THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
THE SECOND PENANG BRIDGE PROJECT
Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
TABLE OF CONTENT
BRIEFING OF CHINA HARBOUR ENGINEERING COMPANY (CHEC)
INTRODUCTION OF SECOND PENANG BRIDGE PROJECT(P2B)
DESIGN MANAGEMENT AND TECHNICAL RESOLUTIONS
CONSTRUCTION PLANNING & MANAGEMENT
PLANNING & SCHEDULING
HEALTH & SAFETY & ENVIRONMENT (HSE)
QUALITY MANAGEMENT
RISK MANAGEMENT
CONCLUSION
ACKNOWLEDGEMENT
29 January 2013 CHEC Construction (M) Sdn Bhd 2
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
HISTORY & EVOLUTION
Since founded in the 1980s, CHEC has spanned 3 stages within 30 years, and keeps moving on the fast track of development.
Leap
Development
Initiation
Preliminary stage
Early 1980s-late 1990s
(
Labour supply, contracting of lowend project or project with Chinese factors)
Secondary Stage
Late 1990s-2005
(Overall contracting of projects)
Third Stage
2006-present
(Contracting of EPC, BOT and other sophisticated projects)
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
INITIATION (EARLY 1980S-LATE 1990S)
Friendship Port, Mauritania 300,000DWT Drydock, Malta
360m long,62m wide and 12.5 deep
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
DEVELOPMENT(LATE 1990S-2005)
Gwadar Deep Water Port Project (Phase I), Pakistan Dredging & Reclamation of Macau International Airport, Macau
Client: Ports and Shipping Wing, MOC, Pakistan
Contract value: USD 248 million
Construction period: March 2002 to April 2004
Scope of Works:
Design & build of three multi-purpose berths with
602m long to accommodate 50,000 DWT container vessels plus navigation dredging and associated facilities.
Client: Macao Airport Authority
Contract Value: US$ 677 million
Construction Period: Jan. 1992 to Jan. 1995
Scope of Works:
Design and build an artificial island of 115m 2 including 34M m 3 sandfill with ground improvement and 8km seawalls plus 300,000 m 2 pavement and two linking bridges for an international airport.
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
LEAP(2006-PRESENT)
Energia Costa Azul LNG Terminal Work Pack II
Breakwater, Baja California, Mexico
Client: Energia Costa Azul. (Sempra Energy)
Contract Value: US$ 161.3 million.
Construction Period: January 2005 to May 2008.
Scope of Works:
• Design and construct 660 m long and 25 m water deep breakwater at 300 m offshore.
• Supply and install 12 nos. precast concrete caissons which are 38 m wide,
46 m long and 25.5 m high, each caisson weighs approx. 18,000T.
Phase1 Project of International Container Terminal in
Ho Chi Minh City, Vietnam
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
LEAP(2006-PRESENT)
Hambantota International Airport, Sri Lanka
Scope of works:
3500m*60m runway; 370m*45m taxiway;
110,000m 2 parking apron; 12,000m 2 passenger terminal and control tower; 10,000m 2 cargo terminal and others, such as installation and commissioning of navigation aids, lighting, firefighting and rescuing facilities, energy supply and pollution discharge system.
New Puking Hotel, Macao
Project Features:
228m in height,
44 floors, covering 12,000 m 2 .
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
LEAP(2006-PRESENT)
Boubyan Seaport Project Stage 1 – Road, Bridge & Soil Treatment, Kuwait
Employer: Mega Project Agency, Ministry of Public Works
Contractor: CHEC – GDC – SAC Joint Venture
Contract Value: US$ 413 million
Contract Period: July 2007 to December 2009
Scope of Works:
• Design and build 33km three lanes carriageway including 1.3km sea crossing bridge with the navigation channels 35m + 45m +
35m of 17m above HAT (sea level)
• Design and build 29km rail section including 1.3km sea crossing bridge, 9.8km railway viaducts and rail embankments
• Approximately 50 million lin. m vertical band drains plus the surcharge are adopted for ground improvement works.
• Maintain the works for five years after the substantial completion.
Design, Construction and Completion of The Second
Penang Bridge, Malaysia (ongoing) a project under the cooperative framework between China and Malaysia, and the largest civil work in Malaysia for the past 20 years
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
ORGANIZATIONS & SUMMARY
4, 35, 70+
4 worldwide business regions, 35 overseas offices covering over 70 countries and areas
Network of Overseas Business and Branches
Middle
East
4bn, 2.4bn+
Newly signed contract value over 4bn USD and turnover over 2.4bn USD in 2010;
9.5bn+ contract value of ongoing projects over 9.5bn
USD;
7,000+
Over 7000 domestic and international staff;
Africa
Asia
6
5
Latin
America
CHEC is recognized as a worldrenowned international contractor;
5
CHEC, major international operating division of CCCC, contribute mostly to CCCC’s ranking No. 5 among international Contractors so far as turnover is concerned according to ENR.
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CORE BUSINESS
海事工程
Marine Engineering
轨道交通
Railways
公路桥梁
Roads and Bridges Aviation
成套设备
Complete Plant
疏浚吹填
Dredging & Reclamation
其他领域
Others: Investment, Environment,
Natural Resources, Buildings, etc.
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
INTEGRATED RESOLUTION & SERVICES
CHEC provides full services of project planning, feasibility study, financing, design, construction, maintenance and operation to create the maximum value for its clients.
Full Service
Creating the greatest value for our clients
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CORE VALUES
CHEC: the ocean of a thousand streams, the bearer of great social responsibility, the seeker of everlasting excellence.
Excellent leader and organizer to provide full service in the field of marine engineering
Fulfilling both commercial and social responsibilities;
Ensuring safety and Quality;
Establishing win-win cooperation.
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
PROJECT INTRODUCTION
PROJECT ALIGNMENT
29 January 2013
BRIDGE ALIGHMENT & PERSPECTIVE VIEW
CHEC Construction (M) Sdn Bhd 14
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
INTRODUCTION OF SECOND PENANG BRIDGE(P2B)
PROJECT PACKAGES
Package 1: Main Navigation Span and Substructure & Foundation Works of
Approach Spans
Package 2: The Design, Construction and Completion of the Superstructure for the Approach Spans
Package 3: The Design, Construction and Completion of the 7km Batu Maung
Interchange and the Landside Works
29 January 2013 CHEC Construction (M) Sdn Bhd 15
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
INTRODUCTION OF SECOND PENANG BRIDGE(P2B)
CHEC’S SCOPE OF WORK - PACKAGE 1
From approximately CH0+543.46m to CH16+913.46m( 16km long ). comprises of:
Main Navigation Span comprising of the navigation span of 117.5m + 240m +
117.5m(total 475m) arrangement
Substructure & Foundation of approach spans structure comprising of series of 55m span (excluding the bridge bearings)
Deck drainage , road pavement, marking & signages, street lighting, decorative lighting, aviation lighting and navigation lighting for main navigation span
ARRANGEMENT
Bridge type : A four-lane dual carriageway bridge with two motorcycle lanes
Design speed : 80 km/h
Overall deck width: 29.8 m for Approach Spans
35.6 m for Main Navigation Span
Span arrangement: 475m (117.5m+240m+117.5m) for Main Navigation Span
55 m of each span for Approach Spans
29 January 2013 CHEC Construction (M) Sdn Bhd 16
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
INTRODUCTION OF SECOND PENANG BRIDGE(P2B)
PROJECT QUANTITIES
Foundation Piles
PHC Driven Spun Piles(Ø1.0mx40mm) : 5,187 nos. (5,168 nos.)
