Report to the Cabinet Member for Environment, Planning and Cultural Services Report submitted by: Interim Executive Director for Environment Date: 5 November 2014 Part I - Item No. Electoral Division affected: N/A North West Coast Connections Project: Stage 2 Consultation on Outline Route Corridors/Substation Siting (Appendix 'A' refers) Contact for further information: Phil Megson, 01772 534162, Environment Directorate, Philip.Megson@lancashire.gov.uk Executive Summary National Grid Electricity Transmission plc (NGET) is undertaking an informal public consultation on the North West Coast Connections Project. The Project will connect proposed new nuclear generation at Moorside (near Sellafield, West Cumbria) by new electricity transmission lines to the existing national grid electricity transmission network. The public consultation concludes on 28 November 2014. NGET has identified an emerging preference - Onshore North and Onshore South with Tunnel Group Options - for reinforcing the electricity transmission network to link Moorside to the national grid. For Lancashire, the emerging preference involves a Tunnel under Morecambe Bay from Roosecote in Cumbria to the Heysham peninsula to connect to the national grid via a new substation that is currently under construction to the east of Heysham. The tunnel head and associated infrastructure are the only elements of the emerging preference that would have a permanent presence above ground in Lancashire. The tunnel head is consistent with the 'Heysham Energy Coast' designation in Lancaster City Council's Site Allocations Development Plan Document and, subject to detailed siting at the next stage in the Project, would avoid, as far as reasonably practicable, national and local environmental designations. It is concluded that, in comparison to other route corridor options, the emerging preference has the least impacts on Lancashire. It is therefore recommended that Onshore Group South with Tunnel Options should be supported. Recommendation The Cabinet Member for Environment, Planning and Cultural Services is asked to agree that: 1. Onshore South Tunnel Option Section H2.1 and Tunnel Head Outline Siting Area H2T1 should be supported as this route corridor option has the least impacts on Lancashire compared to other route corridor options. 2. Onshore South Group Options should be opposed due to the high level of environmental impacts on Lancashire compared to Onshore South Tunnel Option Section H2.1 and Tunnel Head Outline Siting Area H2T1. 3. If Onshore South with Tunnel Group Options is selected by NGET to proceed to the next stage (Stage 3) of the NWCC Project, NGET should be encouraged to assess the feasibility of: Utilising a rail based option to export tunnel spoil from, and to import construction materials to H2T1 during the construction phase of the Project; Maximising local labour, expenditure on goods and services; Achieving legacy impacts from the project, which should include investment in the local housing stock to provide workforce accommodation. Background and Advice The North West Coast Connections (NWCC) Project is a Nationally Significant Infrastructure Project under the Planning Act 2008. To meet future energy demand, to increase security of supply and to decarbonise electricity generation to contribute to the Government's targets of reducing greenhouse gas emissions, National Policy Statement (NPS) EN-1 sets out the Government’s conclusion that there is a significant need for new major energy infrastructure. NPS EN-1 includes information regarding the specific need for new major electricity networks infrastructure in Section 3.7. There is a need for National Grid Electricity Transmission plc (NGET) to strengthen its electricity distribution network in Lancashire and Cumbria to connect proposed new nuclear generation at Moorside (near Sellafield, West Cumbria) by new electricity transmission lines to the existing electricity network. By virtue of NPS EN-1 the need for the Project has been demonstrated. The process for bringing forward the NWCC Project is set out below: Stage 1 Strategic Options (informal consultation) Stage 2 Routeing/Siting (public consultation) – current stage Stage 3 Detailed Routeing/Siting Stage 4 The Application (public consultation) Stage 5 Consideration of the application by the Planning Inspectorate (PINS) and Secretary of State. Stage 1 NGET undertook an informal consultation on six Strategic Options between 11 May 2012 and 19 July 2012. NGET's appraisal work concluded that that Option 3 (Cumbria Ring onshore) achieved the best balance between the technical, socioeconomic and environmental considerations. The County Council's assessment of the Strategic Options concluded that Options 3 and 4 (Cumbria Ring Offshore) should be taken forward for further consideration by NGET, with Option 4 being the County Council's preferred Option1. Indeed a consensus was reached by all the planning authorities in Lancashire and Cumbria potentially affected by the NWCC Project, with the exception of the Lake District National Park, which concluded that offshore only Options should be taken forward. Stage 2 Based on consultation feedback and further technical appraisal of the options, NGET has identified potential route corridors where new infrastructure could be located. These route corridor options fall into three groups: 1. Onshore North and Onshore South Group Options; 2. Onshore North and Onshore South with Tunnel Group Options; 3. Onshore North and Offshore South Group Options. Maps of the Options are attached to this report at Appendix 'A1' to 'A3' along with a key to the maps at Appendix 'A4'. As NGET's technical appraisal of the Options has progressed, NGET has an emerging preference (shown in green on the Map). The impacts of the emerging preference on Lancashire are considered in the next section of this report. The current informal consultation commenced on 4 September 2014 and will conclude on 28 November 2014. The feedback from the consultation process will inform NGET's consideration of Detailed Routeing / Siting (Stage 3) and the Application (Stage 4). There will be formal consultation on the application for a Development Consent Order. NGET'S EMERGING PREFERENCE – IMPACTS ON LANCASHIRE In so far as the emerging preference affects Lancashire, there would be a Tunnel under Morecambe Bay from Roosecote, near Barrow in Furness to Heysham (Section