HINDUSTAN PETROLEUM CORPORATION LIMITED, E & P DEPT, 2nd FLOOR, Gresham Assurance bldg, Sir P.M.Road, Fort, MUMBAI-1 TENDER DOCUMENT FOR ELECTRIFICATION JOB AT BATHINDA IRD Page 1 of 153 INDEX Sr.No. 1. 2. 3. 4. 5. 6. 7. 8. DESCRIPTION TENDER COVER PAGE INDEX PROJECT DESCRIPTION AND SCOPE OF THE JOB SCHEDULE OF QUANTITIES TIME SCHEDULE TECHNICAL SPECIFICATIONS SPECIAL CONDITIONS OF CONTRACT SAFETY, HEALTH & ENVIRONMENT PAGES FROM TO 1 1 2 2 3 6 7 29 30 31 32 126 127 145 146 153 Page 2 of 153 PROJECT DESCRIPTION AND SCOPE OF THE JOB Page 3 of 153 SCOPE OF THE JOB PROJECT DESCRIPTION/SITE INFORMATION The proposed electrification job is to be executed at Bathinda POL Installation, Bathinda in the state of Punjab. The location addresses is as below: Hindustan Petroleum Corporation Limited Bathinda IRD Phoos Mandi Road - 492101 Punjab. Ph: (0164)2430430 Project Incharge:Shri Gurmeet Singh :- 09417602067 The brief scope of the work involves but not limited to the following:1. Installation, Testing & Commissioning of 1500 KVA Transformer & DG Sets (500KVA- 2Nos.) along with Synchronizing cum AMF Panel. 2. Design, engineering, fabrication, supply, erection, testing and commissioning of Double Poles, HPole, Isolation switch, CT & PT unit, Vaccuum Circuit Breaker and PCC Panel. 3. Design, engineering, fabrication, supply, erection, testing and commissioning of the Panels for the New Pumps of MS and HSD, Lighting for Pump house and gantry. 4. Supply, erection, testing and commissioning of FLP fixtures. 5. Supply, laying, testing and commissioning of the HT & LT Cables. 6. Supply, installation, testing and commissioning of the Earthing system. 7. Obtaining approval from electrical inspectorate and local/ central authority for the entire system of energization. 8. Executing other miscellaneous jobs such as civil works etc. The complete requirements shall be executed with single point responsibility including preparation of working drawings based on design, obtaining approvals from Statutory authorities for commissioning of the electrical system. Page 4 of 153 SITE CONDITION: The job needs to be carried out in the Depot premises. , hot work/ cold work/ other work permission has to be obtained for working on a daily basis. The explosive meter readings and check for presence of flammable vapour shall be checked by contractor‟s supervisor along with HPCL‟s representative before undertaking any work. Full time supervisor to be provided at work spot and job shall be carried out only after complying with all safety norms of the depot. Also, during hot work necessary precautions have to be taken to prevent any incidents due to presence of any petroleum vapours. Since the Terminal is in operation A full Time Qualified Engineer who is technically competent and having sufficient Site experience to be posted for supervising and carrying out all the Jobs as per the Scope and technical specifications. Before quoting for the said job the contractor is required to visit the site and make himself acquainted with the scope of the job and the working condition and quote accordingly. The tenders are required to go through the tender document thoroughly and carefully and offer their most competitive rates for the job. In case of any clarifications contractor may contact Shri B.S. Gopalkrishna, Manager-E&P, Engg & Projects Deptt, 2nd Floor, Gresham House, Sir P. M. Road, Fort, Mumbai- 400001 on 022-22608531 & Shri GURMEET SINGH Manager-E&P, HPCL IRD, Bathinda, Punjab- 492101 on (0164)2430430/ 09417602067 regarding any queries. The contractor shall arrange all equipment, tools, power and water required for execution, testing & completion of the job. All the safety precautions including supplying & providing localised fire screens for welding of reinforcements etc shall be arranged by the Contractors as per the directions of Engineer in charge at no extra cost to HPCL. Following to be submitted by the Party to EIC for approval before commencement of the job: 1. 2. 3. 4. 5. Design & Working Drawing of the Panels. Layout of the cable route. Layout of the earthing grid and plan. Preparation of any other drawing / design required for execution of the work. Electrical drawings for the approval of the Statutory Authority. . After the job is completed, 4 copies of all the above drawings (As built) shall be submitted along with CD containing soft copy in Autocad latest version. NOTES: 1. Any cables / piping encountered during electrification job during execution of the job, the same shall be separated using Sand Bed and Tiles or to be re-routed, if necessary as directed by the Engineer incharge at no extra cost to HPCL. Page 5 of 153 2. On receipt of LOI/ PO/ FOI, contractor is required to prepare a detailed date wise schedule of work/Bar Chart of the activities as per PO and submit the same to Engineer-In-Charge for approval before commencement of activities. 3. The Contractor has to give progress report with photographs every fortnight in hard copy as well as soft copy. Scope also includes shifting of any scrap materials lying at the constructional area to the designated place inside the depot premises at no extra cost. Job also includes site clearing from any debris, vegetation, bushes and trees, etc and make the site free for construction at no extra cost. The contractor shall arrange for all materials, equipment, tools, power and water required for execution & completion of the job. The bidders are required to go through the tender document thoroughly and carefully and offer their most competitive rates for the job. They are also advised to visit the site before offering their quotation. SITE VISIT The bidder is advised to visit and examine the site of works at all locations and their surrounding and obtain for himself on his own responsibility all information that may be necessary for preparing of the bid and entering into the contract. The cost of visiting the sites shall be at bidder‟s own expenses. No extra claim on account of non-familiarity of site conditions shall be entertained during execution of works. Page 6 of 153 SCHEDULE OF QUANTITIES Page 7 of 153 BATHINDA ELECTRIFICATION JOB Sr. No. Item Description Quantity Unit 1 EXCAVATION Earthwork in excavation for Foundations of buildings, pipe supports, equipment foundation, drain ,pit, trenches etc. or any other place as directed, in Ordinary soils including Soft rock / Disintegrated rock, in both Dry and Wet conditions, including backfilling etc, in layers of 150mm at all heights and depths as per Drawing and Specifications wherever required , in Foundation pits, under floors and other places with excavated suitable surplus earth, including reclaiming from spoil heaps kept elsewhere including dressing and leveling, watering and mechanical compaction etc. Transporting surplus soil to unobjectionable place within boundary limits and spreading in layers and as per Specifications and direction of Engineer. The Measurement for payment shall be for the theoretical volume only and it shall be the volume of the block of the excavation having maximum bottom dimension of the foundation as per drawing and to actual depth. 2350 CUM 2 SAND FILLING Supplying and filling approved quality course sand as per IS 383 - 1970 in layers of compacted thickness 200 mm each for as directed by EIC. Rate to include arranging for approved quarries /borrow pits outside Depot premises, loading, transportation, unloading, removal of debris, organic matter etc, spreading in layers, watering and compacting each layer till desired compaction is achieved and finishing to slopes and grades as per drawings specifications and instructions of Engineer In Charge. Job also to include compaction completely. Rate to include the execution of the job as per latest codal provisions, attached Technical specifications and as directed by EIC. 100 CUM 3 PLAIN CEMENT CONCRETE 1:2:4 Supply and laying PCC 1:2:4, using 20 mm and downsize crushed aggregate including providing shuttering for formwork, mixing, compacting by Vibrators, curing etc complete for foundations etc. Cement shall conform to IS 8112 – 43 grade / 53 grade or IS 1489. Cement shall be Ultratech, ACC, L&T or approved make. Rate to include the execution of the job as per latest codal provisions, attached Technical specifications and as directed by EIC. 120 CUM 4 REINFORCED CEMENT CONCRETE M-25 Supply and laying RCC M-25, using 20 mm and downsize crushed aggregate including providing shuttering for formwork, mixing, compacting by Vibrators, curing etc complete for foundation etc. Cement shall conform to IS 8112 – 43 grade / 53 grade or IS 1489. Cement shall be Ultratech, ACC, L&T or approved make. Rate to include the execution of the job as per latest codal provisions, attached Technical specifications and as directed by EIC. 425 CUM Page 8 of 153 5 STEEL REINFORCEMENT Supply, fabrication, tying and laying in position TMT (Thermo Mechanically Treated) steel reinforcement conforming to IS 1786, Fe-500 (latest edition) manufactured by SAIL/TISCO/RINL .Job includes, cutting, cold bending, tying with 20 SWG black annealed binding wire and placing in position at all heights/line/ levels etc, complete in all respects as per standard specification. Laps, chairs and spacer bars shall not be considered for measurement and payment purposes. Rate to include execution of the job as per latest codal provisions, attached Technical specifications and as directed by EIC. 27 TM 6 STRUCTURAL STEEL 25 TM Supply, Fabrication & Erection of steel structure for base frames, supports for switchgear, bus ducts, dummy panel, adaptor boxes and additional supports for proper cable termination etc, cable and cable tray supports out of rolled MS sections. Job to include painting with 2 coats enamel paint over 2 coats of zinc phosphate primer as per instruction of EIC. 7 PRECAST CONCRETE SLAB Providing & erecting in position precast concrete trench cover units to match with the flooring of required sizes and thickness as directed at site using reinforced cement concrete with M-25 design mix as per IS 456-2000 with 20 mm downgraded coarse aggregates including formwork to give fair and smooth finish, casting, vibrating providing lifting arrangement, loading / unloading transporting, load testing etc., complete but excluding cost of reinforcement (which will be separately paid as per Reinforcement Item No. 229.0), all as per specification and as directed by the engineer in charge. The cement content shall be governed by design mix or soil characteristics as per soil investigation report (report shall be forwarded to the successful bidder), whichever is higher. The slab rate shall consists of sunken MS handles of 10 mm dia or as directed by Engineer Incharge. Concrete to be used shall be ready mix concrete/ weigh batcher only. RMC shall be from approved RMC Plants like ACC, L&T, Ultra Tech etc. The scope of mix design is included in the scope of bidder and the same to be vetted by reputed engineering institute like IIT, Kharagpur or any other reputed Engineering Institutes/ Consultant duly approved by HPCL. 115 CUM 8 PAVER BLOCK Paver Block-Supply and laying 80mm thick glazed interlocking blocks of approved colors in approved design, brand and pattern as directed, of compressive strength 400Kg/sq. cm. placing each against its neighbour on the un-compacted sand, cutting the pieces to fill up edges next to the edge restrains. The paver blocks should have chamfered top edges of not less than 4mm and shall be laid with a min. Of 2mm gap which in turn shall be packed with sane and compacted with plate/surface vibrator to the correct line, level and gradient and as directed by EIC After laying compact with vibrator. Sweep dry fine sand over the surface, making sure it fills all the gaps between the paver. Vibrate the area again to give 900 SM Page 9 of 153 strong interlocking bond. Sweep off excess sand including all work complete as per direction of engineer-in-charge. (interlocking blocks pattern to be approved by Owner) 9 10 TRANSFORMER INSTALLATION & COMMISSIONING Shifting from client's store & erection on foundations, assembling of all loose supplied accessories testing for pre-commissioning checks with due coordination with the supplier & Commissioning Of TRANSFORMER of 1500KVA , 11/0.433KV, Oil Natural Air Cooled, Distribution transformer. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. Inspection & Testing Specification in Section 16.1.2 of IS 2026 with latest amendment. The routine test shall be as follows. a) Visual Inspection. b) Insulation Resistance Test. c) Fixing up of marshaling box d) Megger e) H.V test f) Polarity Test. g) Winding Resistance Test h) Separate Source Voltage with stand. i) Oil used in the transformer shall be tested as per Oil Tests Specification in IS: 335-1972 as modified to date. D.G. SET INSTALLATION & COMMISSIONING Shifting from client's store and erection on foundations, assembling of all loose supplied accessories& Installation of Diesel Generator in coordination with the DG vendor. Pre-commissioning of the DG Sets with due co-ordination with the DG supplier and final commissioning of the same. Structural support supply & fabrication shall be paid separately under respective item. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 500KVA, Speed 1500 RPM a) Inspection & Testing b) Governor response. c) Voltage regulations and AVR Response. d) Automatic Mains Failure cum Auto Start operation of Diesel Generating Set and load transfer to D.G Bus. 1 EACH 2 EACH e) The DG vendor to provide necessary assistance to the electrical vendor for executing the following tests at site in the presence of the client’s representative before energization. Page 10 of 153 f) Checking the alignment by engine manufacturer’s representative and obtaining approval. g) Insulation resistance test on alternator, control panel and cabling / Bus bar trunking. h) Checking the engine safeties for satisfactory operation. i) Checking vibration levels. j) Testing of individual protective devices on engine and alternator and ensuring that the wiring is carried out properly. k) Full load running for 8 hours continuously. All the readings shall be logged to evaluate the fuel consumption, lube oil pressure, water & oil temperature vis-àvis the electrical load. l) The noise level at 1m from the enclosure and the temperature rise inside the enclosure shall be measured. m) The DG set shall be deemed to be commissioned after satisfactory performance of all associated equipment. n) Laying, wrapping up with insulation of the exhaust piping system o) Installation of the exhaust & fuel system of the piping. 11 SYNCHRONISING PANEL Erection, Testing & Commissioning of Synchronizing Panel with provision of Auto Synchronization & Testing of Load Sharing and recording of all parameters. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 1 EACH 1 LS HT SIDE 12 SUPPLY, INSTALLATION OF 11KV OUTDOOR STRUCTURE & EQUIPMENTS Supply, Installation, Testing & Commissioning of 11KV Outdoor Structure and equipments, all accessories and fixing material as per drawings and documents of this SOW, as stated below including transportation upto site/ yard and unloading. 11KV, 400A, 50Hz, 25kA for 1 sec, 3-pole, outdoor type, Gang operated disconnector with operating handle from ground. - 2 Each 11KV, 50Hz, outdoor type, drop out fuse with base unit. - 6 Each 11KV, 50Hz, outdoor type, Strain Insulators. - 9 Each 11KV, 50Hz, outdoor type, Pin (post) insulators. 12KV, 50Hz, 10kA, outdoor type, distribution class, lightning arrestor. - 12 Each – 3 Each 7/0. 144" ACSR conductor with terminations. - 1 Lot Outdoor structure for mounting of equipments. - 1 Lot 10 SWG, 75 sqmm, 2 m high, chain link fence with supports and barbed wire, hot dip galvanized. - 1 Lot 2 x 1.5m wide x 1.8m high, chain link fence gate with tubular pipes, hot dip galvanized. - 1 Each Cement gravel, G.I. pipes, paint, accessories and fixing material. - 1 Lot Page 11 of 153 11Mtr MS Round Pole 13 - 2 Each VACUUM CIRCUIT BREAKER:- Supply & erection of 11 KV VCB 800A CT Ratio 100/1 PT Ratio 11KV/110V (Make :-Schneider/ L&T/ ABB/ Siemens). (BOQ As per ANNEXURE-A). 1 EACH 16 Supply of 3C x 150 sqmm XLPE FRLS insulated 11 KV grade armoured cables confirm to IS – 7098 Part - II with latest amendments as per Technical Specifications attached and as advised by EIC. MTC for the cables also needs to be provided. The approved makes of the cable are Polycab/ NICCO/ CCI/ Finolex/ RPG/ Havels/ equivalent approved makes. 100 METER 17 Laying of 3C x 150 sqmm HT cables rated for 11KV in readymade trench or buried in ground, supported on structure with etc in miscellaneous locations pull through pipes concrete including all the consumables like CI number tags every 25 mtr. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 100 METER 18 HT CABLE INDOOR TYPE JOINT KIT:- Supply and termination of HT cable termination kit (Indoor joints) for 3C x 150sq.mm. AL-XLPE cable It shall be heat shrinkable type and of approved make. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 2 EACH 19 HT CABLE OUTDOOR TYPE JOINT KIT:- Supply and termination of HT cable termination kit (Outdoor joints) for 3C x 150sq.mm. AL-XLPE cable It shall be heat shrinkable type and of approved make. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 2 EACH 20 NFLP CABLE GLANDS:- Supply & Installation of Single Compression Non Flameproof nickel plated cable glands of approved make & termination of cables include supply of lugs of approved make. The job also includes labour component for cutting, stripping of cable insulation, drilling of gland plate and fixing the same. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 4 EACH 14 15 LT PANELS PMCC Panel (details attached as Annexure-B) MCC Panel (details attached as Annexure-C) HT CABLE A LT CABLE SUPPLY OF LT CABLES: Supply of XLPE FRLS insulated 1.1 KV grade armoured cables confirm to IS – 7098 Part - I with latest amendments as per Technical Specifications attached and as advised by EIC. MTC for the cables also needs to be provided. The approved makes of the cable are Polycab/ NICCO/ CCI/ Finolex/ Page 12 of 153 21 22 23 24 25 26 27 28 29 30 31 32 33 34 B I 35 36 37 38 39 40 41 42 43 44 45 46 47 48 RPG/ Havels/ equivalent approved makes. 3C x 95 sqmm Al armored cable 3C x 120 sqmm Al armored cable 3C x 185 sqmm Al armored cable 3.5C x 25 sqmm Al armored cable 3.5C x 50 sqmm Al armored cable 3.5C x 70 sqmm Al armored cable 3.5C x 95 sqmm Al armored cable 3.5C x 150 sqmm Al armored cable 3.5C x 185 sqmm Al armored cable 3.5C x 300 sqmm Al armored cable 3.5C x 400 sqmm Al armored cable 3.5C x 500 sqmm Al armored cable 3C x 2.5 sqmm Cu armored cable 6C x 2.5 sqmm Cu armored cable 600 3650 4650 850 700 50 180 225 135 2800 2450 550 6200 11500 METER METER METER METER METER METER METER METER METER METER METER METER METER METER LAYING OF LT CABLES LAYING OF CABLES BELOW GROUND:- Laying, Testing & Commissioning of LT XLPE insulated PVC sheathed FRLS armoured cable with Aluminium conductor 1.1 KV grade conforming to IS 7098 Part I of following sizes as per attached technical specifications. The job includes excavation up to a minimum depth of 750 mm and a minimum width of 300mm. Laying & compaction of 150mm sand bed, laying of bare cable along with overlaying of 150mm sand bed, along with laying of bricks in transverse directions. Rate also includes tagging of cable with the Aluminium cable tag at an interval of 100m and at the change of direction. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 3C x 95 sqmm Al armored cable 3C x 120 sqmm Al armored cable 3C x 185 sqmm Al armored cable 3.5C x 25 sqmm Al armored cable 3.5C x 50 sqmm Al armored cable 3.5C x 70 sqmm Al armored cable 3.5C x 95 sqmm Al armored cable 3.5C x 150 sqmm Al armored cable 3.5C x 185 sqmm Al armored cable 3.5C x 300 sqmm Al armored cable 3.5C x 400 sqmm Al armored cable 3.5C x 500 sqmm Al armored cable 3C x 2.5 sqmm Cu armored cable 6C x 2.5 sqmm Cu armored cable 50 300 500 100 75 25 50 45 35 300 150 350 200 1500 METER METER METER METER METER METER METER METER METER METER METER METER METER METER Page 13 of 153 LAYING OF CABLES IN BUILD-UP TRENCH:- Laying, Testing & II 49 50 51 52 53 54 55 56 57 58 59 60 61 62 Commissioning of LT XLPE insulated PVC sheathed FRLS armoured cable with Aluminium conductor 1.1 KV grade conforming to IS 7098 Part I of following sizes as per attached technical specifications. The job includes laying of cables in the cable tray laid in the trench at different levels of cable trench with the support of angles. Rate also includes tagging of cable with the Aluminium cable tag at an interval of 100m and at the change of direction. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 3C x 95 sqmm Al armored cable 3C x 120 sqmm Al armored cable 3C x 185 sqmm Al armored cable 3.5C x 25 sqmm Al armored cable 3.5C x 50 sqmm Al armored cable 3.5C x 70 sqmm Al armored cable 3.5C x 95 sqmm Al armored cable 3.5C x 150 sqmm Al armored cable 3.5C x 185 sqmm Al armored cable 3.5C x 300 sqmm Al armored cable 3.5C x 400 sqmm Al armored cable 3.5C x 500 sqmm Al armored cable 3C x 2.5 sqmm Cu armored cable 6C x 2.5 sqmm Cu armored cable 450 3200 4000 650 600 25 130 180 100 2500 2300 200 4200 8000 METER METER METER METER METER METER METER METER METER METER METER METER METER METER 50 150 150 100 25 1800 2000 METER METER METER METER METER METER METER ABOVEGROUND CABLES:- Laying, Testing & Commissioning of LT XLPE III 63 64 65 66 67 68 69 insulated PVC sheathed FRLS armoured cable with Aluminium conductor 1.1 KV grade conforming to IS 7098 Part I of following sizes as per attached technical specifications. The job includes laying of cables in the cable tray along with proper dressing at all heights. Vertical run shall be clamped by means of 16 SWG GI wire whereas the horizontal run shall be tied by means of nylon chord. All power cables shall be laid in a single run whereas control cables can have maximum two runs. Rate also includes tagging of cable with the Aluminium cable tag at an interval of 100m and at the points of turning. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 3C x 95 sqmm Al armored cable 3C x 120 sqmm Al armored cable 3C x 185 sqmm Al armored cable 3.5C x 25 sqmm Al armored cable 3.5C x 50 sqmm Al armored cable 3C x 2.5 sqmm Cu armored cable 6C x 2.5 sqmm Cu armored cable END TERMINATION Page 14 of 153 A 70 71 72 73 74 75 76 77 78 79 80 81 82 83 B 84 85 86 87 88 89 90 91 92 93 94 95 96 97 NFLP CABLE GLANDS:- Supply & Installation of Double Compression Non Flameproof nickel plated cable glands of approved make & termination of cables include supply of lugs of approved make. The job also includes labour component for cutting, stripping of cable insulation, drilling of gland plate and fixing the same. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 3C x 95 sqmm cable gland 3C x 120 sqmm cable gland 3C x 185 sqmm cable gland 3.5C x 25 sqmm cable gland 3.5C x 50 sqmm cable gland 3.5C x 70 sqmm cable gland 3.5C x 95 sqmm cable gland 3.5C x 150 sqmm cable gland 3.5C x 185 sqmm cable gland 3.5C x 300 sqmm cable gland 3.5C x 400 sqmm cable gland 3.5C x 500 sqmm cable gland 3C x 2.5 sqmm cable gland 6C x 2.5 sqmm cable gland 3 15 15 5 5 4 5 10 5 35 30 24 20 40 EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH FLP CABLE GLANDS:- Supply & Installation of Double Compression Flameproof nickel plated cable glands of approved make & termination of cables include supply of lugs of approved make. Rate to include supply & installation of PVC hoods of suitable size over the glands. The job also includes labour component for cutting, stripping of cable insulation, drilling of gland plate and fixing the same. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 3C x 95 sqmm cable gland 3C x 120 sqmm cable gland 3C x 185 sqmm cable gland 3.5C x 25 sqmm cable gland 3.5C x 50 sqmm cable gland 3.5C x 70 sqmm cable gland 3.5C x 95 sqmm cable gland 3.5C x 150 sqmm cable gland 3.5C x 185 sqmm cable gland 3.5C x 300 sqmm cable gland 3.5C x 400 sqmm cable gland 3.5C x 500 sqmm cable gland 3C x 2.5 sqmm cable gland 6C x 2.5 sqmm cable gland 4 15 18 4 1 1 1 1 1 1 1 1 160 50 EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH Page 15 of 153 98 99 100 101 102 103 104 105 106 107 108 109 110 111 STRAIGHT THROUGH JOINTS Supply & Performing of Straight through joints including joint kits with heat shrinkable or equivalent type joint kit for 1.1 KV XLPE Cables of following sizes. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 3C x 95 sqmm cable 3C x 120 sqmm cable 3C x 185 sqmm cable 3.5C x 25 sqmm cable 3.5C x 50 sqmm cable 3.5C x 70 sqmm cable 3.5C x 95 sqmm cable 3.5C x 150 sqmm cable 3.5C x 185 sqmm cable 3.5C x 300 sqmm cable 3.5C x 400 sqmm cable 3.5C x 500 sqmm cable 3C x 2.5 sqmm cable 6C x 2.5 sqmm cable 2 5 6 2 1 1 1 1 1 5 6 2 10 12 EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH EACH 112 113 114 115 116 TESTING & COMMISSIONING OF PUMPS: Testing & commissioning of 415V 3 phase induction Motors of following ratings. Rate to include replacing of grease if required, checking of rotation and other insulation tests, recoupling the motor with pump and checking as per standard engineering practices. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 75 KW rating Motor 55 KW rating Motor 37 KW rating Motor 30 KW rating Motor 15 KW rating Motor 7 4 3 2 2 EACH EACH EACH EACH EACH 40 EACH 117 EARTHING SYSTEM G.I. PIPE ELECTRODE:- Supply and erection of G.I. earth pipe electrode 65mm diameter, atleast 3.0 mtr. below ground with 40Kg charcoal and salt with alternate layers of charcoal and salt with 19mm dia GI pipe with funnel with a wire mesh for watering 230 brick masonry chamber (300mm x 300mm x 300mm) C.I. cover 300mm x 300mm (10 Kg) complete as per para 7.3 of I.S. 3043 with necessary length of double G.I. earth wire no.6 SWG bolted with lug to the plate and covered in 19 mm dia G.I. pipe 3.0 mtr. long complete connected to the nearest switchgear with end socket as per directions and duly tested by earth tester and recording the results. Excavation work is included in the scope of contractor. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. Page 16 of 153 118 Cu PLATE ELECTRODE:- Supply and erection of Copper. earth plate size 600X600X6.3 mm earth pit, atleast 3.0 mtr. below ground with 40Kg charcoal and salt with alternate layers of charcoal and salt with 19mm dia GI pipe with funnel with a wire mesh for watering and 230 brick masonry chamber (300mm x 300mm x 300mm) C.I. cover 300mm x 300mm (10 Kg) complete as per para 7.3 of I.S. 3043 with necessary length of double G.I. earth wire no.6 SWG bolted with lug to the plate and covered in 12 mm dia G.I. pipe 3.0 mtr long complete connected to the nearest switchgear with end socket as per directions and duly tested by earth tester and recording the results. Excavation work is included in the scope of contractor. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 6 EACH 750 300 300 1000 1000 METER METER METER METER METER 100 METER 125 126 127 128 129 CABLE TRAY:- Supply & Installation of pre-fabricated perforated, hot dipped GI cable tray with coupler plate, 90 deg. bends, tees, hardware etc. made out of 2.5mm thick sheet up to size 300 mm cable tray and 3mm thick sheet for tray of above 300mm width. Length of cable tray shall be 2.5 m. The cable tray shall be laid at all heights above the ground and as per the direction of Engineer Incharge. 750mm perforated cable tray 450mm perforated cable tray 300mm perforated cable tray 100mm perforated cable tray 50mm perforated cable tray 500 300 500 200 450 METER METER METER METER METER 130 131 132 GI PIPES:- Supply and laying of following size of hot dipped GI class 'B' pipes in required length fixed on in concrete or buried in trench/concrete for cable/GI strip protection. End of pipes to be sealed. Job includes minor civil works and to be carried out as per the instructions of EIC. 50mm GI Pipes 80mm GI Pipes 100mm GI Pipes 150 150 200 METER METER METER 119 120 121 122 123 124 GI STRIP:- Supply, Laying & Connecting of following size hot dipped GI strip along the cable trench/ cable structure tray, wall structure etc including welding at joints, anti-corrosive paint on welded portions. Clamping complete with GI hardwares, labour etc as per instructions of EIC. 50mm x 6mm GI strip 25mm x 6mm GI strip 25mm x 3mm GI strip 10mm SWG hot dipped GI wire 1C x 2.5 sqmm Cu cable Supply, Laying & Connecting of Cu strip of 50 x 6 mm for earthing including welding at joints, anti-corrosive paint on welded portions. Page 17 of 153 133 LIGHTING FIXTRUES 150W MH WELL GLASS FITTING:- Supply, installation and commissioning OF Flameproof and Weatherproof Well Glass Fixture suitable for 150 W Metal Halide Lamp in cast aluminium alloy LM6 construction ¾” ET entries, including inbuilt control gear box, lamps and choke. The materials has to be certified by CMRI, Dhanbad, CCOE etc for use in group flame zone I, IIA, & IIB as IS: 2148 1981. The fitting to be provided with FLP Junction Box complete with lamps. Rate to include fixing of GI clamp, hardware etc as required and as specified by EIC. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 60 EACH 134 BULK HEAD FIXTURES:- Supply, installation and commissioning OF Flameproof and Weatherproof IP 66 Bulk Head Fixture suitable for 150 W Metal Halide Lamp in cast aluminium alloy LM6 construction ¾” ET entries, with ES27 holder, FLP control gear box, lamps, choke. The materials has to be certified by CMRI, Dhanbad, CCOE or approved agencies etc for use in group flame zone I, IIA, & IIB as IS: 2148 - 1981. The fitting to be provided with FLP Junction Box complete with Lamps, rate to include fixing of MS Clamps, hardwares etc as required and as specified by E.I.C. Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 20 EACH 135 MS STREET LIGHT POLES:- Supply & Installation of 11.0 mtr long MS Tubular swaged & welded type Street Light Pole Confirming to ISS – 2713 – 1969 complete with Base plate, MS pipe inserts for I/C & O/G cables, necessary foundations min. length 1.8 M to be grouted below ground. The pole shall be painted with Bitumen paint up to planting height. Pole shall be provided with 2 coats of epoxy based primer And 2 coats of finish paint of approved colour. Pole shall be fitted with single arm bracket of 2.0M Long to fix St. Light fixture complete with suitable CI Cable end Box with bottom type cable entry, Earth boss, internal wiring from cable end box up to the light fixture, with all Hardwares. Base plate shall be minimum 300 x 300 x 10 mm. 10 EACH 136 250W SON T PLUS LIGHT:- Supply & Installation of Bajaj type BGEST 250 SV IP 66 FFG street light fittings or equivalent make with 1 no. 250 W SON T plus HPSV lamps or any other approved equivalent make. 10 EACH 137 16A SPN, 240V FLP ROTARY SWITCH:- Supply, installation and commissioning OF Flameproof Weatherproof IP 66 Rotary Switch FLP junction box complete, rate to include fixing of GI Clamps, hardware etc as required and specified by EIC. 10 EACH 138 FLP LDB:- Supply, installation and commissioning of FLP/WP IP-66 Lighting Distribution Board a. Incomer 32A TPN SFU & b. Outgoing 6 Nos of 16A SPN Switches with bottom type cable entry etc as required and specified by E.I.C. The Incomer shall be suitable to cable of 3.5C x 95 sq.mm and should also have loop in loop out arrangement along with metallic stopper. The outgoings shall be provided with 16A FLP Rotary Switches. Certificates: Certified by CMRI, Dhanbad for Group II A & II B, CCOE Nagpur and carry ISI mark on nameplate itself as per 4 EACH Page 18 of 153 IS: 2148:1981. 139 FLP 4-WAY JB:- Supply, installation and commissioning OF FLP 4-way Junction Box with Terminals with top & bottom type cable entries complete, rate to include fixing of galvanized MS Clamps, hardwares etc as reqd. & specified EIC. Certificates: Certified by CMRI, Dhanbad for Group II A & II B, CCOE Nagpur and carry ISI mark on nameplate itself as per IS: 2148-1981. 8 EACH 3 2 EACH EACH 142 FLP PUSH BUTTONS:- Supply, installation and commissioning OF Flameproof Weatherproof IP 66 pressure die cast aluminium alloy LM 6 construction On/Off Push Button Station with I/Lamp having 2 no. ¾” ET entries from bottom and colour shade as per shade 631 of IS-5. Hardware Steel:- Stainless Steel Earthing: 1 no. Red Mushroom stay put type press and turn to lock and reverse turn to release with pad locking arrangement but without lock & key. Element: 10 A 1 NO + 1NC contact element of approved make. Indicating Lamp: 1 no Red indicating lamp of approved make. Certificates: Certified by CMRI, Dhanbad for Group II A & II B, CCOE Nagpur and carry ISI mark on nameplate itself as per IS: 2148:1981. 60 EACH 143 CHAIN LINK FENCING:- Supplying, stretching and straining chain link fencing, 1.8m high, made with 10SWG galvanised steel chain link 50mm mesh, 3mm dia Galvanised steel guard wire at top & bottom, fixing to angle posts of 65x65x6 @ 3.0m c/c and lateral supports with angle 75x75x6 @ change of direction or at 15m c/c including 6mm Galvanised steel rods and galvanised steel J hooks & providing 2 MS flats 50mm x 5mm thick bolted to the vertical post, 50 mm NB (medium) pipe to be clamped at top & bottom along the length of the fencing to the vertical post including excavation, PCC M10 for fixing angle post, two coats of synthetic enamel paint over coat of primer, all complete as per drawings, specifications and as directed by the Engineer. The job also includes providing 1 No. Gate of 3m width and 1 Gate of 1.5m width.(Note: The supply of all the above items is included in the scope and payment will be made on Running meter basis). Job to be executed as per attached technical specifications and as directed by Engineer Incharge complete. 100 METER 144 BLUE METAL FOR TRANSFORMER:- Supplying & laying blue metal in layers of 20 mm down size coarse aggregate of uniform size/graded for transformer yard. 40 CUM 140 141 FLP SOCKET WITH PLUG:- Supply, installation and commissioning OF Flameproof Weatherproof IP 66 Switch Socket with Plug Top. Plug top must be interlocking with the switch in ON position and cannot be detached unless it is rotated to OFF position. The cable entry shall be at the bottom suitable for following ratings as per the advice of EIC. Certificates: Certified by CMRI, Dhanbad for Group II A & II B, CCOE Nagpur and carry ISI mark on nameplate itself as per IS: 2148:1981. 63A TPN+E with Plug top. 32A TPN+E with Plug top. Page 19 of 153 145 ELECTRICAL SIREN:- Installing & commissioning of HPCL Supplied Electrically operated siren of 3 KM range vertical or horizontally mounted, operated with starter, provision to manually operate through Push Button or thru PLC command as per the instruction of EIC. 1 EACH 146 HAND OPERATED SIREN:- Installing & commissioning of Hand operated siren of 1 KM range vertical or horizontally mounted, as per the instruction of EIC. 2 EACH 147 FLP TELEPHONE:- Supply of ZONE 1, GAS GROUP IIA/IIB, IP-66 Electronic Push Button Telephone, Intrinsically safe circuit, with hand set and push button dialer. 1 No.3/4 ET cable entry, with 1 No.3/4ET FLP Brass Ni. plated cable gland, w/o blanking plug and M.S. Canopy. Approved make- Flame proof controls/ approved equivalents. Finish: Epoxy Blue Colour/approved equivalent colour. The materials has to be certified by CMRI, Dhanbad, CCOE etc for use in group flame zone I, IIA, & IIB as per IS:2148 - 1981. 2 EACH 148 FLP FANS:- Supply & Installation of free standing pedestal type fan with adjustable rod of 24” dia with safety guard. The same shall be having IP 66 degree of protection and shall flameproof & weatherproof type suitable for ZONE 1, GAS GROUP IIA/IIB. The materials has to be certified by CMRI, Dhanbad, CCOE etc for use in group flame zone I, IIA, & IIB as IS: 2148 - 1981. 1 EACH 149 CHEQUERED PLATE:- Supply, fabricate and cover the cable trench in MCC Rooms using 5 mm thick MS chequered plates as directed at site. Rate to include providing and fixing of lifting hooks in all the plates and painting with 2 coat of enamel paint of approved shade over 2 coat of zinc phosphate primer as per the instructions of EIC. 25 SQUARE METER 20 20 20 METER METER METER RCC HUME PIPE:- Supplying and laying RCC hume pipes of NP3 class at designated places or as directed by EIC. Job to include collars/joints jointed with stiff mixture of CM 1:2 proportion, curing, aligning and joining etc. to correct line, level, slope and gradient complete. Job also to include excavation ( a min. of 300 more in all directions), 200mm thick sand bedding, followed by 150mm thick PCC 1:2:4(with 20mm down aggregate),laying of hume pipe and backfilling the trench with approved quality sand to a depth of 150mm and then placing murrum & compacting using a surface vibrator and completing the top of the finished surface below the level of bitumen carpet with 100 mm thick RCC 1:2:4 with provision of reinforcement of 8mm 200 c/c including backfilling at all depths and job to be executed as per attached technical specification and directions of EIC complete. Note: Party to quote for the item including the entire scope of the above job as one job and no separate payment will be made. 150 151 152 500 mm NB Hume Pipe 350 mm NB Hume Pipe 200 mm NB Hume Pipe Page 20 of 153 MISCELLANEOUS ITEMS: 153 Supply and fix Rubber Mat confirming to IS - 15652 and the same to be laid in Meter Room suitable for HT Panel as per the directions of EIC. 10 SM 154 Supply and fix Rubber Mat confirming to IS - 15652 and the same to be laid in MCC and Control Rooms suitable for LT Panel as per the directions of EIC. 25 SM 155 Supply of 11 KV Rubber Gloves for electrical operation works. 1 PAIR 156 Supply and fix shock treatment chart with glass frame as per directions of EIC. 2 EACH 157 Supply if First Aid Box with accessories. 1 EACH 158 Supply and fix Exit sign Board suitable for 230V supply with battery back - up. 2 EACH 159 Supply & fixing 20 W tubular emergency light fixtures of approved make suitable with 4 hours back up battery. 4 EACH 50 50 50 50 EACH EACH EACH EACH 160 161 162 163 PAINTING & STENCILLING:- Righting of following sizes letters, numbers by painting, radium stickers on panels, transformers as per directive of EngineersIn-Charge. Rate shall be inclusive of paints, radium paper, all tools - tackles, manpower etc complete for the job. Signwriting 1” size Signwriting 2” size Radium Stickers 1” size Radium Stickers 2” size 164 CABLE MARKER:- Supply and Installation of Cable Markers for showing the route of cable laying within the Depot premises. 100 EACH 165 STATUTORY APPROVALS:- Preparation of Drawing, obtaining Approval of the LT work / modification Works carried out for the proposed facilities, from the Office of the Electrical Inspectorate Office and all applicable agencies. The job shall include obtaining approval for the entire executed job of LT/ HT and also the required approvals for the commissioning of DG set/ Transformer/ MCC Panels etc and any other approval associated with this job not mentioned above but required for successful commissioning of the entire job. Job includes liasoning, arrangements for site visits by Electrical Authority concerned like PSEB, Electrical Inspectorate etc. Obtainance of clearance to commission facilities complete as per direction of EIC. Job includes energization from PSEB HT side of line and the enhancement of the Contract Demand of the Energy from PSEB. Liasoning thereof to ensure commissioning of the entire Depot. Note:- All Statutory Fees shall be paid by HPCL. However liasoning shall be 1 LS Page 21 of 153 made by the party with the Electrical Authorities. 