ESTABLISHMENT OF UNIT RATES FOR COMMON BUILDING AND ROAD WORK ACTIVITIES May 2010 Establishment of Unit Rates for Construction Works - PPRA Table of Contents 1.1 Background Information ...................................................................................................... 4 1.2 An Overview of Tanzania Construction Industry ............................................................. 5 1.3 Objectives of the Study ........................................................................................................ 5 2.0 METHODOLOGY ..................................................................................................................... 6 2.1 Methodology Adopted ........................................................................................................ 6 2.2 Selection of a Survey Team .................................................................................................. 7 3.0 DATA COLLECTION AND AGGREGATION ........................................................................ 7 3.1 Data Collection ....................................................................................................................... 7 3.1.1 Geographical Coverage ................................................................................................ 7 3.1.2 Institutions Visited ......................................................................................................... 7 3.1.3 Establishment of Common Activities and their Inputs ............................................. 8 3.2 Data Aggregation .................................................................................................................. 9 3.2.1 Road-works .................................................................................................................... 9 3.2.2 Building Works ................................................................................................................ 9 4.0 UNIT RATE BUILD-UP ............................................................................................................. 9 4.1 Unit Rate Build-Up ............................................................................................................. 10 5.2 Elements for Establishing Unit Rate ..................................................................................... 10 5.3 Establishment of All- In - Rates .......................................................................................... 11 5.3.1 Labour .......................................................................................................................... 11 5.3.2 Materials ....................................................................................................................... 11 5.3.3 Plant and Equipment Costs ........................................................................................ 12 5.3.4 Cost of Tools ............................................................................................................... 12 5.4 Output/Productivity Rates ................................................................................................. 13 5.4.1 Labour Productivity .................................................................................................... 13 5.4.2 Equipment/Plant Production Rate ............................................................................ 13 5.5 6. 0 Unit Rates Build-Up for Selected Items ............................................................................ 13 COMPARISON OF COLLECTED UNIT RATES AGAINST BUILT-UP RATES .................. 14 6.1 Inputs Comparison .............................................................................................................. 14 6.1.1 Materials ....................................................................................................................... 14 2 Establishment of Unit Rates for Construction Works - PPRA 6.1.2 6.2 Unit Rate Comparison for Road Works .......................................................................... 15 6.2.1 6.2 Average Collected, TANROADS, LGAs & Built-up ................................................. 15 Building Works .................................................................................................................... 24 6.2.1 7.0 Equipment/Plants ........................................................................................................ 15 Collected Vs Built-up .................................................................................................. 24 CHALLENGES FACED IN ESTABLISHING UNIT RATES .................................................... 29 7.1 Description of Work Items ................................................................................................. 29 7.2 Specifications ........................................................................................................................ 30 7.3 Construction Materials ....................................................................................................... 30 7.4 Labour Productivity ............................................................................................................ 31 7.5 Equipment /Plant ................................................................................................................ 31 8.0 CONCLUSIONS AND RECOMMENDATIONS ................................................................... 31 8.1 Conclusions .......................................................................................................................... 31 8.2 Recommendations .............................................................................................................. 