SuPER PROJECT WIRING AND SYSTEM PROTECTION by Jennifer Cao Senior Project ELECTRICAL ENGINEERING DEPARTMENT California Polytechnic State University San Luis Obispo 2006 ii TABLE OF CONTENTS Section Page List of Figures and Tables…………………………………………………….iii Acknowledgements…………………………………………………………….v Abstract………………………………………………………………………..vi I. Introduction……………………………………………………………………1 II. Background…………………………………………………………………....3 III. Requirements………………………………………………………………….7 IV. Design………………………………………………………………………..11 V. Testing………………………………………………………………………..19 VI. Conclusions and Recommendations…………………………………………30 VII. Bibliography…………………………………………………………………32 Appendices A. Parts List and Cost……………………………………………………………….33 B. Time Schedule Allocation………………………………………………………..36 iii LIST OF FIGURES AND TABLES Figures Page 1. Simplified SuPER System Block Diagram…………………………………………5 2. SuPER System Wiring Diagram…………………………………………………..13 3. SuPER System Combiner Box and Load Outlets…………………………………16 4. SuPER System Switchboards Junction Box……………………………………....17 5. SuPER System Wiring, Rearview……..……………………………………….….18 6. Motor Current Draw vs. Torque…………………………………………………..21 7. Motor Power vs. Torque…………………………………………………………..22 8. Motor Speed vs. Torque…………………………………………………………...22 9. Motor Voltage vs. Torque…………………………………………………………23 10. Motor Efficiency vs. Torque……………………………………………………..23 11. Operational Motor Current Draw vs. Torque……………………………………25 12. Operational Motor Power vs. Torque……………………………………………26 13. Operational Motor Speed vs. Torque…………………………………………….26 14. Operational Motor Voltage vs. Torque…………………………………………..27 15. Operational Motor Efficiency vs. Torque………………………………………..27 16. Motor Speeds vs. Torque Comparison…………………………………………...28 Table Page I. SuPER System Daily Use……….…………………………………………………..4 II. SuPER System Currents……………………………………………………………7 iv III. SuPER System Load Currents…..………………………………………………...8 IV. DC Motor Characteristics………………………………………………………..21 V. Operational DC Motor Characteristics…………………………………………...24 VI. Price List and Cost……………………………………………………………….33 VII. Estimated Time Schedule……………………………………………………….36 VIII. Actual Time Used………………………………………………………...……37 v ACKNOWLEDGEMENTS I would like to dedicate my senior project to my parents and friends for all of their support and encouragement. I would like to give a special thank you to my advisor, Dr. Ali Shaban, the SuPER team, and to my friend Kenneth Poulter for their knowledge and assistance. vi ABSTRACT This senior project focuses on connecting together the components of the SuPER system prototype in a safe fashion, following the National Electrical Code as much as possible. The prototype is a design of a 12V photovoltaic system that is to provide 400WH/day to a domestic household in a third world country. This senior project report will discuss the system parameters and requirements, the design and implementation of the system, and the testing of the system connections. It also includes the wiring diagram and parts list, which is the groundwork to be built upon in the future. In addition, this report will include recommendations for the next generation prototype. 1 I. INTRODUCTION The Sustainable Power for Electrical Resources (SuPER) project came to life due to a professor who had a vision of providing electricity to people in underdeveloped areas of the world. According to Dr. James Harris, approximately one third of the world’s population does not have access to electrical power [1]. His idea was to provide low-cost, sustainable power for individual households with a 20year life cycle [2]. Using a photovoltaic source was the most logical way to provide this energy, because solar energy is plentiful in third world countries. The development of this low cost photovoltaic system will take some time, but using the Moore’s Law method, the vision will be utilized by rural families in the near future. The SuPER system uses a photovoltaic source and a battery for energy storage. The battery will be used to provide power when the photovoltaic cannot provide enough alone, such as during the night or on cloudy days. The system provides direct current (DC) power to the loads. DC power is used instead of alternating current (AC) power, because the photovoltaic cell and battery are inherently DC. In addition, since the system is to provide energy to a single household, and will not be connected to a grid, long distance transmission is not necessary. Therefore, DC to AC conversion is not required. DC power is quite useful and practical since LED lighting is more efficient than incandescent bulbs, and there are many appliances on the market that use DC power. 2 My senior project was to design and implement the wiring and system protection of the SuPER system. The wiring will connect all of the system components together. The system consists of the photovoltaic array, the DC-DC converter, and the combiner box, switch and controller boards, all of the sensors, the battery, and the loads. In this report, the process of my senior project from the background, to the requirements, design, construction, testing, and my conclusion will be discussed. There is a wiring diagram that is included that shows how all of the components are connected, which type of protection devices are used, and the approximate lengths of and types of conductors used. 3 II. BACKGROUND With the diminishing amount of fossil fuels left and the growing knowledge plus development of solar panels, many parts of the world are using photovoltaic sources for their power needs. People are trying to not use the power from the utility company’s grid, but instead powering their homes with their own solar panels. Families are even selling back power to the utility companies. Sometimes a distributed electrical power grid is not always available to connect to, in the case of recreational vehicles (R.V.) that connect to the grid in order to use the AC power or invert it to DC power, when they can. In other times when the grid is not available, they use their charged batteries for use in the coach area of the vehicle. Although, more and more of these R.V.s now have solar panels on their roofs. This allows them to be in rural areas and not have to depend on the grid. In addition, many of the R.V. appliances use DC power, which makes solar power the way to go. Such appliances include overhead lights, the furnace fan, the fan over the range, the vent fan in the bathroom, the water pump, LP gas leak detector, stereo, and the refrigerator when it is in the LP gas mode [3]. These R.V.s also have a power distribution system and panel with system protection devices such as circuit breakers and fuses. There are also companies such as SunWize Technologies that have developed a portable power generator. This generator is a transportable source of battery power. It can generate either AC or DC power to run small appliances like laptop