166 MODIFICATIONS IN EXISTING PANEL The job includes tapping off the input for the existing Panels of Depot, Pipeline and Siding from the new PMCC Panel. The job also includes carrying out any required modification in the existing panels for the charging of the existing Panels and the commissioning of the entire Electrical facility. The job needs to be executed with all the required safety and to be followed in strict adherence to electrical standards and guidelines. The job to be done as per the instructions of Engineer Incharge. 167 SHIFTING OF EXISTING DG SETS The job includes dismantling of the existing DG sets (200KVA & 100 KVA) from the existing location along with all the accessories and shifting the same to the new location as directed by the Engineer Incharge. Both the DG sets needs to be installed, tested and commissioned at the new location keeping in view all the safety precautions and in line with the CPCB guidelines. Further any damage caused during dismantling shall be borne by the vendor. LADDER TYPE CABLE TRAY:- Supply & Installation of pre-fabricated ladder type, hot dipped GI cable tray with coupler plate, 90 deg. bends, tees, hardware etc. made out of 2.5mm thick sheet up to size 300 mm cable tray and 3mm thick sheet for tray of above 300mm width. Length of cable tray shall be 2.5 m. The cable tray shall be laid on the RCC trench and shall be supported on the angles at different levels as per the direction of Engineer Incharge. 168 750mm ladder type cable tray 1500 METER 169 450mm ladder type cable tray 700 METER NOTE:- Following points to be noted:The bidder is advised to visit the site and understand the complete scope of the job before bidding in the tender. Any procurement of the material to be done only after the approval from the Engineer Incharge Item No. 12 & 13 to be executed based on the requirement at the site and the approval from the Engineer Incharge. The same may or may not be executed. Item No. 166 & 167 is kept in the tender for any required modification in the Panel. This item may or may not be executed / may be removed from the scope of the tender as per the requirement. Page 22 of 153 VCB 630A, BATHINDA Sr. No. FAULT LEVEL System Voltage Level RATING QUANTITY PAINT SHADE Degree of Protection A A1 ANNEXURE- A DESCRIPTION OF ITEMS Cable In - Cable Out Unit Panel :- 25kA for 3 sec :- 11 KV :::- Alu-Zinc / RAL 7032 :- IP 4X 630 A 1 MOVING PORTION:Indoor type metal clad, totally enclosed & fully interlocked draw out type Vacuum Circuit Breaker as per IEC 62271-100/ 200/ IS 3118. Single break trip free breaker with SPMX mechanism, mounted on a truck carriage, complete with self-contained operated fully interlocked rack in & rack out mechanism ON & OFF Indicator with hand trip device, spring release coil, shunt trip coil & auxiliary switch of 6 NO + 6 NC. 1 800 A, 25 KA for 3 sec VCB (Cassette/ Trolley Mounted) A2 Sheet Steel/ Alu-Zinc Enclosure + Aluminium Connections +Side Entry Cable Box B CT (APPROVED MAKE) & PT DETAILS : B1 2 Core CT with accuracy Class 5P 10 for protection & Class 1.0 for metering, 15VA, STR 25KA for 1 sec, 100A/1A + 1A 3 B2 3-phase PT with ratio 11000/V3/ 110/V3; 100VA Class 1.0, OVF 1.9 for 30 sec for metering backed by HT fuses and LT MCB. 1 C C1 C2 BREAKER PANEL INDICATION LAMPS Breaker On/ Off/Trip/ Trip Circuit Healthy/ Spring Charge etc. R-Ph. / Y-Ph. / B-Ph. 5 3 D D1 D2 D3 D4 D5 D6 D7 D8 D9 SWITCHES AND OTHER ACCESSORIES : DC ON/OFF Switch AC ON/OFF Switch Heater with heater switch & thermostat Cubicle illumination lamp 15A, 230V, 3 pin plug & socket Local Remote Switch T-N-C Switch Mech. ON-OFF push button Hooter/ Alarm 1 1 1 1 1 1 1 1 1 1 Page 23 of 153 E E1 E2 E3 METERS : Ammeter with selector switch Voltmeter with selector switch MFM with RS485 port (in MODBUS) F RELAYS : IDMT O/C & E/F protection relay (ER make MIT 103/ C&S make IRIPro-V / Schneider make MiCOM P111L) without communication. F1 1 1 1 1 F2 Trip Circuit Supervisor relay type - VAX 31 (Alstom/ Equivalent make) 1 F3 Auxiliary relay type VAA33 for Transformer Fault Indication (Alstom/ Equivalent makes) 1 F4 Master Trip relay type - VAJH13 (86) (Alstom/ Equivalent make) 1 Page 24 of 153 S.No. 1 1 2 3 4 2 1 2 3 4 3 1 4 1 2 3 4 5 6 7 8 9 10 11 12 5 1 2 3 4 5 6 7 8 9 10 11 12 6 1 7 1 8 1 2 MAIN PMCC PANEL, BATHINDA DESCRIPTION OF ITEM POWER INCOMER 2500A 4P ACB EDO Type with SR 18G Release Under Voltage Release TNC Switch Aux. Contactor with Add on Block DG INCOMER 2000A 4P ACB EDO Type with SR 18G Release Under Voltage Release TNC Switch Aux. Contactor with Add on Block INTERLOCKING Electrical interlocking between Power & DG Incomer ANNEXURE : B Unit QTY. Nos. Nos. Nos. Nos. 1 1 1 2 Nos. Nos. Nos. Nos. 1 1 1 2 Nos. 1 Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. 2 1 1 2 6 6 6 2 4 4 2 2 Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. 1 1 1 1 1 2 2 2 1 1 1 1 Set 1 Set 1 Set Set 1 1 METERING & CONTROL Volt Meter 0-500V Digital with VSS Ampere Meter 0-2500A Digital with ASS Ampere Meter 0-2000A Digital with ASS Multi Function Meter with 2 D/O High/Low Voltage Protection CT 2500/5A,15VA CT 2000/5A, 15VA Control MCB 6A SP 10KA Neutral Link 40A Phase & Off Indication Light Red Phase & Trip Indication Light Amber Phase Indication Light Blue On Indication Light Green OUTGOING FEEDERS 1600A 4P ACB EDO Type with Thermal Release 800A 4P ACB EDO Type with Thermal Release 630A 4P MCCB 50KA 'DN' Spreader Link Door Operating Handle 400A 4P MCCB 50KA 'DN' Spreader Link Door Operating Handle 250A 4P MCCB 50KA 'DN' Spreader Link Door Operating Handle Cubical Space CUBICAL PANEL Cubical Panel made out from 16/14 SWG CRCA sheet steel duly power coated in Siemens grey colour size of panel 3900 mm (W) X 2200 mm (H) X 1000 mm (D) Floor Mounted (Back Open) BUS BAR Bus Bar 2400A TPN AL MISC. ITEMS Wiring & Fixing material Hardware & legends Page 25 of 153 MCC PANEL, BATHINDA S.No. 1 1 2 1 2 3 4 5 6 7 8 9 10 3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 4 1 5 1 6 1 2 DESCRIPTION OF ITEM INCOMMER 1600A 4P ACB EDO Type with Thermal Release METERING & CONTROL Volt Meter 0-500V Digital with VSS Ampere Meter 0-1600A Digital with ASS KWH Meter Digital (LG + 1119) CT 1600/5A, 15VA Control MCB 6A SP 10KA Neutral Link 40A Phase & Off Indication Light Red Phase Indication Light Amber Phase Indication Light Blue On Indication Light Green OUTGOING FEEDERS 800A 4P ACB MDO Type with Thermal Release 400A 4P MCCB 50KA 'DN' Spreader Link Door Operating Handle 250A 4P MCCB 50KA 'DN' Spreader Link Door Operating Handle 63A 4P MCCB 36KA 'DN' - 0 (For Lighting) Spreader Link Door Operating Handle 63A 4P MCB 10KA (For Lighting) 32A 4P MCB 10KA (For Lighting) Star Delta Starter 100 HP (75 KW) Star Delta Starter 75 HP (55 KW) Star Delta Starter 50 HP (37 KW) DOL Starter 40 HP (30 KW) DOL Starter 20 HP (15 KW) Space for Star Delta Starter 75 HP (55 KW) CUBICAL PANEL Cubical Panel made out from 16/14 SWG CRCA sheet steel duly power coated in Siemens grey colour size of panel 8850 mm (W) X 2100 mm (H) X 1000 mm (D) Floor Mounted (Back Open) BUS BAR Bus Bar 1600A TPN AL MISC. ITEMS Wiring & fixing material Hardware & legends ANNEXURE : C Unit QTY. Nos. 1 Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. 1 1 1 3 3 1 2 1 1 2 Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. 2 2 2 2 2 2 2 3 3 3 2 2 8 5 4 3 2 4 Set 1 Set 1 Set Set 1 1 Page 26 of 153 S.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 STARTER DETAILS, BATHINDA 20 HP DOL STARTER (15 KW) Description Of Item 63A TP MCCB 36KA 'DN' - 2 Spreader Link Door Operating Handle 70A TP Contactor MNX 70 Over Load Relay 24 - 40A Control MCB 6A SP 10KA 63A Fuse Base 63A Fuse Link On & Off Ind. Light Red & Green Start & Stop Push Button Single Phase Preventor 10 KVAR Capacitor Bank MPP Type Capacitor duty power contactor suitable for 10 KVAR Capacitor MPX 12 Power Terminal Block Bus Bar Type Remote On/Off Push ButtonT. B. 5 mm2 Amperemeter 0-60A Digital with ASS CT 60/5A Wiring & fixing Material S.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 S.No. 1 2 3 4 5 6 ANNEXURE : D Unit Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Set Qty. 1 1 1 1 1 1 3 3 2 2 1 1 1 6 3 1 3 1 40 HP DOL STARTER ( 30 KW) Description Of Item 100A TP MCCB 36KA 'DN' Spreader Link Door Operating Handle 110 TP Contactor MNX 110 Over Load Relay 45 - 75A Control MCB 6A SP 10KA 63A Fuse Base 63A Fuse Link On & Off Ind. Light Red & Green Start & Stop Push Button Single Phase Preventor 20 KVAR Capacitor Bank MPP Type Capacitor duty power contactor suitable for 25 KVAR Capacitor MPX 25 Power Terminal Block Bus Bar Type Remote On/Off Push ButtonT. B. 5 mm2 Amperemeter 0-100A Digital with ASS CT 100/5A Wiring, Bus Bar & fixing Material Unit Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Set Qty. 1 1 1 1 1 1 3 3 2 2 1 1 1 6 3 1 3 1 50 HP STAR DELTA STARTER (37 KW) Description Of Item 125A TP MCCB 36KA 'DN' Spreader Link Door Operating Handle 70 TP Contactor MNX 70 Over Load Relay 30 - 50A Electronic Star- Delta timer 0-60 sec Unit Nos. Nos. Nos. Nos. Nos. Nos. Qty. 1 1 1 3 1 1 Page 27 of 153 7 8 9 10 11 12 13 14 15 16 17 18 19 Control MCB 6A SP 10KA 63A Fuse Base 63A Fuse Link On & Off Ind. Light Red & Green Start & Stop Push Button Single Phase Preventor 20 KVAR Capacitor Bank MPP Type Capacitor duty power contactor suitable for 25 KVAR Capacitor MPX 25 Power Terminal Block Bus Bar Type Remote On/Off Push ButtonT. B. 5 mm2 Amperemeter 0-150A Digital with ASS CT 150/5A Wiring, Bus Bar & fixing Material Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Set 1 3 3 2 2 1 1 1 6 3 1 3 1 S.No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 75 HP STAR DELTA STARTER (55 KW) Description Of Item 200A TP MCCB 36KA 'DN' Spreader Link Door Operating Handle 95A TP Contactor MNX 95 Over Load Relay 45 - 75A Electronic Star- Delta timer 0-60 sec Control MCB 6A SP 10KA 125A Fuse Base 125A Fuse Link On & Off Ind. Light Red & Green Start & Stop Push Button Single Phase Preventor 20 KVAR + 20 KVAR Capacitor Bank MPP Type Capacitor duty power contactor suitable for 50 KVAR Capacitor MPX 50 Power Terminal Block Bus Bar Type Remote On/Off Push ButtonT. B. 5 mm2 Amperemeter 0-200A Digital with ASS CT 200/5A Wiring, Bus Bar & fixing Material Unit Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Set Qty. 1 1 1 3 1 1 1 3 3 2 2 1 1 1 6 3 1 3 1 S.No. 1 2 3 4 5 6 7 8 9 10 11 100 HP STAR DELTA STARTER (75 KW) Description Of Item 250A TP MCCB 36KA 'DN' Spreader Link Door Operating Handle 110A TP Contactor MNX 110 Over Load Relay 66 - 110A Electronic Star- Delta timer 0-60 sec Control MCB 6A SP 10KA 125A Fuse Base 125A Fuse Link On & Off Ind. Light Red & Green Start & Stop Push Button Unit Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Nos. Qty. 1 1 1 3 1 1 1 3 3 2 2 Page 28 of 153 12 13 14 15 16 17 18 19 Single Phase Preventor 25 KVAR + 25 KVAR Capacitor Bank MPP Type Capacitor duty power contactor suitable for 60 KVAR Capacitor MPX 60 Power Terminal Block Bus Bar Type Remote On/Off Push ButtonT. B. 5 mm2 Amperemeter 0-250A Digital with ASS CT 250/5A Wiring, Bus Bar & fixing Material Nos. Nos. Nos. Nos. Nos. Nos. Nos. Set 1 1 1 6 3 1 3 1 Page 29 of 153 TIME SCHEDULE Page 30 of 153 ELECTRIFICATION JOB AT BATHINDA IRD PART LOCATION COMPLETION PERIOD FROM DATE OF BATHINDA IRD ISSUE OF FOI /LOI/ PO 4(FOUR) MONTHS NOTE: 1) Time for completion shall be reckoned from the date of issue of Fax/ Letter of Intent/Purchase Order by HPCL. 2) Time for completion shall include the time required for Design, vetting, QAP/ITP approval, mobilization, supply, inspection, demobilization, carrying out the works as per requirements of Contract Document and instructions of HPCL Engineer-in-Charge. 3) The job scope is as defined in tender. Page 31 of 153 TECHNICAL SPECIFICATIONS Page 32 of 153 TECHNICAL SPECIFICATIONS FOR ELECTRIFICATION JOBS STANDARDS Materials and equipment to be supplied by the contractor for this work shall be in accordance with relevant IS specifications. The following standards shall be applicable to various instruments. 1. 2. IS: 2516 IS: 4047 3. 4. 5. 6. 7. IS: 1818 IS: 2607 IS: 2208 IS: 3072 IS: 3106 8. IS: 4237 9. IS: 375 10. 11. 12. IS: 2705 IS: 1248 IS: 2419 Specification for AC Circuit Breakers Specification for Heavy duty air break switches and fuse for voltage not exceeding 1000 V. Specification for AC Isolators and earthing switches. Air Break Isolators for voltages not exceeding 1000V HRC Cartridge fuses links up to 650V. Code practice for installation and maintenance of Switchgear. Code of practice for selection, installation and maintenance of fuses (Voltages not exceeding 650V) General requirements for switchgear and control gear for voltages not exceeding 1000V. Marking and arrangement for switchgear busbars, main connection and auxiliary wiring. Current transformers. Direct acting electrical indicating instruments. Dimensions of electrical indicating instruments. Erection of equipment and material whether supplied by owner or contractor shall be in accordance with the best engineering practice, conforming to respective provisions of IS codes. Site testing shall conform to relevant IS code. In addition the work shall conform to the following: i) Indian Electricity rules and Acts. ii) Fire insurance regulations. iii) Requirements of Electrical Inspector. iv) Requirements of State Electricity Boards. v) Requirements of Factory Inspector vi) Requirements of State/Central/Local Authorities vii) Requirements of Chief Controller of Explosives Nagpur. Note: A Copy of the above mentioned codes/manual to be provided by the vendor at the site at no extra cost. SPECIFICATION FOR TESTING AND COMMISSIONING OF MOTORS: Power cables of the specified size shall be laid under ground from the MCC room to the motors, and emerge through a pipe of suitable diameter with bends laid up to motor base in the pump house flooring. Glands at the terminal box shall be of double compression type GP brass glands. No sealing compound shall be used in the terminal box. All electrical and mechanical checks shall be made in accordance with IS: 900. Page 33 of 153 Ventilation and cooling system of the motors shall be checked and corrected if necessary. Phase sequence of the motors shall be checked. Direction of rotation of the motors shall be checked. When no load working is found satisfactory load shall be connected with all necessary adjustment of settings for testing for further 1 hour. Contractor shall make all arrangements for de-coupling and recoupling of the pump sets with feeler gauge at no extra cost. Contractor shall be present during commissioning of the pump sets. Motor operation with push button stations shall be checked for correct operation. SPECIFICATIONS FOR FLAME PROOF PUSH BUTTON STATIONS: Each motor shall be provided with two FPBS. Each FPBS shall be provided with one indicating lamps of neon type fixed with screwed type CP brass glands, for ON positions. The push buttons shall have the following specifications: Enclosure Degree of protection No. of earthing points Painting Rating of contracts Push Buttons Cable entry Indicator Lamps Shall conform to : : : : : : : : : Cast aluminum LM-6 IP - 66 2 Epoxy 415V, 50 Hz 1NO + 1NC From Button 1 No. for on Position. IS-2148 Only flame proof double compression glands shall be used for terminating the control cables of the motor. Unused entries shall be closed by flame proof plugs. The control cables shall be of 6C X 1.5 sq mm. Size and wired to get on/off controls of the motor from places mentioned above. The FPBS shall be fixed on a frame made out of ISA 50X50X6 angle iron frame welded to the steel column of the gantry. On each column a frame of sufficient size to accommodate 2 Nos. of the FPBS shall be provided. The cables and the earthing wire shall be neatly clamped to the columns by means of MS clamps and shall be straight with no bends. The cable shall gradually enter the GI pipe and lead to the MCC. FPBS shall be fixed to the frame by nuts and bolts. SPECIFICATION FOR CABLES: General Scope This specification covers the basic requirements for design, manufacture, inspection and testing at vendor‟s works, of XLPE insulated cables upto 1.1KV for power, control and lighting purpose to be used in the Oil Terminal Project of M/s Hindustan Petroleum Corporation Ltd. (HPCL), at Mandir Hasaud – Raipur. Page 34 of 153 Codes and standards The design, construction, manufacture and performance of XLPE insulated cables shall comply with all currently applicable statutes, regulations and safety codes of the locality where cables will be installed. The cables shall conform to the applicable Indian, IEC and British Standards. The relevant Indian standards are: IS: 613 (1984) Copper rods and bars for electrical purposes IS:1885-(Part32) (1993) Electro Technical vocabulary - electric cables IS: 2633 (1986) Method of testing uniformity of coating on zinc coated articles. IS:3961-(Part4) (1968) Recommended current ratings for Polyethylene insulated cables. IS: 3975 (1988) Mild steel wire, formed wires and tapes for armouring of cables. IS: 5831 (1984) Specification for PVC insulation and sheath of electric cables. IS: 6474 (1984) Specification for Polyethylene insulation and sheath of electric cables. IS:7098-(PartI) (1988) Specification for cross-linked Polyethylene insulated, PVC sheathed cables. (For working voltages upto and including 1100 volts) IS: 8130 (1984) Conductors for insulated electric cables and flexible cords. IS: 10418 (1982) Drums for electric cables. IS: 10462 (1983) (Part 1) Fictitious calculation method for determination of dimensions of protective coverings of cables IS: 10810 (Pt 58) Methods of test for cables : Part 58 Oxygen Index test IS: 10810 (Pt 61) Methods of test for cables : Part 61 Flame retardant test IS: 10810 (Pt 62) Methods of test for cables : Part 62 Flame retardant test for bunched cables IEC:60540& 60540A Test methods for insulation & sheaths of electric cables IEC: 230 (1966) Impulse tests on cables and their accessories IEC: 60332 (3 parts) Tests on electric cables under fire conditions Page 35 of 153 IEC: 811 (5 parts) Test methods for insulating and sheathing materials of electric cables. IEC: 840 (1988) Tests for power cables with extruded insulation for rated voltages above 30KV upto 150KV ASTM: D2863 Standard method for test for flammability of plastics using oxygen index method IECAS-61-402 NEMA- Thermoplastic insulated wire & cable for transmission & distribution WC5 of electrical energy IECAS-66-524 NEMA- Cross linked thermosetting poly ethylene insulated wire & cable for WC5 transmission & distribution of electrical energy IEC: 840 (1988) Tests for power cables with extruded insulation for rated voltages above 30KV up to 150KV The cables & accessories shall also confirm to the provisions of the Indian Electricity Rules and other statutory regulations in force in the country. In case of any contradiction between various referred standards/ specifications/ data sheets and statutory regulations, the following order of priority shall be given: - Statutory regulations - Data sheets - Unit Specifications - This Specification - Codes & Standards General construction and material of construction The cables shall be suitable for laying on trays, trenches, ducts and conduits and for underground-buried installation with uncontrolled backfill and possibility of flooding by water & chemicals. Outer sheath of all PVC insulated cables shall be black in color and minimum value of the oxygen index shall be 29 at 27+/-2 0 C .In addition suitable chemicals shall be added in to the PVC compound of the outer sheath to protect the cable against rodent & termite attack. Sequential marking of the length of the cable in the meters shall be provided at every one meter. The embossing or engraving shall be legible or indelible. The overall diameter of the cables shall be strictly as per the values declared by the manufacturer in the technical information subject to a maximum tolerance of +/- 2mm up to overall diameter up to 60mm and +/- 3mm for above 60mm. Page 36 of 153 XLPE insulated FRLS cables All power and control cables shall be heavy-duty type, 1100V grade, with Copper/Aluminum Conductor, XLPE insulated, PVC inner sheathed, armoured and overall FRLS PVC sheathed. All cables covered in this specification shall be FRLS unless otherwise specified in the data sheet. The outer sheath of XLPE cables shall possess flame propagation properties meeting requirements as per IS-10810 (Part-62) category AF. Exact type of the cable shall be as specified in the cable quantity list. Conductor The conductor shall be composed of plain aluminum or high conductivity annealed copper wires complying with relevant Indian standards. The conductors of size above 6mm2 shall be stranded. Insulation The insulation shall be of cross linked polyethylene (XLPE) compound with anti oxidant stabilisers and shall conform to IS-7098, Part-1. (As applicable) Filler and inner sheath (1) The filler and inner sheath shall be of the following: (a) Unvulcanized rubber, or (b) Thermoplastic materials (2) Unvulcanized rubber or thermoplastic material used shall not be harder than PVC used for insulation and PVC used for outer sheath. The material chosen shall be compatible with temperature ratings of the cable and shall have no harmful effect on any other component of the cable. (3) The inner sheath shall be applied by extrusion method such that it fits closely on the laidup cores and shall be possible to remove without damaging the insulation. (4) Single core cables shall have no inner sheath. Armouring (1) (2) Armouring shall be one of the following: (a) Galvanized round steel wire (b) Galvanized steel strip (c) Any metallic non-magnetic wire/strip. Where the cable diameter below armour does not exceed 13mm, the armour shall consist of galvanized round steel wires. Where the diameter below armouring is greater than Page 37 of 153 13mm, the armour shall consist of either galvanized round steel wires or galvanized steel strips. (3) The joints in armour wires or strips shall be made by brazing or welding and any surface irregularities shall be removed. Outer sheath (1) The outer sheath shall be poly-vinyl chloride (PVC) compound conforming to the requirements of Type ST1/ST2 compound as per IS: 5831 and shall be of FRLS type only. (2) Outer sheath of all PVC cables shall be black in colour and the minimum value of oxygen index shall be 29 at 27 2 deg. C. In addition suitable chemicals shall be added to the PVC compound of the outer sheath to protect the cable against rodent and termite attack. (3) The outer sheath shall be applied by extrusion over the armouring. Dimension / thickness of materials The thickness of insulation, inner sheath, outer sheath and dimension of wire/strips used for armouring shall be as per relevant standards. Core identification Cores of cable shall be identified by colour coding of PVC insulation by adopting the following scheme. (1) (2) (3) (4) (5) (6) (7) 1 core : Red, black, yellow, blue or natural 2 core : Red and black 3 core : Red, yellow and blue 4 core : Red, yellow, blue and black 5 core : Red, yellow, blue, black and gray 6 core and above : The core identification shall be done by printing numbers or by providing colored strips all along cores. The insulation of cores shall be of the same colour and numbered sequentially. The numbers shall be printed in Hindu-Arabic numerals on the outer surface of cores. The numbers shall be repeated at regular intervals along the core and the spacing between consecutive numbers shall not exceed 50mm. For reduced neutral conductors, the insulation colour shall be black. Identification of Cables The cables shall be clearly and permanently marked with following information throughout the length. (1) Voltage grade. (2) Manufacturer‟s name or trade mark. (3) Year of manufacture. Cross sectional area of conductor and no of cores. Page 38 of 153 Cable Drums (1) Cables shall be supplied in non-returnable wooden drums of heavy construction. The wood used for construction of the drum shall be properly seasoned, free from defects and wooden preservatives shall be applied to the entire drum. All ferrous parts shall be treated with a suitable rust preventive finish or coating to avoid rusting during transit or storage. (2) The vendor shall indicate in the offer, the maximum length of cable, which can be accommodated on one drum. The actual length supplied on each drum shall be within tolerance limit of +5%. The drum length shall be as per the cable quantity list. (3) The cables shall be wound on drums of suitable barrel diameter, securely battened, with the take-off and fully protected against mechanical damage. The cut ends of cable shall be sealed by means of non-hygroscopic sealing material to avoid ingress of water during transit or storage. Also, PVC /Rubber end caps shall be supplied free of cost for each drum with a minimum of eight per thousand metre length. (4) The following information shall be stencilled on each drum. (a) Name of manufacturer, brand name or trademark. (b) Nominal cross sectional area of conductor (c) Number of cores. (d) Type of cable and voltage grade. (e) Cable code (f) Length of cable on the drum. (g) Number of lengths on drum (if more than one). (h) Drum number. (i) Direction of rotation of drum (by means of an arrow). (j) Reference standard (k) Approx. gross weight. (l) Job number. (m) Country of manufacture (n) Year of manufacture. A tolerance of +/- 3% shall be permissible for each drum. However, overall tolerance for each size of cable shall be limited to +/ - 2%. Offer with short / non-standard lengths are liable for rejection. If nonstandard drum lengths are specified in the data sheet, then same shall be supplied. Cable quantity The bidder shall quote unit rates for all types of cables as indicated in the Job Schedule List. Inspection and tests Note :- Manufacturer’s test certificate to be provided comprising of the following tests result for all the cables supplied:(1) All routine tests, acceptance tests, type tests & additional type tests for improved fire performance shall be carried out as listed in IS-7098 (Part-2). (2) The test for resistance to Ultraviolet radiation: This test shall be carried out as per DIN 53387 or ASTM-G-53 on outer sheath. The retention value of tensile strength & ultimate elongation Page 39 of 153 value after the test shall be minimum 60% of the tensile strength and elongation value before the test. The test certificates with respect to this test (not older than 1 year) from recognized testing laboratory to be furnished for review by PMC before dispatch clearance of cables. In case test certificates are not available, test is to be conducted by vendor at his own cost in any recognized test laboratory or in-house testing laboratory, before dispatch clearance of cables. Sampling for this test is to be carried out one for each order, provided the outer sheath remains the same. (3) Acceptance tests as per IS-1554 Part-1 and IS-7098 Part-2 and the following special tests to be performed on the cables as per the sampling plan. This tests are to be witnessed by PMC/ Owner before the dispatch of cables: a) Accelerated Water absorption test for insulation as per NEMA –WC-5 (For PVC insulated cables) and as per NEMA WC-7 (For XLPE insulated cables). Test certificates with respect to this test (not older than one year) from recognized testing laboratory to be furnished for review by PMC before dispatch, clearance of cables. In case test certificates are not available, test is to be conducted by vendor at his own cost in any recognized test laboratory or in-house testing laboratory, before dispatch clearance of cables. Sampling for this test is to carried out one for each order. (4) Dielectric Retention test: The dielectric strength of the cable insulation tested in accordance with NEMA WC-5 at 75 ± 1o C shall not be less than 50% original dielectric strength. Test certificates with respect to this test (not older than one year) from recognized testing laboratory to be furnished for review by PMC before dispatch, clearance of cables. In case test certificates are not available, test is to be conducted by vendor at his own cost in any recognized test laboratory or in-house testing laboratory, before dispatch clearance of cables. Sampling for this test is to carried out one for each order. (5) Oxygen Index Test: The test shall be carried out as per ASTM D2863 or applicable Indian Standard specifications. Sampling to be done for every offered lot / size as per sampling plan. (6) Flammability Test: The test shall be carried out on finished cable as per IS-10810 (part 61 & 62). Sampling for this test is to be carried out one for each order, provided the outer sheath remains the same. The acceptance criteria for tests conducted shall be as under: Part-61: The cable meets the specifications if there is no visible damage on the test specimen within 300 mm from its upper end. Part-62: The maximum extent of charred portion measured on the test sample should not have reached a height exceeding 2.5m above the bottom edge of the burner at the front of the ladder. (7) Test for rodent & termite repulsion property: The vendor shall furnish details to analyze the property by chemical method. Sampling to be done for every offered lot / size as per the sampling plan. Information required with the bid Vendor shall furnish technical particulars / description and performance details of all cables, current carrying capacities and derating factors, for all conditions of cable laying. Page 40 of 153 CABLE LAYING: 1 General Cable installation shall include power and control cables. These shall be laid in trenches/ cable trays as detailed in the cable layout drawings. Cable routing given on the cable layout drawings shall be checked in the field so as to avoid interference with structures, heat sources, drains, piping, air-conditioning duct etc. Any change in routing shall be done to suit the field conditions wherever deemed necessary, after obtaining approval of Engineer-incharge. 1.1 Deleted 1.2 The lengths indicated in the cables schedule is only approximate. The contractor shall ascertain the exact, length of cable for a particular feeder by measuring at site. All cable routes shall be carefully measured .Before the start of cable laying, the contractor shall prepare cable drum schedule and get that approved by Engineer-in -charge to minimize/avoid straight through joints and then the cables cut to the required lengths, leaving sufficient lengths for the terminations of the cable at both ends. The various cable lengths cut from the cable reels shall be carefully selected to prevent undue wastage of cables. Extra loop length shall be given for feeder cables where required as per the directions of Engineer-in-charge to meet contingencies. Cables shall be laid in directly buried trench or in RCC trench (underground trench) or in cable tray along pipe sleepers or in over head trays as shown on cable layout drawings. Overhead trays shall be installed 2700 nun (minimum) above grade level. At road crossings overhead trays shall be installed at 7000 mm (minimum) above grade level or cables shall be routed cable tray culvert/ Electrical road crossings as per layout drawings. Sufficient care shall be taken while laying cables to avoid formation of twist, sharp bend etc. in order to avoid mechanical injuries to cables. Rollers shall be used for pulling of cables Cable installation shall provide minimum cable bending radii as recommended by cable manufacturer. 1.3 Cables shall be neatly arranged in the trenches / trays in such a manner that criss-crossing is avoided and final take off to the motor / switchgear is facilitated. Arrangement of cables within the trenches / trays shall be in line with cable layout drawings. Cable routing between cable trench and equipment/motors shall be taken through GI pipe sleeves of adequate size. Pipe sleeves shall. be laid at an angle of maximum 45 to the trench wall. Bending radius of pipes shall not be less than 8D. It is to be ensured that both the ends of GI pipe sleeves shall be sealed with approved weather proof sealing plastic compound after cabling. In places where it is not possible, cables shall be laid in smaller branch trenches. 1.4 All cables shall be identified close to their termination point by cable tag numbers as per cable schedule. Cable tag numbers shall be punched on aluminum straps (2mm thick, 20 mm wide and of enough length) securely fastened to the cable and wrapped around it. Each underground cable shall be provided with cable tags of lead securely fastened every 30 m of its underground length with at least one tag at each end before the cable enters/leaves the ground. In unpaved areas, cable trenches shall be identified by means of cable markers as per installation drawing. These cable markers shall be placed at location of changes in the direction of cables and at intervals of not more than 30 in and also at cable straight through joint locations. 1.5 All temporary ends of cables must be protected against dirt and moisture to prevent damage to Page 41 of 153 the insulation. For this purpose, ends of cables shall be taped with an approved PVC end cap or rubber insulating tape. 1.6 Each row of cables shall be laid in place and before covering with sand. All wall openings/pipe sleeves shall be effectively sealed after installation of cables to avoid seepage of water inside building/lined trench. Every cable shall be given an insulation test in presence of Engineer-in-charge/Owner before filling the cable trench with sand Any cable which is found defective shall be replaced 1.7 Where cables pass through foundation walls, the necessary openings shall be provided in advance for the same by another agency. However, should it become necessary to cut holes in existing structures for example floor slab etc., the electrical contractor shall determine their location and obtain approval of the Engineer-in-charge before carrying out the same. 1.8 Cables for road crossings shall be taken through ERC (Electrical Road Crossing) as shown in the cable layout drawings. At road crossing and other places where cables enter pipe sleeves adequate bed of sand shall be given so that the cables do not slack and get damaged by pipe ends. 1.9 Wherever cable trench crosses storm water, waste water channel/drain, cables shall be taken through PVC/RCC pipes. Where cables are required to cross drains of depth more than 1200 mm, cables shall be taken over the drain on cable trays supported suitably using ISMC 150/200 sections. 1.10 Ends of cables leaving trench shall be coiled & capped and provided with protective cover till such time the final termination to the equipment is completed. 2 Cables laid direct in ground Cables shall be laid underground in excavated cable trenches where specified in cable layout drawings. Trenches shall be of sufficient depth and width for accommodation of all cables. Cables shall be properly spaced and arranged with a view of heat dissipation and economy of design. Maximum number of cable layers in trench shall be preferably limited to 5 layers. Minimum depth of cable trench shall be 750 mm for low voltage. The depth and the width of the trench shall vary depending upon the number of layers of cables as per EIL installation Standards Cables shall be laid in buried trenches at depth as shown in the cable layout drawings. It is to be insured by the contractor that the bottom of buried trenches shall be cleared of all rocks, stones and sharp objects before cables are placed. The trench bottom shall be filled with a layer of sand. This sand shall be leveled and cables laid over it. These cables shall be covered with 150 mm of sand on top of the largest diameter cable and sand shall be lightly compacted. A flat protective covering of 75 min thick second class red bricks shall then be laid and the remainder of the trench shall then be back -filled with soil, rammed and leveled. 3 Cables laid in concrete trench Cables shall be laid in 3 or 4 tiers in concrete trench as shown on layout drawings. Concrete cables trenches shall be filled with sand in hazardous area to avoid accumulation of hazardous gases and oil. RCC covers of trenches shall be effectively sealed to avoid ingress of chemical Page 42 of 153 and oil in process area. Removal of concrete covers where required for the purpose of cable laying and reinstating them in their proper position after cables are laid shall be done by electrical contractor. All wall openings/pipe sleeves shall be effectively sealed after installation of cables to avoid seepage of water 4 Above ground cables 4.1 Cables installed above grade shall be run in cable trays, clamped on walls, ceiling or structures and shall be run parallel or at right angles to beams, walls or columns. Cable routing shall be planned to be away from heat sources such as hot piping, gas, water, oil drainage piping, air-conditioning duct etc. Each cable tray shall contain only one layer of cables as far as possible for power cables. However control cables may be laid in double layer in the cable trays. 4.2 Individual cable or small group of cables (up to 3 to 4 cables) which run along structures / walls etc. shall be clamped by means of 16 SWG GI saddles on 25 x 6 mm saddle bars. Alternatively small group of cables can be taken through 100/150 mm slotted channel tray / ISMC 100. Cables shall be supported so as to prevent sagging. In general, distance between supports shall be approximately 300 mm for cables up to 25 mm diameter and maximum 450 mm for cables larger than 25 mm dia. to prevent the sagging of cables. 4.3 Cable laid on supporting angle in cable trenches, structures, columns and vertical run of cable trays shall be suitably clamped by means of G.I. saddles / clamps, whereas cables in horizontal run of cable trays shall be tied by means of nylon cords. Distance between supporting angles shall not exceed 600 mm. 4.4 All cable trays (other than galvanized trays) and supporting steel structures shall be painted before laying of cables. The under surfaces shall be properly degreased, derusted, descaled and cleaned. The painting shall be done with one coat of red oxide zinc chromate primer. Final painting shall be done with two coats of approved bituminous aluminum paint unless otherwise specified. 4.4 All cable trays (other than galvanized trays) and supporting steel structures shall be painted before laying of cables. The under surfaces shall be properly degreased, derusted, descaled and cleaned. The painting shall be done with one coat of red oxide zinc chromate primer. Final painting shall be done with two coats of approved bituminous aluminum paint unless otherwise specified. 4.5 Where cables rise from trench to motor, lighting panel, control station, junction box etc., they shall be taken in (31 pipe for mechanical protection up to a minimum of 300 mm above grade. Cable ends shall be carefully pulled through conduit to prevent damage to cable. 