H2.1 on Map) to enable electricity distribution cables to connect into the national grid at Heysham substation. NGET prefer this option because the siting of the potential connection point at Heysham would allow the most effective connection from Section H2 to the National Electricity Transmission System. NGET has considered whether there would be any benefit to connecting to a location other than at Heysham and has concluded that such an approach would require constructing new, and additional, infrastructure to connect the tunnel head to the connection point and there would be no electrical or system benefit in doing so. Tunnel Head Outline Siting Area (H2T1) is located to the east of Heysham, north east of Heysham substation adjacent to A683. H2T1 is co-located with a new substation that is currently under construction. The overall site area is 10 hectares. NGET's tunnel head outlining siting area identification process in the Heysham peninsula has sought to avoid internationally and nationally designated areas of the highest amenity, cultural or scientific value, as far as reasonably practicable, and 1 Decision by the Cabinet Member for Economic Development, Environment and Planning on 16 July 2012 areas of local amenity value such as ancient woodland, groundwater sources and nature conservation areas. Where possible, the process has also taken advantage of screening provided by landform and opportunities to group similar land uses together. NGET have also taken into account the location of settlements although it has not been possible to avoid proximity to all settlements. This will be a key consideration at the next stage (Stage 3 Detailed Routeing and Siting) in the NWCC Project. The new substation is a key factor that has influenced tunnel head outlining siting area identification, as the cables passing through the tunnel would have to connect to this substation. It is worth noting that the other tunnel options (H2.2 and H2.3) would emerge at the same point in Lancashire so the above considerations would also apply. The tunnel under Morecambe Bay would be constructed using two Tunnel Boring Machines – one from Lancashire and one from Cumbria. The length of the tunnel in H2.1 is 22km. Each Tunnel Boring Machine would advance 20-25m per day depending on geology (rock or glacial till). Large volumes of material would have to be imported to the tunnel construction project at Heysham and 400,000 tonnes of tunnel spoil would have to be exported from the site for recycling or disposal [the same would apply in Cumbria]. NGET see the A683/link road/M6 being important for the import and export of construction materials. When in service the tunnel head would incorporate a secure entrance to the tunnel, a road access and ventilation equipment would be housed in a building, the dimensions of which would be dependent on the design of the tunnel chosen, and its ventilation requirements. The maximum dimensions of the building could be 40m long, 30m wide and 12m high. The Planning Performance Agreement Authorities commissioned WYG to peer review the assumptions used by NGET in developing the tunnel option. WYG's review has found that there are no major issues regarding the assumptions. The review has highlighted a number of technical matters that need to be considered if NGET select the Onshore South with Tunnel Option to the next stage of the Project. NGET'S ALTERNATIVE ROUTE CORRIDORS AND SEARCH AREAS NGET have considered alternative Route Corridors and Siting Areas options, which have been "parked" or are not being taken forward. "Parked" options that would impact on Lancashire are: 1. Onshore South Group (Sections G3 and G4): Lindale (Cumbria) via Nether Kellet to either a substation currently under construction at Middleton or a new substation at Quenmore. 2. Offshore South Group (Section L): offshore cable landfall between Blackpool and Lytham St Annes to an existing substation at Stanah. The "parked" alternatives may be revisited by NGET if any "showstoppers" emerge through the current consultation or further assessment by NGET of the emerging preference. Options not being taken forward not being taken forward by NGET that would impact on Lancashire are: 1. Morecambe Bay sub-sea cables and Overhead Lines 2. Arnside and Silverdale Area of Outstanding Natural Beauty (AoNB). THE COUNTY COUNCIL'S ASSESSMENT OF THE EMERGING PREFERENCE'S IMPACT ON LANCASHIRE The Appraisal has utilised the same headings as NGET for assessing the impact of the emerging preference. Existing and Proposed Infrastructure The 132kV overhead line from Lancaster to the existing Heysham substation passes to the east of Heysham and the larger 400kV overhead line extends from the Heysham substation across the Heysham Peninsula, to the south of the A683. NGET is currently constructing a new substation at Middleton on land that is identified as being suitable for energy related activities in Lancaster City Council's Site Allocations Development Plan Document (DPD). The existing and proposed infrastructure has influenced NGET's designation of H2T1. H2T1 would be co-located with the new substation. Co-locating the tunnel head with the new substation would obviate the need to construct new, additional infrastructure to connect the tunnel head to the connection point. It is likely that other siting options would result in increased impacts by virtue of the requirement for new, additional infrastructure. Landscape, Seascape and Visual Amenity The tunnel head and associated infrastructure are the only elements of the emerging preference that would have a permanent presence above ground in Lancashire. Much of the area to the west, south and south east of Heysham has a number of significant energy related structures such as Heysham 1 and 2 nuclear power stations, wind turbines, electricity sub-stations and pylons which exert a strong industrial influence over the landscape character suggesting a likely low level of landscape sensitivity to a tunnel head development. The County Council's assessment concludes that there would be no significant effects on the setting, character and visual amenity of any nationally designated landscape, nationally registered historic designed landscape, Green Belt, Conservation Area, listed building or regionally important historic designed landscape. The tunnel head would not have a material impact on seascape. The detailed design for the Tunnel