computers, lights, small 4 power tools or televisions, and fans. The battery is recharged from photovoltaic modules. This system is only meant for emergency power, farms, camping and boating, or other like kind situations. This system also does not need fuel and requires little maintenance [4]. This system sounds like what the SuPER project is trying to achieve, however the system currently is retailed for $1,496. At this price, the families we are trying to get electricity to cannot afford a system of this kind. With the technology already in place, and will continue to develop, and as the demand grows, the components of the system will become less expensive. That is what we are planning for. That is where the SuPER system comes in. This system will consist of a photovoltaic panel that will provide DC power into a DC-DC converter that will then charge up a battery at 12-volt and provide the 12-volt to loads such as a refrigerator, lights, a laptop computer, and a pump. The expected summary of the daily use is noted in Table I [2]: Table I: SUPER SYSTEM DAILY USE Daily Source Solar Energy Production Total Energy use Allocation Lighting Pump/motor Computer/communications Portable battery charging Energy storage: 12V AGM lead acid battery rated at 66 A h (Wh) 400 397 60 187 100 50 The total cost goal of the system is to be under $500. This price includes the cost to replace the battery every five years. This system is to have a life cycle of 20 years. 5 With this price, a family will only spend $2-3 per month, making this an affordable system for a family in an underdeveloped country. Since all of these systems have different components that work together, and will be used by people to power up equipment that can be expensive, all of them need to be wired and protected. That is what my goal was for my senior project, to do a system wiring and protection of the SuPER system. The SuPER system’s simplified block diagram is displayed below in Figure 1 [5]. The major parts of the system had to be wired together following the National Electrical Code as much as possible. Figure 1: Simplified SuPER System Block Diagram The photovoltaic panel that was used for the SuPER system was a prior donation to the California Polytechnic State University. The panel is a BP-150SX. 6 The rated maximum power output voltage is 34.5V and rated current is 4.35A. The battery, which is used to store the energy produced is a 12V deep cycle gel, made by MK (MK-8G31DT). The battery that was actually purchased is rated for 98 Ah at 4.88 current draw. This is a good choice, since for a 400 Wh, 12V system, the minimum battery capacity is 33 Ah and it is ideal to use a battery with at least double the storage capacity required [5]. The DC-DC currently used is manufactured by OutBack Power Systems. This will be replaced soon by a DC-DC buck converter, designed by students. The DC-DC converter will convert the approximately 40V DC from the solar panel to a useable 12V DC to charge up the battery and supply voltage to the loads. The wiring to the different loads also is implemented. There were five loads that were planned for, but only four loads were wired for. The fifth load does have all of the equipment and protection ready for wiring. There are also some switch printed circuit boards, a PIC, and sensor boards, which have voltage, current, and temperature sensors on them that needed power supplied to them. The PIC is a device that is connected to a PC, which is used to generate a PWM drive signal for a DC-DC converter, in order to transfer energy from the photovoltaic panel to the battery and loads. These are all of the major components of the SuPER system. 7 III. REQUIREMENTS The goal was to link and power all of the different components of the system. In order to achieve this goal, the different specifications of the components needed to be tested and figured out. The most important specification was the current. This is because these components will be connected together through conductors. Following the NEC, conductors come in different sizes, which correspond to the ampacity they can carry. The conductor length also comes into play for voltage drop. However, for this system, all of the loads, meaning everything that would be wired, would be connected within 50 feet or less of each other. The system is built on a moving cart, therefore there would not be enough voltage lost to worry about. Therefore the requirements were only based on the current. In discussing the other components and their test results with the other members of the SuPER team, the currents that would be flowing in the system were determined. These currents are listed in Table II. Table II: SUPER SYSTEM CURRENTS Component Photovoltaic DC-DC Converter Battery Current (A) 4-8 15 30 After having these currents determined, I had to figure out the currents for each of the loads we were considering. These were the loads that would connect to the system 8 and use the energy that the system was providing. For these current requirements, since we did not have the actual loads and their specifications, I looked at the system expected daily use from Table I. Using this table and information Dr. Harris had written in his NSF RUI proposal [6] about the expected usage time, I was able to characterize/define some of the electrical loads. By using the following equations, the expected currents were calculated: Watt[W ] * Hours[h] = Power[W ] RunningTime[h] Power[W ] I [ A] = 12[V ] The results of these calculations are in Table III below. Table III: SUPER SYSTEM LOAD CURRENTS Load Wh Hours Lights 60 4 TV 8 1 Refrigerator 50 6 Pump/Motor 187 1 Total current (A) 1.25 0.67 0.69 15.58 18.19 Each of these loads requires some sort of receptacle to connect to on the system cart. These are the receptacles that the conductors would actually connect to so that they could supply power to the terminals for a load to be plugged into. During the design process, we also decided to research for and install components for, but not wire for, a PC laptop. The reason we did not wire for such a laptop was that laptops run on 19V, and not 12V. However, they are only expected to draw about 3.5A. With this 9 information, I was able to find and install the components for later use. With this information and the information found in Table III, conductor sizes could be found for the receptacles. Besides finding the correct conductor to connect the system, my other requirement was to find ways in order to protect the system. With the current information, I was able to find the size of circuit breakers or fuses that needed to be used. At first, I just used circuit breakers in my design. Although, after testing and using the connected system, we found out that the circuit breakers did not act fast enough in some situations. From this, the circuit breaker for the motor was removed and switched out with a