Driven Steel Piles(Ø1.6mx22mm) : 368 nos.
(360 nos.)
Bored piles(Ø2.0mx121m) : 66 nos. (Main Spans) (14+21+21+14)
Bored Piles(Ø1.5mx105m) : 80 nos . (Approach Spans) (8x10)
Materials
Concrete : 263,000 m 3
Reinforcement : 42,700 tonne
Stayed cables : 753 tonne
29 January 2013 CHEC Construction (M) Sdn Bhd 17
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
PROJECT MANAGEMENT FRAMEWORK
ORGANIZATIONAL CHART
MHA
JKSB
UEM BUILDERS BHD
PACKAGE 2
CERGAS MURNI
PACKAGE 3A
CHEC CONSTRUCTION SDN BHD
PACKAGE 1 ( 中国港湾 )
IJM CONSTRUCTION
PACKAGE 3B
HRA TEGUH
PACKAGE 3C
SUBCONTRACTORS CONSULTANTS SPECIALISTS ADVISORS
SECTION 1 SECTION 2 SECTION 3 SECTION 4
MMSB HPDI
FDINE
(SLT&PDA)
THEIDI
(SOIL)
CTESI
(TEST)
TPEIJG
(MLT)
CCYY
(SURVEY)
GEONAMICS
(STATNAMIC)
MR. PETER AECOM HK OTHER
HRA HRA
AECOM
29 January 2013
ICP ICP
CHEC Construction (M) Sdn Bhd 18
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CODES, STANDARDS & SPECIFICATIONS
CODES, STANDARDS & SPECIFICATIONS
JKR, LLM, Arahan Teknik (Jalan)
British Standard(BS), BD, BA, European Code(EN)
American AASHTO
Chinese Standard
General
Volume I
Conditions of Contract
Employer's
Requirements
Design-Build(DB)
Contract for P2B
Volume II
Specifications
Volume III
Contract Drawings
Malaysian JKR
Specifications
Supplementary
Speciffications from
Contractor
Contractual Documents related with Technical Requirements & Standards
29 January 2013 CHEC Construction (M) Sdn Bhd
Design Brief
19
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
SOLUTIONS FOR NAVIGATIONAL CHANNEL
BRIDGE OPTIONS AND PARAMETERS – SOLUTIONS FOR NAVIGATIONAL CHANNEL
Finalized and Adopted Option - Perspective View of Concrete cable stayed bridge (Feb 2008)
Arrangement of 117.5m + 240m + 117.5m
29 January 2013 CHEC Construction (M) Sdn Bhd 20
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
SOLUTIONS FOR NAVIGATIONAL CHANNEL
BRIDGE OPTIONS AND PARAMETERS – PERCEPTION OF MARINE VIEWING PLATFORM
29 January 2013
Perspective View of Marine Viewing Platform (Dec 2007)
CHEC Construction (M) Sdn Bhd 21
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
TYPE OF FOUNDATIONS
BRIDGE OPTIONS AND PARAMETERS – TYPE OF FOUNDATIONS
Bored Pile
2.0m
Diameter with depth of 120m for Main Navigational Channel
1.5m
Diameter with depth of 105m for Landside Approach Spans
Driven Steel Pile
1.6m
Diameter with depth of 83m for High Piers Area
PHC Driven Spun Pile
1.0m Diameter with depth of 53m for Most of Approach Spans
29 January 2013 CHEC Construction (M) Sdn Bhd 22
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
SITE INVESTIGATION
Objective
Carry out detailed geotechnical investigation along the proposed bridge alignment
Identify the subsurface soil profile, bedrock geology, ground water condition and the presence of unfavorable soil conditions, if any
Provide basis for engineering design of the foundation
Primary Borehole and Findings
Planning and Summary of Primary Borehole
Test Equipments & Methods
Laboratory Test and Findings
Recommendations
Additional Borehole and Analysis
Planning and summary of Additional Borehole
Testing method and Determination of Estimated Borehole Depth
Comparisons & Findings
Reanalysis & Recommendations
29 January 2013 CHEC Construction (M) Sdn Bhd 23
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
SITE INVESTIGATION - ADDITIONAL BOREHOLE AND ANALYSIS
Planning and summary of Additional Borehole
29 January 2013
Drilling Rig & CPT Test System
CHEC Construction (M) Sdn Bhd 24
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
SITE INVESTIGATION - ADDITIONAL BOREHOLE AND ANALYSIS
Planning and summary of Additional Borehole
29 January 2013
Site Investigation – ABH14
CHEC Construction (M) Sdn Bhd 25
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
SITE INVESTIGATION - ADDITIONAL BOREHOLE AND ANALYSIS
Planning and summary of Additional Borehole
29 January 2013
Site Investigation – ABH8
CHEC Construction (M) Sdn Bhd 26
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - PRIMARY PLANNING & GENERAL LAYOUT
Test Stages
It is proposed that, 10 numbers of piles are to be tested in two stages. Stage 1 will cover 6 numbers of piles consisting of PHC piles and steel pipe piles.
Stage 2 will cover 4 numbers of piles which will be bored piles and a steel pipe pile. Stage 1 piles are sacrificial piles and stage 2 piles are working piles.
Stage 1: involves high strain dynamic pile load test(PDA) and static pile load test(SLT/MLT) on 5 numbers of PHC piles (4 concrete spun piles of
Φ1m, 1 concrete spun pile of Φ1.2m) and 1 number of steel pipe pile of
Φ1.2m.
Stage 2: covers 4 numbers of piles, includes 2 numbers of bored cast-inplace piles of Φ2.5m and steel pipe driven piles of Φ1.6m.
29 January 2013 CHEC Construction (M) Sdn Bhd 27
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - PRIMARY PLANNING & GENERAL LAYOUT
Locations of Testing Piles
29 January 2013 CHEC Construction (M) Sdn Bhd 28
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - PRIMARY PLANNING & GENERAL LAYOUT
Scheme on Piling Test
No. Pile Type
BHT1 PHC Pile
BHT2 PHC Pile
BHT3 Steel Pile
BHT4 PHC Pile
BHT5 PHC Pile
BHT6 PHC Pile
BHT7 Bored Pile
BHT8 Bored Pile
BHT9 Steel Pile
BHT10 Steel Pile
Pile Diameter
(m)
1.0
1.0
1.2
1.0
1.0
1.2
2.5
2.0
1.6
1.6
Pier
Ref.