32 3 Establishment of Unit Rates for Construction Works - PPRA 1.0 INTRODUCTION 1.1 Background Information Procurement reforms in Tanzania started way back in 1990’s and has brought important changes that make expenditure of public funds for acquisition of works, goods and services to be managed in rational manner. The reforms culminated to the enactment of the Public Procurement Act No. 21 of 2004 (PPA, Cap 410), which established an oversight body, the Public Procurement Regulatory Authority (PPRA) and decentralized procurement to the public entities. All these efforts were aimed at putting in place, amongst others, the most effective measures to achieve the desired outcome of the procurement of works, goods and services in the public sector. PPRA and the Government Procurement Services Agency (GPSA) have jointly developed a system for procurement of Common Use Items and Services (CUIS). The main purpose of establishing the system is to ensure that public fund allocated for procurement of commonly used items and services by public bodies are properly controlled in a manner that will minimize waste. Section 7(m) of the PPA, Cap 410 provides for establishment of a list of such common use items to be reviewed on an annual basis as one of the important functions of the PPRA. The objective of the system is to improve efficiency and effectiveness in procuring supplies, services and works in common use by more than one Procuring Entity (PE), which may be subject to common procurement. In the process of attainment of such objective, PPRA came up with the decision of carrying out the study in order to establish average unit rates for common activities in the construction works which will be reviewed from time to time. This study was intended to cover mainly those activities which constitute the largest proportion in terms of value of contracts awarded. The procurement market in Tanzania, like in many other countries, is dominated by building and civil works in terms of total value of contracts awarded. Recent statistical data show that, within developing countries, procurement of works is often the largest domestic market. As for Tanzania, in the financial year 2007/08 the volume of awarded contracts for the works was 61 % of the all procurement while in 2008/09 works contracts accounted for 56% (Mlinga, 2009). 4 Establishment of Unit Rates for Construction Works - PPRA 1.2 An Overview of Tanzania Construction Industry The construction industry is the sector of the economy that transforms various resources into constructed physical, economic and social infrastructure necessary for socio-economic development. It embraces the process by which the said physical infrastructure are planned, designed, procured, constructed or produced, altered, repaired, maintained and demolished 1 . The term construction covers a wide variety of activities; these include the dwellings, non residential buildings and civil engineering works such as roads, bridges, dams, harbours, railroads etc. Construction activity also encompasses repair, renovations, rehabilitations and maintenance of existing structures, etc. Infrastructure projects, in particular, require large capital outlays on the part of spending public bodies and therefore there is need to ensure that their procurement achieves value for money. The industry comprises numerous stakeholders, namely; clients, consultants, contractors, materials producers and suppliers, and equipment/plants suppliers. Equally important, are procurement systems, management philosophies, techniques and tools that play significant roles in the determination of the performance of each stakeholder. The government is involved in the construction industry as the client, operator and regulator. It executes those roles through its agencies such as Local Government Authorities(LGAs), Ministries, Tanzania Building Agency (TBA), Tanzania National Roads Agency (TANROADS), Tanzania Electrical and Mechanical Services Agency(TEMESA), NHBRA and regulatory boards such as National Construction Council (NCC), Public Procurement Regulatory Authority (PPRA), Architect and Quantity Surveyor Registration Board (AQRB), Engineers Registration Board (ERB) and Contractors Registration Board (CRB) etc, 1.3 Objectives of the Study The objectives of the study are: • to comply with Section 7(m) of the Public Procurement Act No. 21 of 2004 [PPA, CAP 410] which requires PPRA to establish a list of works, services and supplies in common use by more than one procuring entities. PPRA had already established the list of common use items and supplies with their average prices and published the same in the website. 1 Construction industry policy, 2003 5 Establishment of Unit Rates for Construction Works - PPRA 2.0 • to respond to an outcry of the stakeholders on the significant differences in unit rates for common activities in construction industry; • o establish a database for average prices of construction materials; hiring rates for equipments, equipment productivity; labour productivity for the selected common activities. • to assist the government and suppliers, service providers, contractors and consultants to have access of the prevailing unit rates in common activities in construction works • to be used as basis or indicative figures by Procuring Entities when preparing engineers estimates. METHODOLOGY 2.1 Methodology Adopted In order to achieve the objectives of this study the following methodology was adopted:- • Identification and establishment of comprehensive list of common activities in both roads and buildings works as a tool to collect the existing unit rates in the industry; • Identification and establishment of comprehensive list of equipment/plants and materials as a tool to collect for hiring rates and prices respectively; • Data collection; the institutions earmarked for data collection were TANROADS, Municipals and District Councils and professional associations; • Compilation and analysis of the data collected; • Establishment of unit rates for some of the activities for both roadworks and buildings works from the first principles; • Comparison of the built-up unit rates against the average collected unit rates and • Clarification on the discrepancies proposal for way forward. 6 Establishment of Unit Rates for Construction Works - PPRA 2.2 Selection of a Survey Team Collection and Compilation of average prices for construction activities is a complex assignment as they consist of a long and varied set of operations. The assignment necessitates having a survey team with detailed knowledge of the construction industry to ensure that information provided by material suppliers, construction contractors and other stakeholders can be evaluated for reasonableness, and practical use. In this survey engineers and quantity surveyors were selected with a supporting staff to undertake the assignment. The survey team comprised the following members:1. Eng. Mary M. Swai (PPRA) Manager Research & Documentation 2. Eng. Raymond J. Mbishi (PPRA) Procurement Expert 3. Qs. Grentina B. Kidulile (PPRA) Procurement Expert 4. Eng Raphael Mahundi (UDSM) Civil Engineer 5. Said Mrisho (Ardhi University) Quantity Surveyor 6. Alois Manamba (PPRA) Library and Documentation Officer 3.0 DATA COLLECTION AND AGGREGATION 3.1 3.1.1 Data Collection Geographical Coverage In the collection of data, five zones were identified and visited taking into account geographical location. The identified zones were; Northern [Arusha, Manyara, and Kilimanjaro], Lake (Mwanza and Mara), Central [Dodoma, Singida, Tabora and Shinyanga], Southern Highlands [Iringa and Mbeya], Southern Zone[Mtwara and Lindi] and Eastern [DSM, Morogoro and Tanga]. The basis for the choice of the zones was to get more representative unit rates from different locations for analysis. 