fuse. This fuse will act faster and help the components of the system stay protected. In addition, all of the protection equipment that was used had to be DC rated. To further protect the system, the system should be grounded. Usually in DC applications, there are only two conductors used, the positive and negative conductors. Although, based on an article, To Ground or Not to Ground: That is Not the Question, written by John Wiles, using a third, ground conductor, is the correct and NEC code compliant way to protect a photovoltaic system. The system is only then connected to a grounding electrode at one point in the system, usually in the power center (a.k.a load center, combiner box). Therefore, all of the ground conductors come together in the combiner box and that bus bar is connected to the system ground. Proper grounding effectively reduces potential problems that can result from surges and faults [7]. Reading the NEC codes, I found in article 250, that 10 for a system that is greater than 50V, but not greater than 300V, the system does not need to be grounded [8]. Our system currently only goes up to 40V. However, in order to ensure the safety of the people that will be handling the system and to protect the equipment, I decided to ground the system. 11 IV. DESIGN During the design process, the NEC Handbook was used to find as many codes and regulations that could be found that applied to our system. However, some codes were not followed due to cost and consideration that this is the first prototype. The future prototypes and final product should follow all codes. These recommendations will be mentioned in this and the conclusion sections. The first step I took in the design process was to create a diagram that showed where all of the parts were in the complete system. This diagram would show how everything is connected to each other. It also showed information, such as the expected voltage and current. The final diagram is shown in Figure 2. I decided to use red for the positive (hot) conductor, black for the negative (neutral) conductor, and green for the ground conductor. From there and using the currents calculated, I used Table 310.16 from the NEC to find the conductor size for each of the connections [8]. For most of the system we used size 10 AWG THHN/THWN stranded copper conductor, which is rated for up to 40A. It is always a best idea to overrate components in your system; however, this conductor size is overrated by quite a bit. It is mainly the choice of the designer, especially when costs matter. For the battery, although 10 AWG conductor is correctly rated, 6 AWG THHN/THWN-2 cable was used in order to best fit the connection to the terminals. For the loads, 12 however, we used 12 AWG non-metallic sheathed cable type NM-6 (romex) cable. 12 AWG copper conductor is rated for 30A. This cable type was used mainly because they will need to be connected to the receptacles. Most receptacles fit 12 AWG conductor. Also, solid conductor, instead of stranded conductor, is normally used due to the ease of attaching the conductor. The receptacles that I decided to use are AC rated receptacles. There is no standard DC receptacle out in the market currently, and the ones that are usually used are not practical or safe. The most common receptacle is the cigarette lighter plugs, which are flimsy, and their electrified terminals are exposed [9]. Ian Woofenden wrote in his article, “DC Receptacles & Plugs: Unsafe Connectors?,” about there should be a standard plug for DC applications out there. He discussed the various DC connector types out there and stated that they are expensive, unsafe, or not as practical as the typical AC plugs. He also mentions that the simplest and most common solution is the standard 120VAC receptacles. These are not tested or rated for DC and there is always the possibility that someone may accidentally plug 120VAC appliances into these receptacles that were wired for12VDC usage. He found that in these situations, installers and homeowners rely on labels or different colored receptacles to distinguish the receptacles. A more practical solutions, Woofenden says is using a 240VAC receptacle. These receptacles use a different configuration, as opposed to the 120VAC receptacle, for the prongs. This is a more expensive solution, but it allows for less confusion [9]. This article helped point me in the right direction in deciding on which receptacles to use. It was difficult to find a 240VAC receptacle at 13 Figure 2: SuPER System Wiring Diagram 14 the time, therefore I choose to use 120VAC 15A and one 20A, used for the motor outlet, for my design. Labeling was used to distinguish each outlet and what the current ratings are and that the receptacles are meant for DC usage. For the loads that we already obtained, some had to have their cords and/or plug adapters changed. The portable DC television had a power adapter that would convert the AC power to DC power for usage on an AC circuit. Consequently, the plug section was sliced off and an adapter for the 15A receptacle was installed. The refrigerator and laptop (with an adapter) had the cigarette lighter adapter. For these loads, a splitter and a cigarette lighter adapter converter to two clamps were purchased. For this situation, the two clamps were cut off and the conductors were connected to another 15A plug adapter. This allowed the splitter to be connected to the converter, and the converter connected to a receptacle. This was safe, since all of the conductors and receptacles were overrated, the actual two loads combined would not reach the rating. This solution worked out also because the outlet meant for the laptop had not been connected for the first prototype. For the pump, a Dayton ¼ horsepower permanent magnet motor (model 6MK98), was purchased in order to simulate it. This motor’s current is rated at 21A, therefore we used 10 AWG conductor instead of the 12 AWG romex cable. A 20A 120 VAC receptacle was used for this load however. Also, since the three conductors were not already protected and combined in a sheath, a non-metallic type LFNC-B conduit was used. This type of conduit is discussed in Article 356 of the NEC. The conduit is liquid tight and flexible. In order to know what size conduit to use, Table C.5 of the NEC is used. This table lists the type of conductor that would 15 go in the conduit and the conductor size and would then tell you what size conduit you need for all of the conductors to fit. In our case, the ½ inch size conduit was used. For the future prototype, all of the wiring and protection equipment storage used should be weather resistant (UV protected and liquid tight). This means that the conductors should be in some sort of protection, such as conduit, the entrance and exit holes of the combiner boxes and the boxes itself should also be protected or rated for weather resistance. In addition