Site Investigation in the 21st Century? Chris Clayton FOR PERSONAL USE ONLY (c) Chris Clayton Issues Site Investigation in the 21st Century • • • • • Background Aims Constraints Urbanization Essential components 2 FOR PERSONAL USE ONLY (c) Chris Clayton Issues Site Investigation in the 21st Century • • • • • Background Aims Constraints Urbanization Essential components 3 FOR PERSONAL USE ONLY (c) Chris Clayton Terzaghi oedometer 1923 CPT Delft Grondmechanika 1945 SPT 1902-1947 BRE laboratory 1945 Most of the techniques we routinely use are between 60 and 100 years old 4 Bishop with U4 1944-45 FOR PERSONAL USE ONLY (c) Chris Clayton 1906 2006 5 FOR PERSONAL USE ONLY (c) Chris Clayton Background “… engineers imagined that the science of foundations would consist in carrying out the following program: 1. Drill a hole into the ground. 2. Send the soil samples obtained from the hole through a laboratory with standardized apparatus served by conscientious human automatons. 3. Collect the figures, introduce them into the equations, and compute the result” “Unfortunately, soils are made by nature and not by man, and the products of nature are always complex.” Terzaghi, 1936 6 FOR PERSONAL USE ONLY (c) Chris Clayton Total increase in construction cost (%) Cost over-run on UK highway projects Background 100 ? current spend 25 0 0 1 10 5 SI cost / construction tender cost (%) 7 (from TRL Project Report 60) FOR PERSONAL USE ONLY (c) Chris Clayton Background Cause of cost over-runs on 12 highway projects interpretation of SI project planning site investigation planning additional work amended work quality control variation in quantities bills of quantities specification 60 100 % net additional cost 200 8 (Tyrrell, Lake and Parsons, 1985) FOR PERSONAL USE ONLY (c) Chris Clayton Issues Site Investigation in the 21st Century • • • • • Background Aims Constraints Urbanization Essential components 9 FOR PERSONAL USE ONLY (c) Chris Clayton “Subsurface projects present an enormous risk for the primary project “stakeholders”, i.e. the owner and contractor. Realistically, not all risk for subsurface conditions can be entirely avoided or eliminated. “ • Ground geometry • Groundwater • Ground properties Aims and • Hazards and risks – Geologic hazards – Geomaterial hazards – Geotechnical hazards – Land use hazards Hatem, 1998 health and safety cost and • Residual uncertainties following GI geotechnical risk quality environment programme 10 FOR PERSONAL USE ONLY (c) Chris Clayton Aims Ground geometry 11 (A ‘geological model’ from Fookes, 1997) FOR PERSONAL USE ONLY (c) Chris Clayton Ground hazards and risks Aims • Geologic hazards • Geomaterial hazards • Geotechnical engineering hazards Risks Vulnerability • Land use hazards 12 FOR PERSONAL USE ONLY (c) Chris Clayton Geotechnical problems during construction 5% Soil boundaries 4% 6% 22% Aims Soil properties Ground water 9% Contamination Obstructions Planning of SI 10% Services 20% Detailed design Other 11% 13% From a survey of 28 construction projects (Clayton, 2001) 13 FOR PERSONAL USE ONLY (c) Chris Clayton Example of risk analysis 14 (see the ICE/DETR Report on ‘Managing Geotechnical Risk’) FOR PERSONAL USE ONLY (c) Chris Clayton Issues • • • • • Background Aims Constraints Urbanization Essential components 15 FOR PERSONAL USE ONLY (c) Chris Clayton Constraints • • • • Ground conditions Equipment Supervision Knowledge and experience (in local conditions) • Education • Computation techniques • Conditions of contract (?) • Money (?) 16 FOR PERSONAL USE ONLY (c) Chris Clayton Constraints SPT hammers U100 disturbance Most data used in design are not fundamental - variations in the ways drilling, sampling and testing are done make the results very variable 17 FOR PERSONAL USE ONLY (c) Chris Clayton observed / predicted settlement Constraints Predicted and observed settlements for spread footings on sand 20 10 5 1 0.2 0.1 0.05 0.1 1.0 10 100 predicted settlement (mm) 18 Clayton, Simons and Instone, 1988 FOR PERSONAL USE ONLY (c) Chris Clayton Predicted v. observed pile capacities shaft capacity base capacity Constraints observed pile performance A B C D E F G H I J K L M N O P predictions of pile performance 0 1000 2000 3000 4000 pile capacity (kN) 5000 6000 19 Wheeler, 1999 FOR PERSONAL USE ONLY (c) Chris Clayton Constraints The need for experience Building on dolomite damaged by subsidence (courtesy Prof. G. Heymann) “There are