-
-
-
-
-
-
P26
P27
P13
P38
Pile Length
(m)
58
68
72.8
50.5
66
62
120
95
90
90
Test Load
(kN) (x2.5)
9500
9500
Reaction
System
Stage
Anchor Pile 1 st Stage
Anchor Pile 1 st Stage
14500
9500
Anchor Pile &
Osterberg Test
1 st Stage
Anchor Pile 1 st Stage
Anchor Pile 1 st Stage 9500
11500 Anchor Pile 1 st Stage
80000 Osterberg Test 2 nd Stage
32500 Osterberg Test 2 nd Stage
24000 Osterberg Test 2 nd Stage
24000 Osterberg Test 2 nd Stage
High-strain Dynamic Pile Test(PDA)
Osterberg Cell Test
Static-load test(MLT)
Dynamic load test(PDA)
29 January 2013 CHEC Construction (M) Sdn Bhd 29
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - DISCUSSIONS & FURTHER ACTIONS
Revised Test Scheme
Load Test Location
BHT8
Category near P15 non-working pile 1.6m steel pile
BHT11 near P163 non-working pile 1.0m spun pile
BHT12 near P292 non-working pile 1.5m bored pile
N.A.
N.A.
BHT7
N.A.
N.A.
N.A.
N.A.
*P49-15
*P185-8
P33-7
P24
P25
P26
P27 working pile working pile working pile working pile working pile working pile working pile
Pile Type
1.0m spun pile
1.0m spun pile
1.6m steel pile
2.0m bored pile
2.0m bored pile
2.0m bored pile
2.0m bored pile
PDA initial restrike initial restrike
NIL
NIL
NIL
Type of Load Test
MLT Statnamic test pile anchor pile test pile
NIL
NIL anchor pile anchor pile test pile anchor pile working pile working pile
NIL test pile(O-cell) working pile
NIL
NIL
NIL
NIL
NIL
NIL
NIL
NIL working pile working pile working pile working pile
Instrument ation no no yes yes no no no no yes no no
Purpose
To establish correlation
To establish correlation
To establish correlation
For acceptance of driven pile
For acceptance of driven pile
For acceptance of driven pile
For acceptance of installed pile and verification of pile design
NOTES:
*Selected pile was determined by the Engineer for statnamic test for P49 and P185 Suspicious working pile shall be checked and verified for acceptance as follows: a) Driven pile - by PDA or statnamic b) Bored pile - by statnamic
All working piles for statnamic test shall be tested to 2 times Working Load
29 January 2013 CHEC Construction (M) Sdn Bhd 30
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - DISCUSSIONS & FURTHER ACTIONS
Revised MLT – Principles & Methodology
29 January 2013
Details of Test Platform
CHEC Construction (M) Sdn Bhd 31
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - DISCUSSIONS & FURTHER ACTIONS
Revised MLT – Principles & Methodology
29 January 2013
Details of Test Platform
CHEC Construction (M) Sdn Bhd 32
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - DISCUSSIONS & FURTHER ACTIONS
Statnamic Test - Principles & Methodology
Gravel
Container
Gravel container
Gravel
Silencer
Cylinder
Platform
Laser
Laser beam
Laser
Pile
Piston
Load cell
Pile to be tested
29 January 2013
Statnamic Schematic
CHEC Construction (M) Sdn Bhd 33
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - DISCUSSIONS & FURTHER ACTIONS
Statnamic Test – Set Up
29 January 2013
Offshore Setup of Statnamic Test
CHEC Construction (M) Sdn Bhd 34
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
GEOTECHNICAL INVESTIGATION & PILING TEST
PILING TEST - DISCUSSIONS & FURTHER ACTIONS
Statnamic Test – Set Up
29 January 2013
Land Setup of Statnamic Test
CHEC Construction (M) Sdn Bhd 35
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction Processes & Method Statements
Construction basically consists of two parts, namely foundation of approach spans and whole main cable-stayed bridge. For foundation of approach spans, activities cover piling(PHC Spun Pile,
Steel Pile and Bored pile), pilecap and pier construction.
While for main cable-stayed bridge, from substructure to superstructure, major construction works include piling, construction of pilecap
& Pylon & Deck & Cable &
Pavement & Facilities and so on.
29 January 2013 CHEC Construction (M) Sdn Bhd 36
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction Processes & Method Statements
29 January 2013 CHEC Construction (M) Sdn Bhd 37
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Requirements on Fabrication of PHC Spun Pile
Manufacture Requirement of PHC Piles
• PHC Spun Pile Performance Requirements
Item
Nominal diameter
Min. characteristic strength
(MPa)
Parameter Test method or reference standards
1000 mm MS 1314-4:2004
Characteristic value for 28 day age compressive strength of 150mm cube
78.5 under the same curing condition
(guarantee rate above 95% (failure rate less than 5%)) shall not be less than 78.5MPa
Effective prestress 8.4 MPa
Cracking flexural capacity 936.6 kNm
Ultimate flexural capacity 2085.7 kNm
Min. wall thickness 140 mm
Local specifications (ICP-PHC Pile Type
C)
Min. concrete cover 55 m
Shortest distance from concrete surface to the outermost rebar
29 January 2013 CHEC Construction (M) Sdn Bhd 38
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
Construction Methodology of Driven Piles
• Driving of Piles
Difference between pile top elevation and the designed elevation
Δh(m)
Set Criteria of Hydraulic Hammer for Spun Pile
Blow energy
E(KJ)
Average penetration of last 20cm
Detailed operations
Up to the design height
E≥150
0<Δh≤1.5
Δh>1.5
E≥150 ~ 180
≤8
>8
≤5
≤5
Stop driving
Carry out high strain dynamic test and analyze test results, report to designer and supervising engineer if the test result is not satisfactory
Stop driving
Carry out high strain dynamic test and analyze test results, report to designer and supervision engineer if the test result is not satisfactory
29 January 2013 CHEC Construction (M) Sdn Bhd 39
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
Construction Methodology of Driven Piles
• Driving of Piles
Set Criteria of Hydraulic Hammer for Tubular Steel Pile
Difference Between the Actual Level and
Design Level of the
Pile Top Δh (m)
Ram Energy
E (kj)
Detailed operations
≤6
Average penetration depth for the last 10 blows
Reach the design pile top level
E≥250
>6
Stop Driving
Carry out high strain dynamic test and analyze test results, report to designer and supervision engineer if the test result is not satisfactory
0<Δh≤1.5
Δh>1.5
≤4
E≥250~300
≤4
Stop driving
Carry out high strain dynamic test and analyze test results, report to designer and supervision engineer if the test result is not satisfactory
29 January 2013 CHEC Construction (M) Sdn Bhd 40
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
Construction Methodology of Driven Piles
• Driving of Piles
29 January 2013
Pile Deviation Tolerances
Inspection Item
Pile Type
Vertical Pile
Raked Pile
Permitted deviation from the intended position(mm)
75
75
• Updated Acceptance Criteria for Deviation of Driven Piles
Pile shaft inclination tolerance
1/75
1/25
- The tolerance of pile installation for marine driven piles within 150mm shall be acceptable and applicable WITHOUT further analysis or action for the
Second Penang Bridge Project, including both spun piles and steel piles.