to creating an outlet for the motor, the motor needed a cord to connect to this outlet receptacle. A 10 AWG, three wire cable (SJO) was used for the cord and a 20A plug adapter was connected to the motor. The last set of wires used is 18 AWG, which can carry 14A, for all of the circuit boards and sensors for the system. These loads all needed to be powered up, but did not draw a lot of current. After obtaining all of the conductors for the system, an area where all of the conductors would go and combine had to be designed. This is also an area where the system protection would be. Since the system is DC, these components needed to be DC rated, and AC components could not be substituted. A PSPV Combiner Box and circuit breakers from OutBack Power were purchased. The circuit breakers were rated based on the currents found originally. The lights, television, and laptop are using 10A circuit breakers. The refrigerator has a 15A breaker. The battery and motor both have 30A circuit breakers, originally. The motor 30A circuit breaker later was switched out with a 30A fuse for faster response time. Then an extra power bus was connected to a 2A circuit breaker. This power bus bar is meant to power up the circuit boards and sensors. Lastly, the photovoltaic is connected to a 10A circuit 16 breaker that is isolated from the loads power bus. This is due to the different voltages that are involved. According to the NEC Article 720, if the voltages are less than 50V, two different voltages can be contained in the same combiner box. In creating the design, I also had to pay attention to grounding all of the metal enclosures. Basically, every component of the system had to have its enclosure grounded. Then from the combiner box, the neutral bus bar had to be grounded, and become the system ground. Once the design was together, which is Figure 2, the construction process began. The following Figures 3, 4, and 5 show the final wired and protected system. Figure 3: SuPER System Combiner Box and Load Outlets 17 Figure 4: SuPER System Switchboards Junction Box 18 Figure 5: SuPER System Wiring, Rearview 19 VI. TESTING The wiring system gets tested every time the system is turned on, since all of the loads are now being supplied from components on the cart instead of an external AC power source. All of the components get powered up and have not demonstrated any abnormal behaviors, which indicate that the wiring is correct and functioning as expected. Further testing is done by using the DC motor. A dynamometer was installed on the cart and connected to the motor in order to vary the torque and measure the speed of the motor. Using the following equation, the maximum torque was found: P[W ] = 1.18 x10 −2 * T [lb − in] * n[rpm] 1 (746) = 1.18 x10 − 2 * T *1800 4 T = 9.1624[lb − in] The rated speed of the motor, 1800 rpm, was found from the motor’s manual/specification sheet [10]. Before this information was calculated, the motor had been tested, by a SuPER project member, to a higher torque while connected to the rest of the system. This caused solder on a couple of traces on the main switchboard to melt, creating a short. The issue occurred partly due to the traces not being able to handle large current, and because the circuit breakers did not trip. This event led to the realization that the circuit breakers are meant only for fault currents and work slower than fuses. Since then, the circuit breaker for the motor has 20 been replaced by a 30A fuse. Once this issue was fixed, further motor testing could be done. Seeing as the main switchboard was still not functioning, this part of the circuit had to be bypassed. The motor was actually first tested isolated from the system by a SuPER project member, in order to test if the motor was working according to specifications. In order to perform this test, the motor was still connected to the dynamometer. A shunt was connected in series with the motor; on the neutral conductor (the plug adapter was disconnected). A voltmeter was connected across the shunt that measured values in mV, with a maximum of 50mV, which corresponded to 30A. This connection allowed the current to be measured. To find the current though, since only voltage was measured across the shunt, the mV value found had to be multiplied by 30A/50mV. Another voltmeter was connected across the neutral conductor of the motor and the positive DC supply, from the school’s power lab, in order to measure the voltage across the motor. This DC supply also was the source to power up the motor. Once, this configuration was connected, the torque, using the dynamometer, was adjusted and all measurements, including the speed was collected. The results are shown in Table IV. 21 Table IV: DC MOTOR CHARACTERISTICS Torque [lb-in] 0 0.5 1 1.5 2 2.5 3 3.5 4 5 6 7 8 Speed [rpm] 1840 1734 1670 1620 1588 1500 1470 1460 1425 1270 1140 1060 939 Voltage [V] 12.26 11.74 11.41 11.16 11.08 10.64 10.6 10.6 10.4 9.7 8.9 8.7 8.14 Current [A] 5.1 6.6 7.2 8.1 9 9.9 10.8 11.7 12.6 15 16.2 18 19.8 Power Efficiency [%] [W] 62.526 0.000 77.484 13.226 82.152 24.028 90.396 31.774 99.72 37.646 105.336 42.080 114.48 45.533 124.02 48.702 131.04 51.415 145.5 51.586 144.18 56.075 156.6 56.005 161.172 55.091 Figures 6 thru 10 show the effects of different parameters compared to the torque. Motor Current Draw vs. Torque 25 Current (amps) 20 15 Series1 10 5 0 0 2 4 6 8 10 Torque (lb-in) Figure 6: Motor Current vs. Torque 22 Motor Power vs. Torque 180 160 Power (watts) 140 120 100 Series1 80 60 40 20 0 0 2 4 6 8 10 Torque (lb-in) Figure 7: Motor Power vs. Torque Motor Speed vs. Torque 2000 Speed (rpm) 1800 1600 1400 1200 Series1 1000 800 600 400 200 0 0 2 4 6 8 10 Torque (lb-in) Figure 8: Motor Speed vs. Torque 23 Motor Voltage vs. Torque 14 12 Voltage (V) 10 8 Series1 6 4 2 0 0 2 4 6 8 10 Torque (lb-in) Figure 9: Motor Voltage vs. Torque Motor Efficiency vs. Torque 60.000 Efficiency (%) 50.000 40.000 Series1 30.000 20.000 10.000 0.000 0 2 4 6 8 10 Torque (lb-in) Figure 10: Motor Efficiency vs. Torque 24 These test results show that the motor is working according to specifications. This allows us to eliminate the motor as a cause for a problem when later testing is done on the system. The next step in testing the motor was to use the motor while it was connected to the SuPER system. For this case, the motor’s power is supplied from the photovoltaic and the battery. For the most part, the connection configuration was kept the same; however, the power supplied to the motor was now coming from the parallel connection of the photovoltaic and the battery. An additional voltmeter was also connected across the battery. The results from this test are in Table V. Table V: OPERATIONAL DC MOTOR CHARACTERISTICS Torque [lb-in] 0 0.5 1 1.5 2 2.5 3 3.5 4 5 6 7 8 Speed [rpm] 1960 1925 1895 1870 1839 1809 1784 1760 1719 1676 1622 1571 1523 Voltage Voltage Shunt of of