4.6 All G.I. Pipes shall be laid as per layout drawings and site conditions. Before fabrication of various profiles of' pipes by hydraulically operated bending machine (which is to be arranged by the contractor) all the burrs from the pipes shall be removed. GI Pipes having bends shall be buried in soil / concrete in such a way that the bend shall be totally concealed. For G.I. pipes buried in soil, bitumen coating shall be applied on the buried lengths, Installation of G.I. pipes shall be undertaken well before paving is completed and necessary co ordination with paving agency shall be the responsibility of Electrical Contractor. Page 43 of 153 Following guide shall be used for sizing of G.I. pipe. a) b) c) d) 4.7 1 cable in a pipe - 53% of pipe cross-sectional area occupied by cables. 2 cables in a pipe - 31 % of pipe cross-sectional area occupied by cables. 3 cables in a pipe - 43% of pipe cross-sectional area occupied by cables. 4 and above cables in a pipe - 40% of pipe cross-sectional area occupied by cables. After the cables are installed and all testing is complete, conduit ends above grade shall be plugged with a suitable weatherproof plastic compound/bitumen/suitable sealing compound. Alternatively rubber bushes shall be employed for the purpose of sealing. TERMINATIONS 5.1 All PVC cables up to 1100V grade shall be terminated at the equipment by means of compression type cables glands suitable for the cable size. They shall have a screwed nipple with conduit electrical threads and check nut. The cables shall be identified close to their terminations points at both the ends of cable ( cable numbers shall be punched on aluminum straps 2 mm thick and securely fastened to the cable, wrapped around it ) and also along the route at recommended intervals, by cable tag numbers. All cable entries for outdoor termination shall be preferably through bottom. Outdoor cable termination through top of equipment shall not be permitted. 5.2 Power cables cores wherever color coding is not available sha ll be identified with red, yellow and blue PVC tapes. Where copper to aluminum connections are made, necessary bimetallic washers shall be used. 5.3 In case of control cables, all cores shall be identified at both ends by their terminal numbers by means of PVC ferrules suitable for core size. Wire numbers shall be as per schematic/ wiring/inter-connection diagram. All unused spare cores of control cables shall be neatly bunched and ferruled with cable tag at both ends, for future use. For trip circuit identification additional red ferrules shall be used only in the particular cores of control cables at the termination points in the Switchgear/ Control panels and Control Switches. 5.4 Contractor shall drill holes for fixing glands wherever necessary. Gland plate shall be of nonmagnetic material/ aluminum sheet in case of single core cables. All unused cable entries on equipment/panels shall be plugged/ sealed. 5.5 The cable shall be terminated at electrical equipment/switchboards through glands of proper size. The individual cores shall then be dressed and taken along the cables ways or shall be fixed to the panels with polyethylene straps. The cable glanding shall be done as per manufacturer‟s instructions. Cable armor shall not be exposed after termination is complete. In case of termination of cables at the bottom of a panel over a cable trench having no access from the bottom close fit holes shall be drilled in the gland plate for all the cables in one line, and then gland plate shall be split in two parts along the centre line of holes. After fixing bottom plate, uncovered cable holes/gaps shall be sealed with cold setting compound. 5.6 Crimping of lugs to cable leads shall be done by hand crimping / hydraulically operated tool as per requirement. Insulation of the leads shall be removed before crimping. Conductor surface shall be cleaned and shall not be left open. Suitable conducting jelly shall be applied on the conductor lead. Lugs shall enclose all strands of cable core. Cutting of strands shall not be allowed. Page 44 of 153 5.7 The contractor shall bring to the notice of Engineer-in-charge any mismatch in cable glands, lugs provided with the equipment vis-a-vis to the cable size indicated in cable schedule for taking corrective action. 5.8 The cable joints in power and control cables shall be avoided as far as possible. In case a joint is unavoidable, the following shall be insured: The number of joints shall be restricted to minimum as far as possible. The location of joints shall be identified with permanent markers. No joints shall be allowed in hazardous areas without the approval of Engineer-in charge. The jointing and termination of medium voltage power cables shall be carried out by trained personnel only. Jointing and termination of high voltage cables shall be done by skilled and experienced jointer duly approved by Engineer-in-charge. Only type tested termination kits of approved make shall be used. 5.9 No unauthorized repairs, modifications shall be carried out on the hazardous area equipment terminal boxes and junction boxes. Damaged enclosures of hazardous area equipment shall be brought to the notice of Engineer-in-charge by contractor. After termination is complete, all the bolts, nuts, hard ware‟s of terminal box shall be properly placed in its po sition and tightened. 5.10 Where required, cable sealing boxes intended to be used with the apparatus shall be filled with solid setting type bituminous compound unless otherwise specified. TESTING AND COMMISSIONING 6.1 Field testing and commissioning of electrical installation shall be carried out as per specification. 6.2 Before energizing, the insulation resistance of every circuit shall be measured from phase to phase, phase to neutral and from phase/neutral to earth. 6.3 Where splices or terminations are required in circuits rated above 650 volts, insulation resistance of each length of cable shall be measured before splicing and or / terminating. After completion of splices and /or terminations measurements shall be repeated. 6.4 The insulation resistance of directly buried cables shall be measured before cable trenches are backfilled. Measurements shall be repeated after back filling. For cables up to 1.1 kV grade 1000 V Megger and for H.V. Cables 2.5 kV / 5 kV Megger shall be used. 6.5 D.C. High Voltage test shall be conducted on cables given below after installation. All 1100 volts grade cables in which straight through joints have been made. All cables above 1100 V grade. The D.C. High Voltage test shall be performed as detailed below in the presence of the Engineer-InPage 45 of 153 charge or his authorized representative only. Cables shall be installed in final position with the entire straight through joints complete. During the high voltage test, all other electrical equipment related to the cable installation, such as switches, instrument transformers, bus bars, etc., must be earthed and adequate clearance shall be maintained from the other equipment and framework to prevent flash over. In each test, the metallic sheath/screen/armor shall be connected to earth. 6.6 All checks and tests shall be made as per standard test performs available with site engineer. All test readings shall be recorded and submitted to HPCL in triplicate sets. 6.7. Cable schedule, cable layout drawings, Interconnection drawings shall be marked by contractor for 'AS BUILT STATUS' and two sets of copies shall be submitted to HPCL. CABLE MARKERS: Contractor shall supply and fix CI cable markers at every 15mts distance and also at every change of direction. Cable markers shall be as per IS specifications. CABLE TRAYS (Contractor supply) Cable trays shall be fabricated out of 10 SWG GI perforated sheets. The cables shall be secured to the trays at every 1 m with painted MS hooks. The width of the trays shall be sufficient width to accommodate all cables with 50mm clear spacing. This shall be supplied and installed by the contractor. GANTRY AND PUMP HOUSE: For gantry flame proof well glass fittings shall be provided one in each bay and one above each of the checking platform. Two Nos. flame proof rotary switches shall be provided to control these circuits. For pump house FLP well glass fittings shall be provided one in each bay and one FLP rotary switch be provided for every 3 Nos. of the fittings. The switches shall be provided at 1.6mt ht. from the floor level in both the structures. SPECIFICATIONS FOR EARTHING SYSTEM: MATERIALS FOR EARTHING: Earthing system shall comprise of GI strips and GI plates, GI wires of proper size as specified, GI Electrodes, salt, charcoal, G1 clamps, bolts, etc. All earthing pits shall be of pipe electrode type mentioned in IS 3043 Latest edition with all GI parts. The earthing conductor shall be laid at 500 mm depth inside the ground. When cable trenches are provided the conductor shall be clamped to the walls of the trench. Page 46 of 153 All the joints under ground shall be welded and protected from rusting by treating with Barium chromate. Such welded surfaces shall be protected by applying Zinc chromate red oxide and aluminium paint. Finally they shall be treated with Bitumen paint. Equipment and machinery like motors, control panel, oil circuit breaker and transformer shall be earthed individually. Exposed parts of the earthing conductor shall be treated with Bitumen Paint. MAKE: Cables offered shall be from reputed manufacturer. Vendor to specify manufacturer‟s name in the technical bid. It will be mandatory to supply the same make cable if accepted by us during technical evaluation. DRAWING AND DATA: The vendor shall furnish technical particulars of cables, type, make and BIS certificate with their offer in duplicate failing which the offer is liable to be rejected. NOTE: Any deviation from the above specifications shall be brought out clearly by the vendor on separate sheet. Both the specifications and job schedule shall be duly filled, signed and returned to HPCL without which offers are liable to be rejects. SPECIFICATION FOR ERECTION AND COMMISSIONING OF PANELS MAIN MCC PANEL: Following pre-commissioning checks and tests shall be carried out on Main MCC panel: Control wiring, busbar and other live parts of the circuit shall be meggered by 1000V for Resistance values. If interior of the equipment is moist or gives lower Resistance value, then entire equipment shall be dried up as per instruction of Engineer-in-charge. All protective alarm or other relays shall be checked for the working if required by secondary injection method and test certificate shall be given. All the fuses of the main and control circuit shall be checked for rating and continuity. All indicating lamps shall be working. The doors shall be closing properly and gaskets shall not peel off. The tripping and closing mechanism shall work properly. Various clearances shall be maintained as per rules. Metallic parts of the equipment shall be properly earthed. Interlocking arrangement of transformer OCB and DG shall be checked for proper working. If any of the above is not satisfactory, it shall be reported to the Engineer-in-charge for necessary corrective action. Page 47 of 153 LIST OF ACCEPTABLE MAKES OF MATERIAL/COMPONENTS The following are the acceptable makes of materials & components to be used in the installation:1) ACB L&T /GE/SIEMENS /SCHENIEDER 2) FUSE SWITCH L&T /GE/SIEMENS /SCHENIEDER 3) HRC FUSES L&T /GE/SIEMENS /SCHENIEDER 4) CONTACTORS L&T /GE/SIEMENS /SCHENIEDER 5) THERMAL O/L RELAYS L&T /C&S /GE/SIEMENS /SCHENIEDER 6) CONTROL SWITCHES KAYCEE /SALZER 7) PUSH BUTTONS TEKNIC /VAISHNO /SCI 8) INDICATING LAMPS TEKNIC /VAISHNO /FTC /L&T 9) TIMERS EAPL /L&T /TEKNICA /SIEMENS 10) INDIATING METERS DIGITAL AE/RISHABH /INDOTECH 11) TERMINALS CONNECTWELL /ELMEX /TOSHA 12) MCB‟S MDS/INDO-KOPP /GE /L&T 13) PROTECTIVE RELAY AVKC /GE /EASUN 14) MCCB ABB /L&T /SIEMENS /SCHNIEDER 15) 4 POLE CHANGEOVER HAVELLS /HPL-SOCOMCE 16) CT AE/INSEL/ C&S/ GILBERT & MAXWELL/ AREVA/ KAPPA ELECTRICALS/ PRAGATI ELECTRICALS/ SILKAANS 17) SPP MINILEC /L&T 18) CABLE GLANDS BRACO/ COMET/ COMOS/ SWITCH 19) FLP FITTINGS FLAMEPROOF EQUIPMENTS/ BALIGA/ SUDHIR (Wellglass & Floodlight Fittings SWITCHGEARS/ SHYAAM SWITCHGEARS/ ACTIVAA Push Buttons, Telephone etc.) TECHNO-CONTROLS PVT. LTD./ FLEXPRO/ FCG 20) LIGHTINGS BAJAJ ELECTRICALS/ SURYA ROSHINI/ PHILLIPS/ WIPRO/ GE 21) STRAIGHT THRU JOINTS M-SEAL/ 3-M/ RAYCHEM 22) CABLES CCI/ HAVELS/ POLYCAB/ RPG/ KEI/ FINOLEX 23) ATS/ MANUAL CHANGEOVER HAVELLS/ SIEMENS/ L&T/ SCHNEIDER/ ABB 24) BUSBAR HINDALCO/ EQUIVALENT APPROVED MAKE Page 48 of 153 Specific Requirements: All components shall be rated for in-panel (i.e. with the components inside the panel) continuous current carrying capacity with end temperatures as defined in this tender document and shall be rated for specified short circuit rating for 1 sec. All bus bars and jumpers of outgoing feeders shall be rated 20% higher than the incomer or outgoing switch. The switchboard shall be rated for specified MVA level or fault current for 1 sec. Links shall be used for connecting the FDS and the vertical bus bar. Short circuit capacity of this link shall be as the vertical bus bar. All MCB‟s supplied shall be rated for 240/415 V, IP20, DIN rail mountable, and with pad lock support, Biconnect upper & lower terminals, Safety shutter at cable terminals & Suitable for clip on accessories. Minimum compartment size for the contactor feeder shall be 200 mm. Maximum height of operating handle/ switch shall exceed 1900 mm and the minimum height shall be below 300 mm. A minimum of 10% spare shall be provided in each terminal block, without affecting the size of the module. Control bus shall be provided and the power for same shall be derived from the incomer or Control transformers wherever applicable. Earthing of doors shall be done with flexible braided copper up till the earth bus bar in the respective module. The earth bus shall run into every module and the size of the bus bar shall be furnished. Proper space and arrangement should be available in cable alley to clamp and segregate the power and control cables. The rear door shall be of 400 mm width and shall vertical-split type for rear access. This is done to ensure minimum rear clearance. Following details shall be provided along with offer; Comprehensive characteristics of the O/L relay. Minimum clearance required on all the three sides of the panels. Page 49 of 153 Rating of space heater provided for panel and its adequacy. For multiplication of breaker contacts, latched in type relays (VAJC of Alstom make or equivalent) shall only be used. Alternatively, only breaker auxiliary contacts shall be used wherever required. Protection relays shall be numerical type, communicable, with protocol for communication as IEC –5-103. Vendor shall therefore specifically mention the relays offered in their quotation. No other makes/ models of relays shall be accepted. Prior to the ordering of the relay, vendor shall take approval from HPCL regarding the ordering information details. Other than the relays mentioned above, any other relays required for achieving the operation of the switchboard shall be supplied by the vendor without any extra cost. The MCCB breaking capacity shall have Icu = 100% of Ics for the entire range. Coil of the contactor shall be suitable for operation on 240V, 1 PH, AC supply and shall work satisfactorily between 65 to 110% of rated value. CT‟s shall have minimum ratings of 10VA and metering equipments shall have sufficient ISF‟s. Separate cores shall be used for metering through analogue meters / load managers. When metering is done through relays, protection core shall have additionally the metering class accuracy built into. Maximum height of the Board, including the height of the base channel, shall not be more that 2450 mm The maximum height of the operating handle/ switches shall not exceed 1900 mm and the minimum height not below 300 mm. Unused modules in the panel shall be fully equipped with hinged door, power and control terminals for starter modules and cradle for future use. Outgoing ACB‟s can be mounted in a maximum of two tier execution while the incoming/ bus coupler ACB‟s shall be single tier execution only. The metering and protection equipments associated with a particular breaker shall be mounted on the same panel front. The in-panel current carrying capacity of main phase bus bars shall be 20 % more than incomer breaker rating. The in-panel current rating of the neutral busbars shall be the same as that of respective phase busbars. Page 50 of 153 The minimum earth bus size shall be 25 x 3 mm copper and shall be of adequate cross-section to withstand the specified fault level. Double front M.C.C. shall have two nos. earth busbars, one for each front. Minimum size of bus bars for starter/ feeder power connections above 100 Amp rating shall be 20 x 6 mm Aluminium. Minimum size of bus bars for control bus bars shall be 25 x 3 mm Aluminium. Busbars shall be of high conductivity electrolytic aluminium ( E91E)/ copper. Unloading and stacking of the panels at our premises. TECHNICAL SPECIFICATION MV SWITCHGEARS & PANEL BOARD :The panel shall be manufactured as per the following specification. deviation from In case of any the mentioned, vendor shall bring into notice the same along with its offer. In absence of such deviation, it will be presumed that equipment offered is exactly similar to the specification. The following Standards shall be refered :5 Colors for Ready Mixed Paints 375 Specification for Marking & Gen Arrangement of Swgr, Busbars, Main Connection & Aux. Wiring 398 Specification for Hard Drawn Stranded Aluminum & Steel Cored Aluminum Conductors for Overhead Power Transmission Purpose 513 Cold Rolled Low Carbon Steel Sheet & Strips 722 Specification for A. C. Electricity Meters. (Integrity Meters) 1248 Specification for Direct Acting Electrical Instruments. 1822 AC Motor Starters of Voltages not exceeding 1000 V Page 51 of 153 1841 Specification for EC grade Aluminum Rod Produced by Rolling 1897 Specification for Copper Strips for Electrical Purposes 1901 Visual Indicator Lamps. 2147 Degree of Protection provided by Enclosure for Low Voltage Switchgear 2208 Specification for HRC Fuse Links up to 650 Volts 2516 A.C. Circuit Breaker Requirement for Voltages not Exceeding 1000 V (Part - I, Sec - I + Part - II, Sec-II) 2705 Specification for Current Transformers. 2834 Specification for Capacitors for Power System 2959 AC Contactors for voltages not exceeding 1000 V 3202 Code of Practice for Climate Proofing of Electrical Equipment 3231 Electrical Relays for Power System Protection. 3247 Switchgear General Requirements 3427 Metal Enclosed Switchgear & Control gear 4064 Specs for Heavy Duty Air Break Switches Fuses for Voltages not exceeding 1000 V. 4237 General Requirement for Switchgears & Control gear for Voltage not exceeding 1000 V 6875 Control Switches / Push Buttons 8623 Factory Built Assemblies of Switchgears & Control Gear. 8828 Miniature Circuit Breaker Indian Electricity Acts & Rules :All codes & standards means the latest, wherever not specified. The manufacturing shall generally follow the Indian Standard codes of practice or the relevant British Standard Codes of Practice in the absence of corresponding Indian Standard. Page 52 of 153 REQUIREMENTS OF SWITCHBOARD: A. General: All switchboards shall comply with the requirements of IS 8623 applicable for Factory Built Assemblies. Refer to “Data Sheet of required switchboard” & “SLD” , if any, for rating of feeders, individual components, service designation & total number of each type of feeders required on the switchboard completely assembled in one line up . B. SWITCHGEAR MODULES Feeders are classified into three main categories viz. Air circuit breakers, switch dis-connector fuse/ MCCB feeders and motor starter feeders. MCCB : Fuse less starters with minimum 18 control terminals.. All combination motor starter feeders shall meet requirements of type-II coordination as per IS:13947. All identical modules shall be interchangeable. Internal control wiring of all modules of each type shall be identical for all ratings. C. COMPONENTS: I. Circuit Breaker :1. General Construction : Air Circuit breakers shall be Air break, double break, quick make/ break, fully draw out type, electrically operated, with or without overload and short circuit releases as indicated in enclosed single line diagram. ACB shall be modular in construction and conforming to the latest IS specification IS – 13947 (2) & or IEC60947. It shall comprise three/ four separate identical single pole units operated through a common shaft by the operating mechanism. Exact ratings and no. of poles shall be as indicated in SLD. Circuit breaker for generator incomer and of substations catering primarily to unbalanced loads shall be with four poles with the 4th pole 100% rated. Main poles of the breakers shall operate simultaneously. There shall be no objectionable rebound and the mechanism shall not require any critical adjustment. It shall be strong, rigid, positive and fast in operation. Air Circuit breaker along with its operating mechanism shall be mounted on a Page 53 of 153 wheeled carriage moving on guides or any other suitable mechanism, designed to align correctly and allow easy movements. All Air circuit breaker trucks of the same rating shall be interchangeable. The racking handle, manual charging handle and mechanical close / open push button shall be in the front and shall be an integral part of ACB. All circuit breakers of same rating shall be identical in all respects and shall be interchangeable. Releases are not required to be provided with breakers where relays are used. Arc extinguishing devices shall be easily removable for routine inspection of fixed contact assemblies. Circuit breaker for bus couplers shall be identical to the incoming/outgoing breaker. There shall be distinct overall door for the breaker compartment and it should be lockable. 2. Electrical ACB shall be suitable for operational voltage 415 V AC and insulation voltage of 690 V AC + 10%, 50Hz supply system and shall be suitable for impulse withstand of 12 kV. ACB shall be suitable for isolation according to IEC 60 947-2 The ACB at its rated current shall be suitable for operation in extremely tropical humid climate at 50 Deg C ambient temp. The ACB shall have no derating upto 55 C service temperature. In case the ACB needs derating, manufacturer shall declare the derated current carrying capacity at 55 C service temperature. ACB shall have a service breaking capacity rating (Ics) of 65KA for rated current upto 1600A, 80 KA for rated current from 2000- 3200 A & 100 kA for 4000 to 6300 Amp . ACB shall have minimum short circuit breaking capacity of Icw =70 kA for 1 sec. & Ics = 100% of Icu. The ACB shall be fitted with an under voltage release of 240 or 415 V ac with built-in time delay to avoid nuisance tripping. Circuit breakers shall be suitable for switching duty of motors. Page 54 of 153 ACB can be reverse fed without compromising on the performance. ACB shall be provided with following, Universal motor rated for both 240 V A.C & 110 V DC for charging the breaker closing spring. Closing coil rated for satisfactory operation from 80% to 110% of rated voltage of 110 V DC. Tripping coil rated for satisfactory operation from 50% to 110% of rated voltage of 110 V DC. Limit switches with 2 NO and 2 NC contacts for cutting off the power supply to spring charging motor and closing coil circuit. Each circuit breaker shall have necessary auxiliary contacts for indication, protection, interlocking supervision, metering and other purposes. Min. 8 „NO‟ + 8 „NC‟ breaker operated potential-free changeover contacts rated for 10 amps at 240 V AC and 1.0 amp (inductive breaking) at 110V DC shall be provided for owner‟s exclusive use. All spare contacts shall be wired upto the terminal blocks. If these are not available, keep type relay shall be used to multiply contacts of the breakers. The shunt trip of the circuit breaker shall be wired through an advanced „NO‟ contact, which shall make before the main contact close. Auxiliary contacts and limit switches shall be in dust tight enclosures. 3. Draw Out Mechanism There shall be 4 distinct and separate position on the draw out frame viz. „Service‟, „Test‟, „Fully withdrawn‟ and „maintenance‟ positions for the breakers. In the „Test‟ position the circuit breaker shall be capable of being tested for operation without energizing the power circuits, i.e. the control circuits shall remain undisturbed while the power contracts shall be disconnected. Separate limit switches each having a minimum of 4 „NO‟ contacts shall be provided for both „Service‟ and „Test‟ positions of the circuit breakers. It shall be possible to padlock the draw out ACB in the connected, test and disconnected position of the guide frame. Main plug-in contacts of the guide frame shall not have joints to avoid the heat generation & possibility of loose contacts inside the cubicles. Jaw contacts of the plug-in main contacts shall be detachable from the guide frame to ease the maintenance. If required, it shall be possible to provide rated current coding between circuit breaker and guide frame. Connection of the control circuit between the fixed portion of the cubicle and the breaker carriage shall be by means of a plug and socket having adequate number of pins. The plug and socket shall be so designed that it shall be possible to insert the plug into the socket in one position only, thereby Page 55 of 153 eliminating the possibility of faulty insertion and wiring connections. The plug, after insertion, shall be secured in position by spring clamps, which need considerable force to operate. The length of the plug cord shall be such that the plug can be inserted into the socket only when the breaker is in the „Service‟ and „Test‟ positions but it shall be necessary to withdraw the plug from the socket before the breaker truck can be pulled out into the “Fully Withdrawn” position. Isolating plugs and sockets for power as well as control circuits shall be of robust design and fully self-aligning. Plugs and sockets for power circuits shall be silver faced and shall be shrouded with PVC or any other insulating material shrouds. Each circuit breaker panel shall be provided with integral earthing switch for cable earthing. An integral earthing system or separate earthing carriage shall also be provided, which can be inserted to facilitate earthing of cables after withdrawing the circuit breaker. Circuit breaker cubicles shall be provided with safety shutters operated automatically by the movement of the circuit breaker carriage, to shroud the stationary isolated bus side contacts and the cable side main disconnecting contacts of the circuit breakers, when the circuit breaker is withdrawn. Padlocking facilities shall be provided for locking the shutters positively in the closed position. It shall, however be possible to open the shutters intentionally against spring pressure for testing purposes. Shutters shall be made of permalli/ hylam with minimum 10 mm thickness and shall be painted red in color. The breaker feeder trolley shall remain inside the cubicle even in the drawout position. 4. Indications: Following shall be indicated electrically through cluster type LED color lamps. BREAKER „CLOSE‟ - RED BREAKER „OPEN‟ -GREEN BREAKER „AUTO TRIP‟ -AMBER READY TO CLOSE - YELLOW TRIP CIRCUIT HEALTHY - WHITE Mechanical indicator coupled to the operating mechanism shall be provided to positively show the following It shall be located in a position where it will be visible to the operator standing on the front of the switchgear with cubicle door closed. BREAKER STATUS : Open and Closed. BREAKER POSITION : SERVICE , TEST & Isolated Page 56 of 153 SPRING CHARGE CONDITION READY TO CLOSE when all trip & off conditions are eliminated . Breaker “Service” and “Test” positions shall be indicated by separate indicating lamps on the cubicle door, in case mechanical indication of “service” and “Test” positions are not available on the cubicle door. Physical contact wear indicator shall be provided to indicate the erosion of the contacts. Inspection of the contact shall be possible only with the circuit breaker in ON condition. Operation counter reading at least up to 999 figures. 5. Breaker Operating Mechanism :- Circuit breaker shall be closed by a motor operated spring charged stored energy mechanism and shall open through a shunt tripping device operated by a suitable voltage from battery or rectifier. Spring operated mechanism, shall be complete with motor, opening spring, closing spring with limit switch for automatic charging and all necessary accessories to make the mechanism a complete operating unit. The spring charging motor shall be universal type operable on both AC and DC. Operating mechanism shall be shall be suitable for remote operation and designed to give trouble free service over extended periods and shall be trip free. The ACB shall have trip free mechanism which prevents the mechanism from interfering with the tripping or opening action. operating The closing/ tripping circuits shall be self-opening on completion of their respective functions irrespective of the position of the functions or the position of the control switch. As long as power is available to the spring charging motor, a continuous sequence of closing and opening operations shall be possible. After failure of power supply to the motor, at least one open-close-open operation of the circuit breaker shall be possible. Breaker duty shall be O-3min-CO-3min-CO except for switchgear line up having motor feeders with stage wise, re-acceleration feature in which case the duty shall be O-0.3sec.-CO-3min-CO. Arrangement shall be provided for slow closing and slow opening of circuit breaker for maintenance purpose. Breaker operation shall be independent of the motor, which shall be used solely for compressing the closing spring. Closing action of the circuit breaker shall compress the opening spring ready for tripping. Closing operation shall be completed once the closing impulse is given and the first Page 57 of 153 device in the control scheme has responded even though the control switch/PB is released provided no counter trip impulse is present. When closing springs are discharged, after closing a breaker, closing springs shall automatically be charged for the next operation without waiting for tripping of circuit breaker. In case the limit switch fails to cut out the spring charging motor when the springs are fully charged, the motor shall be automatically decoupled and annunciation for this shall be provided. Motor shall be such that it requires only about 30 sec. for fully charging the closing spring. Motors shall be rated for 240V AC & 110 V DC and shall operate satisfactorily at all values of voltage between 80% to 110% of rated voltage. The circuit breaker shall have facility to charge the spring manually and close the breaker in the event of failure of motor/ control supply to motor. The motor shall be automatically, delinked (mechanically) once the manual charging handle is inserted. Closing time of circuit breakers with manual operating mechanism shall be independent of the speed of the operating handle. Operating mechanism shall be non-pumping electrically and mechanically under every method of closing (except on manual closing of breaker during maintenance). Electrical antipumping feature shall be obtained by means of an auxiliary relay. Use of contactor to achieve this feature is not acceptable. The anti pumping features shall be maintained even when the bus voltage disappears during fault. Operating Mechanism shall be such that failure of any auxiliary spring shall not cause unintended operation of breaker or prevent intended tripping operation and will not cause tripping or closing operation of the power operated closing devices. When the circuit breaker is already closed, failure of any auxiliary spring shall not cause damage to the circuit breaker or endanger the operator and closing of circuit breakers shall be prevented unless the spring is fully charged. A shunt trip shall operate correctly under all operating conditions of the circuit breaker upto the rated breaking capacity of the circuit breaker and all values of supply voltage between 50% and 110% of rated voltage. All breakers shall be trip free and shall be provided with a release to trip the breakers instantaneously if closed on to a fault. Mechanical trip push buttons shall be provided for manual operation of the breaker and shall be brought out to the front of the cubicle door. Mechanically operated „closing‟ device shall be provided for all breakers except circuit breakers controlling motor feeders. Access to mechanical closing device shall be only after opening the cubicle door. The close/trip control switch shall be interlocked to trip before close. Page 58 of 153 The tripping time of C.B. shall not exceed 5 cycles (100 Msec.). The circuit breaker closing time shall be approximately 5-7 cycles. The closing and tripping time of the breaker shall be independent of the speed of the operating handle. 6. Breaker Operating Mechanism Control :- Operating Mechanism shall normally be operated by remote electrical control or through the relay when the breaker is in “Service” position. Provisions shall be made for local electrical control or through the relay when the breaker is in “Test” position by a control switch on the switchgear cubicle door. Also, “Local/Remote” selector switch lockable in “Local” position shall be provided on the cubicle door. Castell key lock if asked for shall be provided on the ACB itself. Facility shall be provided to remove the castell key only when ACB is in OFF condition & it is ensured that contacts are separated such that suitable for isolation. 7. Breaker Safety Interlocks & Features :- Mechanical /Electrical interlocks shall be provided to prevent mal-operation and in particular to ensure: a) The breaker can be operated only if it is in the defined “Full in” or “service” and “test” position inside the panel. It shall be not be possible to operate the breaker in intermediate positions while inserting or withdrawing circuit breaker. It shall not be possible to operate breaker in service position unless its primary contacts are fully engaged. b) The breaker cannot be closed until closing spring is under fully charged condition. c) Withdrawal or engagement of a circuit breaker shall only be possible if it is in the open position. d) Any attempt to withdraw the breaker in the closed position shall trip the breaker. e) Compartment door of a breaker shall not open unless the associated breaker is in open position. However, it shall be possible to defeat this interlock for inspection purposes. f) “Plugging in” a breaker is possible only if earthing isolator is open. g) Closing of earthing isolator is possible only when breaker is fully withdrawn. h) Scraping earthing contact shall be provided for effective earthing of breaker trolley. i) Pulling out of auxiliary circuit plug is not possible when breaker is in service position. j) Pushing in breaker to service position is not possible with auxiliary circuit plug not in position. k) Test to isolated position of circuit breaker can be achieved only when the control plug is removed. l) Isolated to test position of circuit breaker can be achieved only after inserting control plug. m) Automatic safety shutters shall be provided to completely cover the female Page 59 of 153 n) o) p) q) primary contacts, when breaker is withdrawn from service position. To padlock safety shutters and guide rails in the absence of the circuit breaker. To padlock Mechanical 'ON' push-button Access to the accessory of the circuit breaker (like Motor, Shunt etc) shall be prevented with the ACB in ON condition. However defeat interlock shall also be provided. Withdrawal portion of the circuit breaker shall be removable from the guide frame only when it is ensured that breakers is in OFF condition & the contacts are separated suitable for isolation. In the operating positions of the breaker, the circuit breaker shall be securely locked. It can be withdrawn or inserted only with appropriate operations of the interlocking levers. This operating lever shall facilitate to overcome the contact pressure of the main disconnecting contacts while pushing in or drawing out. All ACB‟s shall be with Safety Shutter, Door Interlock, castle-key interlock, Door Seali Sealing Frame. 8. Protection : The ACB shall be equipped with an integral self powered microprocessor based current release, which works on true R.M.S values for ensuring accurate protection. This release shall provide Overload, Short Circuit and Earth fault protection and shall be EMI/EMC compliant. The release should be modular in construction in terms of up-gradation or retrofitting of the vital components like LED scrolling display, rating plug & Ground fault, w/o removing the release from the circuit breakers. Display when added shall be able to visualize the parameters when observed while standing, even if the breaker is mounted at the ground level. Display shall be rotatable at 180° to the axis & angled 15° to the vertical axis. For communication capable feature, without upgrading the entire release, it shall be possible to add the communication module. The release shall necessarily support open bus system like IEC. Communication capable release shall signal the temperature inside the breakers & the temperature inside the panels. Release shall be provided with the rating plug to enable the circuit breaker to use at the lower currents without hanging the current transformer. Protection parameters under such scenario shall be proportional to the current detected by the rating plug. Release shall an option to provide the safety lock to prevent the resetting of the release. Standard release shall have the provision for remote diagnostic, configuration or protection parameters settings, maintenance management via ethernet or internet. Integral Test facility to test healthiness of release and the ACB shall be Page 60 of 153 provided on the over-current release. Test facility shall check the internal wiring & tripping solenoid of the circuit breaker. It shall be possible to conduct the test condition in ON condition with the option of trip. Trip indicators shall be provided to display the exact nature of fault (i.e. O/L, S/C, E/F) that caused tripping of circuit breakers by way of LED indication. The memory of cause of fault retention shall be minimum 48 hours. The circuit breaker shall necessarily be with mechanical re-closing lockout. Release shall also have the LED indication when Release is active, communication is active & Alarm. It shall be possible to change the release setting on load. 9. Setting range of protection release : 1. Overload protection Switchable from I²t to I4t characteristic for optimal adaptation to upstream fuses. Setting Range from IR = 0.4 to 1 In Time Lag Class tr setttable : 2 – 30 seconds Long time delay setting ( 6x IR) for I²t: tr = 2 - 30 s & I4t: tr = 1 - 5 s 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Short time delayed short circuit protection Isd shall be adjustable from 1.25 to 12 of the overload setting in 8 different steps & adjustable time setting for fault discrimination from 0.02 -0.1 - 0.2 -0.3- 0.4 sec. Short time delay shall be switchable ON /OFF & switchable from standard to I2t characteristics curve for optimal selectivity adaptation to downstream fuse. Instantaneous short circuit protection Ii shall have adjustable current setting from 150 % to 1200% of In or can be set equal to the Icu. Instantaneous protection shall have standard phase failure protections for motor protection with the delay time of 20 msec. Earth fault protection Ig if specified will have adjustable current setting as follows. Earth fault module shall be modular & should be retrofitable as required. Size I and II: OFF, 100A to 1200 A. Size III: OFF, 400A to 1200A and adjustable time setting from 100 - 500msec for trip / alarm.. Neutral protection shall be provided as standard protection in both 3 & 4 pole versions. Neutral setting shall be upto 100 % in 4 pole & 200% in 3pole ACB. Neutral protection shall have the time lag class same as phase. Page 61 of 153 II. Moulded Case Circuit Breakers (MCCBs): 1. Construction: MCCB shall conform to the latest IS specification IS – 13947 (2) MCCB shall comprise of a switching mechanism, arc extinguishing device and a trippi tripping unit in a compact moulded case and cover. The insulating case and cover shall be made of high strength, heat resistant and flame retardant thermo setting insulating materials. MCCBs shall be provided with Non-Welding silver alloy main contacts and arcing contacts with arc chutes. Arc extinguishing device shall be made out of a series of design plates mounted in parallel between insulating supports and shall be highly effective in positively drawing out the arc, confining it, dividing it and finally extinguishing the arc in less than 20 msecs. MCCB shall be 3 pole / 4 pole as indicated in drgs. In case of 4 pole MCCB, the 4th pole shall be 100% rated. MCCBs shall be provided with spring assisted, double break, quick make/break manually operated, trip free mechanism. The position of the handle shall clearly indicate “tripped, “ON” & “OFF” positions. It shall be possible to fit accessories on the MCCB such as aux contact, trip indication contact, rotary handle, under voltage coil or shunt trip coil, etc. MCCB shall be manually operated with Rotary Handle which shall have built-in door interlock, defeat & padlocking facility. The rotary handle shall be same as that for SDF or MPCB for better aesthetics. „ON‟ and „OFF‟ position of the operating handle of MCCB shall be displayed and the operating handle shall be mounted on the door of the compartment housing MCCB. All MCCB shall be suitable for remote tripping operation and the tripping device shall be suitable for the specified control supply voltage. If specified in the data sheet, the MCCBs shall be provided with solenoid/ Motorised closing mechanism to make them suitable for remote closing operation. The closing solenoid/ motor shall be suitable for specified control supply voltage. MCCB shall be provided with minimum 2 NO+ 2NC auxiliary contacts. 