Introduction
These training notes are to be used in conjunction with your ASHRAE 90.1 Appendix G - PRM
Navigator training.
In this training session you will be shown how to use the ASHRAE 90.1 Appendix G - PRM Navigator,
IES’s sustainable design workflow navigator, available as an option within the IES <Virtual
Environment>.
Henceforth in this document we will simply refer to this navigator as the “PRM Navigator”.
Prior to using the PRM Navigator, you will need to use ModelIT or the Model Geometry navigator to
create the building geometry from scratch or to edit the geometry. You can also edit geometry which
has been imported from SketchUp or Revit (via the IES SketchUp or Revit plugins) or via a gbXML
import.
This PRM Navigator training assumes that you have already been trained in ModelIT, ApacheSim
and ApacheHVAC.
These notes accompany your training and act as a reference point for your further study. The trainer
will show you how to perform various functions as shown in the following pages.
For more detailed help you can use the Help menu within the specific IES application, and also you
can refer to the user guides accessible from the <VE> Help menu.
1
Background
The PRM (Performance Rating Method) is an assessment method for buildings. It is based on
ASHRAE 90.1 Appendix G (Appendix G is compulsory in certain US states) and is based on running
costs rather than energy. The PRM can be used in the UK for LEED analysis projects.
The PRM is used to determine credit points awarded for percentage energy cost savings (via LEED
EA Credit 1and 2 for new construction, renovation, core and shell or schools projects).
The PRM is based on running costs rather than energy or carbon dioxide emissions. The PRM
compares a proposed building against the average of four baseline buildings. The thermal templates
for the baseline buildings are not fixed – they can be edited.
For PRM analyses you need full design information - the PRM method is not used for early stage
design.
14 energy end uses are reported in the PRM report such as interior lighting, exterior lighting,
elevators, pumps and “receptacle” equipment (eg computers).
Opening the model
We will use a pre-built model (geometry only).
2
Accessing the PRM Navigator
You will first be shown how to access the PRM navigator.
The PRM navigator is divided into a series of main sections, each of these with sub-sections.
Navigator Quality Assurance functions
Each navigator item has a notepad which is useful for recording settings and assumptions. There is a
check box (to remind you that you have completed that item) and an optional date/time stamp.
Some navigator items perform functions when you click on them, and some navigator items are
simply reminders (similar to items in a checklist) for you to do something.
Additionally, the entire workflow for a project can be copied and pasted (for example into a Word
document).
3
PRM navigator items
Preliminary data setup
Workflow concept
This item gives general help about the PRM concept and an overview of the PRM navigator.
Site, location and climate
Here you set the location and climate data, Use the wizard, and select the ASHRAE database for the
design weather data. Enable the “V 3.0 for PRM” check box. This will select the correct ASHRAE
weather percentiles for heating and cooling loads calculations. Select the required climate file for the
simulation and the required holiday template.
Prototype data (ASHRAE baseline)
Select the 90_1_2007_IP.mit file. This brings in predefined templates based on the ASHRAE 90.1
2007 user guide and also brings in standard profiles and grouping schemes. This is used as a
starting point. You could if you wish, create and use your own profiles for both the proposed and
baseline buildings.
Fossil fuel types
Set the fossil fuels used for reporting purposes. This is used to track end use fossil fuel consumptions
(like a “meter”). We will use the default values. Other equipment (eg lighting, computers etc) are
automatically assigned different fuel types.
Update profile working week order
This allows you to set the working week order (eg for the Middle East), and saves you having to
create new profile groups. This amends the weekly profile groups automatically. Tick “All” to update
all the profiles in one operation.
4
Building geometry
To create and edit the building geometry, or to import the building geometry you need to use the
Model Geometry navigator (model geometry creation and editing is covered in separate ModelIT
training sessions).
Site obstructions and shading
This is covered in ModelIT and SunCast training (separate training sessions). The building orientation
is important. Note that shading objects and SunCast analyses are for the proposed building only and
are not relevant for the baseline buildings.
Room/Zone group assignment
This stage is important. This tool assigns rooms to preloaded room groups very quickly. We will use
the “Word Search” option to do this. First, click “Extract”, to extract the schemes from the current
model. We will use the “Space by space method” grouping schemes in this example when performing
the word search. You can then look at the groups in the model browser and see the rooms assigned
to them. You could also assign rooms to groups manually if you need to.
Solar Shading calculations
This runs the solar shading calculations for the proposed building.
5
Envelope thermo-physical properties
ASHRAE baseline constructions
This will import ASHRAE baseline constructions to the project. The climate zone dictates the
constructions that are imported as per ASHRAE 90.1 section 5 guidelines.
Proposed building constructions
Improve baseline
Improve your proposed building constructions to be better than the baseline constructions. This
imports other opaque ASHRAE wall constructions if required. You will then need to assign the new
constructions using the Apply button or assigning them afterwards.
