Government Response to the Public Works Committee Report No 100, December 2008 Review of the Prep School Year Capital Works Program Background As part of its February 2004 election commitments, the Queensland Government announced the introduction of a universally available, non-compulsory, full-time Preparatory Year of schooling in 2007 with full implementation by 2008 in all State primary schools. A major capital works program was required to facilitate the delivery of the prep play and inquiry based curriculum. This program, with expenditure of $290m represented the biggest single capital program of works in the history of state education in Queensland. An audit was carried out in early 2004 by a Review Team (RT) comprising representatives from Treasury, Education Queensland and specialist consultants. The audit identified indicative facilities solutions for approximately 640 schools. A detailed audit of each school commenced on 23 August 2004 with the data collection completed by 10 December 2004. This audit identified the needs of each school and firm solutions were identified and signed off by the School Principal. Detailed design and tender documentation was prepared for the scope of work identified by the audit (for those schools where a building solution was required). The RT made its recommendations for building design after extensive consultation with key stakeholders in both the State and non-state sectors. In particular, consultation occurred with representatives of the Queensland Association of State School Principals (QASSP), Queensland Teachers’ Union (QTU), principals and early childhood teachers. A ‘mock-up’ of the new classroom design was established in an unused portion of the Science Centre. This ‘mock-up’ was used in consulting with key stakeholders such as the QTU, QASSP and general educationalists. There was a very positive response to this design. The design was “trialled” with the end users of the 18 phase-in schools completed in 2005 and the 20 phase-in schools completed in 2006. The process included liaison with the QTU and QASSP as part of the ongoing consultations occurring with these stakeholders. Feedback from these schools was used to improve the design of the various facilities solutions, including selection of building materials, noise attenuation, floor vibration and internal fit out. The Prep Capital Works Program comprised two major phases. The first was completed prior to the 2007 school year ensuring facilities were ready to accommodate the initial half-year cohort of students and the second, completed for the 2008 school year, ensuring accommodation for the first full cohort of Prep year students. The final number and type of facilities delivered by the Preparatory (Prep) Program were: provision of 449 new Prep classrooms, refurbishment of 607 existing primary classrooms, funding allocations to 412 schools to enhance existing classrooms to accommodate preparatory students where 16 or fewer preparatory students were enrolled and funding allocations to enhance the condition of 673 existing preschool classrooms. A post occupancy evaluation of the Prep program sought responses from 130 schools (approximately 20% of schools on the Prep building program) that represented a broad sample by geographic location, size and facilities solutions. Across Queensland, a sample of 130 schools that provided a broad geographic spread, and represented the various facilities solution that comprised the Prep project were selected for inclusion in the Post Occupancy Evaluation. 98 schools responded to the questionnaire, and their responses indicate that: 97% believe that the Prep infrastructure supports teaching and learning 93% stated that the Prep facilities suited their needs 89.7% were happy with the siting of Prep facilities with regard to existing infrastructure. Government Response to the Public Works Committee Report No 100, December 2008 Review of the Prep School Year Capital Works Program The Public Works Committee’s Recommendations Recommendation 1 The committee recommends that Department of Education and Training (DET) install covered links from classrooms to toilets in all future Prep school facilities. Response This recommendation is supported. Comment Covered links are being installed as a standard provision in existing and all future Prep school facilities where Prep classrooms access external toilets. New Prep classrooms are provided with covered links to access either new toilets provided with the classrooms or to existing school toilets. Where Prep classrooms are established from existing school facilities access to external toilets is provided by existing covered links or new covered links are installed as required. The Prep Facility Enhancement Program provided funding of $20 million in 2006-07 to install covered links at schools north of the Barkly Highway and east of the Great Dividing Range. The covered links were installed from Prep classrooms to toilets and to the existing school path network. In 2008-09 an additional $23 million funding was provided to complete the installation of covered links at schools in SEQ. It is anticipated that this program will be substantially complete by 30 June 2009. Recommendation 2 The committee recommends that DET develop Best Practice Guidelines to Prep facilities that include: a) a minimum of 3.4square metres per child per classroom group of 25 students (excluding non teaching space – the kitchen and teacher’s room); b) the location of the toilets within the teacher’s line of sight and as close as possible to Prep classrooms (and, where this is not possible, provide new toilet facilities); c) a balance between indoor and outdoor learning areas for Prep students; and d) siting of classrooms to maintain adequate playground space and proximity to existing outdoor areas. 2a Response: This recommendation is not supported. Comment The current and future focus of Prep delivery standards will be on functionality and practical applications that have been tested and proven to deliver a satisfactory work space rather than prescriptive measures such as ‘area per child’ This approach is supported by the Prep Post Occupancy Evaluation Report completed in June 2008 and regular monitoring of the performance of the classrooms which highlight high levels of satisfaction with the current Prep infrastructure. In developing classroom prototypes extensive input was provided by early childhood experts and practitioners as well as from results of the trials. The Australian Early Childhood Association (AECA) figures that were cited by the Queensland Association of State School Principals (QASSP) relate to standalone licensed child care services that also cater for very young children. Prep is a unique provision for 4.5 – 5.5 yr olds and is incorporated into schools as part of a Prep to year 3 precinct where prep students utilise a range of specialist areas/space (e.g. libraries) 2b Response The recommendation is supported. Comment DET confirms that the Prep Year Facilities Brief will be amended to provide that all future Prep classrooms are sited within reasonable distance of existing toilets and within the teacher’s line of sight from the internal general learning area(s) and/or the outdoor learning area(s), and where this is not possible provide new toilet facilities. The Prep program met the siting guidelines for toilets, provided by the Independent Review Team and within the constraints of the budget. Whilst the location of the toilets within the teacher’s line of sight was sought as a highly desirable objective the existing layout of the school and the preferred location of the Prep classroom did not always make this achievable within the funding limitations. The Prep Program provided 225 additional toilets in situations where it was considered that reasonable access to toilets was not possible. 