spring 2013 T R A N S P O R TAT I O N > DELIVERED The Shenandoah River Bridge’s signature shape is as pleasing to the bottom line as it is to the eye. > pg. 6 © Keith Philpott in this issue Mountain View Corridor By Doug Jackson, P.E., et al. Doug.Jackson@hdrinc.com 14 Using CMGC to Deliver More Project in Less Time © Keith Philpott Mountain View Corridor Shenandoah River Bridge Shenandoah River Bridge Design-Build By Jason Fuller, P.E., et al. Jason.Fuller@hdrinc.com 6 The Shenandoah River Bridge’s signature shape is as pleasing to the bottom line as it is to the eye. 8 Delta Design Delivers Big Savings for Shenandoah River Bridge Design-Build 10 Building the Delta: Erection Engineering for Shenandoah River Bridge [2] > transportation delivered | spring 2013 MAP-21 By David Vozzolo David.Vozzolo@hdrinc.com 22 Making Sense of the MAP- 21 Fixed Guideway Transit Capital Investment Program MAP-21 © Keith Philpott Northern Rail Extension Northern Rail Extension By Simeon, Brubaker, P.E Sim.Brubaker@hdrinc.com 20 © Keith Philpott Model for Risk Management in America’s Last Frontier: Alaska Railroad’s Northern Rail Extension Perspective Perspective By Michaella Wittmann, LEED Fellow, ENV SP, et al. Michaella.Wittmann@hdrinc.com 26 Envision™ Sustainability Infrastructure Rating System Addresses Design Challenges Departments 4 Director’s Letter | 5 News & Notes | 28 What Moves Us [3] direc tor’s Let ter Welcome to our first issue of Transportation Delivered for 2013. EDITORIAL BoARD The transportation market moves into 2013 with many of the same issues challenging owners and leaders around the world during the past several years—increasing capacity demands and funding uncertainties. HDR continues to respond to the challenges by helping our clients develop and implement programs that deliver high value results. Charlie O’Reilly Director of Transportation charles.oreilly@hdrinc.com While risk management has always been a key factor in successful project delivery, it is even more so now. If there ever is a time to use risk management models to support good project outcomes it is when a major investment is being made in projects with highly unique conditions and environment. The Alaska Railroad’s Northern Rail Extension opens a door to America’s last frontier, and to many uncertainties when building an 80-mile extension in a remote location with little access or market for services and materials. On page 20, read how we are working with Alaska Railroad, applying HDR’s cost risk assessment process to help manage budget and schedule. New delivery methods, not commonly used in transportation, are paving the way toward optimizing program and project results. The Mountain View Corridor story on page 14 proves how enhancing the CMGC delivery method with processes such as active risk management, open book estimates, and active contingency budget management allowed UDOT to go beyond cost control and, in this case, build almost double the length of the original project. There has been some good news on the funding front with the MAP-21 and Fixed Guideway Transit CIP. The new two-year funding commitment includes more than $21 billion dedicated to transit programs and affects many of the existing FTA major capital investment grant programs. On page 22, see how HDR’s David Vozzolo is taking the lead, advising our clients and helping the transit community navigate the changes and understand MAP-21 criteria and measures. HDR continues to focus on design innovation as a path to delivering efficient designs to serve tomorrow’s transportation needs. On page 6, the Shenandoah River Bridge is a great example of our people working with owners and contractors to develop elegant and effective solutions. The last feature article in this edition, on page 26, introduces you to the Envision™ Sustainable Infrastructure Rating System. While LEED established sustainability standards for buildings or “vertical infrastructure,” there has not been an equivalent standard for measuring sustainability performance in our horizontal infrastructure. Envision was developed to help project teams improve the performance and viability of infrastructure through the application of more sustainable technologies and methodologies. HDR is a charter member of the Institute for Sustainable Infrastructure, which administers Envision, and is working with the organization to advance the program’s use. I hope you enjoy reading Transportation Delivered. If you have any questions on the information in this issue reach out and let us know. Our experts will be glad to talk with you about their work. Charlie O’Reilly, Director of Transportation [4] Suzanne Putnam Planning & Communications Manager suzanne.putnam@hdrinc.com Ken Wall Editor ken.wall@hdrinc.com Transportation Delivered is a biannual publication produced by HDR, showcasing projects that increase capacity, enhance mobility and improve safety of roadways, waterways, airways and railways. Direct subscription inquiries and address changes to ken.wall@hdrinc.com. To view this publication electronically, go to: www.hdrinc.com/transportationdelivered Transportation Delivered is offset printed on Utopia Two Xtra Green 80# Dull text, which is an FSC-certified paper manufactured with electricity in the form of renewable energy (wind, hydro and biogas) and includes a minimum of 30% post-consumer recovered fiber. ABOUT HDR HDR is a global employee-owned firm providing architecture, engineering, consulting, construction and related services through our various operating companies. Our more than 7,800 professionals are committed to helping clients manage complex projects and make sound decisions. To learn more about HDR’s Transportation program, visit us at www.hdrinc.com/transportation Cover Photo: © Keith Philpott © 2013 HDR Engineering, Inc. News & Notes > Tappan Zee Bridge | Westchester and Rockland Counties, NY Projects HDR Lead Designer for New Tappan Zee Bridge The $3.142 billion design-build contract for the Tappan Zee Hudson River Crossing between Westchester and Rockland Counties in New York was approved in late December by the New York State Thruway Authority board of directors and awarded to the Tappan Zee Constructors consortium Jan. 18. HDR is lead engineer for the consortium, which includes Fluor Enterprises, American Bridge Company, Granite Construction Northeast and Traylor Bros. The project requirements include strict environmental performance commitments to protect the Hudson River estuary, including noise, vibration and air quality monitoring. The new facility will help alleviate daily traffic jams and improve safety on the bridge, which handles more than 138,000 vehicles every day. Key features of the new bridge will include: • Twin three-mile structures with 1,200-foot cable stayed main span bridges carrying eight general traffic lanes, plus emergency lanes and extra-wide shoulders for immediate express bus service when opened • A new toll plaza with at least three highway speed E-ZPass lanes and a dedicated bicycle and pedestrian path on the northern span • Safe scenic overlooks, with anti-climb fencing and security cameras to be monitored 24 hours a day • Strength and capacity provisions to accommodate various mass transit modes AWARDS Rosca Honored as One of 2013 New Faces of Engineering HDR’s Gheorghe Rosca, Jr., P.E., has been named one of the 2013 New Faces of Engineering by the American Council of Engineering Companies. Members from participating engineering societies nominate colleagues 30 years or younger for consideration. Rosca, a rail section manager in HDR’s Riverside, Calif., office, has worked on more than 10 bridge replacements and four double-tracking projects with construction values of $30 to $100 million. He is the client manager for the North County Transit District, managing a $12 million on-call contract. He recently was inducted as president of the Railway Association of Southern California. CSX Honors HDR, Keller with Outstanding Performance Award CSX Transportation Inc.’s environmental department recently honored HDR and Kevin Keller, vice president and a client manager in the Freight Rail Market Sector, with the Outstanding Performance Award for 2012. The award is given by CSX each year to a consultant who has provided exemplary service to its environmental program. CSX recognized HDR and Keller for work on the JAXPORT Intermodal Container Transfer Facility in Jacksonville, Fla. HDR assisted with a successful Transportation Investment Generating Economic Recovery (TIGER) III grant application for the project, resulting in an award of $10 million. PEOPLE Patrick R. Hickox, P.E., has joined HDR as Bridges & Structures director. Hickox has more than 24 years of experience in design, construction and asset