Evolution of Long-Term LNG Sales Contracts: Trends and Issues Philip R. Weems, Partner, King & Spalding LLP During the 40+ year history of the LNG industry, customs and practices have developed with regard to documenting long-term LNG sales (“SPAs”). Although the foundational approach to SPAs has, in general, remained unaffected since the first contracts of the early 1960’s, market changes, fresh challenges and new players are resulting in approaches to contractual terms that may differ from the “traditional” LNG way. While clearly much can be learned from past LNG precedent, present circum-stances may necessitate a different course than in past SPAs. This article will review common alternative drafting and risk-sharing approaches as well as changes to contracting practices for representative Asian and Atlanticbasin SPAs, with an emphasis on contractual and legal issues rather than purely commercial concerns. In preparation of this article, the author examined many, but not all, of the SPAs signed during the relevant period, including: 3 from the 1960’s; 11 from the 1970’s; 9 from the 1980’s; 17 from the 1990’s; and 21 since 2000. These SPAs are from 14 existing or planned exporting nations (and 2 nations which hoped to do so but the projects were cancelled) and 9 existing or planned importing nations. Given the task of reviewing four decades of experience and the necessary brevity of this article despite the intricacy of the subject matter, the following is intended to be an overview, rather than a comprehensive discussion, on the evolution of certain key SPA issues. 1960’s Compared to the 14 long-term SPAs executed in 2004, relatively few SPAs were signed in the 1960’s. In fact, long-term sales were limited during this decade to Alaskan sales to Japan and Algerian sales to the United Kingdom and France. The LNG lawyer of today would first notice the brevity of SPAs of the 1960’s.1 These SPAs were 20 to 30 page documents with guiding contractual principles rather than the detailed (sometimes overly) clauses we now see. In these initial contracts, perhaps due to the fact that financing was not provided by third parties, no real trend was established with respect to the choice of law. The choice of contractual 2 law was wide, from Algerian law to Japanese law to no choice of law at all (relying instead on empowering the arbitrators to act as “amiables compositeurs” and thereby permitting the arbitrators to decide the dispute according to the legal principles they believe to be just, without being limited to any particular national law). Arbitration of disputes, rather than litigation, by three arbitrators was already the norm, with the International Chamber of Commerce rules applying and the place of arbitration being Geneva, Zurich or Tokyo. In these early days of the LNG industry, not all SPAs were stated in terms of take-or-pay; instead, the simple obligation to purchase the quantity appears to have been 1 For a discussion of principles guiding the choice of contractual structures for LNG export projects and further background on terms of SPAs, see Weems, "Overview of Issues Common to Structuring, Negotiating and Documenting LNG Projects," International Energy Law and Taxation Review (Issue 8, 2000) (available at www.kslaw.com/practice_areas/energy/publications.asp). 2 The choice of law under the oldest SPA (signed on December 12, 1961 between British Gas Methane Limited and Compagnie Algerienne de Methane Liquide) is not known. This SPA expired in 1979. the only necessary requirement: “The annual contract quantity of LNG which Sellers agree to sell and deliver to Buyers, and which Buyers agree to receive and pay for under this Agreement for each contract year … is [____] billion Btu’s…. [C]argoes of LNG shall be delivered and received during each contract year at rates and intervals and volumes which are reasonably equal and constant.” The term of SPAs was 15 years in two instances and 25 years in the other. It was not unusual for the term of the contract to be extended at Buyer’s election if an event of force majeure prevented the delivery of the minimum contract quantity. As these contracts pre-dated the 1973 Oil Crisis, pricing was relatively fixed. The following illustrates the three methods of pricing in these early agreements: ● $0.52 per MMBTU delivered ex ship. ● A price based on (a) the value of the natural gas (determined based on the value of heavy fuel No. 2 from certain Mediterranean and Atlantic refineries and based on wholesale coal prices as published by the French Institute of Statistics); plus (b) the cost of liquefaction (pursuant to a separate liquefaction agreement) and indirect taxes. $0.305 FOB, escalated annually for certain U.S. inflation. ● The “most-favored nation” pricing concept found its way immediately into Japanese contracts through clauses requiring that “if in the future another [LNG] project is placed into operation to supply Japan … under similar conditions such as volume, distance, liquefaction, and ocean transportation techniques, contract term and so forth, sellers will hold a discussion with Buyers concerning the price … and shall endeavor to find a solution satisfactory to all parties concerned.” Noting that each party has the obligation to act in “due regard for appropriate safety precautions,” one SPA introduced the following concept of liability in relation to LNG tankers: “While the LNG tanker is [at berth at Buyer’s terminal]…, Buyers shall indemnify Seller for any injuries or damages they may suffer as a result of the negligence, or willful and malicious acts of Buyers, their agents, employees, contractors and suppliers of labor and materials and their employees while performing services for Buyers.” A mirror indemnity of Buyer for sellers’ negligence, etc. was likewise included. Additional observations regarding SPAs of the 1960’s are as follows: ● In one contract, there was an obligation to use “best efforts” to obtain government approvals within 60 days; otherwise, either party could terminate the SPA with no liability. ● Few specifics are included regarding the facilities to be constructed by either seller or Buyer. In one contract, the port charges payable by Buyer for use of seller’s loading port are frozen for the term (25 years) at the rate existing on July 15, 1969. ● Two SPAs are silent on demurrage (with one simply stating that “Sellers and Buyers shall cooperate in their efforts to unload an LNG tanker within 17 hours after docking”) while one SPA includes a demurrage rate fixed at $24,000 per day. ● ● In one contract, if a default in the performance of any obligation under the SPA occurs and is not remedied in 60 days, the non-defaulting party is entitled to terminate the contract. In general, seller bears the risk of taxes imposed by the export country while buyer bears the risk of taxes imposed by the importing country; but in one SPA if any new income or product related taxes are imposed on seller, buyer is obligated to reimburse seller for 75% of the amount of taxes payable, provided that such recovery is not prohibited by law. ● ● In one contract, force majeure is deemed to include serious accidental damage to the principal pipelines leading from the regasification facilities and to the principal pipeline systems transporting gas to buyer’s “Principal Customer” (defined as any customer who buys at least 10% of the annual contract quantity sold under the SPA). However, whenever the force majeure event ceases, the quantities of LNG not delivered due to force majeure must be sold or purchased as “make-up” quantities in the shortest possible time. Each SPA is silent on (i) damages payable in the event of a failure to purchase or sell; (ii) obligations with regard to off-spec LNG; and (iii) financial security to be provided by either seller or buyer. ● 1970’s By the end of the 1970’s, SPAs had been signed by several other suppliers, including Brunei, Indonesia, and Abu Dhabi. 