Conventional Thermal power plants

advertisement

Contents

:

1 Introduction & Egyptian Power sector key parameters.

2 Recent Energy Challenges for the Egyptian Power sector.

3

Initiatives of the Egyptian Power sector to meet energy challenges

4 Previous Co-operation with the Japanese Companies

5

Recent available Co-operation Opportunities in energy

Sector Power Projects.

1- Introduction &

Egyptian Power sector key parameters

*Based on (2012/2013) EEHC report

Introduction & Egyptian Power sector key parameters.

The electricity and energy sectors plays a vital role in the economical growth to secure adequate electricity supplies at minimum cost to all consumers with the international standards. During the last decade, a rapid increase of electricity demand occurred, the electricity sector has grown rapidly trying to meet this increase.

Introduction & Egyptian Power sector key parameters.

Installed Capacity (MW)

Type

Combined Cycle

MW

11830.5

Steam Cycle

Gas turbine

Hydro

Renewables

Total

%

33

13843.5 45

3504

2842.5

11

9

547

32708

2

100

Yearly Peak Load

Development (MW)

Peak Load Curve

2011/2012-2012/2013

Development of Gross

Energy Generated (GWh)

Energy Generated and

Purchased (GWh)

Energy Sold by Purpose (Gwh)

Fuel Consumption

Development (Ktoe)

Fuel Consumption Rate

(gm/kWh)

International Electrical Interconnection

Recent Challenges for the Egyptian Power sector

Recent Challenges for the Egyptian Power sector

From the year 2012, The electricity sector has faced the following challenges:

1) High increase in the electrical loads in an unmatched way, where the maximum load growth rate in 2012 rate of 10.3% compared to the average past growth rate, which ranged from 4.3% to 8%.

2) Significant shortage in the natural gas supplies by the year 2012.

Recent Challenges for the Egyptian Power sector

3) Necessity of Restructuring electricity tariff as the selling price was less than 50% of the production cost.

4) Significant shortage in the natural gas supplies by the year 2012.

5) Lack of funds needed for new power projects.

6) The low efficiency in some power plants due to:

14

Initiatives

The Egyptian Electricity sector seeks to face the previous stated challenges through the following: a- Ongoing initiative for Existing assets & power sector regulations. b- Private Sector Partnership. c- Changing the energy generation mix.

Initiatives

a- Ongoing initiative for

Existing assets & power sector regulations.

Initiatives

Ongoing initiative for Existing assets & power sector regulations.

Existing Generation assets:

Launching a program to optimize operation and maintenance of GTs & CCGT and steam turbine.

Power sector regulations:

Review tariff system.

Assess potential impact from DSM measures.

Initiatives

The Egyptian Electricity sector seeks to face the previous stated challenges through the following: a- Ongoing initiative for Existing assets & power sector regulations. b- Private Sector Partnership. c- Changing the energy generation mix.

Initiatives

b- Private Sector partnership

b- Private sector Partnership

The Egyptian government and the electricity sector recognized the importance of private sector partnership to improve all production processes and to minimize the investment cost burden.

Initiatives for Private sector

Gradual subsidies removal over the next five years by designing a new electricity tariff structure.

Issuing a Feed-In-Tariff for renewable energy trading.

Repairing the new low of electricity (expected to be issued soon).

Initiating the gradual liberalization of the electricity market.

Initiatives for Private sector for

Renewable Energy

An area of about 7845 km2 on the Gulf of Suez region and the Nile Banks has been allocated for NREA for implementing wind energy projects, Permitted lands are provided to Investors through Land Use agreement against 2% of annual generated Energy from the project or its value.

One window (dealing with one central services unit in the ministry of electricity and renewable energy).

Bankable PPA (Power Purchase agreement)

Government sovereign Guarantees.

Initiatives for Private sector for

Renewable Energy

(2%) Custom duties for all renewable system components.

Lower interest rates for Solar project less than 500 KW & roof top units.

Assessment of environmental impact, including bird migration.

Investors will benefit from selling Certified Emission

Reductions, CERs, resulted from the implemented project.

Incentives for Renewable Energy

Feed In Tariff for PV Power Plant

Installation connected to the low voltage:

Residential 84.8 PT / KWh

Other than residential and up to 200 KW

From 200 Kw up to 500 KW

90.1 PT / KWh

97.3 PT / KWh

Installation connected to the medium voltage from 500 Kw up to 20 MW 97.3 PT/ KWh

Installation connected to the medium voltage

From 20 Mw up to 50 Mw 102.5 PT/ KWh

Incentives for Renewable Energy

Operational Hours

3300

3400

3500

3600

3700

3800

3900

4000

2500

2600

2700

2800

2900

3000

3100

3200

Wind Energy Feed in Tariff

First Stage FiT Second Stage FiT

$ cent / kwhr pt / kwhr

11.48

9.57

82.08

68.4

$ cent / kwhr

11.48

10.56

9.71

8.93

8.19

7.51

8.93

8.33

7.76

7.23

6.73

6.26

5.81

5.39

4.98

4.6

pt / kwhr

82.08

75.053

69.46

63.83

58.58

53.68

63.82

59.53

55.49

51.7

48.12

44.73

41.54

38.51

35.58

32.9

b- Private sector Partnership

The Private Sector Investors have taken part in implementing Generation Power Plants in the

Egyptian power sector through three basic contract

Scheme:

(BOO or BOOT) schemes

IPP scheme

Recently, the Egyptian electricity sector encourages the private sector partnership through the (EPC +

Finance) scheme.