maintenance of complex, long-span bridges with a specialty in cable stayed bridges. His experience includes projects delivered through traditional means, along with extensive alternative delivery experience. A registered professional engineer in 10 states, Hickox is a member of the American Society of Civil Engineers and American Segmental Bridge Institute. Ted Daly has joined HDR in the Newark, N.J., office as Ports & Harbors section leader. He is responsible for managing and growing HDR’s Ports & Harbors practice in the Northeast and supporting international projects. Daly has 23 years of experience in design and development of major coastal, ports, bulk material and container terminals, as well as marine and facility operations and engineering projects. He recently spent time in Bogota, Colombia, where he led a financial feasibility study for the development of a $7 billion dollar pit-to-port coal project, and a feasibility study for the Panama Canal Authority for a new container terminal in the Port of Balboa at Corozal. [5] [6] © Keith Philpott Shenandoah River Bridge Design-Build "Almost heaven, West Virginia Blue Ridge Mountains, Shenandoah River Life is old there, older than the trees Younger than the mountains, blowing like a breeze" The opening verse to John Denver’s “Take Me Home, Country Roads” hints at the natural beauty of the Shenandoah River Valley in West Virginia’s eastern panhandle. Just an hour’s drive from Washington, D.C., the valley boasts a blend of wildlife habitat, farmland and quaint, historic towns. Not surprisingly, the region has evolved into a desirable getaway from the frenzy of urban life. To accommodate increasing travel demands, the West Virginia Department of Highways initiated a project to improve West Virginia 9, including a new bridge across the Shenandoah River. HDR developed a delta frame design that delivered significant savings compared to proposals for more traditional designs. The resulting signature shape of the Shenandoah River Bridge is as pleasing to the bottom line as it is to the eye. [7] D elta D esi g n D elivers BIG SAVINGS for Shenandoah River Bridge Design-Build By Jason A. Fuller, P.E.; and Matthew A. Bunner, P.E. The unique shape of the new delta-frame Shenandoah River Bridge strikes a pose worthy of its picturesque West Virginia surroundings. Equally attractive is the $8 million the West Virginia Division of Highways (WVDOH) saved thanks to a creative design solution. The new Shenandoah River Bridge is part of a project to improve West Virginia 9 in historic and scenic Jefferson County into a fourlane divided highway. Just 58 miles from the Washington, D.C. Beltway, and less than 40 miles from Dulles International Airport, Jefferson County is a prime getaway destination for people living in the Washington and Baltimore metro areas. In addition to being the most visited county in the state, Jefferson County is seeing significant commercial and residential growth. The highest-ranked priority in the West Virginia eastern panhandle transportation improvement plan was a five-mile section of WV9 between Charles Town, W.V., and the Virginia state line, which includes a crossing of the Shenandoah River valley. The valley is both wide and deep, creating a proposed profile grade nearly 200 feet above the river and an overall bridge length of almost 1,800 feet. A bridge made up of a main unit with a three-span continuous deck truss (400 feet – 600 feet – 400 feet) with short plate-girder approach units initially was advanced through the design process. During review of the proposed design it became apparent that other alternatives might be more cost-effective. The fracturecritical nature of the proposed truss presented additional cause to consider making a design change. The August 2007 collapse of the I-35W deck truss bridge in Minnesota occurred relatively late in the Shenandoah truss design process, and was followed by an increased scrutiny within the industry of the gusset plates used in truss construction. In early October 2009, WVDOH changed the project from a traditional design-bid-build process to a design-build letting and invited contractors to bid either the as-designed truss or develop [8] and bid a different structure type. Any proposed alternatives were required to accommodate several design limitations, primarily aimed at compliance with existing environmental commitments and previously established parameters for alignment (horizontal and vertical) and substructure location. As a result, the main span still needed to be approximately 600 feet. Following a December 2009 letting, WVDOH selected Trumbull Corporation as the design-build contractor, with HDR serving as Trumbull’s design consultant. The project team evaluated both concrete and steel alternatives before ultimately determining that a steel delta frame design met all of the owner’s criteria while providing significant savings over more traditional bridge types. The Delta Difference HDR and Trumbull performed preliminary design on both concrete and steel options, but the anticipated construction costs for concrete were much greater than for steel. There was enough of a difference that it became obvious that steel would be more economical, so the preliminary design of the concrete alternative was set aside. For the steel evaluation, it was understood that deck configuration and cost would be similar for all of the bridge types. The differences in cost, therefore, would be driven by the amount of steel, unit cost of fabrication and erection cost. Based on a database of past projects, the team believed that a steel plate girder bridge with span lengths similar to the originally proposed truss (400 feet – 600 feet – 400 feet) would result in approximately 145 pounds per square foot (PSF) of structural steel, or approximately 50 percent more steel than the truss. From a superstructure perspective, the overall length of the main unit would have been ideal for a traditional five-span steel plate girder unit with span lengths of 250 feet – 300 feet – 300 feet – 300 feet – 250 feet. Such a unit would likely only result in approximately 60 PSF of structural steel; however, the design constraints did not allow for additional piers. While investigating the possible plate-girder arrangements, the team determined that the ideal five-span plate girder option actually could be achieved if supports for the girders were provided 150 feet to either side of the existing river pier locations. The supports, envisioned to be steel slant legs at each girder line, could be inclined and meet at the existing river pier locations. With 200 feet vertically from the profile grade to the river, the supports could be inclined as much as 45 degrees and still remain above the required river flood elevation (there was no requirement for navigational clearance). This configuration of steel rigid frame is known as a delta frame, due to its unique triangular appearance. The delta frame design produced 110 PSF of structural steel, which was slightly above the original truss weight, but facilitated significant fabrication cost savings. This fabrication cost savings, along with other costeffective options, offered a savings of about $8 million compared to the other bidders. The Final Design The steel superstructure of the new Shenandoah River Bridge consists of a five-girder, four-substringer system supported by five lines of delta legs—one for each girder. Each individual leg covers a vertical distance of 150 feet and a horizontal distance of 150 feet, creating a girder span of 300 feet between the delta legs. The spans between the abutments and piers are 400 feet – 600 feet – 400 feet. Relatively few rigid steel frames have been constructed over the past several decades. Both slant-leg frames and, to a lesser degree, delta frames were used more extensively during the 1960s and 1970s. The singular nature of the bridge design meant there were no directly applicable design codes for portions of the structure, so the team established tailored design checks. Designers developed a finite element analysis of the erection procedure so each of the 207 steps could be examined individually, and so the temporary works and permanent steel framing could be assessed as a system to provide stability to the structure until completed. The detailed © Keith Philpott >> The delta frame presented a more cost-effective alternative than the originally proposed design while complying with existing environmental commitments and alignment parameters. erection plan had to account for the nearly 200-foot height of the bridge, the unique procedures for erecting the delta legs, tall temporary works, a small site footprint, fluctuating river levels and other challenging site