3.1.2 Institutions Visited Data collection took place between 28th December and 17th April, 2010. Among the institutions that were visited are the following LGAs; Arusha Municipal Council, Arusha District Councils, Meru District Councils, Monduli District Councils, Babati Town Councils, Babati District Councils, Moshi District Council, Moshi Municipal Council, Hai District council, Same Distric Councils, Mwanga District Councils, Tanga City Councils, Mkinga District Council, Muheza District Council, Korogwe District Councils, Iringa District Council, Mbeya District Council, Mbeya Municipal Council, Dodoma Municipal Council, Bahi District Council, Morogoro Municipal Council, Morogoro District Council, Mwanza City Council, Ilemela District Council, DSM City Council, Kinondoni Municipal Council, Temeke Municipal Council, Ilala Municipal Council, Igunga District 7 Establishment of Unit Rates for Construction Works - PPRA Council, Manyoni District Councils, Nzega District Council, Bunda District Council and Musoma District Council. Other institutions were TANROADS regional offices including; Morogoro, Dodoma, Arusha, Kilimanjaro, Mbeya, Iringa, Mwanza, Lindi, Mtwara, Tanga, Manyara. Data was also collected from some Tanzania Building Agency [TBA] regional offices, namely; Iringa, Mwaza, Dar es Salaam, Mara and Manyara. It was also necessary to gather information from the National Construction Council [NCC], Contractor Registration Board [CRB], Tanzania Civil Engineering Contractors Association [TACECA], Association of Consulting Engineers Tanzania [ACET] and Contractor Association of Tanzania [CATA]. In the process of data collection, the suppliers of construction materials, suppliers of equipment/plants as well as the contractors were visited and interviewed to get indepth information on the availability of materials, equipment and production rates. 3.1.3 Establishment of Common Activities and their Inputs During data collection process, unit rates were extracted from the contract documents for the projects executed in the financial year 2009/2010. The identified list of activities was used as a tool for collecting the unit rates. There was also a flexibility of adding more activities which were considered to be common depending on the institutions visited and bills of quantities (BoQ) used. The understanding was that during aggregation of the collected data the team will analyse the collected data and decide which activities are common for the time being as this study is a continuous process. Due to diversity of the construction industry for the purpose of this study, it was agreed that as a starting point the team should concentrate on two categories works, namely, road works and building works. One of the institutions visited, TANROADS, has a system which requires them especially in maintenance activities to collect and find average of the unit rates for each activity from the maintenance contract. The unit rates for maintenance activities from all regions were obtained from their 2nd quarter reports for FY2009/2010. Information on inputs for the constructions activities such as material prices, equipment/plant hiring rates, productivity rates for both equipment/plant and labour as well as prices for handtools were collected using tools specifically designed for the purpose. The information was collected from the suppliers and sellers of the construction materials and hand tools, plant equipment hirers, as well as from clients and contractors. 8 Establishment of Unit Rates for Construction Works - PPRA 3.2 Data Aggregation The data collected was compiled using Microsoft Excel, which made the analysis such as average unit rates, average price of materials and hiring rates for equipment/plants easier. The aggregation for building and road works was done separately. The collected information from the LGAs and TANROADS were compiled separately to enable comparisons of established unit rates from the two major clients of road works 3.2.1 Road-works The list of activities and their average unit rates as aggregated from LGAs and TANROADS are attached as Appendix R1 and Appendix R2, respectively. The list of some of the materials used for road-works and their average price are attached Appendix R3, while the hiring rates of equipment/plant used for road work activities and their average hire rates are attached as Appendix R4 to this report. 3.2.2 Building Works The collected data for building works activities from LGAs, TBA and associations such as TACECA, ACET and CATA were aggregated and the average unit rates for the common activities obtained. The aggregated list of activities and their average unit rates are attached as Appendix B1. The list of building works materials and their average prices are attached as Appendix B2. 4.0 UNIT RATE BUILD-UP Unit rates build-up is the process of developing a unit rate for the activities involved in the execution of the project. Its purpose is to develop an approximation of costs of the resources needed to complete project activities which ultimately establish cost of a project as well as assist in cash flow analysis and checking expenditure during project execution. From the client’s perspective, a unit rate for performing an activity is a vital tool for checking cost and ensure that the contract sum is within the approved budget or cost limit in all stages of implementing the project, namely; pre-construction, during construction and post construction. In the case of contractors, the unit rate build-up is the process of determining the cost of carrying out an activity so as to produce a competitive bid by analyzing the resources required and time it will take to execute an activity. Broadly, for both stakeholders, the process involves aggregating the estimated costs of individual activities or work packages to establish a cost baseline for cost management, as well as tracking changes or trend in the cost of the project. 