Lecture 11: MRP & JIT Material Requirements Planning Product

advertisement
Material Requirements Planning
Lecture 11: MRP & JIT


MRP provides a schedule: when each part or
component should be ordered or produced
produced.

MRP is driven by dependent demand.

MRP is a software system.
Just in time and lean systems
Just-in-time
– Pull vs. Push systems
– JIT requirements
– JIT in services

MRP (materials requirements planning ) is the logic
for determining how many units of each part and
component are needed and when they are needed.
M t i l requirements
Material
i
t planning
l
i
– Product structure tree, BOM
– MRP logic & Time fence


Readings: Chapters 18 & 13
Operations Management – Note11
Dr. Shenghao ZHANG
1
Operations Management – Note11
Dr. Shenghao ZHANG
2
Product Structure Tree & MRP Logic
Given the product structure tree and the lead time and demand
information, provide a materials requirements plan that defines
how many units of each component will be needed and when.
Product Structure Tree for Assembly A
A
B(4)
D(2)
C(2)
E(1)
D(3)
Operations Management – Note11
F(2)
Dr. Shenghao ZHANG
First, units of “A” are scheduled backwards to allow for the lead
time. So,, in the materials requirement
q
plan,
p , we p
place an order for
50 units of “A” on day 9 so as to “receive” them on day 10.
Lead Times
A
1 day
B
2 days
C
1 dayy
D
3 days
E
4 days
F
1 day
Day:
A Required
Order Placement
1
2
3
4
5
6
7
8
9
10
50
50
LT = 1 day
Demand
Day 10 50 A
Day 8 20 B (Spares)
Day 6 15 D (Spares)
3
Operations Management – Note11
Dr. Shenghao ZHANG
4
Repeating the process for all components, we have the
final materials requirements plan:
Next, we schedule the components of “A”. E.g., we need 4 B’s for
each A
A, so for 50 A’s
A s, we need 200 B’s
B s. The lead time is 2 days
days.
Day :
R e q u ire d
O rd e r P la c e m e n t
R e q u ire d
O rd e r P la c e m e n t
A
B
1
2
3
4
5
6
20
LT = 2
7
9
20
50
200
10
50
200
Spares
A
4x50=200
B(4)
D(2)
8
A
LT=1
B
LT=2
C
LT=1
D
LT=3
E
LT=4
F
LT=1
Day:
Required
Order Placement
R
Required
i d
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
Required
Order Placement
Operations Management – Note11
D(3)
F(2)
Dr. Shenghao ZHANG
D(2)
5

MRP programs are usually run every week for a planning
horizon that is 8 to 12 weeks long
long.

MRP is a cost effective formal planning & control system
but it requires commitment at all organization levels.

MRP is data intensive.
intensive Input data includes
– Master Production Schedule (MPS): the quantity and timing of
requirement for end items.
– Bill of Materials (BOM): the quantities of components required to
make each item (product structure trees).
– Inventory Status: inventory on hand, scheduled receipts, order
lead time, lot size, etc.
Dr. Shenghao ZHANG
3
4
5
6
20
7
8
9
20
50
200
10
50
200
100
55
20
400
55
400
20
200
100
300
300
200
200
200
B(4)
7
Part D:: Dayy 6
40 + 15 = 55
C(2)
E(1) D(3)
Operations Management – Note11
Firm orders
from known
customers
MRP: a computerized
p
planning
p
g system
y
Operations Management – Note11
2
A
C(2)
E(1)
1
F(2)
Dr. Shenghao ZHANG
Aggregate
product
p
plan
6
Forecasts
of demand
f
from
random
d
customers
Engineering
design
changes
Master
p
production
schedule
(MPS)
Inventory
y
transactions
Bill of
material
file
Material
p
planning
g
(MRP)
Inventory
record
file
Secondary
Seco
d y reports
epo s
Pi
Primary
reports
Exception reports
Planning reports
R
Reports
t ffor performance
f
control
t l
Planned order schedule for
inventory and production control
Operations Management – Note11
Dr. Shenghao ZHANG
8
Closed Loop MRP
Master Production Schedule (MPS)
Time-phased
Time
phased plan specifying how many units of each
end item the firm plans to build and when to build them.

Aggregate Production Planning
Master Production Scheduling
Material Requirements Planning
C
Capacity
it R
Requirements
i
t Pl
Planning
i
Aggregate Plan
(Product Groups)
No
Realistic?
Feedback
Feedback
Yes
MPS
(Specific End Items)
Operations Management – Note11
Dr. Shenghao ZHANG
Execute:
Capacity Plans
Material Plans
9
Types
yp of Time Fences

Operations Management – Note11
Dr. Shenghao ZHANG
Master Production
d i Schedule
S h d l Time
i Fences
Frozen
– No schedule changes allowed within this window

Moderately
Fi
Firm
Frozen
Moderatel Firm
Moderately
Flexible
Capacity
– Specific
p
changes
g allowed within p
product g
groups
p as
long as parts are available

10
Forecast and available
capacity
Firm Customer Orders
Flexible
– Significant
g
variation allowed as long
g as overall capacity
p
y
requirements remain at the same levels
8
15
26
Weeks
Operations Management – Note11
Dr. Shenghao ZHANG
11
Operations Management – Note11
Dr. Shenghao ZHANG
12
The Demand-Pull Logic
g of JIT
Just-In-Timee (JIT)
Jus
(J )







