Levelling Principle operation required in the determination of heights of points on the surface of the Earth Elementary Land Surveying ELS_Levelling05_06: 1 Equipment 1. Level with tripod (device to gives a truly horizontal line) 2. Levelling staff (a suitably graduated staff for reading vertical heights) 3. Chain/Tape (to enable the points leveled to be located relative to each other on a map) 4. Change plate (staff base plate) 5. Staff bubble Elementary Land Surveying ELS_Levelling05_06: 2 1 Elements of Surveyor’s Level 1. Telescope Diaphragm – plane glass on which a series of line is etched (cross-hairs) Parallax – in focusing the real image formed by the objective lens is made to lie in the same plane as diaphragm Procedure of focusing: a) Adjusting eyepiece to bring diaphragm into sharp focus b) Adjust focusing screw until no parallax Elementary Land Surveying ELS_Levelling05_06: 3 Elements of Surveyor’s Level 2. Compensating Device in Automatic Level The telescope need only be approximately levelled and then a compensating device corrects for the residual mislevelment Elementary Land Surveying ELS_Levelling05_06: 4 2 Levelling Staff 1. Sectional and assembled by slotting onto one another vertically 2. Made of aluminium alloy 3. E-shaped graduation (reading to 1mm for ordinary levelling) Elementary Land Surveying ELS_Levelling05_06: 5 Precision Levelling Staff 1. Used for more accurate work (accuracy to 0.1mm in use with precise level) 2. Spring-mounted at the top 3. Made of invar alloy (iron + nickel) which has a lower coefficient of expansion – unaffected by temperature effects Elementary Land Surveying ELS_Levelling05_06: 6 3 Levelling Terminology 1. Level line is a surface which is at a constant height relative to Mean Sea Level (MSL) and is a curved line 2. Horizontal line is tangential to the level line at any particular point and is perpendicular to the direction of gravity. Over short distance, the 2 lines are taken to coincide Elementary Land Surveying ELS_Levelling05_06: 7 Levelling Terminology (con’t) 3. Datum A level line is chosen in which the elevation of all points is referred a) Mean Sea Level (MSL) is the mean of tidal height over a period of time (> 19 years) b) Principal Datum Hong Kong (PDHK) – most of the works in HK refer to this. It is 1.230m below MSL (revised in June 1984) c) Chart Datum (CD) is a tidal datum for marine works and navigation Elementary Land Surveying ELS_Levelling05_06: 8 4 Relationship among different datums (Source: Lands Department, No Date) Elementary Land Surveying ELS_Levelling05_06: 9 Levelling Terminology (con’t) 4) Bench Marks Points of known elevation above PDHK a) Bench Mark (BM) – established on vertical surfaces such as walls of buildings or substantial structures Elementary Land Surveying ELS_Levelling05_06: 10 5 Levelling Terminology (con’t) 4. Bench Marks (con’t) b) Temporary Bench Marks (TBM) – constructed at locations on site or off site, where the level of the mark is calculated from PDHK 5. Reduced Level (RL) – the height of a point relative to PDHK 6. Height of Collimation is the height of collimation above PDHK +5.00 TBM +10.00 Elementary Land Surveying ELS_Levelling05_06: 11 Levelling Terminology (con’t) 7. Backsight (BS) – 1st sight taken after the level has been set up. It is also a sight taken to a point whose height above HKPD is known 8. Foresight (FS) – last sight taken before moving the level. It is also a sight taken to a point whose height is required to carry on the line of levels 9. Intermediate Sight (IS) – other staff readings taken between BS and FS 10. Change Point (CP) – the staff position at which a FS and then a BS readings are taken BS FS IS CP Elementary Land Surveying ELS_Levelling05_06: 12 6 Levelling Terminology (con’t) FS BS FS IS IS BS Elementary Land Surveying ELS_Levelling05_06: 13 Field Procedure 1. The level is set up at P where BM may be observed and readings taken at points A, B, C and D a) The 1st reading (BS) made with the staff on a point of known RL b) The staff is now held at points A, B and C (ISs) in turn, and record the readings c) A change point (CP) is chosen at D, owing to the nature of the ground and take the reading (FS) Elementary Land Surveying ELS_Levelling05_06: 14 7 Field Procedure (con’t) 2. The staff remains at point D. The level is moved to Q, set up and levelled a) Taking the reading on the staff at the change point D (BS) b) Followed by IS with the staff on E, F and G until a further change becomes necessary 3. This procedure is repeated until all the required levels have been obtained 4. The final staff position is at a point of known RL Elementary Land Surveying ELS_Levelling05_06: 15 Procedure in Levelling 1. Height of Collimation Method ¾ 1st find the height of the line of collimation above the datum Height of collimation (HC) = 128.480 + 3.222 = 131.702m PD a) level at B (rise from A to B) = height of collimation – reading at B = 131.702 – 1.414 = 130.288m PD b) level at B (rise from A to B) = height of collimation – reading at B = 131.702 – 3.484 = 128.218m PD Elementary Land Surveying ELS_Levelling05_06: 16 8 Procedure in Levelling 2. Rise and Fall Method ¾ Rise – 2nd reading < 1st reading ¾ Fall - 2nd reading > 1st reading b) from A to B a) from A to B 1st reading – 2nd reading = 3.222 – 1.414 = 1.808 (rise) level at B (rise from A to B) = level at A + rise = 128.480 + 1.808 = 130.288mPD 1st reading – 2nd reading = 3.222 – 3.484 = -0.262 (fall) level at B (fall from A to B) = level at A - fall = 128.480 + 0.262 = 128.218mPD Elementary Land Surveying ELS_Levelling05_06: 17 Booking and Calculation 1) Rise and Fall Method – each reading is entered on a different line in the appropriate column, except at a change point, where a FS and BS occupy the same line. To check, ΣBS - ΣFS = ΣRise - ΣFall = Last RL – First RL BS IS FS Rise Fall RL Remarks 98.760 BM 1.283 97.477 A 98.415 B 0.145 98.270 C 0.432 97.838 D (CP) 0.663 1.946 1.008 0.938 1.153 2.787 1.585 2.270 0.517 98.355 E 1.218 1.052 99.407 F 0.646 0.572 99.979 G 2.231 3.079 3.450 1.860 99.979 2.231 1.860 98.760 1.219 1.219 1.219 Elementary Land Surveying ELS_Levelling05_06: 18 9 Booking and Calculation (con’t) 2) Height of Collimation Method – the collimation height is obtained by adding the staff reading, which must be a BS, to the known RL of the point on which the staff stands. To check, ΣBS - ΣFS = Last RL – First RL BS IS FS Collimation RL Remarks 99.423 98.760 BM 1.946 97.477 A 1.008 98.415 B 1.153 98.270 C 97.838 D (CP) 98.355 E 0.663 2.787 1.585 100.625 2.270 1.218 3.450 99.407 F 0.646 99.979 G 2.231 99.979 2.231 98.760 1.219 1.219 Elementary Land Surveying ELS_Levelling05_06: 19 Comparison Rise and Fall Method ¾ More accurate ¾ More calculation ¾ Intermediate RLs are known Height of Collimation Method ¾ Quicker ¾ Good for a lot of ISs Elementary Land Surveying ELS_Levelling05_06: 20 10 Accuracy in Levelling For normal engineering works and site surveys Allowable misclosure = ± 5 √ n mm where n = no. of instrument positions OR Allowable misclosure = ± 12 √ k mm where k = length of levelling circuit in km If actual misclosure > allowable misclosure, levelling should be repeated If actual misclosure < allowable misclosure, misclosure should be equally distributed equally between the instrument positions Elementary Land Surveying ELS_Levelling05_06: 21 Summary of Levelling Fieldwork For levelling fieldwork, the following practice should be adhered to in order to improve the accuracy of the levelling works. 