19.05.2011 - Ministry of Development of North Eastern Region

advertisement
Government of India
Ministry of Development of North Eastern Region
******
MINUTES OF THE 4th MEETING
TO REVIEW THE STATUS OF PALATANA POWER PROJECT & ACCOMPANYING
TRANSMISSION AND COORDINATION ISSUES
CHAIRED BY MS. JAYATI CHANDRA, SECRETARY, DONER
Date :
19th May, 2011
Venue:
Committee Room, Ministry of DONER
List of participants is annexed.
Opening the discussions, Secretary, DONER stated that this meeting
specifically is on assessing on the readiness to evacuate power and use it
in the region for the two generating units which will be ready by the
following dates:
2.
(i) Unit I
December, 2011
(ii) Unit II
March, 2012
For evacuation within the region, North Eastern Transmission
Company Ltd. (NETC) is developing a 400 KV double circuit, 861 Km long
trunk transmission line connecting Palatana to Bogaigaon. This line is being
developed in 2 stretches:
Page 1 of 6
(i)
Palatana to Silchar
:
(ii)
Silchar to Bogaigaon :
246 Kms &
415 Kms.
In addition, PowerGrid and the State power utilities are constructing
15 sub-stations (PGCIL – 10, Assam Electric Generation Corporation Ltd – 3
& Tripura State Electricity Corporation Ltd. – 2) and 11 sub-transmission
lines (all PGCIL). With the movement of ODGs through Bangladesh and
BHEL agreeing to swap Bawana (NCT of Delhi) turbine with Palatana, the
2nd generating unit will be ready by March, 2012. Therefore, the readiness
for evacuation needs to be re-evaluated.
3.
There are forest clearances issues in Assam and Meghalaya for the
transmission lines.
Director, Ministry of DONER has visited Assam and
Meghalaya for discussions with State Forest Departments.
Secretary,
DONER has addressed Secretary, Tribal Affairs regarding the Forest Rights
Act.
Secretary directed the State Governments to assist NETC/PGCIL
sorting of issues of compensation demanded by farmers.
Tripura
particularly needs to do more for the Palatana-Silchar line which is of
immediate critical importance.
4.
It was agreed by all that power from the first generating unit can be
evacuated considering the pace and the likelihood of commissioning of
the transmission and sub-transmission lines and sub-stations. Evacuation
readiness of Unit 2 raises serious misgivings. As the Silchar-Bongaigaon 400
KV DC line of NETC will be ready only by June, 2012, it is imperative that
the transmission line upto Byrnihat in Meghalaya is completed by the time
Unit 2 of generation is ready i.e. March, 2012. It also implies that the
Byrnihat sub-station should be ready by March, 2012. These are critical
deadlines for evacuating power from Unit 2.
Page 2 of 6
5.
The important sub-stations by Assam and Tripura will be ready as
follows:
(i)
Hailakandi – Assam
:
November, 2013
(ii)
Azra – Assam
:
December, 2013
(iii)
Surjyamanipur – Tripura
:
December, 2012
(It is important to note that since this sub-station is going to be
completed only by December, 2012, Tripura has to make
contingency plan for drawing power from Unit 1.)
(iv)
P K Bari – Tripura
:
December, 2011
(It will match with Unit 1 of generation.)
6.
The power sharing agreement between the States and OTPC is as
follows:
S.
No.
State
Allocation
(MW)
1
Tripura
196
2
Assam
240
3
Arunachal Pradesh
22
4
Nagaland
27
5
Mizoram
22
6
Manipur
42
7
Meghalaya
79
8
IL&FS / OTPC
98
Total
726
Note: 50% of allocation is assumed to be
linked with Unit -1
Page 3 of 6
7.
It was agreed that at this point, there are many imponderables
about the readiness of the different stakeholders for evacuation of Unit 2
which is going to be ready by March, 2012. It would be very unfortunate if
the generation capacity of Unit 2 is left idle for want of evacuation
infrastructure. It will be a setback to the first commercial power project of
the North Eastern Region.
8.
Secretary, DONER will write to Cabinet Secretary and Power
Secretary.
9.
Meeting ended with vote of thanks to the chair.
…….
Page 4 of 6
Annexure
4th MEETING TO REVIEW THE STATUS OF PALATANA POWER PROJECT,
ACCOMPANYING TRANSMISSION AND COORDINATION ISSUES .
List of participants
Sl. No.
Name of the
participant
Designation and name of the organization
1.
Ms. Jayati Chandra
Secretary, DONER
…in the chair
2.
Ms. Jayashree
Mukherjee
Joint Secretary, DONER
3.
Shri Alemtemshi
Jamir,
Addl. Chief Secretary & Development
Commissioner, Govt. of Nagaland
4.
Shri R.K. Vaish
Principal Resident Commissioner, Govt. of
Arunachal Pradesh
5.
Shri Sumeet Jerath
Principal Secretary(Power), Govt. of
Assam
6.
Shri Saraswati Prasad
Principal Secretary, (Environment
Forest), Government of Assam
7.
Shri Pankaj Jain
R.C. Government of Meghalaya
8.
Shri Arun Kumar
Director, Ministry of Power
9.
Shri Brajesh Mishra
Director, Ministry of DONER
10.
Shri Umakant
Director, Ministry of DONER
11.
Shri Ravinder Gupta
Director, CEA
12.
Shri Sarvant Kumar
Consultant, R.C. Office, Nagaland
13.
Shri T.P. Khaund
Principal Adviser, Govt. of Mizoram
14.
Shri NG Birjit Singh,
Suptd. Engineer(Elec), Electricity
Department, Govt. of Manipur
15.
Shri Khose Sale
Suptd. Engineer, Department of Power,
Govt. of Nagaland
16.
Shri Anil Jain,
General Manager(Corporate Monitoring)
POWERGRID Corporation of India
&
Page 5 of 6
17.
Shri Rakesh Verma
Chief Manager(Corporate Monitoring),
POWERGRID Corporation of India
18.
Shri R.K. Madan,
Sr. Adviser, ONGC
19.
Shri K. Marbasiang
Chief Engineer (Transmission), MeECL.
20.
Shri R. Syibm
Suptd. Engineer, MeECL
21.
Shri Umesh Chandra
MD, NETC
22.
Shri M. Krishna Kumar
Director(Projects), NETC
23.
Shri Kumaresh
Chakrabarti
Director(T) & CMD, i/c. TSECL, Tripura
………
Page 6 of 6
Download