2. Electrical The MCCB shall be suitable for operating voltage of 415 V AC and insulation voltage of 690 V ac system voltage. Page 62 of 153 The MCCB shall be suitable for impulse withstand of 8 kV. The MCCB shall have short circuit breaking capacity Icu of 35 kA rms unless otherwise specified. The MCCB breaking capacity shall have Icu = 100% of Ics for the entire range. The MCCB shall have no derating upto 50 C service temperature. In case the MCCB needs derating, manufacturer shall declare the derated current carrying capacity at 50 C service temperature. The MCCB shall be current limiting type and shall have line-load inter changeability without any loss of capacity. The MCCBs above 100 A, shall have adjustable and properly calibrated overload and short circuit settings. 3.Trip Unit: The MCCBs upto 800A shall be provided with Thermo-magnetic tripping device. Incomer MCCBs shall be provided with microprocessor based release. MCCB shall provide inverse time current characteristics for overload protection, and should trip if any one phase is overloaded. And shall be provided with a device for instantaneous protection against short circuit. In case of Micro-processor based Release, the protections shall be as follows: L –Adj. Overload with inverse time characteristic = 0.4 to 1.0 In (rated current) S – Time Delayed Short Circuit ( Id = 1.5 to 10 Ir; td = 0 to 0.5sec) Ii - Inst S/C Current with instantaneous characteristics = 11In & 4) G - Ground fault protection. In case of Thermal Magnetic protection, following is required. L – Adj. Overload - 0.8 to 1.0 In Ii – Adj S/C protection – 5 to 10 In It shall be possible to change the trip unit from thermo-magnetic to microprocessor based and vice-versa. III. Miniature circuit breakers : MCB shall be heat resistant, molded type, conforming to IS8828/ IEC 60898 and rated for 240/415 V. MCB shall have a minimum breaking capacity of 10KA RMS symmetrical and shall be limiting class 3. MCB shall offer inverse-time over loads and instantaneous characteristics against short Page 63 of 153 circuit currents. The tripping characteristics shall either be C/D class. The tripping mechanism shall be trip free. MCB‟s shall be single, double, triple, four poles. It shall be possible to fit accessories such as aux contact, trip indication contact, shunt trip coil, etc. They Shall meet a degree of protection of minimum IP 20 and shall be clip on type din rail mountable. MCB shall have pad lock support, Biconnect upper & lower terminals, safety shutter on cable terminals. The incoming and outgoing of the MCBs shall be accessible only after opening. The ON and OFF positions shall be clearly marked. The MCBs shall be suitable for operating in ambient of 50 C without de-rating. MCB‟s shall be Quick make, quick break and with non welding silver alloy contacts suitable for manual and automatic operation. MCB‟s shall have Common operating handle and integral tripping for multiple MCB‟s. The 4 pole, 3 pole and 2 pole MCB knobs shall be trucked with adequately strengthened tandem pin. MCB‟s shall have Pressure clamp terminals for cables upto 4 mm sq. and bolted lugs for higher rating. It shall have a trip free mechanism ensuring that contact cannot be held closed against fault. Also, there shall be simultaneous isolation on all poles even if a fault is only a single pole. IV. Earth Leakage Circuit Breakers: Not Applicable V. Switch-Disconnector Fuse : All SDF‟s or switches shall be heavy duty/ motor duty, air break type suitable for load break duty with quick make/ brake manual operating mechanism conforming to IS – 13947 (3) and rated for 660 V AC system. The SDF shall be 3 pole with bolted type removable copper links of adequate size for neutral. In case required, facility shall be available to have switched neutral. The switch-disconnector fuse units shall operate on “QUAD break” mechanism and roller contact system for longer life. Continuous current rating of SDF‟s shall be atleast 15% higher than the full load current of motor/ feeder at the minimum operating voltage. Rating of duty switches for a particular starter module shall be as indicated in the switchboard data sheet. SDF‟s of motor starters shall have AC 23 rating corresponding to full load current of the Motor. Motor duty switches of smaller ratings meeting the requirements of AC 23 duty as per IS:13947, may be accepted in place of specified heavy duty switch rating for particular starter module only if, motor duty switches have been tested and Page 64 of 153 certified for use with the large size of fuse link specified in the switchboard data sheet for the same starter module. Also the AC 23 rating of the switches used shall not be less than the rating of the HRC fuses in the feeder. The switch fuse feeders shall be provided with SDF‟s of AC 22 utilization category. The operating handle shall be mounted on the front door of the compartment having the switch, with the position of the switch clearly indicated on the cubicle door. A user friendly handle coupling arrangement (conforming to IS 8623 – 1993) shall be provided with a self restorable door inter lock and padlocking facility for both ON & OFF positions. The cubicle door shall be interlocked with the switch mechanism so that the door cannot be opened unless the switch is in the OFF position. It shall, however, be possible to release this interlock if so desired for testing purposes. It shall be possible to fit accessories on the SDF such as aux contact, castle-key interlock, etc. In the event of an independent control circuit supply to the coils of the contactors, the main switch shall be provided with necessary auxiliary contacts to disconnect this control supply as well, when the switch is turned to OFF position for isolating the main supply. All live parts of the switch shall be shrouded with suitable insulating barriers so as to prevent accidental contact with the live parts after opening the cubicle front door. Wherever solid links are used for connections between switches and fuses, such links shall be fitted with insulating sleeves. VI. Fuses: Fuses shall be HRC cartridge link type with non -deteriorating characteristics and shall be rectangular in construction as per DIN standard. Screw type “DZ” or Diazed fuses and Rewirable fuses are not acceptable. The HRC fuse shall be of operating class gG with current limiting characteristics. HRC fuse shall be suitable for insulation voltage of 690V ac system voltage and conform to IS – 13703. The HRC fuse shall have breaking capacity of 120 kA. The HRC fuse shall have trip indication flag / pop. Page 65 of 153 Power Fuses shall be pressure fitted type and shall preferably have ribs on the contact blades to ensure good line contact. It shall be possible to handle fuses during off load conditions with full voltage available on the terminals. Wherever required fuse pullers shall be provided. The fuse base shall be so located in the modules to permit insertion of fuse pullers and removal of fuse links without removing any equipment or disconnecting any wiring. VII. Contactors : The contactors shall be air break type, equipped with three main contacts and minimum 2 NO +2NC auxiliary changeover contacts. Where the requirement of auxiliary contacts exceeds the limit of manufacturer‟s standard range, suitable auxiliary contactor with necessary number of contacts shall be provided alongwith the main contactor. Auxiliary contact rating shall be 6A for 240 V.A.C. and 1.5A for 110 V.D.C. The main contacts shall have AC3 ratings . Unless specified otherwise, the coil of the contactor shall be suitable for operation on 240V,1 PH, AC supply and shall work satisfactorily between 65 to 110% of rated value. Auxiliary contactors shall generally be used for interlocking and multiplying contacts. VIII. Thermal Overload Relay : Bimetal relays shall be provided for protecting the motor from thermal overload. Bimetal relays shall be positive acting, ambient temperature compensated type with adjustable setting range. Bimetal relays shall have built-in-single phasing prevention feature, which operate even with 50% rated current at the time of single phasing. Heavy duty starters shall be provided with different tripping class Overload relays, which shall be suitable for motor starting time of 15-60 seconds. Saturable type current transformer operated overload relays are not acceptable. Bimetal overload relays shall be separately mounted type with connecting links rated for the maximum rating of the contactor in a starter module. Bimetal relays shall be manually reset type with the reset push button brought out on the front of the panel. The reset push button shall be capable of being operated without opening the compartment door. Bimetal overload relays of various current ranges required for motors likely to be connected to a contactor must be identical in dimension for interchangeability. In case offered relays are with different dimension for any particular starter module, special mounting plate suitable for mounting different relays shall be provided in all the modules of that size. Overload relay shall be provided with potential free 2 NO + 2 NC changeover auxiliary contacts. Page 66 of 153 Stop push button of the starter and hand reset device shall be separate from each other. IX. Current Transformers : Current transformers shall generally confirm to IS:2075 and rated for operation on 415V 50 Hz system. CT‟s shall be made of class F wound type with the secondary terminals housed in a terminal box and marked indelibly. Also polarity shall be marked. CT‟s shall be mounted on the switchgear stationary part / Bus-Bar either in incoming side or outgoing side of circuit breaker as specified. The CT ratio and ratings shall be as indicated in the switchboard data sheet. However, vendor shall ensure that VA output and ALF of the CTs are adequate for the relays and meters connected on its secondary terminals. Current transformers shall have sufficient capacity to operate with the burden imposed by the devices shown on drawings within their accuracy classification. For general guidance, the protective current transformers shall have an accuracy class “5P”, and an accuracy limit factor of 20. Low reactance C.Ts shall be used for protection. Current transformers for instruments shall have an accuracy class 1.0 or 0.5 as per requirement and instrument security factor less than 5.0. However, accuracy class of 3.0 is acceptable for CT‟s meant for remote ammeters. If a metering load is fed from a protection C.T, suitable 1/1 or 5/5 ratio saturably interposing C.Ts shall be used. However, CT‟s for restricted earth fault and differential protection shall be of class “PS”. And CT‟s shall have a minimum ratings of 10VA. Separate cores shall be used for metering through analogue meters / load managers. When metering is done through relays, protection core shall have additionally the metering class accuracy built into. CT‟s shall be capable of withstanding dynamic and thermal stresses originated by short circuit fault current for three second. If specified separate CT‟s are provided for metering for electricity boards, then provision shall be made for sealing this CT. Unless otherwise required for proper relaying, one side of current transformer secondary shall be grounded in the compartment with the meters or relays which they serve and each current transformer group shall be grounded with a separate identified lead which may be disconnected for testing. The neutral side of CT shall normally be earthed through a link. Page 67 of 153 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 1. 2. 3. X. Potential Tranformers: The PT‟s wherever specified shall be epoxy class F cast resin type with the secondary terminals housed in a terminal box and marked indelibly. The burden and ratio and class of accuracy shall be as given in the specific requirements. However, voltage transformers shall have sufficient capacity to operate with the burden imposed by the devices shown on the drawing with their accuracy classification. The voltage transformers shall have an accuracy class 1.0 or 0.5 from 10% to 120% of normal voltage. The primary rated voltage shall be equal to the rated voltage Vn of the system or if the voltage transformers is connected between phase and neutral then shall be rated to VN/ 3. If not otherwise specified, secondary voltage shall be 110 V or 110/ 3V. For directional relays either a 3-phase 5 limb V.T or three single phase V.Ts with tertiary windings shall be provided. All PT‟s shall be drawout type and it shall be possible to remove voltage transformer from the circuit breaker whenever required. For Incomer feeders PT may be of fixed type since the same are connected on the incoming cable side. The draw out mechanism shall disconnect the busbars and the V.T, and primary and secondary terminals shall be earthed. The primary connection shall be disconnected before V.T or its primary fuses become accessible. Automatic shutter shall be provided to shroud the busbar when PT is withdrawn. Connections between the busbars and PT shall be completely shrouded. HRC fuse protection shall be provided on primary side. Miniature circuit breakers with auxiliary contacts will be preferred on the secondary side. Plug in type test terminal blocks should be provided for each PT circuit. Unless otherwise specified for proper relaying one side of potential transformer secondary shall be grounded at the transformer and the ground connection shall be identified and removable for testing. XI. Indicating And Metering Instruments: Instruments shall be provided as specified in Data Sheet/SLD. All auxiliary equipment such as shunts, transducers C.Ts, V.Ts that are required shall be included in the supply of switchboard. All indicating instruments and meters shall be capable of carrying continuously their full load currents and full voltage across their pressure coils. They shall not be Page 68 of 153 damaged by the passes of fault currents or the existence of over pressure on the primary side of their instrument transformers, for the maximum permitted duration of fault conditions which may occur during normal operation. 4. 5. 6. 7. 8. 9. 1. Make of all indicating instruments shall be as specified and shall be square pattern moving iron of 96/144mm size having 90 Deg scale suitable for flush mounting. All instruments and meters shall be back connected. Meters shall be provided with zero adjusting device for external operation. 1. Ammeters, Voltmeters, Power Meters : 2. 3. 4. 5. 6. 7. 8. 9. 10. These shall be of moving iron type with accuracy class of 1.0 as per IS:1248. The range shall be as indicated in Data Sheet/SLD. Ammeter for motors shall have nonlinear suppressed scale to read starting current. The motor full load current reading shall be at one-third scale. For other feeders full load current reading shall be at centre of scale. Voltmeter shall be suitable for direct line connection. K.W, KWH, KVARH meter shall be suitable to measure unbalanced loads on a 3phase 4-wire system with minimum accuracy class of 2.5 Power meters shall be of registering type and shall be flush mounted type. They shall be provided with test terminal blocks. 2. Load Managers : 1. 2. 3. 4. 5. It shall be suitable for operation on 50 Hz, 3-phase 4-wire system with Accuracy Class1.0 or 0.5. , PT- ** kV/ 3 //110/ 3, CTR- as per requirement. It should be flush mounted, preferably in a drawout case. Features : kW, kVA, kVAR, kWH, kVAH, kVARH (lag), kVARH (lead), MD kW, MD kVA, PF, Freq., V rms, I rms and with RS-232/ 485 port (import export). 3. Frequency Meters : These shall be digital type square pattern 144 mm x 144 mm size suitable for flush mounting and shall operated off a V.T secondary voltage of 110 volts. The standard range shall be 45-50-55 Hz. 4. Power Factor Meters : The power factor meter shall also be square pattern 144 mm x 144 mm size suitable for flush mounting. The meter shall operate off 110 volts secondary voltage. The C.T secondary current shall be as shown on the relevant drawing. The standard range shall Page 69 of 153 be 0.5-1.0-0.5. XII. Relays : A marking strip shall be provided in front of each terminal block and a diagram plate at the back of each case to identify connection. All relays shall be mounted in front of the panel in instrument chamber. The current and voltage coils shall be rated as specified on the relevant approved schematic drawings. Relay covers shall be of non-ignitable materials and anti fungus treatment shall be provided for all relays. Relay contacts shall withstand repeated operation and shall make or break the maximum currents in their circuits without deterioration. All spare contacts shall also be wired up to the external terminals. Relay coils (in case of electromechanical relays)/ circuits (in case of numerical relays) shall carry their normal currents indefinitely and such currents as can occur under fault conditions. Relay mechanisms shall not be affected by vibration or magnetic fields, which may occur in normal operation. Relays on which the function of a contact may be changed from „NO‟ to „NC‟ and vise-versa by simply changing the contact arrangement / by software selection are preferred. Relay contacts shall be self / hand reset type as indicated in attachment-II. All relays shall have built in flags/ indications to indicate relay operation. It shall be possible to reset the flags without opening the relays case. 1. Auxiliary relays/contactors : Auxiliary relays/contactors shall generally be used for interlocking and multiplying contacts. Auxiliary contacts shall be capable of carrying the maximum current. In any case their rating must not be less than 5A for 240 V a.c at a power factor between 0.3 and 1, and 2 A for 110 V.d.c (inductive load). All auxiliary relays shall be supplied in non-drawout cases. 2. Tripping Relays : All tripping relays shall be lockout type with hand reset contacts and shall be suitable to operate on the specified d.c voltage. These relays shall have self-coil cut-off contacts and shall be provided with hand reset operation indicators. Indicators shall be capable of being reset without opening the relay case. Tripping relays will be acceptable in non-drawout cases. The number of contacts shall be as shown on the approved schematic drawings. Master tripping relay ( lock-out relays ) shall be of the hand reset type and shall have at least 2 „NO‟ + 2 „NC‟ spare contacts, in addition to those required by the protection and tripping scheme. 3. Protective Relays : Page 70 of 153 All protective relays as mentioned in the data sheet shall be numerical type, communicable on IEC open protocol, back connected, drawout/ non-drawout type, suitable for flush mounting and fitted with dust tight covers. Trip circuits shall be automatically broken and current transformer secondary circuits shorted, when a drawout type relay is withdrawn from its case. All protective relays shall be with built in test facility. The protective relay cases shall have provision for insertion of test plug at the front for “testing and calibration” purposes. It shall be possible to test the relays without disconnecting the wiring and without withdrawing the relays. The insertion of the test plug shall automatically short circuit the CTS and permit extension of external power supply to the relay. The plug-in type of relays will not be acceptable. Each protective relays shall be provided with minimum 2 nos. potential free contacts of required configuration. Each tripping relay shall be lockout type with hand reset/ self rest coil cut-of contact. The tripping relay shall be suitable for satisfactory operation from 50% to 110% of the specified control supply voltage. XIII. Auxiliary equipments: 1. Indicating Lamps : Indicating lamps shall be provided on each panel as specified below; Breaker ON Breaker OFF Breaker Auto Trip Trip Ckt Healthy - Red Lamp Green Lamp Amber Lamp White Lamp DC Fail - Blue Lamp The indicating lamps shall be Cluster LED type having low wattage, long life and shall be suitable for the voltage indicated on the specific requirements. The lamps shall be easily replaceable from front. Lamps shall be supplied complete with the necessary current limiting resistor duly tested for its rating. Lamps shall be provided with translucent and heat resistant lamp covers to diffuse light. 2. Push Buttons : Push buttons shall be rated for continuous current rating of 10A at 240V a.c., 0.25 pf or 2A at 110 V d.c (inductive load). Push buttons elements shall be spring return type. Stop push button shall be of stayput type. Page 71 of 153 All push buttons shall have 2 NO + 2 NC momentary contacts. Push buttons colours shall be as follows : Stop/Open/Emergency - Red Start/Close - Green Trip circuit “Healthy” - Black Reset/Test - Yellow/ White Red push buttons shall be on the left side and green push buttons on the right side. 3. Control and Selector Switches : All control switches shall be rotary, back connected type having a cam-operated contact mechanism with phosphor bronze contacts. Unless otherwise stated, all Circuit Breaker Control Switch shall be Trip – NeutralClose Switch with spring return to neutral from both ON and OFF positions and lockable in neutral position. The switch shall be provided with pistol grip type handle. They shall be arranged to close the breaker by being turned clockwise. The trip, neutral and close positions shall be clearly indicated. The movement shall be such that the switch cannot be operated inadvertently and that it is mechanically interlocked to trip before close. The operating switch shall be located on the centerline at about 1.5 meters from the floor level. Number of ways, locking system, lost motion device etc., if required shall be shown on the relevant schematic drawings. Two spare ways shall be provided on these switches. All selector switches shall be provided with knob type handle. Ammeter selector switches shall have make before break feature on its contacts. The selector switch shall generally have 4 positions for reading 3 phase currents and fourth position for OFF. Voltmeter selector switch shall have 4 positions. Three shall be used to measure phase to phase voltage and fourth shall be OFF position. Remote/ Trip/ off selector switch for the motor feeders shall be lockable in OFF position. imer : 4. Timer: For re-acceleration duty, timers unless otherwise stated, shall be electronic type and shall have stepless continuously adjustable time setting of 0-60 secs. The time settings, where specified, shall be accurately set before dispatch of the switchboard. Page 72 of 153 Timers for auto-transfer schemes shall be of static type with timing ranges suitable for the scheme employed. The contacts shall be rated for 6A for 240 V.A.C. D. Construction: I. General:The switchboards shall be totally metal enclosed, compartmentalized, modular type, fully draw out, free standing, floor mounting, suitable for indoor installation. However, the incomer and bus tie feeders with load break switches, control supply transformer modules, DB‟s, ASB‟s wherever specified in attachment-II may be in fixed execution. The switchboard shall be assembled out of standard prefabricated sheet steel units/ standard vertical sections of uniform height, joined together to form a rigid, free standing, completely enclosed composite board of continuous line up to uniform height, depth & especially front line-up. Each vertical section shall comprise the following compartments. A metal enclosed horizontal main bus bar compartment running horizontally at top. A metal enclosed busbar compartment running vertically (at rear or in center of the section) along the height of the section and housing the vertical bus bars serving all feeder modules in this section. A metal enclosed horizontal auxiliary bus bar compartment running horizontally at top for control, interlock, and indication and metering wiring. Individual with-drawable feeder modules in multitier mode. Cable termination compartment. The switchboards shall conform to constructional requirements as per IS 13947. Each unit of the switchgear shall have necessary internal sheet metal barrier to form separate compartments for bus bars, instruments & relays, feeders and cable connection etc. Each compartment shall be constructed and designed, to confine the damage caused by an internal fault to that compartment. To achieve this compartment segregation and /or suitable arc propagation barrier shall be provided. Independent pressure release valves shall preferably be provided if required for different compartments. The switchboard shall be dust & vermin proof with enclosure protection not less that IP52 as per IS- 2147 except for bus bar compartment. An equivalent degree of protection as per any relevant international standard shall also be accepted. If necessary, openings for natural ventilation shall be provided. These shall be Page 73 of 153 louvered with GI wire mesh. Wire mesh for bus bar compartment shall be such as to protect against objects of 1 mm and above. Metal sheets shall be provided between two adjacent vertical panels running upto full useful height of the switchboard. The switchboard shall be fabricated using suitable mild steel structural sections or using pressed and shaped cold rolled sheet steel of adequate thickness. The sheet steel used for panel shall be of minimum 2mm for load bearing members, 1.6mm for non- load bearing members. The thickness of base channel shall be minimum 3mm. Wherever required, stiffeners shall be provided to increase stiffness of large size doors and covers. Maximum height of the Board, including the height of the base channel, shall not be more that 2450mm The switchboard shall be provided with integral base frame for each vertical panel. The switchboard integral base frame shall be suitable for directly bolting with the help of foundation bolts and shall also be suitable for tack welding to the HPCL‟s floor embedded channels. Suitable removable type lifting hooks and/ or jacking pads shall be provided on each panel or shipping section for ease of lifting of switchboard. On removing the eye-bolts no holes offering access to panel shall be permitted. All hardware shall be corrosion resistant. All joints, and connections of the panel members shall be made by zinc passivated high quality steel bolts, nuts and washers, secured against loosening. Star washers shall be used to ensure effective continuity. It shall be possible to extend the switchgear in either direction for future expansions. Ends of bus bars shall be suitably drilled for this purpose. Panels at extreme ends shall have openings, which shall be covered with plates screwed to the panel. Details of drilled holes in bus bar and openings in panels provided for future extension shall be clearly shown in drawings. The switchboard shall have adequate strength to withstand all stress likely to be encountered in the event of an electrical fault, shipping, handling, installation, and operation, without distortion or damage. The switchboard shall be constructed in shipping sections of one vertical panel. The switchboard shall be as completely assembled as possible within shipping and handling limitations, wired and ready for installation in accordance with this specifications. All metering and protection equipment associated with a particular circuit shall be housed in separate and independent compartment earmarked for that particular circuit Page 74 of 153 and in the fixed portion of the vertical panel in case of breaker panels. Access to all operating devices shall be from the front of the switchboard. All auxiliary devices for control, indication, measurement and protection such as push buttons, control and selector switches, indicating lamps, Ammeters, Voltmeters, KWH meters and protective relays shall be mounted on the front side of the respective compartments only. However, mounting of some of these devices on the trolley may be accepted provided necessary blanking plates are provided to cover the opening left in the panel door when trolley is withdrawn out of panel. The design shall be such that unless required for maintenance/ inspection purposes, all power on/off or start/stop and relay reset operations shall be performed without opening the panel door. All barriers shall be of fire retardant, non-inflammable & non hygroscopic materials such as FRBP/FR-2 only. Hylam is not acceptable. All openings, covers and doors shall be provided with double lip neoprene Gaskets. All doors shall be of lift – off type with pad locking facility. Doors should not be an integral part of the drawout module. Panels shall be suitable for bottom entry of cables unless otherwise specified. All modules shall have cable termination facility in cable alley without duplicated terminals and it should be possible to terminate / disconnect cables without removing the modules. II. PCC/PMCC/MCC/MOVDB/MLDB/CPDB PANELS : PCC/ MCC shall be of single/double front execution. The design of feeder trolleys shall not change for single front or double front execution. Separate vertical bus bars shall be provided for each front. Identical feeder modules in both the fronts shall be interchangeable. The outgoing feeder trolleys shall be fully drawout and shall be with-drawable without having to unbolt or unscrew any power and control connection to the equipment mounted on the drawout trolley. Both power and control connection shall be drawout type. The trolley shall be withdraw-able by means of crank and screw arrangement or any alternate mechanism like guided rollers etc. Plug in operation shall be independent of manual force. For drawout type feeders of size equal to or greater than half the useful height of panel, positive clamping arrangement shall be provided on the top portion of the trolley in additional to clamping arrangement at the bottom, to ensure all round positive pressure on the power drawout contacts once the trolley is plugged in. Page 75 of 153 Power drawout contacts shall preferably be located towards the bottom portion of each trolley. The trolley shall be lockable in fully plugged in position and devices shall be provided to ensure positive plugging in. In test position, power contacts shall be totally isolated and a device shall be provided for indication of test postion. Various compartment sizes in a vertical MCC panel shall be multiples of a basic dimension. However, the minimum module size shall be 200mm for switch fuse feeder and 240mm for contactor feeders. Vertical bus bars shall be pre-drilled at regular intervals (wherever necessary as per design requirement) for complete flexibility for changes in sizes of modules. The maximum height of the operating handle/ switches shall not exceed 1900mm and the minimum height not below 300 mm. Unused modules in the panel shall be fully equipped with hinged door, power and control terminals for starter modules and cradle for future use. All switch drives other than rotary switches, shall be lockable in both „ON‟ and „OFF‟ positions. The switches/ moulded case circuit breakers shall be interlocked with the compartment door to prevent opening of the door when the switch/moulded case circuit breaker is in „ON‟ position and to prevent switching on when the door is open. A defeat mechanism for this interlock shall also be provided. Each MCC panel shall have a separate cable alley. The width of this cable alley shall be sufficient to accommodate all the cables and shall have free access for cable terminations and in any case shall not be less than 200mm. Cable alleys shall be provided with suitable doors. Sheet steel barriers shall be provided between individual compartments and cable alley. This barrier shall be provided to safely carryout maintenance work on cable connections to any one circuit in the cable alley with the busbars and the adjacent circuits live. III. CIRCUIT BREAKERS PANELS : Circuit breaker panels shall be single front execution only with distinct bus bar, breaker and cable compartments. The design of each compartment shall be such as to prevent movement of vermin from a particular circuit breaker compartment to any other portion of the panel when the breaker is withdrawn and compartment door is closed. In order to minimize accidental access and avoid accidents due to falling tools, all the outgoing links shall be shrouded. Blanking plates shall be provided for circuit breaker compartments, which would be used after installation to cover the opening in the event of withdrawing the breaker outside the compartment. Outgoing ACB‟s can be mounted in a maximum of two tier execution while the incoming/ bus coupler ACB‟s shall be single tier execution only. The metering and Page 76 of 153 protection equipments associated with a particular breaker shall preferably be mounted on the same panel front. Access to all operating devices shall be from the front of the switchboard. 