COURT OF APPEAL MALAYSIA (APPELLATE JURISDICTION) 5 CIVIL APPEAL NO. R-02-830-06 BETWEEN KRISHNAN NAIR & SONS … APPELLANT 10 AND KEN GROUTING SYSTEM SPECIALIST SDN BHD … RESPONDENT 15 Coram: Sulong Matjeraie, JCA Jeffrey Tan, JCA 20 T Selventhiranathan, JCA 1 GROUNDS OF JUDGMENT [1] This is an appeal by the Appellant against the decision of the learned High Court Judge handed down on 25th September 2007. 5 [2] The crux of this appeal relates to an agreement between the parties on Liquidated Ascertained Damages and whether the Respondent is entitled to be compensated on the agreed amount as provided in the contract. 10 Brief facts of the case [3] Pursuant to an agreement dated 21st January 1999, the Appellant was appointed as a sub-contractor by the 15 Respondent to carry out road works, clearing works, turfing works, construction of games court and drainage in respect of a project known as “The Construction and Completion of Teachers Training College at Kangar, Perlis” (‘sub- contract’). 20 [4] Clause 10.1 of the sub-contract provides as follows:“In the event that the works is delayed and partly or wholly due to your works, then KGSS shall recover any loss or expenses incurred 25 through the Liquidated Ascertained Damages. The Liquidated Ascertained Damages for this subcontract shall be for the amount of RM1,000.00 per day.” 2 [5] It was agreed therefore that the Respondent can recover loss and expenses from the Appellant through Liquidated Ascertained Damages which amounts to a fixed figure of RM1,000.00 per day of delay. According to Clause 9.1 of the sub-contract, the Appellant was required to complete the 5 contracted works by 25th February 1999. It is common ground that the Appellant only completed the contracted works on 30th September 1999. 10 [6] The Appellant commenced an action in the High Court for outstanding payments due and payable under the subcontract. The Respondent, among other things, counterclaimed a sum of RM217,000.00 being Liquidated Ascertained Damages for every day of delay in completing the contracted works calculated from 25th February 1999 to 15 30th September 1999. [7] At the High Court, the learned High Court Judge allowed both 20 the Appellant’s claim and the Respondent’s counterclaim of RM217,000.00. The Appellant’s appeal before us is only in respect of the award on the Respondent’s counterclaim by the learned High Court Judge. 25 3 [8] Before us, a majority decision was reached on the appeal. Justice T Selventhiranathan and I were in the majority while Justice Jeffrey Tan dissented. We now give the reasons for the decision of the majority. 5 [9] There are three main grounds of appeal in the Memorandum of Appeal and these are as follows:- (i) The learned High Court Judge erred in concluding that Clause 10.1 of the sub-contract was a Liquidated 10 Ascertained Damages clause and not a penalty. (ii) The learned High Court Judge erred in concluding that the Respondent need not prove actual loss as required by the Federal Court decision in Selva Kumar a/l 15 Murugiah v Thiagaraj a/l Ramasamy [1995] 1 MLJ 817. (iii) The learned High Court Judge erred in concluding that the Respondent need not give notice to the Appellant before making a counterclaim. 20 [10] To dispose of the third ground of appeal first, we note that there were two letters at pages 212 and 213 of the Appeal Record dated 8th October 1996 and 6th December 1996 25 respectively from the Respondent giving notice to the Appellant of their intention to make a counterclaim. 4 [11] The learned High Court Judge made a finding in his judgment at page 614 of the Appeal Record that the Liquidated Ascertained Damages clause is not a penalty clause. As to whether Clause 10.1 of the sub-contract is a 5 penalty or Liquidated Ascertained Damages provision is no longer an issue in view of section 75 of the Contracts Act 1950 (‘the Act’) and the case of Selva Kumar (supra) in that both are recoverable subject to proof of reasonable compensation, whether or not actual damage or loss is 10 proved to have been caused thereby. Section 75 of the Act says – “When a contract has been broken, if a sum is named in the contract 15 as the amount to be paid in case of such breach, or if the contract contained any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not 20 exceeding the amount so named or, as the case may be, the penalty stipulated for.” (Emphasis added) The words “whether or not actual damage or loss is proved 25 to have been caused thereby” (‘the words in question’) was considered by Peh Swee Chin FCJ when his Lordship delivered the judgment of the Court in Selva Kumar (supra). It was the view of his Lordship that the words in question must be given a restricted construction. Hence despite the 5 words in question, a Plaintiff who is claiming for actual damages in an action for breach of contract must still prove the actual damages or the reasonable compensation in accordance with the settled principles