Gaither/Frazier 9e Chapter 15 Chapter 15 15.4 a. Construct a product structure tree for Product A. Level Code A 0 1 B 2 F(2) 3 H(3) C(3) G D(2) H I(2) H(4) G(3) H Note: low-level-coded product structure tree will require dropping occurrences of item H in level codes 1 and 2 to level code 3. b. Prepare an indented bill of materials for Product A. 0 A 1 Level 2 3 B F H C G H D I G H H 15 - 1 Quantity 1 1 2 3 3 1 1 2 2 3 1 4 Gaither/Frazier 9e 15.6 Chapter 15 Complete the MRP schedule for the part below. Lot size = 2,000+ Lead time = 1 weeks On hand = 1,300 Safety stock = 400 Allocated = 300 1 2 Week 3 Gross requirements 1100 700 1500 900 1850 1400 Scheduled Receipts 2000 Available 2600 1500 800 1300 400 550 4 5 6 Net requirements 700 1450 850 Planned order receipts 2000 2000 2000 Planned order releases 2000 15 - 2 2000 2000 Gaither/Frazier 9e 15.8 Chapter 15 Complete an MRP schedule for the E subassembly and all of its components. Week ITEM E Lot size = Lead time = On hand = Safety stock = Allocated = 1 900+ 1 500 200 500 Gross Requirements Scheduled Receipts Available Net Requirements Planned Order Receipts Planned Order Releases G Lot size = Lead time = On hand = Safety stock = Allocated = 1500+ 1 400 Gross Requirements Scheduled Receipts Available Net Requirements Planned Order Receipts Planned Order Releases H Lot size = Lead time = On hand = Safety stock = Allocated = 1500+ 1 800 600 Gross Requirements Scheduled Receipts Available Net Requirements Planned Order Receipts Planned Order Releases I Lot size = Lead time = On hand = Safety stock = Allocated = 2000+ 2 800 500 500 Gross Requirements Scheduled Receipts Available Net Requirements Planned Order Receipts Planned Order Releases 1000 800 2 1000 3 700 4 900 5 800 800 200 900 700 800 900 900 900 900 900 2 3 1800 4 1800 5 800 800 1000 1500 1500 500 1300 1500 200 2 3 900 4 900 5 300 300 600 1500 900 2 3 900 4 900 900 900 900 1 1800 700 1100 700 1500 1500* 1 900 1000 1200 1500 1500 1 900 2000 1800 5 1100 900 2000 2000 * This order for 1500 units needs to be expedited to be available within the same week. 15 - 3 Gaither/Frazier 9e 15.9 Chapter 15 a. Prepare an MRP schedule for all the items to cover a six-week planning horizon. Product B353 Lot size = LFL Gross requirements Lead time = 1 Scheduled Receipts On hand = 340 Available Safety stock = 100 Net requirements Allocated = 50 Planned order receipts Planned order releases 1 2 750 190 190 560 560 560 1 Product R25 Lot size = LFL Gross requirements 2240 Lead time = 1 Scheduled Receipts On hand = 2500 Available 2300 Safety stock = 200 Net requirements Allocated = 0 Planned order receipts Planned order releases 1 Product N35 Lot size = LFL Gross requirements 1120 Lead time = 1 Scheduled Receipts On hand = 1500 Available 1285 Safety stock = 200 Net requirements Allocated = 15 Planned order receipts Planned order releases 1 Product K45 Lot size = LFL Gross requirements 1680 Lead time = 1 Scheduled Receipts On hand = 2000 Available 1720 Safety stock = 200 Net requirements Allocated = 80 Planned order receipts Planned order releases 1 Product B5 Lot size = 10000+ Gross requirements Lead time = 1 Scheduled Receipts On hand = 750 Available 200 Safety stock = 300 Net requirements Allocated = 250 Planned order receipts Planned order releases 14080 15 - 4 Week 3 0 4 1800 5 6 1500 0 1800 1800 0 0 1500 1500 1800 1500 2 3 7200 4 5 6000 6 60 60 7140 7140 0 0 6000 6000 0 7140 6000 2 3 3600 4 5 3000 6 165 165 3435 3435 0 0 3000 3000 0 3435 3000 2 3 5400 4 5 4500 6 40 40 5360 5360 0 0 4500 4500 0 5360 4500 2 14280 3 4 12000 5 6 200 14080 14080 0 0 12000 12000 0 0 12000 Gaither/Frazier 9e 15.9 Chapter 15 Continued Product F3 Lot size = 8000+ Gross requirements Lead time = 1 Scheduled Receipts On hand = 7600 Available Safety stock = 300 Net requirements Allocated = 100 Planned order receipts Planned order releases Product L7 Lot size = Lead time = On hand = Safety stock = Allocated = Product D9 Lot size = Lead time = On hand = Safety stock = Allocated = 1000+ 2 11000 1000 175 1 2 14010 7200 7200 6810 8000 8000 1 Gross requirements Scheduled Receipts Available 9825 Net requirements Planned order receipts Planned order releases 1000* (Need to expedite) 1 2000+ 2 25000 1000 200 Gross requirements Scheduled Receipts Available 23800 Net requirements Planned order receipts Planned order releases 3000* (Need to expedite) Week 3 1190 4 12000 5 6 1190 10810 10810 0 0 10810 2 10305 3 4 9000 5 6 9825 480 1000 8480 520 520 8480 8480 0 0 2 26800 3 4 22500 5 6 23800 3000 3000 22500 0 0 22500 22500 0 0 b. Are the MRP schedules for all items feasible from a material supply perspective? If not, what might be done? The MRP schedules for items L7 and D9 are not feasible. For item L7 it may be possible to use safety stock to resolve the problem. However, using safety stock will not resolve the problem for item D9. 3000 units of D9 must be expedited to meet the MPS for product B353, or else the MPS must be changed. 15 - 5