ENVIRONMENTAL STATEMENT RELATING TO PROPOSED WESTERN EXTENSION OF HATFORD QUARRY, HATFORD, OXFORDSHIRE. 5. PROJECT DESCRIPTION 1. The proposed scheme is shown on the application drawings forming part of the planning application. The following key drawings are included in the ES reduced to A4 size: Site Location Plan Scheme of Working Landscaping and Restoration For full scale drawings refer to the planning application (Vol 1). 2. The areas included in the application are: Planning Application Area (gross) Additional Extraction Area Quarry Boundary Extension Area 24.1Ha 9.0Ha 12.4Ha 3. The economic minerals comprise the Highworth Sands and the underlying Highworth Limestones separated by a band of silt or silty clay. The general dip is approximately 1 in 80 from north west to south east, but it varies. 4. The depth of the sand and limestone also varies. The sand varied up to 5 metres deep on the northern boundary, but thins out towards the south. The limestone varies from 2.2 m to up to 7m thick. The existing ground levels fall from the north west (104m aod) to the south east (88m aod). The depth of working varies, with a maximum of approximately 12 metres. 5. It is estimated that the western extension contains estimated recoverable mineral resources comprising: Sand Limestone Total 205,000 tonnes 479,200 tonnes 684,200 tonnes 6. The limestone includes a substantial proportion of rock that is suitable for processing to produce a Type 1 aggregate. This is a particularly hard rock suitable for a wide range of uses including road sub-base. It is envisaged that the site will be worked at a rate of approximately 120,000 tonnes a year, giving an overall working life of 5 – 6 years. An overall planning permission period of 7 years is requested to allow for the site restoration. 7. The existing eastern working area will be completed in early 2013 and it is proposed that extraction will follow on into the western extension area. The eastern area will then be restored in accordance with the approved restoration scheme following the completion of extraction, and in any case before September 2013 to comply with the planning conditions. However the site office/weighbridge and associated screen bank, and existing western screen bank (alongside the plant site) will be retained for the duration of the proposed western extension. Scheme of Working and Restoration 8. The proposed sequence of working and restoration shown on the submitted drawings is described below: Phase 1: Pumping, backfilling and re-grading of the central quarry area to establish final levels. The existing processing plant site and associated settlement ponds within this area will be retained. Phase 2: Screening and safety bunds will be constructed on the northern, western and southern boundaries of the extension area as shown: (i) A 3m screening/safety bund inside the hedgerow alongside Sandy Lane to the north. (ii) A 7m screening and noise attenuation bund on the northern half of the western boundary to protect the amenities of The Hideaway, located 150m from the extraction boundary. (iii) The western bund (above) tapers into a 3m safety/screening bund on the remainder of the western site perimeter, and continues around the southern boundary. The 3 metre bunds will be constructed primarily using soils from the extraction area (and beneath the bund footprint). The core of the 7m bund will be constructed of quarry waste and surfaced with soils. Phase 3: Mineral extraction will commence in Phase 3N (North). The sand overlies the limestone and will therefore be extracted first. Limestone extraction will be commenced as soon as practicable and be worked in tandem with the sand. Extraction will then progress into Phase 3S (South) which is principally limestone. The sand will be removed by excavator/backhoe and taken by dump truck to the plant site for screening and grading. The limestone will be extracted by a 70 tonne hydraulic excavator that has recently been introduced to work the limestones at both Hatford and Shellingford quarries. This avoids the need to use a ‘pecker’ which generates higher impact noise. The excavated materials will be taken to the existing plant site for crushing, screening and grading ready for sale. Phase 4: Mineral extraction will continue into Phase 4N (North) and 4S (South) Phase 5: Site restoration will be carried out upon the completion of extraction and removal of the plant site: (i) Regrading of extension area and necessary adjustments to previously worked area to provide consistent base levels for restoration. (ii) Removal of settlement lagoons and provision of with amenity/wildlife and attenuation pond linked to outfall drainage pipe. (iii) Removal of eastern screening bank and grading it contours either side of the gas main. (iv) Removal of the northern, western and southern screen banks, final grading and spreading of restoration soils. Restoration 9. The land will be restored at the lower level to the contours shown on the landscaping and restoration scheme. The site will principally be restored to agriculture in accordance with the landowners requirements. However opportunities have been taken to provide ecological value through the inclusion of the two ponds, whilst the northern bank alongside Sandy Lane can be planted with trees and provide a wildlife corridor. In addition a Geological RIGS site will be provided in the Upper Corallian Strata on the northern boundary where it is accessible from Sandy Lane. 10. The ecological survey has discovered a rare plant in the existing quarry screen bank that will be removed as part of the approved restoration scheme. It is therefore proposed to translocate the plant to a permanent suitable location on the northern quarry boundary (refer to Environmental Statement for further details). Hours of Working 11. The existing permitted quarry operating hours will continue. These are: 0730 – 1800 Monday – Friday 0730 – 1300 Saturdays And not on Sundays and recognised public holidays. Access & Traffic 12. It is not proposed to change the rate of extraction at the quarry and traffic generation will therefore be similar to previous levels. All HGV traffic would be subject to the terms of the existing Lorry Routeing Agreement. This requires the use of the B4508 between the site access and the A417 and onwards via the A road network. Local roads are excluded except for local deliveries. 13. At an annual rate of extraction of 120,000 tonnes the average daily lorry movements would be 48 – 24 in and 24 out. Employment 14. Five full time staff would normally be based at the site. However the quarry also supports the employment of central company staff (management and administration) and operational staff (drivers and fitters etc). Stephen Bowley Planning Consultancy August 2012