is a matter for Stage 3 of the project. Up to three 'ventilation islets' would be required in Morecambe Bay for tunnel ventilation and to provide a safe means of exit for workers in the event of an emergency. The number of 'ventilation islets' has still to be agreed by the Health & Safety Executive. Each 'ventilation islet' would be 55m in diameter and 20m above the sea bed. Part of each structure would be permanently under water. The amount visible above the waterline would vary according to tide. If it is assumed that three 'ventilation islets' are required and that these are equally spaced, the nearest 'ventilation islet' would be at a distance of 5-6km from the Heysham coast. The County Council's assessment concludes that at this distance the nearest 'ventilation islet' (and more distant 'ventilation islets') and the tunnel head would not have a material impact on seascape. Ecology Within the emerging preference, only Section H2 includes elements that affect Lancashire. On the basis of the proposed scale of development within Lancashire compared to other options it appears that this option is likely to have the least ecological impact on Lancashire2. If Onshore South with Tunnel is selected by NGET to proceed to the next stage of the Project, a detailed ecological survey and assessment of impacts will be required to demonstrate that routes and siting locations of least impact within the study corridor have been selected. The ecological survey and impact assessment will also need to inform the necessary measures to avoid, mitigate or compensate for ecological impacts. Measures will be required to avoid impacts on designated sites (SSSI and BHS) at Heysham Moss. Historic Environment Impacts are limited to (i) potential wrecks or early prehistoric remains within Morecambe Bay that may be impacted directly or indirectly by the proposed 'ventilation islets'; and (ii) potential for prehistoric or later medieval/post medieval remains at H2T1. The potential in the first case is perhaps low to very low, in the second it is probably a little higher. There is no indication that any discoveries made would be of such significance as to require preservation in situ at the expense of the development. Soils and Geology There are no geological designations, landfill sites or significant areas of land in H2T1. The area is Grade 3 agricultural land. There may be the presence of peat and soft organic silts associated within Heysham Moss. This could be an issue which may need additional consideration if tunnel infrastructure is to be sited within this area. The County Council already have issues with settlement of some of the existing roads in this area. 2 Ecological impacts on the marine environment have not been addressed as these fall outside Lancashire. Natural England and the Marine Management Organisation, the appropriate bodies for commenting on the marine environment, have been consulted separately by NGET. Natural England is the body responsible for assessing any ecological impacts on statutory sites such as those associated with the proposed 'ventilation islets'. Water Environment H2T1 would not impact on Source Protection Zones, Principal Aquifers or superficial deposits designated as aquifers. Part of H2T1 is located within an area with a risk of tidal flooding (Flood Zones 2 and 3). H2T1 is protected from coastal flood defences, which are maintained to the standard of a 0.5% annual probability flood event (1 in 200 year frequency). NGET anticipate that there is sufficient space available within H2T1 to identify a tunnel entrance outside of the area susceptible to flooding if the flood defences failed. This issue will need to be addressed at the next stage (Stage 3) in the NWCC Project. The detailed siting of the tunnel head is a matter for Stage 3 of the Project. The siting and design of the tunnel head should evaluate the need for flood protection measures on site to provide mitigation against flooding in the event of flood defence failure. Noise and Vibration Lancaster City Council Environmental Health, on behalf of the County Council, has identified potential for noise and vibration impacts from the following identified sources linked to the H2T1 proposal:1) 2) 3) 4) 5) Noise and vibration from tunnelling works Noise from tunnel ventilation system Noise from other plant and machinery Noise and vibration from general construction activity Noise from traffic or other transport (e.g. rail/ship) serving the proposed development. Noting the proposed area for the siting of the tunnel head at Heysham, the impact on noise sensitive uses at elevated position in the locality requires specific consideration. The potential noise/vibration impact will be a consideration in the detailed design and positioning of the scheme (Stage 3 of the Project). A noise assessment should be undertaken to properly assess the current noise climate and noise arising from the proposed development in both construction and operational phases. The noise assessment should also consider and assess any mitigation measures where proposed to control noise levels and any noise limits or other controls that may be used to limit exposure to noise. In relation specifically to vibration reference is made by National Grid in the consultation documentation to the requirements currently imposed on some quarries. This standard may not provide sufficient mitigation against the vibration caused by tunnel-boring, which will have different characteristics from the vibration experienced from the use of explosives in quarries. Also if there are existing weakened structures close to the tunnel route (these would need to be identified through the assessment process), tighter standards may be appropriate. An impact assessment, referring to knowledge gained from similar projects, will therefore need to consider the impact of vibration arising from tunnelling/construction activities and any measures used to control levels or reduce exposure. The assessment methodology for noise/vibration should be agreed in writing through the Development Consent Order process. Informed by the findings of the assessment, the local authority may look to place control requirements on the development through powers granted under Section 60 of the Control of Pollution Act 1974. Other environmental health considerations that are relevant, but fall outside the 'noise and vibration' heading are set out below. Whilst these considerations are relevant to later stages in the Project, they are worth signposting to NGET. Air Quality/Odour/Dust During the construction phase there is potential impact from the following sources:1) Dust arising from tunnelling and other construction work, particularly the handling of excavated material. 