FORT BRAGG
FORT BRAGG
FORT SEWARD
FORTUNA
FOSTER CITY
FOSTER CITY
FOWLER
FREEDOM
FREMONT
FREMONT
FREMONT
FREMONT
FREMONT
FREMONT
FREMONT
FRENCH CAMP
FRENCH CAMP
FRENCH GULCH
FRESNO
FRESNO
FRESNO
95629
95629
95519
95521
95525
95537
95435
93622
93622
93622
93623
93623
93624
96029
95630
95630
95763
95941
95941
96041
94933
95942
95631
95436
95437
95456
95542
95540
94403
94404
93625
95019
94536
94537
94538
94538
94539
94555
94583
95231
95336
96033
90707
93612
93650
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRESNO
FRIANT
FRIANT
FRIANT
FULTON
GALT
GALT
GALT
GARBERVILLE
GARBERVILLE
GARBERVILLE
GARBERVILLE
GARDEN VALLEY
GEORGETOWN
GEORGETOWN
GERBER
GEYSERVILLE
93657
93668
93701
93702
93703
93704
93705
93706
93710
93710
93711
93720
93721
93722
93722
93725
93726
93726
93727
93727
93728
93729
93740
93760
93776
93778
93778
93792
95816
93626
93626
93626
95439
95632
95632
95632
95501
95542
95542
96127
95633
95634
95634
96035
92081
GEYSERVILLE
GILROY
GILROY
GLEN ELLEN
GLENCOE
GLENHAVEN
GLENN
GOLD RIVER
GOLD RUN
GONZALES
GOODYEARS BAR
GRANITE BAY
GRASS VALLEY
GRASS VALLEY
GRASS VALLEY
GRASS VALLEY
GRATON
GRAYSON
GRAYSON
GRAYSON
GREENBRAE
GREENFIELD
GREENVILLE
GREENWOOD
GRIDLEY
GRIMES
GRIZZLY FLATS
GRIZZLY FLATS
GROVELAND
GROVELAND
GROVER BEACH
GROVER BEACH
GUADALUPE
GUADALUPE
GUALALA
GUERNEVILLE
GUERNEVILLE
GUINDA
GUSTINE
GUSTINE
HALCYON
HALF MOON BAY
HAMILTON CITY
HANFORD
HANFORD
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 123
95441
95020
95021
95442
95232
95443
95943
95670
95717
93926
95944
95746
95945
95949
95959
95960
95444
95360
95363
95387
94904
93927
95947
95635
95948
95950
95636
95684
95321
95321
93433
93483
93434
93434
95445
95446
95471
95637
95322
95322
93420
94019
95951
93230
93232
HARMONY
HAT CREEK
HATHAWAY PINES
HAWKINS BAR
HAWKINS BAR
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HAYWARD
HEALDSBURG
HELM
HERCULES
HICKMAN
HIDDEN VALLEY LAKE
HILLSBOROUGH
HILMAR
HOLLISTER
HOLLISTER
HOLLISTER
HOLT
HONEYDEW
HOOPA
HOOPA
HOOPA
HOPLAND
HORNITOS
HUGHSON
HUME
HURON
HURON
HURON
HYDESVILLE
IGO
INVERNESS
INYOKERN
93435
96040
95233
95527
95563
94540
94541
94542
94542
94543
94544
94544
94544
94545
94545
94545
94546
94552
96064
95448
93627
94547
95323
95467
94010
95324
95023
95023
95024
95234
95545
95546
95547
95573
95449
95325
95326
93628
93210
93234
93245
95547
96047
94937
93526
INYOKERN
INYOKERN
IONE
IRVINE
ISLETON
JACKSON
JACKSON
JACKSON
JACKSON
JAMESTOWN
JENNER
JOHNSON PARK
JOLON
KEDDIE
KELSEY
KELSEYVILLE
KENSINGTON
KENSINGTON