known knowns. These are things that we know that we know. There are known unknowns. That is to say, there are things that we know we don’t know. But there are also unknown unknowns. There are things we don’t know we don’t know.” Donald Rumsfeld 20 FOR PERSONAL USE ONLY (c) Chris Clayton Constraints Growing problems with UK education and training •Very small proportion of civil engineering graduates now take a soil mechanics or geotechnical engineering MSc •Civil Engineering MEng/PhD graduates are not adequately trained (ab initio) to practice as geotechnical engineers •Engineering geology postgraduate courses are not valued by leading geology departments •Very difficult to identify the next generation of senior geotechnical laboratory technicians •Are the working conditions of the light percussion driller compatible with high quality technical output? 21 FOR PERSONAL USE ONLY (c) Chris Clayton Constraints Growing problems with knowledge and experience • Few consultants (or SI engineers / geologists) understand the details of drilling and testing techniques. • Specification of more complex work can be poor. • Consultant supervision is pointless unless informed and rigorous. • GI contractors cannot afford to supervise fieldwork unless paid. • Drillers and technicians are a most important resource. They need to be trained, and feel part of the team. 22 FOR PERSONAL USE ONLY (c) Chris Clayton Issues • • • • • Background Aims Constraints Urbanization Essential components 23 FOR PERSONAL USE ONLY (c) Chris Clayton Urbanization Urbanization • At the beginning of the 20th century 7% of the world’s population could be considered ‘urban’. Most urban dwellers lived in developed countries. • By 1950 30% of the population lived in urban areas, and by 2000 47% was urban 24 FOR PERSONAL USE ONLY (c) Chris Clayton Urbanization Urbanization • At the beginning of the 20th century 7% of the world’s population could be considered ‘urban’. Most urban dwellers lived in developed countries. • By 1950 30% of the population lived in urban areas, and by 2000 47% was urban • By 2030 it is expected that >60% of the world’s population will live in an urban world. • Most of the new urban areas will be in 25 developing countries. FOR PERSONAL USE ONLY (c) Chris Clayton Predicted Asian population growth URBAN RURAL 2 1 19 50 19 75 20 00 20 30 0 19 50 19 75 20 00 20 30 Population (billions) Urbanization 3 From Zlotnik (2003) 26 FOR PERSONAL USE ONLY (c) Chris Clayton Urbanization Anyone who believes that India is an ‘economic powerhouse’ should ‘try living there’. ‘The shortcomings of infrastructure are a huge problem. In Delhi ‘some areas are blighted by daily four-hour power cuts’. ‘A report last week highlighted a 73km rail project in East Bengal that is still unfinished after 32 years.’ (Justin Huggler in The Independent, Sept 2006) 27 FOR PERSONAL USE ONLY (c) Chris Clayton Urbanization Urban vulnerability • • • • Instability of natural slopes Mining impacts Damage to infrastructure Effects of construction on nearby structures 28 FOR PERSONAL USE ONLY (c) Chris Clayton Hong Kong, Po Shan Road Slide, 1972 • Rainfall of 700mm in 3 days prior to slide • Main slide involved 25,000m3 debris, moving 280m in 1 minute • 1 block of flats pushed off foundations onto another • 67 people died 29 FOR PERSONAL USE ONLY (c) Chris Clayton Merriespruit tailings dam failure, South Africa 28m high tailings dam, failed 21 February 1994, 17 died30 FOR PERSONAL USE ONLY (c) Chris Clayton Kinzie Street Bridge, Chicago 13 April 1992 Downtown basements flooded as a result of piling work. President signs disaster declaration. 31 FOR PERSONAL USE ONLY (c) Chris Clayton Heathrow Airport Central Terminal Area collapse 20 October 1994 32 FOR PERSONAL USE ONLY (c) Chris Clayton The Straits Times 2004 33 FOR PERSONAL USE ONLY (c) Chris Clayton Urbanization Urban ‘ground’ - London • • • • • • Made ground Archaeological heritage Contaminated land Infrastructure Obstructions Ordnance 34 FOR PERSONAL USE ONLY (c) Chris Clayton Reconstruction of Southwark’s topography c. AD50 on modern street plan London Bridge South Bank of River Thames (2008) 200m 35 Yule (1988) FOR PERSONAL USE ONLY (c) Chris Clayton London Bridge Hotel lift shaft excavation http://www.londonbridgehotel.com/p_geology.html 36 FOR PERSONAL USE ONLY (c) Chris Clayton Archaeological heritage Rediscovery of the Rose Theatre in 1989 37 FOR PERSONAL USE