conditions. The final plans even included a future re-decking scheme, which was analyzed to ensure its viability. After consideration of changes to the dead load as a result of removing portions of the deck, the re-decking scheme involves removing and replacing an outside third of the deck, replacing the other outside third, then the middle third. Traffic lanes will be restricted and temporary barriers used. The Finished Product The new Shenandoah River Bridge is in aesthetic harmony with its surroundings. The project exists within a unique ecosystem where the scenic Shenandoah River is bounded by steeply rising wooded mountains, providing picturesque locations for canoeing, rafting, fishing and wildlife viewing. For the bridge to gracefully integrate into these surroundings, it must complement rather than overpower them. The shallow plate-girder superstructure is only 10 feet deep, which, when compared to truss options (which varied from 40 to 80 feet deep) and other options such as segmental concrete (which would be nearly 35 feet deep near the piers), is much less obtrusive. The triangular shape of the delta frame, one of the most basic structural forms, yields a sense of stability and strength, of simplicity and functionality. The earth-tone reddish-brown color of the weathering steel blends with the natural colors of the valley and is bounded and complemented by the natural concrete color of the deck and barriers as well as the piers and abutments. The Shenandoah River Bridge opened in November 2012 and now ranks as one of the longest delta frame bridges ever constructed. -> For more information, contact Jason.Fuller@hdrinc.com. [9] © Keith Philpott Building the D el t a >> As construction progressed, the symmetry of the Shenandoah River Bridge allowed the crew to apply knowledge gained in earlier stages and continuously improve their performance. The Shenandoah River Bridge soars nearly 200 feet above a wide river valley in West Virginia’s eastern panhandle. It features a steel superstructure consisting of a five-girder, foursubstringer system supported by five lines of delta legs—one for each girder. The bridge is one of the longest delta frames ever constructed, with 300-foot spans between the legs and 600 feet between the main piers. The Shenandoah River Bridge’s distinctive design demanded unique procedures for erecting the legs and tall temporary works and to accommodate the small site footprint, fluctuating river levels and other challenging site conditions. As part of our services as lead designer for the project, HDR provided erection engineering services, including step-by-step analysis of the structure and design of the temporary support system. [10] Step-by-Step Modeling and analysis of the staged bridge erection developed as an extension of the final design of the completed structure. The team modified the non-composite detailed model used for analyzing the completed structure steel weight to perform the staged erection analysis. Falsework towers, tensioned stays and temporary supports were added to the model. All elements of the modular truss falsework tower sections were included in the model as beam elements to facilitate design of the tower elements for all global and local effects. Stays were modeled as tensiononly cable elements and springs were used to model the connection (jacks) of cross girders to structural steel girders or legs. The vertical connection of the cross girder to structural steel was modeled with compression-only springs. Erection Engineering for Shenandoah River Bridge The project team implemented a geometric nonlinear analysis to evaluate the structure, including falsework, piece-by-piece with load tracking. The structure was modeled in 77 stages. A stage was considered to be the amount of work that could be completed during a shift or between any appreciable wind or thermal event. Each stage was separated into individual steps. A new step was specified each time the lifting crane was released and a new piece was placed. A total of 207 individual steps were defined. Geometry and Loads The nodal geometry of the structure was defined based on its final completed position. Stay tensioning forces were iterated to determine the load necessary to place leg tips in their proper locations. As new pieces were added, the nodal locations were adjusted to account for the location and rotation of the previous piece to which they were being bolted. The dead load in the staged erection analysis was similar to the completed structure steel dead load. A detail weight of 7 percent was used, and the geometric nonlinear analysis provided direct results for first and second order effects. The team applied a 70 mph wind load to the structure at the end of each stage, using three attack angles per stage to envelope the behavior. Within a stage (step-to-step), the wind results were reduced to 30 mph to simulate the maximum forces during a work shift. The analysis included a total of 231 wind cases. Thermal loads were tested by applying a thermal change of 100° F to the structure at the end of each stage to capture thermal effects from stage to stage. Thermal effects were reduced to 50° F within a stage to simulate the maximum forces during a work shift. A total of 77 thermal cases were applied to the structure. Checking the Design As part of the erection engineering process, the team checked the adequacy of the permanent structural steel (girders, legs, stringers, cross frames, leg diaphragms, leg lateral bracing and bearings) and the temporary works (towers, cross girders, stays and foundations) for all stages of steel erection. The team used construction load factors based on AASHTO guidelines to check the elements. The erection procedure provided in the construction plans was specified to match the modeling assumptions of the analysis. Temporary elements were designed and detailed to match the modeling assumptions. By Jason Fuller, P.E.; Nicholas Cervo, P.E.; Anthony Ream, P.E.; and Matthew Bunner, P.E. Analyzing 207 dead load cases, 231 wind load cases and 77 thermal cases acting on 17,634 members, 17,805 plates and 141 springs produces a large amount of data. It was crucial to envelop the results wherever possible to reduce design and data extraction time. Element capacities based on maximum unbraced length during construction were first checked against maximum factored loads based on non-concurrent dead, wind and live loads from any point during construction. As mentioned previously, wind loads were based on 70 mph and thermal loads were based on ±100° F. If the non-concurrent loads exceeded the member capacity based on maximum unbraced length, concurrent loads occurring during the maximum unbraced stages were determined and used. If loads still exceeded capacity, a 30 mph wind and ±50° F thermal change was used. As a result, wind speeds and thermal changes during the erection of these elements were restricted on the plans furnished to the steel erector. Very few elements required a wind or thermal restriction from stage to stage. [ The Shenandoah River Bridge’s distinctive design demanded unique procedures for erecting the legs and tall temporary works and to accommodate the small site footprint, fluctuating river levels and other challenging site conditions. ] A completed delta frame (two legs and girder between) for one or more girder lines provided a significant amount of bracing to the temporary towers. After closing a delta frame, the structural steel also transferred a large portion of dead, wind and thermal loads during construction to the supports. Even prior to the formation of a delta, attaching multiple lower leg pieces to the falsework cross girder and lower knuckle (and river pier) provided significant rigidity to the temporary structural system. The participation of the structural steel as a temporary support helped reduce the size of temporary works and created a stable, stiff system prior to completion. [11] Building the D el t a HDR designed the erection process for the girders using similar tools, procedures and code provisions as the completed final design. The team considered moments, axial loads, lateral bending and shears, as well as large unbraced lengths due to partial installation of cross frames. We gave particular attention to stages with single or dual girder systems. Single girders, where erected, were fixed to supports or temporary falsework cross girders using attached cross frames. The two girder pieces directly atop the river piers were spliced on the ground and lifted into place for a total length of 180 feet and a distance between supports of 150 feet. Weight and space restrictions prevented a dual girder pick; therefore, the large unsupported length of the single girder