Battery Motor Voltage [V] [V] [mV] 13.09 12.53 8 13 12.34 10.5 12.93 12.25 12 12.85 12.18 13.5 12.79 12.15 15.2 12.72 12.05 16.75 12.67 11.93 18 12.64 11.86 19.5 12.5 11.78 21 12.49 11.8 24.5 12.37 11.78 27.4 12.27 11.58 30.5 12.2 11.51 33.6 Current Power Efficiency [A] [W] [%] 4.8 60.144 0.000 6.3 77.742 14.634 7.2 88.2 25.396 8.1 98.658 33.606 9.12 110.808 39.234 10.05 121.1025 44.141 10.8 128.844 49.099 11.7 138.762 52.472 12.6 148.428 54.757 14.7 173.46 57.103 16.44 193.6632 59.398 18.3 211.914 61.338 20.16 232.0416 62.064 25 Figures 11 thru 14 show the effects of different parameters compared to the torque, while connected to the SuPER system. Motor Current Draw vs. Torque 25 Current (amps) 20 15 Series1 10 5 0 0 2 4 6 8 10 Torque (lb-in) Figure 11: Operational Motor Current Draw vs. Torque 26 Motor Power vs. Torque 250 Power (watts) 200 150 Series1 100 50 0 0 2 4 6 8 10 Torque (lb-in) Figure 12: Operational Motor Power vs. Torque Motor Speed vs. Torque 2500 Speed (rpm) 2000 1500 Series1 1000 500 0 0 2 4 6 8 10 Torque (lb-in) Figure 13: Operational Motor Speed vs. Torque 27 Motor Voltage vs. Torque 12.6 Voltage (V) 12.4 12.2 12 Series1 11.8 11.6 11.4 0 2 4 6 8 10 Torque (lb-in) Figure 14: Operational Motor Voltage vs. Torque Motor Efficiency vs. Torque 70.000 Efficiency (%) 60.000 50.000 40.000 Series1 30.000 20.000 10.000 0.000 0 2 4 6 8 10 Torque (lb-in) Figure 15: Operational Motor Efficiency vs. Torque 28 The current draw remained pretty much the same; however the power started out lower than before but went higher. The graph was also more linear. The speed was faster during this test. The motor voltage was also higher than when the motor was not connected to both the photovoltaic and battery. This affect may have occurred due to the DC-DC converter constantly monitoring and maintaining the battery voltage. These results tell us that when the photovoltaic is used, we are able to run the motor at higher speeds. Figure 15 shows the speeds for the two different conditions verses torque. Motor Speeds vs. Torque 2500 Speed (rpm) 2000 1500 Operational Motor Speed 1000 Characteristic Motor Speed 500 0 0 5 10 Torque (lb-in) Figure 16: Motor Speeds vs. Torque Comparison This conclusion is a good indication that the system works agreeably. 29 These tests prove that the motor function according to specifications and properly and that the wiring of the system can handle the currents when the system is operating. It also shows that the photovoltaic and battery can supply to a large load for reasonable amount of time. This demonstrates that the SuPER system could already be used to power loads. 30 VII. CONCLUSION AND RECOMMENDATIONS The wiring and connection including the protection, after some renovations, operate and function properly, and as intended. We have been able to use the system to power up all of the loads necessary. The SuPER system no longer needs to rely on an AC power source. Overall, the wiring and system protection is sufficient for the first prototype. As for recommendations for the future prototypes, the actual wiring scheme does not have to change, however the parts used should. As mentioned earlier, all of the parts should be protected from the environmental elements. The NEC code should be referenced and used more. Some of the recommended codes that should be looked at will be mentioned. Article 312 has a Table 312.6(B) that lists the minimum wire-bending space at terminals. This table affects the conductor length that we use due to the extra length needed to be used for the bending in and out of boxes. Article 314.16 mentions how many conductors can actually be in a box. As for entering boxes, conduit bodies, or fittings, there are regulations for the conductors in Article 314.17. Eventually, these boxes, the combiner box and switchboard junction box, should be manufactured by students. Articles 312.11 and 314 have construction and installation specifications. Bus bars will need to be installed in these boxes and Article 408.3 state how these should be arranged and supported. The system grounding should be studied in more detail. Since the first prototype is a moving cart 31 and there is no great place to install a grounding electrode; there is no proper system ground that the system can connect to. The article, To Ground or Not to Ground: That is Not the Question, mentioned earlier has great information on grounding and also refers to NEC code articles. These articles should be read in the current NEC code book. However, overall continued research should be done in order to find more codes and regulations that have not yet been identified. 32 VIII. BIBLIOGRAPHY [1] Harris, James G. Graduate Seminar: Development of Sustainable Power for Electrical Resources. EE 563 Graduate Seminar presentation 9/30/05: Development of Sustainable Power for Electrical Resources – SuPER System. September 30, 2005. [2] Harris, James G. White Paper for Sustainable Power for Electrical ResourcesSuPER. July 15, 2005. <http://www.ee.calpoly.edu/~jharris/research/super_project/white_paper_susp er.pdf> [3] Polk, Mark J. Basic RV Electricity. <http://rveducation101.com/Articles/Basic_RV_Electricity_Savvy.pdf>. [4] SunWize Technologies. Portable Power Generator. <http://www.sunwize.com/catalog/images/system_SW_PPG.pdf)>. [5] Tal, Eran. SuPER System Prototype Design and Implementation. Master Thesis. San Luis Obispo: California Polytechnic State University, 2006. [6] Harris, James G. NSF proposal. August 31, 2005. [7] Wiles, John. To Ground or Not to Ground: That is Not the Question. Home Power #72. August/September, 1999. [8] Earley, Mark W., et al. NEC 2005 Handbook. 10th ed. Quincy: National Fire Protection Association, Inc., 2005. [9] Woofenden, Ian. DC Receptacles & Plugs: Unsafe Connectors?. Home Power #111. February/March 2006. [10] Dayton DC Motors. Operating Instructions and Parts Manual - 6MK98, 6MK99, and 6ML01 thru 6ML07. 