Change Request for Certification and Release of Funds Form ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE Scope CHANGE TYPE: PROJECT NAME Budget Schedule ISD2R\YES NM PROJECT NUMBER DATE 09/10/2008 AGENCY CODE 630 LEAD AGENCY HUMAN SERVICES DEPARTMENT OTHER AGENCIES EXECUTIVE SPONSOR Department of Health PROJECT PHASE Commission on Deaf and Hard of Hearing Developmental Disability Planning Council Aging & Long Term Services Department Department of Workforce Solutions Children, Youth, and Families Department Pamela Hyde, Secretary Human Services Department PROJECT MANAGER Jan Christine AGENCY HEAD Pamela Hyde, Secretary Human Services Department AGENCY CIO/IT LEAD Terri Gomez, CIO Human Services Department Planning PROJECT DESCRIPTION (PROVIDE A BRIEF DESCRIPTION AND PURPOSE FOR THIS PROJECT) The ISD2R project must be undertaken because the State of New Mexico’s Income Support Division (ISD) legacy application, Integrated Service Delivery 2 (ISD2), has been in operation for 20 years and has now far exceeded its life expectancy. The system is fragile and costly and expensive to maintain. The YES New Mexico portion of the project is necessary to support the “no wrong door” strategy for the State of New Mexico by providing a common Web portal for existing and potential customers of HSD Income Support Division (ISD) and six other agencies with a total of 26 programs for eligibility screening and application submission. HSD proposes to combine these two projects, previously reported and appropriated separately. The Planning Phase was previously certified. The project Planning Phase was restarted May 2008 after project cessation and a review requested by HSD executive management. Planned Start Date 08/01/08 Planned End Date 06/15/09 JUSTIFICATION FOR CHANGE IN CERTIFICATION (INCLUDE BUDGET ADJUSTMENT REQUEST; BUSINESS VALUE AND/OR PROGRAM RESULTS) THE ISD2R AND YES NM PROJECTS HAVE BEEN UNDER HSD EXECUTIVE REVIEW SINCE 2Q08. DURING THAT REVIEW, THE CORE PROJECT TEAM AND REPRESENTATIVES FROM ALL HSD DIVISIONS VISITED FOUR (4) STATES WHERE SIMILAR SYSTEMS HAVE BEEN IMPLEMENTED. PREVIOUS TO AND DURING THE REVIEW, THE PROJECT TEAM ALSO SPOKE WITH APPROXIMATELY TWENTY-FIVE (25) STATES. This is a controlled document, refer to the document control index for the latest revision Revision: 2/14/08 Page 11 Change Request for Certification and Release of Funds Form ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE THE TEAM LEARNED FROM THE RECENT TELECONFERENCES AND STATE VISITS 1) OTHER STATES CONSIDER EQUAVALENT PROJECTS TO ISD2R AND YES TO BE ONE PROJECT, 2) SUCCESSFUL PLANNING PHASES TYPICALLY COST $2,000,000, 3) SUCCESSFUL PLANNING PHASES REQUIRE APPROXIMATELY EIGHT (8) TO TEN (10) MONTHS TO COMPLETE, 4) DOCUMENTATION DELIVERABLES REQUIRED BY THE FEDERAL PARTNERS IS CONSIDERABLY MORE EXTENSIVE THAN ANTICIPATED, AND 5) EXAMPLE DELIVERABLES WERE PROVIDED BY OTHER STATES. ON THE BASIS OF THE ABOVE LESSONS LEARNED, THE ISD2R\YES NM TEAM 1) CREATED A REVISED PROJECT SCHEDULE FOR THE PLANNING PHASE, 2) RE-ESTIMATED THE PLANNING PHASE, AND 3) IS REQUESTING THAT THE ISD2R AND YES NM PROJECTS BE RE-COMBINED. Amount Requested this Certification Assumptions: 1) The planning phase requires a total of $2,000,000. 2) For Federal financial reporting purposes, the Planning Phase will include the ISD2R Phase Zero certification, the ISD2R\YES Planning Phase, and the YES NM Initiation Phase. 3) Remaining funding from previously certified phases will be combined into this project. See the certification history in the next section. $ 1,101,000.00 Additional Funds Amount Previously Certified $ 90,000.00 ISD2R\YES Phase Zero $ 634,600.00 ISD2R\YES Planning $ 275,000.00 YES Initiation Phase - $100,600.00 (Certified in two Phases) $ 899,000.00 Net amount certified Remaining Appropriation not Certified Remaining Appropriation $ 6,353,115.15 not Certified Total Appropriated Amount (include any new funds) $ 4,600,600.00 General Fund $ 2,651,515.15 Anticipated Federal Match $ 7,252,115.15 Total GF, JPA and FFP CERTIFICATION HISTORY (INCLUDE ANY PREVIOUS PROJECT OR PHASE CERTIFICATIONS) Date Amount Funding Source(s) (use specific citations to laws, grants, etc.) 12/12/2005 $90,000 04/20/2007 $634,600 ISD2R/YES NM Planning 12/14/2007 $275,000 YES Initiation (includes $100,600 transfer