- While for pile deviation more than 150mm, it’s recommended that
FURTHER calculation shall be carried out to justify the structural acceptance.
CHEC Construction (M) Sdn Bhd 41
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
29 January 2013
Driving PHC Spun Piles
CHEC Construction (M) Sdn Bhd 42
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
29 January 2013
Demobilization of Piling Rigs(Sub-mariner)
CHEC Construction (M) Sdn Bhd 43
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
29 January 2013
Demobilization of Piling Rigs
CHEC Construction (M) Sdn Bhd 44
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
Construction Methodology of Bored Piles
• Borehole Construction
Slurry Fluid Index After Hole Cleaning
Item
PH
Value
Density
(g/cm 3 )
Adhesive ness(s)
Plasticity
Index 8 ~ 10 ≤1.10 20 ~ 22 98% & above
Permeability Rate
(ml/30min)
≤20
Sand
Content (%)
≤2
29 January 2013
Item(JJC-1D)
Hole Center
Position
Hole Diameter
Inclination
Hole Depth
Allowable Deviation
Pile group (on the sea area) , not exceeding 75mm
Remarks
Use GPS, theodolite to determine vertical and horizontal alignment
Not less than the pile design diameter
Not exceeding 1/75 of pile length
Friction Pile: Not less than hole design depth
End Bearing Pile: Deeper than design depth by not less than 50mm
Check before concrete pouring
Check before concrete pouring
Check before concrete pouring
CHEC Construction (M) Sdn Bhd 45
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
29 January 2013
Bored Pile Construction
CHEC Construction (M) Sdn Bhd 46
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
29 January 2013
Bored Pile Construction
CHEC Construction (M) Sdn Bhd 47
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
29 January 2013
Bored Pile Construction
CHEC Construction (M) Sdn Bhd 48
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
Driven Records & Findings
29 January 2013
Summary of Driven Piles
Notes : 19 replacement piles @ P193-21 A & B, P280-15A & B, P107-07 A & B, P102-12 A & B, P61-13 A & B, P120-04 A & B,
P122-07A, 07B & 08A, P137-07 A & B, P9-17 A & B
CHEC Construction (M) Sdn Bhd 49
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
Driven Records & Findings
29 January 2013
Summary of Bored Piles at Main Span
CHEC Construction (M) Sdn Bhd 50
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Construction Specifications and Piling Control
Driven Records & Findings
Summary of Bored Piles at Approach Spans
29 January 2013 CHEC Construction (M) Sdn Bhd 51
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Inspection Methods & Records
Inspection Methods & Acceptance Criteria
• Inspection Objective
- PDA Test
To evaluate the activated static capacity, driving stresses, hammer performance and to assess the integrity of the pile during the pile driving.
- PIT Test
To check the quality of pile foundation works for the approach spans.
- Sonic Logging Test(CSL)
To check the quality of bored pile foundation works.
29 January 2013 CHEC Construction (M) Sdn Bhd 52
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Inspection Methods & Records
Inspection Methods & Acceptance Criteria
• High Strain Dynamic Testing
- Pile Integrity Determination for Spun Pile
Pile Integrity Determination Criteria
BETA Value(BTA)
100%
80 to 99%
60 to 80%
< 60%
Description
Uniform Pile
Slight Damage
Damage
Pile Broken (generally pile is then rejected)
Qualification Determination
Good
Qualified
Unqualified
Unqualified ( Broken)
29 January 2013 CHEC Construction (M) Sdn Bhd 53
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Inspection Methods & Records
Inspection Methods & Acceptance Criteria
• Pile Integrity Test
- Sonic Logging Test(For Bored Piles Only)
Concrete
Quality
FAT (First Arrival time) Increase (%)
Good 0 to 10
Questionable 10 to 20
Poor/Flaw
Poor/Defect
20 to 30
>30
Simultaneously Satisfies
/ An Item Satisfies
add
add
or
or
Energy
Reduction(dB)
<6
<9
9 to 12
>12
29 January 2013 CHEC Construction (M) Sdn Bhd 54
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Inspection Methods & Records
Inspection Methods & Acceptance Criteria
• Pile Integrity Test
- Sonic Logging Test(For Bored Piles Only)
Class
I
II
III
IV
Characteristics
The pile is integral.
All sonic parameters of all the points in the testing profiles are regular, and there is no sonic velocity less than allowable low limit.
The pile is with slight flaw.
Some of sonic parameters of certainn points in one of the testing profiles are irregular, there are no sonic velocity less than allowable low limit.
The pile can be judged as obviously defective.
Sonic parameters of many continuous points in one of the testing profiles are irregular.
Sonic parameters of the same depth points in two or more testing profiles are irregular.
There are few sonic velocities of concrete less than the allowable low limit.
The pile can be judged as seriously defective or with fracture.
Sonic parameters of many continuous points in one of the testing profiles are irregular.
Sonic parameters of the same depth points in two or more testing profiles are irregular.
There are many sonic velocities of concrete less than allowable low limit or there is no way of detecting whether the first achieved wave or received signals are seriously defective.
29 January 2013 CHEC Construction (M) Sdn Bhd 55
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Inspection Methods & Records
Inspection Methods & Acceptance Criteria
• Proposed Acceptance Criteria for Bored Piles
29 January 2013
- Proposed Acceptance Criteria
The proposed acceptance criteria is shown as below, which can be applied to bored piles for both Approach Span and Cable-stayed Bridge in Second
Penang Bridge Project.