Initiatives b- Private Sector partnership

Already signed agreements with private investors in power plants Projects

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Frame Work Agreement

Power Purchase Agreements

Memorandum of Understanding

Accessibility Land Agreements - FIT

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Framework

Agreements

Power Purchase

Agreements

MOU

Accessibility Land

Agreements

Agreement Parities

Constructing (3200 Mw) Coal Power Plant

(in El-Hamrawain) Site

Constructing (6

× 660 Mw) Coal Power

Plant

Smart Meters

Constructing (2100 Mw) Pump storage power plant in (Ataqqa) site

Party (1): EEHC

Party(2): Orascom/IPIC Consortium

Party (1): EEHC

Party(2): Dong Fang (DEC)

Party (1): EEHC

Party(2): Huawei

Party (1): HPPEA

Party(2): Sinohydro Corporation Ltd.

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Framework

Agreements

Power Purchase

Agreements

Agreement

MOU

Accessibility Land

Agreements

Parities

Constructing (4640 Mw) Coal Fired

Power Plant

Transmission System Development

Party (1): EEHC

Party(2): Shanghai Electric

Party (1): EEHC

Party(2): State Grid

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Framework

Agreements

Power Purchase

Agreements

MOU

Accessibility Land

Agreements

Agreement Parities

Power Purchase Agreement from

(2640 Mw) Coal Power Plant in

(Eyoun Mousa) site

Power Purchase Agreement from

(2300 Mw) Metoubas Power Plant in

(Kafr El-Shiehk) site

Party (1): EEHC

Party(2): Nowise

Party (1): EEHC

Party(2): Benchmark

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Framework

Agreements

Power Purchase

Agreements

MOU

Accessibility Land

Agreements

Agreement Parities

Conversion of (Assuit) & (West Dumyat) to be worked as (750 Mw) CCGT

Party (1): EEHC

Party(2): General consortium

Electric/Orascom

Implementing (5 Billion) Projects:

(3000 Mw) Solar power plant as (600 Mw) each 5 yrs.

• Providing a part of project profits for development & training on solar power projects (519 M$)

Party (1): EETC

Party(2): Sky power/Gulf development consortium

Constructing (2000 Mw) solar power plant

Party (1): EETC

Party(2): Sky power/Gulf development consortium

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Framework

Agreements

Power Purchase

Agreements

MOU

Accessibility Land

Agreements

Agreement Parities

Constructing (2000 Mw) Projects based on

(BOO) or (EPC+Finance) in addition to implementing a human development programs for training, learning& qualifying.

Party (1): EETC

Party(2): Tera Nex/Tera Sola Consortium

Constructing (2200 Mw) CCGT in (West

Dumyat) site.

Constructing (1500 Mw) solar power plant

Constructing (200 Mw) Wind power plant

Party (1): EEHC

Party(2): Acwa power/Masder Consortium

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Framework agreements

Power Purchase

agreements

Agreement

Constructing (6000 Mw) Coal power plant

MOU

Accessibility Land

Agreements

Parities

Party (1): EEHC

Party(2): Tharwa investment company

Constructing (2000 Mw to 4000 Mw) Coal power plant in (Safaga) Site

Party (1): EEHC

Party(2): Acwa power

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Framework agreements

Power Purchase

agreements

MOU

Accessibility Land

Agreements

List of Chinese companies signed MOUs with the ministry of electricity

Harbin Electric Group

AVIC International Holding Company

China Gezhouba Group Corporation CGGC

China Machinery Engineering Corporation

Dong Fang Electric Group

Huawei North Africa Region

Huawei Technologies Co.Ltd

Shanghai Electric Company

Sinohydro Corporation Ltd

State Grid Corp of China

b- Private sector Partnership

Already signed agreements with private investors in power plants Projects:

Framework agreements

Power Purchase

agreements

MOU

Accessibility Land

Agreements

Agreement

4 Entry permit

MOUs to some pieces of NREA land owned in Aswan for executing the required necessary studies and measurements for constructing (200

Mw) solar power plants according to

(FIT) contracting model

Parities

Part (1): NREA

Parties:

(50 MW) O-capital Company

(50 Mw) FAS Company

(50 Mw) Philadelphia Company

(50 Mw) Static Company

Initiatives

The Egyptian Electricity sector seeks to face the previous stated challenges through the following: a- Ongoing initiative for Existing assets & power sector regulations. b- Private Sector Partnership. c- Changing the energy generation mix.