from 4/20/07 Planning certification to YES Initiation). ISD2R Phase Zero This is a controlled document, refer to the document control index for the latest revision Revision: 2/14/08 Page 21 Change Request for Certification and Release of Funds Form ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE APPROPRIATION HISTORY (INCLUDE ALL FUNDING SOURCES, E.G. FEDERAL, STATE, COUNTY, MUNICIPAL LAWS OR GRANTS) Fiscal Year Amount Funding Source(s) FY 09-10 $1,000,000 Estimated (86%) FFP Laws of 2005 $6,200,000 ISD2R Laws 2008, Chapter 3, Section 7, Subsection 27 Extended the appropriation from Laws of 2005 through the end of FY10. FY 2008 $1,500,000 Estimated (75%) FFP Laws of 2007 $4,500,000 ISD2R Laws 2008, Chapter 3, Section 7 , Subsection 27 Extended the appropriation from Laws of 2007 through the end of FY10. FY 2008 $2,000,000 FY08 100,600 YES NM Chapter 3 , Section 7, Subsection 26 JPA approved 04-17-2007 Commission on Deaf and Hard of Hearing, $50,000 Department of Health $38,000 Developmental Disability Planning Council $5,000 Aging & Long Term Services Department $3,000 Department of Workforce Solutions, JPA $2,600 Children, Youth & Families Department, JPA $2,000 Note: Expected overall Federal match for the funds appropriated to ISD2R for the Planning Phase is 45% This is a controlled document, refer to the document control index for the latest revision Revision: 2/14/08 Page 31 Change Request for Certification and Release of Funds Form ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE BUDGET Comments: Planning estimated to complete June 2009 Description FY07 & prior Phase Zero Staff Internal IT PM, Documentation Consulting Services IT PM, Data Modeling & Conversion/ Planning Experts Portfolio Management Tool, Travel (400s) Hardware/ Software/ Travel Planning & YES NM Initiation FY09 FY10 FY11 Planning $656.8 $90.0 $90.0 TOTAL FY08 $75.0 $1,113.2 $64.0 $230.0 $139.0 $2,000.0 INDEPENDENT VERIFICATION & VALIDATION (INCLUDE SUMMARY OF THE LATEST IV & V REPORT) IV&V was waived for the ISD2R\YES NM Planning Phase. IMPACT OF CHANGE (MAY INCLUDE SIGNIFICANT RISKS & MITIGATION STRATEGY; SECURITY, CONSOLIDATION & MAINTENANCE STRATEGIES; RECORDS RETENTION; & BUSINESS PERFORMANCE MEASURES) The only impacts of the planning phase are 1) to reduce risk for the overall project implementation, and 2) to meet the requirements of the Federal Partners FNS and CMS for documentation that will be incorporated into the Implementation Advanced Planning Document (IAPD). This is a controlled document, refer to the document control index for the latest revision Revision: 2/14/08 Page 41 Change Request for Certification and Release of Funds Form ALL CERTIFIED PROJECTS MUST FOLLOW NM STATE POLICIES AND PROCUREMENT CODE SECURITY STRATEGY (APPLICATION AND DATA SECURITY PROCESS, PLAN, OR STANDARD) Not Applicable for the Planning Phase. The final documents for the phase will identify a security plan and the standards. IT SYSTEM ANALYSIS On this document, or as an attachment, provide a summary response, including changes, to the following IT infrastructure topics relating to this project: During the planning phase, the impact to hardware, network, and software will be minimal. Some laptops will be added for team members. Four servers that are already available and configured will be placed in development/test and production areas of the existing HSD architecture. These servers will be used for the Portfolio Management tool used throughout the project life cycle for ISD2R\YES. The architecture for the portfolio management tool is three (3) tiers with presentation (web), application, and database components. For the planning phase, two environments will be implemented: development\test, and production. When the project moves to implementation, development and test environments may be separated. During the planning phase only a total of approximately (10) people will be using the Portfolio Management software. BUSINESS CONTINUITY STRATEGY On this document, or as an attachment, provide a summary response, including changes, of your business Continuity Strategy. There will be no changes to the business Continuity Strategy as a result of the Planning Phase of ISD2R\YES NM. This is a controlled document, refer to the document control index for the latest revision Revision: 2/14/08 Page 51