KENSINGTON
KENSINGTON
KENTFIELD
KENTFIELD
KENWOOD
KENWOOD
KERMAN
KERMAN
KETTLEMAN CITY
KETTLEMAN CITY
KEYES
KING CITY
KING CITY
KING CITY
KINGS CANYON
KINGS CANYON
KINGSBURG
KINGSBURG
KINGSBURG
KNEELAND
KNIGHTS FERRY
KNIGHTS LANDING
KNIGHTS LANDING
KNIGHTS LANDING
KNIGHTSEN
KORBEL
KYBURZ
93527
93555
95640
92612
95641
92629
95642
95647
99210
95327
95450
96013
93928
95971
95667
95451
94706
94707
94707
94708
94901
94904
95409
95452
93630
93631
93234
93239
95328
93930
93930
93930
93633
93633
93631
93631
93631
95549
95361
95645
95645
95645
94548
95550
95720
LA GRANGE
LA GRANGE
LA GRANGE
LA HONDA
LA HONDA
LA PORTE
LA SELVA BEACH
LAFAYETTE
LAGUNITAS
LAKE ALMANOR
LAKE ALMANOR
LAKE ALMANOR
LAKE BERRYESSA
LAKEHEAD
LAKEPORT
LAKEPORT
LAMONT
LARKSPUR
LARKSPUR
LARKSPUR
LATHROP
LATON
LATON
LAYTONVILLE
LAYTONVILLE
LAYTONVILLE
LE GRAND
LEBEC
LEBEC
LEGGETT
LEMOORE
LEMOORE
LINCOLN
LINCOLN
LINDEN
LINDEN
LITTLE NORWAY
LITTLE NORWAY
LITTLE RIVER
LITTLE VALLEY
LIVE OAK
LIVE OAK
LIVERMORE
LIVERMORE
LIVERMORE
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 124
95329
95329
95329
94020
94020
95981
95076
94549
94938
96020
96137
96137
94558
96051
90267
95453
93241
94904
94939
94977
95330
93242
93242
95417
95454
95490
95333
93243
93243
95585
93245
93656
95648
95648
95236
95236
95721
95735
95456
96056
95816
95953
92660
94513
94550
LIVERMORE
LIVERMORE
LIVERMORE
LIVERMORE
LIVERMORE
LIVERMORE
LIVERMORE
LIVERMORE
LIVINGSTON
LOCH LOMOND
LOCH LOMOND
LOCKEFORD
LOCKWOOD
LODI
LODI
LODI
LOLETA
LOMA MAR
LOMPOC
LOMPOC
LOMPOC
LONG BARN
LOOMIS
LOS ALAMOS
LOS ALAMOS
LOS ALTOS
LOS ALTOS
LOS ALTOS
LOS ALTOS HILLS
LOS ALTOS HILLS
LOS BANOS
LOS BANOS
LOS GATOS
LOS GATOS
LOS GATOS
LOS GATOS
LOS GATOS
LOS GATOS
LOS GATOS
LOS GATOS
LOS GATOS
LOS GATOS
LOS MOLINOS
LOS OLIVOS
LOS OSOS
94550
94550
94551
94551
94551
94551
94551
94588
95334
95426
95461
95237
93932
95240
95241
95242
95551
94021
93436
93437
93438
95335
95650
93440
93441
94022
94022
94024
94022
94024
93635
93635
95030
95030
95030
95031
95032
95032
95032
95033
95033
95033
96055
93441
93401
LOS OSOS
LOS OSOS
LOS OSOS
LOST HILLS
LOTUS
LOWER LAKE
LUCERNE
LUCERNE VALLEY
MAD RIVER
MAD RIVER
MADERA
MADERA
MADERA
MADERA
MADISON
MAGALIA
MANCHESTER
MANTECA
MANTECA
MANTECA
MANTON
MANTON
MARICOPA
MARICOPA
MARINA
MARIPOSA
MARIPOSA
MARKLEEVILLE
MARSHALL
MARTELL
MARTELL
MARTINEZ
MARTINEZ
MARYSVILLE
MARYSVILLE
MARYSVILLE
MARYSVILLE
MARYSVILLE
MARYSVILLE
MAXWELL
MC ARTHUR
MC FARLAND
MC FARLAND
MC FARLAND
MC KITTRICK
93402
93405
93412
93249
95651
95457