2) Dust associated with vehicles accessing and leaving the site (e.g. tracked/spilt material along access routes). 3) Potential odour impact from material excavated from the tunnel e.g. odorous silts 4) Pollutant emissions arising from plant, construction plant, road vehicles or other transport. An assessment of the above impacts (dust, odour and air quality impacts) should be undertaken, again the methodology being agreed in writing through the Development Consent Order process. Where impacts are identified the assessment should include measures to mitigate the impacts and proposed monitoring if considered appropriate. Existing identified air quality issues in the Lancaster area (identified through the Local Air Quality Management regime) are linked to the road transport emissions. The addition of road traffic, particularly HGVs will provide an additional source to the wider road network. It is therefore strongly recommended that alternative transport options are considered (rail / ship) particularly in relation to the removal of excavated material. Enhancements to the rail transport system could provide a transport legacy to Heysham which may also bring air quality benefits. Land Contamination (Heysham Tunnel Head Site) There are some alluvial and lacustrine deposits in the vicinity of the proposed tunnel head that are known to be gas bearing/generating. Additionally, the tunnel entrance will be close to the former railway sidings and some contamination is possible. However, the immediate area has been subject to site investigation and little by way of significant contamination was noted. Economic Activity Whilst the H2T1 interacts with a number of economic activity receptors in the Heysham peninsula, development would not prejudice the operation of these receptors. Development within H2T1 could have temporary negative impacts on accessibility during the construction phase, which could impact on the economic productivity of the workforce and business transport logistics. Having regard to the existing and the proposed highway network (A683/Heysham M6 link/M6), NGET considers that these impacts would be "minor" at worst, and would not be material consideration in the appraisal of H2T1. This impact could be mitigated by the use, if feasible, of a rail based solution for the export of tunnel spoil and import of construction materials. Development of H2T1 could also have temporary positive impacts during the construction phase through expenditure on local labour goods and services (and multiplier effects). NGET do not identify any 'legacy' impacts 3 at this stage in the NWCC Project. The tunnel and associated development would be consistent with the statement in Lancaster City Council's Site Allocations DPD that "through the energy coast the City Council will look to support proposals that contribute to the economic growth of the district within this sector, supporting job creation and the development of local supply chains." If, following an assessment of the consultation responses, NGET selects Onshore North and Onshore South with Tunnel Group Options to take forward to the next stage in the Project (Stage 3) the temporary positive impacts of the Project in the construction phase should be assessed in more detail. NGET should also to identify, in consultation with impacted local authorities, 'legacy' impacts. Planning Policy H2T1 is located in the 'Heysham Energy Coast' in Lancaster City Council's Site Allocations DPD. The City Council anticipates further energy investment and energy related development, including "the construction of new substations and other grid required infrastructure" (Policy HEY1). The development of the tunnel head would be consistent with this policy. H2T1 is not located in an area that is constrained by a policy in the adopted Lancashire Minerals and Waste Local Plan. Traffic and Transport In the consultation documentation, NGET highlight the importance of A683, the Heysham-M6 link road (currently under construction) and M6 for the import of construction materials to the tunnel head. If, following an assessment of the consultation responses, NGET selects H2.1 to take forward to the next stage in the NWCC Project, NGET will undertake a multimodal Strategic Transport Network Assessment to assess how construction materials will be imported to the site and tunnel spoil arising from boring the tunnel will be exported from the site. Whilst these impacts would be temporary in nature, construction of the Tunnel, subject to NGET securing a Development Consent Order, would commence in 2018 3 This could include, for example, the conversion of Houses in Multiple Occupation in Morecambe into self contained units to house workers during the construction phase rather than housing workers in caravans, short term lets or B&Bs, which is the case with other NGET projects. and conclude in 2024. The export of 400,000 tonnes of spoil would result in more than 14,000 HGV movements over the period. The import of construction materials is not yet quantified but the combined imports and exports to and from the site would have a significant impact on the road network. The feasibility of non-road based options should be examined in the Strategic Transport Network Assessment. It is understood that rail freight operators are able to utilise wagons with a capacity to carry 72 tonnes and that, even with the known constraints on the Morecambe line, could accommodate a train with eight 72 tonnes wagons. The presence of a dismantled railway to the east of the site, which runs south from the existing Morecambe line, offers potential for a rail based solution to be implemented from the export of spoil excavated from the Tunnel during construction. NGET should be encouraged to pursue a rail based option if this proves to be technically feasible. Aviation and Defence H2T1 is marginally within the 3.6km Obstacle Limitation Surface4 for the Middleton Sands micro-light flying site. This facility is an unlicensed aerodrome and is not, therefore, formally safeguarded. NGET considers that a 12m high tunnel head building would be unlikely to impact on micro-light flying activities. The County Council's Assessment of NGET's Alternative Route Corridors and Search Areas that would impact on Lancashire Parked Alternatives: 1. Onshore South Group (Sections G2, G3 and G4): Lindale (Cumbria) via Nether Kellet to either a substation currently under construction at Middleton or a new substation at Quenmore. 