9 Establishment of Unit Rates for Construction Works - PPRA 4.1 Unit Rate Build-Up The proposed model for building up unit rates is basically intended to examine individual resources and the amount needed for each activity. It consists of three stages:• • • Establishment of all-in rates for the individual resources in terms of Tshs per hour/day for labour Tshs per hour/day for items of plants/equipment and the cost of material. All these can be referred to as inputs required for each activity depending on the activity to be executed; Selection of methods and outputs or productivities of the plants/equipment required for each activity. These two depend on the specifications of the inputs, process or workmanship required. This phase is inputs-process stage in order to obtain the required product; and Adding an overhead and profit to the net cost obtained from above. By using standard spreadsheets [Microsoft Excel], one is able to process basic information on inputs to provide an output [unit rate]. 5.2 Elements for Establishing Unit Rate The key elements to consider when establishing a unit rate are direct costs, indirect costs, overheads and profit. These elements are explained further below: a) Direct Costs: cover materials, labour, plant and tool costs, and transport of materials and equipment which are directly related to the construction of a project. b) Indirect Costs: are cost incurred away from the site or are costs allocated to the project as well as costs incurred by a company that uses in-house resources to implement a project. These cover: • Preliminaries: - Site camp facilities, insurance, bonds, road signs, safety measures, general transport, tendering costs, accommodation, hire of support equipment, etc. • Risks: - Bad weather, work rectification, delayed payment, carelessness by employees, rising prices, etc. 10 Establishment of Unit Rates for Construction Works - PPRA The indirect costs have not been considered in this model; the assumption is that the costs will be covered in the preliminary and general items of the respective project based on the terms and conditions of contract. c) Profit/mark-up: profit is defined as a return on investment. This is normally judged or assessed rather than calculated. The margin depends on the judgement of the market and the state of the business. It is what provides the contractor with an incentive to perform the work as efficiently as possible. d) Overhead costs: are costs which cannot be attributed to a single task of construction work. They are basically hidden costs of managing and running a construction firm. Usually it is expressed as a percentage of the annual turnover of the company. The costs include; salaries of staff [technical, administrative, management, support], running cost of office [renting, telephone, electricity, water, stationery, etc.], taxes [withholding tax, stamp duty composition, VAT, etc.], interest on overdraft, business promotion [e.g. printing of calendars with company logo], renewal of licences, etc. 5.3 Establishment of All- In - Rates 5.3.1 Labour The cost element in labour has been made up of wages and emoluments to be paid to workers and statutory costs, which are incurred automatically as a result of payment for labour. Wage rates have been developed for each labour craft [unskilled, skilled and foreman] which represent the total hourly cost rate to the construction contractor. The main items considered include; statutory minimum wage, workman's insurance, payroll levy, training levy, social security, cost of non-productive time, transport for workers, medical costs. These summed costs have been expressed as an hourly cost with the possible exception of vacation which may be easily converted to an hourly cost. There is a debate whether contractors are normally paying these statutory costs to their employees. However, there is a need for establishing exactly costs which contractors are required to pay their employees which should be considered in the unit rate establishment. 5.3.2 Materials Under normal circumstances prices for materials and supplies should involve summarising the information obtained from inquiries made and quotations by suppliers in order to make a proper comparison and choice. For purposes of 11 Establishment of Unit Rates for Construction Works - PPRA this model, the prices for materials and supplies have been obtained from the suppliers and contractors in the respective regions visited. The averages of prices for materials and supplies have been used in establishing the unit rates. Waste consideration has been taken into account in the build-up of respective unit rate by allowing some percentage. Allowances for transport and handling costs, i.e., load, off-load, stockpile or warehouse materials have been taken into consideration as part of build-up the unit rates. Construction materials which need secure storage such as temporary building should be considered as indirect costs to be built-up under preliminary and general costs. 5.3.3 Plant and Equipment Costs Construction equipment and plants refers to the instruments, machinery, and other mechanical implements required in the performance of construction work. The plant/equipment cost is either the cost of owning and operating the plant or hiring the equipment from hiring firms. When plant is already owned, cost should include allowances for; ownership costs [depreciation based on the purchase price and expected economic life, return on capital, labour for maintenance and related overheads, parts for maintenance, insurance, road licence, etc.] and running costs [emoluments of the operators, fuel, lubricants, tyres and other consumables]. In this model, the assumption is that the equipment/plants are hired and respective hire rates have been obtained from hirer and contractors in the respective regions visited. The averages of the collected hiring prices for equipment/plants have been used in establishing the unit rates. 