Custom construction type
You can create your own constructions using APcdb and then apply them.
Surface assignment
Above ground
Assign surfaces to the proposed building if required for rooms above Z=0 (you only need to do this if
you haven’t clicked Apply when improving your baseline above)
Ground contact
Assign ground contact constructions to the proposed building if required.
6
Room/Zone thermal template data
Space classification
Assigns thermal templates to zones by matching room group names to the template names for both
the baseline and proposed buildings. Note: that this won’t work properly if you haven’t set up room
groups properly first.
Internal heat gains
Equipment
There should be the same values in the proposed and baseline buildings – you will get a warning if
the values are different. Leaving the proposed cells blank assigns the baseline values to the
proposed values.
People
Sets the occupancy data for baseline and proposed buildings (the same for both buildings).
Lighting
Sets the lighting gains for the proposed buildings. The gains for the baseline building are fixed. The
10% reduction option reduces any current values by 10% each time you use this option.
7
ASHRAE 62.1 parameters
These are minimum fresh air ventilation requirements for ASHRAE 62.1. They are the same for
proposed and baseline buildings.
Note: This option is only applicable for early stage design and not generally suitable for a full LEED
analysis. You would either use this navigator item or the “Air Exchange >Outside Air Ventilation Rate
(simple)“ navigator item below. The option of which rates methodology to use is chosen later in the
process.
Occupancy and Ventilation tab
The Occupancy and Ventilation tab shows default values for both the the proposed and baseline
buildings. The “Default Occupancy Density” column shows values from ASHRAE 62.1. Requirements
are shown per person and per m 2. You are only able to change the design occupancy and the
percentage increase in ventilation for the proposed building. We will set the appropriate occupancy
categories for the space types in our model.
Exhaust requirements tab
There are pre-set flow rates for different space categories. Rates are only required for the restrooms
in this training example, Use the “toilets – public” category for restrooms (with say 1 unit) and set the
categories for other spaces to “none”.
Zone Air Distribution tab
Here we set any local regulations requirements. We will just use the default values, which are typical.
Ez is an efficiency factor to account for ventilation losses (eg Ez = 0.8 means that 80% of breathable
air is delivered to the space and 20% is lost beforehand.
Air exchange
Outside air ventilation rate (simple)
This starts the building template manager in the System tab, and allows you to enter your own rates
in “System outside air supply” if you prefer to use them instead of the ASHRAE 62.1 values above.
The values are used later in the sizing calculations (not the simulations). The option of which rates
methodology to use is chosen later in the process.
Infiltration
This starts the building template manager Air Exchanges list. Add other infiltration rates if required.
8
Other end uses
Exterior lighting
Enter areas/lengths as required. This calculates baseline values, then you can enter your proposed
values. External lighting power (but no gains) is applied to the last room in the model browser.
“Tradeable” refers to where you can improve the proposed values compared with the baseline
values. “Non-tradeable” refers to where proposed values cannot be less than the baseline values, for
example lighting on the building facade.
Elevators
Enter peak consumptions per elevator for both proposed and baseline buildings. This will not apply if
there are no elevator spaces (ie no elevator thermal templates) in the project.
Service hot water
This starts the building template manager. The default consumption is zero. You need to enter your
required consumption rates and profiles.
9
HVAC systems
Assign rooms
Use the “assign selected rooms to room groups” facility to apply zones to HVAC systems (eg by air
handling units grouping schemes).
System schedules
Sets the times of day for plant operation, and setpoints. This automatically updates profiles (in APpro)
for your baseline and proposed schedules. You can either amend the existing schedules or create
additional (alternate) schedules using a prefix.
Baseline system
Here you create the HVAC system for the baseline building.
Edit current baseline
The first time this option is clicked, the “Import prototype system” window will appear. You can then
select the appropriate ASHRAE baseline system as per ASHRAE 90.1 tables G3.1.1A and 1B. For
example, the appropriate system for non-residential buildings of 4 or 5 floors and less than 75,000 ft 2
is System 5 or 6.
Select the appropriate systems (in this example we will chose System 5, VAV with reheat with a fossil
fuel boiler), and these will appear in the ApacheHVAC view (Note: if you subsequently want to import
more prototype systems, you will need to click the Import prototype system” icon in the ApacheHVAC
toolbar).
We will then edit each multiplex and assign the rooms to the multiplexes using the “assign from
Room Group” button and selecting the AHU room groups.
Note: if you have created your own alternate schedules using a prefix (in System Schedules above),
you will need to assign them manually in all the system controllers (except for ON or OFF profiles).
You will see how to edit the system names in the ApacheHVAC view for your convenience, to reflect
the AHU’s serving each system.