2. Offshore South Group (Section L): offshore cable landfall between Blackpool and Lytham St Annes to the existing substation at Stanah. Onshore South Group (Sections G2, G3 and G4): The Onshore South Group of sections would connect Moorside to either a new substation, currently under construction at Middleton, or to an existing substation at Quernmore. In Lancashire the route would be around the head and eastern shore of Morecambe Bay, designated as a Ramsar Site, SAC, SPA and SSSI. The Search Area for Section G3 includes a large area of open access land within the Arnside and Silverdale AoNB at Leighton Moss. Sections G2, G3 and G4 benefit from an opportunity corridor for the installation of new 400kV circuits, which would replace the existing 132kV overhead line. In Sections G2, G3 and G4, where alternative route corridors have been proposed, NGET have concluded that the use of the opportunity corridor is preferable. 4 Obstacle Limitation Surfaces are used for safeguarding for licensed aerodromes in accordance with the Civil Aviation Authority's Civil Aviation Publication 168. NGET has expressed a marginal preference to connect into the substation at Middleton that is currently under construction, notwithstanding it would require modification to connect this option. NGET's decision to "park" this option is supported because it would have greater adverse impacts on Lancashire in comparison with NGET's emerging preference (see section below on the County Council's assessment of the relative merits of NGET's emerging preference (Onshore South with Tunnel Option) and NGET's alternative Route Corridors and Search Areas). Offshore South Group (Section L): The Offshore South Group is a strategic option with mainly offshore circuits to distribute electricity generated at Moorside to the NGET substation at Stanah. The option would comprise High Voltage Direct Current (HVDC) cables laid offshore (Sections I, J and K), together with relatively short onshore underground HVDC cable connections (Section L). HVDC is necessary due to the length of the offshore connections involved. As the national grid distributes electricity at 400kV (and 275kV) Alternating Current (AC) two converter stations would be required to convert HVDC to AC before connecting to the Stanah substation. Each converter station would require a site 550m x 350m, with 28m high transformer buildings. Two Outline Siting Areas (LC1 and LC2) have been identified between the former Poulton-le-Fylde to Fleetwood railway and the Wyre Estuary. One of the key considerations for Converter Station siting is the need to transport heavy transformers to the site, which would weigh between 200 tonnes and 400 tonnes each. Depending on the size selected between 7 and 26 transformers would be required. The transformers would be transported to the UK by ship and, ideally, would be transported to the converter station site by barge. Alternatively, transport by road is likely to require selective road strengthening. The converter stations would export electricity via the Stanah substation, which connects into the national electricity transmission system. These considerations, together with the existing industrial uses, have determined the general location of the Converter Station Outline Siting Areas. The converter stations would be sited on land allocated by Wyre Borough Council in the Fleetwood – Thornton Area Action Plan for industry to the north of the Stanah substation. The onshore cable route (L1) would avoid or mitigate any potential effects on the internationally important Ribble and Alt Estuary (SPA and Ramsar designations) and the nationally important Lytham St Annes Dunes Site of Special Scientific Interest (SSSI). Route L2.1 is preferred by NGET to L2.2 as it would avoid two crossings of the River Wyre which is designated as a SSSI and as part of the Morecambe Bay Special Area of Conservation (SAC), Special Protection Area (SPA) and Ramsar site5. NGET's decision to "park" this option is supported because it would have greater adverse impacts on Lancashire in comparison with NGET's emerging preference 5 Ramsar sites are wetlands of international importance designated under the Ramsar Convention. In the UK, the first Ramsar sites were designated in 1976. (see section below on the County Council's assessment of the relative merits of NGET's emerging preference (Onshore South with Tunnel Option) and NGET's alternative Route Corridors and Search Areas). Alternatives not being taken forward: 1. Morecambe Bay sub-sea cables and Overhead Lines NGET have assessed the installation and direct burial of cables under Morecambe Bay the installation of overhead lines across the Bay and consider both to be technically feasible. However, the provisions of the Habitats Regulations6 act as a major constraint. Construction would be limited to seasonal and or tidal construction windows to avoid disturbance, particularly birds. Construction may also damage inter-tidal habitats. The highly dynamic tidal and sediment environment of the Bay would affect the cables, once installed, as a result of over burial or exposure, or would affect the foundations of pylons for overhead lines through scour. Regular maintenance, including protecting cables or foundations with rock armour, would be likely to change the habitat over time, and could interfere with the coastal processes that contribute to the ecological interest for which the sites within the Bay are designated. The overhead lines option would also have significant landscape and visual impacts, which may have impacts on tourism around the Bay. The provisions of the Habitats Regulations mean that either of these options could only be taken forward if there are no less damaging alternatives available. NGET accept that there is potential for less damaging, more easily deliverable and maintained options that could be brought forward and, therefore, propose that subsea cables or overhead line options are not taken forward. The County Council agrees with NGET's assessment and consequent decision not to take forward these options for the reasons given. 