95458
92356
95552
95552
93637
93638
93638
93639
95653
95954
95459
95336
95337
95366
96059
96059
93252
93252
93933
95338
95338
96120
94940
95642
95654
94553
94553
95661
95901
95901
95903
95991
95992
95955
96056
93205
93250
93350
93251
MCARTHUR
MCARTHUR
MCCLELLAN
MCKINLEYVILLE
MCKINLEYVILLE
MEADOW VALLEY
MEADOW VALLEY
MEADOW VALLEY
MEADOW VISTA
MENDOCINO
MENDOTA
MENLO PARK
MENLO PARK
MENLO PARK
MERCED
MERCED
MERCED
MERCED
MERCED
MERIDIAN
MERIDIAN
METTLER STATION
METTLER STATION
MI WUK VILLAGE
MIDDLETOWN
MIDDLETOWN
MIDDLETOWN
MIDPINES
MILL CREEK
MILL VALLEY
MILL VALLEY
MILL VALLEY
MILLBRAE
MILLVILLE
MILPITAS
MILPITAS
MILPITAS
MILPITAS
MILPITAS
MINERAL
MINERAL
MIRAMONTE
MIRANDA
MODESTO
MODESTO
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 125
96056
96056
95652
95519
95521
95656
95956
95971
95722
95460
93640
94025
94027
94028
95329
95340
95341
95344
95348
95957
95957
93301
93313
95346
95461
95461
95467
95345
96061
94941
94941
94942
94030
96062
94583
94583
95035
95035
95036
96061
96063
93641
95553
95350
95351
MODESTO
MODESTO
MODESTO
MODESTO
MODESTO
MODESTO
MODESTO
MODESTO
MOJAVE
MOKELUMNE HILL
MONTARA
MONTE RIO
MONTE SERENO
MONTEREY
MONTEREY
MONTEREY
MONTEREY
MONTGOMERY
CREEK
MONTGOMERY
CREEK
MONTGOMERY
CREEK
MORAGA
MORGAN HILL
MORGAN HILL
MORRO BAY
MORRO BAY
MOSS BEACH
MOSS LANDING
MOSS LANDING
MOUNT AUKUM
MOUNT HERMON
MOUNT HERMON
MOUNTAIN HOUSE
MOUNTAIN RANCH
MOUNTAIN RANCH
MOUNTAIN VIEW
MOUNTAIN VIEW
MOUNTAIN VIEW
MOUNTAIN VIEW
MOUNTAIN VIEW
MUIR BEACH
MURPHYS
MYERS FLAT
95352
95353
95354
95355
95355
95356
95357
95358
93502
95245
94037
95462
95030
93924
93940
93942
93944
96001
96065
96084
94556
95037
95038
93442
93443
94038
93950
95039
95656
95018
95041
95391
95246
95246
94039
94040
94040
94041
94043
94965
95247
95554
NAPA
NAPA
NAPA
NAVARRO
NELSON
NEVADA CITY
NEVADA CITY
NEW CUYAMA
NEWARK
NEWARK
NEWARK
NEWBERRY SPRINGS
NEWCASTLE
NEWMAN
NEWMAN
NEWMAN
NICASIO
NICE
NICOLAUS
NIPOMO
NIPOMO
NIPOMO
NIPOMO
NORDEN
NORDEN
NORTH EDWARDS
NORTH FORK
NORTH HIGHLANDS
NORTH HIGHLANDS
NORTH SAN JUAN
NORTH SAN JUAN
NORTH SAN JUAN
NOVATO
NOVATO
NOVATO
NOVATO
NOVATO
NOVATO
NOVATO
NOVATO
NUBIEBER
O NEALS
OAK RUN
OAKDALE
OAKDALE
94558
94558
94559
95463
95958
95949
95959
93254
94538
94560
94560
92365
95658
95350
95360
95360
94946
95464
95659
93420
93444
93444
93454
95724
95724
93523
93643
95652
95660
95960
95960
95960
94945
94945
94947
94947
94948
94949
94954
94998
96068
93645
96069
95361
95361
OAKDALE
OAKHURST
OAKHURST
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLAND
OAKLEY
OAKLEY
OAKVILLE
OCCIDENTAL
OCEANO
OLD STATION
OLEMA
OLIVEHURST
OLIVEHURST
OLIVEHURST
ORANGE COVE
ORANGE COVE
ORANGE COVE
ORANGEVALE
ORANGEVALE
ORCUTT
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 126
95361
93644
95389
94601
94602
94603
94604
94605
94606
94607
94607
94608
94609
94610
94611
94612
94612
94613
94614
94615
94618
94619
94621
94623
94623
94623
94704
94705
95816
94513
94561
94562
95465
93445
96071
94950
95901
95918
95961
93646
93646
93675
95662
95662
93440
ORCUTT
ORCUTT
OREGON HOUSE
ORICK
ORINDA
ORINDA
ORLAND
ORLAND
ORLAND
ORLAND
ORLEANS
OROSI
OROVILLE
OROVILLE
OROVILLE
PACHECO
PACIFIC GROVE
PACIFIC HOUSE
PACIFICA
PAICINES
PALERMO
PALO ALTO
PALO ALTO
PALO ALTO
PALO ALTO
PALO ALTO
PALO ALTO
PALO ALTO
PALO ALTO
PALO ALTO
PALO CEDRO
PARADISE
PARADISE
PARLIER
PARLIER
PASKENTA
PASO ROBLES
PASO ROBLES
PASO ROBLES
PATTERSON
PAYNES CREEK
PEBBLE BEACH
PENN VALLEY
PENN VALLEY
PENNGROVE
93454
93455
95962
95555
94523
94563
95963
95963
95963
96130
95556
93647
95965
95966
95966
94553
93950
95726
94044
95043
95968
94034
94066
94301
94303
94303
94304
94304
94305
94306
96073
95967
95969
93648
93727
96074
93446
93447
93465
95363
96075
93953
95946
95946
94951
PENRYN
PESCADERO
PETALUMA
PETALUMA
PETALUMA
PETALUMA
PETALUMA
PETROLIA
PHILLIPSVILLE
PHILO
PIEDMONT
PIEDMONT
PIEDMONT
PIEDMONT
PIERCY
PIERCY
PIKE CITY
PILOT HILL
PILOT HILL
PINE GROVE
PINE GROVE
PINECREST
PINECREST
PINEDALE
PINEHURST
PINOLE
PINOLE
PIONEER
PISMO BEACH
PISMO BEACH
PITTSBURG
PITTSBURG
PLACERVILLE
PLANADA
PLATINA
PLATINA
PLEASANT GROVE
PLEASANT GROVE
PLEASANT HILL
PLEASANTON
PLEASANTON
PLEASANTON
PLEASANTON
PLEASANTON
PLEASANTON
95663
94060
93003
94952
94952
94953
94954
95558
95559
95466
94602
94610
94611
94618
95587
95587
95960
95664
95664
95665
95666
95314
95364
93650
93641
94564
94803
95666
93448
93449
94553
94565
95667
95365
96076
96076
95668
95668
94523
94538
94566
94566
94566
94566
94566
PLEASANTON
PLEASANTON
PLEASANTON
PLEASANTON
PLEASANTON
PLEASANTON
PLEASANTON
PLUMAS LAKE
PLYMOUTH
POINT ARENA
POINT REYES
POINT REYES
STATION
POLLOCK PINES
POPE VALLEY
PORT COSTA
PORTOLA VALLEY
POTTER VALLEY
PRATHER
PRESIDIO
PRINCETON
PRINCETON
PRINCETON
PROBERTA
PULGA
QUINCY
RACKERBY
RAIL ROAD FLAT
RAIL ROAD FLAT
RAIL ROAD FLAT
RAIL ROAD FLAT
RAISIN
RAISIN CITY
RANCHO CORDOVA
RANCHO CORDOVA
RANCHO CORDOVA
RAYMOND
RAYMOND
RED BLUFF
RED BLUFF
RED TOP
REDCREST
REDDING
REDDING
REDDING
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 127
94566
94568
94588
94588
94588