3 Moreover, Iran sought to become a supplier and in 1978 executed an SPA for proposed LNG sales to Columbia LNG in the U.S. New importers signing SPAs in the 1970’s included European buyers in Italy and Spain and U.S. buyers constructing terminals on the East Coast of the United States as well as Pacific Lighting in California (who proposed to construct a terminal in California to receive Indonesian LNG4). Global LNG Routes (1977) In Operation (or Approved by U.S. Authorities) 5 Many of the SPAs completed during the 1970’s continued to be rather succinct documents of between 25 and 40 pages; however, a few began to become more detailed and to cover issues not addressed in prior agreements. For example, the 1973 SPA between Pertamina and its five Japanese purchasers (known as the “Western Buyers”) approached 100 pages, while the 1978 Agreement for the Sale and Purchase of Liquefied Natural Gas between the National Iranian Gas Company, as seller, and Columbia LNG Corporation, as Buyer, was almost 80 pages. Ample variety continued to be reflected in the choice of law to govern the SPA, including the laws of Japan, France, New York, and Iran; interesting selections were the choice of the laws of the “United Kingdom” (rather than of England) in the 1976 Sonatrach - Distrigas SPA and the decision in the 1973 Pertamina - Pacific Lighting SPA to apply “generally recognized principles of private international law, custom and practice.” International Chamber of Commerce arbitration rules were almost universally chosen during the decade, with venue of the arbitration being in Japan, Paris, Geneva or Zurich; the lone exception was the National Iranian Gas Company SPA in which the parties selected arbitration in Tehran under Iranian arbitration procedures. It was during the 1970’s that a contractual term of 20 years was established as the norm. More than one contract during this time dealt with the complication of splitting the quantity obligation between multiple buyers. In most instances, no credit support was deemed necessary to guarantee the obligations of the party executing the SPA. Nonetheless, with the unusual choice of a company based in Bermuda to serve as seller under the 1970 Brunei - Japan SPA, the precedent of a full guarantee of seller’s obligation was established as Shell Petroleum N.V. and Mitsubishi Shoji Kaisha, Limited also signed the SPA as “Guarantors”, agreeing that “[i]f Seller fails so to perform any of its obligations under the Agreement, the Guarantors, acting jointly and severally with each other, shall themselves ensure the performance of the obligations in question and shall perform the obligations as Guarantors.” The use of take-or-pay clauses developed into a standard practice. Generally, the buyer’s obligation to purchase was stated as an annual quantity obligation, but in one instance the buyer was required to take in each quarter "at least 97% of one-fourth of its [annual contract] Quantity.” Pricing of LNG remained full of variety, with approaches such as: ● $0.486 per MMBTU, delivered by seller on an ex ship basis. ● 3 An ex ship price divided into an “LNG Abu Dhabi is not reflected on the U.S. government's map, as the trade commenced later in the decade. 4 For more information, see Weems and Keenan, "Greenfield LNG Import Terminal Approvals," LNG Journal (May-June 2002) (available at www.kslaw.com/practice_areas/energy/publications.asp). 5 Transportation of Liquefied Natural Gas, Office of Technology Assessment, Congress of the United States (1977). Element” based on crude oil export prices and a “Transportation Element” (with the LNG Element having a minimum LNG price of $0.99 per MMBTU [escalating at an agreed rate] and the Transportation Element being $0.30 per MMBTU [escalating based on changes in seller’s actual cost of transportation payable to its transporter]). $0.63 FOB, adjusted for changes in a basket of currencies but not to be less than a stated minimum price. ● ● The higher of the base price (set initially at $1.30 FOB) or a “Floor Price,” with monthly adjustments to the base price based on changes in certain fuel oils and semi-annual adjustments to the Floor Price based on changes in a basket of European exchange rates. ● The higher of the base price (set initially at $1.50 FOB) or a “Floor Price” (escalating at an agreed rate), with semi-annual adjustments to the base price to be based on crude oil export prices and on U.S. inflation. These different approaches to pricing were obviously influenced by major changes in oil pricing from 1973 onward. Uncertainty about pricing in the buyer’s market led to the adoption of perhaps the first LNG price review clause (governed by the laws of the “United Kingdom”). This clause (i) required the parties to meet every four years; (ii) required the parties to adapt the price “in a reasonable and fair manner to the economic circumstances then prevailing on the imported Natural Gas market and on the market for other imported energy supplies competing with this product in the East Coast and Gulf Coast areas of the [U.S.] within the framework of long term contracts;” (iii) provided for arbitration to determine the price revision if the parties could not reach agreement in 90 days; and (iv) provided that no arbitration award on price revision would become effective until approved by governmental authorities “having jurisdiction in the countries of the parties.” As had been the practice in the 1960’s, specific remedies applicable to non-performance were not included (aside from the ability in one contract to terminate the contract if non-performance is not remedied in 60 days). Therefore, remedies for seller non-performance were based to a great extent on the underlying choice of law (such as the Uniform Commercial Code Article 2 when New York law was chosen). A 1970 SPA confirmed the view of take-or-pay as seller’s exclusive remedy by stating that “in respect of non-fulfillment by any Buyer of its obligations to take delivery of LNG hereunder, Seller shall … rely solely on the remedy afforded by [the clause requiring buyer to pay the shortfall at the contract price].” Although the 1973 Pertamina - Pacific Lighting SPA ensured that the obligations to sell and purchase LNG were not effective until satisfaction of certain conditions precedent, the maximum 30 month period to obtain U.S. approval to import LNG and to obtain financing of Pacific Lighting’s import facilities proved, in hindsight, to be a major underestimation. In fact, it was not until 1981 that Pacific Lighting abandoned its hope to obtain California approval of the siting of the import terminal. In another Indonesian contract, although no conditions precedent were included, seller obtained the right to terminate the SPA if it was unable to obtain, within six months, “firm and binding commitments from Japanese lenders… on terms satisfactory to Seller, for financing of construction of [the port and liquefaction facilities].” Destination restrictions were common, reinforced often through the requirement that ships be dedicated to trading between seller and buyer. Limited rights to alter the receiving terminal were incorporated into a few SPAs, such as the following provision: “The scheduled port of destination is the port of Boston (Massachusetts) where Buyer has now at its disposal the required facilities…. However, Buyer shall have the right to designate any safe port on the East Coast of the United States of America, subject to the designation being notified to Seller in writing at least 15 days prior to the scheduled date of delivery; provided, however, that all required authorizations and permits, and any delay which may result therefrom, shall be the responsibility of the Buyer; provided also that the sales price stated … shall be adjusted in such case to take into account the variations in the length of the voyage and any additional costs which would be incurred as a result therefrom.” Additional observations regarding SPAs of the 1970’s are as follows: A distinguishing characteristic between force majeure under some Asian SPAs and those from ● other regions was introduced in 1973 with one Asian contract deeming force majeure to include “[t]he reserves of natural gas in [certain named fields] which can economically be produced for purposes of this Contract have been fully depleted.” In one instance under an ex ship SPA, even if the buyer was excused from purchasing LNG due to a buyer force majeure, the buyer was nonetheless obliged to pay certain transportation costs incurred by seller during the force majeure. ● Australia (and a failed potential supplier, Dome Petroleum Limited of Canada). On the importing side, South Korea began its big push into LNG by signing ex ship agreements with Indonesia, while new buyers in Belgium and Taiwan also joined the industry. Most of these contracts were for a term of 20 years, although Algeria’s SPAs with France were 25 year agreements. The average length of SPAs began to approach 75 pages (though Algerian SPAs continued to fall in the 40 page range). Tax risks continued to be divided based on the concept that seller bears the risk of taxes imposed by the export country while buyer bears the risk of taxes by the importing country. In one instance, buyers agreed to an equal sharing of seller’s increased natural gas or freight taxes outside of the importing country, provided seller had exercised “reasonable diligence” to avoid the increase or new imposition of taxes. ● ● Not all SPAs included the obligation to pay demurrage if loading (or unloading) of a particular cargo was delayed. Furthermore, in other agreements, cargoes loaded/unloaded quickly over the year were netted against cargoes loaded/delayed over the same year, in order to determine any demurrage payable. Scheduling of deliveries was to be at rates and intervals reasonably equal and constant throughout the year. In a precedent setting move that is, with increasing frequency, today challenging receiving terminal operations with multiple users, different scheduling years evolved during this decade. For example, a contract year of April 1 to March 31 was established in the 1970 Brunei Japan SPA while a contract year of January 1 to December 31 was set in both the 1973 SPA between Indonesia (Pertamina) and the Western Buyers and in the 1976 SPA between Algeria (Sonatrach) and Distrigas of the U.S. ● ● A few SPAs addressed liabilities in relation to an accident occurring while loading (or unloading) of an LNG tanker. When such liability was addressed, the negligence, willful misconduct or intentional act of the party or its agents (including the LNG transporter) was the determining factor, with no stated financial limit for such liability exposure. 