Title - Department of Planning, Transport and Infrastructure

advertisement
Revision 0
Specification: Contract Specific Requirements
CONTRACT SPECIFIC REQUIREMENTS
DPTI XXCxxx
Page 1
Revision 0
Specification: Contract Specific Requirements 110
110
1.
WORKS GENERAL PROVISIONS
CONTRACTOR’S PROGRAM
Only insert here additional requirements regarding formatting, layout, frequency of provision etc. Do not insert any
clauses dealing with contractual matters – these are covered in the Conditions of Contract.
2.
STAGE CONSTRUCTION
To be compiled for each project.
3.
MAJOR CONSTRAINTS
To be compiled for each project. ("Major Constraints" should list only the constraints not covered elsewhere in the
Specification, refer Clause 110.2).
4.
CONTRACTOR’S PERSONNEL
The Contractor’s personnel shall meet the following minimum requirements:
TITLE
QUALIFICATIONS
Contractor’s
Representative
Site Supervisor
(Roadworks)
Quality Management
Representative
Demonstrated
understanding of the
principles and practices of
Quality Management or
have completed a course in
Quality Management
EXPERIENCE
REQUIRED
5 years of on-site work of a
similar magnitude and
complexity.
3 years of on-site work of a
similar magnitude and
complexity.
3 years of on-site work of a
similar magnitude and
complexity.
TIME REQUIRED ON
SITE
During customary working
hours.
During customary working
hours.
The QMR is not required to
be based permanently on
site when works are in
progress but shall be on site
when critical activities are
being undertaken.
or
The QMR is required to be
based permanently on site
when works are in progress.
Environmental
Management
Representative
Community
Consultation
Representative
Demonstrated
understanding of the
principles and practices of
Environmental Management
or have completed a course
in Environmental
Management
Demonstrated
understanding of the
principles and practices of
Community Consultation
3 years of on-site work of a
similar magnitude and
complexity.
Refer Part 150 of these
Contract Specific
Requirements.
3 years of on-site work of a
similar magnitude and
complexity.
Refer Part 180 of these
Contract Specific
Requirements.
The Contractor’s Representative may / shall not be the Quality Management Representative. Other positions shall be
filled by separate individuals.
5.
CONTRACTOR'S COMPOUND AND SUPERINTENDENT'S REQUIREMENTS
Information to be included in this section:
DPTI XXCxxx
Page 2
Revision 0
Specification: Contract Specific Requirements 110
Sketch of location(s) of land available to Contractor if Principal making land available for use by the
Contractor.
Planning requirements (approvals in Hills Face Zone, etc.)
Details of the Superintendent's requirements:
Buildings
Telephone, Power, Fax, Furniture, etc.
Lunch room and toilet facilities
Meeting Room (6 m x 3 m minimum)
Examples:
The area shown on Sketch CS110 is available for the Contractor's use during the Contract. The tenderer shall
submit as post tender information the proposed usage of the allocated area.
The Contractor shall obtain a written agreement with the landholder and Local Council to establish a compound or
any area used for the storage of plant or materials. Copies of these agreements shall be submitted to the
Superintendent prior to establishment of the compound. A written release shall be obtained from the landholder
after de-establishment.
Example of Superintendent's Site Compound:
The Contractor shall allow for the unloading (at the commencement of the Contract) and loading (at the completion
of the Contract) of the Superintendent's site office.
Within the main compound the Contractor shall provide an area for the Superintendent's site office (12 m x 3 m)
and an adjacent area (12 m x 6 m) for vehicles.
These areas shall be enclosed by a 2.15 metre high galvanised chain link security fence installed on outward
cranked posts topped with three (3) strands of barbed wire (or similar and approved) and shall be provided with a
hard standing area of a minimum of 100 mm of rubble in front of the site office and for the vehicle parking area.
The following shall be provided and connected to the site office with all connection charges at the Contractor's
expense:
(a)
Power supply 240 V, 45 amps.
Connection of power to the Superintendent's site office shall comply with AS 3000 "SAA Wiring Rules" and
shall be carried out by an electrical worker who is licensed to perform any electrical works.
The connection shall include an operational check of the site office residual current device (RCD) in
accordance with AS 3760 "In-service Safety Inspection and Testing of Electrical Equipment".
The Contractor shall issue a Certificate of Compliance for the connection of electricity including the RCD
check.
(b)
Two telephone lines.
(c)
Water supply and waste connections to one toilet, one hand basin and one kitchen sink.