10
System parameters
You will see a list of your baseline HVAC systems where you can edit coil temperatures, oversizing
factors and define energy saving measures if required. The “System” area in this dialogue box refers
to the main AHU coils. The “Zone” area refers to the room level coils. Check to see if economisers
are required for the project climate zone (ASHRAE table G3.1.2.6B).
When you click the Apply button, the 3 additional baseline systems (90, 180 and 270 Deg) are also
created and this information is passed to the sizing spreadsheets which are located in, for example,
Project name\loads data\90 deg baseline
Proposed system
Here you repeat the process as described for the baseline system above, but for your proposed
system. You can use any of the first three options below.
Improve upon baseline
When you select this option this will create the “proposed.asp” ApacheHVAC file (which initially will
be a copy of the baseline system) and this will be shown in the ApacheHVAC view. You can then
improve/change the system to become your proposed system.
Note: if you have performed this step previously, the next time you select this option you will see a
message warning you that the current proposed.asp file will be overwritten.
In this example we will use System 9c for the proposed system (active beams which can operate in
heating or cooling mode).
We will then edit each multiplex and assign the rooms to the multiplexes using the “assign from
Room Group” button and selecting the AHU room groups. This step is only necessary if you have
deleted any of the baseline systems in the proposed .asp file and have replaced them with a different
system.
Edit current proposed
If you have already generated a proposed system you can use this option to edit it.
Or custom system
You can create your own custom system from scratch.
System parameters
You can improve the parameters of your proposed system, for example using energy recovery with
65% sensible heat effectiveness or choosing to use Demand Controlled Ventilation.
11
Room conditions (setpoints)
This starts the building template manager in the Room Conditions tab where you can edit the
heating/cooling setpoints or heating/cooling profiles if you wish to modify them at this stage, for both
the baseline and proposed buildings.
Alternatively, you could select rooms by AHU group and edit this data using the Edit Group Attributes
facility. This data is used for ASHRAE load calculations, HVAC system sizing purposes & unmet load
hours checks. Note: this data is NOT used in the controllers in the HVAC networks when the PRM
simulations are run.
Generally you may not need to use this workflow as default setpoints will have previously been set
within the “System Schedules” dialogue. If all of your spaces have the same setpoint and operational
hours across all templates then there should be little you need to do here.
However, if different setpoints are being used in the building or where any unconditioned spaces
have OFF heating and cooling profiles, this should be set here in the template manager as this would
play an important role in the unmet load hours checks.
12
Other input data
Renewable energy systems
You can set up renewable energy systems for the proposed building.
Define tariffs data
Here you create advanced tariff data (as opposed to simple flat rate tariffs) which can then be
selected later in the Cost workflow. You don’t need to set tariff data prior to simulations. Tariff data
can be set at any point prior to generating PRM reports.
Electricity
For this training example, select the “Commercial Unrestricted” tariff. Choose the bills to be made
monthly. Select the Basic tariff type and for a standing monthly charge enter a monthly standing
charge of £50.
Select “Time of use Rates” and create a regime eg “Annual Tariff”. Check the “Weekday off-peak”,
“Weekday on-peak”, “Weekend off-peak” and “Weekend on-peak” checkboxes and enter the
appropriate times. Leave the others unchecked. Enter rates for the checked items.
The advanced tariffs shown and created here can be selected later in the Cost>Set Utility Tariff
Data>Detailed option>Set Advanced Rate, to show the energy cost improvement (if any) of the
proposed building against the baseline building.
Gas
Oil
Taxes/discount
13
Generate baseline
Generate the baseline model
This creates the baseline model and assigns all the baseline data you have created. This option will
only be enabled if you have completed and checked all the previous navigator steps. Note: if you
have already generated the baseline model and then make any changes to it, you must re-generate
the baseline model. The baseline model has no shading obstructions.
The glazing percentage for the baseline building is either 40%, or is the same percentage as the
proposed building, whichever is the least. Usually the glazing for the baseline building is the same as
the proposed building.
You can now view either the real or baseline buildings in the ModelIT view by selecting
View>Model>Real, or >PRM baseline.
You can also view either the proposed or baseline buildings in the ASHRAE 90.1 PRM view by
toggling the “proposed” or “baseline” option in the top toolbar.
14
Sizing runs
Room load calculations
Calculates room loads using the ASHRAE method, then calculates cooling airflow requirements for
the proposed and four baseline buildings, and creates the load spreadsheets
Access loads data spreadsheets
Once room load calculations have been done, you can then look at spreadsheets containing the
calculated data.
You have the option to amend the data in the spreadsheets for either the proposed or baseline
buildings. In the 62.1 OA tab you have the option to override the 62.1 vent rates with your own values
set in the VE>Room Data> System tab> System Outside Air Supply.