94588
94588
95961
95669
95468
94956
94956
95726
94567
94569
94028
95469
93651
94129
95970
95970
95970
96078
95965
95971
95972
95232
95245
95248
95248
93652
93652
95655
95670
95742
93653
93653
96080
96080
95340
95569
96001
96002
96003
REDDING
REDDING
REDDING
REDWAY
REDWOOD CITY
REDWOOD CITY
REDWOOD CITY
REDWOOD CITY
REDWOOD CITY
REDWOOD CITY
REDWOOD ESTATES
REDWOOD ESTATES
REDWOOD VALLEY
REEDLEY
REEDLEY
REEDLEY
REEDLEY
RESCUE
RESCUE
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHMOND
RICHVALE
RIDGECREST
RIDGECREST
RIO DELL
RIO LINDA
RIO LINDA
RIO NIDO
RIO OSO
RIO VISTA
RIO VISTA
RIO VISTA
RIPON
RIPON
RIVER PINES
96049
96099
97405
95560
94061
94062
94063
94063
94064
94065
95044
95044
95470
93654
93654
93654
99999
95672
95682
90221
94530
94801
94802
94803
94804
94805
94806
94806
94807
94808
94850
95974
93555
93555
95562
95661
95673
95471
95674
94520
94571
94571
95366
95366
95675
RIVERBANK
RIVERBANK
RIVERBANK
RIVERBANK
RIVERDALE
RIVERDALE
ROBBINS
ROBBINS
Rocklin
ROCKLIN
ROCKLIN
ROCKLIN
RODEO
RODEO
ROHNERT PARK
ROHNERT PARK
ROHNERT PARK
ROSEVILLE
ROSEVILLE
ROSEVILLE
ROSEVILLE
ROSEVILLE
ROSEVILLE
ROSEVILLE
ROSS
ROUGH AND READY
ROUND MOUNTAIN
RUMSEY
RUTH
RUTH
RUTH
RUTHERFORD
RYDE
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
95361
95363
95367
95367
93656
93656
95676
95676
95677
95677
95765
95775
94572
94577
94927
94928
94931
95661
95678
95678
95678
95746
95747
95841
94957
95975
96084
95679
95526
95526
95551
94573
95680
94298
95628
95758
95812
95814
95814
95815
95816
95816
95816
95816
95816
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SACRAMENTO
SAINT HELENA
SAINT HELENA
SALIDA
SALINAS
SALINAS
SALINAS
SALINAS
SALINAS
SALINAS
SALINAS
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 128
95816
95816
95817
95818
95818
95819
95820
95821
95822
95823
95824
95825
95825
95826
95827
95828
95829
95830
95831
95832
95833
95834
95834
95834
95834
95834
95835
95836
95837
95837
95838
95841
95842
95843
95864
94574
94574
95368
93901
93902
93905
93905
93906
93907
93908
SALINAS
SALINAS
SALYER
SAMOA
SAN ANDREAS
SAN ANSELMO
SAN ARDO
SAN BRUNO
SAN CARLOS
SAN CARLOS
SAN CARLOS
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
93912
93915
95563
95564
95249
94960
93450
94066
94070
94070
94303
94080
94101
94102
94103
94104
94105
94105
94105
94106
94106
94107
94108
94108
94109
94110
94111
94111
94112
94114
94115
94116
94117
94118
94119
94121
94122
94123
94123
94124
94127
94128
94129
94131
94132
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN FRANCISCO