Proposed Acceptance Criteria for Bored Piles
Inspection after
Repair
N/A
N/A
I
II
Class Class (ASTM)
III
IV
Acceptance Remedial Measure
Good
Questionable/
Poor
Poor/ Defect
Acceptable
Acceptable*
Obvious defects, remedy required
Serious defects, remedy required
N/A
N/A
Remove defect concrete by chiseling or pressure water jetting and concrete casting or pressure grouting
Remove defect concrete by chiseling or pressure water jetting and concrete casting or pressure grouting
CHEC Construction (M) Sdn Bhd
Crosshole Sonic
Logging(CSL)
Crosshole Sonic
Logging(CSL)
56
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Inspection Methods & Records
Inspection Methods & Acceptance Criteria
• Proposed Acceptance Criteria for Bored Piles
- Supplementary Acceptance Criteria on Class II Bored Piles
Acceptance Criteria for Bored Piles with Class II anomalies
Type
1
2
3
4
5
6
No. of detected anomalies Action to be taken
1 line of anomaly (side) No treatment required
1 or 2 lines of anomalies (diagonal) No treatment required
2 lines of anomalies (adjacent sides) No treatment required
2 lines of anomalies (opposite sides) No treatment required
2 lines of anomalies (side and diagonal)
No treatment required
3 lines of anomalies
Further investigation to define problem
29 January 2013 CHEC Construction (M) Sdn Bhd 57
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Piling Construction – Technical routings and Resolutions
Inspection Methods & Records
Inspection Records & Further Discussions
• Inspection on Acceptance for Bored Piles
29 January 2013 CHEC Construction (M) Sdn Bhd 58
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Pilecaps
Construction Survey
Preparation of Pile Heads
Bottom Forms and Waling of Pile cap
Rebar (Reinforcement) Bending of the 1st Layer (First Casting)
Steel Side Forms Erecting (for first casting)
Concrete Placing of the 1st Layer (or first casting)
Removal of Forms
Concrete plug Placing (or plugging of pile head)
Construction of Precast RC Shell
Rebar Bending of the 2nd Layer of Pile Cap
Concrete Placing of the 2nd Layer of Pile Cap
Anti-corrosion Treatment of Pile Cap
29 January 2013 CHEC Construction (M) Sdn Bhd 59
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Pilecaps
29 January 2013
Layout Plan of Steel Waling of Pile Cap
CHEC Construction (M) Sdn Bhd 60
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Pilecaps
29 January 2013
Installation of Steel Waling of Pile Cap
CHEC Construction (M) Sdn Bhd 61
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Pilecaps
29 January 2013
Installation of Steel Waling of Pile Cap
CHEC Construction (M) Sdn Bhd 62
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Pilecaps
Construction of Precast RC Shell
• Brief Introduction
In the second casting operation of the pile cap, precast RC shell (concrete plank or facial precast concrete panel) shall be installed around the pile caps from P1 to P282 of the proposed bridge except P23~28 (which is the main navigational span). For the second casting of each pile cap, six pieces of precast RC shell shall be required. There are two types of the precast RC shell involved. The heights of the two types of panels are 3.8m and 3.2m respectively.
29 January 2013
Height of RC Shell
3800mm
3200mm
Part of Concrete Plank Height(mm)
Upper portion
Lower portion
Upper portion
Lower portion
2000
1800
1400
1800
CHEC Construction (M) Sdn Bhd
Thickness(mm)
250
200
250
200
63
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Pilecaps
Construction of Precast RC Shell
29 January 2013
Installation of RC Shell & Joint Details
CHEC Construction (M) Sdn Bhd 64
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Pilecaps
Construction of Precast RC Shell
29 January 2013
Precasting & Installation of RC Shell Details
CHEC Construction (M) Sdn Bhd 65
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Piers
Scope of Works on Piers
• The construction of Piers will depend on the fabrication, assembly and erection of appropriate steel formworks. Steel moulds shall be fabricated to suit to the three types of piers and crossheads to be constructed.
• All the 296 piers are low piers which are to be constructed using one continuous set installation of pre-fabricated steel formworks from pier to crosshead. These low piers have maximum height of about 5 meters from top of pile cap to top of crosshead. These piers shall be constructed using layer of pre-fabricated steel pier modules which are installed, casted, removed and installed on the next layer, repeating the concreting process until the crosshead level is reached.
Summary of Moulds for Piers
PIER & CROSSHEAD TYPE PIER TYPE TYPE OF STEEL MOULD
C1
C1A
C1B
Free Piers
Fixed Piers
M.J. Piers
Type 1/1A
Type 1B
29 January 2013 CHEC Construction (M) Sdn Bhd 66
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Piers
Construction Procedures
Construction Procedures
4. INSTALLATION OF MOULD TYPE 1, 1A OR 1B AFTER PIER RE-BAR
INSTALLATION a) Prior to setting up the pier mould assembly, re-check the steel base for any movement by visual inspection and using bar level. If the alignment and level have been disturbed, fix the base accordingly. b) Apply approved mould oil on the internal surface of the mould. c) Using crane, lift the pier mould assembly no. 1 on the designated pick up points using appropriate spreader/frame to be connected to the mould. d) Secure the pier mould assembly no.1 onto the base and install the diagonal supports with turn-buckles anchored to the pile cap using the previously installed dowels. e) Once secured, release the mould from the lifting frame and prepare for lifting of the pier mould assembly no.2. f) Lift the pier assembly no.2 just like the first one, and slowly put in place on top of the steel base mould until properly aligned. g) Secure the mould in place using the diagonal braces and then release the mould from the lifting frame. h) Adjust the diagonal braces using the turnbuckles and insert the bolts and nuts to form the concreting outline. i) When all bolts and nuts are installed, adjust the diagonal braces if necessary for proper alignment and verticality. j) Check the top of the mould using bar level to make sure the next mould assembly would fit well.
29 January 2013 CHEC Construction (M) Sdn Bhd 67
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Piers
Construction Procedures
Construction Procedures
6. INSTALLATION OF STEEL MOULD SUPPORTS a) Once all re-bar works are complete, install the vertical spine members to join continuously the pier and crosshead moulds. b) The horizontal bracing members shall then be installed at the top of the crosshead. Bracket members to be bolted into the spine member to ensure the stiffness and rigidity of the steel mould.
29 January 2013 CHEC Construction (M) Sdn Bhd 68
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Piers
29 January 2013
Construction Procedures
Construction Procedures
10. REMOVAL OF FORMWORKS g) Using the crane and frame, lift down the crosshead mould assembly and place it in the designated place for cleaning and future use; h) Remove the bolts joining the two pier mould assemblies, and keep them in proper storage for future use; i) Place hydraulic jack support and timber support below the pier mould assembly to prevent abrupt or accidental dropping of the heavy mould. j) Loosen the turn-buckles of the diagonal braces of the first pier mould assembly to separate the mould internal face from the concrete surface. k) Once the mould has separated from the concrete surface, use the crane and lifting frame to hold the first pier assembly and detach the diagonal braces from the mould; l) After that, slowly take out the mould away from the pier by using the crane and stockpile in designated place for cleaning and preparation for next use. m) For the removal of the second pier mould assembly, repeat steps (h) to (l) above. n) Immediately after removal of moulds, check for any defects on the concrete. Minor surface defects should be immediately rectified. Major defects shall be reported and method to rectify shall be submitted for approval prior to doing repairs. o) As stated in curing works, immediately spray curing compound on the concrete surface. p) Apply anti-corrosion paint onto the cured concrete surface within the height of 2m from top of pile cap immediately after the surface getting dry.