33 Appendix A: Parts List and Costs Table VI: PARTS LIST AND COSTS Product NEC Handbook and CD 2 A Circuit Breaker (Outback Power) 10 A Circuit Breaker (Outback Power) 15 A Circuit Breaker (Outback Power) 30 A Circuit Breaker (Outback Power) 30A, 600VDC Touch Safe Fuse Holder (OutbackSGOBFH30) 30A Midget Fuse (KTK30) PSPV Combiner Box (Outback Power) Bus Bar kit (Outback Power) 15 A Outlet Receptacle 20 A Outlet Receptacle Metal Switch Box Outlet Receptacle Cover 10/3 SJO Wire Price per unit 258.75 Quantity Total *Circuit breakers and combiner box are rated for DC usage 1 258.75 10.2 1 10.2 For circuit board 10.2 4 40.8 PV, lights, TV, laptop 10.2 1 10.2 2 10.2 Refrigerator Pump and Battery (Only one was used for Battery, Pump 20.4 (motor) used fuse) 18 2 8.8 2 118.15 16.15 For Motor and Battery (Only used one for 36 Motor) For Motor and Battery (Only used one for 17.6 Motor) Service Panel/Load 1 118.15 Center For circuit board 1 16.15 inside combiner box 0.48 4 1.92 For Loads 3.99 1.57 1 5 3.99 For pump/motor 7.85 Receptacle boxes 0.22 5 1.26 10 1.1 12.6 To make cord for 34 motor with plug 15A connector adapter plug 20A 125V connector adapter plug 10 AWG THHN stranded conductor (ft) 6 AWG THWN-2 stranded conductor (ft) 20/2 Bell Conductor 12 AWG THHN romex nonstranded wire (ft) Romex connectors Non-metallic Conduit 1/2" Conduit connectors Red Wire Connectors Yellow Wire Connectors Cable Ties 1" Sticky Mount Pads for Cable Ties Plywood (3/4 2x4 BC) Lug 1.99 2 9.68 1 0.37 130 0.68 6 0.18 35 Donated ~35 1.38 4 0.95 10 1.19 4 1.59 1 2.49 1 7.92 1 1.39 1 11.99 1 1 1 Connector for TV and car cigarette lighter 3.98 charger Connector for motor 9.68 receptacle 30 ft for Red and Black each, 70 ft for 48.1 Green 3 ft for Red and Black 4.08 each Bell is a red and a white 20 AWG conductor, used to power up circuit 6.3 boards and probes From circuit breakers 0 to receptacles For knockout holes in 5.52 boxes Type LFNC-B (liquid tight), from circuit breakers to 9.5 pump/motor To connect conduit to combiner box and 4.76 main switch box To connect larger 1.59 spliced wires To connect smaller 2.49 spliced wires A large assortment of 7.92 cable ties (zip ties) To mount ground 1.39 conductor to frame To mount panels and 11.99 outlets 1 To connect ground 35 Metal Junction Box 13.82 1 13.82 Bushing 1.29 1 1.29 Screws, washers, nuts 0.98 11 10.78 Spacers Electrical Tape 0.63 1.97 8 3 5.04 5.91 Plywood (3/4) 0.21 1 0.21 Pump Total 274.57 1 274.57 985.63 conductor to frame (had two) For Main Switch circuit board For knockout holes with just conductor For plywood to cart, receptacles, lug, circuit boards in panel, etc. For circuit boards to be spaced in main switchboard box Red, Black, Green Scrap piece to mount main switchboard Dayton DC motor 6MK98, 1/4 hp, 12V, permanent magnet *Prices do not include taxes or shipping 36 Appendix B: Time Schedule Allocation Table VII: ESTIMATED TIME SCHEDULE Estimated Time Task EE 463 Research and define connector, lead and grounding specifications Once SuPER cart with general components is built, implement loads on cart Design service panels Construct service panels Instrument cart with new service panels and ground protection EE 464 Research NEC for high voltage/low voltage service panel specifications Change service panels as needed Change plug adapters on all loads/get loads ready for testing Test loads and check wiring and ground protection Write Paper Hours 27 27 18 27 27 6 12 6 12 37 Table VIII: ACTUAL TIME USED Task EE 463 diagram (1st draft) diagram (2nd draft) diagram (3rd draft) diagram (4th draft) diagram (5th draft) Home Depot trip diagram (6th draft) Research Load Installed NEC CD to computer diagram (7th draft) Research Load Figured out what to buy Figured out what to buy/Changed price/spec list Home Depot trip Researched NEC codes Researched DC items Changed diagram a little (8th draft) Changed diagram (9th draft), ordered items, Date Hours Notes 3.00 2.00 1.00 4/10/2006 4/12/2006 4/14/2006 4/17/2006 4/20/2006 4/23/2006 4/24/2006 4/25/2006 4/25/2006 4/27/2006 4/28/2006 Computer crashed and had to redo the 2.00 changes Changed black conductor grounding location, changed black conductors to loads, added wall 1.00 outlets to loads and grounded them 1.00 Researched prices and products Added specs, made excel sheet of 2.00 products/prices Researched 1/4 hp, 12V, permanent magnetic DC motor. Emailed company to see if could 1.50 get a donation. Installed NEC CD and called tech support 0.50 about installing/uninstalling for license Added laptop load and changed pump circuit breaker from 20A to 40A. Added general bus 1.50 to excel price sheet 0.50 Prices with shipping to order Figured out the lengths of conductors to buy, 0.50 where to put panels, etc. 5/2/2006 0.75 Added items to buy, prices, notes, etc. 1.20 Purchased items, missing 40A single pole CB Tried to find wire stripping requirements, 1.00 found other codes that should follow Researched circuit breakers, panels, 3.50 conductors, connections, gauges, etc. Combined panels, rerouted conductors, made 2.50 conductors sizes more clear 5/4/2006 Changed diagram to add circuit board, entered actual prices of items purchased, ordered 1.50 parts/supplies 5/1/2006 5/2/2006 38 entered prices Parts 5/8/2006 diagram (10th draft) Returned items to Home Depot 5/10/2006 Home Depot trip 5/12/2006 Home Depot trip 5/13/2006 Home Depot trip Construct panel and install load receptacles 5/14/2006 5/14/2006 Pacific Home and Garden trip 5/15/2006 diagram (11th draft) and price/spec list Returned items to Pacific Home and Garden diagram (12th draft) 5/8/2006 Received parts, tried to install parts, read 1.00 diagrams/instructions Changed diagram to look more like PSPV Combiner box, moved circuit breakers and 2.75 loads around Returned AC circuit breakers, two AC panels, 1.00 and wiring books Bought 35 ft 20 AWG/2 bell wire (red and white, used as hot and negative) to power up circuit boards and for current probes (for the 0.75 other parts of the project.) Bought UL Non-Metallic Conduit type LFNC-B (liquid tight), 1/2" plastic conduit 1.00 connector, and water pipe ground clamp Bought Carol 10/3 90 C UL water-resistant SJOOW CSA (-40C) FT-2 P-7K-123033 MSHA 300 V wire to create cable with plug for motor, screws, mount pads for zip ties, romex connectors, ground lug for PV ground 1.50 conductor to metal frame 5/17/2006 Mounted panel and receptacle boxes to wood, 4.00 wired 3 loads + DC motor Bought ground screws, receptacle plug for motor, grommets for metal punch-outs in 1.00 panel, electrical tape Corrected red conductors going to and from PV and DC-to-DC converter, routed conductors for the circuit boards and probes, moved circuit board out of combiner box, added a box for conductors to run through circuit boards, ran all conductors through new 3.00 box, added items/prices 5/19/2006 Exchanged receptacle plug for motor and 0.75 grommets for correct ones (wrong sizes/fit) 5/23/2006 0.10 Added ground to switchboard metal box 39 Home Depot trip misc. store trips 5/19/2006 diagram (13th draft) 5/30/2006 Installation/Wired cart 6/4/2006 diagram (14th draft) Prices EE 464 Found NEC code for two different voltages in one combiner box Bought 15A plug adapter for DC TV Worked on diagram (15th draft) Worked on cleaning up the wires on the cart and got 2 prong adapter installed for TV and for car charger Cleaned up wires on the cart Researched and purchased fuses Installed fuse for motor Ran motor test Diagram (16th draft) 6/6/2006 6/6/2006 Bought plastic rings for conductors to go through instead of grommets, electrical tape, asked about metal box for switchboards, tried 1.00 to find plug to fit SO cable for motor 4.50 Changed the diagram, conductors needed to be removed/reversed from the pv to dc-to-dc 1.00 converter Installed switchboard box, wired everything 13.00 up Changed diagram after installation, removed some conductors from switchboard box, added ground conductor from PV again, 0.50 changed some conductor specs Added prices, deleted items 1.00 Art 720 10/10/06 0.50 10/12/06 0.50 changed 1A circuit breaker to 2A 10/17/06 4.00 10/18//06 1.00 4.00 11/1/06 11/7/06 11/10/06 1.00 3.00 With Solar Power and Battery Changed the 30A Circuit Breaker for the 0.50 motor to a 30A Fuse 40 Prices Total 11/10/06 0.50 Added items on price list 79.80 *Since many of the tasks fell into multiple categories picked for estimation, the actual tasks were not categorized. 