2c Response This recommendation is supported. Comment Appropriate access to outdoor learning areas will remain a key siting consideration in DET’s future Prep delivery standards. Preparatory facilities were sited to achieve integration with the junior primary precinct of the school and access existing facilities. Access to existing outdoor learning areas was a significant factor considered in the siting of new buildings and the selection of buildings for refurbishment. Outdoor learning areas were provided as part of the design of all new Prep buildings. In the 37 instances where the siting of Prep classrooms did not achieve reasonable access to existing facilities, additional outdoor learning areas were provided as part of the program. 2d Response The recommendation is supported. Comment DET will continue to include the need to provide adequate playground space in close proximity within future Prep delivery standards. In accessing outdoor play areas, DET’s intention was to use existing junior play areas and equipment. This was part of the siting criteria that located Prep buildings as close as possible to the junior precinct of the school. New buildings were sited to minimise the impact on existing play structures. In those cases where playground equipment had to be removed schools received funding for its replacement. Siting and consideration of access to playground equipment was done on a case-by-case basis. As a result, there were some variations in approach due to the wide range of existing facilities at schools as well considerable variability in the size of school sites across the State. Recommendation 3 The committee recommends that for future projects DET seek input from all interested parties, including teachers and parents, in the consultation process. Response: This recommendation is supported. Comment Extensive consultation was an integral part of the delivery of the Prep program. An outline of this process is provided below. DET monitored the implementation of Prep closely during the trial and phase-in period, 2003-2006, and the roll-out of the main program in 2007 and 2008. A number of mechanisms, including surveys, routine departmental activities and meetings with key stakeholders facilitated the monitoring process. Parents and school staff were surveyed during 2007 to capture perceptions of the Prep implementation, identify challenges and inform school planning processes to support implementation of the full cohort in 2008. In developing prototypes for Prep year classrooms an education brief informed the initial design as well as feedback gathered from DET representatives, the Queensland Association of State School Principals, Queensland Teacher’s Union and early education groups as part of the consultation process involving the two classroom prototypes built at Tullawong State School and Proserpine State School. Recommendation 4 The committee recommends that for future projects DET conducts a post occupancy evaluation of all schools and ensure all interested parties are consulted, including teachers and parents. Response: This recommendation is supported. Comment Post occupancy evaluations will be integral to program delivery and will inform future (major) capital works programs such as Building the Education Revolution and Pre Prep. The Prep program comprised more that 1000 schools and it was impractical to impose significant demands on the time of school staff and parents in every primary school in the state. As a result the post occupancy evaluation of the prep program sought responses form 130 schools (approximately 20% on the prep building program) representing a broad sample by geographical location, size and facilities solutions. In addition a comprehensive review process was undertaken by the Prep team with the end users of the 38 phase in schools and this feedback was used to improve the design of facilities solutions. Recommendation 5 The committee recommends that for future projects DET ensure a local industry participation plan is prepared. Response: The recommendation is supported. Comment DET and DPW are aware of the requirements of the Local Industry Policy. A key criterion for the evaluation of tenders for the Prep School Year Capital Works Program was demonstrated evidence of local industry participation in the building program. A more detailed summary of DPW criteria is provided at attachment A. The recommendation of the committee has been noted and Department of Public Works advises that for projects in which it is involved, Local Industry Participation Plans will be prepared in accordance with the Local Industry Policy. Attachment A Background DPW information re Prep Year Implementation Contractors are required under the Queensland Government’s Local Industry Policy to provide full, fair and reasonable opportunity to local suppliers and subcontractors to tender for work associated with the delivery of Government resource base projects. A critical component of local content is the integration of training and skill development. The initiatives included by Public Works were: reference to Australian Standards and codes in project documentation, giving priority to locally manufactured products using a priority order for specifying building industry products that gives precedence to functional, performance and technical specifications without unreasonably disadvantaging local manufacturers including clauses in contract documentation that require building industry contractors to report on local industry participation at prescribed times throughout the contract period, and requiring contractors to advise sub-contractors and suppliers of local industry participation requirements using local tender boxes, where appropriate, to ensure that local industry participants are not disadvantaged advertising locally by using regional, state-wide or national newspapers as appropriate, when using an open tendering process identifying local service providers by consulting the whole-of-government prequalification (PQC) system for building industry contractors and consultants working closely with the Department of Employment and Training to improve compliance with the State Government Building and Construction Contracts Structured Training Policy (generally known as the 10% Training Policy) incorporating non-price tender evaluation criteria specifically reflecting the intent to achieve local industry participation on all projects identified under the Local Industry Policy monitoring building industry contractors’ compliance with Local Industry Policy requirements of contracts that require regular Local Industry Participation reports, and providing individual projects reports to departments for inclusion of data in reports to the Department of State Development on building projects that require local industry participation reporting in accordance with the Department of State Development Guide lines for developing Local Industry Participation Plans.