SAN GERONIMO
SAN GREGORIO
SAN JOAQUIN
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
94133
94133
94134
94143
94158
94963
94074
93660
94538
95002
95008
95013
95035
95037
95101
95102
95110
95110
95110
95111
95112
95113
95113
95116
95117
95118
95119
95119
95119
95120
95121
95122
95123
95124
95124
95125
95125
95125
95126
95126
95126
95126
95127
95128
95129
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JOSE
SAN JUAN BAUTISTA
SAN LEANDRO
SAN LEANDRO
SAN LEANDRO
SAN LEANDRO
SAN LEANDRO
SAN LORENZO
SAN LUCAS
SAN LUCAS
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN LUIS OBISPO
SAN MARTIN
SAN MATEO
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 129
95129
95130
95131
95132
95133
95133
95134
95135
95136
95138
95139
95140
95141
95148
95150
95151
95153
95153
95154
95160
95160
95161
95192
95045
94577
94577
94578
94579
94580
94580
93930
93954
90071
90603
93401
93402
93403
93405
93406
93408
93420
93433
93449
95046
94025
SAN MATEO
SAN MATEO
SAN MATEO
SAN MATEO
SAN MATEO
SAN MATEO
SAN MATEO
SAN MATEO
SAN MIGUEL
SAN MIGUEL
SAN MIGUEL
SAN MIGUEL
SAN MIGUEL
SAN PABLO
SAN QUENTIN
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAFAEL
SAN RAMON
SAN RAMON
SAN RAMON
SAN RAMON
SAN RAMON
SAN RAMON
SAN RAMON
SAN SIMEON
SAND CITY
SANGER
SANGER
SANTA BARBARA
SANTA BARBARA
SANTA BARBARA
SANTA BARBARA
SANTA CLARA
SANTA CLARA
SANTA CLARA
SANTA CLARA
94062
94401
94401
94402
94403
94404
94404
94404
93446
93451
93451
93451
93451
94806
94964
92264
94901
94901
94903
94904
94912
94913
94915
94915
94956
95816
94506
94582
94583
94583
94583
94583
94583
93452
93955
93657
93711
93101
93103
93105
93110
95050
95050
95050
95051
SANTA CLARA
SANTA CLARA
SANTA CRUZ
SANTA CRUZ
SANTA CRUZ
SANTA CRUZ
SANTA CRUZ
SANTA CRUZ
SANTA CRUZ
SANTA CRUZ
SANTA MARGARITA
SANTA MARGARITA
SANTA MARIA
SANTA MARIA
SANTA MARIA
SANTA MARIA
SANTA MARIA
SANTA MARIA
SANTA MARIA
SANTA MARIA
SANTA NELLA
SANTA ROSA
SANTA ROSA
SANTA ROSA
SANTA ROSA
SANTA ROSA
SANTA ROSA
SANTA ROSA
SANTA ROSA
SANTA ROSA
SANTA ROSA
SANTA YNEZ
SARATOGA
SARATOGA
SARATOGA
SAUSALITO
SAUSALITO
SCOTIA
SCOTTS VALLEY
SCOTTS VALLEY
SCOTTS VALLEY
SEA RANCH
SEA RANCH
SEA RANCH
SEASIDE
95053
95054
95060
95062
95062
95062
95062
95064
95065
95066
93422
93453
92674
92693
93454
93454
93455
93456
93457
93458
95322
95401
95402
95403
95404
95405
95406
95407
95407
95409
95492
93460
95070
95070
95071
94965
94966
95565
95060
95065
95066
95445
95497
95497
93955
SEBASTOPOL
SEBASTOPOL
SEBASTOPOL
SELMA
SELMA
SELMA
SELMA
SELMA