5.3.4 Cost of Tools The cost of hand tools and miscellaneous non-capitalized equipment should be estimated and incorporated in the establishment of unit rate. This is the ownership cost of tools to be used in respective activities, which is spread over the entire project. Cost of tools is computed as follows: Cost of tools per person-day = Cost of tools over the project / Expected person-days over the project It should be noted that the cost of tools per project would be factored depending on the number of projects for which they may be used. 12 Establishment of Unit Rates for Construction Works - PPRA 5.4 Output/Productivity Rates 5.4.1 Labour Productivity Estimating labour productivity is subject to many diverse and unpredictable factors. The complexity of the variables affecting productivity makes it difficult to estimate a production rate. The labour effort needed to perform a particular task varies with many factors, such as the relative experience, capability, morale of the workers, the size and complexity of the job, the climatic and topographic conditions, the degree of mechanization, the quality of job supervision, amount of similar task repetition, and the existing labourmanagement agreements and/or trade practices. The effort from these labour efficiency factors and work practices that exist in the project locality must be considered in each productivity assignment. Therefore, in this model, labour productivity rates are based on records of past production rates for the same or similar work and interviews with the practitioners in the industry. 5.4.2 Equipment/Plant Production Rate After determining the type of equipment/plants to be employed, the establishment of the production rates of each equipment/plant is an important step in the process of build-up the unit rate. Again, estimating equipment/plant productivity is subject to unpredictable factors. The production rates may depend of the factors such as; the quantity and type of vegetation, soil conditions, topography, climate conditions, skills of operators etc. In this model, emphasis has been placed on the importance of establishing a reasonable production rate. In the absence of historical established production rates, the productivity rates have been through interviews with the practitioners during data collection exercise. Per hour rental costs of the construction equipment/plant have been used as the basis to price them. Due to difficulties of getting the production rates for some of the equipment/plant, unit rates for some of activities could not be established. 5.5 Unit Rates Build-Up for Selected Items As explained above the objective of the study is to establish average unit rates for common activities in construction works. This model presents some of identified common used unit rate. The identification applies the 80/20 rule, which states that approximately 80 percent of the project cost is contained in 20 percent of the activities. This is because identified activities account for most of the project cost. The built up unit rates for activities in the road-works and building projects have been established and are attached to this report as 13 Establishment of Unit Rates for Construction Works - PPRA Appendix R5 and Appendix B3 respectively. Establishing the unit rates for the remaining common activities will be carried on as study continues. 6. 0 COMPARISON OF COLLECTED UNIT RATES AGAINST BUILT-UP RATES 6.1 Inputs Comparison 6.1.1 Materials The inputs for establishing unit rates collected were material prices and equipment hiring rates. It was observed that there is significant difference in materials prices and hiring rates in the region visited. The average materials prices presented in the table below have influence in establishing unit rate for selected activities. Table No.1: Summary Average Materials Prices Collected in the Regions S/No MATERIAL S REGIONS UNIT 1 DAR DOM MORO MBEYA ARUSHA K’NJARO 13,300 13,500 13,500 13,000 1.62 2.1 2.0 Bag 12,500 13,000 ton 1.5m 1.04 ton 1.5 m - - 1.5 m - 1.62 m 2.0 m 2.0 m 3 Re – bars – Mild Steel Re-bar High Tensile Steel Aggregates M3 40,000 50,000 80,000 75,000 45,000 25,000 60,000 50,000 4 Fuel Lts 1,450 1,430 1,450 1,800 1,440 1,530 1,500 1,500 5 Sands m3 10,000 7,500 10,000 25,000 10,000 15,000 25,000 25,000 6 Stone m3 25,000 10,000 15,000 20,000 15,000 15,000 20,000 15,000 7 Concrete pipe 600mm Concrete pipe 900mm Concrete pipe 1200mm m 90,000 75,000 50,000 120,000 50,000 120,000 75,000 80,000 m 125,000 120,000 75,000 180,000 80,000 150,000 120,000 120,000 m 160,000 150,000 120,00 200,000 120,000 180,000 150,000 150,000 8 9 14 17,000 IRINGA Cement 2 3. 12,700 MWZ Establishment of Unit Rates for Construction Works - PPRA The prices of construction materials vary from one place to another due to geographical location. For instance, cement price is higher in Mwanza region compared to Dar-as-salaam because of transportation costs involved due to distance from the source which is Dar es Salaam. The price of cement being higher in Mwanza, this will have direct impact on the established unit rates on activities such as concrete, stone masonry, blocks walling, etc which cement is incorporated. Aggregates in Morogoro and Mwanza are at higher prices compared to other regions. In general price of materials in Mwanza is higher compared to other regions. 6.1.2 Equipment/Plants Equipment/plants are major input in construction activities which account for 40 – 60% of the project cost. The data collected has revealed that there is significant difference in hiring rates of major equipment/plants used in construction especial for civil engineering projects. The table presents the average hiring rates collected in the different regions. Table No.2: Summary Average Equipment Prices Collected in the Regions S/No. EQUIPMENT Dar 1. Concrete Mix 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Motor Grader Bulldozer Roller Wheel loader Water Bowser Pedestrian Roller Tipper 7 tons Tipper 10 tons Tipper 15 tons Bitumen Distributor Chip Spreader Excavator 12. 13. 6.2 100,000 Dod REGIONS [Average Hiring Prices in Tshs.] Moro Iringa Mbeya Mwanza 90,000 50,000 500,000 666,666 568,000 600,000 650,000 500,000 500,000 381,500 400,000 450,000 150,000 190,000 150,000 71,500 80,000 93,333 125,000 150,000 120,000 120,000 200,000 200,000 180,000 140,000 200,000 250,000 300,000 200,000 200,000 800,000 300,000 800,000 1,200,000 625,000 475,000 700,000 800,000 600,000 40,000 Arusha K’njaro 100,000 700,000 600,000 800,000 700,000 600,000 1,000,000 600,000 600,000 560,000 450,000 500,000 400,000 550,000 560,000 372,000 500,000 450,000 650,000 157,500 350,000 200,000 350,000 120,000 150,000 25,000 300,000 120,000 120,000 100,000 180,000 140,000 140,000 220,000 200,000 450,000 560,000 Unit Rate Comparison for Road Works 6.2.1 Average Collected, TANROADS, LGAs & Built-up The comparison of the average unit rates for the collected data, TANROADS, LGAs and the built-up rates indicates that grass cutting, bush clearing and site clearance there are no significant differences. For the cut and spoil, cut and borrow to fill shows that 15 Establishment of Unit Rates for Construction Works - PPRA built up unit rates are significantly higher than the unit rates for TANROADS and the average collected. TANROADS unit rate is the highest in the activity