2. Arnside and Silverdale AoNB A direct connection across the AoNB could be achieved using overhead lines or underground cables. It provides the shortest potential connection between Lindale (in Cumbria) and either Middleton or Quernmore. NGET initially considered this option, but formed the view, in conjunction with stakeholders (including the County Council), that as the AoNB is associated with significant amenity, environmental and cultural heritage assets and that there are alternatives to this route corridor, it should be avoided. This view accords with the Holford Rules7, the Habitats Regulations and the principles of the AoNB – to protect the natural beauty. NGET's decision not to take forward this route corridor is supported because of the significant adverse impacts on landscape, ecology and cultural heritage assets. 6 The Conservation of Habitats and Species Regulations,2010. These are non-statutory principles for routeing overhead transmission lines formulated by Lord Holford in 1959 and updated in the 1990s. 7 The County Council's Assessment of the Relative Merits of NGET's Emerging Preference (Onshore South with Tunnel Option) and Nget's Alternative Route Corridors and Search Areas Existing and Proposed Infrastructure In Lancashire, the Onshore South with Tunnel Option provides the opportunity to colocate the tunnel head with the new substation (under construction), which connects into the national electricity transmission system. This would obviate the need to construct new, additional infrastructure for other grid connection options. Existing 132kV electricity transmission lines run from Natland substation to Lancaster. In the Onshore South group Options, this infrastructure represents opportunity corridors for the replacement of regional electricity transmission lines owned by Electricity North West Limited (ENW) with national grid electricity transmission lines operating at 400kV. New substations would be required at the interfaces between the new national grid electricity transmission lines and the unaffected regional electricity distribution network. In Lancashire, the Offshore South Group Options underground cables would be required from the landing point between St Annes and Blackpool to the proposed converter stations at Stanah. The Option provides the opportunity to co-locate the converter stations with the Stanah substation, which connects into the national electricity transmission system. This would obviate the need to construct new, additional infrastructure for other grid connection options. From a Lancashire perspective the opportunity to co-locate infrastructure and the restricted geographical footprint favour the Onshore South with Tunnel Option Landscape, Seascape and Visual Amenity In Lancashire, the Onshore South with Tunnel Option would result in no significant effects on landscape and seascape character. The Onshore South Group Options have the likely potential for significant effects on the setting and character of the nationally important Arnside and Silverdale and Forest of Bowland AoNBs. The elevated topography within these designated areas and wider landscape would contribute to maximising likely visual effects. The M6 motorway corridor is becoming increasingly congested with tall vertical structures, especially the section to the east of the Arnside and Silverdale AoNB where there is the potential for significant cumulative effects with wind energy development. Whilst the visual amenity of Lancaster's Green Belt would likely be adversely affected by this option, it is worth noting that the area between the AoNBs and Lancaster has considerable historic interest. Thus, there could be significant effects on the setting and character of the nationally important registered historic designed landscape at Capernwray Hall Park, various Conservation Areas, listed buildings and regionally important historic designed landscapes. Cable undergrounding is not considered to be a viable option in much of the search area as it would result in significant losses of key features of the landscape's character. Many of these features would take an unacceptably long period of time to re-establish. Due to the substantial mitigating effect of distance, the Offshore Group South Option would likely have no significant effects on the setting, character and visual amenity of any nationally designated landscape. However, due to extensive use of cable undergrounding there would, overall, likely be a substantial loss of landscape fabric which, in turn, could result in significant effects on the setting, character and visual amenity of Fleetwood, Blackpool and Lytham's Green Belt, the nationally important registered historic designed landscapes at the Mount Fleetwood, Fleetwood Memorial Park, Stanley Park and Lytham Hall, various Conservation Areas and listed buildings. Due to the large scale of the proposed HVDC converter stations and the close proximity of the proposed siting areas to residential receptors and the open, windswept landscape to the east of the River Wyre it is unlikely that all of the landscape, visual and seascape effects could be adequately mitigated. Having undertaken a strategic level analysis and assessment of the characteristics of the development proposals, baseline landscapes of the search areas and their sensitivity and capacity for change together with a consideration of likely effects it is clear that the Onshore South with Tunnel Option is the best option for Lancashire's landscapes by a considerable margin. Ecology The County Council's assessment of the options in so far as they would impact on Lancashire concludes that, having regard to the ecological constraints present (SSSI and BHS) at Heysham Moss and the small development footprint of H2T1 compared to other options, the emerging preference is likely to have the least ecological impact on Lancashire compared to the other options. Whichever option progresses to Stage 3 will require a detailed ecological survey and assessment of impacts to demonstrate that routes and siting locations of least impacts within the study corridor have been selected. The ecological survey and impact assessment will also need to inform the necessary measures to avoid, mitigate or compensate for ecological impacts. Historic Environment The Onshore South with Tunnel Option has the least impact on