1. Circuit Breaker Compartment The circuit breaker compartment shall be fully drawout, that is, bus side and outgoing power and control connections shall be made through drawout contacts. Suitable guides shall be provided to facilitate easy withdrawal of the circuit breaker. All incidental feeder compartments shall be interchangeable. There shall be three positions for the drawout trolley viz : “Full in” or “Service” position –In this position both power and control circuits shall be connected. This shall be the normal operating position of the circuit breaker. “Test” position- The power contacts shall be disconnected in this position but the control connections shall not be disturbed, it shall be possible to close and trip the breakers in this position. “Full out” Position- both power and control circuits shall be disconnected in this position and breaker removed from the cubicle. The circuit breaker shall be lockable in “service” and “test” positions. Safety shutters shall be provided when the breakers is in withdrawn/drawout position. The earth connection must remain connected in “Test” position. Earthing of the unit shall be done with a “pin” or with scrapping earth connections. The earth connection shall make before the main power/ control contacts make and break after the power/ control contacts are disconnected. Earthing connection through a plug and socket connection shall not be acceptable. Any unused circuit breaker compartment shall be fully equipped and provided with compartment door, vertical busbars and control terminals/wiring etc. such that the same could be used for housing outgoing breakers in future without any modifications to the panel. The current transformers shall be mounted on the fixed portion of the compartment. However, current transformers associated with built-in-releases may be mounted on the breaker trolley. All terminals except wiping/ sliding type control terminals shall be shrouded with plastic covers to prevent accidental contact. For direct termination- Clip on shrouded type terminals shall be provided. Breaker shall not be mounted directly under the busbars. Preferably a barrier of suitable material shall be provided between the arcing device and the busbars. Special care shall be taken to cool the ionised air. Page 77 of 153 2. Separate Cubicle Compartment Separate compartment totally enclosed from all sides shall be provided for cable termination, on the rear side. Access to cables shall be from the rear side after opening the cabling compartment door. The incoming/ outgoing cable termination shall be staggered for each circuit and barriers of sheet steel or insulating material shall be provided between termination of two circuits such that maintenance on one circuit could be carried out while the other circuit is live. Suitable clamping arrangement shall be provided for cables and cable termination. Termination blocks shall not be used for supporting the cables. Provision shall be made for terminating each outgoing cable with a separate bolted connection. Number of cables per termination shall be minimum two numbers unless otherwise specified. In case the total number of cables entering a particular panel can not be accommodated in the cabling compartment an extension panel shall be added to the cabling compartment for accommodating extra cables. The enclosure design of cabling compartment shall be such as to prevent the movement of vermin from this compartment to any other part of the switchboard. The incoming and outgoing cables shall have bottom entry unless otherwise specified. IV. Auxiliary service Boards: (N.A.) V. Accessibility/ Safety/Interchangeability : Checking and removal of components shall be possible without disturbing adjacent equipment. All equipments shall be easily accessible and it shall be possible to set all measuring relays independently without de-energising the switchboard. In the TEST position it shall be possible to replace the fuses, contactor coils, inspect switch, contactor operation etc. It should be possible to selectively program the control terminals for SERVICE or TEST application and bypass / include field inter locks suitably. It should be possible to program at least 30% of control terminals. Adequate barriers shall permit personnel to work safely within an empty compartment with the bus bars energised. Compartment for cable connection shall allow cable pulling; termination and connection work with the subject cubicle only being de-energized. Unused CT secondary terminals must be short-circuited. All terminals shall be shrouded with plastic covers to prevent accidental contact. Page 78 of 153 Front/ rear access shall be available to all components in each cubicle, which requires adjustment, maintenance or replacement, except in case of double front panels. Rear access shall be available to all cable boxes of circuit breaker vertical section. Rear side of these cable chambers shall be provided with additional removable expanded wire guards/mesh with voltage danger notice board, to allow visual inspection of busbars/CT and cable terminations and avoid accidental touch when rear cover is removed. Terminal strips for outgoing control cables connection should be accessible to facilitate working and testing with breaker in test/service condition and while the switchboard is energised. Both the vertical and horizontal bus bars shall be provided with anti-tracking barriers as an integral part of bus bar zone. In the cabling chamber shrouds shall be provided on the side of vertical bus bars. The switchboard shall be designed to ensure maximum safety during operation, inspection, connection of cables, relocation of outgoing circuits and maintenance, with the busbar system energized and without taking any special precautions. Means shall be provided to prevent shorting of power and/or control terminals due to accidental dropping of maintenance tools etc. inside switchboard. Blanking plates shall be provided for all sizes of modules to cover the openings in the event of withdrawing the feeder modules. All identical equipment and corresponding parts shall be fully interchangeable without any need for resorting to structural modification. As a safety feature spring loaded safety shutters shall be provided for shrouding the main incomer contact after the feeder / ACB module is with-drawn to ISOLATED position in switchboards. VI. DRAWOUT CONTACTS All power contacts(both on busbar side and cable side) shall be fully drawout, self aligning, plug-in design which get automatically disconnected when the drawout module is withdrawn from the service position. Removable type male and female contacts shall be provided. The main power contacts shall be spring loaded type for maintaining constant pressure. The drawout contacts shall be only between copper / copper alloy / aluminium faces all of which are silver plated. Page 79 of 153 Control circuit contact shall have a minimum 15A AC / DC continuous rating rated. Power Circuit contact rating shall be as per the continuous current in attachment-II and shall be the in-panel rating. VII. Busbars: The main and vertical busbars (droppers) shall be a TPN system suitable for 415V, 3 phase, 4W, 50Hz system. The main and vertical busbars shall be housed in separate fully enclosed chambers to prevent direct contact with the buses energised when switchboard is under operation. All phase and neutral bars shall be housed in a common chamber. The main bus bars feeding the switchboard shall comprise of 3 phase & neutral bus-bars extending horizontally at the top through all units of the switchgear line up. Interconnection between the main bus bars and individual units shall be made by using vertical bus bars of adequate rating. These interconnections and the vertical bus bars shall be compartmentalized, and fully shrouded using sheet metal. The supply of neutral shall be through a neutral busbar and stab-in contact in all units wherever required. External looping through a separate contact is not permitted. Auxiliary Bus Bars: Auxiliary bus bars each of minimum size 28 sq.mm copper shall be provided for following applications. Exact number of bus bars shall depend on various control, metering and auxiliary power distribution requirements specified in material requisition. 240 A.C. control supply for space heater for Panel and motor. Control supply for breaker tripping, closing and indication circuits. Control supply for breaker spring charging motors, motor starter control and indication circuit. AC potential supply for KWH meters. For distribution of power from bus to individual feeder modules, the vertical bus bars shall branch off from the main bus. Two entirely different sets of vertical busbars for front and back portion shall be provided for double front panel. Tee-off connectors shall be used for distributing auxiliary supply to each vertical panel. Main horizontal busbars and auxiliary buses shall be of uniform cross-section throughout the length. Similarly, vertical busbars shall be of uniform cross-section throughout the height of the switchboard. Tapered busbar arrangements are not acceptable. Page 80 of 153 The in-panel current carrying capacity of main phase bus bars shall be 20 % more than incomer breaker rating. The in-panel current rating of the neutral busbars shall be half/full that of the respective phase busbar. The in-panel current carrying capacity of the vertical phase bus bars shall be 20 % more than the connected load to be catered in each vertical panel. However, size of vertical busbars shall not be less than 50x 10mm Aluminium per phase. Minimum size of bus bars for starter/ feeder power connections above 100 Amp rating shall be 20 x 6 mm Aluminium/equivalent CU. Minimum size of bus bars for control bus bars shall be 25 x 3 mm Aluminium/equivalent CU. Current density of copper busbar shall not be more than 1000 A/sq. in. Thermal design of the busbars shall be based on installation of the switchgear in poorly ventilated conditions. The cooling air volume shall take into account only the bus enclosure. The maximum operating temperature of busbars at max. design temperature shall not exceed the final end temperature (hot spot temperature including the joints) 95 deg C under normal operating conditions and 200 deg C for short circuit conditions. And the same shall be capable to withstand the full fault level without any deformation. The current rating referred in the data sheets are for design ambient temperature at site conditions and for being inside the cubicle at fully loaded condition ie. In-panel rating. The vendor shall suitably derate the nominal rating to suit the above condition. Successful vendor shall furnish the calculations for busbar sizing. All joints surfaces at aluminium to copper joints shall be silver/ tin plated, alternatively cup-al washers (bimetallic washers) may be used. Busbars shall be of high conductivity electrolytic aluminium (E91E)/ copper . Independent insulating supports for each phase busbar (vertical as well as horizontal) shall be provided. Busbars shall be supported on insulators made of nonhygroscopic, non-inflammable, non-carbonizing material (like SMC,DMC epoxy bonded fiberglass) resistant to acids and alkalis and shall have non-hygroscopic characteristics with tracking index equal to or greater than 800 as per IEC 112. Supports shall be adequately sized and braced to withstand the electrodynamic forces developed during specified short circuit level without permanent deformation. Successful vendor shall submit calculation for withstand capacity of busbar supports. Both horizontal and vertical bus bars, bus joints and supports shall dynamically brazed, thermally sized for being capable of withstanding dynamic and thermal stresses Page 81 of 153 of the specified short circuit currents for 3 second. The short circuit capacity of the neutral bus bars shall be in line with IS : 13947. Dynamic stresses shall be calculated on the basis of the specified peak short circuit currents. All bus bars shall be insulated with heat shrunk PVC sleeves of 1100V grade. Red, yellow and blue colour shall be used for phase bus bars and black colour shall be used for neutral bus bars. The sleeves used shall be capable of withstanding the temperatures attained by busbars during normal operation and short circuits. Joints shall be shrouded suitably. Only zinc passivated high tensile strength steel bolts, nuts and washers shall be used for all bus bar joints and supports. Removable neutral links shall be provided on feeders to permit isolation of the neutral busbar. The support design shall be such that creepage distance between phases shall be higher than those specified in IS-4237. Necessary anti tracking barriers shall be built-in in the design of the support. The clearance shall be at least 35 mm between phases and phase to earth in the main busbar zone and 28 mm in vertical busbar (droppers) zone. However clearances at components shall be as per individual standards. Both main and vertical busbars shall be housed in a separate metallic chamber segregated from rest of the panel and shall be accessible for inspection with special tools only. Rubber grommets shall be used for all wire entries to make the entries dust and vermin proof. Isolating links/ fish plates shall be provided between two auxiliary bus sections. The connection between the busbars and the terminals of the circuit breakers shall be suitably shrouded. VIII. Cubicle Module Accessories And Wiring :Switchboard shall be supplied completely wired internally to equipments and terminal blocks and ready for external cable connections at the terminal blocks. The vendor shall carry out all control wiring within a cubicle and also inter-cubicle wiring between cubicles of same switchgear. Interpanel wiring within each shipping section shall also be vendor‟s responsibility. For wiring between shipping sections, vendor shall provide terminal blocks on adjoining shipping sections and supply suitable jumper wires duly ferruled and numbered for respective panel termination. Interconnection schedule for wiring carried out between shipping sections shall be provided by vendor. Page 82 of 153 Wiring shall run in enclosed plastic channel and shall leave at least 25% spare space for future use. The interpanel wiring shall be taken through PVC sleeves or suitable grommets and protected by beadings. Neatly bunched flexible stranded copper conductor wires shall be used for connection between moving parts. The same shall be soldered at the ends before connections are made. All control signaling, power, protection and metering wiring shall be by BIS approved PVC insulated, 1100 V grade, copper stranded conductor wires of minimum 1.5 sqmm section provided the control fuse rating is 10 amps or less. For 16 amps control fuse circuit 2.5 sqmm copper conductor shall be used.. For CT secondary circuit, copper stranded conductor wires of minimum 2.5 sqmm shall be used. Minimum size of power wiring shall be 4 sq.m. copper. Each wire shall be terminated on a separate terminal. Terminal strips for connecting incoming control cables shall be Elmex/ Technoplast/Wago make plug in type of adequate size and shall be located conveniently and separated by barriers from power circuits for easy accessibility and ease of connection without danger of contact with live part. Sufficient terminals shall be provided on each terminal strip to ensure that not more than one outgoing wire is connected per terminal. And at least 20% spare terminals shall be provided in each terminal strip. Wires shall not be joined or tied between terminal points. Rubber grommets shall be provided at all such locations, so that metal parts should not come in contact with any control wire/cables. All spare contacts of equipments including ACB, relays, contractors shall be terminated to terminal block. Conductors shall be terminated with adequately sized compression type lugs for connection to equipment terminal and strips. And proper PVC sleeving shall be provided at each termination. Stranded conductors shall be soldered at the ends before lugging. All power terminals shall be of stud type. Clamp type terminal for direct conductor termination shall be acceptable for wires unto 10 sqmm size and bolted type terminals with crimping type copper lugs shall be provided for all outgoing cable connections larger than 10 sqmm. Each wire shall be identified at both the ends by, numbered ferrules provided at each end, all in accordance with the connection diagram. All ferrules shall be made of non-deteriorating materials and of yellow colour with black lettering.. The ferrules shall be firmly located on each wire so that they cannot move or turn freely on the wire. Page 83 of 153 All mounted equipment shall have tags of self-sticking PVC tapes at the rear. In addition, identification numbers shall be painted on the panel wall, to give permanent identification mark. Mounting of relays for a particular breaker panel shall be limited to that particular panel only. All auxiliary equipment terminals shall be made with pressure type terminals. All spare contacts of aux. relays, timers etc. shall be wired up to the terminals. C.T. terminal shall be with shorting and earthing facility. Phase identification for CT secondary wires shall be done using coloured PVC sleeves. Different voltage terminals, C.T. terminals, potential free terminals, power and control terminals shall be segregated. Duplication of a terminal block, wherever necessary shall be achieved by solid bonding link. Control cables entry shall be from the bottom. It shall be possible to have the control cable entry from both the left and right side corners at the front portion of the switchgear without cutting any standard part of the switchgear. Cable lugs and requisite cable glands for these cables are not included in the scope of supply of the switchboard. Supporting facilities shall be provided for clamping the control cables. All control cables shall be of 2.5 sq.mm ywy, construction. Multi pin plug provided should have scraping earth terminal. E. Control Supply : Breaker tripping and closing devices shall operate on 110 V DC/ 240AC unless otherwise specified in the data sheet. The exact detail will be finalized during detailed engg. The control power supply shall be arranged as follows. External 240V AC control supply shall be provided for auxiliary power and heater circuits to any one panel of the switchboard. Any other intermediate voltage required in the panel, shall be derived by vendor by providing suitable control transformer- resistor. Vendor to loop both these supply to all the panels in case of multibreaker panels forming one unit. Each panel shall also have control supply switch and HRC fuses or MCBs for isolation. Vendor shall provide suitable control switch and fuse at the point of receiving control supply. F. Inspection chamber: The instrument / control chamber shall incorporate the protection, control and indicating devices like indication lamps, switches, meters, relays etc. Page 84 of 153 This chamber shall be totally segregated from rest of the panel and shall be provided with a separate door which can be opened when circuit breaker is ON. Wherever equipments are mounted on the door, the wiring shall be with flexible wires. The wires shall be neatly bunched and clamped and shall be sufficiently long so that the door can be opened without causing unnecessary stress on the terminations at the instruments. G. Power Connection : The incoming and outgoing power connection shall be through XLPE / PVC, Aluminium/ Copper cables as indicated in the data sheet / drgs. The various cable sizes and number of cables shall be as indicated in the material requisition. The power cable shall enter the switchboard from the bottom bottom/top as specified. Cable glands, lugs and the requisite bushes for sealing power cable entries shall be excluded from the scope of supply of the switchboard. Provisions shall be made for terminating each outgoing cable with separate bolted connections. All terminals shall be properly sized for cable cores. “Cupal” washers shall essentially be used for copper to aluminium joints. The switchboard shall be supplied complete with supports for clamping outgoing and incoming cables. Terminal blocks shall not be used to support cables. Ample space and support arrangement shall be provided in the cubicles at the rear of the switchboard to accommodate these cables. The head room available between cable gland plate and terminal lug shall not be less than 750 mm for incomers and major outgoing feeders/motors. The cable sockets shall be at such angle that the cable tails may be brought up for termination with minimum bending and setting. In case cable termination cannot be accommodated inside the panel, a suitable box for mounting at bottom/rear of panel shall be supplied by vendor. Earth strip shall also be brought to this box. In lieu of this dummy panel can also be provided. Vertical cable alley covering the entire height with hinged door shall be provided for cable connection. The minimum width of cable alley shall be 300mm. Non-magnetic cable gland plates shall be provided for termination of single core cables. H. Earthing :The switchboard shall be constructed to ensure satisfactory electrical continuity Page 85 of 153 between all metal parts not intended to be alive and the earth terminals of the board. The earth bus shall be uniform & continuous and shall run the full extent of each board. The minimum earth bus size shall be 50x6 sq.mm copper and shall be of adequate cross-section to withstand the specified fault level with necessary termination arrangement at both ends. It shall be bolted to the frame-work of each unit. Double front M.C.C. shall have two nos. earth busbars, one for each front. A separate Cu vertical earth bar shall be provided in all sections for earthing of individual functional units. All cubicles shall be connected to this earth busbar. All doors and movable parts shall be earthed using flexible braided copper connections to the fixed frame of the switchboard. All with-drawable chassis shall be earthed through spring loaded silver plated copper scrapping earth contact which make-before & break-after the power contacts are engaged / disengaged. A suitable vertical earth bus shall be provided for each front of the panel for this purpose. The earth bus shall be easily accessible in each cable compartment either directly or through a branch extension to ground the cable armor and shields. In each of the vertical sections the earth bus bar shall be provided with minimum of two (over and above the no. of feeders in each vertical sections) earthing bolts of 10 mm dia with nuts to make termination of fourth core/ armor of cable. Mating surfaces of all bolted parts shall be specially zinc passivated to ensure continuity between them. Provision shall be made to connect the earthing busbar to the plant-earthing grid at two ends for which two nos. of earth terminals shall be provided on each switchboard, at the back near the floor. Positive earthing of circuit breaker truck/ frame shall be maintained when it is in the connected position and in all other positions whilst the auxiliary circuits are not totally disconnected. Earthing by mere touching of metal-to-metal is not considered to be satisfactory earthing. Hinged doors and movable parts shall be earthed through flexible copper earthing braid. All the non-conducting metal parts of the circuit breaker truck shall be bonded together and shall make perfect electrical connections to earth through substantial sliding contacts, at service and test positions. Such sliding contacts shall be arranged to make before power plug-in and interrupt after draw out. Page 86 of 153 All non-current carrying metallic parts of the mounted equipment shall be earthed. I. Space Heaters : The cubicles shall be provided with space heaters to prevent moisture condensation and maintain cubicle temperature 50C above the ambient. The space heaters with porcelain connectors shall be located at the bottom of each section of the switchboard, and shall be supplied from 240V AC aux. Bus for space heater and controlled through a double pole MCB and thermostat. The thermostat shall preferably be located in the metering/relay chamber. J. Name Plate : Nameplate shall be provided on each panel as per schematic drawings for each equipment (like switch, indicating lamp, meter, relay, auxiliary contactors, terminal strips and other devices) mounted on the switchboard for easy identification. Identification with stickers is not acceptable. Special warning labels shall be provided on manual switching of interlocked circuit breaker, earthing switches, PT panels, removable covers and doors giving access to live bus. Special warning label shall be provided inside the switchboard also, wherever considered necessary. Identification tags shall be provided inside the panels matching with those shown on the circuit diagram. A nameplate with the switchgear designation shall be put at the top of the central panel of the switchgear on both front and rear side. A separate feeder nameplates giving feeder details and panel number shall be provided at front as well as rear. The nameplates for feeder compartments shall be in two parts. One part shall have necessary details pertaining to the switchboards. The other parts shall be removable and shall contain all details regarding the drives/ equipment controlled by the particular module. Each cubicle shall be labelled in the front and rear of the cubicle. Caution/warning name plate labels stating live terminals/ busbars shall be provided on all removable covers or doors giving access to cables or busbars. K. Base-Frame: The panels shall be suitable to be installed on a base frame. Amply dimensioned oblong holes shall be provided on the bottom of all units for their assembly on the base frame, which in turn shall have threaded holes. In addition, the panels shall have an additional base channel at the bottom with smooth surface. The base frame shall be of IS Sections. Page 87 of 153 L. Painting : All metal surfaces shall be thoroughly cleaned, degreased, pickled and phosphatised to remove mill scale, rust, grease and dirt. The under surface shall be prepared using the seven tank process. And thereafter under surface shall be prepared by applying a coat of phosphate paint and a coat of yellow zinc chromate primer. The under surface shall be made free from all imperfections before undertaking the finishing coat. Fabricated structures shall be pickled and then rinsed to remove any trace of acid. After preparation of the under surface, all metal surfaces (both internal and external surfaces) shall be applied with two coats of epoxy based primer. Subsequently the work shall be powder coated with two coats of epoxy based final paint as per colour shade No. 631 of IS:5, unless otherwise specified. Final coat shall be of air-drying synthetic enamel paint. The finished panels shall be dried in stoving ovens in dust-free atmosphere. Panel finish shall be free from imperfections like pinholes, orange peels, runoff paint, etc. The final finish on the inside surface shall be glossy and the external surface should be semi-glossy. All unpainted parts shall be zinc passivated or suitably treated to prevent rust formation. If these parts are moving elements, then these shall be greased. Drawings : The manufacturer shall develop his own general arrangement and schematic drawing adding necessary auxiliary devices, accessories, components etc. peculiar to supplied equipment, which are required for safe, convenient, efficient and proper operation of the LT switchgear. The number of circuit breaker panels and equipment/accessories schedule for each breaker panel shall be as indicated in the material requisition given in the specific requirement of tender document. Manufacturer shall submit for HPCL‟s approval the single line diagrams, general arrangement drawings, flooring and mounting detail drawings and schematic diagrams. Approval of GA drawings is required before the fabrication of cubicles is started. Approval, of schematic drawings is required before the manufacturer proceeds with the cubicle wiring. The approval of HPCL of any of the manufacturers drawings shall not relieve the manufacturer of his responsibility for supplying equipment confirming with the relevant specifications and standards or for any mistakes, errors or omissions in manufacturers drawings. Once manufacturers schematic diagrams have been finally approved by HPCL, the Page 88 of 153 manufacturer shall prepare wiring connection diagrams for each cubicle. These diagrams shall show any wiring inside the cubicle starting from the cubicle terminal strips. These diagrams shall be used by owner for troubleshooting and shall show every device, terminal and wire number. Manufacturer shall submit the required number of prints and reproducible of schematic, GA and wiring diagrams and catalogues, routine/ type test certificates as detailed in our drawing data schedule given in the specific requirement of the tender document. The manufacturers drawings shall replace HPCL‟s preliminary drawings sent with the enquiry. TESTS AND INSPECTION : Inspection may be carried out at various stages of manufacture and also after the completion of manufacture. The final despatch clearance shall be given by Third Party Inspection agency appointed by vendor from the list of approved TPI agency. All expenses towards TPI shall be to vendor‟s account. The vendor shall submit QAP after placement of PO. During fabrication, switchgear may be subjected to tests by vendor as per HPCL directive and same shall be witnessed by the inspector. Manufacturer shall furnish all necessary information concerning the supply to such inspectors. Stage inspection after the pre-treatment and preparation of under surface and before final painting shall be carried out by HPCL, if specifically mentioned in tender document. During final inspection, all routine and acceptance tests shall be carried out at manufacturer‟s works under his care and expense. Inspection shall not relieve vendor of his responsibility of guarantee and other contractual responsibilities. The vendor shall intimate the readiness of panels for inspection to owner also and owner at their discretion may depute personnel to carryout inspection. Equipment shall be dispatched only after the issuing of release note by TPI agency. All routine and acceptance tests as specified by the applicable standard code shall be conducted on the switchboard as a whole. Routine and acceptance test may also be conducted on major components like relays, CT‟s, PT‟s etc, at respective manufacturers works. In lieu, test certificates from respective manufacturers shall be submitted during inspection and may also be acceptable. HPCL‟s decision will be final on the matter. In addition, acceptance test as detailed below shall be conducted to check mechanical and electrical operation and switchboard wiring to the specification and approved schematic drawings. These tests shall be provisionally conducted at manufacture‟s works by providing temporary connection to switchgear units in order to simulate the actual conditions. Tests shall be finally performed at site, in presence of the Page 89 of 153 manufacturer‟s specialist, once the external cable connections have been completed. Acceptance tests but not limited to the following shall be conducted by TPI, final QAP shall be approved by owner and the testing & witness by TPI will be guided as per the approved QAP ; a) A general visual check, dimension measurement and bill of material check. b) Manual and electrical operation of CB, relays, circuit functioning shall be checked under the worst conditions of auxiliary supply voltage. c) Dry insulation test with power frequency voltage for the main and auxiliary circuits. d) Insulation resistance of the main and auxiliary circuits shall be checked before and after High Voltage withstand test. e) Operation check shall be carried out for every control function as per the approved schematic diagrams by manually simulating fault conditions and operation of control switches/relays etc. f) For equipment bought from other sub-suppliers certified test reports of test carried out at the manufacturers works shall be submitted. Normally, all routine tests as specified in the relevant standards shall be conducted by the sub-supplier at his works. g) Interchangeability of similar modules on a random basis and may be done on one module of each size. The TPI agency shall be one of the following:BV EIL DNV IRS LLOYDS SGS STATUTORY AUTHORITY APPROVAL: The switchgear supplied shall be meet the Central Electrical Inspectorate requirement and guidelines and changes required, if any, shall be carried out by the vendor without any extra cost. Minor changes in wiring scheme, if required, to ensure working of the electrical system in a logical and safe manner shall be carried out by the vendor at site without any extra cost. PACKING, TRANSPORT & UNLOADING : The switchboard shall be shipped to site packed in wooden casings in order to facilitate storage in open yards. No part of the switchboard shall be visible after packing. They shall be wrapped with polythene sheets before being placed in wooden cases to prevent damage to the finish and to avoid any ingress of water. Casings shall have skid bottoms for handling. No other mode of packing shall be acceptable. Each panel after packing shall be identified with details of panel by indelible ink. The unloading shall be carried Page 90 of 153 out by the vendor at site through mechanical means and stored on a level ground. The vendor‟s representative shall check the panels against any damage during the transit. The vendor shall replace damaged parts without waiting for the insurance claims and the responsibility of taking up the claims with Insurance agency shall be on the account of vendor. GUARANTEE : The switchboard along with all equipment shall be guaranteed for trouble-freeoperation for a period of 12 months from the date of commissioning or 18 months from the date of arrival at site, whichever is earlier. Any defects discovered during this period shall be rectified free of cost. Any cost towards transportation, taxes and duties for replacement shall also have to be borne by the vendor. The vendor shall furnish a guarantee certificate to this effect. Page 91 of 153 DOC NO.: TECHNICAL PROCUREMENT SPECIFICATION TYPICAL SCOPE OF INSPECTION AND TESTS PAGE 1 OF 2 R0 TPS No.: ITEM : PANELS AT BATHINDA IRD - PUNJAB. EQPT. NOS.: The following inspection and test shall be conducted and records submitted. Please read the same in conjunction with the “specific requirement document”. ( Any extra test required to be done as per Specific requirement shall have to be carried out by the bidder. The QAP shall be submitted by bidder after placement of PO. Sl. No. Description Ins./test Reqd. Witness by TPI Reqd. 1.0 Physical verification for compliance with P.O. spec., scope, approved drawings & BOM 2.0 Routine tests 2.1 Power frequency Voltage dry tests on main circuits. NA 2.2 Voltage tests on control and auxiliary circuits 2.3 Measurement of resistance of main circuit 2.4 Mechanical operation test 2.5 Tests of the auxiliary electrical and pneumatic devices NA 2.6 Verification of wiring Remarks Page 92 of 153 2.7 Electrical operation test 2.8 Megger test 2.9 Safety interlocks and protection against electric shock and short circuits 2.10 Verification of CT ratio and polarity of CTs 2.11 Verification of nameplate information & marking 2.12 Relay operation tests Shall be conducted by relay manufacturer 2.13 Separate testing of breaker operating mechanism and other accessories NA NA NA - Not Applicable 0 21.10.2009 ORIGINAL ISSUE SDB KSC REV.NO. DATE PREPARED CHECKED DESCRIPTION APPROVED HINDUSTAN PETROLEUM CORP. LTD Page 93 of 153 DOC NO.: TECHNICAL PROCUREMENT SPECIFICATION ITEM SCOPE OF INSPECTION AND TESTS PAGE 2 OF 2 R0 : PANELS AT BATHINDA IRD - PUNJAB. The following inspection and test shall be conducted and records submitted Sl. No. Description 3.0 Type tests 3.1 Impulse voltage dry test 3.2 Power frequency voltage dry test Ins./test Reqd. Witness Reqd. Remarks a) Temperature rise tests of Switchboard 3.3 b) Temperature rise tests of Circuit breaker Copies of Certificates of type tests conducted on similar equipments shall be furnished. 3.4 Verification of dielectric properties 3.5 Verification of making and breaking capacity of breaker 3.6 Verification of temp. limits and characteristics of relays 3.7 Short time current tests on main circuits --- --- 3.8 Short time current test on earthing circuits --- --- 3.9 Mechanical operation test --- --- 3.10 Verification of degree of protection --- --- HINDUSTAN PETROLEUM CORP. LTD Page 94 of 153 I.EARTH WORK AND BACKFILLING 1.0 SCOPE 1.1 This section of the specification covers the technical requirements for excavation and filling & around structures, buildings, pipes, foundations, trenches, pits, drains, culverts, channels, cable ducts, underground facilities & similar works. It also covers filling areas and plinths with selected materials, conveyance and disposal of surplus spoils and/or stacking them properly as directed by the Consultant. 1.2 The contractor shall be fully responsible for proper setting out works, profiling in excavation, stacking, etc. taking adequate safety measures etc. The Contractor shall carry out all works meant within the intent of this specification even if not explicitly mentioned herein. All works shall be executed to the satisfaction of the Consultant. 1.3 Existing trees, shrubs, any other plants, pole lines, fences, signs, monuments, buildings, pipelines, drains, sewers or other surface or subsurface systems/ drainage facilities within or adjacent to the works being carried out which are not to be disturbed, shall be protected from damage by the Contractor. The Contractor shall provide and install suitable safeguards approved by the Consultant for this purpose. 1.4 During excavation, the Contractor shall take all necessary precautions against soil erosion, water & environmental pollution, and where required undertake additional works to achieve this objective. Before start of operations, the Contractor shall submit to the Consultant for approval, his work plan and the procedure he intends to follow for disposal of waste materials etc. and the schedule for carrying out temporary and permanent control works. However, the approval of the Consultant to such plans and procedures shall not absolve the Contractor of his responsibility for safe and sound work. 2.0 GENERAL 2.1 The Contractor shall make his own surveying arrangements for locating the coordinates and positions of all work and establishing the reduced levels (RL‟s) at these locations based on two reference grid lines and one bench mark which will be furnished by the Owner. The Contractor has to provide at site all the required survey instruments, along with qualified surveyors, to the satisfaction of the Consultant so that the work can be carried out accurately and according to the specification and drawings. 2.2 The Contractor shall furnish all skilled and unskilled labour, plant, tools, tackle, equipment, men and materials required for complete execution of the work in accordance with the drawings and as described herein and/or as directed by the Consultant. 2.3 The Contractor shall control the grade in the vicinity of all excavations so that the surface of the ground will be properly sloped or dyked to prevent surface water from running into the excavated areas during construction. Page 95 of 153 2.4 All materials obtained from excavation shall remain the Owner‟s property. All salvaged materials of archeological importance or of value (in the opinion of the Consultant) shall be segregated from the other materials and both stacked separately and in a regular manner at location indicated by the Consultant. 2.5 Excavation shall include removal of trees including roots & organic remains, vegetation, grass, bushes, shrubs, plants, poles, fences etc. that are in the area to be excavated as well as beyond the excavation line so as to ensure safety of the excavated side slopes and of men and equipment operating in the area. Before start of excavation work, joint measurements of ground level shall be taken after clearing all grass, vegetation etc. 2.6 Excavation shall include the removal of all materials required to execute the work properly and shall be made with sufficient clearance as decided by the Consultant to permit the placing and setting of forms, inspection and completion of all works to the satisfaction of the Consultant for which the excavation was done. 2.7 Classification of Earth Work: The earth work shall be classified under the following main categories. a) b) c) All types of soils, murrum, boulders. Soft rock. Hard rock. 2.7.1 Ordinary soils: This includes earth, murrum, top deposits of agricultural soil, reclaimed soil, clay, sand or any combination thereof and soft and hard murrum, shingle etc., which is loose enough to be removed with spades shovel and pick axes. Boulders not more than 0.03 cum. in volume found during the course of excavation shall also fall under this classification. 2.7.2 Soft Rock: This shall include all materials which are rock or hard conglomerate, all decomposed weathered rock, highly fissured rock, old masonry, boulders bigger than 0.03 cum in volume but not bigger than 0.5 cum and other varieties of soft rock which can be removed only with pick axes, crow bars, wedges and hammers with some difficulty. The mere fact that the contractor resorts to blasting and / or wedging and chiseling for reasons of his own, shall not mean the rock is classifiable as hard rock. 2.7.3 Hard Rock: This includes all rock other than soft rock mentioned in para 2.07.02 viz. Soft rock, occurring in masses, boulders having approximate volume more than 0.5 cum plain or reinforced cement concrete, which can best be removed by blasting or chiseling and wedging where blasting cannot be permitted owing to any restriction at site. 3.0 CODES AND STANDARDS Page 96 of 153 3.1 All standards, specifications, acts and code of practice referred to herein shall be the latest editions including all applicable official amendments and revisions. 3.2. In case of conflict between this specification and those (IS standards, codes etc.) referred to here in, the former shall prevail. 