CHEC Construction (M) Sdn Bhd 69
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Piers
29 January 2013 CHEC Construction (M) Sdn Bhd 70
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Piers
29 January 2013 CHEC Construction (M) Sdn Bhd 71
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Pilecaps and Piers at Approach Spans
Construction of Piers
29 January 2013 CHEC Construction (M) Sdn Bhd 72
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction Engineering – Responsibility Matrix and Techniques
Organization and Responsibility Matrix
29 January 2013 CHEC Construction (M) Sdn Bhd 73
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction Engineering – Responsibility Matrix and Techniques
Construction Stages & Analytic Techniques
29 January 2013 CHEC Construction (M) Sdn Bhd 74
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction Engineering – Responsibility Matrix and Techniques
Construction Stages & Analytic Techniques
29 January 2013 CHEC Construction (M) Sdn Bhd 75
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction Engineering – Responsibility Matrix and Techniques
Construction Stages & Analytic Techniques
• Objectives of Construction Engineering
Construction Analysis is to be carried out for the main cable-stayed bridge construction taking full account of the sequence and method of construction, permanent loads, and temporary loads during construction, construction schedule, material properties, time dependent effects, etc.
The objective of the Construction Analysis is:
- To establish a methodology for the construction of the bridge which does not cause overstress to any part of the permanent bridge structure during construction
- Results in a structure exhibiting the dead load geometry and force distribution defined by the designer and as shown in the contract drawings
- Based on the construction erection analysis, a Construction Manual shall be produced, which aims at outline the construction methods and techniques used in the construction, with respect to their influence on the final geometry and force distribution in the completed bridge structure.
29 January 2013 CHEC Construction (M) Sdn Bhd 76
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction Engineering – Responsibility Matrix and Techniques
Construction Stages & Analytic Techniques
• Analytic Construction Sequences & Stages
29 January 2013 CHEC Construction (M) Sdn Bhd 77
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Pilecaps Encased with Steel Fender
Steel Fender – Fabrication, Delivery and Installation
• Lower Down Steel Fender Casing
29 January 2013 CHEC Construction (M) Sdn Bhd 78
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Pilecaps Encased with Steel Fender
Steel Fender – Fabrication, Delivery and Installation
29 January 2013
Installation of Steel Fender
CHEC Construction (M) Sdn Bhd 79
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Pilecaps Encased with Steel Fender
Steel Fender – Fabrication, Delivery and Installation
29 January 2013
Installation of Steel Fender
CHEC Construction (M) Sdn Bhd 80
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Pilecaps Encased with Steel Fender
Concreting Work of Pilecap
29 January 2013
Sequence of concreting work for main pier pilecap
CHEC Construction (M) Sdn Bhd 81
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Pilecaps Encased with Steel Fender
Concreting Work of Pilecap
29 January 2013 concreting work for main pier pilecap
CHEC Construction (M) Sdn Bhd 82
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Pilecaps Encased with Steel Fender
Temperature & Crack Control
• Introduction
The dimension of pile cap supporting the main tower is 48.1m
×
17.5m
×
6.0m and the volume of concrete to be cast is 5051m3. The dimension of accessory pile cap is 42.7m
×
10.6m
×
4.0m and the volume of concrete to be cast is about 1810m3 .The grade of concrete used for pile cap is 40Mpa at 28 days.
• Temperature Criteria Specified in JKR Specification
NO. Items
1 Placing Temperature
2 Maximum Internal Temperature
3 Maximum Temperature Gradient
4 Rise rate in Temperature
Requirement
≤ 36 ℃
≤ 70 ℃
≤27.7
℃
≤ 10 ℃ /30min
29 January 2013 CHEC Construction (M) Sdn Bhd 83
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Pilecaps Encased with Steel Fender
Temperature & Crack Control
• Temperature Control Measures in-Situ
- Concrete Preparation
- Placing Temperature Control
◊ Proper measures should be taken to control the placing temperature.
◊ Fresh Cement can not be used on site immediately because of the high temperature and the fresh cement shall be cooled in the storehouse of manufacturer, which has been reached agreement with supplier.
◊ Set the sunshine shutter, lay gravel higher and utilize from the bottom of stockpile, sprinkling cool water on gravel to reduce the temperature.
- Controlling the Pouring Interim and Layer Thickness
- Design Cooling Water Pipe
◊ The concrete poured in two layers separately. Pipes with cycling cooling water embedded in these layers to bring out the internal heat.
29 January 2013 CHEC Construction (M) Sdn Bhd 84
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Pylon Construction – Overview and Detailing
Construction Stages of Pylon Tower
29 January 2013
General Layout of Construction Stages of Pylon Tower
CHEC Construction (M) Sdn Bhd 85
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Pylon Construction – Overview and Detailing
Construction Sequence of Pylon Tower
29 January 2013 CHEC Construction (M) Sdn Bhd 86
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Pylon Construction – Overview and Detailing
Pylon Tower Construction
29 January 2013 CHEC Construction (M) Sdn Bhd 87
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Pylon Construction – Overview and Detailing
Pylon Tower Construction
• Cross Beam
29 January 2013
General Layout of Cross Beam Formwork Support at Pylon Tower
CHEC Construction (M) Sdn Bhd 88
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Transition Piers
29 January 2013
General Layout of Cross Beam Formwork Support at Transition Pier
CHEC Construction (M) Sdn Bhd 89
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
General Description
29 January 2013
2 . 6 8 0
S1
8
S0
1
M0
1
1 0 3 . 2 8 0
S T A Y C A B L E
M18
2 . 6 8 0
CHEC Construction (M) Sdn Bhd
C L O F B R I D G E
90
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
Traveler form consists of the following:
- Loading bearing system
- Travel system
- Anchorage system
- Formwork system
- Operation platform
- Embedded fitting / material system
29 January 2013 CHEC Construction (M) Sdn Bhd 91
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
29 January 2013
General Arrangement of Form Traveler
CHEC Construction (M) Sdn Bhd 92
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
29 January 2013
Components of Form Traveler
CHEC Construction (M) Sdn Bhd 93
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Assembly and Installation Methodology
29 January 2013
Form Traveler on Transportation Barge Against Steel Fender
CHEC Construction (M) Sdn Bhd 94
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Assembly and Installation Methodology
29 January 2013
General Layout of Position During Lifting of Form Traveler
CHEC Construction (M) Sdn Bhd 95
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
29 January 2013
Lifting & Positioning of Form Traveler
CHEC Construction (M) Sdn Bhd 96
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Operation during Construction
29 January 2013
Traveler Form installation in position
CHEC Construction (M) Sdn Bhd 97
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Operation during Construction
29 January 2013
Step 1 : n section : Casting of Edge Beam at side & main span simultaneously n Section Edge Beam - Longitudinal Stressing n-1 & n-2 Section Diaphragm – Transverse Stressing
CHEC Construction (M) Sdn Bhd 98
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Operation during Construction
29 January 2013
Step 2:
Installation of 1st Cable Stay and 1st stage stressing at n Section
CHEC Construction (M) Sdn Bhd 99
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Operation during Construction
29 January 2013
Step 3:
Lowering down Slab Formwork Support Frame (Arch) with top slab formwork by using hollow jacks– 1m.