41 Analysis of Senior Project Design Summary of Functional Requirements: The SuPER system is to provide DC electricity to a small family unit in an underdeveloped country. My portion of the project is to wire the system together and provide system protection. Primary Constraints: The main constraint for this project was the knowledge of the National Electrical Codes. Having access to the codes were not the issue, but knowing what to look for and how to understand the code is difficult. Unless I had prior knowledge of certain codes and regulations, I would not have known to look for them in the NEC. Other constraints were having the skills to easily assemble the system. Power tools had to be used, and some tasks needed strength. The construction of the project could have been done, however the ease and amount of time spent would be varied according to prior skill level. Economic: The estimated cost for the components of my project is listed in the following table: Circuit Breakers and Panels were all AC rated Estimate Product Product NEC 15 A Circuit Breaker 20 A Circuit Breaker 40 A Circuit Breaker Price per unit Price per unit 300 Quantity Total Notes Quantity 1 Total 300 3.19 4 12.76 2.99 1 2.99 1 Load 8.7 2 17.4 Pump and Battery 3 Loads, 1 Panel for PV 42 6 space outdoor 100A panel 2 space outdoor 70A panel 4 ground bar (bus) Outlets 10 AWG wire (single wires) 6 AWG wire (estimate per foot) Plywood (30 x 18) 8 ft Ground Rod Screws Water Pipe Clamp (Ground Rod) Pump Total 22.49 1 22.49 Service Panel 19.97 1 19.97 Panel for PV 4.27 0.5 1 6 4.27 3 for DC-to-DC converter for Loads 0.9 130 117 30 ft for Red and Black each, 70 ft for Green 0.9 6 5.4 3 ft for Red and Black each 1 0 To mount panels and outlets 1 For plywood to cart, onto plywood, ground screw? 3.52 1 3.52 274.57 1 274.57 783.37 Clamp onto water pipe to substitute ground rod Dayton DC motor 6MK98, 1/4 hp, 12V, permanent magnet However, the estimated prices were for AC rated components and not DC rated. Also, as the construction went on, many more items needed to be purchased to put the system together. The actual products purchased and prices are listed in the following table: 43 Actual Product NEC Handbook and CD 2 A Circuit Breaker (Outback Power) 10 A Circuit Breaker (Outback Power) 15 A Circuit Breaker (Outback Power) 30 A Circuit Breaker (Outback Power) 30A, 600VDC Touch Safe Fuse Holder (OutbackSGOBFH30) 30A Midget Fuse (KTK30) PSPV Combiner Box (Outback Power) Bus Bar kit (Outback Power) 15 A Outlet Receptacle 20 A Outlet Receptacle Metal Switch Box Outlet Receptacle Cover 10/3 SJO Wire 15A connector adapter plug 20A 125V connector adapter plug 10 AWG THHN stranded wire (ft) 6 AWG THWN-2 stranded wire (ft) 20/2 Bell Wire 12 AWG THHN romex non-stranded *Circuit breakers and combiner box are rated for DC usage Price per unit Quantity 258.75 1 258.75 10.2 1 10.2 For circuit board 10.2 4 40.8 PV, lights, tv, laptop 10.2 1 10.2 Refrigerator Pump and Battery (Only one was used for Battery, Pump (motor) used fuse) Total 10.2 2 20.4 18 2 36 8.8 2 17.6 118.15 1 118.15 16.15 1 16.15 0.48 4 1.92 For Loads 3.99 1.57 1 5 3.99 7.85 For pump/motor Receptacle boxes 0.22 5 1.1 1.26 10 12.6 1.99 2 3.98 9.68 1 9.68 0.37 130 48.1 0.68 6 4.08 0.18 35 6.3 Donated ~35 0 For Motor and Battery (Only used one for Motor) For Motor and Battery (Only used one for Motor) Service Panel/Load Center For circuit board inside combiner box To make cord for motor with plug Connector for TV and car cigarette lighter charger Connector for motor receptacle 30 ft for Red and Black each, 70 ft for Green 3 ft for Red and Black each Bell is a red and a white 20 AWG wire, used to power up circuit boards and probes From circuit breakers to receptacles 44 wire (ft) Romex connectors Non-metallic Conduit 1/2" Conduit connectors Red Wire Connectors Yellow Wire Connectors Cable Ties 1" Sticky Mount Pads for Cable Ties Plywood (3/4 2x4 BC) Lug Metal Junction Box Bushing Screws, washers, nuts 1.38 0.95 4 5.52 10 9.5 1.19 4 4.76 1.59 1 1.59 2.49 1 2.49 7.92 1 7.92 1.39 1 1.39 11.99 1 11.99 1 1 1 13.82 1 13.82 1.29 1 1.29 0.98 11 10.78 Spacers Electrical Tape 0.63 1.97 8 3 5.04 5.91 Plywood (3/4) 0.21 1 0.21 274.57 1 274.57 985.63 Pump Total For knockout holes in boxes Type LFNC-B (liquid tight), from circuit breakers to pump/motor To connect conduit to combiner box and main switch box To connect larger split wires To connect smaller split wires A large assortment of cable ties (zip ties) To mount ground wire to frame To mount panels and outlets To connect ground wire to frame (had two) For Main Switch circuit board For knockout holes with just wire For plywood to cart, receptacles, lug, circuit boards in panel, etc. For circuit boards to be spaced in main switchboard box Red, Black, Green Scrap piece to mount main switchboard Dayton DC motor 6MK98, 1/4 hp, 12V, permanent magnet For the estimated time, I believe that I estimated more time for certain tasks than it actually took and not enough time for tasks that ended up taking longer. My estimated times are listed in the following table: 45 Estimated Time Task Hours EE 463 Research and define connector, lead and grounding specifications 27 Once SuPER cart with general components is built, implement loads on cart 27 Design service panels 18 Construct service panels 27 Instrument cart with new service panels and ground protection EE 464 27 Research NEC for high voltage/low voltage service panel specifications Change service panels as needed Change plug adapters on all loads/get loads ready for testing Test loads and check wiring and ground protection Write Paper 6 12 6 12 The actual time was difficult to categorize as I had done for the estimation, due to the fact that many of the tasks occurred at the same time or had to do with each other. Therefore, my actual time is a total of the time spent, and is shown in the following table: 46 Task EE 463 diagram (1st draft) diagram (2nd draft) diagram (3rd draft) diagram (4th draft) Date Hours 3.00 4/10/2006 2.00 1.00 2.00 diagram (5th draft) Home Depot trip diagram (6th draft) 4/12/2006 4/14/2006 4/17/2006 1.00 1.00 2.00 Research Load Installed NEC CD to computer 4/20/2006 1.50 4/23/2006 0.50 diagram (7th draft) Research Load Figured out what to buy Figured out what to buy/Changed price/spec list Home Depot trip Researched NEC codes Researched DC items Changed