Initiatives c

- Changing the energy

Generation mix

c- Changing the energy Generation mix

Meeting the future electricity demand requires diversification of the energy mix by including the new generation technologies (such as clean coal, nuclear and renewable energy), with taking into consideration choosing the best generation mix taking into consideration the optimum:

Technological aspects.

Environmental aspects.

Economical and social dimensions.

The current and expected situation of electricity demand and peak load and generated energy.

c- Changing the energy Generation mix

Recent Situation Of Coal utilization in Egyptian power sector:

In that framework, The importance of coal utilization in power generation appears as an alternative to natural gas power plants due to the following:

The Prediction of resuming the insufficient local quantities of natural gas to cover the future load demand.

The economic competitiveness of coal with comparing the recent and future predicted exportation prices of coal and natural gas.

Previous Co-operation with

Japanese Companies

Previous Co-operation with Japanese Companies

NO Project Name

Contractor/

Consortium

Task

1

2

3

41

Cairo West Steam

Units “5 & 6”

(2 × 320 MW)

Maroubiny Company Steam Boilers

Cairo North (1)

CCGT (750 MW)

Mitsubishi for heavy industries/Toyota Tosusho

Hitachi /Somotomo

Hitachi /Somotomo

Gas Turbines

Transformers

Steam Turbines

Mitsubishi for heavy industries/Toyota Tosusho

Steam Turbines

Noubaria

(1 & 2) – CCGT

(1500MW)

AE for energy systems/

Somotomo/ the Egyptian

Company ” Consis”

Switch yard

(500KV)

Contract date

1999

2002

2002

2009

2003

2003 contract

(Million

US$)

77.8

115.1

6.7

34.8

61

52.5

Previous Co-operation with Japanese Companies

NO Project Name

Contractor/

Consortium

Task

4

Kurimat (2) –

CCGT

(750 MW)

Hitachi /Somotomo Steam Turbines

5

Cairo North (1)

CCGT

(750 MW)

Mitsubishi for heavy industries/Toyota Tosusho

Gas Turbines

Toyota Tosusho/Toshiba

Mechanical works

Ibara Koryorition/Ibara yusheKora Hydrotech

Pumps and their accessories

Contract date

2005

2007

2008

2008 contract

(Million

US$)

20.35

103.4

37.4

13.5

Toyota Tosusho/Toshiba Electrical works 2008 16

Previous Co-operation with Japanese Companies

NO

6

Project Name

Contractor/

Consortium

Task

Mitsubishi for heavy industries/Toyota

Tosusho

Toyota Tosusho/Toshiba

El Atf– CCGT

(750 MW)

Ibara Koryorition/Ibara yusheKora Hydrotech

Gas Turbines

Mechanical works

Pumps and their accessories

Contract date

2007

2008

2008

Toyota Tosusho/Toshiba

Electrical works

2008 contract

(Million

US$)

104

43.5

12.4

16.5

Previous Co-operation with Japanese Companies

NO Project Name

Contractor/

Consortium

Task

7

Cairo West

Steam Units

“7 & 8”

(2 × 350 MW)

Mitsubishi for heavy industries/Toyota Tosusho

Hitachi /Somotomo

Steam

Turbines

Steam Boilers

8

9

10

Abo Qir Steam

(2× 650 MW)

Mitsubishi for heavy industries/Toyota Tosusho

Ain Sokhna

Steam

(2× 650 MW)

Banha CCGT

(750MW)

Hitachi /Somotomo

Hitachi

Hitachi / Toyota Tosusho

Steam

Turbines

Steam

Turbines

Pumps

Mechanical works

Contract date contract

(Million

US$)

2007 99.9

2007

2009

2009

2010

2012

174.4

318.1

301.3

40

27.2

Previous Co-operation with Japanese Companies

NO Project Name

Contractor/

Consortium

11

Suez steam

(650MW)

12

South Helwan steam

(3× 650 MW)

Hitachi

Mitsubishi for heavy industries/Toyota

Tosusho

Task

Pumps

Steam

Turbines

Contract date contract

(Million

US$)

2013 20.8

2014 289.1

Recent Co-operation

Opportunities in Power

Projects

Recent Co-operation Opportunities in Power Projects a- Conventional Thermal power plants b- Coal Fired thermal Power plants

a- Conventional

Thermal power plants

a- Conventional Thermal power plants

EEHC Multi-Packages Tenders

Power Plant

Installed

Capacity (MW)