1. Levelling should always start and finish at points of known RL so that misclosure can be detected 2. Where possible, all sight lengths should be below 60 m 3. The staff must be held vertically by suitable use of a bracket bubble 4. BS ≅ FS Lengths 5. Reading should be booked immediately after they are observed. Important readings, particularly readings at change points, should be checked 6. The rise and fall method of reduction should be used if possible, especially for control works Elementary Land Surveying ELS_Levelling05_06: 22 11 Collimation Error if level is set up, levelled and the line of sight or collimation is not truly horizontal, it will sweep out a cone as it is rotated. this cone will be either above or below the horizontal plane Staff Horizontal Line Level Line of Sight Elementary Land Surveying ELS_Levelling05_06: 23 Permanent Adjustment – Two Peg Test 1. On fairly level ground, set 2 points A and B, a maximum of 60m apart. Let this distance be L metres 2. Set up the level exactly midway between the points at point C and level carefully 3. Place a levelling staff at each peg in turn and obtain readings S1 and S2 S1 – S2 = (S1’ + x ) – (S2’ + x) = S1’ – S2’ = true difference on height between A and B X is the error due to collimation error (inclination of the collimation line by angle α Elementary Land Surveying ELS_Levelling05_06: 24 12 Permanent Adjustment – Two Peg Test 4. Move the level so that it is L/10 metres from point B at D. Take readings S3 and S4 Apparent difference in height between A and B = S3 – S4 If there is any difference between the apparent and true value, e = (S1 – S2) – (S3 – S4) m per L metres (e should be less than ±0.5mm per 10 m for average precision) Elementary Land Surveying ELS_Levelling05_06: 25 Permanent Adjustment – Two Peg Test 5. Any error e of the level should be adjusted using the adjusting screw with the collimation line altered to the correct staff reading For example, to adjust the level with instrument at D and staff at A, S4’ = S4 – e(L/10 + L) / L 6. The test should be repeated to ensure that the adjustment has been successful Elementary Land Surveying ELS_Levelling05_06: 26 13 Two Peg Test - Example The reading obtained from a two-peg test carried out on an automatic level with a single levelling staff set up alternately at 2 pegs A and B placed 60m apart are as follows: 1. With the level midway between A and B Staff reading at A = 1.283m Staff reading at B = 0.860m 2. With the level positioned 5 m from peg B on the line produced from AB Staff reading at A = 1.612m Staff reading at B = 1.219m Find the collimation error (e) and corrected staff reading (S4’)? Elementary Land Surveying ELS_Levelling05_06: 27 Errors in Levelling Errors in Equipment 1. Collimation Error Keep sight distance roughly equal Check by two peg test regularly 2. Parallax Error Move eye with respect to eyepiece, see if any relative movement between target & cross-hairs, if so adjust eyepiece 3. Defects of Staff Zero error, check by tape, does not affect height difference if one staff is used 3-section staff should be properly extended 4. Tripod Robust, properly tightened On soft ground, force it firmly into the ground Elementary Land Surveying ELS_Levelling05_06: 28 14 Errors in Levelling (con’t) Field Errors 1. Staff not vertical Staff is held vertical with aid of a bracket bubble 2. Unstable ground A change plate should be used 3. Instrument not level Ensure that the circular bubble is centered before and after a reading is taken 4. Weather condition Avoid windy condition Avoid line of collimation close to the ground in hot weather 5. Checking Start and finish at points of known height Run a loop Elementary Land Surveying ELS_Levelling05_06: 29 Errors in Levelling (con’t) Reading and Booking Errors 1. Misreading of the staff graduation Keep sight distance < 60 m, otherwise it becomes impossible to take accurate readings 2. Erroneous Booking Carefully entered the reading into the fieldbook always read the staff, book the observation and then check that the recorded entry agrees with a second reading through the telescope. Elementary Land Surveying ELS_Levelling05_06: 30 15 Error adjustments in levelling calculations Elementary Land Surveying ELS_Levelling05_06: 31 Error adjustments in levelling calculations 1. Rise and Fall Method BS IS FS Rise Provisional RL Correction Corrected RL Remarks 32.640 - 32.640 BM 32.893 0.003 32.896 CH0 0.318 32.575 0.003 32.578 CH20 Fall 1.944 1.691 0.253 2.009 0.367 2.114 4.425 0.833 31.742 0.003 31.745 CH40 1.223 2.842 0.856 30.886 0.005 30.891 CH60 1.347 0.124 30.762 0.005 30.767 CH80 0.775 0.572 31.334 0.005 31.339 CH100 0.816 1.298 32.632 0.008 32.640 BM 4.433 2.123 2.131 32.632 4.433 2.131 32.640 -0.008 -0.008 -0.008 Elementary Land Surveying ELS_Levelling05_06: 32 16 Error adjustments in levelling calculations 2. Height of Collimation Method BS Collimation Provisional RL Correction Corrected RL Remarks 34.584 32.640 - 32.640 BM 32.893 0.003 32.896 CH0 32.575 0.003 32.578 CH20 31.742 0.003 31.745 CH40 1.223 30.886 0.005 30.891 CH60 1.347 30.762 0.005 30.767 CH80 31.334 0.005 31.339 CH100 0.816 32.632 0.008 32.640 BM 4.433 32.632 IS FS 1.944 1.691 2.009 0.367 2.842 2.114 4.425 0.775 32.109 33.448 4.433 32.640 -0.008 -0.008 Elementary Land Surveying ELS_Levelling05_06: 33 Error adjustments in levelling calculations Note: ¾ Misclosures = -0.008m ¾ No. of instrument station = 3 ¾ Correction is +0.0027m and is added to the RL found from each instrument station ¾ No adjustment is applied to the initial BM, since this level cannot be altered. Elementary Land Surveying ELS_Levelling05_06: 34 17 Additional Levelling Methods 1. Inverted Staff ¾ Used to determine the RL of points, such as the soffit of a bridge, underpass or canopy ¾ The inverted staff reading is booked with a negative sign BS IS FS Rise Fall 1.750 -3.100 4.850 1.490 4.590 -4.210 -2.560 1.640 8.900 Remarks BM 77.150 A) Frame (lift-shaft) 72.560 B) Floor Level 76.610 C) Canopy 8.410 68.200 D) Kerb 13.000 68.200 4.050 4.200 -2.460 RL 72.300 1.640 13.000 72.300 -4.100 -4.100 -4.100 Elementary Land Surveying ELS_Levelling05_06: 35 Example BS IS FS 1.432 -0.874 -1.235 Collimation RL 31.432 30.000 TBM A 31.793 32.667 Top of wall -1.107 0.558 32.900 Arch soffit 1.383 30.410 B 0.148 30.410 0.148 30.000 0.410 BS Remarks 0.410 IS FS Rise Fall 1.432 -0.874 -1.235 -1.107 2.667 0.233 1.383 0.558 0.148 2.900 RL Remarks 30.000 TBM A 32.667 Top of wall 32.900 Arch soffit 2.490 30.410 B 2.490 30.410 0.148 2.490 30.000 0.410 0.410 0.410 Elementary Land Surveying ELS_Levelling05_06: 36 18 Additional Levelling Methods 2. Reciprocal Levelling ¾ ¾ By means of reciprocal levelling, the need for applying curvature and refraction corrections may be avoided 2 similar instruments in correct adjustment are required H = ((a1 – b1) + (a2 – b2)) / 2 Elementary Land Surveying ELS_Levelling05_06: 37 Example In levelling across a river, reciprocal levelling observations gave the following results for staffs held vertically at X and Y from level stations A and B on each bank respectively: ¾ Staff ¾ Staff ¾ Staff ¾ Staff reading reading reading reading of of of of X X Y Y from from from from A B A B = = = = 1.753m 2.080m 2.550m 2.895m If the RL of X is 90.370m PD, calculate the RL of station Y. (note: Y is lower than X) Elementary Land Surveying ELS_Levelling05_06: 38 19 Effects of Earth’s Curvature and Atmospheric Refraction A. Earth’s Curvature In Δ, L2 + R2 = (R + c)2 L2 = (R + c)2 - R2 L2 = 2cR + c2 L2 ≅ 2cR c ≅ L2 / 2R (km) = 0.0785 L2 (m) where radius of the Earth, R ≅ 6370 km and L in km Elementary Land Surveying ELS_Levelling05_06: 39 Effects of Earth’s Curvature and Atmospheric Refraction Refraction ¾ Line of sight is not really horizontal and bent downwards towards the Earth ¾ Value not constant, affected by pressure, temperature, latitude, humidity etc. ¾ Usually taken as 1/7 and opposite of the correction of curvature Combined correction = 0.0785 L2 * (6/7) = 0.0673 L2 (m) where L in km If L = 120m, c = -0.00097m ≅ 0.001m ≅ 1mm The effect is negligible for ordinary levelling Elementary Land Surveying ELS_Levelling05_06: 40 20 Example A staff is held at a distance of 200m from a level and a reading of 2.758m obtained. Calculate the reading corrected for curvature and refraction. Elementary Land Surveying ELS_Levelling05_06: 41 21