ONLY (c) Chris Clayton Grand Buildings, Trafalgar Square, London London Underground tunnels 38 FOR PERSONAL USE ONLY (c) Chris Clayton 39 FOR PERSONAL USE ONLY (c) Chris Clayton Redevelopment London Bridge area John Dugleby’s map of 1792 superimposed on a 1:1250 Ordnance Survey Map of 1950 40 FOR PERSONAL USE ONLY (c) Chris Clayton Battersea Power Station - existing foundations 41 FOR PERSONAL USE ONLY (c) Chris Clayton Battersea foundations Desk study 42 Exhumation, examination and testing FOR PERSONAL USE ONLY (c) Chris Clayton Bomb damage to London Bridge area Total destruction Damage beyond repair Seriously damaged, doubtful if repairable Seriously damaged but repairable at cost General blast damage, not structural Blast damage, minor in area Clearance areas Post-war 1:1250 bomb damage map 43 FOR PERSONAL USE ONLY (c) Chris Clayton Issues • • • • • Background Aims Constraints Urbanization Essential components 44 FOR PERSONAL USE ONLY (c) Chris Clayton Components Essential components • Competence / registration – – – – – Engineers Geologists SILC Technicians Drillers (AGS, 2006) • Early involvement of geotechnical experts (hazard + risk assessment, conceptual design) • Desk study and walkover survey • Geological, geotechnical and land use ground models. • Targetted planning of ground investigation 45 FOR PERSONAL USE ONLY (c) Chris Clayton Geotechnical and contaminated land models 46 FOR PERSONAL USE ONLY (c) Chris Clayton Components Essential components • Targetted direct investigation – – – – Accurate identification of soil boundary locations Groundwater positions / conditions Contaminated land investigation Repeatable test results • • • • Supervision Informed interpretation Appropriate analysis Hand-over of residual risks (risk registers) • Contribution to CDM 47 FOR PERSONAL USE ONLY (c) Chris Clayton The way forward? Summary • Definitions of content (essential components), to define negligence. • Definitions of education, training, experience for all levels of staff, to define necessary levels of competence. • Quality driven by site investigation industry, perhaps by peer review. Distinct geotechnical design strategies for • ‘Routine’ construction • Major projects or ‘difficult ground’ 48 FOR PERSONAL USE ONLY (c) Chris Clayton The way forward? Design strategy - Routine construction • • • • • • • • • • Recognise and understand current GI inadequacies. Make great use of desk study information Develop ground and land-use models (esp. cities) Proper planning and informed interpretation of site investigations Use local and company experience, and material performance database (case records) Hazard identification and risk analysis Conceptual design to avoid or mitigate risks Limited, basic, quick, repeatable ground investigation? Conservative and simple analyses Observation (and possibly monitoring) during construction 49 FOR PERSONAL USE ONLY (c) Chris Clayton Windowless sampler 100mm ID 70mm ID 47mm ID Drive sampling rig 48% AR 81% AR 116% AR 50 (courtesy Dando and Archway) FOR PERSONAL USE ONLY (c) Chris Clayton Cone truck and Mostap sampler (courtesy Lankelma) 51 FOR PERSONAL USE ONLY (c) Chris Clayton The growth of web sources of information High-resolution vertical and oblique air photography of University of Southampton From www.maps.live.com 52 FOR PERSONAL USE ONLY (c) Chris Clayton British Geological Survey borehole database (www.bgs.ac.uk/geoindex) 53 FOR PERSONAL USE ONLY (c) Chris Clayton Merging geotechnical & geological data Borehole data Land use Archaeology Contamination Obstructions Superficial geology Solid geology Hydrogeology Fence model 3D model 54 GSI3D from www.lithosphere.de FOR PERSONAL USE ONLY (c) Chris Clayton The way forward? Design strategy – Major projects “Project owners must recognise that there are certain types of projects that simply cry out for a more sophisticated approach to doing the subsurface portion of the work.” (from Brierley, 1998) • Use only when advanced geotechnical computation can yield major savings / gains. • Need for sophisticated sampling and testing • Advanced numerical modelling • International and flexible approach to procurement. • Partnering with ground investigation specialists. • University collaboration? 55 FOR PERSONAL USE ONLY (c) Chris Clayton Download a free copy of “Site Investigation” by Clayton, Matthews and Simons from www.geotechnique.info FOR PERSONAL USE ONLY (c) Chris Clayton