1980’s Indonesia and Algeria dominated this decade, signing the vast majority of executed SPAs.6 However, the 1980’s did see the emergence of new supplies from Malaysia and It should be noted that the first major dispute on a SPA occurred during this period, when the Algerian government refused to approve the LNG pricing authorized by U.S. agencies, leading to various disagreements on pricing which led to the eventual termination (or renegotiation) of most Algerian SPAs providing for deliveries to U.S. terminals.7 Gas competition issues began to influence the structuring approach to SPAs. For the first time, multiple participants in one joint venture chose to execute separate, parallel SPAs with each buyer. However, because performance of the multiple SPAs was to occur simultaneously from an operational standpoint, the parties agreed in each SPA that the “LNG to be sold and delivered to each Buyer under [the SPA] shall be sold and delivered commingled with LNG to be sold and delivered by [named other sellers] to each Buyer under the other sale and purchase agreements concluded between Buyer and the Other Sellers.” Each of the multiple SPAs deems a set portion of each commingled cargo to be from the respective seller. This decade saw much less variety in the choice of law to govern the SPA, with English law and New York being almost the exclusive choices. Although the ICC arbitration rules were still chosen on several occasions (with the arbitration to be held in either Paris or New York), for the first time the UNCITRAL Rules, adopted in 1976, were also utilized (with hearings to be in Geneva or New York). In one unique provision in the 1981 Arun II Trade SPA signed between Indonesia and Japanese buyers, the place of arbitration was agreed to be Paris; yet, the SPA provides that if Pertamina had, at the time of its dispute with the Japanese buyer, another ongoing arbitration in Paris with another LNG purchaser and if arbitrating in Paris could require Pertamina to take “mutually contradictory actions in its respective disputes,” then the place of arbitration would be moved to New York. Take-or-pay clauses remained, typically on an annual basis but in at least two instances on a quarterly basis. In the first part of the decade, buyers had little ability to reduce their take-or-pay amount (and in some cases the reduced amount had to be re-taken within a certain number of years via socalled “Make-Good” provisions). Interestingly, as the decade drew to a close and lower oil prices brought on more of a buyer’s market for LNG, buyers enjoyed more flexibility to increase or decrease annual take-or-pay amounts. Pricing of LNG generally followed existing approaches; for example: ● An initial price of $5.78 per MMBTU, FOB, based on a 1981 crude oil export price of $35.69, with annual adjustments for changes in such export prices. A price determined, in part, on the average landed price, in dollars, of “all other liquefied natural gas on long term contracts being imported into Japan,” and the “actual figure shall be determined prior to the first delivery of LNG in a fair and reasonable manner.” The remaining portion of the price was to be based on the Japanese Crude-oil Cocktail, a weighted average landed price of all crude oil imported into Japan during a “reasonable period to be agreed.” ● ● An ex ship price divided into an “LNG Element” based on crude oil export prices and a “Transportation Element” (with the LNG Element having a base LNG price of $4.284 per MMBTU and the Transportation Element having a base price of $0.47 per MMBTU (escalating at an agreed rate)). Price review clauses, if included, were typically only an obligation of the parties to review the price “in good faith in the light of all the circumstances relevant at the time;” the contract price would only be changed if the parties agreed to do so. Continuing the practice in the 1960’s and 1970’s, few specific remedies applicable to seller’s non-performance were built-in. If a clause dealing with remedies was inserted, it was typically along these lines (in both English law and New York law governed SPAs): “[Subject to Buyer’s liability for any take-or-pay deficiency], the Seller shall be liable to either Buyer and either Buyer shall be liable to Seller for loss and damage which has been suffered as a result of the breach by the party liable of any one or more of its obligations hereunder, to the extent that the party liable should reasonably have forseen the loss or damage.” An important development occurred when the initial Japanese FOB buyers from Indonesia insisted that a liability regime for LNG accidents at the loading port be incorporated into the SPA. Accordingly, a 1981 Indonesian SPA added a multi-page exhibit of “principles” for determining the liability of the “shoreside interests” and of the “LNG vessel interests” in the event of an LNG “incident.” These SPA principles obligated the parties to agree to separate “Omnibus and Waiver Agreements,” governed by English law and subject to the jurisdiction of the High Court of Justice in London, overriding the existing Conditions of Use the Master of the LNG vessel was required to sign upon entry of the vessel into the Indonesian port. Under these liability principles the parties set the liability limit of the LNG vessel owner at $150 million, a limitation of liability which was to “continue in effect for as long as the [vessel] Owner can obtain customary P and I Club cover for the risk.” Somewhat surprisingly, although almost 25 years has elapsed since the port liability limit for vessel owners was established in Indonesia, the $150 million liability limit has not been increased; recent SPAs have also adopted this limit for other LNG ports, based in part on the view that higher liability coverage is not yet available from P&I Clubs insuring LNG vessels. Additional observations regarding SPAs of the 1980’s are as follows: ● In at least one instance, the SPA had a hardship clause which (in recognition that the SPA was a long-term contract that the parties intended to be “fair and reasonable for its full term”) obligated the parties to make, in a “spirit of mutual understanding and cooperation,” mutually acceptable revisions to the SPA to eliminate any substantial hardship suffered from a change in circumstances. Tax clauses in some instances became more comprehensive. For example, some clauses required seller in ● ex ship contracts to not take any action which would lead to seller having a permanent establishment in buyer’s country. In place of an unrestricted indemnity for taxes in the buyer’s country, in some cases the seller agreed to “use its best efforts to cease to be subject to [the importing country’s] income tax, by appropriately reordering its affairs connected with the performance” of the SPA. ● As a result of a disputed force majeure event centered on whether a party could claim force majeure if an employee caused an accident due to its negligence, a few contracts entered into late in the decade were amended to remove the “outside the reasonable control of the party” requirement. In its place, force majeure was deemed to also comprise, for example, any serious accidental damage to a facility unless it resulted from the “willful negligence” on the part of the party’s management. ● Moreover, several SPAs began to address the possibility of extended force majeure, providing either that the other party had the right to terminate the SPA after a set period (2 to 3 years) or, in the case of seller, to sell otherwise undeliverable LNG to third parties if the force majeure had exceeded 9 months. “Non-utilization provisions” first appeared during this period to address the exposure of the shipping party to un-reimbursed transportation costs if the other party suffered a force majeure. Under some SPAs, the party claiming force majeure would in certain instances still be required to make payments during the force majeure in an attempt to make the other party whole for the cost of its unused, dedicated LNG shipping fleet. ● ● Most favored nations pricing provisions were not uncommon, with the stated purpose in one instance being to “maintain comparability between the Contract Sales