Lancashire. Impacts are limited to (i) potential wrecks or early prehistoric remains within Morecambe Bay that may be impacted directly or indirectly by the proposed 'ventilation islets'; and (ii) potential for prehistoric or later medieval/post medieval remains at H2T1. The potential in the first case is perhaps low to very low, in the second it is probably a little higher. There is no indication that any discoveries made would be of such significance as to require preservation in situ at the expense of the development. All other proposed routes that have been considered will have higher potential impacts but again there seems to be no reason to suspect that an acceptable route could not be constructed. Soils and Geology The Onshore South with Tunnel Option has the least impact on Lancashire. From a County Council perspective this option has the least impact on the highway network because of the limited area of highway network that is affected. The Onshore South Group Options should not have a significant affect on the highway network in relation to soils and geology, as pylons would be used along the route and would be sited away from the existing highway network. Mitigation by undergrounding cables in sensitive locations has the potential to increase the impact on the highway network in relation to soils and geology. The Offshore South Group Option could potentially have the most impact on the highway network in relation to soils and geology. This route corridor travels east from the coast to the south of Blackpool Airport and then north to Stanah. As it is a shallow below ground cabling exercise, it will cross numerous highways in areas were the ground conditions are poor and the existing road construction is thin and therefore there is the potential for settlement of the existing carriageways as a result of the works. This would be an option that should be avoided in relation to soils and geology. For all options, any impact on the existing highway network as the result of underground/trenching or tunnelling construction would require pre works surveys (SCANNER, Deflectograph etc.) to establish a baseline condition for the highway network followed by subsequent condition surveys to establish whether settlement or deterioration had occurred. Water Environment The Onshore South with Tunnel Option would not impact on Source Protection Zones or major aquifers. This would be within an area with a risk of tidal flooding (Flood Zones 2 and 3). If necessary flood defences could be reinforced to mitigate risk from flooding. The Onshore South Group Options would not impact on Source Protection Zones or major aquifers. The Option connecting to Heysham substation would be within an area with a risk of tidal flooding (Flood Zones 2 and 3). The River Keer fluvial floodplain, Pine Lake and neighbouring enclosed water bodies, and Island Pond (Quernmore substation option) would have to be crossed by Onshore South Group Options. In the Offshore South Group Options, NGET consider that aquifer designations, surface water quality designations and consideration of surface water resource protection have not been material in identification of cable route corridors. NGET has had regard to the need to avoiding extensive areas of flood risk and static water bodies in the outline siting of Converter Station infrastructure process. Outline Siting Area LC1 lies outside Flood Zones 2 and 3 due to the presence of landfill which has built up ground levels. Outline Siting Area LC2 lies partly within Flood Zones 2 and 3 but has formal flood defences. The water environment is not a significant differentiator as flood defences could be installed or reinforced in areas at risk from flooding. Noise and Vibration In the Offshore South Group Options, the location of settlements has been a key consideration in the outline siting of Converter Station infrastructure process. Due to settlements being located quite closely together in the search area it has not been possible for NGET to avoid identifying the outline siting areas in proximity to all settlements. Noise and vibration impacts will be a consideration at the detailed design stage (Stage 3) of the Project. Potentially noise and vibration impacts will be more significant for the Onshore South with Tunnel Option (in respect of the tunnel construction and operational phases) and the Offshore South Group Options (in respect of the operation of the Converter Stations) than the Onshore Group South options in the absence of mitigation. To inform the next stage in the Project noise assessments should be undertaken to properly assess the current noise climate and noise arising from NGET's selected Option in both construction and operational phases. The noise assessment should also consider and assess any mitigation measures where proposed to control noise levels and any noise limits or other controls that may be used to limit exposure to noise. Economic Activity Minimising interaction with settlements and other economic activity receptors is a feature of all the options. Whilst the geography of the impacts will vary depending on which option is chosen, it is not considered to be a significant differentiator between the options at this stage. ????? looks like some words are missing here Planning Policy In so far as the Onshore South with Tunnel Option affects Lancashire it is supported by policy in that the tunnel head and associated infrastructure is located in the 'Heysham Energy Coast' identified in Lancaster City Council's Site Allocations DPD. In respect of Onshore South Group Options and the onshore elements of the Offshore Group Options, planning policy offers protection to broad areas of environmental and socio economic impact. No policies place an absolute constraint on the route corridors identified at this stage in the Project. Traffic and Transport The Onshore South with Tunnel Option would potentially have significant impacts during the construction phase (2018 – 2024) if a road based solution is adopted. The export of 400,000 tonnes of tunnel spoil would result in more than 14,000 HGV movements over the period. The import of construction materials is not yet quantified but the combined imports and exports to and from the site would have a significant impact on the road network between the tunnel head and the M6. The presence of a dismantled railway to the east of the site, which runs south from the existing