Assign room sizing data
Assigns the calculated flow rate data from the spreadsheets to the HVAC system. If required, you
could edit the flowrates in the HVAC network directly. You will now be able to see calculated flowrate
values in the HVAC network in green.
Note: Alternatively, you could copy and paste data from the above spreadsheets into a multiplex in
the proposed building HVAC network, or you could amend the spreadsheet and assign the room
sizing data again.
Note: If you change data for the baseline building within the baseline spreadsheets, you will have to
make the changes in the spreadsheets for each of the four baseline buildings.
15
System load calculations
This runs ASHRAE loads calcs again to calculate room coil loads and boiler/chiller sizes (taking into
account oversizing factors) using previously calculated airflow rates, and assigns the sized data to
the HVAC networks. You will now be able to see autosized values in the HVAC network in green. DX
units are automatically selected based on any coils using DX cooling.
Update fan and coil sizing data
Note: It is only necessary to do this if you have unchecked the “update Apache HVAC system sizes?”
option in the loads calculation dialogue.
Sizing reports
Allows you to review sizes and flow rates if you need to, for the proposed and four baseline bulidngs
below.
Proposed
Baseline 0
Baseline 90
Baseline 180
Baseline 270
16
Simulations
Proposed model simulation
If you need to, you can run a simulation just on the proposed building, as a test. Also, if you have
simulated the proposed and all four baseline buildings and you subsequently change the proposed
HVAC network, you only have to re-simulate the proposed building and not the baseline buildings.
0 deg. baseline model simulation
If you need to, you can run a simulation just on the 0 deg. baseline building, as a test.
Full PRM simulation
This runs the proposed and four baseline simulations.
Note: you must enable the ApacheHVAC link and you must select the proposed HVAC network .asp
file in the Apache simulation control dialogue.
Note: if you change the proposed HVAC networ
17
Cost
Set utility tariff data
The tariff data that you set is very important as it affects the cost savings in the PRM report.
Simple option
Set flat rate
This opens the Tariff Analysis overview dialogue in the Vista view. This shows the fuel costs of
the proposed and baseline buildings after the simulations have been performed.
For this training example the “Simple/Flat rate” option is chosen as well as the ASHRAE 90.1
“Energy dataset” option, and we will enter flat rates in cost per kWh for your selected currency.
The energy costs of the proposed and baseline buildings will be shown with the percentage
cost improvement of the proposed building over the baseline building.
Set currency
Set up cost analysis assignments
18
Detailed option
Set advanced rate
This opens the Tariff Analysis overview dialogue as above, but the “Advance/Variable rate”
option is chosen, where advanced rates are available. These advanced rates are the ones
from the Other Input Data>Define Tariffs Data workflow and include any that you created in
that workflow.
Set currency
Set site supply
Set utility suppliers
Set up cost analysis assignments
Set proposed results dataset
Check tariff assignments
Review cost analysis
Set Energy dataset option to 90.1
19
Results
Set parameters for ‘unmet load hour’ temperature tests.
In this training example we will use the default values. These values are tolerances (similar to a
bandwidth either side of the set-point).
The PRM allows a maximum of 300 unmet load hours in both the proposed and baseline buildings,
and allows a maximum of 50 hrs difference between the proposed and baseline building.
If you fail this test you could look at the room temperature and setpoints variables in Vista to help you
track down where the problems are.
20
BPRM report
User details
Enter details for the user, software used and the building.
Data for Tables 1.3 and 1.4
Here you enter features and plant descriptions for the proposed and baseline buildings. Correct
documentation is important for the BPRM report.
Cost Savings Summary -Table 1.8.2(b)
Energy Savings Summary -Table 1.8.2
Baseline Costs - Table 1.8.1(b)
Baseline Energy - Table 1.8.1
Full Report
This generates the full PRM report.
The Performance Rating Table (table 1.8.2) is one of the key tables in the PRM report and shows
energy end uses for the proposed and baseline buildings. The values for the baseline building are the
average of the values for the four baseline buildings. The table also shows the percentage savings
for each end use and the total savings for the whole building.
The most important table is the Energy Cost & Consumption by Energy Type (table 1.8.2 (b)). It
shows the energy cost and consumption by energy type for the proposed and baseline buildings, and
also shows the energy generated by any renewables used. The table summarises the percentage
energy and cost savings of the baseline building over the proposed building.
The tariff data that you previously set is very important as it affects the cost savings in the PRM
report.
Detailed simulation reports
These reports display a full breakdown of results (these are needed for submission).
Proposed
Baseline 0
Baseline 90
Baseline 180
Baseline 270
21
ASHRAE 62.1
These reports are normally not required (unless you are doing PRM analyses for ASHRAE 62.1
purposes only).
Proposed
Baseline 0
Baseline 90
Baseline 180
Baseline 270
Display selected reports
This concludes the PRM Navigator training session.