Price under the [SPA] and prices payable under the Japanese Contracts” existing on the date of the SPA. The rise in project financed liquefaction facilities resulted in more provisions aimed at ensuring that seller’s revenues are not unnecessarily interrupted. An example is the disputed force majeure clause in one SPA of this period that required buyer to continue to pay in full, to an escrow account at a bank in a neutral country, for the contractual quantity of LNG regardless of buyer’s assertion that buyer is excused from taking LNG due to a force majeure event. ● 1990’s The 1990’s saw a steep rise in developments affecting the LNG industry, with SPAs being signed by new exporters in Qatar, Oman, Nigeria and Trinidad and by new importers in Turkey, Puerto Rico and Greece. In the first part of the decade, Asian suppliers (particularly Indonesia8, Malaysia and Qatar) signed, renewed or substantially amended a multitude of SPAs with principally Japanese, South Korean or Taiwanese buyers. On the other hand, the second half of the decade witnessed the re-birth of U.S. LNG imports, increases in supplies to Europe and the emergence of the Middle East as a key Asian supplier. The decade also saw, in dollars terms, the largest contractual dispute to date on an SPA. ● Destination restrictions existed, either expressly in the SPA or practically due to transportation limitations and location specific pricing provisions. For example, one ex ship SPA stated if buyer made an “emergency need” request, seller may, in its discretion, agree to change the place of delivery to another port in the same country as the buyer. ● Again, not all SPAs included the obligation to pay demurrage if loading/unloading of a cargo was delayed. One ex ship SPA simply required the parties to discuss in good faith how to distribute any additional costs incurred by a party as a result of a delay in berthing, unloading or departing. 11 For the Indonesian perspective on contractual and legal issues associated with SPAs, see A. Nasution, Special Advisor to Pertamina President Director, "Allocating Price Risk in LNG Sales Contracts" (IBA Energy Law Conference, The Netherlands, 1990). To contrast the Indonesian seller's view with the Japanese buyer's approach, see Greenwald, "LNG Export Projects to Japan: The Purchaser's View" (IBA Energy Law Conference, The Netherlands, 1990). The length of SPAs signed during the 1990’s continued to vary, in part based on the style of the draftsmen; while a few remained in the 50-60 page range, several exceeded 80 pages and one SPA, in a rather odd example for a major project that did not proceed after signing, exceeded 175 pages. With an average length reaching around 90 pages, most agreements were for a 20 year term, but at least two Middle East SPAs had a term of 25 years. None of the SPAs from this decade that were reviewed for this article had a governing law other than New York or England. Although the number of SPAs governed by New York law exceeded that of English law, especially during the end of the decade, the number of agreements governed by English law saw a marked increase. In some SPAs, the parties expressly agreed that the newly effective United Nations Convention on Contracts for the International Sale of Goods 9 and the Convention on the Limitation Period in the International Sale of Goods would not apply to the SPA. From a dispute resolution standpoint, the methods chosen were the following: (i) ICC in Geneva; (ii) ICC in London; (iii) UNCITRAL in London; (iv) UNCITRAL in New York; and (v) in several instances, ICC in Paris. As mentioned above, the SPAs of the 1990’s bred the largest SPA dispute to date and one of the largest in English legal history. When the Italian state electric utility, ENEL, attempted in 1996 to cancel its SPA with Nigeria LNG Ltd (reportedly claiming force majeure), the result was the filing of a breach of contract arbitration against ENEL for $13 billion. At the time, this claim was reportedly the largest one ever brought under English law. Fortunately, the matter soon settled when the parties agreed that Nigerian LNG would be shipped to France instead of Italy, in exchange for Russian gas diverted by French buyers to Italy. 10 Take-or-pay clauses continued to be relied upon, determined now almost exclusively on an annual basis. In spite of this, the parties to a 175 page SPA, which was governed by English law, decided to avoid using the words denoting take-or-pay; instead, the buyer under this SPA was granted an annual right to either “lift and purchase” the annual contractual quantity or “accrue a right to be allocated Make-Up LNG” by payment “for the corresponding quantity not lifted.” Buyers continued to have some limited ability to reduce their take-or-pay amounts (generally not exceeding 5%). With the evolution of annual contract quantities, quantities to be made-up from prior year reductions, make-up LNG, option quantities, force majeure restoration quantities, etc., provisions were added to the SPA to account for the relative priority of each contractual quantity right or obligation. Flexibility in scheduling delivery of the take-or-pay quantity began to be of major concern to some buyers, especially those located in countries with peak winter demand. This resulted in one Atlantic SPA requiring delivery of 62% of the annual contract quantity during October 1- March 1 and 38% of the annual contract quantity during April 1 to September 30. As new markets for LNG opened, pricing of LNG began to move gradually more away from its crude oil origins; for example: ● A price based on the “Net Back Fraction” calculated using actual sales of LNG and regasified LNG by buyer to customers within certain U.S. states, with buyer having the obligation to “diligently seek to maximize the proceeds” from such resale by negotiating terms with customers “which in Buyer’s reasonable commercial judgment are the most favorable available to Buyer … in the prevailing circumstance.” A price based approximately 90% on crude oil export prices (based on an initial factor of $3.24 MMBTU at $18 per barrel) and approximately 10% on changes in U.S. inflation. ● ● A price divided into an LNG element based on certain crude oil prices and on a transportation element, with buyer paying seller’s actual cost of transportation using certain dedicated LNG tankers. A price based on crude oils imported in Japan in that month plus a “Constant” (initially set at $.77) to be revised upward prior to the first delivery under the SPA if agreed by the parties to be “necessary by taking into consideration relevant factors including the prevailing energy situation.” ● ● Notwithstanding that the importer was located in another country, a price based on crude oils 9 The CISG came into effect in 1988; it is presently in effect in the U.S. but not in England. Note that the United Kingdom, however, may soon ratify the CISG as well. See UK Parlimentary Debate, 7 Feb 2005. 10 See Weems and Keenan, "Greenfield LNG Import Terminal Approvals," LNG Journal (May-June 2002) (www.kslaw.com/practice_areas/energy/publications.asp). imported in Japan; however, the price automatically adjusts upon a 5% differential between the contract price and pricing under buyer’s existing SPAs for Middle East LNG supplies. Aside from the SPA mentioned above, the 1990’s saw few uses of most favored nations clauses for comparative pricing. Price review clauses, also called “contract price reopeners,” were sometimes incorporated into Atlantic SPAs supplying LNG to Europe. Rather than making any changes dependent on the parties’ ability to reach agreement, a party was allowed to resort to arbitration to determine adjustments, bearing in mind pricing of LNG and gas in Western Europe, which in any event allow buyer “to market the LNG supplied … in competition with all competing sources or forms of energy (including, but not limited to, natural gas, fuel oil, gasoil, coal, LPG, district heating and electricity)…. such that “Buyer is able to achieve a reasonable rate of return on the LNG delivered hereunder.” Creditworthiness of the buyer became more of a focus during this decade as special purpose companies and subsidiaries of smaller gas companies without large balance sheets executed SPAs. This was especially the case in situations where the seller project financed its liquefaction facilities partly on the strength of the buyer’s credit. The importance of the soundness of contractual arrangements increased as sellers had to find comfort that buyer would perform by examining the soundness of buyer’s gas resale agreements and power sales agreements. In one example, the subsidiary was required to provide a parent guarantee for several hundred million dollars. However, if seller was not required to finance the construction of additional facilities to provide the quantities sold under the SPA, the buyer was simply required to obtain the issuance of letters of credit for the value of 2 to 