Morecambe line, offers the potential for a rail based solution to be implemented for the export of spoil excavated from the Tunnel during construction and the import of materials for tunnel construction. NGET should be encouraged to pursue a rail based option if this proves to be technically feasible as would provide significant mitigation against the impacts of traffic and transport. For the Onshore South Group Options impacts would be less if conventional pylons are used (modular design) rather than T pylons (pre-assembled). The use of T Pylons may require the construction of temporary access roads. Undergrounding, to mitigate visual impacts may also require the construction of temporary access roads. The Offshore Group Options would potentially have significant impacts on the road network during the construction phase if there is a need for the converter station transformers to be delivered by road. NGET's preference would be to deliver the transformers to site by barge. There are potential issues of settlement associated with this option relating to the nature of soils and geology beneath highways. Aviation and Defence In Lancashire it is concluded that use of any of the identified route corridor options would not be expected to result in negative impacts on aviation interests. Comparative Costs This Report focuses on the impacts of the Project on Lancashire, not the costs of the project. The overall comparative costs of the substantive route corridor options (excluding mitigation) are included for information: Onshore South Group Options Overhead Lines Onshore South with Tunnel Options (NGET's preference) Offshore South Group Options £ 770 million emerging £1,296 million £1,828 million Mitigation of impacts will be considered in the 'planning balance' by the Panel at the Examination stage of the Project. If the Secretary of State approves the Development Consent Order, OFGEM (the electricity industry regulator) will consider whether the costs of mitigation are acceptable. Conclusion The assessment of the impacts on Lancashire of the emerging preference (Onshore South with Tunnel Option) and the alternative options (Onshore South Group Options and Offshore South Group Options) leads to the conclusion that the Onshore with Tunnel Option performs better in terms of impacts than the alternative options in respect of 'existing and proposed infrastructure', 'landscape, seascape and visual amenity', 'ecology', 'historic environment', 'soils and geology'. The emerging preference is the only option supported by planning policy. 'Water environment' and 'aviation and defence' are not significant differentiators between the options. 'Noise and vibration' is not a significant differentiator at this stage, but impacts and potential mitigations will need to be addressed at the detailed design stage. 'Economic activity' is not a significant differentiator at this stage, but there is the opportunity achieving legacy impacts from the Project. In respect of 'traffic and transport' impacts on Lancashire, the emerging preference may perform less well than Onshore Group South Options if a road based solution for the export of tunnel spoil and import of construction materials is utilised. If a rail based solution is feasible, the traffic and transport impacts on Lancashire would be significantly reduced. It is recommended that: 1. Onshore South Tunnel Option Section H2.1 and Tunnel Head Outline Siting Area H2T1 should be supported as this route corridor option has the least impacts on Lancashire compared to other route corridor options. 2. Onshore South Group Options should be opposed due to the high level of environmental impacts on Lancashire compared to Onshore South Tunnel Option Section H2.1 and Tunnel Head Outline Siting Area H2T1. 3. If Onshore South with Tunnel Group Options is selected by NGET to proceed to the next stage (Stage 3) of the NWCC Project, NGET should be encouraged to assess the feasibility of: Utilising a rail based option to export tunnel spoil from, and to import construction materials to H2T1 during the construction phase of the Project; Maximising local labour, expenditure on goods and services; Achieving legacy impacts from the project, which should include investment in the local housing stock to provide workforce accommodation. Consultations N/A Implications: This item has the following implications, as indicated: Risk management No significant risks have been identified in relation to the proposals contained within this report. Financial The PPA is a means by which the County Council (and other local planning authorities affected by the proposals) can participate and engage in a positive way with the developer and reach a fully informed view on the local impacts of the proposals. The PPA would provide funding from NGET to the County Council (and other local planning authorities affected by the proposals) for three of the four major work streams relating to the National Infrastructure Directorate (NID) process for local authorities; considering the applicant's Statement of Community Consultation; commenting on the quality of the applicant's consultation process and producing a technical Local Impact Report. Preparation of the Local Impact Report in particular is likely to be resource hungry. The PPA would not fund the County Council (and other local planning authorities affected by the proposals) to make its own representations on the application by NGET for a DCO. Legal A PPA does not fetter the participating Authorities in the view they take on the merits of a proposal. Equality and Diversity The PPA allows the County Council (and other local planning authorities affected by the proposals) to be properly resourced to ensure the views and concerns of local communities are given voice within the planning process which is essential given that the ultimate decision on NGET's proposal will be made at a national level. List of Background Papers Paper Date Contact/Directorate/Tel NWCC Project Planning Performance Agreement 14 May 2012 Phil Megson/Environment Directorate/01772 534162 NWCC Main Report (3 volumes) NGET 1 August 2014 Phil Megson/Environment Directorate/01772 534162 NWCC Appendices 1- 5 NGET 1 August 2014 Phil Megson/Environment Directorate/01772 534162 NWCC Tunnel Proposal Technical Overview (WYG) October 2014 Phil Megson/Environment Directorate/01772 534162 Reason for inclusion in Part II, if appropriate N/A