required a top flange stiffening truss to provide adequate bending resistance. The single girder was analyzed with a geometric nonlinear buckling analysis for the unbraced and stiffened top flange to determine buckling safety factors. The team checked dual girders with every other cross frame attached for global buckling of the two-girder system. The strength and stiffness of the attached cross frames were checked for their adequacy to prevent global buckling. Special attention was given to the upper leg pieces when installed as cantilevers. Once tied to opposing legs using diagonal stays, these 130-foot-long cantilevers were able to withstand 70 mph winds without additional bracing. Putting the Plan into Action Construction of the steel structure began with erecting the portion of the steel structure at the second river pier up to the second abutment, forming one complete side of the bridge’s framing stabilized by the abutment. The crew then constructed three lines of deltas at the first river pier. Once complete, the middle pieces of the center span for the three lines were erected, connecting the two river pier delta frames. Following this step, the other two delta lines were erected at the first river pier and attached to the second half of the structure. The final step of the steel erection was placing the girders back to the beginning of the bridge (see Figure 1, Construction Sequencing). Executing the plan required falsework towers placed at six locations along the structure—75 feet on either side of each river pier (towers 2, 3, 4 and 5) and approximately 100 feet from each end support (towers 1 and 6). Each falsework [12] > Figure 1: Construction Sequencing tower included two legs placed 28.5 feet on either side of the longitudinal centerline of the bridge, directly in the middle of the exterior girder/leg bays. The two tower legs were connected with transverse cross girders that supported the legs or girders. The tower legs comprised modular truss frames bolted together to obtain the correct height. Tensioned stay cables were used to provide support, stability and geometry during the complex process of erecting the delta legs. The structural steel legs were constructed in three pieces. The first piece was a lower knuckle that sits on the pier, the second was a lower leg section bolted to the knuckle and resting on a lower cross girder on the falsework tower, and the final piece was the upper leg, which was bolted to the lower piece and cantilevered. An upper knuckle piece was then installed to connect the cantilever leg piece to the girder. After opposing lower leg pieces were bolted to the lower knuckle, a horizontal stay was placed between the lower leg tips and tensioned. This brought the lower leg tips to their correct cambered position and reduced the reaction loads acting on the temporary falsework cross girder. Once an upper leg piece was bolted to the lower leg, a diagonal stay was attached to the tip of the upper leg piece and the top of the opposing lower leg at the elevation of the horizontal stay. This brought the upper leg tip to its correct cambered position for installation of the upper knuckle piece. The diagonal stay also reduced major axis bending forces in the upper leg due to dead and wind loads. When all five lines of girder delta frames had been constructed at a pier and braced off the adjacent abutment, the falsework towers at the river pier were removed. Stays were removed after the towers to prevent leg deflections from applying loads to the falsework towers. The keeper system connecting the structural steel girders or legs to the falsework cross girders was detailed to allow © Keith Philpott >> Construction of the Shenandoah River Bridge was completed in November 2012. for jacking and shimming. Jacking and shimming allowed for adjustment of girder and leg elevations. Girders could be vertically adjusted. Also, by coordinating jacking of opposing legs on either side of a river pier, the delta frame could be rotated about the fixed bearings to adjust tip elevation of the girders both vertically and longitudinally. These adjustments would help facilitate installation of girder pieces. The majority of the erection was performed using two 300ton cranes with over 300 feet of boom. Occasionally, the crew brought in a 500-ton hydraulic truck crane to assist with picks that were difficult to make from the valley floor. The additional crane(s) were used for the picks near the ends of the spans at the tops of the valley. To accommodate the use of the cranes, pile-supported crane pads had to be installed and used at Abutment 2. Between the abutment and a conspan structure, the geometry would not permit the cranes to sit directly on bedrock. To transfer load directly, concrete footings were located at the top of the fill directly under the outriggers of the crane. The concrete footings were constructed on H-piles, which transferred the load directly into the bedrock, bypassing any conveyance of load to the adjacent substructure units. Symmetry is Good Construction success often is defined by production rates. Because this structure is symmetrical about both the longitudinal centerline and the transverse centerline, it comprises four similar quadrants. This proved to be an advantage as construction progressed. With each section that went up, including temporary works, the crew gained experience that sped up the process for subsequent sections. Construction of the Shenandoah River Bridge began in late 2010, with steel erection from September 2011 to August 2012, and was completed in November 2012. -> For more information, contact Jason.Fuller@hdrinc.com. [13] M ou n ta i n V i ew C o r r i do r Using CMGC to Deliver more Project in less Time By Doug Jackson, P.E.; and Khalid Bekka, Ph.D. The Mountain View Corridor is a planned freeway, transit and trail system in western Salt Lake County and northwestern Utah County, serving 13 municipalities. The Utah Department of Transportation (UDOT) is implementing Mountain View Corridor in phases, building infrastructure for initial needs and gradually expanding systems over time. As program manager, HDR recently supported UDOT in completing the first of using the Construction Manager General Contractor (CMGC) delivery method. [14] © Keith Philpott many projects that will make up the Mountain View Corridor [15] To meet the demands and challenges of UDOT’s largest CMGC project to date, the project team modified its standard CMGC format to include an innovative and proactive risk management process, active contingency budget management, open-book cost estimating and a structured iterative preconstruction cost development model. In addition to adapting the CMGC process, the project team established four guiding principles that helped set the stage for successful project delivery: transparency, collaboration, solution-oriented decision making and flexibility. From this foundation, the Mountain View Corridor team generated remarkable results, including: • Extending the project limit from 9 miles to 15 • Reducing the overall estimated construction cost from $346 million to $249 million • Mitigating risk and reallocating $43 million in contingency budget to purchase right-of-way and build more of the project • Shaving a year from the construction schedule by designing, acquiring right-of-way, and building simultaneously with no delays to the critical path > Figure 1: Project Limit Extension 15 9 miles miles Why CMGC? UDOT chose the CMGC delivery method due to a number of challenges facing the Mountain View Corridor program. One key factor was UDOT’s plan to simultaneously deliver two large-scale projects in the Salt Lake Valley. The $1.2 billion I-15 Core designbuild project was scheduled to be bid and constructed at the same time as Mountain View Corridor. If both > Figure 2: Project Map with Highlighted Areas Representing Completed Construction were design-build projects, the concurrent proposal processes between Mountain View Corridor and I-15 Core would have significantly strained the consulting and contracting industries for resources, especially in marketing, design and construction during proposal preparation and preliminary engineering needed to estimate the project cost. Additionally, design-build proposal preparation requires significant private investment, where as CMGC requires significantly less private investment during the procurement phase. Another consideration was the need to conduct major utility relocations. Site conditions were complex because two major interstate power and gas transmission facilities ran longitudinally along and through the planned freeway alignment. None of [16] > Figure 3: Reducing Overall Estimated Construction Cost > Figure 4: Mitigating