3 cargoes. In some SPAs, in exchange for buyer’s guarantor being able to limit its parent guarantee amount, the seller limited its maximum liability. Extensive remedies clauses became more fashionable during the 1990’s. Although many contracts maintained the prior approach of relying on remedies afforded under the governing law (including those governed by the Uniform Commercial Code via the choice of New York law and certain Asian SPAs into Japan governed by English law), other contracts chose more detailed and specific remedies for non-performance. The remedies for seller non-performance were broadly divided into three categories: (a) the actual net cost of replacement gas or LNG; (b) the actual net cost of alternative replacement fuels; or (c) liquidated damages. The following are highlights of example provisions detailing remedies for non-performance of the sale or purchase obligations: ● As to seller’s liability, determined based on the costs buyer reasonably incurs to purchase either LNG (on an FOB basis), natural gas or a reasonable alternative fuel in replacement for the shortfall quantity of LNG, plus reasonable additional shipping costs incurred by buyer, but minus the contract sales price and any costs saved. As to seller’s liability, a “Shortfall Payment” in dollars for the quantity (exceeding a minimum threshold of 2.5%) not delivered, determined by multiplying the Shortfall Quantity by the following: ● – (a) the cost to buyer of replacement naptha/condensate/distillate volumes, delivered to the discharge port; multiplied by (b) a pre-agreed heat rate adjustment factor to convert the LNG Shortfall Quantity to naptha/condensate/distillate (which buyer would utilize at its downstream power station to generate the same amount of electricity), minus a pre-agreed adjustment for LNG boiloff and losses during regasification; minus – the cost (on a $/MMBTU basis, delivered ex ship) which would have been incurred by buyer for the Shortfall Quantity of LNG. As to seller’s liability, liquidated damages of 25% of the average contract sales price multiplied by the shortfall quantity. ● ● As to buyer’s liability, confirmation that “Buyer’s sole liability for or arising out of or in connection with any failure to take delivery of, or if not taken, to pay for LNG when required to do … shall be limited to its obligation to make [take-or-pay] payments.” Broad force majeure clauses, covering much more than simply “acts of God,” retained their dominance in SPAs during this decade. The traditional approach to defining a force majeure event as an “event occurring outside the party’s reasonable control” remained popular; but, several SPAs of this period avoided such a test and instead named a specific and exclusive list of events that were deemed to constitute force majeure. The debate also centered on events affecting transportation assets and downstream assets which should be specifically included or excluded; for example: ● Inclusion of damage to, loss or failure of the pipeline transmission and distribution facilities or of trucks engaged in the transportation of LNG or Regasified LNG from the receiving facilities. ● Inclusion of delays in construction of relevant upstream facilities, new liquefaction trains and related facilities, certain new buyer facilities, and port facilities and the dredging thereof. Inclusion of the “inability of one or more of buyer’s customers to take delivery of LNG, Regasified LNG or Natural Gas pursuant to its/their purchase contract(s) with Buyer.” ● ● Inclusion of certain events preventing a power plant from continuously purchasing regasified LNG from buyer for at least 30 consecutive days (but pro-rating the effects of such event based on a comparison of the contract quantity under the SPA over the last 12 months to the “total amount of Natural Gas whether domestic or otherwise and including LNG … purchased by Buyer during the same period of time”). Exclusion of circumstances which constitute a “Political Force Majeure,” as defined in the Power Purchase Agreement between buyer and the state electricity board. ● ● Exclusion of damage to an LNG tanker during certain voyages when carrying LNG not produced by seller. Exclusion of circumstances affecting buyer’s facilities if damage or failure resulted from gross negligence on the part of buyer’s management. ● A marked difference in the approach to reserves depletion developed. Asian SPAs addressed depletion of specified reserves of natural gas, while Atlantic SPAs specifically excluded the “natural depletion by production” of gas reservoirs. Lastly, although apportionment clauses had long been used to require seller to divide any available LNG supplies between long-term buyers, provisions were added requiring buyer to (for example) “devise and notify to Seller a fair and equitable system for apportioning its purchases between Seller and such other suppliers.” The approach to conditions precedent varied by project. In some SPAs, the parties decided to bear considerable condition precedent risk for a set period of time while awaiting certain governmental approvals, the execution of ancillary contracts, and financing or other investment decisions. In one instance (addressed in a 4 page provision in the SPA), in addition to conditions precedent relating to government approvals “obtained in form and substance satisfactory to the [relevant party] in it sole discretion,” seller was able to terminate the SPA with no liability unless seller had (a) executed a gas supply contract, an additional SPA with another purchaser, and an EPC contract for construction of seller’s LNG facilities, each in form acceptable to seller in seller’s sole discretion; and (b) made an affirmative final investment decision, in its sole discretion, to construct, own and operate seller’s proposed LNG facilities. Destination restrictions lingered in SPAs of the 1990’s, with the following being representative of the effects of such restrictions: “… all LNG sold hereunder shall be for Buyer’s account only. Buyer shall deliver LNG purchased hereunder into the LNG receiving facilities at [______] (the “Discharge Port”), unless prevented from so doing by reasons of Force Majeure or operational problems encountered at the Discharge Port or with the LNG Ship, in which case, Buyer may change the discharge destination to another suitable port in [Buyer’s country]. Should Buyer wish to change the destination to a port outside [Buyer’s country] in accordance with the foregoing, Buyer must first secure Seller’s consent, which shall not be unreasonably withheld.” Some, but by no means all, SPAs executed during this period addressed liabilities for LNG accidents occurring at the loading/unloading terminal. While some contracts were silent on the subject, others specifically required the party responsible for transportation to take certain actions aimed at causing the vessel owner and other related parties to execute port liability agreements provided the agreements are (in one instance) “reasonably acceptable to reputable insurers;” the level of protection and indemnity insurance required “does not unreasonably increase the cost of such insurance;” and “Seller is not exposed to any liability under the [agreement].” An unusual provision used for an SPA (governed by English law) for Japanese deliveries provided the following in order to resolve “nonlegal claims,” presumably resulting from an LNG incident involving the vessel: “If any demand or claim is made by any third party in Japan against Seller, Ship Owner, and each Buyer collectively or any of them, although according to the unanimous opinion of Seller and each Buyer there is no legal liability for the claim (for which purpose “legal liability” shall include cases of strict liability under the law or by contract) on the part of any of the parties, including Ship Owner against which it is brought, then the parties, together with the Ship Owner if willing, shall promptly discuss the claim in good faith and shall continue to do so as necessary until the claim is disposed of in order to find a reasonable solution with a view to disposing of the claim, protecting the interest of all the parties, including Ship Owner, and preserving the smooth operation of the matters contemplated in this Agreement.” unable to receive LNG under its supply SPA for a specified period of time (e.g., 48 months) due to a breach of contract and if such seller shares a portion of the damages payable to it for breach of the supply SPA. In another SPA, Buyer agreed to be jointly liable with its transporter for “any damage to the Loading Port Facilities, discharge of oil within the Loading Port or any other obstruction affecting the normal operation of the Loading Port Facilities.” Under this provision, the aggregate liability of Buyer and its transporter for any one incident was limited to $150 million “or such higher amount of insurance coverage as the Parties may agree from time to time