of clearing borrow area and remove overburden. The differences could be attributed by the lack of clear specification on the haulage distance of the borrow materials and distance for disposing the removed overburden. The details of comparison of the average unit rates are indicated in figure No. 1 below. Figure No.1: Comparison of Unit Rates for Site Clearance, Bush Clearing, Cut and Spoil, Cut and Borrow to Fill, Grass Cutting and Clear Borrow area and Remove Overburden The comparison of the average unit rates from the TANROADS, LGAs, collected and the built-up for gravelling within Free Haulage Distance (FHD) indicates that there is no significant difference between the unit rates from TANROADS, collected average and LGAs collected. The built up rate is significantly the highest. The established unit rate has considered FHD to be 10 km and the difference could FHD specified in the specifications in contract document used by these institutions as unit rate for gravelling is influenced very much with haulage distance of the gravel materials. Furthermore, in 16 Establishment of Unit Rates for Construction Works - PPRA the built up rate has taken into account an overhead cost and profit margin of 30%. The overhead cost and profit margin vary very much from one company to another. Figure No.2 below shows the comparison of the average unit rates discussed. Figure No.2; Comparison of Unit Rates for Pothole/Eroded Road Section Filling, Gravelling within FHD In the comparison of unit rates for road formation activities, the average unit rates built -up for heavy grading, light reshaping and heavy reshaping are the highest while the LGAs rates are the lowest for the same activities. For light grading the LGAs rate is the highest while the built up rate is the lowest. The rates for TANROADS are slight higher than the average collected except for the light grading. The difference in rates can be contributed by the specifications given to the contractor whether road formation category includes watering and compaction or not. Other factors could be equipment/plants hiring rates, productivity rates and topography type. Figure No.3 shows comparison of the unit rates for discussed activities. 17 Establishment of Unit Rates for Construction Works - PPRA Figure No.3; Comparison of Unit Rates for Road Formation Category In the comparison of unit rates for road surfacing activities, it indicates that the built up rates are significantly lower than the unit rates from TANROADS, Average unit rates collected. The unit rate from LGAs is the highest in resealing single surface layer. TANROADS unit rates for bituminous surface layers and bituminous double seal are the highest. This significant difference may also due to specifications used for different types of roads and the road usage which may require different thicknesses. Figure No. 4 below shows comparison of the unit rates for discussed activities. 18 Establishment of Unit Rates for Construction Works - PPRA Figure No.4; Comparison of the Unit Rates for Road Surfacing Activities In the comparison of the activity for excavation of the drains, as it can be seen in figure 5 below, the built up rate is slightly higher than the unit rates from TANROADS, Average collected and collected LGAs for excavation of side drains, excavation of mitre/catch water drains and excavation for inlet/outlet of culvert. There is a significant difference for activity of excavating and backfill for structures where the LGAs collected is the highest and the built up rates is the lowest. The issue of types of structures and where to excavate the material used to fill depend much with the drawings and specifications given. 19 Establishment of Unit Rates for Construction Works - PPRA Figure No.5: Comparison of the Unit Rates for Excavation of the Drains The comparison for installing concrete pipe culverts of different sizes indicates that the built-up unit rates are lower than the average unit rates collected, TANROADS rates and the LGAs’ rate. This could be attributed by the haulage distance for materials incorporated in the built-up. For this case built-up unit rates have considered that the source of all materials is 10 km from the site. It should be noted that the unit rate for installing the concrete pipe depends very much on the haulage distance of the materials used. However, this also could be contributed by the specifications given in the contract documents as it common to find that the activity for installing culvert concrete pipe per metre includes construction of approach ramps, wing-walls, headwalls and bedding while in other BoQs these activities are separated. Figure No.6 below gives the details comparison for unit rates for installing concrete pipe culvert, 20 Establishment of Unit Rates for Construction Works - PPRA Figure No.6: Comparison of the Unit Rates for Installing Concrete Pipe Culverts Figure No.7 below shows that the unit rates for reinforced concrete classes 10, 15, 20 and 25 per cubic metre for built-up unit rates from first principle are higher than the unit rates collected from TANROADS, LGAs as well as the average collected. 21 Establishment of Unit Rates for Construction Works - PPRA Figure No.7; Comparison of the Unit Rates for Concrete Classes The comparison of the unit rates for reinforcement bars for both mild and high yield steel indicates that the unit rates from TANROADS for reinforcement with mild steel is the lowest with the unit rate from LGAs being the highest followed by the built up rate. For reinforcement with high yield steel the built up rate is the highest. During data collection it was noted that in the industry reinforcement bars are treated the same in terms of prices regardless of the strength i.e. mild or high tensile steel. Further probing indicates that the reinforcement claimed to be high tensile bars in up country their strengths when tested do not reach that of high tensile steel. The price of reinforcement bars in Dar es Salaam revealed high tensile steel is 1,300,000 per tonne while mild steel is 1,100,000 per tonne. Figure No.8 below shows details of comparison. 22 Establishment of Unit Rates for Construction Works - PPRA Figure No.8; Comparison of the Unit Rates for Reinforcement Bars The comparison of the unit rates for stone masonry and grouted stone pitching indicates that the built-up unit rates are higher than average collected TANROADS and LGAs. There is no significant difference between the built up rates, average collected, LGAs collected and TANROADS for loose stone pitching. The unit rates form TANROADS for grouted stone pitching is the lowest. Figure No.9 below shows details of comparison. 