diagram a little (8th draft) Changed diagram (9th draft), ordered items, entered prices Notes 4/24/2006 4/25/2006 1.50 0.50 4/25/2006 0.50 4/27/2006 4/28/2006 0.75 1.20 5/1/2006 1.00 5/2/2006 3.50 5/2/2006 2.50 5/4/2006 1.50 5/8/2006 1.00 Parts diagram (10th draft) Returned items to Home Depot 5/8/2006 2.75 5/10/2006 1.00 Home Depot trip 5/12/2006 0.75 Computer crashed and had to redo the changes Changed black wire grounding location, changed black wires to loads, added wall outlets to loads and grounded them Researched prices and products Added specs, made excel sheet of products/prices Researched 1/4 hp, 12V, permanent magnetic DC motor. Emailed company to see if could get a donation. Installed NEC CD and called tech support about installing/uninstalling for license Added laptop load and changed pump circuit breaker from 20A to 40A. Added general bus to excel price sheet Prices with shipping to order Figured out the lengths of wires to buy, where to put panels, etc. Added items to buy, prices, notes, etc. Purchased items, missing 40A single pole CB Tried to find wire stripping requirements, found other codes that should follow Researched circuit breakers, panels, wires, connections, gauges, etc. Combined panels, rerouted wires, made wires sizes more clear Changed diagram to add circuit board, entered actual prices of items purchased, ordered parts/supplies Received parts, tried to install parts, read diagrams/instructions Changed diagram to look more like PSPV Combiner box, moved circuit breakers and loads around Returned AC circuit breakers, two AC panels, and wiring books Bought 35 ft 20 AWG/2 bell wire (red and white, used as hot and negative) to power up circuit boards and for current probes (for the other parts of the project.) 47 Home Depot trip 5/13/2006 1.00 Bought UL Non-Metallic Conduit type LFNC-B (liquid tight), 1/2" plastic conduit connector, and water pipe ground clamp Bought Carol 10/3 90 C UL water-resistant SJOOW CSA (-40C) FT-2 P-7K-123033 MSHA 300 V wire to create cable with plug for motor, screws, mount pads for zip ties, romex connectors, ground lug for PV ground wire to metal frame Home Depot trip 5/14/2006 1.50 Construct panel and install load receptacles 5/14/2006 4.00 Pacific Home and Garden trip 5/15/2006 1.00 diagram (11th draft) and price/spec list 5/17/2006 3.00 Mounted panel and receptacle boxes to wood, wired 3 loads + DC motor Bought ground screws, receptacle plug for motor, grommets for metal punch-outs in panel, electrical tape Corrected red wires going to and from PV and DCto-DC converter, routed wires for the circuit boards and probes, moved circuit board out of combiner box, added a box for wires to run through circuit boards, ran all wires through new box, added items/prices 5/19/2006 0.75 Exchanged receptacle plug for motor and grommets for correct ones (wrong sizes/fit) 5/23/2006 0.10 5/19/2006 1.00 4.50 5/30/2006 1.00 6/4/2006 13.00 Returned items to Pacific Home and Garden diagram (12th draft) Home Depot trip misc. store trips diagram (13th draft) Installation/Wired cart diagram (14th draft) Prices 6/6/2006 6/6/2006 Added ground to switch board metal box Bought plastic rings for wires to go through instead of grommets, electrical tape, asked about metal box for switch boards, tried to find plug to fit SO cable for motor Changed the diagram, wires needed to be removed/reversed from the pv to dc-to-dc converter Installed switchboard box, wired everything up 0.50 Changed diagram after installation, removed some wires from switchboard box, added ground wire from PV again, changed some wire specs Added prices, deleted items 1.00 Art 720 EE 464 Found NEC code for two different voltages in one combiner box Bought 15A plug adapter for DC tv Worked on diagram (15th draft) 10/10/06 0.50 10/12/06 0.50 changed 1A circuit breaker to 2A 48 Worked on cleaning up the wires on the cart and got 2 prong adapter installed for tv and for car charger Cleaned up wires on the cart Researched and purchased fuses Installed fuse for motor Ran motor test Diagram (16th draft) Prices Total 10/17/06 4.00 10/18//06 1.00 4.00 11/1/06 11/7/06 1.00 3.00 11/10/06 11/10/06 0.50 0.50 79.80 With Solar Power and Battery Changed the 30A Circuit Breaker for the motor to a 30A Fuse Added items on price list If Manufactured on a commercial basis: The end product is estimated at around $500 per unit for a life cycle of 20 years. This price also includes the replacement battery every five years. Purchase price and the number of units sold per year are yet to be determined. However, the estimated profit per year is about 5-10% of the investment. Environmental: This system is a photovoltaic power supply system, therefore should be safe for the environment. The only part of our system that could be an environmental impact is the battery when it is disposed of. The battery has to be disposed of correctly and safely. Manufacturability: The portion of the project that I am responsible for is possible to manufacture and would not be difficult. However, manufacturing all of the components, such as the conductors and circuit breakers or fuses, may not be cost effective. The combiner box and switchboard junction boxes should be manufactured 49 though. I believe that these components are easy to manufacture and will cost less than to purchase. Sustainability: This project is very sustainable. The system is estimated to have a 20 year life cycle with little maintenance, besides replacing the battery every five years. The system is also using a sustainable form of energy. As for future upgrades, the final product will be of modular design, making the upgrades easy to do. Ethical: This project is meant to provide power to families in underdeveloped countries that currently do not have electricity. It also is not meant to make a large profit; therefore this project is very ethical. Health and Safety: Once the final design is manufactured, following all of the NEC codes, this system should be safe for any person to use. The system does have current flowing; therefore, users should be cautious when handling it. If users are being safe around the system, then there are no other health and safety concerns. Social and Political: The impact that this system will have to the families in underdeveloped countries is huge. The families will not be able to use light at night in order to work or read and get a better education. Also, they will be able to pump clean water to use and refrigerate their vaccines or food. This will end up helping the social and political state of these countries. Development: This project taught me about DC systems and more about renewable energy. I also learned how to use the NEC and got a better understanding of grounding. Overall, I learned a lot of information about a power system by being 50 able to apply what I learned in school and finding out about what is used out in the real world.