SELMA
SELMA
SEVILLE
SHAFTER
SHANDON
SHANDON
SHASTA
SHASTA LAKE
SHASTA LAKE
SHASTA LAKE
SHAVER LAKE
SHAVER LAKE
SHEEP RANCH
SHELL BEACH
SHERIDAN
SHINGLE SPRINGS
SHINGLE SPRINGS
SHINGLETOWN
SIERRA CITY
SISQUOC
SISQUOC
SITES
SMARTVILLE
SMARTVILLE
SNELLING
SNELLING
SODA SPRINGS
SODA SPRINGS
SODA SPRINGS
SODA SPRINGS
SOLEDAD
SOLVANG
SOLVANG
SOMERSET
SOMES BAR
SONOMA
SONOMA
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 130
95401
95472
95473
90720
93622
93622
93657
93662
93706
93721
93292
93263
93451
93461
96087
96003
96019
96089
93602
93664
95250
93449
95681
95682
95682
96088
96125
93454
93455
95979
95977
95977
95369
95369
95724
95724
95728
95728
93960
93463
93464
95684
95568
95476
95476
SONORA
SONORA
SONORA
SOQUEL
SOULSBYVILLE
SOUTH DOS PALOS
SOUTH SAN
FRANCISCO
SOUTH SAN
FRANCISCO
SOUTH SAN
FRANCISCO
SPRECKELS
SQUAW VALLEY
SQUAW VALLEY
STANDARD
STANFORD
STEVINSON
STEWARTS POINT
STINSON BEACH
STIRLING CITY
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
92651
95370
95379
95073
95372
93665
94080
94083
94112
93962
93646
93675
95373
94305
95374
95480
94970
95978
90212
90404
94545
95201
95202
95202
95203
95204
95204
95204
95205
95206
95206
95207
95207
95208
95209
95209
95210
95211
95212
95213
95213
95215
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STOCKTON
STONYFORD
STONYFORD
STORRIE
STRATFORD
STRAWBERRY
STRAWBERRY
VALLEY
SUISUN
SUISUN
SUISUN
SUISUN
SUISUN CITY
SUISUN CITY
SUISUN CITY
SUISUN CITY
SULTANA
SUNNYVALE
SUNNYVALE
SUNNYVALE
SUNNYVALE
SUNNYVALE
SUNNYVALE
SUNOL
SUTTER
SUTTER CREEK
TAFT
TAFT
TAFT
TAYLORSVILLE
TAYLORSVILLE
TEHACHAPI
TEHAMA
TEMPLETON
THORNTON
TIBURON
TOLLHOUSE
TOMALES
TRACY
95219
95219
95234
95236
95240
95267
95336
95979
95979
95980
93266
95375
95981
94533
94534
94585
95685
94534
94585
94585
94585
93666
94085
94086
94087
94088
94089
95014
94586
95982
95685
92647
93268
93453
95934
95983
93561
96090
93465
95686
94920
93667
94971
92110
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRACY
TRANQUILLITY
TRAVER
TRAVIS AFB
TRES PINOS
TRINIDAD
TRONA
TULARE
TUOLUMNE
TUPMAN
TURLOCK
TURLOCK
TURLOCK
TWAIN
TWAIN HARTE
TWIN BRIDGES
UKIAH
UKIAH
UNION CITY
UNION CITY
UPPER LAKE
UPPER LAKE
VACAVILLE
VACAVILLE
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 131
92691
92707
94520
94550
94577
94588
95201
95206
95304
95304
95304
95376
95376
95376
95377
95377
95378
95378
95385
95385
95391
95391
93668
93673
94535
95075
95570
93562
93274
95379
93276
95380
95380
95382
95984
95383
95735
95482
95482
94587
94587
95485
95493