Risk and Reallocating Contingency Budget $100M $30M (approx.) Reduction Build More Project Total Reallocated to Project Construction Cost $346M Original $43M $13M $249M TMP Purchase Right-of-Way PRECONSTRUCTION PHASE the conflicts were resolved prior to bringing the contractor on board. With CMGC, the owner could work with the major utility companies to establish master agreements to allow the project to move forward and eventually address individual conflicts. This type of utility risk is very difficult to shift to a contractor. Similar to utilities, right-of-way acquisition was not completed prior to bidding. Approximately 275 individual parcels were in conflict with the freeway alignment at an estimated cost of about $212 million. Design progression and input from third parties created additional challenges throughout the design process to locate drainage and utility facilities with minimal right-of-way impact. The CMGC approach allowed the process to begin and provided a mechanism for the rightof-way team to help optimize the construction schedule and minimize potential delays. Ultimately, nearly 150 agreements were required to handle approximately 500 individual conflicts throughout the project. A total of 29 cities, service districts, utility companies and third parties owned or had interests within or adjacent to the corridor—all with varying levels of development. Because this was a Greenfield project, UDOT did not have ownership rights that are typical with most reconstruction projects. This meant that most of the public and private utilities had prior rights that UDOT had to acquire. Thus, UDOT had to conduct extensive negotiations with landowners and utility companies. Again, CMGC benefited this effort as it provided a much more flexible project delivery approach. CONSTRUCTION PHASE Proof is in the Returns Transparency and Partnership—During the selection process, a key criterion for UDOT was determining whether the contractor would willingly participate in a transparent and collaborative process of open-book estimating and risk analysis. In the submittal, the contractor was required to demonstrate to UDOT its approach to estimating the project and how it would produce and share its estimate directly with UDOT. Targeted Maximum Price—The primary objective to be achieved through the preconstruction phase of a CMGCdelivered project is a mutually agreed-upon construction cost. For Mountain View Corridor, UDOT chose to use a targeted maximum price (TMP), rather than a guaranteed maximum price, to provide maximum opportunity to build as much of the roadway as it could afford. However, while the final cost of construction is important, the process followed by the project team to reach this goal is even more important. Each step built confidence that the TMP was not simply a representation of the lowest cost, but that it provided the best project value. The approach taken for Mountain View Corridor used the following core elements: 1) open-book estimation; 2) risk analysis; and 3) project optimization (design and construction optimization). These elements complemented each other in successful implementation of the CMGC process. Departing from a conventional linear approach, the management team recognized that for a large-scale, complex project, an iterative process provided the team with an opportunity to work toward both an agreeable TMP and the best project value. [17] > Figure 5: Cost-Reduction Measures $25M $12M $6M $9.5M design analysis and construction innovation utility relocations schedule compression elimination of a rail bridge Preconstruction Cost Reduction—Cost reduction is perhaps the most significant achievement attained through the CMGC process on Mountain View Corridor. The estimated risk-adjusted construction cost was reduced throughout the project by approximately $100 million, or roughly one-third of the initial construction estimate. This reduction was achieved over a 10-month period using risk analysis in an iterative process. At each meeting, the team exchanged ideas on how to avoid or mitigate identified risks. The following items represent some of the largest cost-reduction measures: • $25 million saved through design analysis and construction innovation (DART process) • $12 million cost reduction in utility relocations • $6 million saved in indirect cost attributable to schedule compression • $9.5 million saved attributable to elimination of a rail bridge Contingency Funds Reduction and Reinvestment — The amount of owner-controlled program contingency decreased dramatically throughout the project’s construction phase— dropping 16 percent from year one to year two (from $73 million to $61 million) and an additional 52 percent from year two to year three (from $61 million to $29 million). Ultimately, $43 million in contingency was reinvested in expanding the corridor. One third of the funds were used to purchase additional right-of-way, and the other two-thirds were used to build more roadway. Cost Growth/Change Management — On almost all projects today, especially high-profile infrastructure projects, a key measurement of project success is cost growth and change [18] management. How much additional money was required to cover the cost of quantity overruns, changed conditions, incomplete or inaccurate plans, etc.? This is especially true for Mountain View Corridor, given the amount of time and effort put into cost risk analysis, risk mitigation and active risk management conducted throughout the project. At the end of the preconstruction phase, the project team set a TMP for construction of $249 million. Now, three years later, with construction complete and the roadway open to the traveling public, the final projected construction cost is approximately $235 million. The original construction contract amount was $220 million. The difference between the original contract amount and the risk-based TMP of $246 million accounted for high probability/ low-cost impact construction risk, quantity growth attributed to bidding plans at 60 percent design versus final design plans, and scope modifications required to expand the project limits. With all of these items accounted for today, the contract grew by 6.6 percent, but is still 6 percent under the agreed-upon TMP for construction. Schedule Control — Mountain View Corridor was delivered on schedule, with some segments of the roadway opened early. One section of the roadway was opened six months early to provide congestion relief in one of the local communities where roadway construction was being completed on an arterial street crossing the corridor. The entire CMGC process was completed in less than four years—from UDOT obtaining funding for the project to the roadway opening to the traveling public. Along the way, the team notched a number of significant accomplishments, including: • Collaborative Preconstruction Phase — Owner, program manager, designer, and contractor worked collaboratively to plan, design, estimate, mitigate risk, and reach price agreement (TMP) in 10 months. • Accelerated Right-of-way Acquisition — With 418 parcels purchased and 140 residential relocations, no construction delays resulted. • Efficient Utility Relocation — With 481 utility conflicts, 165 utility agreements, 28 utility companies, and a $47 million relocation cost, no construction delays resulted. • Fast-tracked Construction — With a 36-month construction schedule that involved 5.5 million cubic yards of earthwork, 313,000 tons of asphalt, 294,000 square yards of concrete paving, 10 bridges constructed, 163,000 square feet of retaining wall, and 15 miles of new roadway, no construction delays resulted. Photo courtesy of Copper Hills Constructors >> The Mountain View Corridor CMGC project opened 15 miles of new roadway in December. Delivering Value through Partnership and Flexibility Given the differences—and the clear trade-offs—among delivery methods, it is critical that the selection of any given method be made carefully with consideration given to project characteristics and the owner’s priorities. Looking beyond the delivery method, processes and techniques such as risk analysis and open-book estimation process also are increasingly recognized as proven factors to success. For Mountain View Corridor, the CMGC delivery method provided an ideal framework to implement a number of innovative and proactive techniques. Furthermore, CMGC’s progressive and collaborative features provided the balance between realizing the contractor’s innovation and the owner maintaining control over the process. As the Mountain View Corridor experience shows, when the CMGC delivery method is enhanced with processes such as active risk management, with a set of workshops and openbook estimates