3.3 Some of the relevant Indian standards, Acts and Codes are referred to here below: IS: 383 1970 Specification for coarse and fine aggregates from natural sources for concrete. IS 2720 (Part- 2) 1973 Methods of test for soils-Determination of water content IS 2720 (Part4-4 ) 1985 Methods of test for soils-Grain size analysis IS 2720 (Part-5 ) 1985 Methods of test for soils-Determination of liquid limit & plastic limit IS 2720 (Part-6 ) 1972 Methods of test for soils-Determination of shrinkage factors IS 2720 (Part-7 ) 1980 Methods of test for soils-Determination of water content-Dry density relation using light compaction IS 2720 (Part-8 ) 1983 Methods of test for soils- Determination of water content-Dry density relation using heavy compaction IS 2720 (Part-14 ) 1983 Methods of test for soils-Determination of dry index(relative density) IS 2720 (Part-21 ) 1977 Methods of test for soils-Determination of total soluble solids IS 2720 (Part-23 ) 1976 Methods of test for soils-Determination of calcium carbonate IS 2720 (Part-24 ) 1976 Methods of test for soils-Determination of cation exchange capacity IS 2720 (Part-27 ) 1977 Methods of test for soils-Determination of total soluble sulphates IS 2720 (Part-29 ) 1975 Methods of test for soils-Determination of dry density of soil in-place by core cutter method IS: 3764 1992 Safety code for excavation work IS: 4081 1986 Safety code for blasting and related drilling operations IS: 4701 1982 Code of practice for earth work on canals Page 97 of 153 IS: 9759 1981 Guide lines of dewatering during construction IS: 10379 1982 Code of practice for field control of moisture and compaction of soils for embankment and sub grade Indian Explosives Act 1940 as updated. 4.0 EXCAVATION IN SOIL 4.1 Side and bottom of excavation shall be cut sharp and true to line and level. Undercutting shall not be permitted. When machines are used for excavation, the last 300 mm before reaching the required level shall be excavated manually or by such equipment that soil at the required final level will be left in its natural condition. Suitability of strata (at the bottom of excavations) for laying the foundation thereon shall be determined by the Consultant. 4.2. Excavation for foundation shall be to the bottom of lean concrete and as shown on drawing or as directed by the Consultant. The bottom of all excavations shall be trimmed to required levels and when excavation is carried below such levels by error, it shall be brought back to the specified level by filling with concrete of nominal mix 1:3:6 (cement: coarse sand: 40 mm down aggregates) as directed by the Consultant. 4.3 The Contractor shall ascertain for himself the nature of materials to be excavated and the difficulties, if any, likely to be encountered in executing this work., sheeting, shoring, bracing, maintaining suitable slopes, draining etc. shall be provided and installed by the Contractor, to the satisfaction of the Consultant. 4.4. All excavation for installation of underground facilities, such as pipe lines, sewer line, drain lines etc. shall be open cuts. For deep and huge excavations and in other excavations, if required by the Consultant, the Contractor shall submit for Consultant‟s approval an “Excavation Scheme” showing the methodology to be adopted for excavation in order to maintain the stability of side slopes, means for ensuring safety of existing facilities nearby, dewatering. However, the Contractor shall be fully responsible for the scheme irrespective of any approvals granted. Benching shall be provided for deeper excavation wherever required. 4.5 When excavation requires bracing, sheeting or shoring etc. the Contractor shall submit drawings to the Consultant, showing arrangements and details of proposed installation. The Contractor shall also furnish all supporting calculations as called for and shall not proceed until he has received written approval from the Consultant. However, the responsibility for adequacy of such bracing, sheeting, shorting etc. will rest with the Contractor, irrespective of any approval of the Consultant. 4.6 The Contractor shall have to constantly pump out any water collected in excavated pits and other areas due to rain water, springs etc. and maintain dry working conditions at all times until the excavation, placement of reinforcement, shuttering, concreting, backfilling Page 98 of 153 is completed. The Contractor shall remove all slush/muck from the excavated areas to keep the work area dry. Sludge pumps, if required, shall be employed by the Contractor for this purpose. 4.7 The Contractor shall remove all materials arising from excavations from the vicinity of the work either for direct filling, stacking the subsequent filling or for ultimate disposal as directed by the Consultant. In no case shall the excavated soil be stacked within a distance of 1.5 m from the edge of excavation or one third the depth of excavation whichever is more. Material to be used for filling shall be kept separately. 5.0 EXCAVATION IN ROCK 5.1 General 5.1.1 All clauses from 4.1 to 4.7 shall be applicable to excavation in rock also. In case of any discrepancy between the above mentioned clause and those specified in this clause then this clause shall govern. 5.1.2 For the work of excavation in rock, Contractor shall engage specialised agency having experience of excavation in rock involving wedging and blasting. The agency shall be subject to approval of Consultant and the Contractor shall furnish details of relevant experience in support while seeking approval for the agency. 5.1.3 In case of overbreaks in rock excavation, the excavated level shall be brought to the level shown on drawings with plain cement concrete of nominal mix 1:3:6 as described in para 4.02.00. 5.2 Excavation by Blasting 5.2.1 Blasting shall be resorted to only with the written permission of the Consultant. All the statutory laws, (Explosives Act etc.) rules, regulations, Indian Standards etc. pertaining to the acquisition, transport, storage, handling and use of explosives etc. shall be strictly followed. 5.2.2 The contractor shall obtain Licenses from Competent Authorities for undertaking blasting work as well as for procuring, transporting to site and storing the explosives as per Explosives Act. The Contractor shall be responsible for the safe transport, use, custody and proper accounting of the explosive materials. 5.2.3 The Contractor may adopt any method of blasting as permitted according to explosives act/rule consistent with the safety and job requirements (after approval from the Consultant) and so as not to injure men or damage materials/structures during blasting operations. 5.2.4 The magazine for the storage of explosives shall be built by the Contractor to the designs and specifications of the Explosives Department concerned and located at the approved Page 99 of 153 site. No unauthorised person shall be admitted into the magazine which, when not in use, shall be kept securely locked. No matches or inflammable material shall be allowed in the magazine. The magazine shall have an effective lightning conductor and the following shall be hung in the lobby of the magazine. a) A copy of the relevant rules regarding safe storage, both in English and in the language(s) with which the workers concerned are familiar. b) A statement of up to date stock in the magazine. c) A certificate showing the last date of testing of the lightning conductor. d) A notice stating that smoking is strictly prohibited. 5.2.5 The Contractor shall also observe any specific instructions given by the Consultant. The Contractor shall be responsible and liable for damage to property and any accident which may occur to workmen or to the public or to materials on account of any operation connected with the storage, transportation, handling or use of explosives and the blasting operations. The Consultant or his authorised representative shall frequently check the Contractor‟s compliance with these precautions and the manner of storing and accounting of explosives. The Contractor shall provide necessary facilities for this. 5.2.6 All materials, tools and equipments used for blasting operations shall be of approved make and type. In special cases, the Consultant may specify the type of explosives to be allowed. The fuse to be used in wet locations shall be sufficiently water resistant so as to be unaffected when immersed in water for 30 minutes. The rate of burning of the fuse shall be uniform and precisely known to permit evaluation of the distance to which the firer should move before explosion takes place. Detonators shall be capable of effective blasting of the explosives. 5.2.7 The blasting powder, explosives, detonators, fuses etc. shall be fresh and not damaged due to dampness or any other Cause. Explosives shall be kept dry and shall not be exposed to direct rays of the sun or be stored in the vicinity of fire, stoves, steam pipes, or heated metal etc. They shall be inspected before use and damaged articles shall be discharged totally and removed from site immediately. 5.3 Blasting Operations 5.3.1 The blasting operations shall remain in the charge of a responsible, competent, authorised and experienced supervisor (called Man-in-Charge) and workmen who are thoroughly acquainted with the details of handling explosives and blasting operation and with the rules governing such work. Page 100 of 153 5.3.2 All rules under the Explosives Act and other local rules in force shall be fully observed. All blasting works shall be done in accordance with the stipulations contained in IS: 4081. Blasting shall only be carried out at certain specified times preferably during the mid-day lunchtime or at the close of work as directed in writing by the Consultant. The hours when blasting will be done, shall be made known to people in the vicinity. All the charges shall be prepared by the Man-in-Charge (as defined in 5.03.01) above) only. Proper precautions for safety of persons and property shall be taken. 5.3.3 Prior to blasting, red danger flags shall be displayed prominently around the area to be blasted and shall be kept in position until blasting work is completed. All people, except those who actually light the fuses, shall be prohibited from entering this area. The flags shall be planted 200 metres from the blasting site and all persons including workmen shall be evacuated from the flagged area atleast 10 minutes before firing. A warning whistle shall be sounded for this purpose. 5.3.4 Controlled Blasting shall be carried out within 200 metres of an existing structure unless otherwise permitted by the Consultant in writing. Where (generally with in plant area) controlled blasting is to be carried out in the proximity of other structures, then sand bags and/or earth bags etc. shall be used on top of the blast holes to prevent the rock fragments from causing damage to adjacent structures and property. At all stages of blasting operations, precautions shall be taken to preserve the rock in the soundest possible condition below and beyond the lines specified for the excavation. The quantity and strength of explosives used shall be such that it will neither damage nor crack the rock outside the limits of excavation. Any method of blasting which leads to overshooting shall be discontinued. 5.3.5 No explosive shall be brought near the work in excess of the quantity required for a particular amount of firing to be done and surplus left after filling holes shall be removed to the magazine. A careful and day to day account of the explosives shall be maintained by the Contractor in an approved manner and in an identified register, which shall be open to inspection by the Consultant at all time. 5.3.6 At a time not more than ten such charges shall be prepared and fired. The man-inCharges shall blow the whistle in a recognised manner for cautioning the people. The number of blasts to be fired and actual number of shots heard shall be compared and the person responsible shall satisfy himself by examination that all blasts have exploded before any person working in the area is permitted to re-approach the work site. Sufficient time shall be allowed to account for delayed blasts. The Man-in-Charge shall inspect all the charge. The withdrawal of the unexploded charge shall not be permitted under any circumstances. After tamping, the unexploded charge shall be flooded with water and the hole marked in a distinguishable manner. Another hole shall be jumped at a distance of 450 mm from the old hole and fired in the usual way. This process shall be continued till the original blast is exploded. The Man-in-Charge shall at once report to the Contractor‟s office and the Consultant, all cases of misfire, the cause for the same and what steps where taken in connection therewith. Page 101 of 153 5.3.7 If misfire is found to be due to defective materials, the whole quantity in the box form which the defective materials was taken must be sent to the Authority directive by the Consultant for inspection to ascertain whether any of the remaining materials in the box are also defective. 5.4 Chiseling / Wedging Where blasting is prohibited for any reasons or it is not practicable in the opinion of the Consultant, then the excavation shall be carried out by chiseling, wedging or any other approved method. The decision of the Consultant in this regard shall be final binding on Contractor. 5.5 Line drilling and pre-shearing The number, size and location of holes shall be carefully worked out by the Contractor and shall be subject to the approval of the Consultant. Line drilled holes shall generally be 48 mm dia. and, if so directed, interior blasting holes shall also be made. The Contractor shall carry out test to determine the amount of explosives required to ensure an even break at the line drilled holes after the interior holes are blasted and irregularities in the vertical drilled line face shall be removed and trimmed by wedging, splitting, chiseling and barring. 6.0 EXCAVATION BELOW GROUND WATER TABLE 6.1 Wherever ground water table is met with during excavation, the Contractor shall immediately report this fact to the Consultant who shall arrange to record the exact level of the water table before start of dewatering operation. The decision of the Consultant regarding sub-soil water level shall be final and binding on the Contractor. Ground Water Table for the purpose of this clause shall be taken as the level of standing water observed during the process of excavation. Capillary action of water in the surrounding soil mass shall not be considered for the above purpose. 6.2 The Contractor shall dewater and maintain dry working conditions by maintaining the water table below the bottom of the excavation level by well-point dewatering or deep well dewatering or any other method approved by the Consultant. He shall continue doing so till excavation, concreting, curing, and all other operation included in the scope of work, which require dry condition in the area are completed. 7.0 LIFT The Contractor is required to excavate upto any depth as shown on the drawings or as directed by the Consultant. Lifting of excavated materials shall be done either by manual Page 102 of 153 or mechanical or both means if called for by the Consultant. 8.0 CARRIAGE OF MATERIALS 8.1 The EIC shall indicate the disposal/ stacking areas for excavated materials. The carriage of excavated materials shall be done by the methods mentioned below: a) The excavated materials shall be carried beyond the initial lead of 50 m but upto 500 m by manual /animal labour or by mechanical means. If directed by the Consultant this material shall be used directly for filling purposes. b) For leads exceeding 500 m the Contractor shall transport the excavated materials by mechanical means only and as directed by the Consultant. The Contractor may be allowed to carry materials through Kuccha roads. Providing and maintaining of the Kuccha roads shall be the responsibility of the Contractor. The transported material shall be neatly stacked as directed by the Consultant. 8.2 Some excavated materials required for filling purposes, may have to be carried upto a lead of 500 m and stacked as per instructions of the Consultant. Excavated materials carried beyond 500 m shall normally be for disposal purpose only. Double handling of materials shall be avoided as far as possible. However, depending on site condition excavated materials carried beyond a lead of 500 m may also be required to be brought back for filling purpose. 9.0 FILLING 9.1 Materials 9.1.1 Materials to be used for filling purpose shall be stone, sand or other inorganic materials and they shall be clean and free from shingle, salts, organic matter, large roots and excessive amount of sod, lumps, concrete or any other foreign substances which could harm or impair the strength of the substances in any manner. All clods shall be suitably broken to small pieces. When the materials are mostly rock boulders, these shall be broken into pieces not larger then 150 mm size. Sand used for filling shall be clean, medium grained and free from impurities. Fines less than 75 microns shall not be more than 20%. In any case, the materials to be used for filling purposes shall have the prior written approval of the Consultant. 9.1.2 If excavated materials are to be used for filling, then the Contractor shall select the materials from the stockpile, land and transport this material and execute the filling. This shall include excavation of earth, which may become hard due to lying in stockyard for a long period of time. Page 103 of 153 9.1.3 In case the materials have to be brought from pits/quarries, it shall be the Contractor‟s responsibility for identification of such quarry areas, obtaining approval from their use from concerned authorities, excavation/quarrying loading and carriage of such material, unloading and filling at specified locations. The Contractor shall pay any fees, royalties etc. that may have to be pain for utilisation of borrow areas. 9.2 Filling Procedure 9.2.1 After completion of foundation, footings, walls and other construction below the elevation of the final grades, and prior to filling, all temporary shoring, timber etc. shall be sequentially removed and the excavation cleaned of all trash, debris, and. perishable materials. Filling shall begin only with the written approval of the Consultant. Also, areas identified for filling shall be cleared of all soft pockets, vegetation, bushes, slash etc. In case of plinth and similar filling the ground shall be dressed and consolidated by ramming and light rolling. 9.2.2 Fill materials shall not be dropped directly upon or against any structure or facility where there is danger of displacement or damage. Filling shall be started after the concrete/masonry has fully set and shall be carried out in such a manner so as not to cause any undue lateral thrust on any part of the structure. 9.2.3 All space between foundation (concrete or masonry) and the sides excavation shall be filled to the original surface after making allowance for settlement, Fill shall be placed in horizontal layers not exceeding 200 mm loose thickness. Each layer shall be watered and compacted with proper moisture content and with such equipment as may be required to obtain a compaction/density as specified. Trucks or heavy equipment for depositing or compacting fill shall not be used within 1.5 meters of building walls, piers for operation. The methods of compaction shall be subjected to approval of Consultant under any circumstances. 9.2.4 Fill adjacent to pipes shall be free of stones, concrete etc. and shall be hand placed and compacted uniformly on both sides of the pipe and where practicable up to a minimum depth of 300 mm over the top of pipes. While tamping around the pipes, care should be taken to avoid unequal pressure. 9.2.5 Filling shall be accurately finished to line, slope, cross section and grade as shown on the drawings. Finished surface shall be free of irregularities and depressions and shall be within 20 mm of the specified level. 9.2.6 Where filling with stone from excavated materials is specified, it shall be from broken pieces of boulders. At first a 75 mm thick cushion of selected earth shall be laid over which the 200 mm thick graded stones shall be laid in loose layers of 200 mm then the interstices filled with properly graded fine materials consisting of selected earth brought from borrow areas. Each layer shall be watered and compared to the specified density before the next layer is laid. However, no cushion shall be required where filling is over non-rocky surface. Page 104 of 153 9.2.7 Where filling with 65 mm down graded stone obtained from excavated, it shall be selected stone laid over and initial 50 mm thick cushion layer of selected earth and then stone laid in 200 m loose thick layers, interstices filled with the specified density before the next layer in laid. However, no cushion shall, be required where filling is over nonrocky surface. 9.2.8 Where clean stone fill is specified, it shall consist of clean selected stone metal of 40-mm nominal size. It shall be laid in layers not exceeding 150 mm (loose) and lightly tamped before the next layer is laid. No compaction shall be required for this type stone filling. 9.3 Compaction 9.3.1 Where compaction to 95% Standard Proctor Density or more is called for, it shall be by mechanical means only. Where access is possible, compaction shall be by 12 tonne rollers smooth wheeled, sheep foot or wobbly wheeled as directed by the Consultant. A smaller weight roller may be permitted by the Consultant in special cases, but in any case not less than 10 passes of the roller will be accepted for each layer. Each layer shall be wetted or the material dried by aeration to moisture content of 3-5% above the Optimum Moisture Content to be determined by the Contractor. Each layer shall be watered, rammed and compacted to the density as specified Consultant. 9.3.2 For compacting sand layer, water shall be sprayed over it to flood it and it shall be kept flooded for 24 hours to ensure maximum compaction. Vibro-compactors shall also be used if necessary to obtain the required degree of compaction. Any temporary works required to contain sand under flooded condition shall also be undertaken. The surface of the consolidated sand shall be dressed to required levels or slope. 9.3.3 After the compacted fill has reached the desired level, the surface shall be flooded with water for 24 hours, allowed to dry and then rammed and consolidated to avoid any settlement, at a later date. The compacted surface shall be properly shaped, trimmed and consolidated to an even gradient or level. All soft spots shall be excavated, filled and consolidated. 9.3.4 The degree of compaction of compacted fill in place will be subject to tests by the Consultant as the work progresses, and the contractor shall provide the necessary facilities to make such tests. If any test indicates that the compaction achieved is less than the specified degree of compaction, the Consultant may require fill placed subsequent to the last successful test to be removed and re-compacted by the Contractor. Compaction procedure shall be amended as necessary to obtain satisfactory results. 9.3.5 When semi-compacted fill is specified by the Consultant, the contractor shall fill up such areas with available earth from stock piles of borrow pits or directly from excavation without special compaction except that obtained by moving trucks etc. Page 105 of 153 II. PLAIN AND REINFORCED CONCRETE & ALLIED WORKS 1.0 SCOPE 1.1 This specifications covers the general requirements for concreting to be used on jobs using on-site production facilities including requirements in regard to handling, storage of ingredients, proportioning, batching, mixing and testing and quality assurance. This also covers the transportation of concrete from the mixer to the place of final deposit and the placing consolidation, curing, protecting, repairing and finishing of concrete. 1.2 The work shall include providing of materials, all necessary plant and equipment, providing adequate Consultating supervision and technical personnel, skilled and unskilled labour, etc. as required to carry out the entire work as indicated on the drawings and/or described herein subsequently and/or as directed by the Consultant. 1.3 The Contractor shall carry out all works meant within the intent of this specification even if not explicitly mentioned herein. All works shall be executed to the satisfaction of the Consultant. 2.0 GENERAL 2.1 The Contractor shall make his own surveying arrangements for locating the coordinates and positions of all work and establishing the reduced levels (RLs) at these locations, based on two reference grid lines and one bench mark, which will be furnished by Owner. The Contractor has to provide at site, all the required survey instruments, along with qualified surveyors, to the satisfaction of the Consultant so that the work can be carried out accurately and according to the specifications and drawings. 2.2 The contractor shall establish a site laboratory for testing of material and quality assurance as per the requirements of this specification. The laboratory shall be manned by qualified Consultant. 2.3 Any approval, instructions, permission, checking, review, etc. whatsoever by the Consultant, shall not relieve the Contractor of his responsibility and obligation regarding adequacy, correctness, completeness, safety, strength, quality, workmanship, etc. 3.0 CODES AND STANDARDS 3.1 All work shall be carried out as per the stipulations contained in various sections of these specifications and the latest Indian Standards, Acts, Codes and best practices. 3.2 All applicable standards, specifications, etc. and codes of practice shall generally be the latest editions, including all applicable official amendments and revisions. A complete set of all these documents shall generally be available at site, with the Contractor. Page 106 of 153 3.3 3.4 In case of conflict between the stipulations contained in various sections of these specifications and stipulations of Indian Standards, Codes, etc. the requirements of stipulations contained in various sections of these specifications, shall prevail over that of Indian Standards, Codes, etc. The following are the various relevant Indian Standards: IS: 73 1992 Specification for paving bitumen IS : 216 1961 Specification for coal tar pitch IS: 269 1989 Specification for 33 grade Ordinary Portland cement IS: 280 1978 Specification for mild steel wire for general Consultanting purposes IS: 383 1970 Specification for coarse and fine aggregates from natural sources for concrete IS:432 (Parts I) 1982 Specification for mild steel medium tensile steel bars and hard drawn steel wire for concrete reinforcement – Mild steel & medium tensile bars IS: 432(Parts II) 1982 Specification for mild steel medium tensile steel bars and hard drawn steel wire for concrete reinforcement - Hard drawn steel wire IS: 455 1989 Specification for Portland slag cement IS: 456 2000 Code of practice for plain and reinforced concrete IS: 457 1957 Code of practice for general construction of plain & reinforced concrete for dams & other massive structures IS: 516 1959 Method of test for strength of concrete IS : 650 1991 Specification for standard sand for testing of cement IS: 702 1988 Specification for industrial bitumen IS : 737 1986 Wrought aluminium and aluminium alloy plate for general Consultanting purposes IS: 800 1984 Code of practice for general construction in steel Page 107 of 153 IS: 816 1969 Code of practice for use of metal are welding for general construction in mild steel IS: 1161 1998 Specification for steel tubes for structural purpose IS: 1199 1959 Methods of sampling and analysis of concrete IS: 1200 (Part-II) 1974 Method of measurement of building and civil Consultanting works - Concrete works IS: 1200 V) (Part- 1982 Method of measurement of building and civil Consultanting works - Form work IS: 1200 VIII) (Part- 1993 Method of measurement of building and civil Consultanting works - Steel work & iron work IS: 1200 XVIII) (Part- 1974 Method of measurement of building and civil Consultanting works - Demolition & dismantling 1993 Specification for bitumen felts for waterproofing and damp proofing IS: 1322 IS: 1363 (Part 1) 2002 Hexagon head bolts, screws and nuts of product grade „C‟ – Hexagon head bolts (size range M 5 to M 64) IS: 1363 (Part 2) 2002 Hexagon head bolts, screws and nuts of product grade „C‟ – Hexagon head screws (size range M 5 to M 64) IS: 1363 (Part 3) 2002 Hexagon head bolts, screws and nuts of product grade „C‟ – Hexagon nuts ( size range M5 to M 64) IS: 1489 (Part-I) 1991 Specification for Portland-pozzolana cement: Fly ash based IS:1489 (Part-II) 1991 Specification for Portland Pozzolana Cement: Calcined clay based. IS : 1566 1982 Specification for Hard-drawn steel wire fabric for concrete reinforcement. IS : 1609 1991 Code of practice for laying damp proofing bitumen felts. IS : 1786 1985 Specification for high strength deformed steel bars and wires for concrete reinforcement. IS : 1791 1985 General requirements for batch type concrete mixer. treatment using Page 108 of 153 IS: 1834 1984 Specification for hot applied sealing compound for joints in concrete IS : 1838 (Part-I) 1983 Specification for preformed fillers for expansion joints in concrete pavements and structures (non extruding and resilient type).Bitumen impregnated fibe IS: 2016 1967 Plain washers IS: 2074 1992 Specification for ready mix paint, air drying, red oxide zinc chrome IS : 2386 (Part 1) 1963 Methods of test of aggregates for concrete – Particle size & shape IS : 2386 (Part 2) 1963 Methods of test of aggregates for concrete – Estimation of deleterious material and organis impurities IS : 2386 (Part 3) 1963 Methods of test of aggregates for concrete – Specific gravity, Density, voids, absorption and bulking IS : 2386 (Part 4) 1963 Methods of test of aggregates for concrete – Mechanical properties IS : 2386 (Part 5) 1963 Methods of test of aggregates for concrete – Soundness IS : 2386 (Part 6) 1963 Methods of test of aggregates for concrete – Measuring mortar making properties of fine aggregates IS : 2386 (Part 7) 1963 Methods of test of aggregates for concrete – Alkali aggregate reactivity IS : 2386 (Part 8) 1963 Methods of test of aggregates for concrete – Petrographic examination IS : 2438 1963 Specification for roller pan mixer. IS : 2502 1963 Code of practice for bending and fixing of bars for concrete reinforcement. IS : 2505 1992 General requirements for concrete vibrators, immersion type. IS : 2506 1985 General requirements for concrete vibrators, screen board type. IS : 2514 1963 Specification for concrete vibrating table. IS : 2571 1970 Code of practice for laying in-situ cement-concrete flooring. IS : 2645 2003 Specification for Integral cement water proofing compounds for cement mortar and concrete Page 109 of 153 IS : 2722 1964 Specification for portable swing weigh batchers for concrete. (single and double type) IS : 2750 1964 Specification for steel scaffoldings. IS : 2751 1979 Code of practice for welding of mild steel plain and deformed bars for reinforced concrete construction. IS: 2812 1993 Recommendation for manual tungsten inert gas arc welding of aluminium and aluminium alloys IS : 3025 (Part 1986 22) Methods of sampling and test (physical & chemical) for water & waste water – Acidity IS : 3025 (Part 1986 23) Methods of sampling and test (physical & chemical) for water & waste water – Alkalinity IS : 3037 1986 Specification for bitumen mastic for use in water proofing of roofs IS : 3150 1982 Specification for hexagonal wire netting for general purposes. IS : 3370 (Part I) 1965 Code of practice for concrete structures for the storage of liquids – General requirements IS : 3370 (Part II) 1965 Code of practice for concrete structures for the storage of liquidsReinforced concrete structures IS : 3384 1986 Specification for bitumen primer for use in waterproofing & damp proofing. IS : 3414 1968 Code of practice for design and installation of joints in buildings. IS : 3550 1965 Methods of test for routine control for water used in Industry. IS : 3558 1983 Code of practice for use of immersion vibrators for consolidating concrete. IS : 3696 (Part I) 1987 Safety code for scaffolds and ladders – Scaffolding IS : 3696 (Part II) 1991 Safety code for scaffolds and ladders – Ladders IS : 4014 (Part I) Code of practice for steel tubular scaffolding – Definition & amterials IS : 4014 (Part II) Code of practice for steel tubular scaffolding - Safety Regulation for scaffolding IS : 4031 (Part 1) 1996 Methods for physical tests for hydraulic cement – Determination Page 110 of 153 of finess by dry sieving IS : 4031 (Part 2) 1999 Methods for physical tests for hydraulic cement – Determination of fineness by specific surface by Blaine air permeability method IS : 4031 (Part 3) 1988 Methods for physical tests for hydraulic cement – Determination of soundness IS : 4031 (Part 4) 1988 Methods for physical tests for hydraulic cement – Determination of consistency of standard cement paste IS : 4031 (Part 5) 1988 Methods for physical tests for hydraulic cement – Determination of initial and final setting times IS : 4031 (Part 6) 1988 Methods for physical tests for hydraulic cement – Determination of compressive strength of hydraulic cement (other than masonry cement) IS : 4031 (Part 7) 1988 Methods for physical tests for hydraulic cement – Determination of compressive strength of masonry cement IS : 4031 (Part 8) 1988 Methods for physical tests for hydraulic cement – Determination of transverse and compressive strength of plastic mortar using prism IS : 4031 (Part 9) 1988 Methods for physical tests for hydraulic cement – Determination of heat of hydration IS : 4031 (Part 1988 10) Methods for physical tests for hydraulic cement – Determination of drying shrinkage IS : 4031 (Part 1988 11) Methods for physical tests for hydraulic cement – Determination of density IS : 4031 (Part 1988 12) Methods for physical tests for hydraulic cement – Determination of air content of hydraulic cement mortar IS : 4031 (Part 1988 13) Methods for physical tests for hydraulic cement – measurement of water retentivity of masonry cement IS : 4031 (Part 1989 14) Methods for physical tests for hydraulic cement – Determination of false set IS : 4031 (Part 1991 15) Methods for physical tests for hydraulic cement – Determination of fineness by wet sieving IS : 4130 Safety Code for demolition of buildings. 1991 Page 111 of 153 IS : 4218 (Part 3) 1999 ISO general purpose metric screws threads – Basic dimensions IS : 4326 1993 Code of practice for earthquake resistant design and construction of buildings. IS : 4461 1998 Code of practice for joints in surface hydro-electric power stations. IS : 4656 1968 Specification for form vibrators for concrete. IS : 4671 1984 Expanded polystyrene for thermal insulation purposes IS : 4925 1968 Specification for batching and mixing plant. IS : 4990 1993 Specification for plywood for concrete shuttering work. IS : 4995 (Part I) 1974 Criteria for design of reinforced concrete bins for the storage of granular and powdery materials – General requirement & assessment of bin loads IS : 5256 1992 Code or practice for sealing joints in concrete lining on canals. IS : 5525 1969 Recommendations for detailing of reinforcement in reinforced concrete work. IS : 5624 1993 Specification for foundation bolts. IS : 5871 1987 Specification for bitumen mastic for tanking and damp proofing IS : 6461 (Part 1) 1972 Glossary of terms relating to cement concrete – Concrete aggregates IS : 6461 (Part 2) 1972 Glossary of terms relating to cement concrete – Materials (other that cement and aggregates) IS : 6461 (Part 3) 1972 Glossary of terms relating to cement concrete – Concrete reinforcement IS : 6461 (Part 4) 1972 Glossary of terms relating to cement concrete – types of concrete IS : 6461 (Part 5) 1972 Glossary of terms relating to cement concrete – Formwork for concrete IS : 6461 (Part 6) 1972 Glossary of terms relating to cement concrete – Equipment, tools & plant IS : 6461 (Part 7) 1973 Glossary of terms relating to cement concrete – Mixing, Laying, Compaction, Curing and other construction aspects IS : 6461 (Part 8) 1973 Glossary of terms relating to cement concrete – Properties of Page 112 of 153 concrete IS : 6461 (Part 9) 1973 Glossary of terms relating to cement concrete – Structural aspects IS : 6461 (Part 1973 10) Glossary of terms relating to cement concrete – Tests & testing apparatus IS : 6461 (Part 1973 11) Glossary of terms relating to cement concrete – Prestressed concrete IS : 6461 (Part 1973 12) Glossary of terms relating to cement concrete - Miscellenaneous IS : 6494 1988 Code of practice for water proofing of underground water reservoirs and swimming pools. IS : 6509 1985 Code of practice for installation of joints in concrete pavements. IS : 7193 1994 Specification for glass fiber base coal-tar pitch and bitumen felts. IS : 7293 1974 Safety code for working with construction machinery. IS : 7634 (Part 3) 2003 Code of practice for Plastic pipe selection, handling, storage and installation for potable water supplies – Laying and jointing of PVC pipes IS : 7861 (Parts I) 1975 Code of practice for extreme weather concreting – Recommended practice for hot weather concreting IS : 7861 (Parts 1981 II) Code of practice for extreme weather concreting – Recommended practice for cold weather concreting IS: 8042 1989 Specification for White Portland cement IS: 8043 1991 Specification for hydrophobic Portland cement IS: 8112 1989 Specification for 43 Grade Ordinary Portland Cement IS : 9103 1999 Specification for concrete admixtures IS : 9417 1989 Recommendations for welding cold-worked steel bars for reinforced concrete construction. IS : 9595 1996 Recommendations for metal-arc welding of carbon and carbon manganese steels. IS : 10262 1982 Recommended guidelines for concrete mix design. IS : 11384 1985 Code of practice for composite construction in structural steel and Page 113 of 153 concrete. IS : 12118 1987 Specification for two-part poly-sulphide based sealants – General requirements IS : 12118 1987 Specification for two-part poly-sulphide based sealants – Methods of test IS : 12200 2001 Code of practice for provision of water stops at transverse construction joints in masonry and concrete dams IS : 12269 1987 Specification for 53 Grade ordinary Portland cement. IS: 12330 1988 Sulphate resisting Portland Cement IS : 12600 1989 Specification for low heat Portland cement SP : 23 1982 Handbook of concrete mixes. SP : 24 1983 Explanatory Handbook on IS: 456 SP : 34 1987 Handbook on concrete reinforcement and detailing. 4.0 MATERIALS 4.1 General: 4.1.1 All the materials used in the manufacture of concrete shall be in accordance with the Technical Specification for Properties, Storage and Handling of Common Building Materials, which shall be deemed to form a part of this specification. 4.1.2 The Consultant shall have the right to inspect the sources of materials, the layout and operation of procurement and storage of materials, the concrete batching and mixing equipments and the quality control system. Such an inspection shall be arranged by the contractor and the Consultant s approval shall be obtained prior to starting the work. 4.2 Aggregates 4.2.1 Aggregate in general designates both fine and coarse inert materials used in the manufacture of concrete. Coarse Aggregate is faction retained on 4.75 mm IS sieve. Fine Aggregate is faction which passes through 4.75 mm IS sieve. 