23 Establishment of Unit Rates for Construction Works - PPRA Figure No.9; Comparison of the Unit Rates for Stone Masonry, Loose Stone and Pitching, Grouted Stone Pitching 6.2 Building Works 6.2.1 Collected Vs Built-up This comparison was made for sub-structure activities for the unit rate average collected, Associations LGAs and the built-up unit rates. The built-up unit rates for excavate earth surface, load up surplus excavated material and lay hardcore of 300mmthick bed is the highest. Figure No.10 below gives details of the comparison of sub-structure activities. This could be attributed to the haulage distance of filling materials. 24 Establishment of Unit Rates for Construction Works - PPRA Figure No.10; Comparison of the Unit Rates for Some of Sub-structure Activities The comparison for blocks walling for 230mm thick indicates there is a significant difference between built-up unit [Tshs.37,828.00] and collected unit rate [Tshs. 25,063.49] and from the associations [Tshs. 29,666]. Furthermore, no significant difference for blocks walling for 150 mm & 100mm. Figure No.11 shows the details of the comparison. 25 Establishment of Unit Rates for Construction Works - PPRA Figure No.11; Comparison of the Unit Rates for Block Walling The comparison of the unit rates for reinforcement bars for high yield steel indicates that the the built up rates are significantly higher than the collected average. Furthermore, it is noted that the high yield steel [25mm] the rate per kg is the highest [ for the collected average i.e Tshs. 3,709.12 per kg]. For other sizes there is no much differences between the unit rate per kg for the average collected. Figure No.12 shows the details of the comparison. 26 Establishment of Unit Rates for Construction Works - PPRA Figure No.12; Comparison of the Unit Rates for High Steel Bars The comparison of the unit rates for reinforcement bars for mild steel indicates that the built up rates are lower than the average collected except for 8mm, 10mm, 20mm and 25 mm where the collected average are the highest. Figure No.13 shows the details of the comparison. 27 Establishment of Unit Rates for Construction Works - PPRA Figure No.13; Comparison of the Unit Rates for Mild Steel Bars The comparison for concrete works shows that the unit rates for reinforced concrete classes 10, 15, 20 and 25 per cubic metre for unit rates built-up from first principle are higher than unit rates from the average collected and LGAs. This could be attributed by the availability of materials incorporated in the activity in terms of haulage distance and prices of materials such aggregate and sand. Figure No.14 shows the details of the comparison. 28 Establishment of Unit Rates for Construction Works - PPRA Figure No.14; Comparison of the Unit Rates for Reinforced Concrete Classes. 7.0 CHALLENGES FACED IN ESTABLISHING UNIT RATES Establishing unit rates is a very complex undertaking. This is due to the fact that it requires a number of input parameters which vary very much depending on the details needed and available during the estimating process. It is a discrete process for each project and for each piece of work. Embarking on establishing unit rates, poses challenges which sometimes may affect the accuracy of the built-up rates. During this exercise in particular, a number of challenges were encountered and are presented here under: 7.1 Description of Work Items The survey revealed that there is no consistence in the descriptions of work items among the public entities. The significant difference was note in the LGAs compared to the other public entities for both building and roadworks project. This affected the process as the tool prepared to collect common activities couldn’t fit all public entities visited. This led to missing some important activities in the Bills of Quantities [BoQ] as the items works were compounded together i.e. supply and installation of culverts, in 29 Establishment of Unit Rates for Construction Works - PPRA some of the BoQ this item meant to supply, installation, surrounding concrete, masonry works and measured per linear metre while others the same item breakdown to supply and installation, concreter and masonry works and measured separate. The review of the contract documents revealed that this is attributed by lack of clear specifications and different specifications on the same work item in the public entities. 7.2 Specifications One of the important documents in the contract documents that ensure the public entities achieve the required quality and value for money is specification. This is document essential document in the contract which clearly and accurately describes the essential technical requirements for items, materials, or services including the procedures by which it can be determined that the requirements have been met. In this study, however, it was observed that there lack of consistency in preparing specifications with the public bodies in the same item of works. Some of the specifications are weak to extent that it is difficult for PEs to ascertain the works have been performed to the required quality. In LGAs it was revealed that there is a lack of clear specifications in the contracts as well as lack uniformity in the same item works. However, for case of TANROADS, it was observed that there are specifications prepared head quarter office and are being used by the all regions. To great extent inconsistency in specifications has been one of the major attributes to have different unit rates in the same activities. Normally, specifications are available for review before a contractor bids on a project, and are often relied upon by the contractor in order to provide an accurate quote. For this matter, the clear and unclear specifications will yield different unit rates. 7.3 Construction Materials The Tanzania construction industry market is flooded with a variety of construction materials. The materials in the market come from many different manufacturers (countries) with great variations in quality and price. Material prices especially for building works vary very much in the market leading to difficulties in selecting the ones to base during the establishing unit rate process. One of the important factors in establishing unit rate is the source of the materials as it has direct impact on the rate in terms of transportation and handling charges. During the study it was observed that the source of most of the materials is Dar es Salaam i.e. cement, bitumen, fuel, building materials etc. In fact the referred materials are major inputs in the project and account for significant portion of the project cost. The transport and handling charges as well as varieties with different qualities can be observed as major reasons of having significant different rates in the regions on the same work items. 