to promote transparency, the outcomes are robust. In fact, the application of CMGC showcased how a delivery method can be customized to meet the owner’s goals. The modifications made for Mountain View Corridor provided greater control and flexibility in contracting and decision making, integration of risk analysis and management methods, risk allocation opportunities, and—above all— transparency and credibility in the cost and schedule estimation process. While CMGC is not appropriate for all projects, its ability to manage and deliver high-risk projects while minimizing conflicts and building partnerships proved an exceptional fit for Mountain View Corridor. -> For more information, contact Doug.Jackson@hdrinc.com. [19] A Model for Risk Management in America’s Last Frontier © Roman Krochuk | Dreamstime.com Alaska Railroad’s Conducting major civil works in the interior of Alaska presents unique challenges beyond the obvious extreme weather conditions. For example, resources that might be taken for granted in most project locations, such as access to high speed internet for file sharing and basic communication, aren’t available here. More significantly, the cost and availability of materials and fuel are heavily impacted when working in such a remote environment. To be successful, projects such as the Northern Rail Extension currently being constructed in the Fairbanks region require a very detailed approach, particularly with regard to risk management. The program manager, owner, contractor, designers and the rest of the team must work together to identify and understand the project risks and to develop mitigation measures to address them. Northern Rail Extension The Alaska Railroad Corporation (ARRC) initiated the Northern Rail Extension program to construct 80 miles of new track between Fairbanks and Delta Junction. Completing this regionally significant project will provide freight and potentially passenger rail service to these communities and allow improved access to Fort Greely and other military training facilities in the area. Construction of Northern Rail Extension Phase 1 (NRE1), the first of four planned phases, includes a bridge, approach road and levee associated with the alignment’s crossing of the Tanana River near Salcha. The project is being delivered using the construction manager general contractor (CMGC) model. [20] Risk Management As program manager for NRE1, HDR is responsible for developing the risk management approach. The project team implemented a cost risk assessment (CRA) process throughout the project to identify and quantify risks related to both cost and scope. A vital component of the CRA process is a series of risk workshops held at key stages during the design. Representatives from ARRC, the program manager, the CMGC and the designers attend the workshops and collaborate to reach consensus on the outlook of specific risks. The workshops cover topics on the design status, materials sourcing and pricing, management and contracting issues. These sessions produced a consensus-based determination on the probability of occurrence for cost and schedule risks, and the impact, if the risk occurred. The discussions are documented in a risk register. Based on the project’s progress, the workshops have incorporated refinements to the bridge and levee designs, developing more detail for the construction costs and schedules, and obtaining pricing for subcontracting and materials. Many of the risks that were identified early in the process have been incorporated into the baseline cost and schedule as either contractor-controlled or owner-controlled risks. At the close of 2012, the remaining uncertainties entail pricing of materials (steel and riprap) from alternative sources, schedule for obtaining permits (CLOMR and USACE 404), and site and weather conditions that could impact construction. As mentioned Northern Rail Extension By Simeon Brubaker, P.E. >> Working in a remote environment such as interior Alaska requires a detailed approach, particularly with regard to risk management. previously, constructing big projects in the middle of Alaska creates considerable challenges with regard to the cost and availability of materials and fuel. At the mid-point of the contract, fuel and steel escalation costs remain negative in the budget. Part of the CRA process focuses on minimizing these cost risks. The CMGC considered structural steel fabrication domestically and in Asia, ultimately selecting a firm in China. To address the risk associated with fabricating overseas, HDR worked with a subconsultant to provide hands-on reviews of the fabrication yard, detailed and comprehensive reviews of quality control measures, documentation, testing procedures, and project submittals and requests for information. Members of the project team made numerous trips to China to monitor the fabrication process and help ensure that the quality control processes were followed by the fabricator and that the final product was constructed in conformance with the contract documents. Another risk identified early in the design phase involves the foundations for the Tanana River crossing. There was little historical information available for driving large-diameter piling in the unconsolidated sand and gravel formations expected on the project site. HDR facilitated numerous reviews and design revisions with the client, the engineer of record and the geotechnical consultant through both the pre-construction phase and during construction of the project. At this time, nearly 50 percent of the piling has been driven with no major claims from the CMGC, and the designers have confidence in pile capacities for the finished product. More Keys to Success Truly mitigating risk is made possible by paying extra attention to all the little things that can impact a project. HDR maintains a crew of qualified engineers and technicians to administer this contract, with someone available on-site 24/7 (regardless of the aforementioned extreme weather conditions). We’ve retained the services of local surveyors and materials testing labs to work as sub-consultants, minimizing cost impacts to the client and providing more intimate knowledge of the project area. All project information, including correspondence to all parties involved in the project, daily work reports, materials testing data, submittals and correspondence from the CMGC, are managed using a web-based database. This provides the client, designers, CMGC and other involved parties to access and manage project documentation in real time, eliminating much duplication and inconvenience while minimizing the potential for error. Construction of NRE1 began in July 2011 and is scheduled for completion by July 2014. Permitting and other pre-construction work has been done for subsequent phases in preparation for future funding availability. -> For more information, contact Sim.Brubaker@hdrinc.com. [21] Making Sense of the [22] MAP- 21 Fixed Guideway Transit Capital Investment Program © Keith Philpott By David Vozzolo Moving Ahead for Progress in the 21st Century (MAP-21) provides $105 billion in surface transportation funding to be administered by the U.S. Department of Transportation (USDOT) through September 30, 2014. MAP-21 represents a two-year federal funding commitment, including more than $21 billion dedicated to transit programs. This new legislation affects many of the existing Federal Transit Administration (FTA) major capital investment grant programs, which raises questions for owner/operators, consultants and others in the transit industry. HDR has developed our own interim guidance and counsel to help navigate changes to FTA’s funding mechanisms, including New Starts and Small Starts and the introduction of the Core Capacity Improvements program. This article highlights some of these modifications. More detailed materials are available online at www.hdrinc.com/map-21, and will be updated as appropriate. [23] The Programs within the Program MAP-21 maintains the basic eligibility requirements and structure of the New Starts and Small Starts programs, and introduces some changes on how bus rapid transit (BRT) projects are defined in each program. MAP-21 also introduces a new eligible program for Core Capacity improvement projects. However, funding for the major capital investment program has not been increased. New Starts, also known as Fixed Guideway Capital Investment Grants, continue to be defined as a “minimum operable segment or an extension to an existing fixed guideway transit system.” New Starts includes fixed guideway BRT projects in which the majority operates in separated right-of-way dedicated for transit use during peak periods, represents substantial investment in a single route in