4.2.2 Aggregate shall consist of natural sand, crushed stone and gravel from a source known to produce satisfactory aggregate for concrete and shall be chemically inert, strong, hard, Page 114 of 153 durable against weathering, of limited porosity and free from deleterious materials that may cause corrosion to the reinforcement or may impair the strength and / or durability of concrete. Aggregates shall conform to I.S. 383 4.2.3 Properties: Aggregates with a specific gravity below 2.6 shall not be used without special permission of the Consultant. Machine-made sand will be acceptable provided the constituent (rock/gravel) is sound, hard, dense and is acceptable to the Consultant. Sand, natural gravel and crushed rock shall be prepared for use by such screening or washing, or both, as necessary to remove all objectionable foreign matter. 4.2.4 The coarse aggregate and fine aggregate shall be tested from time to time as required by the Consultant to ascertain its suitability for use in construction and the charges for testing aggregate shall be born by the contractor as specified herein after. Sampling of the aggregates for mix design and determination of suitability shall be taken under the supervision of the Consultant and delivered to the laboratory, well in advance of the schedule placing of concrete. Records of tests which have been made on proposed aggregates and on concrete made from this source of aggregates shall be furnished to the Consultant in advance of the work for use, in determining suitability of the proposed aggregate. 4.2.5 The grading of aggregates shall be such as to produce a dense concrete of specified strength and consistency that will work readily into position without segregation and shall be based on the “mix design” and preliminary test on concrete specified herein-after. 4.2.6 Grading of Coarse Aggregate : Coarse aggregates shall be either in single or graded, in both the cases. The grading shall be within the following limits. IS Sieve Designa tion Percentage passing for single sized aggregates of nominal size 63 40 20 16 12.5 mm mm mm mm mm Percentage passing for graded aggregates of nominal size 10 mm 40 20 mm 16 12.5 mm mm mm 75mm 100 - - - - - - - - - 63mm 85- 100 - - - - 100 - - - 85- 100 - - - 95- 100 - - 100 37.5mm 0-30 Page 115 of 153 100 19mm 0-5 0-20 100 85- 100 - - 30-70 95-100 100 100 85- 100 - - - 90-100 - 100 16mm - - - 100 11.2mm - - - - 85-100 100 - - - 90-100 9.5mm - 0-5 0-20 0-30 0-45 85-100 10-35 25-55 30-70 40-85 4.75mm - 0-5 0-5 0-10 0-20 0-20 0-5 0-10 0-10 0-10 2.36mm - - - - 0-5 0-5 - - - - 4.2.7 Foreign Material Limitations: The percentages of deleterious substances in the coarse aggregate delivered to the mixer shall not exceed the following : Percentage by weight of aggregates Substances 4.2.8 Uncrushed Crushed i) Material finer than 75 micron IS Sieve. 3.00 3.00 ii) Coal and lignite 1.00 1.00 iii) Clay lumps 1.00 1.00 iv) Soft fragments 3.00 -- v) Total of all the above substances 5.00 5.00 Grading of fine aggregate shall be within the limits indicated hereunder : Page 116 of 153 4.2.9 4.2.10 IS Sieve Designation Percentage Passing for Grading Grading Grading Zone-I Zone-II Zone-IIII Grading Zone-IV 10 mm 100 100 100 100 4.75 mm 90-100 90-100 90-100 95-100 2.36 mm 60-95 75-100 85-100 95-100 1.18 mm 30-70 55-90 75-100 90-100 600 micron 15-34 35-59 60-79 80-100 300 micron 5-20 8-30 8-30 20-65 150 micron 0-10 0-10 0-10 0-15 Foreign Material Limitations : The percentages of deleterious substances in fine aggregate, delivered to the mixer shall not exceed the following : Substances Percent by weight Uncrushed Crushed i) Material finer than 75 micro IS sieve 3.00 15.00 ii) Shale 1.00 -- iii) Coal and lignite 1.00 1.00 iv) Clay lumps 1.00 1.00 v) Total of all above substances 5.00 including items (I) to (iv) for uncrushed sand and items (iii) and (iv) for crushed sand 2.00 Fineness Modulus : The fine aggregate shall have a fineness modulus of not less than 2.2 or more than 3.2. The fineness modulus is determined by adding the cumulative percentages Page 117 of 153 retained on the following I.S. sieve sizes (4.75 mm, 2.36 mm, 1.18 mm, 600 micron, 300 micron and 150 micron) and dividing the sum by 100. 4.2.11 Storage of aggregates: All coarse and fine aggregates shall be stacked separately in stock piles in the material yard near the work site in bins properly constructed to avoid inter mixing of different aggregates. Contamination with foreign materials and earth during storage and while heaping the materials shall be avoided. The aggregate must be of specified quality not only at the time of receiving at site but also at the time of loading into mixer. Rakers shall be used for lifting the coarse aggregate from bins or stock piles. Coarse aggregate shall be piled in layers not exceeding 1.00 metres in height to prevent conning or segregation. Each layer shall cover the entire area of the stock pile before succeeding layers are started. Aggregates that have become segregated shall be rejected. Rejected material after re-mixing may be accepted, if subsequent tests demonstrate conformity with required gradation. 4.3 Cement 4.3.1 The cement generally used shall be the Ordinary Portland cement 43 / 53 grade or PPC. However, any special type of cement such as High strength cement or sulphate resisting cement may be used under specific circumstances. 4.3.2 Cement unless otherwise specified or called for by the Consultant shall be measured in 50 kg bags. Use of bulk cement will be permitted only with the approval of the Consultant. Changing of brands of type of cement within the same structure will not be permitted. Joint account of cement consumed at site for every day for items of work carried shall be maintained by the Contractor for verification to ensure effective control on quality of work. 4.3.3 A certified report attesting to the conforming of the cement to IS specifications by the cement manufacturer‟s chemist shall be furnished to the Consultant, if demanded. Should at any time the Consultant have reasons to consider that any cement is defective, then irrespective of its origin and / or manufacturers test certificate, such cement shall be tested immediately at a National Test Laboratory / Departmental Laboratory or such approved laboratory, and until the results of such tests are found satisfactory, it shall not be used in any work. Cement held in store for a period of ninety (90) days or longer shall be retested before use in work. 4.3.4 The contractor shall make his own arrangements for the storage of adequate quantity of cement. If supplies are arranged by the Department, cement will be issued in quantities to cover work requirements of one month or more, as deemed fit by the Consultant and it will be the responsibility of the contractor to ensure adequate and proper storage, which will provide complete protection from dampness, contamination and minimize caking and false set. Cement bags shall be stored in a dry enclosed shed (storage under tarpaulins will not be permitted), well away from the outer walls and insulated from the floor to avoid contact with moisture from ground and so arranged as to provide ready access. Damaged or reclaimed or partly set cement will not be permitted to be used and shall be removed from the site. The storage arrangements shall be such that there is no dead storage. No more than 12 bags shall be stacked in any tier. The storage arrangement shall be got approved by the Consultant. Consignments in cement shall be stored as received and shall be consumed in the order of their delivery. Page 118 of 153 4.4 Reinforcement 4.4.1 Steel reinforcement bars for concrete shall be either cold twisted high yield strength deformed bars conforming to IS 1786 or TMT bars with strength requirements conforming to IS 1786 manufactured by SAIL, TATA or RINL. The grade of steel shall be as shown in the drawings, or as mentioned in the schedule of items or as directed by Consultant. 4.4.2 Storage: Steel reinforcement shall be stored in such a manner that they are not in direct contact with ground but stacked on top of an arrangement of timbers sleepers or the like. Bars of different classifications and sizes shall be stored separately. In cases of long storage or in coastal areas, reinforcement shall be stacked above ground level by at least 15 cm, and a coat of cement wash shall be given to prevent scaling and rusting at no extra cost to the owner. Fabricated reinforcement shall be carefully stored to prevent, distortion, corrosion and deteriorations. 4.4.3 Contractor shall submit the manufacturers test certificate for steel. Random tests on steel supplied by contractor may be performed if the Consultant so desires as per relevant Indian Standards. All costs incidental to such tests shall be at contractors expense. Steel not conforming to specifications shall be rejected. 4.5 4.5.1 Water Water used for mixing and curing shall be clean and free from injurious amounts of oils, acids, alkalis, sugar, organic materials or other substances that may be deleterious to concrete or steel. Potable water is generally considered satisfactory for mixing concrete. The maximum permissible values of impurities shall be as given in clause no. 5.4 of lS:456. 4.5.2 In case of doubt regarding development of strength, the suitability of water for making concrete shall be ascertained by the compressive strength and initial setting time tests specified in lS:456. 4.5.3 Average 28 days compressive strength of atleast three 150 mm concrete cubes prepared with water proposed to be used shall not be less than 90% of the average strength of three similar concrete cubes -prepared with distilled water. The cubes shall be prepared, cured and tested in accordance with IS:456. 4.5.4 The initial setting time of a concrete test block made with the appropriate cement and the water proposed to be used shall not be less than 30 minutes and shall not differ by + 30 minutes from the initial setting time of control test block prepared with the same cement and distilled water. The test shall be carried out as per IS:4031. 4.5.5 Where concrete, made from water, proposed to be used does not satisfy the above requirements and/or contains an excess of acid, alkali, sugar, salt or other deleterious, substances, then the Consultant may refuse to permit its use. Sea water shall not be used for curing and mixing in concrete. Page 119 of 153 4.5.6 Testing of water shall be done at intervals indicated by Consultant. The sample of water taken for testing shall be typical of the water proposed to be used for concreting, due account being paid to seasonal variation. The samples shall not receive any treatment before testing other than that envisaged in the regular supply of water proposed for use in concrete. The sample shall be stored in a clean container previously rinsed out with similar water. The following concentrations represent the maximum permissible values. a) Limits of acidity : To neutralize 200 ml sample of water, using phenolphthalein as an indicator, it should not require more than 2 ml of 0.1 normal NaOH. The details of test shall be as given in IS: 3025 (Part 22). b) Limits of alkalinity : To neutralize 200 ml sample of water, using methyl orange as an indicator, it should not require more than 10ml of 0.1 normal HCL. The details of test shall be as given in IS : 3025 (Part 23). c) Percentage of solids shall not exceed the following : Organic 0.02% (200 mg/litre) Inorganic 0.30% (3000 mg/litre) Sulphates (as SO4) 0.05% (500 mg/litre) Alkali chlorides (as cl) 0.20% (2000 mg/litre) for plain concrete work & 0.10% (1000 mg/litre) for reinforced concrete work Suspended matter 0.20% (2000 mg/litre) 4.6 Admixtures 4.6.1 Admixtures in concrete for promoting workability, entraining air for similar purposes may be used only after the written permission from the Consultant is obtained. These shall be free from injurious amount of chloride, etc. Addition of admixtures should not reduce the specified strength or durability of concrete and should not have detrimental effect on reinforcement. The admixtures shall conform to lS:9103 and shall be of proven make and from a reputed manufacturer. Calcium chloride as accelerating admixture is not permitted to be used other than in mass concrete works. The Contractor shall produce latest test results carried out at approved Government Test Houses for the approval of the Consultant, before use. 4.7 Embedded parts 4.7.1 Steel for light structural work and for preparation of inserts and embedments shall conform to IS:2062. Page 120 of 153 4.7.2 Bolts to be embedded in concrete shall, unless otherwise detailed in drawings, conform to IS:5624. Material for bolts, shall, unless otherwise mentioned in drawings or the schedule of items, be corrosive resistant/coated steel conforming to IS:2062. 4.7.3 Nuts and locknuts shall conform to IS:1363 (Part 1 to 3) for diameters 6 to 39 and IS 3138 for Hexagon Bolts and Nuts (M-42 to M-150)”. 4.7.4 Plain washers shall conform to IS:2016 and spring washers shall conform to IS:3063. 4.7.5 Steel pipe sleeves shall conform to Medium class of IS: 1161. 4.8 Filling material 4.8.1 General: Filling material shall conform to what is shown in drawing, described in the Schedule of Items or otherwise directed by the Consultant. Earth or sand for filling under floors shall correspond to those described elsewhere in these specification. 4.8.2 Mastic Bitumen: Mastic Bitumen shall conform to IS: 3037 or IS: 5871 as appropriate. 4.8.3 Flexible Boards: Flexible boards for use in expansion joints shall correspond to the description given in drawing or the Schedule of Items or the instruction of Consultant. 5.0 GRADES OF CONCRETE 5.0.1 Concrete shall be in grades as tabulated below: Grade Designation Specified Characteristic compressive strength at 28 days (N/mm2) M10 10 M15 15 M20 20 M25 25 M30 30 M35 35 M40 40 Page 121 of 153 5.0.2 The characteristic strength is defined as the strength of material below which not more than 5% of the test results are expected to fall. 5.0.3 In the designation of a concrete mix, latter M refers to the mix and the number to the specified characteristic compressive strength of 15 cm cubes at 28 days. 5.0.4 Minimum grades of concrete to be followed shall be as per guidelines of Table 5 of IS: 456 unless otherwise mentioned in the drawings/ schedule of items. Concrete leaner than those given above may be used for lean concerte, mudmat, or for foundations of masonry walls. 5.1 Concrete mix proportioning 5.1.1 Concrete mix proportions shall be selected based on the requirements of workability, strength, and durability. The proportions of cement, aggregates and water shall be determined either by designing the mix only. Adopting nominal mix is limited to leveling courses only. Design mix concrete is designated as M20, M25, etc. and Nominal mix Concrete is designated as 1:2:4, 1:3:6, 1:4:8 or 1:5:10. The proportions referred to is by weight (mass) and not by volume. Use of volumetric mix concrete shall not be permitted. 5.1.2 Workability of concrete a) Workability of fresh concrete is mainly governed by placing conditions and compaction. The degree of workability necessary to allow the concrete to be well compacted and to be worked into the corners of formwork and around the reinforcement shall be as stipulated under clause no. 7.0 of IS:456. b) The workability of concrete shall be checked at frequent intervals. The workability of concrete measured in accordance with IS:1199 for every sample taken for testing shall be recorded with the corresponding cube test result. c) Not withstanding the above, the slump to be maintained for work in progress shall be as per directions of the Consultant. d) Consultant may permit use of plastisizers for improving workability. Use of certain other admixtures such has water proofing compounds also have an effect on workability and shall be considered during mix design. 5.1.3 Durability of concrete: Page 122 of 153 a) The durability of concrete is mainly governed by the permeability of concrete. Dense concrete is least permeable. In addition, cement content and water-cement ration and compaction of concrete play a major role in producing impermeable concrete. b) Durability requirements is decided depending on the exposure conditions as stipulated in clause 8.2 of IS 456. is to be taken into account while designing the mix. For given aggregates, the cement content should be sufficient to make sufficiently low water cement ratio and table 5 of IS: 456-2000 shall be taken as guideline for durability considerations. c) Stipulations of minimum cement content and limiting water cement ratio should be considered during design of mix. 5.1.4 Design Mix Concrete a) Design Mix Concrete shall be used for all reinforced concrete works. The mix proportions shall be as per mix design, designed for each grade of concrete, workability and durability requirements. The characteristic strength shall not be less than the appropriate values given in Table-2 of IS:456:2000. b) In proportioning concrete, the quantity of both cement and aggregates shall be determined by mass. Water shall be either measured by volume in calibrated tanks or weighed. All measuring equipment at site shall be maintained in a clean and serviceable condition, and their accuracy shall be periodically checked. c) To keep the water-cement ratio to the designed value, allowance shall be made for the moisture contents in both fine and coarse aggregates and determination of the same in accordance with lS:2386 Part (III) shall be made as frequently as directed by the Consultant.. d) With the permission of the Consultant, for any of the above mentioned grades of concrete, if the water quantity has to be increased, proportionately cement quantity shall also be increased, to keep the ratio of water to Cement same as adopted in mix design for the corresponding grade of concrete. The extra cement required on account of this shall be at no extra cost to Owner. e) At the beginning of the project, if so desired by the contractor, he/they may be allowed by the Consultant , till the designed mix is obtained, to carry out the reinforced concrete work in foundation and plinth as per equivalent nominal mix against the specified design mix concrete as per IS codes. However, all other specification for design mix shall govern for nominal mix also and nothing extra shall be paid for use of extra cement or else on this account whether the cement is supplied by the Owner or procured by the contractor. 5.1.5 Mix design: Mix design shall generally be done at any of the approved laboratory. The following is the guideline to be followed: Page 123 of 153 a) IS:10262 shall be followed as general guidance for mix design. The minimum value of target strength of design mix of various grades of concrete shall be as per clause no. 9.2 of IS:456. However, the Consultant may allow change in target strength values based on adequate numbers of works test results. b) Minimum cement content from durability consideration for different exposures and sulphate attack shall be as given in Table-4 and 5 of IS:456. In case higher value is obtained from strength consideration, same shall be provided. c) Preliminary tests/trial mix, as specified or as required by the Consultant, shall be carried out sufficiently ahead of the actual commencement of the work with different grades of concrete made from representative samples of aggregates and cement expected to be used on the works. These tests are to be conducted to arrive at the grading of aggregates, water-cement ratio, workability and the quantity of cement required to give Preliminary (target) compressive strengths as specified in clause 9.2 of IS 456. d) At least four trial mixes are to be made and minimum six test cubes taken for each trial mix noting the slump for each type of mix. The cubes shall then be properly cured and three cubes for each mix shall be tested in a laboratory (approved by the Consultant) at 7 days and others at 28 days for obtaining the compressive strength. The test reports shall be submitted to the Consultant. The design mix particulars shall indicate, with the help of graphs and curves etc. the extent of variation in the grading of aggregates which can be allowed. While designing mixes, over wet mixes shall be avoided. For the structures, where assessment of early strength is required the concrete cubes shall also be tested for early age strength at 1 day and 3 days for establishing the values. d) The Contractor shall submit the test reports of mix design to the Consultant for his review, indicating design criteria, analysis and proportioning of materials, etc. On the basis of the above test reports, a mix proportion by mass and the water-cement ratio, shall be determined by the Contractor such that concrete prepared with this mix will yield the desired characteristic strength and shall have suitable workability. The mix design to be adopted on the works shall be subject to the approval of the Consultant. The proportions, once decided for different grades of concrete, shall be adhered to, during all concreting operations as long as the quality of the materials does not change. If, however, at any time, the quality of materials being used has changed from those for Preliminary mix design, or there is a change either in the required strength of concrete, or water-cement ratio or workability, the Contractor shall have to make similar trial mixes and Preliminary tests to ascertain the revised mix proportions and watercement ratio to be used for obtaining the desired strength and consistency. e) The entire cost of all the trial mixes including all the preparatory works for trial mixes, preparation of test cubes and their testing shall be borne by the Contractor. 5.1.6 Nominal mix Concrete Page 124 of 153 a) Nominal mix concrete shall be used only for plain cement concrete works and where shown on drawings or specifically allowed by the Consultant. Such concrete shall not require preparation of trial mixes and all such concrete shall be mixed in a mechanical mixer. Proportions for nominal mix concrete shall be according to Table-9 of IS:456. b) The proportion of mix may be slightly adjusted within limits, keeping the total value of aggregates to a given quantity of cement constant to suit the sieve analysis of both the aggregates. Cement shall on no account be measured by volume, but it shall always be used directly from the bags (i.e. 50 kg/bag). The proportion of cement, sand, aggregate and water for concrete of proportion 1:5:10, 1:4:8, 1:3:6 & 1:2:4 by volume shall generally consist of quantities as given below : Quantity of materials used per bag of cement Proportion of Ingre c) Cement Fine aggregate (sand) Coarse aggregate Total of fine and coarse aggregates Water 1:5:10 1 170 kg. 340 kg. 800 kg. 60 ltrs. 1:4:8 1 130 kg. 272 kg. 625 kg. 45 ltrs. 1:3:6 1 102 kg. 204 kg. 480 kg. 34 ltrs. 1:2:4 1 68 kg 136 ltrs. 350 kg. 32 ltrs. The quantity of water used shall be such as to produce concrete of consistency required by the particular class of work and shall be decided by the use of slump cone. Sufficient care should be taken to see that no excess quantity of water is used. The final proportion of the aggregate and quantity of water shall be decided by the Consultant on the basis of test in each case. The for each class of work shall in general be as follows: Type of concrete Max slump (in mm) Mass concrete 50 Concrete below water proofing treatment 50 Coping 25 Floor paving 50 Page 125 of 153 d) As a general guidance the Nominal mix concrete of mix proportion 1:5:10 shall approximately correspond to grade M5, 1:4:8 shall correspond to grade M7.5, 1:3:6 to grade M10 and 1:2:4 to grade M15 of IS:456. e) If fine aggregates are moist, the amount of surface water shall be determined. Also an allowance shall be made for bulking in case of volume batching, in accordance with IS:2386 (Part-Ill). Allowance shall also be made for surface water present in the aggregates, when computing the water requirement. In the absence of exact data the amount of surface water may be estimated as follows: Aggregate Very wet sand Moderately wet sand Moist sand Moist gravel or crushed rock Approximate quantity of surface water Percentage by mass l/ cum 7.5 120 5.0 80 2.5 40 1.25-2.5 20-40 f) If nominal mix Concrete made in accordance with specified proportions does not yield the specified strength of the corresponding grade and fails to satisfy the requirements of “acceptance criteria for concrete” as specified in IS:456, such concrete shall be treated in the following manner: i) In case the Consultant is satisfied that lower strength of concrete is attributed to material and workmanship of the Contractor, then such concrete shall be replaced by concrete of specified strength. The Consultant may, however, also accept such lower strength concrete but such lower strength concrete shall be classified as belonging to the appropriate lower grade proportion. ii) In case the Consultant is satisfied that lower strength of concrete is not attributable to the Contractor, he may direct in writing to increase the cement content to obtain specified strength at no extra cost to Owner. The use of richer mix shall be continued until the Consultant instructs otherwise. g) Nominal mix proportion shall not be classified as higher grade proportion either on the ground that the test strengths are higher than the minimum specified or in the case where the Consultant directs use of additional cement over the quantity specified for the particular mix proportion to achieve the minimum specified strength. h) However, only in some exceptional cases including concreting in some isolated areas, the Consultant may allow the quantity of aggregates to be determined by an equivalent volume basis after the relationship between weight and volume is well established by trials and the same shall be verified frequently. Page 126 of 153 SPECIAL CONDITIONS OF CONTRACT Page 127 of 153 1.0 GENERAL 1.1 Special Conditions of Contract (SCC) shall be read in conjunction with the General Conditions of Contract (GCC) also referred to as General Terms & Conditions of Works Contract, Schedule of Quantities, specifications of work, drawings and any other document forming part of this Contract wherever the context so requires. 1.2 Notwithstanding the sub-division of the document into these separate sections and volumes, every part of each shall be deemed to be supplementary of every other part and shall be read with and into the Contract so far as it may be practicable to do so. 1.3 Where any portion of the GCC is repugnant to or at variance with any provisions of the Special Conditions of Contract, then unless a different intention appears, the provision(s) of the Special Conditions of Contract shall be deemed to override the provision(s) of GCC only to the extent that such repugnancy or variations in the Special Conditions of Contract are not possible of being reconciled with the provisions of GCC. 1.4 Wherever it is stated in this Bidding Document that such and such a supply is to be affected or such and such a work is to be carried out, it shall be understood that the same shall be affected and /or carried out by the Contractor at his own cost, unless a different intention is specifically and expressly stated herein or otherwise explicit from the context. Contract Price shall be deemed to have included such cost. 1.5 The materials, design & workmanship shall satisfy the applicable relevant Indian Standards, the job specifications contained herein & codes referred to. Where the job specifications stipulate requirements in addition to those contained in the standard codes and specifications, these additional requirements shall also be satisfied. In the absence of any Standard / Specifications / Codes of practice for detailed specifications covering any part of the work covered in this bidding document, the instructions / directions of Engineer-in-Charge will be binding upon the Contractor. 1.6 In case of contradiction between relevant Indian standards, GCC, Special Conditions of Contract, Specifications, Drawings and Schedule of Rates, the following shall prevail in order of precedence. i) ii) Detailed Purchase Order along with Statement of Agreed Variations, if any, and its enclosures . Fax of Intent (FOI)/Letter of Intent(LOI) Page 128 of 153 iii) iv) v) vi) vii) viii) Schedule of Quantities AND Technical specifications Special Conditions of Contract Drawings/data sheets/job procedures Instructions to Bidders General Conditions of Contract Relevant Indian Standards. 1.7 SAFETY, FIRE FIGHTING AND SPECIFIC REQUIREMENTS OF HPCL 1.7.1 Contractor shall provide adequate number of standard lengths of IS Stamped Fire hoses, IS Stamped DCP Fire extinguishers, fire buckets with sand and nozzles. These items can be taken back by the Contractor after completion of work. Sand shall also be maintained dry by the Contractor with fresh supply, whenever required. Work permit may not be issued by HPCL in the absence of above items. 1.7.2 Safety Helmets shall be provided to all the employees of Contractor including that of his labour contractors. 1.7.3 Safety Belts and Harnesses shall be provided by the Contractor in adequate number for the workers working at heights. 1.7.4 Proper earthing shall be provided for all equipments and generators. 2.0 THE WORK 2.1 Scope of Work & Scope of Supply 2.1.1 2.2 The scope of work and Scope of Supply covered in this Contract will be as described in Scope of work provided in the Instructions to bidders, Schedule of Quantities, Technical Specifications, Drawings, etc. Time Schedule The Completion period for this job shall be 4 (FOUR) Months from the date of LOI. 2.2.1 Time is the essence of this Contract. The period of completion given includes the time required for mobilization as well as testing, rectifications, if any, retesting, demobilization and completion in all respects to the satisfaction of the Engineerin-Charge. 2.2.2 A joint program of execution of work will be prepared by the Engineer-in-Charge and Contractor. This program will take into account the time of completion period of the Contract. Page 129 of 153 2.2.3 Monthly execution program will be drawn up by the Engineer-in-Charge jointly with the Contractor based on availability of materials, work fronts and the joint program of execution as referred to above. The Contractor shall scrupulously adhere to the Targets / Program by deploying adequate personnel, Construction Equipment, Tools and Tackles and also by Timely Supply of required materials coming within his scope of supply as per Contract. In all matters concerning the extent of target set out in the monthly program and the degree of achievement, the decision of the Engineer-in-Charge will be final and binding upon the Contractor. 2.2.4 Contractor shall give every day category-wise labour and equipment deployment report along with the progress of work done on previous day in the proforma prescribed by the Engineer-in-Charge. 2.3 Measurement of Works 2.3.1 Mode of measurement will be as specified in Specifications or SOR. 2.4 Payment Terms 2.4.1 Payment will be released within 15 days of submission of duly certified Running Account Bills at Disbursement section at Mumbai after deduction of WCST(Works Contract Sales Tax) or VAT whichever is applicable, IT(Income Tax) and any other statutory deduction as applicable from time to time, Any MRR(Materials Received Report- An internal document forwarded by HPCL Site –in-Charge/ Engineer to Disbursement Section along with Contractor‟s Bill and duly certified measurement sheets for release of payment) Deductions, LD, etc. In case of Final Bill, Payment will be released within 45 days of submission of duly certified Final Bill along with all requisite documents, drawings, etc. Payment break up for various items covered in SOR/PRICED BID is as indicated as Appendix 1 to SCC. No further alteration is permitted in approved payment break up. 2.5 Temporary Works 2.5.1 All temporary works, enabling works, including dewatering of surface and subsoil water, preparation and maintenance of temporary drains at the work site, preparation and maintenance of approaches to working areas, adequate lighting, wherever required, for execution of the work, shall be the responsibility of the Contractor and all costs towards the same shall be deemed to have been included in the quoted prices. 2.6 Quality Assurance Page 130 of 153 2.6.1 Detailed quality assurance programme to be followed for the execution of Contract under various divisions of works will be mutually discussed and agreed to. 2.6.2 The Contractor shall establish, document and maintain an effective quality assurance system as outlined in the specifications and various codes and standards. 2.6.4 2.6.4 The Owner/Consultant or their representative shall reserve the right to inspect/witness, review any or all stages of work at shop/site as deemed necessary for quality assurance and / or timely completion of the work. In case Contractor fails to follow the instructions of Engineer-in-Charge with respect to above clauses, next payment due to him shall not be released unless and until he complies with the instructions to the full satisfaction of Engineer-inCharge 2.7 Leads 2.7.1 For the various works, in case of contradiction, leads mentioned in the Schedule of Quantities shall prevail over those indicated in the Technical specifications. 3.0 ROYALTY, INCOME TAX, SERVICE TAX AND PRICES 3.1 Royalty 3.1.1 All royalties etc., as may be required for any Borrow Areas, including right of way etc., to be arranged by Contractor shall be deemed to have been included in the quoted prices. 3.1.2 Contractor‟s quoted rates should include the royalty on different applicable items as per the prevailing State Government rates. In case, Owner is able to obtain the exemption of royalty from the State Government the Contractor shall pass on the same to Owner for all the items involving royalty. Any increase in prevailing rate of royalty shall be borne by the Contractor at no extra cost to the Owner. 3.2 Income Tax 3.2.1 Income Tax at the prevailing rate as applicable from time to time shall be deducted from Contractor‟s Bills as per Income Tax Act and quoted rates shall be inclusive of this. Owner will issue the TDS (Tax Deduction at Source) Certificate. Firm Prices 3.3 3.3.1 The contract price shall remain firm and fixed till the completion of work in all respects and no escalation in prices on any account shall be admissible to the Contractor except for statutory variations as per General Terms and Conditions (GTC). Page 131 of 153 4 4.1 PROVIDENT FUND,LABOUR, LABOUR LAWS AND SITE REQUIREMENTS Provident Fund 4.1.1 The Contractor shall strictly comply with the provisions of Employees Provident Fund Act and register himself with Regional Provident Fund Commissioner (RPFC) before commencing work. The Contractor shall deposit Employees and Employers contributions to the RPFC every month. The Contractor shall furnish along with each Running bill, the challan / receipt for the payment made to the RPFC for the preceding month. The Contractor shall furnish the code number allotted by the RPFC Authority to the Engineer-in-Charge before commencing the work. 4.1.2 In case the RPFC challan / receipt, as above, is not furnished, Owner shall deduct 16% (sixteen percent) of the payable amount from Contractor‟s running bill and retain the same as a deposit. Such retained amounts shall be refunded to Contractor on production of RPFC Challan / receipt for the period covered by the related running bill. 4.2 Labour License 4.2.1 Before starting of work, Contractor shall obtain a license from concerned authorities under the Contract Labour (Abolition and Regulation) Act 1970, and furnish copy of the same to Owner. 4.3 Labour Relations 4.3.1 In case of labour unrest/labour dispute arising out of non-implementation of any law, the responsibility shall solely lie with the Contractor and they shall remove/resolve the same satisfactorily at his cost and risk. 4.3.2 The Contractor shall at all times take all reasonable precautions to prevent any unlawful, riotous or disorderly conduct by or amongst his staff and labour and to preserve peace and protection of persons and property in the neighbourhoods of the Works against such conduct. 4.4 4.4.1 Employment of Local Labour The Contractor shall ensure that local labour skilled and / or unskilled, to the extent available shall be employed in this work. In case of non – availability of suitable labour in any category out of the above persons, labour from outside may be employed. Page 132 of 153 4.4.2 The Contractor shall not recruit personnel of any category from among those who are already employed by other agencies working at site but shall make maximum use of local labour available. 4.5 Site Cleaning 4.5.1 The Contractor shall clean and keep clean the work site from time to time to the satisfaction of the Engineer-in-Charge for easy access to work site and to ensure safe passage, movement and working. 4.5.2 The Contractor shall dispose off the unserviceable materials, debris etc., to the earmarked area within the premises or any other location outside the premises as decided by the Engineer-in-Charge. No extra payment shall be paid on this account. 4.5.3 Review/Approval of Drawings, Design and other documents submitted by Contractor 4.5.3.1 HPCL/consultant will normally require and utilize a maximum time frame of seven (07) working days from the date of Receipt for Review/Approval of Drawings, Design and other documents submitted by Contractor. Upon Review of the submitted documents, HPCL may give their comments and ask for redesign/ resubmission after necessary rectifications/ modifications and the time frame of 7 working days will be applicable for same. 4.6 Protection of Existing Facilities 4.6.1 Contractor shall obtain all clearance (work permit) from the Owner, as may be required from time to time, prior to start of work. Work without permit shall not be carried out within the existing premises. 4.6.2 Contractor shall obtain plans and full details of all existing and planned facilities/services/utilities from the Owner and shall follow these plans closely at all times during the performance of work. Contractor shall be responsible for location and protection of all facilities/utilities and structures at his own cost. 4.6.3 Despite all precautions, should any damage to any structure / utility etc. occur, the Contractor shall contact the Owner / authority concerned and Contractor shall forthwith carry out repair at his expenses under the direction and to the satisfaction of Engineer-in-Charge and the Owner/concerned authority. 4.6.4 Contractor shall take all precautions to ensure that no damage is caused to the existing facilities etc., during construction. Existing structures/facilities/utilities damaged / disturbed during construction shall be repaired and restored to their Page 133 of 153 original condition by Contractor after completion of construction to the complete satisfaction of Owner. 4.7 Work Front 4.7.1 The work involved under this Contract may include such works as have to be taken up and completed after other agencies have completed their jobs. The Contractor will be required and bound to take up as and when the fronts are available for the same and no claim of any sort whatsoever shall be admissible to the Contractor on this account. Only extension of time limit shall be admissible, if the availabilities of work fronts to the Contractor are delayed due to any reason not attributable to the Contractor and the same is clearly recorded. 