95687
95688
VACAVILLE
VALLECITO
VALLECITO
VALLEJO
VALLEJO
VALLEJO
VALLEJO
VALLEJO
Vallejo
VALLEJO
VALLEJO
Vallejo
VALLEJO
VALLEY ACRES
VALLEY FORD
VALLEY FORD
VALLEY HOME
VALLEY SPRINGS
VALLEY SPRINGS
VERNALIS
VERNALIS
VICTOR
VICTORVILLE
VILLA GRANDE
VINA
VISALIA
VISALIA
VISALIA
VISALIA
VOLCANO
WALLACE
WALNUT CREEK
WALNUT CREEK
WALNUT CREEK
WALNUT CREEK
WALNUT CREEK
WALNUT CREEK
WALNUT CREEK
WALNUT CREEK
WALNUT CREEK
WALNUT GROVE
WALNUT GROVE
WALNUT GROVE
95696
95229
95251
94503
94503
94583
94589
94590
94590
94590
94591
94591
94592
93268
94972
94972
95361
95252
95255
95385
95385
95253
92394
95486
96092
93277
93279
93291
93292
95689
95254
94595
94595
94596
94596
94597
94597
94597
94598
94598
95690
95690
95690
WALNUT GROVE
WASCO
WASHINGTON
WATERFORD
WATSONVILLE
WATSONVILLE
WATSONVILLE
WATSONVILLE
WATSONVILLE
WAUKENA
WAUKENA
WAWONA
WEIMAR
WEIMAR
WEITCHPEC
WEOTT
WEST POINT
WEST POINT
WEST POINT
WEST SACRAMENTO
WEST SACRAMENTO
WEST SACRAMENTO
West Sacramento
WEST SACRAMENTO
WEST SACRAMENTO
WEST SACRAMENTO
WEST SACRAMENTO
WEST SACRAMENTO
WESTLEY
WESTPORT
WESTWOOD
WESTWOOD
WHEATLAND
WHEATLAND
WHISKEYTOWN
WHITE PINES
WHITETHORN
WHITETHORN
WHITMORE
WILDWOOD
WILLIAMS
WILLITS
WILLOW CREEK
95690
93280
95986
95386
95019
95076
95076
95076
95077
93274
93282
95389
95713
95736
95546
95571
95255
95255
95404
95605
95691
95691
95691
95695
95695
95798
95828
95961
95387
95488
96137
96137
95692
95692
96095
95223
95589
95589
96096
96076
95987
95490
95573
WILLOW CREEK
WILLOWS
WILLOWS
WILSEYVILLE
WILSEYVILLE
WINDSOR
WINTERS
WINTERS
WINTERS
WINTON
WINTON
WISHON
WITTER SPRINGS
WOODACRE
WOODBRIDGE
WOODBRIDGE
WOODLAKE
WOODLAND
WOODLAND
WOODLAND
WOODSIDE
WOODSIDE
WOODSIDE
YETTEM
YOLO
YORKVILLE
YOSEMITE NATIONAL
PARK
YOSEMITE NATIONAL
PARK
YOUNTVILLE
YUBA CITY
YUBA CITY
YUBA CITY
YUBA CITY
YUBA CITY
YUBA CITY
ZAMORA
ZENIA
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 132
96039
95988
95988
95257
95257
95492
95694
95694
95695
95301
95388
93669
95493
94973
95258
95258
93286
95695
95695
95776
94026
94061
94062
93670
95697
95494
95389
95389
94599
95661
95901
95991
95992
95993
95994
95698
95595
APPENDIX C
DA APPROVED METERS
The table below lists the makes and models of currently approved DA meters. The contents of the list is
subject to change. The list has been provided for informational purposes only.
MAKE
MODEL
PSI
QUAD 4
SCHLUMBERGER
VECTRON LXS
GE
KV
Pacific Gas and Electric Company, CONFIDENTIAL – For Internal Use by Authorized Personnel Only
10/5/05
Page 133
Download