a defined corridor or subarea, and has features that emulate services provided by rail (defined stations, traffic signal priority, short bi-directional headways). Small Starts are defined as a “new fixed guideway capital project or a corridor-based bus rapid transit project which is requesting less than $75 million in Section 5309 funds and has a total capital cost less than $250 million.” Unlike New Starts BRT projects, the majority of a corridor-based BRT project does not operate in a separated right-of-way dedicated for transit use during peak periods. The new Core Capacity Improvement designation is defined as a “substantial corridor-based capital investment in an existing fixed guideway system that increases the capacity of a corridor by not less than 10 percent.” Eligible corridors must be at or over capacity or projected to be at or over capacity within the next five years, and projects must not include State of Good Repair elements for an existing fixed guideway system. Cutting the Red Tape MAP-21 simplifies the project approval process, first by eliminating the Alternatives Analysis as a stand-alone requirement, relying instead on local decision-making and a review of alternatives completed during the metropolitan planning and National Environmental Policy Act (NEPA) environmental review processes. Project sponsors will now submit a letter request to FTA/USDOT seeking entry into project development for New Starts, Core Capacity and Small Starts projects. The project is not evaluated nor rated at this stage, but FTA/USDOT will make a determination that the project is accepted into the project development phase. The NEPA environmental review is completed during project development, and New Starts and Core Capacity project sponsors must complete this phase within two years or request an extension from FTA (this new two-year rule does not apply to Small Starts). Following the NEPA decision and selection of the locally preferred alternative, FTA evaluates and rates New Starts and Core Capacity projects based on statutory criteria for approval into the engineering phase, followed by a full funding grant agreement (FFGA). Small Start projects are evaluated after the project development phase [24] and the NEPA decision and rated in consideration of a single-year grant or an expedited grant agreement. Specific definitions of the new project development and engineering phases are evolving. Originally after the passage of MAP-21, many within the industry assumed that the level of detail in the new engineering phase would be identical to the final design phase in the previous authorization bill (SAFETEA-LU). However, current thinking is that the new project development phase is similar to a combination of planning and conceptual engineering, with perhaps some initial preliminary engineering level of detail appropriate to define the project and identify potential effects in completion of the environmental document. The engineering phase would then include completion of preliminary engineering and more detailed final design, as appropriate, leading to funding decisions and execution of a full funding grant agreement. In Small Starts, project development would encompass engineering and design, similar to the current process. These definitions and processes are to be addressed further over the next several months as FTA continues to prepare interim guidance. Project Evaluation and Ratings Under SAFETEA-LU, FTA was required to evaluate and rate New Starts projects prior to approval into preliminary engineering, final design and the full funding grant agreement, and to rate Small Starts projects prior to project development and the project construction grant agreement (PCGA). Under MAP-21, FTA will not rate projects until approval to initiate the engineering phase and execution of the FFGA for New Starts and Core Capacity projects, and not until the funding decision for Small Starts. Project ratings are based on project justification, land use policies and patterns, and local financial commitment for New Starts and Small Starts. Additional factors addressing capacity needs are rated for Core Capacity projects. A congestion relief criterion has been added while the operating efficiencies criterion has been eliminated. And note that cost effectiveness is specifically defined in statute as “cost per rider,” eliminating the current “transportation system user benefit” measure. Quantitative measures will no longer be compared to the “New Starts baseline” as defined by FTA, and project sponsors have flexibility in whether comparisons are made to existing conditions, the no-build or future conditions. MAP-21 actually increases the number of evaluation criteria for Small Start projects, but requires that FTA evaluate the benefits of a Small Start project against the federal share (as opposed to total project cost) when calculating project justification criteria. Project ratings for New Starts, Core Capacity, and Small Starts are based on a five-point scale with comparable weight applied to each criterion; note the bill includes specific language that a medium rating may not be required for any single criterion. In January 2013, FTA published a Final Rule addressing definitions and rating criteria established prior to MAP-21, and Draft Policy © Keith Philpott >> More information on MAP-21 can be found at www.hdrinc.com/map-21. Guidance with detailed procedures and rating thresholds for five of the six criteria and measures. FTA indicates that subsequent rulemaking and policy guidance anticipated in 2013 will address the full set of MAP-21 criteria and measures, define the project advancement process and complete all other requirements. MAP-21 allows for the use of “warrants” under certain conditions, enabling projects to automatically achieve ratings for project justification criteria. Much work needs to be done to apply the warrants-based approach. Program of Interrelated Projects MAP-21 allows the simultaneous development of a combination of multiple New Starts and Core Capacity projects. Non-federal funds committed to a project in the Program of Projects may be used to meet the non-federal share for any other project in the Program of Projects, though federal share cannot exceed 80 percent for any one project. Any federally funded project within the Program of Projects must follow the MAP-21 rating and project advancement process. FTA evaluates and rates all projects in the Program (federally funded and non-federally funded) as one applicant. Non-federally funded projects in a Program of Projects do not need to meet federal requirements that would otherwise not apply (e.g., NEPA). FTA completes an annual review of a program implementation plan, and the project sponsor must repay all federal funds if the complete Program of Projects is not implemented within a reasonable timeframe. This opportunity currently does not apply to Small Start projects. Including a non-federally funded project in a program of interrelated projects does not impose government requirements that would not otherwise apply to the project. Additional guidance is needed on what requirements may or may not be applied. We Started a Project Under the Old Program— What Happens Now? FTA has not yet provided any specific transitional guidance for projects that are initiating or currently completing AAs, or for projects currently in New Start Preliminary Engineering and Final Design phases or the Small Starts Project Development phase. The APTA Policy and Planning Committee is in discussions with FTA staff to propose initial guidance. HDR’s online MAP-21 interim guidance document will be updated as new information becomes available. Summary The interpretation in this article represents the latest information available from FTA and through industry outreach. The landscape of federal transit funding continues to evolve as FTA and the industry adapt to the MAP-21 legislation. Though the current authorization applies only through September 2014, it is anticipated that many of the policy and procedural changes established during MAP-21 will carry forward to the next authorization bill. -> For more information, view our online resources at www.hdrinc.com/map-21 or contact the author at David.Vozzolo@hdrinc.com. Editors note: David Vozzolo is a nationally recognized leader in planning and development of rail and bus rapid transit projects, and is Vice-Chair of the APTA Policy and Planning Committee. He previously served as Deputy Associate Administrator for FTA’s Office of Planning and Environment. During his time with FTA, David was responsible for designing and implementing the New Starts evaluation and rating process and eventually managed the New Starts program. [25] PERSPE C TIVE