in Hadley v Baxendale (1854) 9 Exch 341; [1843-60] All ER Rep 461. Any 5 failure to prove such damages will result in the refusal of the court to award such damages. [12] 10 For ease of reference pages 827 onwards of the said judgment of Peh Swee Chin FCJ are reproduced in extenso hereunder:“But what is far more interesting in that case is that the Indian Supreme Court, when referring to the words in question, i.e. “whether or not actual loss or damage was proved to have been caused 15 thereby” stated that the words in question were intended to cover 2 kinds of contracts. In the first kind, the Court would find it very difficult to assess such reasonable compensation. In the second kind, the Court could access such reasonable compensation with settled rules. Such dichotomy of contracts by the Indian Supreme Court 20 represents, in our view, a logical basis for the words in question, words added by the legislature to the section in question without seemingly any thoughtfulness about the desirability of some appropriate limitations thereto. We agree with the Indian Supreme Court’s dichotomy of such contacts. 25 Secondly, we therefore further hold that the words in question viz. “whether or not actual damage was proved to have been caused thereby”, are limited or restricted to those cases where the Court would find it difficult to assess damages for the actual damage or 30 loss as distinct from or opposed to all other cases, when a plaintiff in each of them will have to prove the damages or the reasonable compensation for the actual damage or loss in the usual ways. 6 However, there remains to be done further work, for their Lordships in the Indian Supreme Court did not identify or elaborate the contracts of the kind for the breach of which the Court finds it difficult to assess damages or “the reasonable compensation” for actual loss 5 or damage. The search will have to continue for the precise attributes of this kind of contract. Conceivably the archetype of cases of the kind just mentioned, in our view, is undoubtedly the well-known case of Chaplin v Hickso [1911] 2 10 KB 786; [1911-13] All ER Rep 224. In that case Miss Chaplin, an actress agreed with Hicks, a theatrical manager, for Miss Chaplin to be at a meeting for him to interview her and also 49 other actresses where he could select 12 out of such 50 actresses for giving remunerative employment to. He was in breach of contract for not giving Miss 15 Chaplin a reasonable opportunity to attend the interview. It was also argued for him in the Court of Appeal that only nominal damages were payable and the award for substantial damages by the High Court was wrong. The submission of nominal damages was to the effect that she would have had only a chance of one in four of being 20 successful, a chance which itself further depended on the imponderables. The argument for nominal damages was rejected by the Court of Appeal and the High Court’s award was upheld. Very clearly Miss Chaplin failed to prove the damages for the actual 25 damage i.e. the amount of such damage or loss, and one may query as to why she should be given substantial damages and not merely nominal damages as would have been seemingly and normally the case. We feel we ought to explain even further below. 30 A few words may first be necessary to explain the nature of nominal damages, which are damages, say RM10, (traditionally of about 40 shillings in England), which could be awarded in each and every breach of contract, in the absence of actual loss or damage, inherently in such a case, or alternatively in the absence or failure of 35 proof of such actual loss or damage. 7 To revert to the poser above about Miss Chaplin, basically, the evidence in Miss Chaplin’s case indubitably suggested a real loss, a loss that was not too remote, going by the rules in Hadley v Baxendale [1854] 9 Ex. 341; [1843-60] All ER Rep 461, but at the same time it was 5 quite difficult to assess the damages or the amount of money that should be given to her for such loss of such opportunity to be selected. In a good number of cases, rules for quantifying amounts of money 10 for damages have evolved in Courts for some but not all but not all types of cases, in other words, a measure of damages for some of these cases has been respectively established e.g. the measure of damages in a sale of goods being the difference between the market value and contract price etc. However, a measure of damages i.e. a 15 settled rule for assessing damage, has not been developed for cases of the type of Miss Chaplin’s and such measure for her case has still not been established, it would still be left to the good sense and fair play of the Court to fix a reasonable amount as compensation. Thus, it will mean that for lack of an established measure of damages in any 20 particular case, the case will be one in which the Court finds it difficult to ascertain the amount of actual loss or damage. The Court will not shirk its duty, however, when such actual loss or damage is manifested from the evidence and it is not too remote, to find a reasonable sum for the Plaintiff. 