is available and would generally be taken out by reputable operators of LNG vessels, based on normal industry practice, to cover such incidents and which is available from a recognised P&I club under usual P&I club rules.” During the period since 2000 the LNG industry has experienced the signing of an unprecedented number of SPAs. The International Group of Gas Importing Companies (GIIGNL) reported earlier this year that at least 63 long term and medium term contracts were in force at the end of 2004. GIIGNL also reported that 14 SPAs were signed in 2004, and 2005 has seen the signature of many others (e.g., Yemen with Kogas, Total and Suez LNG; Sakhalin in Russia with various Japanese buyers; and Iran with Indian buyers). Many of these contracts anticipate deliveries to North America.11 While the first decades of LNG history were dominated by a few players, recent years have opened the industry to many more participants. As noted in the following table, 12 countries exported LNG in 2004 while 13 countries imported LNG. Not surprisingly, as more complex project structures came to pass (especially as more special purpose entities became LNG purchasers), more detailed termination clauses were adopted. In some SPAs these provisions occupy several pages of the agreement. For example, in one instance buyer is specifically authorized to terminate the SPA if (a) construction of Seller’s Facilities is not completed by a deadline; (b) seller becomes bankrupt, etc.; (c) seller fails to pay to Buyer an amount exceeding an agreed threshold amount; (d) seller fails to deliver at least 50% of the annual quantity in two consecutive years (for reasons other than force majeure); (e) if a seller’s force majeure prevents delivery of at least 50% of the annual quantity in any year and it is apparent such prevention will continue for another year; or (f) if seller disposes of a substantial part of Seller’s Facilities without the prior consent of buyer. Moreover, in circumstances where the buyer was entitled to resell a portion of its LNG to a third party for import into a different receiving terminal, special termination provisions arose to enable seller to terminate such resale SPA if such seller is 11 Lastly, during the 1990’s yet another scheduling year was established, with Trinidad contracts adopting an October 1 to September 30 contract year. 2000’s LNG imports into the U.S. in 2004 reached a record 652 Bcf, compared to 2003 imports of 507 Bcf. However, LNG imports still represent only about 2.9 % of U.S. consumption and 15.5 % of U.S. imports, so additional LNG demand in the U.S. is expected by many LNG suppliers. have followed similar paths, with common choices being UNCITRAL arbitration in London or New York, ICC arbitration in Paris or London, or, in at least one instance, AAA in New York. While the majority of current SPAs are consistently for a term of 20 years (or 25 years, for some Middle East and Australian agreements), a 3.4 million tons per annum agreement signed in 2004 was for a term of only 17 years. It is noteworthy that of the 14 SPAs that GIIGNL reports were signed in 2004, 10 of these were for an annual volume of less than one million ton per annum. The signing of the latest SPAs suggests that, by the end of the decade, the number of exporting countries is set to increase to at least 18 and importing countries to at least 16. In early 2005, liquefaction facilities began shipping from Egypt, and facilities in Norway, Russia, and Equatorial Guinea are now under construction (with Iran and Yemen soon to commence construction). On the import side, a new regasification terminal opened in the United Kingdom in 2005 and new regasification terminals are now under construction in Mexico and China. As shown in the following map of key trade routes in operation as of 2004, Asian and Atlantic trades are becoming much more intertwined than in the past. Key LNG Trade Routes 2004 12 In the sampling of recent SPAs reviewed, New York law was chosen in half. The length of SPAs continues to rise somewhat from the last decade (e.g., after excluding technical exhibits, this sampling contains, respectively, 106, 99, 75, 74, 80, 65, 95, 109, 104 and 151 pages). Arbitration provisions in both Asian and Atlantic SPAs At least two significant public SPA disputes have occurred since 2000. First, as a result of the failure of Enron’s LNG terminal project in Dabhol, India, it is reported that both Oman LNG LLC and Abu Dhabi Gas Liquefaction Company Limited have each invoiced for take-or-pay amounts due under SPAs signed in the late 1990s with the Enron subsidiary Dabhol Power Company. Recently, these ongoing SPA claims, along with amounts not paid under related shipping contracts, were said to amount to $1.3 billion. 13 Second, a dispute concerning an Algerian SPA signed in 1987 with Trunkline LNG is ongoing in both London and Houston. In an UNCITRAL arbitration seated in London, Sonatrach and its affiliates are reportedly seeking approximately $600 million of damages. In 2003, the London arbitration panel found that Duke Energy LNG Sales Inc. repudiated the 1987 SPA by failing to diligently perform LNG marketing obligations; however, the panel also found that Sonatrach and Sonatrading breached their obligations under the 1987 SPA to provide shipping. Apparently, a hearing on damages issues is scheduled to commence in September 2005. The Houston portion of the second dispute concerns Duke’s contract for the sale of the Algerian regasified LNG. After Sonatrading ceased supplying LNG to Duke under the 1987 SPA, Duke asserted in 2002 to its gas buyer under the resale contract, Citrus Trading, that it had suffered a “loss of LNG supply” preventing it from performing its supply obligations. As a result, Citrus filed a lawsuit in March 2003 in the U.S. District Court for the Southern District of Texas 14 against Duke LNG alleging that Duke LNG breached the Citrus gas resale agreement by failing to provide sufficient volumes of gas to Citrus. Citrus has denied that Duke LNG had the right to terminate the gas resale agreement and contends 12 Source: "The LNG Industry in 2004," GIIGNL, Paris. 13 See GE, Bechtel Clear Last Hurdle in Dabhol Restart, The Financial Express, July 7, 2005 (available at www.financialexpress.com). 14 Citrus Trading Corp. v. Duke Energy LNG Sales, Inc., Cause No. 2003-12166 (U.S. 165th District Court, Harris County, Texas). 15 The Sonatrach and Citrus disputes are reported in Duke Energy Corp.'s 10-Q filing with the SEC, filed on August 9, 2005 (available at www.dukeenergy.com/investors/publications/sec.asp). that Duke LNG’s termination of the agreement was itself a breach, entitling Citrus to terminate the gas resale agreement and recover damages in the amount of approximately $187 million. 15 The Duke-Citrus case has not yet gone to trial. Recent SPAs have granted the buyer somewhat more flexibility as to its take-or-pay obligations (however, this flexibility should be viewed in context, because the buyer’s commitment is still typically well in excess of 90% of the annual contract quantity). In any event, the take-or-pay contract remains alive and well (although some argue that in concept take-or-pay is less of an issue for the U.S. because the market’s liquidity now always provides a gas purchaser at the market price). A recent major Asian SPA governed by English law clearly sets out the basic sale and purchase obligation on an FOB basis: “Seller shall sell and deliver LNG in Cargoes at the Delivery Point or make available for delivery LNG and Buyer shall take and pay for, or pay for if not taken, LNG in accordance with and subject to the provisions of this Agreement.” The October 13, 2003, Nigeria LNG Limited and BG LNG Services, LLC agreement (as filed with the U.S. Securities and Exchange Commission) states the basic take-or-pay obligation in the English law SPA as follows: “in any Sales Period, Buyer shall be entitled to take the [annual contract quantity] required to be made available for loading pursuant to the above (less Boil-off and LNG Heel) in such Sales Period or to accrue a right to Make up LNG … in respect of all or part of such quantity as it does not so take but in any event Buyer shall have the obligation to make full payment in respect of the entire [annual contract quantity].