Envision™ Sustainabilit y Infrastruc ture Rating System Addresses Design Challenges by Michaella Wittmann, LEED Fellow, ENV SP; David Taylor, ENV SP; and Mona Eigbrett, LEED AP BD+C, ENV SP LEED is such a common term in the building industry that it is rare to even see the acronym spelled out anymore. Of course, LEED stands for Leadership in Energy and Environmental Design—a program that became the industry standard for “green” buildings, or vertical infrastructure. But what equivalent is there for horizontal infrastructure? Until recently, there was no single, cross-infrastructure sustainability rating system available, although there were a number of sectorspecific systems. Increasingly, owners of horizontal infrastructure are seeing conservation measures and the use of alternative materials and technologies as part of design requirements. These requirements won’t go away. In fact, they are likely to be more common. To meet these challenges, the Envision™ rating system was developed as a project assessment tool and to offer guidance for sustainable infrastructure design. Envision was created by a strategic alliance of the Institute for Sustainable Infrastructure (ISI) and the Zofnass Program for Sustainable Infrastructure at the Harvard University Graduate School of Design. ISI, which was formed by the American Public Works Association, American Council of Engineering Companies and American Society of Civil Engineers, recently deployed Envision. A certification tool, it is meant to provide industry-wide sustainability metrics for all infrastructure types—an approach similar to its vertical facility counterpart, LEED. The tool can be used by infrastructure owners, design teams, community groups, environmental organizations, constructors, regulators and policy makers. These groups may be interested in certifying a project to gain public acceptance, see long-term cost savings, offer risk-avoidance, achieve third-party verification or protect and enhance environmental assets. Envision provides guidance for integrating sustainability into infrastructure projects, which is often difficult to define and [26] measure. The tool could have far-reaching impacts, including creating cost-effective, more energy-efficient and adaptable longterm infrastructure investments. How Does Envision Work? Envision evaluates, scores and gives recognition to infrastructure projects that use transformational, collaborative approaches to assess sustainability indicators over the course of a project’s life cycle. It features assessment tools that can be used for infrastructure projects of all types, sizes, complexities and locations. With a collaborative, focused effort, Envision can help owners develop an infrastructure investment with longer-term viability, at a potentially lower cost, with fewer negative impacts on the community. In fact, Envision can help teams develop projects with significantly reduced impact and move toward restoration of previously disturbed sites. Essentially, using Envision helps an organization demonstrate that a project is the best solution for a community, with the added value of being measured and verified by a third-party rating system. Knowing that every solution will not apply to every project, the creators of Envision built flexibility into the tool. The rating system can help serve as a roadmap for project sustainability, even if project certification is not pursued. It can be used as a checklist or simply to provide guidance when designing a project. The checklist can help project teams assess project sustainability and increase awareness of broader community and resource issues. Both the checklist and guidance manual are free tools that help set a project’s direction and provide for early project review. A project also can move through the full process of achieving certification at the Bronze, Silver, Gold and Platinum levels. Project teams review 60 sustainability criteria, called credits, divided into five categories: Quality of Life, Leadership, Resource Allocation, Natural World, and Climate and Risk. © Keith Philpott >> The Envision program establishes a universal sustainability rating system for horizontal infrastructure. The number of points earned for each credit depends on the level of achievement: • Improved: achieves performance somewhat better than conventional • Enhanced: indicates that superior performance is within reach • Superior: features sustainable performance that is noteworthy • Conserving: essentially achieves zero impact • Restorative: restores natural or social systems Advancing the Tool HDR is a charter member of ISI and is working with the organization to advance the use of Envision. Our management team has made sustainability a high priority and believes that our professionals can lead the development of sustainable projects using Envision. HDR has established a goal to reach 100 credentialed Envision Sustainability Professionals (ENV SP) by the end of 2013, and to have 10 percent of our credentialed employees become qualified to provide third-party verification of non-HDR projects. HDR employees currently serve on four of the seven ISI committees. ISI and HDR recently presented an Envision webinar to the federal Partnership for Sustainable Communities—which includes the Department of Transportation, Department of Housing and Urban Development and the Environmental Protection Agency—as well as the Federal Transit Administration headquarters and regional offices, to provide a better understanding of the tool’s potential for new transit projects. We conducted a similar webinar for the American Public Transit Association. HDR helped the William Jack Hernandez Sport Fish Hatchery in Anchorage, Alaska, become the inaugural project registered with ISI, and we currently are talking with a variety of clients about Envision to determine if it might be used on their projects. Our goal is to help owners, communities, constructors and others create cost-effective, more energy-efficient and adaptable longterm infrastructure investments. -> Find more information at www.sustainableinfrastructure.org or please contact Michaella.Wittmann@hdrinc.com. [27] 8404 Indian Hills Drive | Omaha, NE 68114-4049 www.hdrinc.com PRSRT STD US POSTAGE PAID OMAHA, NE PERMIT NO. 963 T R A N S P O R TAT I O N > DELIVERED 3421 0413 SPRING 2013 What Moves Us Delivering safe, reliable and efficient infrastructure day in and day out is hard work unless you’re seriously passionate about what you do. The passion our employees have for their families, communities and industry fuels their desire to develop innovative solutions to today’s transportation challenges. Tom Kim, P.E. | Southern California Transportation Director Los Ang eles, C A Tell us a little about yourself and your family. Both of my parents worked at Yongsan (U.S. Army Garrison in South Korea) for the American government. They met there and served over 20 years and were then invited to come to the United States. I was born in Seoul, South Korea, and when I was 15 years old my family immigrated to the United States. I am the oldest child with three younger sisters, and we lived and went to high school in La Crescenta, Calif. I am married and have two children, Tommy Jr. and Pricilla. Tommy Jr. is currently studying at Cal Poly (my alma mater) and wants to be an engineer, and Pricilla is studying at U.C. Davis and wants to be a veterinarian. What inspired you to get into the engineering industry? In school I was very good at math, so engineering, to me, seemed like a natural fit. I am the odd one out in my family as everyone else is in the jewelry business. What are you most passionate about? I am passionate about making a difference. I like that what I do matters and will help the quality of life for others. I want to contribute to people’s lives, and I am passionate about turning a “can’t do” into a “can do.” Tell us about your role at HDR. As the Southern California Transportation Director, I oversee our transportation group’s operations and program development in the region. I am a practice builder and manage / direct high-profile projects. What has been your favorite project and why? I have the opportunity to work on some fantastic projects across all modes in Southern California, and with great clients who consider HDR a trusted advisor. One project I am engaged in right now is the Port of Long Beach Pier B Rail Facility. This project provided an opportunity for us to work with multiple market sectors and build a client for life. I also am very proud of completing the Colton Crossing Project. This is a critical link to our nation’s movement of goods and has a large impact on the economy. People thought the project would never be built, and now it is in construction. ->