Process number

Expected Tendering date

Cairo West Steam

Assuit Steam P.P

Damanhur CCGT

650 Mw

×

1

1 × 650 Mw

1 × 900 Mw

18

17

19

Start: 1 st half 2015

Closing: June 2016

Start: 1 st half 2015

Closing: June 2016

Start : last quarter of 2015

Closing: end of 2016

EPC + Finance

MHI participate in the (Suif) site tender among 14 other investor

a- Conventional Thermal power plants

Gas Units Conversion to CCGT to face Summer 2015 loads

Power Plant

Assuit

West Damietta

El-Mahmoudia

Installed Capacity

(MW)

8 × 125 Mw

4 × 125 Mw

2 × 160 Mw

Commissioning date of gas units

Units (1,2,3) in 31/5/2015

Units (4,5,6) in 30/6/2015

Units (7,8) in 31/8/2015

Units (1,2) in 30/6/2015

Units (4,3) in 31/7/2015

Unit (1) in 31/7/2015

Unit (2) in 8/8/2015

a- Conventional Thermal power plants

Gas Units Conversion to CCGT to face Summer 2015 loads

Power Plant

Ataqa

Sharm El-sheikh

Hurghada

Installed Capacity

(MW)

4 × 160 Mw

Commissioning date of gas units

Unit (1) in 31/5/2015

Unit (2) in 8/6/2015

Unit (3) in 16/6/2015

Unit (4) in 1/7/2015

6 × 48 Mw

5 /2015

6 × 48 Mw

b- Coal fired Thermal

Power Plants

b- Coal fired Thermal Power Plants

Recent MOU signed with

Chinese companies for Coal power plants implementation

Coal power plants to be financed by EXIM- Bank

Coal power plants to built through BOO or Boot Model

b- Coal fired Thermal Power Plants

Coal power plants to built through Chinese private sector investors under (EPC +

Finance) scheme.

Company Name

AVIC

Shanghai Electric

Corporation & Shanghai

Electric Power

Dong Fang

NWPC

Project

Capacity

1320 MW

2640 Mw

1320 Mw

1320 Mw

Budget

(Billion USD)

2

4

2

2

b- Coal fired Thermal Power Plants

Coal power plants to built through Chinese private sector investors under (EPC +

Finance) scheme.

Company Name

CGGC

CMEC

Harbin

AVIC

Sino-Hydro

Project

Capacity

1320 MW

1320 Mw

1320 Mw

1320 Mw

1320 Mw

Budget

(Billion USD)

2

2

2

2

2

b- Coal fired Thermal Power Plants

Recent Candidate sites for Coal power plants implementation

Coal power plants to be financed by EXIM- Bank

Coal power plants to built through BOO or Boot Model

b- Coal fired Thermal Power Plants

Coal power plants to be financed by EXIM- Bank

Company Name

AVIC

Project

Capacity

1320 MW

Budget

(Billion USD)

2

Shanghai Electric

Corporation & Shanghai

Electric Power

Dong Fang

NWPC

2640 Mw

1320 Mw

1320 Mw

4

2

2

b- Coal fired Thermal Power Plants

Recent Candidate sites for Coal power plants implementation

Coal power plants to be financed by EXIM- Bank

Coal power plants to built through BOO or Boot Model

b- Coal fired Thermal Power Plants

Coal power plants to built through BOO or Boot Model

Company Name

CGGC

Shanghai Electric

Corporation & Shanghai

Electric Power

CMEC

Harbin

AVIC

Sino-Hydro

Project

Capacity

1320 MW

2000 Mw

1320 Mw

1320 Mw

1320 Mw

1320 Mw

Budget

(Billion USD)

2

3.5

2

2

2

2

Fruitful expected Egyptian – Japanese cooperation framework

In the Light of the previous, the Japanese Side is invited to co-operate with the Egyptian side in the field of implementing coal power plants according to the following suggested steps:

1) Sign MOU between the two parties includes providing the

Egyptian side with a preliminary technical and economical feasibility study carried out by the Japanese side as EPC + finance.

2) Signing an (EPC + Finance) contract between parties in the light of preliminary feasibility study results.

Fruitful expected Egyptian – Japanese cooperation framework

In the frame work of the continuous co-operation between the

Japanese and the Egyptian sides specially in the energy sector with the most advanced and efficient technologies, And with taking into consideration that the coal power plants are one of the most essential promoted projects decided to be established in Egypt. It is expected that the Japanese side continue its effective support to the Egyptian side in different energy projects specially the coal fired thermal power plants.

a- Conventional Thermal power plants

Damanhour

CCGT

• 6 th October

• Cairo west

• Assuit (Waledia)

a- Conventional Thermal power plants

El Mahmoudia

West Domiaata

Attaqa

Sharm Elsheik

Hurghada Assuit

b- Coal fired Thermal Power Plants

Recent Candidate sites for Coal power plants implementation

Download