4.8 Site Facilities 4.8.1 The Contractor shall arrange for the following facilities at site, for workmen deployed/engaged by him / his sub-contractor, at his own cost: i) ii) iii) iv) 4.9 Arrangement for First Aid. Arrangement for clean & potable drinking water. A crèche where 10 or more women workers are having children below the age of 6 years. Any other facility/utility as may be required under the Contract as per the existing legislation/regulations. Contractor’s Site Office and Stores 4.9.1 Owner shall provide land only for contractor‟s site office and stores and fabrication yard, if any at site. However, same shall be dismantled prior to submission of Final Bill. 4.9.2 The Contractor shall remove all temporary buildings / facilities etc., before leaving the site after completion of works in all respect. 4.10 4.10.1 Construction Power and Water Owner shall not provide power and the Contractor shall be exclusively responsible to make his own arrangements for supply of power, without any extra cost to the Owner. 4.10.2 Water required for the works shall be arranged by the Contractor. The contractor has to make all necessary arrangement for drawing water including making temporary storage, pumping etc. Page 134 of 153 4.10.3 CEMENT : Cement required for execution of the job under the entire scope of work ( other than for Ready Mix Concrete where the cement is from the RMC manufacturer scope ) contained in this tender shall be supplied at provided at site by the contractor at his own cost. Contractor to include the cost of cement required for execution of various items included in this tender in their quoted rates. Cement shall be of 43 / 53 Grade PPC as specified in the technical specifications of Ultra Tech Cement/ Gujarat Ambuja / ACC / Birla/Lafarge Makes only and shall conform to IS relevent standards of latest edition.. Contractor to produce Invoice Copy of every batch of cement procured at site to EIC. However, HPCL‟s decision with regard to the specific brand of cement to be procured for the execution of the work shall be final and binding on the contractor. Cement shall be procured and brought to site atleast 15 days in advance. Sample from every batch of cement brought to site shall be tested for standard test as per the specification of relevant IS standards in approved Laboratory and Test Certificate shall be submitted to EIC for verification. Only after obtaining approval of EIC, cement shall be put into use. Manufacturer‟s Batch Test Certificates backed by Factory‟s Invoice for the batch will also be acceptable for approval of cement. Contractor shall bring cement well in advance before full consumption of previous lot. No claims for extension of completion period for stoppage of work on account of non-availability of cement / delays is testing procedures will be entertained/accepted by HPCL. For all computation purposes, the theoretical cement consumption shall be considered as per CPWD standards. Cement cost shall be recovered for under-consumption at the penal rate of Rs.7000/- per MT. Empty cement bag shall be the property of the contractor. Theoretical weight of cement in a bag will be considered as 50 Kgs. Bags weighing upto 4% less shall be accepted by HPCL. Any shortage in weight of any cement bag by more than 4% will be to contractor‟s account. Contractor shall maintain necessary weighing scale at site for the purpose of random checking of the weight of cement bags by representative of HPCL. The contractor will be required to maintain a stock register for receipt, issuance and daily consumption of cement at site. Cement shall be regulated on the basis of 1st receipt to go as 1st issue. Cement not consumed within 3 months after bringing to site shall not be used and shall be removed from site with prior written permission of EIC. All RA bills including the final bills will be accompanied by Cement Consumption Statements giving the detailed working of cement used. Contractor shall construct suitable temporary godown at site for storage of cement under his lock and key. The contractor will be fully responsible for safe custody of cement. HPCL will not entertain any claims by the Contractor for theft, loss or damages to cement. Contractor shall not remove from the site any cement bags at any time. Permissible wastage shall be total 3% of the theoretical consumption. However, these wastage shall be considered in excess of the theoretical quantity required for the various Page 135 of 153 items of work. No extra payment will be made towards this wastage and the same will be in the contractor‟s account. The contractor shall be penalised for any under-consumption of cement at the rate of Rs7000/- per MT. 4.10.4 STEEL : Entire quantity of reinforcement / structural steel required for the project shall be supplied and provided at site by the contractor at his own cost. Contractor to include the cost of steel reinforcement / structural steel required to be used against various items of this scope of work in their quoted rates. HPCL shall not supply any reinforcement / structural steel. The contractor shall make necessary arrangement at his own cost for unloading, storage of steel in the open duly fenced under locking arrangement. The reinforcement steel shall be procured from Tata/SAIL/Vizag Steel only as per SOR & technical specifications and will produce invoice for the same to EIC for every batch of procurement along with Manufacturer‟s Test Certificate. In the case of steel reinforcement or structural steel the theoretical quantity of steel shall be taken as the quantity required as per design or as authorised by Architect/Consultant /HPCL‟s Engineer including authorised lap lengths/chairs etc. No further claim towards additional wastage due to lap length / full length bars or other consideration including rolling margin will be entertained. No payment will be made or measurement recorded for binding wires which shall be of 18 SWG gauge and shall be provided by the contractor. For the purpose of dealing and accounting, only linear measurements will be taken and any difference in weight based on linear measurement and actual weight shall be to contractor‟s account. Quoted rate shall be deemed to include the above and the wastage mentioned below. No claim whatsoever shall be entertained on account of wastage and difference in weight as referred to above. All binding wires required for tying the reinforcement in position etc. will be supplied by the contractor. Cost of this binding wire and labour will be included in the item for binding and placing reinforcement in position. It will be necessary that the contractor get the steel tested at his own cost at a Govt. approved laboratory as per the testing schedule or as per the EIC‟s advise, for strength and other properties specified in IS – 1786 latest editioin before using it in the work. The contractor will be required to maintain a register for recording details of steel receipt, steel utilised and balance at site. Final bill will be accompanied by steel consumption statement. In every case, it shall be the contractor‟s responsibility to ensure the standard of quality and the correctness of quantity of steel procured at site by him. The permissible wastage (wastage defined as bars having less than 3 mt. Length) shall be of 3% of theoretical consumption. Recovery for less consumption as per theoretical consumption will be recovered at Rs.50,000/- per MT. All scrap (scrap defined as pieces Page 136 of 153 of steel bars measuring less than 3 mt. in length) shall be the property of the contractor. The wastage quantity shall not be considered to be included within the theoretical quantity and no extra shall be payable on account of wastage. 4.11 Construction 4.11.1 Rules and Regulations 4.11.2 Contractor shall observe in addition to Codes specified in respective specification, all national and local laws, ordinances, rules and regulations and requirements pertaining to the work and shall be responsible for extra costs arising from violations of the same. 5.0 Procedures 5.1 Various procedures and method statements to be adopted by Contractor during the construction as required as per the respective specifications shall be submitted to Engineer-in-Charge in due time for approval. 5.2 Security 5.2.1 As the premises will be protected area, entry into the area shall be restricted and may be governed by issue of photo gate passes. The Contractor shall arrange to obtain through the Engineer-in-Charge, well in advance, all necessary entry permits/gate passes for his staffs and labourers and entry and exit of his men and materials shall be subject to vigorous checking by the security staff. The Contractor shall not be eligible for any claim or extension of time whatsoever on this account. 5.2.2 It shall be the responsibility of the contractor to safeguard all his materials/owned from theft, damage etc. For this purpose the contractor shall be allowed to keep his own security inside HPCL premises 5.3 Drawings and Documents 5.3.1 Drawings accompanying the Bidding Document are indicative of scope of work and issued for bidding purpose only. Purpose of these drawings is to enable the bidder to make an offer in line with the requirements of the owner. 5.3.2 The contractor as per „scope of work‟ shall carry out preparation of detailed and working drawings. Detailed construction layout drawings as needed shall be prepared by contractor and got reviewed/approved by Engineer-in-Charge/Architect before taking up the work. Page 137 of 153 5.4 Rounding off 5.4.1 All payments to and recoveries from the Contractor shall be rounded off to the nearest rupee. Wherever the amount to be paid / recovered consists of a fraction of a rupee (paise), the amount shall be rounded off to the next higher rupee if the fraction consists of 50 (fifty) paise or more and if the faction of a rupee is less than 50 (fifty) paise, the same shall be ignored. 5.5 Contractor’s Billing System 5.5.1 HPCL will provide an approved format for Measurement sheets, Bill Summary and Bill Abstract. Contractor has to ensure that these data are updated for each subsequent RA and Final Bill. 5.5.1 HPCL will utilize these data for processing and verification Contractor‟s bill. 5.6 Site Organization 5.6.1 The Contractor shall without prejudice to his overall responsibility to execute and complete the works as per specifications and time schedule progressively deploy adequate qualified and experienced personnel together with skilled / unskilled manpower and augment the same as decided by Engineer-in-Charge depending on the exigencies of work to suit the construction schedule without any additional cost to Owner. 5.6.2 The Contractor shall provide all necessary superintendence during the execution of the Works and as long thereafter as the Engineer-in-Charge may consider necessary for the proper fulfilling of the Contractor‟s obligations under the Contract Such superintendence shall be given by sufficient persons having adequate knowledge of the operations to be carried out (including the methods and techniques required, the hazards likely to be encountered and methods of preventing accidents) for the satisfactory and safe execution of the Work. The workmen deployed by the Contractor should also possess the necessary license etc., if required under the existing laws, rules and regulations. 5.7 of the Additional / Extra Works Owner reserves the right to execute any additional works / extra works, during the execution of work, either by themselves or by appointing any other agency, even though such works are incidental to and necessary for the completion of works awarded to the Contractor. Page 138 of 153 5.8 Responsibility of Contractor 5.8.1 It shall be the responsibility of the contractor to obtain the approval for any revision and/or modifications decided by the contractor from the Owner / Engineerin-Charge before implementation. Also such revisions and / or modifications if accepted / approved by the Owner / Engineer-in-Charge shall be carried out at no extra cost to the owner. Any change required during functional requirements or for efficient running of system, keeping the basic parameters unchanged and which has not been indicated by the contractor in the data / drawings furnished along with the offer shall be carried out by the contractor at no extra cost to the owner. 5.8.2 All expenses towards mobilization at site and demobilization including bringing in equipment, work force, materials, dismantling the equipment, clearing the site etc. shall be deemed to be included in the prices quoted and no separate payments on account of such expenses shall be entertained. 5.8.3 It shall be entirely the contractor‟s responsibility to provide, operate and maintain all necessary construction equipment, steel scaffoldings and safety gadgets, cranes and other lifting tackles, tools and appliances to perform the work in a workman like and efficient manner and complete all the jobs as per time schedule. 5.8.4 Preparing approaches and working area for the movement of his men and machinery. 5.8.5 The procurement and supply in sequences and at the appropriate time of all materials, and consumables shall be entirely the contractor‟s responsibility and his rates for execution of work will be inclusive of supply of all these items. 5.9 Coordination with other agencies 5.9.1 Contractor shall be responsible for proper coordination with other agencies operating at the site of work so that work may be carried out concurrently, without any hindrance to others. The Engineer – in – Charge shall resolve disputes, if any, in this regard, and his decision shall be final and binding on the Contractor. 5.10 Underground and overhead structures 5.10.1 The Contractor will familiarize himself with and obtain information and details from the Owner in respect of all existing structures, and utilities existing at the job site before commencing work. The Contractor shall execute the work in such a manner that the said structures, utilities, etc. are not disturbed or damaged, and shall indemnify and keep indemnified the Owner from and against any destruction thereof or damages thereto. Page 139 of 153 5.11 Documents required with final bill 5.11.1 Statement of final bills – issue of No Claim/ No Due Certificate 5.11.2 The Contractor shall furnish a No-Claim/No-Due declaration indicating that there are no balance dues to his sub-vendor/sub-contractors/labour contractors along with the Final Bill. 5.12 Working hours 5.12.1 Depending upon the requirement, time schedule / drawing/ programme and the target set to complete the job in time, the works may also have to continue beyond normal working hours/night hours / holidays or during such periods with out causing any inconvenience to the neighbours/others with due permission from EIC, for which no extra claim shall be entertained. However for all such working contractor‟s responsible representative shall be available at site to receive the work permit to be issued by HPCL. With out responsible representative of the contractor, no work shall be allowed inside the premises. 6.0 TESTS, INSPECTION AND COMPLETION 6.1 Tests and Inspection 6.1.1 The Contractor shall carry out the various tests as enumerated in the technical specifications of this Bidding Document and technical documents that will be furnished to him during the performance of the work at no extra cost to the Owner. 6.1.2 All the tests either on the field or at outside laboratories concerning the execution of the work and supply of materials by the Contractor shall be carried out by Contractor at his cost. 6.1.3 The work is subject to inspection at all times by the Engineer-in-Charge. The Contractor shall carry out all instructions given during inspection and shall ensure that the work is being carried out according to the technical specifications of this bidding document, the technical documents that will be furnished to him during performance of work and the relevant codes of practice. 6.1.4 Compressed air for carrying out works ,if required shall be arranged by the Contractor at his own cost. 6.1.5 For material supplied by Owner, Contractor shall carry out the tests, if required by the Engineer-in-Charge, and the cost of such tests shall be reimbursed by the Owner at actual to the Contractor on production of documentary evidence. Page 140 of 153 6.1.6 6.2 All results of inspection and tests will be recorded in the inspection reports, proforma of which will be approved by the Engineer-in-Charge. These reports shall form part of the completion documents. Any work not conforming to execution drawings, specifications or codes shall be rejected and the Contractor shall carry out the rectifications at his own cost. Final Inspection After completion of all tests as per specification the whole work w ill be subject to a final inspection to ensure that job has been completed as per requirement. If any defect is noticed, the Contractor will be notified by the Engineer-in-Charge and he shall make good the defects with utmost speed. If however, the Contractor fails to attend to these defects within a reasonable time (time period shall be fixed by the Engineer-in-Charge) then Engineer-in-Charge may have defects rectified at Contractor‟s cost. 6.3 Inspection of Supply Items 6.3.1 All inspection and tests on bought out items shall be made as required by specifications forming part of this contract. Various stages of inspection and testing shall be identified after receipt of Quality Assurance Programme from the contractor / manufacturer. 6.3.2 Inspection calls shall be given for association of Owner , as per mutually agreed programme in prescribed proforma , giving details of equipment and attaching relevant test certificates and internal inspection report of the contractor. All drawings, general arrangement and other contract drawings, specifications, catalogues etc. pertaining to equipment offered for inspection shall be got approved by Owner and copies shall be made available to Owner before hand for undertaking inspection. 6.3.3 The contractor shall ensure full and free access to the inspection engineer of Owner at the contractor‟s or their sub-contractor‟s premises at any time during contract period to facilitate him to carry out inspection and testing assignments. 6.3.4 The contractor / sub – contractor shall provide all instruments, tools, necessary testing and other inspection facilities to inspection engineer of Owner free of cost for carrying out inspection. 6.3.5 Where facilities for testing do not exist in the contractor‟s / sub-contractor‟s laboratories, samples and test pieces shall be drawn by the contractor / subcontractor in presence of Inspection Engineer of Owner and duly sealed by the later and sent for tests in Government approved test house or any other testing laboratories approved by the Inspection Engineer at the contractor‟s cost. Page 141 of 153 6.3.6 The contractor shall comply with the instructions of the Inspection Engineer fully and with promptitude. 6.3.7 The contractor shall ensure that the equipment / assemblies / component of the plant and equipment required to be inspected are not assembled or dispatched before inspection. 6.3.8 The contractor shall not offer equipment for inspection in painted conditions unless otherwise agreed in writing with the Owner . 6.3.9 The contractor shall ensure that the parts once rejected by the inspection engineer are not used in the manufacture of the plant and equipment. Where parts rejected by the inspection engineer have been rectified or altered, such parts shall be segregated for separate inspection and approval, before being used in the work. 6.3.10 On satisfactory completion of final inspection and testing, all accepted part of the work and equipment shall be stamped suitably and inspection certificate shall be stamped suitably and inspection certificate shall be issued in requisite copies for all accepted items. For stage inspection and for rejected items, only inspection memo shall be issued indicating therein the details of observations and remarks. 6.3.11 All inspections and tests shall be made as required by the specifications forming part of this contract. Contractor shall advise HPCL in writing at least fifteen days in advance of the date of final inspection / tests. Manufacturers inspection or testing certificate for equipment and materials supplied may be considered for acceptance, at the discretion of Engineer-in-Charge. All costs towards testing etc. shall be borne by the contractor within their quoted rates. 6.4 6.4.1 Documentation Completion Documents The following documents shall also be submitted by the Contractor in triplicate as part of completion documents : a) b) c) d) e) Test certificate for materials supplied by the Contractor. Certified records of field tests on materials / equipment, as applicable. Material appropriation statement as required. Six sets of drawings showing therein the as built conditions of the work duly approved by the Engineer-in-Charge along with one set of reproducible on polyester film (drawings prepared by Contractor) along with soft form of the same. Other documents as mentioned in Technical Specification. Page 142 of 153 6.4.2 “AS BUILT” Drawings Upon completion of work, the Contractor shall complete all drawings to “As built” status (including all vendor / Sub – vendor‟s drawings for bought out items) and provide the Owner, the following : a. b. 7.0 7.1 7.1.1 7.2 One complete set of all original tracings / reproducible along with the soft form of the same. Six complete sets of prints. OTHERS Dispute Settlement between Govt. Dept. / PSU & PSE In the event of any disputes or differences between the Contractor and the Owner, if the Contractor is a Government department, a Government company or an undertaking in the public sector, then such disputes or differences shall be resolved amicably by mutual consultation or through the good offices or empowered agencies of the Government. If such resolution is not possible, then the unresolved disputes or differences shall be referred to arbitration of an arbitrator to be nominated by the Secretary. Department of legal affairs (Law Secretary) in terms of the Office Memorandum No. 55 / 1 / 75 – CF dated 19th December 1975 issued by the Cabinet Secretariat (Dept. of Cabinet Affairs) as modified from time to time. The Arbitration Conciliation Act 1996 shall not be applicable to the arbitrator under this clause. The award of the arbitrator shall be binding upon parties to the dispute, provided, however any party aggrieved by such award may make a further reference for setting aside or revision of the award to Law Secretary whose decision shall bind the parties finally and conclusively. Project Scheduling and Monitoring 7.2.1 The following schedules / documents / reports shall be prepared and submitted by the CONTRACTOR for review / approval at various stages of the contract. 7.2.3 After placement of Purchase Order Upon placement of Purchase Order, Contractor has to furnish a detailed bar chart within 15 days of issue of FOI/LOI. 7.2.4 7.2.4.1 Project Review Meetings The CONTRACTOR shall present the programme and status at various review meetings as required. Page 143 of 153 Monthly Review Meeting Level of Participation: Senior Officers of Owner & Contractor. Agenda a)Progress Status/ statistics. b) Completion Outlook c) Major hold ups / slippages. . d) Assistance required. e) Critical issues. f) Client query / approval. Venue 7.2.5 : Site Progress Reports I) a) b) c) d) e) f) Monthly Progress Report This report shall be submitted in three copies on a monthly basis within Ten calendar days from cut-off date as agreed upon, covering overall scenario of the work. The report shall include but not be limited to the following : Brief introduction of the work. Activities executed / achievements during the month. Scheduled vs actual percentage progress and progress curves for subordering, manufacturing / delivery, sub-contracting, construction activities and overall quantum wise status of purchase orders against scheduled. Areas of concern / problems / hold ups, impact and action plans. Resource deployment status. Annexure giving status summary for Material Requisitions and deliveries, sub-contracting and construction Distribution: OWNER II) Two copies & One at Site. Daily Report: Daily report in duplicate as out lined in 2.2.4 of SCC and any other additional information/data/guideline/job procedure sought by Engineer-in-Charge shall be submitted without fail to HPCL at site by contractor. 7.3 General Environment Requirement The contractor has to ensure efficient use of natural resources like water, fuel oil and lubricants. The contractor should ensure proper awareness to workers to maintain a green and clean environment inside / outside the building premises. The contractor must collect and dispose of all the waste and scrap materials at the designated place only as directed by Engineer – in – Charge. Page 144 of 153 7.4 DEFECT LIABILITY PERIOD/Warranty Period As per clause No. 5n of GTC. 7.5 Form C/D etc will not be issued by M/s HPCL APPENDIX -1 TO SCC TERMS OF PAYMENTS 1.1 The basis and terms of payment without prejudice to any other mode of recovery available to Owner, shall be as given below : 1.2 The Contractor shall be paid monthly running account bills at stages of completion of individual item / work, based on the joint measurement, in the following manner after deductions of necessary dues payable by Contractor to the Owner such as Retention money, Taxes, Duties etc. in accordance with various provisions made elsewhere in this document. 1.3 SPECIAL PAYMENT TERMS Following payment shall be made to the contractor against the running bills subject to the rate awarded to him and the clause regarding retention money as per general terms and conditions. FOR ITEM NOS. 5, 6, 8, 12 TO 16, 18 TO 34, 70 TO 111, 117 TO 142, 147 TO 159, 168 & 169 70% against Supply 25% against installation & commissioning 5% after completion and acceptance by HPCL as per SOQ ALL OTHER ITEMS 95% progressively till completion of the concerned job 5% after completion and acceptance by HPCL as per SOQ NOTES : 1. For Each stage, necessary testing shall be completed prior to claiming the break-up as given above percentage 2. Partial bill will be processed only after submission of duly certified copy of proof of payment towards royalty. 3. Final bill will be processed only after submission of “No objection certificate” from relevant statutory authorities towards payment of royalty. Page 145 of 153 SAFETY, HEALTH AND ENVIRONMENT REQUIREMENTS Page 146 of 153 SAFETY , HEALTH & ENVIRONMENT POLICY SPECIFICATION FOR SAFETY HEALTH AND ENVIRONMENT (SHE) MANAGEMENT CONTENTS ________________________________________________________________________ CLAUSE NO. TITLE ________________________________________________________________________ 1.0 SCOPE 2.0 REFERENCES 3.0 REQUIREMENT OF SAFETY, HEALTH AND ENVIRONMENT (SHE) 4.0 3.1 MANAGEMENT RESPONSIBILITY 3.2 HOUSE KEEPING 3.3 SAFETY, HEALTH & ENVIRONMENT DETAILS OF SHE MANAGEMENT SYSTEM BY CONTRACTOR 4.1 ON AWARD OF CONTRACT 4.2 DURING JOB EXECUTION Page 147 of 153 1.0 SCOPE This specification establishes the Safety Health and Environment (SHE) management requirement to be complied with by the Contractors during construction. Requirements stipulated in this specification shall supplement the requirements of SHE Management given in relevant Act (s) / legislations. General Conditions of Contract (GCC), Special Conditions of Contract (SCC) and Job Specifications. Where different documents stipulate different requirements, the most stringent shall be adopted. 2.0 REFERENCES This document should be read in conjunction with following: - 3.0 General Conditions of Contract (GCC) Special Conditions of Contract (SCC) Job Specifications REQUIREMENTS OF SAFETY HEALTH & ENVIRONMENT (SHE) MANAGEMENT SYSTEM TO BE COMPLIED BY BIDDERS 3.1 MANAGEMENT RESPONSIBILITY 3.1.1 The Contractor should have a documented SHE policy to cover commitment of their organization to ensure health, safety and environment aspects in their line of operations. 3.1.2 The SHE management system of the Contractor shall cover the SHE requirements including but not limited to what is specified under Para 1.0 and para 2.0 above. 3.1.3 Contractor shall be fully responsible for planning and implementing SHE requirements. Contractor as a minimum requirement shall designate / deploy the following to co-ordinate the above : No. of workers deployed Up to 250 - Designate one safety supervisor Above 250 & up to 500 - Deploy one qualified and experienced safety Engineer / officer Page 148 of 153 Above 500 engineer/officer as above. - One additional safety (for every 500 or less) Contractor shall indemnify & hold harmless Owner / HPCL & either representatives free from any and all liabilities arising out of non – fulfillments of SHE requirements. 3.1.4 The Contractor shall ensure that the Safety, Health and Environment (SHE) requirements are clearly understood & faithfully implemented at all levels at site. 3.1.5 The Contractor shall promote and develop consciousness for Safety , Health and Environment among all personnel working for the Contractor. Regular awareness, program site meetings shall be arranged on SHE activities to cover hazards involved in various operations during construction. 3.1.6 Arrange suitable first aid measures such as First Aid Box, trained personnel to give First Aid, Stand by Ambulance or Vehicle and install fire protection measures such as : adequate number of steel buckets with sand and adequate fire extinguishers to the satisfaction of HPCL/Owner. 3.1.7 The Contractor shall evolve a comprehensive planned and documented system for implementation and monitoring of the SHE requirements. This shall be submitted to HPCL/Owner for approval. The monitoring for implementation shall be done by regular inspections and compliance to the observations thereof. The Contractor shall get similar SHE requirements implemented at his sub-contractor(s) work site/office. However, compliance of SHE requirements shall be the sole responsibility of the Contractor. Any review / approval by HPCL/Owner shall not absolve contractor of his responsibility / liability in relation to all HSE requirements. 3.1.8 Non-Conformance on SHE by Contractor (including his Sub-contractors) as brought out during review/audit by HPCL/Owner representatives shall be resolved forthwith by Contractor. Compliance report shall be provided to HPCL/Owner. 3.1.9 The Contractor shall ensure participation of his Resident Engineer / Site-in-Charge in the Safety Committee / SHE Committees meetings arranged by HPCL/Owner. The compliance of any observations shall be arranged urgently. He shall assist HPCL/Owner to achieve the targets set by them on SHE during the project implementation. 3.1.10 The Contractor shall adhere consistently to all provisions of SHE requirements. In case of non-compliance or continuous failure in implementation of any of SHE provisions; HPCL/Owner may impose stoppage of work without any Cost & Time implication to Owner and/or impose a suitable penalty for non-compliance with a notice of suitable period, up to a cumulative limit of 1.0% (one percent) of Contract Value with a maximum limit of Rs. 10 Page 149 of 153 lakhs. This penalty shall be in addition to all other penalties specified else where in the contract. The decision of imposing stoppage work, its extent & monitory penalty shall rest with HPCL/Owner & binding on the Contractor. 3.1.11 All fatal accidents and other personnel accidents shall be investigated by a team of Contractor‟s senior personnel for root cause & recommend corrective and preventive actions. Findings shall be documented and suitable actions taken to avoid recurrences shall be communicated to HPCL/Owner. Owner / HPCL shall have the liberty to independently investigate such occurrences and Contractor shall extend all necessary help and co-operation in this regard. 3.2 HOUSE KEEPING 3.2.1 Contractor shall ensure that a high degree of house keeping is maintained and shall ensure inter alia the followings wherever applicable: a. All surplus earth and debris are removed/disposed off from the working areas to identified location(s). b. Unused/Surplus Cables, Steel items and steel scrap lying scattered at different places within the working areas are removed to identified location(s). c. All wooden scrap, empty wooden cable drums and other combustible packing materials, shall be removed from work place to identified location(s). d. Roads shall be kept clear and materials like: pipes, steel, sand boulders, concrete, chips and bricks etc. shall not be allowed on the roads to obstruct free movement of men & machineries. e. Fabricated steel structural, pipes & piping materials shall be stacked properly for erection. f. Water logging on roads shall not be allowed. g. No parking of trucks / trolleys, cranes and trailers etc. shall be allowed on roads which may obstruct the traffic movement. h. Utmost care shall be taken to ensure over all cleanliness and proper upkeep of the working areas. Page 150 of 153 i. j 3.3 Trucks carrying sand, earth and pulverised materials etc. shall be covered while moving within the premises. Only properly designed steel scaffolding materials to be used for working at heights more than 3.0M . Double scaffolding using wooden ballis may be allowed for working at height less than 3.0M SAFETY, HEALTH AND ENVIRONMENT 3.3.1 The Contractor shall provide safe means of access to any working place including provisions of suitable and sufficient scaffolding at various stages during all operations of the work for the safety of his workmen, and, HPCL/Owner. Contractor shall ensure deployment of appropriate equipment and appliances for adequate safety and health of the workmen and protection of surrounding areas. 3.3.2 The Contractor shall ensure that all their staff and workers including their subcontractor(s) shall wear Safety Helmet and Safety shoes. Contractor shall also ensure use of safety belt, protective goggles, gloves etc. by the personnel as per job requirements. All these gadgets shall conform to relevant IS specifications or equivalent. 3.3.3 Contractor shall ensure that a proper Safety Net System shall be used at appropriate locations. The safety net shall be located not more than 30 feet (9.0 metres) below the working surface at site to arrest or to reduce the consequences of a possible fall of persons working at different heights. 3.3.4 Contractor shall ensure that flash back arrester shall be used while using Gas Cylinders at site. Cylinders shall be mounted on trolleys. 3.3.5 The Contractor shall assign to his workmen, tasks commensurate with their qualification, experience and state of health for driving of vehicles, handling and erection of materials and equipments. All lifting equipments shall be tested certified for its capacity before use. Adequate and suitable lighting at every work place and approach there to, shall be provided by the Contractor before starting the actual operations at night. 3.3.6 Hazardous and/or toxic materials such as solvent coating, or thinners shall be stored in appropriate containers. 3.3.7 All hazardous materials shall be labelled with the name of the materials, the hazards associated with its use and necessary precautions to be taken. Page 151 of 153 3.3.8 Contractor shall ensure that during the performance of the work, all hazards to be health of personnel, have been identified, assessed and eliminated. 3.3.9 Chemical spills shall be contained & cleaned up immediately to prevent further contamination. 3.3.10 All personnel exposed to physical agents such as ionizing radiation, ultraviolet rays or similar other physical agents shall be provided with adequate shielding or protection commensurate with the type of exposure involved. 3.3.11 Where contact or exposure of hazardous materials could exceed limits or could otherwise have harmful affects, appropriate personal protective equipments such as gloves, goggles, aprons, chemical resistant clothing and respirator shall be used. - A Crèche where 10 or more female workers are having children below the age of 6 years. - Reasonable Canteen facilities are made available at appropriate location depending upon site conditions. 3.3.13 Suitable facilities for toilet, drinking water, proper lighting shall be provided at site and labour camps, commensurate with applicable Laws / Legislation. 3.3.14 Contractor shall ensure storage and utilization methodology of materials that are not detrimental to the environment. Where required Contractor shall ensure that only the environment friendly materials are selected. 3.3.15 All persons deployed at site shall be knowledgeable of and comply with the environmental laws, rules & regulations relating to the hazardous materials substances and wastes. Contractor shall not dump, release or otherwise discharge or dispose off any such materials without the express authorization of HPCL/Owner. 4.0 DETAILS OF SHE MANAGEMENT SYSTEM BY CONTRACTOR 4.1 On Award of Contract The Contractor shall prior to start of work submit his Safety Health and Environment Manual or procedure and SHE Plans for approval by HPCL/Owner. The Contractor shall participate in the pre-start meeting with HPCL/Owner to finalise SHE Plans including the following : - Job procedure to be followed by Contractor for activities covering. Handling of equipment, Scaffolding, Electric Installation, describing the risks involved, actions to be taken and methodology for monitoring each activity. - HPCL/Owner review / audit requirement. Page 152 of 153 - 4.2 4.2.1 Organization structure along with responsibility and authority records / reports etc. on SHE activities. During job execution Implement approved Safety Health, and Environment management procedure including but not limited to as brought out under para 3.0. Contractor shall also ensure to: - arrange workmen compensation insurance, registration under ESI Act, third party liability insurance etc., as applicable. - arrange all HSE permits before start of activities (as applicable) like hot work, confined space, work at heights, storage of chemical / explosive materials and its use and implement all precautions mentioned therein. - submit timely the completed checklist on SHE activities, Monthly SHE report, accident reports, investigation reports etc. as per HPCL/Owner requirements. Compliance of instructions on SHE shall be done by Contractor and informed urgently to HPCL/Owner. - ensure that Resident Engineer / Site-in-Charge of the Contractor shall attend all the Safety Committee / SHE meetings arranged by HPCL/Owner. Only in case of his absence from site that a second senior most person shall be nominated by him in advance and communicated to HPCL/Owner. - display at site office and work locations caution boards, list of hospitals, emergency services available. - provide posters, banners for safe working to promote safety consciousness. - carryout audits / inspection at sub contractor works as per approved SHE document and submit the reports for HPCL/Owner review. - assist in SHE audits by HPCL/Owner, and submit compliance report. - generate & submit HSE records / report as per SHE Plan. - appraise HPCL/Owner on SHE activities at site. Page 153 of 153