…” seller’s right to reduce the annual quantity for major scheduled maintenance of seller’s facilities or its vessels; (iv) buyer’s right to reduce the annual quantity for major scheduled maintenance of buyer’s facilities or its vessels or due to “operational constraints at [a third party’s LNG import facilities]”; (v) seller’s right to reduce the annual contract quantity due to inadequate gas reserves or deliverability from the defined gas supply area; (vi) adjustments due to differences in gross heating value from that estimated in the annual scheduling program; (vii) differences in the parties’ obligations to purchase during a “build-up period” versus the basic quantities to be sold and purchased throughout the term of the SPA; (viii) the parties’ rights to cancel a cargo which buyer cannot schedule for delivery; (ix) the effects of a force majeure; (x) fractional cargoes due to the conversion from cargoes to BTUs; and (xi) off-spec LNG. Such quantity adjustments, especially if multiple delivery destinations are anticipated under the SPA, are resulting in more detailed quantities provisions; for instance, the quantities provisions in one recent SPA approach 25 pages, in part to address separate rules for seller’s deliveries under the ex ship SPA to European receiving terminals and to North American receiving terminals. Although (as discussed below) destination restrictions have eased further, pricing provisions remain based on the gas market where the LNG will be imported. The following table indicates the wide differences in LNG pricing in 2004-2005 for Asian import prices. 16 It is not uncommon for an SPA to now address quantity adjustments in relation to a multitude of circumstances, such as: (i) buyer’s right to increase or decrease the annual quantity by a set amount (in one SPA, referred to as “Buyer Upward Flexibility Quantity” or “Buyer Downward Flexibility Quantity”); (ii) seller’s ability, upon Buyer’s agreement, to reduce the annual quantity for a “Seller’s Diversion” (i.e., a diversion from delivery to buyer); (iii) 16 www.abareconomics.com/australiancommodities/june05/pdf/asiapacificlng.pdf. While the Indonesian SPAs of the 1990’s did not include “S Curves” which moderate LNG prices when oil is above or below a certain range, many recent Asian SPAs tend to include such “S Curves”. There has also been a move in some markets to link LNG pricing to power pricing. Examples of pricing approaches in recent Atlantic SPAs are as follows: A price for North American deliveries which is a set percentage of the “NYMEX Henry Hub Natural Gas Futures Contract traded at the Nymex Exchange for the calendar month when completion of unloading or deemed completion of unloading of the relevant cargo takes place.” European system at the time when the … review is requested.” In fact, some contracts now specify when a price review procedure will not apply, such as the 2003 Nigeria LNG Limited and BG LNG Services, LLC agreement (as filed with the U.S. SEC) which states that “[f]or the avoidance of doubt … there is no price review mechanism for deliveries to Lake Charles.” ● ● A price for U.S. deliveries where the formula varies depending on whether the agreed NYMEX Henry Hub Price for the month is less than $2.50, between $2.50 and $4.50, or greater than $4.50 per MMBTU. A price determined for each receiving terminal where seller will deliver LNG, such price to be based on an agreed reference price for that receiving terminal for the month, minus adjustments for certain agreed shipping costs to that receiving terminal, minus agreed pipeline costs, minus agreed terminal costs, and minus agreed fuel costs for such receiving terminal. ● A price for deliveries into the U.S. based in part on the net proceeds, after actual transportation costs, received by buyer from reselling the LNG purchased under the SPA at named receiving terminals, with the understanding that “Buyer shall … diligently seek to maximize the net proceeds from its sales of LNG and Regasified LNG acquired hereunder… [, an obligation] which is intended to ensure that the amount paid to Seller under this Contract reflects the fair market value to Buyer’s … LNG customers.” ● For deliveries into Europe, for 85% of the quantities, a price based on the unweighted average of the monthly average prices for Gas Oil and Heavy Fuel Oil as published in Platt’s Oilgram, and for 15% of the volumes, a price based on an index for downstream power prices. ● “Most favored nations” provisions are not as typical in Asian SPAs as they once were. Lengthy price review provisions are no longer uncommon. A recent SPA for sales into Europe contains a 4 page procedure (which leads to arbitration if the parties cannot agree to revised pricing) if either party has “a good faith basis for believing that for reasons outside the control of the requesting party the method for determining the [price] does not reflect the value of regassified LNG at the import points in the Creditworthiness of both parties is becoming an issue in some SPAs, but no uniform approach has developed. Full parent guarantees are sometimes required to support the buyer’s credit. In one instance for the U.S. market, both the parent of the buyer and the parent of the seller issued certain payment guarantees. In another instance, although the stated limit of the payment guarantee provided by the buyer’s parent is several hundred million dollars, the guarantee amount reduces if the buyer provides “Step-In Rights” to apply to any termination of the SPA by the buyer, namely: (i) a release of buyer’s capacity and associated vaporization rights in a specified regasification terminal; and (ii) an assignment of buyer’s rights under specified shipping contracts. Specific remedy provisions for failure to purchase or sell, as the case may be, are now commonly found in many, but not all, recent SPAs. Although prior contracts were often silent on the issue, buyer’s limit of liability is typically specifically stated. For instance, the limit may be a phrase such as “the payment of the Annual TOP Quantity… shall constitute the sole and exclusive remedy Sellers shall have against Buyer for the obligation to take delivery of LNG.” On the other hand, the practice still varies, if a remedy is stated, for seller’s liability for non-performance. For example: In Asia, capping the seller’s liability, in effect, to a percentage of the value of the cargo not delivered. ● ● Providing for liquidated damages of 25% of the total amount that would have been payable by buyer for the quantity that was not delivered (unless the non-delivery was due to wilful misconduct, in which case the liquidated damages percentage increased to 35%). ● If the shortfall in deliveries in a year is less than 10 cargoes, buyer is granted a 10% discount in the nature of liquidated damages; a stated liquidated damage amount is payable if the shortfall exceeds 10 cargoes. Different remedies depending, in part, on the timing of when seller provided notice of cancellation of ● delivery or of substitution of an LNG vessel with reduced capacity. ● A shortfall payment based on the average contract price over the last 12 months, minus certain costs saved by buyer. The lesser of the cost to replace the gas not delivered or 20% of the contract price. ● Liquidated damages may also be payable if seller fails to deliver on a timely basis. No major alteration in the approach to force majeure has occurred in SPAs of this decade, although provisions are tending to lengthen as more detail is devoted to the parties’ obligations to take actions to resume deliveries of LNG (e.g., procuring additional shipping). Noteworthy developments with regard to force majeure in recent SPAs are: In SPAs providing for multiple delivery destinations: (i) coverage of certain downstream facilities or events in a different manner for each receiving terminal; and (ii) if force majeure prevents deliveries at buyer’s nominated terminal, the obligation for buyer to use reasonable endeavors to receive LNG at another LNG terminal that seller approves (with seller having the right to refuse to unload at such other terminal due to potential additional cost or risk to seller, scheduling difficulties, or safety/operational issues). ● ● The express obligation of seller, in the event of an accident affecting gas production, to take “such measures that are required to resume deliveries”, including “new investments and also temporary deliveries of LNG from [other LNG terminals].” ● In some recent Asian contracts, the exclusion of depletion of gas reserves from allowable force majeure events. ● Coverage of buyer’s downstream power customers only for events which occur during the first 5 contract years or only while such customer is off-taking at least a certain percentage of all of the regasified LNG sold at the receiving terminal. ● The exclusion of events affecting LNG receiving terminals other than the scheduled receiving terminal. ● The inclusion of provisions detailing seller’s rights if a buyer force majeure occurs. ● The obligation of buyer to apportion available capacity at the receiving facility between the SPA and other long-term contracts (i.e., having a term of at least 15 years) only. In a recent Asian SPA, the obligation of buyer to “use reasonable endeavors to take any quantity of LNG not taken previously as a result of Force Majeure.” ● The purchase and sale obligations under many, but by no means all, SPAs of this decade are conditional on the fulfillment of one or more conditions precedent. As is customary, the listed events are centered around government approvals, financing (including the satisfaction of all conditions precedent to the initial drawdown of funds), or the execution of ancillary contracts, with the obligation to satisfy the condition within a relatively short time (generally less than 6 months). In one instance, the SPA was conditional on seller making a final investment decision on the construction of an additional train. The parties typically agree to use reasonable endeavors, or at least to act in good faith, in attempting to satisfy the stated conditions precedent. Given the shortage of excess receiving terminal capacity over the last few years in some countries, one SPA specifically stated that buyer’s obligations are not conditional on buyer making an investment decision, constructing or purchasing capacity at any receiving terminal. As a result of pressure during 2001-2002 by the European Commission, SPAs for supply into Europe no longer contain destination restrictions (for example, it is reported that Nigeria LNG undertook not to introduce territorial restriction clauses in its SPAs signed after October 2002). Many SPAs (especially those of an ex ship nature) for supply into Asia continue to have some restrictions on the ability of the buyer to alter the destination of the cargo; however, some contracts for supply into the U.S. are becoming more flexible (with one FOB contract mentioning that buyer may redeliver any cargo to any LNG terminal so long as the redelivery does not result in buyer failing to arrive timely at the load port in accordance with the loading schedule). Moreover, a change in destination for deliveries to a North American port in an ex ship agreement, in addition to requiring seller’s permission to divert, may result in the use of a pre-agreed (or agreed at the time of the proposed diversion) alternative pricing approach or formula. With respect to each party’s liability for an LNG accident in the other’s terminal, practices in this respect remain inconsistent. While some SPAs elect to not lay out a special liability regime for the LNG loading or unloading port, an Asian SPA included a detailed provision requiring buyer, transporter, seller, and all their related associates, to sign a separate agreement governed by English law that implements the liability regime enunciated in the SPA. Where under such liability provisions a party agrees to indemnify for damages caused by such party’s LNG vessels, the limitation of liability is typically set at $150 million or “such higher amount of insurance coverage which is available from a recognized protection and indemnity club under usual protection and indemnity rules covering an LNG tanker’s liabilities while in or near docking facilities.” In some cases, a party is required to waive, on behalf of itself and the disponent owner and charterer of the LNG vessel, any right of such party to limit buyer’s liability under applicable laws, including the Convention on Limitation of Liability for Maritime Claims 1976. Termination clauses, once infrequent, are now common, with some being very detailed and several pages in length. Events which allow termination of the long-term sales contract can be grouped generally into those related to extended force majeure, those related to failure to pay or deliver LNG, or those related to other events which give rise to the party’s ability to continue to perform in the future (e.g., insolvencyrelated events, credit support events). With regard to extended force majeure, termination is now an available remedy, generally, if the event has occurred for at least 24-36 consecutive months and the event prevented the delivery of at least 50% of the annual contract quantity for such period. As an alternative to termination in one instance, if only a portion of the annual contract quantity had been affected, the party was granted the right to reduce the annual contract quantity under the remaining term of the SPA to in effect eliminate the portion that was not deliverable. Failure of the seller to deliver for non-Force Majeure events may be addressed in several ways, including seller’s (i) failure to make available an amount of LNG of at least [__]% of the annual contract quantity in [__] consecutive years; (ii) failure to “deliver any LNG Cargo Lot for a period of more than 120 … consecutive days”; and/or (iii) delay of at least [__] in commencement of deliveries during the first contract year. Termination for buyer’s failure to make payment is normally tied to a threshold amount (in one case, at least $100 million), which may be directly tied to the amount of credit security provided by buyer’s guarantor. Lastly, other events which have (in at least one instance) been added to the list of those justifying termination of the SPA are (x) buyer’s failure to make available regasification capacity equivalent to [__ billion cubic meters] in any period of [__] years or less and (y) changes in control of a party without the execution of documents confirming existing credit support obligations or without a corresponding transfer of the underlying gas supply assets. Transfer of title, thought to be an issue long ago resolved, has become an issue of import again in some SPAs, especially ex ship sales when the seller is concerned with potential liability for accidents or the parties wish to ensure that the sale is not considered a taxable event in the importing country. Such concerns have in more than one instance driven the parties in ex ship sales to agree to transfer title offshore, immediately prior to the vessel reaching the boundary line of the importing country. A host of issues arise from such offshore title transfers, compounded by situations in which the buyer assumes responsibility for transportation from the offshore delivery point to the receiving terminal and back to the offshore delivery point. True CIF sales, in which seller retains responsibility for transportation but buyer acquires title to LNG at the loading port, are also a recent phenomenon in SPAs. Lastly, the following are some additional observations regarding SPAs signed since 2000: Although some SPAs allow the buyer to reject an off-spec cargo if quality non-conformance is known soon after loading (e.g., within one day), most SPAs commonly obligate the buyer to use reasonable endeavors to attempt to receive the off-spec LNG (i.e., such as treating or blending the LNG with other LNG at the receiving terminal). In light of known quality issues in North American and UK gas markets for today’s typical LNG specification and caps (e.g., 15% of the contract price) in some SPAs on the amount which seller will reimburse buyer for costs incurred in attempts to treat/blend off-spec LNG, some of the risk associated with off-spec LNG appears to have been transferred from seller to buyer. ● ● Due to multiple offtakers in many loading and unloading terminals (particularly receiving terminals under construction which will be used by multiple customers based on two and three day set windows for unloading), scheduling issues have taken on increasing complexity. Although the LNG industry is said to be moving to more of a commodity business, few SPAs require seller to issue negotiable bills of lading. Instead, the common approach remains to rely on the issuance of cargo receipts evidencing the quantity loaded, rather than having the effect of a document of title. However, in one late 2001 SPA, the seller is required to provide “appropriate” bills of lading; if the bill of lading is not available when buyer is obligated to pay for the cargo, the SPA requires the seller to issue an indemnification letter in a form (attached to the ● SPA) which heretofore has been utilized for shipments of crude oil rather than for LNG. Conclusion This article has provided a general overview of changes to contracting practices for representative Asian and Atlantic-basin SPAs and common alternative drafting and risk-sharing methodologies. The 1960’s concept of rather succinct, fixed price SPAs linking a creditworthy seller with a creditworthy buyer and using ships dedicated to a single trade has evolved over the last four decades. SPAs today vary in complexity, influenced by a variety of factors such as the parties concerned and their creditworthiness (or lack thereof), the pricing basis for LNG sold, the depth of buyer’s downstream gas market and its competing fuels, the delivery point, LNG transportation structures, take-orpay flexibility, whether multiple users aggravate schedule issues, influences by gas competition regulators, concerns of lenders, sufficiency of seller’s gas reserves, and the allocation of commercial, operational and political risks related to performance of the agreement. Counsel drafting and negotiating SPAs would be wise to consider both past LNG precedent gained from decades of experience with LNG issues and the need to develop new techniques to appropriately deal with the multitude of challenges presented by the rapidly expanding LNG trade. www.kslaw.com