Connect Front & Back Suspension Leg (Launching System) & launching rails.
Launch the rail to the next segment.
Remove the high strength tension bars
Launch form traveler forward until it in in position of next segment.
CHEC Construction (M) Sdn Bhd 100
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Operation during Construction
29 January 2013
Step 4:
Install the high strength tension bars.
Lift up the whole form Traveler – 1m
Stress the high strength tension bars to tighten the form traveler
Adjust Formwork System, Installation of support
Install the rebar cage to deck slab & diaphragm
2nd stage tension to stay cables symmetrically
Make final adjustment of top slab formwork & diaphragm n Section – casting deck slab & diaphragm
CHEC Construction (M) Sdn Bhd 101
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Operation during Construction
29 January 2013
Step 4:
CHEC Construction (M) Sdn Bhd 102
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Form Traveler
- Operation during Construction
29 January 2013
Step 5:
Cable Stay n Section – 3rd stage stressing simetrically
Adjust edge beam formwork & install rebar cage
The form traveller is ready for edge beam No n+1 concreting
Repeat the similar operation to cast subsequent segment
CHEC Construction (M) Sdn Bhd 103
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Construction of Typical Section
29 January 2013
Casting Sequence of Main Girder Beam
CHEC Construction (M) Sdn Bhd 104
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Construction of Typical Main Girder Beam Segment
• Construction of Typical Section
29 January 2013
Flowchart of Balanced Cantilever Cast-in-situ Construction
CHEC Construction (M) Sdn Bhd 105
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Stitch Construction
3 locations of stitch have been designed for the main girder beam base on the span combination. For the both side span, the stitch location is between SS16 and SS18 with length of 2.0m. For the main span, the stitch location is between both MS18 segments with length of 3.0m.
Based on pre-determined construction sequence, the construction of the stitch at both side spans shall be carried out first only follow by main span. Upon completion of the stitch construction at the main span, remove the traveler form and formwork support for the stitch. Subsequently, remove the stitch formwork support at both side spans. In order to avoid tensile stress, casting for the stitch is recommended to carry out at low temperature hour so as to induce compressive stress during initial setting as a result of increment of temperature.
29 January 2013 CHEC Construction (M) Sdn Bhd 106
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Stay Cable System – Components & Construction Methodology
• General Information
29 January 2013
- Stay Type: multi-strand, double planes of semi-fan type
- No. of Stays: (2x36) + (2x36) = 144
- Stay Length
shortest: ~22m longest: ~131m
- Stay Sizes: 6-37 to 6-73
• Stay Cable Installation
- Saddle Installation Methodology
Each saddle in the bridge pylons is supported by a separate support system.
The construction of the upper pylons is divided into fifteen concrete pours, and as each section is completed, the support system for the saddle in the next section can be fixed to the top of the previous section.
CHEC Construction (M) Sdn Bhd 107
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Stay Cable System – Components & Construction Methodology
• Stay Cable Installation
- Saddle Installation Methodology
29 January 2013
Saddle arrangement
CHEC Construction (M) Sdn Bhd 108
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Stay Cable System – Components & Construction Methodology
• Stay Cable Installation
29 January 2013
Stay pipe suspended by rope and interfacing with formtraveller
CHEC Construction (M) Sdn Bhd 109
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Stay Cable System – Components & Construction Methodology
• Stay Cable Installation
29 January 2013
HDPE Pipe clamp and trolley
CHEC Construction (M) Sdn Bhd 110
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
METHOD STATEMENTS & TECHNICAL RESOLUTIONS
METHOD STATEMENTS & TECHNICAL RESOLUTIONS FOR CONSTRUCTION
Construction of Cable-stayed Bridge – Technology and Methodology
Construction of Superstructure – Deck & Stay Cable System
Stay Cable System – Components & Construction Methodology
• Stay Cable Installation
29 January 2013
Stressing using mono strand jack and application of power seating
CHEC Construction (M) Sdn Bhd 111
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CONSTUCTION PLANNING AND MANAGEMENT
CONSTUCTION PLANNING AND MANAGEMENT
Master Plan – Organizing, Monitoring & Updating
Master Work Programme
29 January 2013
Overall Construction planning & Sequences
CHEC Construction (M) Sdn Bhd 112
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CONSTUCTION PLANNING AND MANAGEMENT
CONSTUCTION PLANNING AND MANAGEMENT
Progress Monitoring & Control
Establishing detail programme such as monthly working programme according to site construction progress and project baseline programme which is approved by the Client
Gathering, recording, and documenting project construction progress
Reporting and comparing actual project results against the baseline programme
Analyzing performance data and determining whether corrective or preventive action should be recommended
Gathering, recording, and documenting project information that provides project status, measurements of progress and reported to top management
Identifying the risk of delaying the project and corresponding actions
29 January 2013 CHEC Construction (M) Sdn Bhd 113
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CONSTUCTION PLANNING AND MANAGEMENT
CONSTUCTION PLANNING AND MANAGEMENT
Construction Supervision – Hierarchy & Implementation
Objective
To implement the Project Quality Plan in order to ensure that the works comply with the requirements of CHEC Construction (M) Sdn. Bhd. as stipulated in the
Contract and shall be constructed in accordance with the following documents:
• The approved construction drawings
• The approved specifications
• All other relevant documents
To satisfy the supervision and certification requirements
Implementation of Quality Assurance / Quality Control (QA/QC) processes
Daily monitoring of the construction activities in order to meet the Project
Quality Policy
29 January 2013 CHEC Construction (M) Sdn Bhd 114
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CONSTUCTION PLANNING AND MANAGEMENT
CONSTUCTION PLANNING AND MANAGEMENT
Quality Management – PDCA
Quality Management System
Level 1: CHEC’s Quality Manual
• The manual outlines the company’s quality policy, which is implemented via the setting up of efficient organizational responsibilities and operating procedures that touch on all relevant requirements by International Standard Organization, ISO 9001:2008 standards.
Level 2: CHEC’s Operating Procedure
• It is a system for controlling all the activities and processes, their interaction, with the attainment of quality, documented under operating procedure.
Level 3: CHEC’s Project Quality Plan
• These are detail instructions describing how specific activities are to be performed.
Functions and responsibilities of staffs and their authorities are also clearly defined. In this project, Project Director is overall in charge and assisted by other members as detailed in the Project Organization Chart.