An integrated set of activities designed to achieve highvolume production using minimal inventories (raw materials
materials,
work in process, and finished goods).
Production is Just-In-Time
Just In Time ((“pull”)
pull ), not Just-In-Case
Just In Case (“push”)
( push ).
Elimination of waste in production effort.
Th timing
The
ti i off production
d ti resources ((e.g., parts
t arrive
i att th
the
next workstation “just in time”).
Ultimate goal: smooth and rapid flow
f
through the system.
“Big JIT” and “little JIT”
Invented in Japan, used in various forms in other cultures.
Fab
Vendor
Fab
Vendor
Fab
Vendor
Fab
Vendor
Sub
Customers
Finall
Fi
Assembly
Sub
Nothing
ot g gets produced
p oduced until
u t needed.
eeded
Need is created by actual demand.
A firm may have both “pull” and “push”.
Operations Management – Note11
Dr. Shenghao ZHANG
13
Operations Management – Note11

Specific product areas

Imported technologies

Efforts concentrated on shop floor

Focus on quality and reliability
Two central philosophies

Cooperative employee unions

Subcontractor networks
– Two bonuses a year in good times
– Respect
R
ffor people
l
– Elimination of waste
Operations Management – Note11
Quality circles
– Small group improvement activities (SGIA)
– Solution shared with management
– High productivity and low unit costs

Bottom-round management style
– Decision
D i i making
ki att llowestt llevell possible
ibl
– Avoid major R & D expenditures and risks

Level payrolls and secure employment
– No pay cut or layoff when business conditions deteriorate
– Workers as assets, not as human machines
– Automotive assembly and consumer electronics

14
Respect for People
The Japanese
p
Approach
pp
to Productivityy

Dr. Shenghao ZHANG
– Long term relationship; suppliers as part of the family
Dr. Shenghao ZHANG
15
Operations Management – Note11
Dr. Shenghao ZHANG
16
Minimizing Waste (I): Uniform Plant Loading
Waste in Operations
p
Waste is anything other than the minimum amount
which
hi h iis absolutely
b l t l essential
ti l to
t production.
d ti
Suppose we operate a production plant that produces a single
product.
d t The
Th production
d ti could
ld b
be accomplished
li h d using
i either
ith off th
the
two plant loading schedules below.
((1)) Waste from overproduction
p
Not uniform
(2) Waste of waiting time
(3) Transportation waste
Jan. Units
Feb. Units
Mar. Units
Total
1 200
1,200
3,500
3
500
or
4 300
4,300
9 000
9,000
Jan Units
Jan.
Feb Units
Feb.
Mar Units
Mar.
Total
3,000
3,000
3,000
9,000
(4) Inventory waste
Uniform
(5) Processing waste
(6) Waste of motion
(7) Waste from product defects
Operations Management – Note11
How does the uniform loading help save costs?
Dr. Shenghao ZHANG
17
Minimizing Waste (II): JIT Production
Operations Management – Note11
Dr. Shenghao ZHANG
18
Minimizing
g Waste (III):
( ) Inventoryy Reduction
Produce what is needed when needed and no more.
WHAT IT IS
• A management philosophy
• “Pull” system through the plant
WHAT IT DOES
• Attack waste
• Expose problems and bottlenecks
• Achieve streamlined production
WHAT IT REQUIRES
•
•
•
•
•
Employee participation
Industrial engineering/basics
Continuous improvement
Total quality control
Small lot sizes
Operations Management – Note11
M hi
Machine
downtime
Scrap
Work in
process
queues
(banks)
WHAT IT ASSUMES
Paperwork
backlog
• Typically repetitive manufacturing
• Stable environment
Dr. Shenghao ZHANG
19
Operations Management – Note11
Vendor
delinquencies
Engineering design
redundancies
Inspection
backlogs
Dr. Shenghao ZHANG
Change
orders
Design
backlogs
Decision
backlogs
20
JIT Requirements
q
(A):
( ) Design
g of Flow Process

Linked operations

Balanced workstation capacities

Reduced lot sizes

Reduced setup/changeover time

Preventive maintenance
Operations Management – Note11
Dr. Shenghao ZHANG
21
Level scheduling

Underutilization of capacityy

Freeze windows
Operations Management – Note11
Dr. Shenghao ZHANG

Build quality into the process

Worker responsibility

SQC (Statistical Quality Control) methods

Fail-safe methods
Operations Management – Note11
Dr. Shenghao ZHANG
22
JIT Requirements (D): Work with Vendors
JIT Requirements (C): Stable Schedule

JIT Requirements (B): Total Quality Control
23

Sharing of requirements schedule

Vendor representatives on the factory floor

Lead time reduction

Frequent deliveries

Quality expectations
Operations Management – Note11
Dr. Shenghao ZHANG
24
JIT Requirements (E): Improve Product Design

Standard product configuration

Reduced number of parts

Process design with product design
Operations Management – Note11
Dr. Shenghao ZHANG
25
JIT in Services

Problem-solving
gg
groups
p

Good housekeeping

Clarification of flows

Leveling of facility load

Demand-pull scheduling

Elimination of unnecessary
y activities

Quality at source and reliable process capabilities

Long term
term, cooperation with suppliers for mutual benefit

Etc.
Operations Management – Note11
Dr. Shenghao ZHANG
26
Download