25 It is significant to add that there are cases of contract in which evidence therein shows there can be no real loss inherently and in such event, nominal damages will be the only damages for judgment obtained by a successful plaintiff either to use it “as a peg to hand his 30 costs on”, or to establish a right or a declaration of right. It is not difficult to imagine such a case when the evidence shows clearly there can be no real loss. For illustration, for such a case clearly showing no real damage or 35 loss where nominal damages would be the only remedy, let us say, eg. that A, a doctor promises to examine the next day, B, a regular patient of his, who is very keen to have A examine him routinely on 8 the following day, A fails to do so the next day. Here A is in breach of contract; but the evidence here clearly shows no actual loss or damage. Whether in any particular case the evidence shows any real damage or not appears to be largely a matter of common sense. 5 Thirdly, therefore, we hold that the precise attributes of such contracts in which it is difficult for a Court to assess damages for the actual damage or loss are cases where there is no known measure of damages employable, and yet the evidence clearly shows some real 10 loss inherently and such loss is not too remote, then the Court ought to award, not nominal damages, but instead, substantial damages not exceeding the sum so named in the contractual provision; a sum which is reasonable and fair according to the Court’s of good sense and fair play. 15 Fourthly, we hold that in any case where there is inherently any actual loss or damage from the evidence or nature of the claim and damage for such actual loss is not too remote and could be assessed by settled rules, any failure to bring in further evidence or to prove 20 damages for such actual loss or damage, will result in the refusal of the Court to award such damages despite the words in question.” [13] In this instant case we are of the view that the losses suffered are all measurable: “over head”, “machinery cost”, 25 “delay in receiving payment”, “interest” and “goodwill” could reasonably be assessed. However, the learned High Court Judge said at paragraph 34 in page 612 of the Appeal Record thus: 30 “Menurut peguamcara Defendan kerugian sedemikian adalah sukar untuk dibuktikan secara terperinci.” 9 (Our translation: “According to the counsel for the Defendant such loss is difficult to prove in detail.”)(‘those words’) 5 [14] However, learned counsel for the Respondent, Mr. Choong Fui-Yu, admitted that he was unable to show to this Court exactly in the evidence where those words were conveyed to the High Court. Although considerable effort had been made, in earnest, to locate those words in the notes of proceeding, we are satisfied that no phrase containing those 10 words was found in the evidence. [15] The Respondent also failed to produce any documentary evidence of the actual loss suffered and could not therefore, based on the authority of the above cited Selva Kumar 15 (supra), be entitled to claim under the Liquidated Ascertained Damages clause. It is interesting to point out here that the ultimate employer to the sub-contract, i.e. the Government of Malaysia, did not impose any Liquidated Ascertained Damages on the Respondent. Likewise there is 20 therefore no reason why the Appellant should now be required to pay Liquidated Ascertained Damages to the Respondent. 25 [16] Further it may be necessary to point out here that the term “the goodwill” mentioned by the learned High Court Judge at page 612 of the Appeal Record was not substantiated in 10 the evidence of the Respondent either. In the event “the goodwill” appearing in the judgment of the learned High Court Judge was not proved either. 5 [17] We are of the considered view that by virtue of the doctrine of stare decisis we are compelled to stand by and follow what has been decided by the Federal Court in Selva Kumar (supra). What Arifin Zakaria FCJ (as his Lordship then was) said in Johor Coastal Development Sdn Bhd v Constrajaya Sdn Bhd [2009] 4 MLJ 445 at page 460 fortified our view 10 when he reaffirmed that “…I am of the view that Selva Kumar is still good law.” [18] 15 For the above reasons, we allowed the appeal with costs and set aside the order of the learned High Court Judge in respect of the counterclaim of RM217,000. 20 Sulong Matjeraie Judge, Court of Appeal Malaysia 3rd August, 2010. 25 11 Counsel for the Appellant: 5 10 Mr Murali Achan M/s Devandran & Co. Advocates & Solicitors No. 12B, Tingkat Atas Lorong Seruling Kompleks PKNPs 01000 Kangar Perlis Counsel for the Respondent: 15 Mr Choong Fui-Yu M/s Gananathan Loh Suite 9-1, Level 9, Wisma UOA Damansara II No. 6, Changkat Semantan Damansara Heights 50490 Kuala Lumpur 12