29 January 2013 CHEC Construction (M) Sdn Bhd 115
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CONSTUCTION PLANNING AND MANAGEMENT
CONSTUCTION PLANNING AND MANAGEMENT
Quality Management & Control
29 January 2013 CHEC Construction (M) Sdn Bhd 116
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
HSE MANAGEMENT
HSE MANAGEMENT
Summary Implementation of HSE Management System
Local Authorities Legislation and requirements and Company Safety Management
System and all HSE procedures were provided with practically guidance on achieving the objectives of the company Health Safety and Environmental Policy. All
HSE obligations relating to the HSE legislations, Requirements, Codes of Practices
Local Authority Requirements and Client requirements, as well as CHEC ‘s requirements have been adhered for the project duration.
Safety & Health Performances and Statistic. From the year 2007 the accumulative workers exposure hours were total up with 12,000,000 hours. With that total exposure hours our company CHEC was manage to sustained two (2) Lost Time
Injuries and fifty one (51) total lost workdays due to accident.
Zero Accident. We manage to sustained 5,000,000 (about three and half years) hours with zero accident. And sad to reports here at 5,120,000 working hours we had one fatality accident due to the human error as a root course of the accident.
Emergency Response Plan The effective ERP was set up for the project and the drills were conducted biannually to ensure the effectiveness of the action plan. And the ERP were effectively utilised during the accident occurred on site during the project period.
29 January 2013 CHEC Construction (M) Sdn Bhd 117
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
HSE MANAGEMENT
HSE MANAGEMENT
Conclusion
All of the Health Safety & Environmental requirements as stipulated by DOSH and
DOE were complied and being implemented on this project. And project HSE Plan and procedure was found in-compliance and practically were implemented on site.
All the Machineries and premises registration were done and approvals from the
DOSH being obtain accordingly.
Training was conducted accordingly, includes the toolbox talk, CIDB and HSE induction is compulsory to all sections.
The commitment from the employer was practically committed and all the recommendation made by the Safety & Health Officer being implemented and immediately rectified as per recommended.
The Performance of Safety & Health in this project was achieved with 5,000,000
(five million working hour with zero LTI in March 2011) the commitment and cooperation from all employees were great. The culture of safety & health was currently adopted into the working procedure.
29 January 2013 CHEC Construction (M) Sdn Bhd 118
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
HSE MANAGEMENT
HSE MANAGEMENT
Conclusion
29 January 2013 CHEC Construction (M) Sdn Bhd 119
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
RISK MANAGEMENT
RISK MANAGEMENT
Technically related Risks : Assessment and Control
Risks of Underground and Geotechnical Conditions
Unforeseen or unexpected underground and geotechnical conditions are major contributors to cost and schedule overruns on large civil engineering projects
The basic problem faced in attempting to predict the geological and geotechnical risks in the project is the adequacy of the information obtained from the site investigation program
Overall risks under control for complicated geo-conditions
For driven piles, high pile loading capacity and economic pile length achieved, dramatically benefiting the Employer with excellent cost reduction as of remeasurement contract
For friction bored piles, due to unforeseen or unexpected geological conditions, the Contractor exposed to great risks with the specified project risk responsibility system
Unlikely to eliminate all geological risks, Effective Risk Sharing Mechanism(RSM) between the Employer and the Contractor
29 January 2013 CHEC Construction (M) Sdn Bhd 120
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
RISK MANAGEMENT
RISK MANAGEMENT
Risk Handling and Managing on Construction
Challenges on Dredging Works - Planning and Methodology
Dredging is a very costly operation and involves many uncertainties that cause environmental impacts and affect project cost
Factors considered in developing a dredging operation , including:
Determining the quantity of material to be dredged
Sampling to determine the physical and chemical properties of material to be dredged to assess production rates so that time and cost estimates are realistic, and to identify any pollutants
Selecting the appropriate dredge type and size, disposal method, and disposal area to ensure environmental protection
29 January 2013 CHEC Construction (M) Sdn Bhd 121
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
RISK MANAGEMENT
RISK MANAGEMENT
Risk Handling and Managing on Construction
Challenges on Dredging Works - Planning and Methodology
The proposed bridge alignment spanning extensive shallows in the Penang Channel requiring dredging for construction boats
Dredging Planning & Scheduling
• Construction requirements of Piling and Launching of SBG, both on access and matching project master program
• Consideration of the speed of sedimentation
Dredging Methodology
• Comparison between Trailing suction hopper dredger(TSHD) and grab dredger on Efficiency & Environmental Impacts
• Approximately 12 million m3 dredging volume, accounting for 10% of the whole project cost
29 January 2013 CHEC Construction (M) Sdn Bhd 122
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
RISK MANAGEMENT
RISK MANAGEMENT
Risk Handling and Managing on Construction
Challenges on Dredging Works - Planning and Methodology
29 January 2013
Dredging Equipments
CHEC Construction (M) Sdn Bhd 123
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
RISK MANAGEMENT
RISK MANAGEMENT
Risk Handling and Managing on Construction
Challenges on Dredging Works - Planning and Methodology
29 January 2013
Dredging Equipments
CHEC Construction (M) Sdn Bhd 124
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
RISK MANAGEMENT
RISK MANAGEMENT
Risk Handling and Managing on Construction
Quality Control to Minimize Impacts on Delays & Cost
Very Low Damage Ratio of 1.26% (<1.5%) of Spun Piles(5187 nos)
29 January 2013 CHEC Construction (M) Sdn Bhd 125
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
CONCLUSION
CONCLUSION
For Second Penang Bridge Project with Design-Build Contract, through well project management system and with effective implementation of such system, during project execution, technical and construction issues have been addressed and managed, which has dramatically helped bring project progress, control and quality under control. Furthermore, such good practices on project management have also helped on the following achievements:
Satisfied and even exceeded the Employer’s expectations on smooth and timely project delivery;
Helped improve and better local people’s quality of life and sustain our the environment;
Contributed to the practices and experiences for civil engineering industry.
Overall it has been proved quite successful project delivery for Second
Penang Bridge Project.
29 January 2013 CHEC Construction (M) Sdn Bhd 126
THE SECOND PENANG BRIDGE PROJECT - Package 1: Main Navigation Span and Substructure & Foundation Works of Approach Spans
ACKNOWLEDGEMENT
ACKNOWLEDGEMENT
The author would like to extend grateful thanks to the Employer of the project
JKSB, especially JKSB’s managing director Dato. Dr. Ismail, also Malaysian Highway
Authority(MHA), other relevant Malaysian Authorities and relevant Departments of Malaysian Government, UEM and other relevant package contractors, our local consultants and specialists for their kindness and collaboration to ensure China
Harbor Engineering Company(CHEC)with successful project delivery for this mega project in Malaysia. It’s great honor and pleasure for CHEC to contribute to the local communities and work with all these respected parties.
Also here, on behalf on CHEC and our team, the author would like to extend our greater appreciation for the organizer JKSB to provide the excellent opportunity to share our knowledge and experiences with all present.
We are looking forward to the potential cooperation with all of you in future.
29 January 2013 CHEC Construction (M) Sdn Bhd 127
!