30 Establishment of Unit Rates for Construction Works - PPRA 7.4 Labour Productivity Establishing unit rates for performing a piece of construction work, depends very much on labour productivity. Estimating labour production rates is subject to many diverse and unpredictable factors. The labour effort needed to perform a particular task varies with many factors, such as the relative experience, capability, morale of the workers, the size and complexity of the job, the climatic and topographic conditions, the degree of mechanization, amount of similar task repetition, etc. The complexity of these variables affecting productivity makes it difficult to estimate common production rates. During the study it was difficulties locate one stop centre for obtaining the labour productivities for various activities. The interviews with the contractors and clients also revealed that everyone has own production rates and there is no common agreement rates. It was also noted that productivity depends on the method use by the contractor in executing the works as methods differ from one to another. 7.5 Equipment /Plant Construction projects, especially civil engineering works are normally heavy equipment oriented as the cost of equipment/plants can range from 25 to 40% of the total project cost. Establishing unit rates for both building and roadworks projects depend much on equipment availability, production rate, capacity, condition, availability and the skills of equipment operators. These factors are among the determining factors of the unit rate for the activities involving equipment/plants. This study has revealed that there is a different hiring rate of equipment/plants within the region itself due to the scarcity of the equipment. Moreover, there is a significant different hiring rates one region to another and other regions there is no supplier of equipment/plants which necessitate to acquire the same from neighbour region. Most contractors who owned equipment/plants are not leasing out their equipment to other contractors primarily because the capacity of their fleet is engaged in executing their own projects and if it happen they normally leasing hiring rate higher than the market rate. 8.0 CONCLUSIONS AND RECOMMENDATIONS 8.1 Conclusions The survey has established lists of common activities in both building and road works with their average unit rates. This is pursuant to Section 7(1)(m) of the Public Procurement Act No. 21 of 2004 [PPA, CAP 410] which requires PPRA to establish a list of works, services and supplies in common use by more than one procuring entities. The prices of different common construction material have also been 31 Establishment of Unit Rates for Construction Works - PPRA obtained as well as average hiring prices for different plant and equipment. This database will be published to assist the government and suppliers, service providers, contractors and consultants to have access to the prevailing unit rates in common activities in construction works. Furthermore, the information may be used as basis or indicative figures by Procuring Entities when preparing engineers estimates. Some of the common activities we built up their rates from 1st principle. Some of these rates are noted to be on higher side and others on lower side of the collected average prices. This may be due to lack of proper description of work activities as well as specifications. 8.2 Recommendations The following recommendations include those from the Survey Team as well as recommendations which were given during the stakeholders’ workshop held on 21st April 2010. a) PPRA should publish historical average unit rates for common construction activities at regular intervals. PEs should submit the relevant data as required from time to time. b) There should be standard descriptions of activities in construction works as much as possible and to be harmonized by the relevant institutions i.e. LGAs Vs TANROADS for road works, TBA, LGAs and others for buildings works. c) Comparison of unit rates between TANROADS and LGAs to be based on the same standard of roads and specifications. d) PPRA should emphasize on PEs to use standardized or harmonised specifications for common activities. e) Survey should also be conducted for big projects since the scope of the current survey was limited to small projects and maintenance works. f) PPRA should collaborate with NCC in preparing indices for the construction industry due to NCC’s experience in establishing unit rates in the past. g) Research should be done on equipment/plants and labour productivity in order to establish credible data which will be used in the model while establishing unit rates for the activities. 32 Establishment of Unit Rates for Construction Works - PPRA h) The results should be compared with the studies already done by TACECA on equipment productivity and NCC on the labour productivity. i) PPRA should conduct studies on best practices from the countries that already established average unit rate for common activities in the construction industry to gain experience and if possible to benchmark. j) PPRA should prepare a model for establishment of unit rates for common activities. The model should allow users to enter their inputs based on the requirement of the projects such as materials prices, haulage distance, equipment/plants hiring rates and other inputs required for the activity in question and model to produce unit cost for executing the activity without including the overhead costs and profit margin. k) PPRA should prepare guidelines for use of the model by PEs. l) PPRA should review the threshold for exclusive preference for construction works to be in harmony with the Construction Industry Policy (CIP) threshold. m) To improve the quality of construction works, drafting of specifications for materials and products as well as workmanship should be enhanced and quality assurance and enforcement strengthened. n) There should be a well established and maintained database for construction labour and equipment productivity. o) PEs are obliged to ensure all procurement/ contracts related information is kept properly for future use. 33