The Principal will pay only the operating costs of telephones for the duration of the Contract and accounts for these
costs shall be made out in the name of the Principal.
DPTI XXCxxx
Page 3
Revision 0
Specification: Contract Specific Requirements 110
Prior to completion of the Contract, the Contractor shall clean up all compound areas and leave them in a
condition comparable to that encountered at the time of possession of site. Payment for the establishment of the
Superintendent's site office will be made under "Establishment Charges" in the Schedule of Rates.
6.
COUNCIL CONTACT PERSON(S)
The contact person is:
Mr / Ms .....................................
..........................................
..........................................
Telephone: ..............................
7.
SUPPLY OF WATER
Details for rural projects to be included.
8.
EXPLOSIVES
Blasting is permitted / not permitted
9.
DPTI INTERVENTION LEVELS
Intervention levels for:
Pavement potholes
Individual pot hole of:
either depth of 50 mm and diameter of 300 mm in traffic lanes, or
depth of 30 mm and diameter of 300 mm in bicycle lanes or pedestrian crossing / walk through.
Minor Pavement repairs (digouts)
Any individual areas of distressed pavement ≤ 20 m2 with:
either deformation of 50 mm under a 1.2 m straight edge in traffic lanes, or
deformation of 30 mm under a 1.2 m straight edge in bicycle lanes or pedestrian crossings.
Pavement edge break
Pavement edge break of 200 mm into the pavement from the nominal edge of seal.
Shoulder edge drop
Shoulder edge drop of 75 mm.
Maintenance of signs



Missing signs shall be replaced.
Signs shall be cleaned or replaced when legibility of the sign is ≤50%.
Sign supports shall be straightened when greater than 10% from the vertical.
Sweeping
Pavement shall be swept where skid resistance is affected.
DPTI XXCxxx
Page 4
Revision 0
Specification: Contract Specific Requirements 110
SPECIAL CONDITIONS SCHEDULE
RISE AND FALL CONTENT FACTORS
CONTENT FACTOR
COMPONENT OF WORKS
CL
CF
CM
CP
CB
For items of work which include bituminous products (i.e.
spray seals and asphalt)
For all other items of work (i.e. items which do not include
bituminous products)
10% is not subject to Rise and Fall.
For the purpose of this clause only, the following items in the Schedule of prices or Schedule of Rates are deemed to
include bituminous products:
S/R Items 56, 57…
____________
DPTI XXCxxx
Page 5
Revision 0
Specification: Contract Specific Requirements 110B
CONTRACT SPECIFIC REQUIREMENTS
110B
1.
WORKS GENERAL PROVISIONS
CONTRACTOR’S PERSONNEL
The Contractor’s personnel shall meet the following minimum requirements:
EXPERIENCE
REQUIRED
TIME REQUIRED ON
SITE
Contractor’s
Representative
5 years of on-site work of a
similar magnitude and
complexity.
The CR is not required to be
based permanently on site
when works are in progress
but shall be on site when
critical activities are being
undertaken.
Site Supervisor
(Roadworks)
3 years of on-site work of a
similar magnitude and
complexity.
3 years of on-site work of a
similar magnitude and
complexity.
During customary working
hours.
TITLE
Quality Management
Representative
QUALIFICATIONS
Demonstrated understanding
of the principles and
practices of Quality
Management or have
completed a course in
Quality Management
The QMR is not required to
be based permanently on site
when works are in progress
but shall be on site when
critical activities are being
undertaken.
The Contractor’s Representative shall not be the Quality Management Representative. Other positions shall be filled
by separate individuals.
2.
LIMITATIONS ON PROGRAMMING AND SEQUENCE OF WORK
AE FS3 will not be available until December 2010. AE’s FS1, FS4, FS5, FS6, FS7 and FS8 will not be available
until February 2011.
3.
MEASUREMENT
In addition to Clause 16 "Measurement ", all AE’s will be defined as one lot as shown in Appendix A "AE Lot
Package Advice". 100% of the payment for the AE will be made on completion of all works for the lot which
includes the 2 coats of pavement marking and the installation of all raised pavement markers and pavement bars.
The "AE Lot Package Advice" form shall be completed and submitted with test results to verify the conformance and
completion of lots for the AE.
___________
DPTI XXCxxx
Page 6
Revision 0
Specification: Contract Specific Requirements 110P
110P
1.
WORKS GENERAL PROVISIONS
STAGE CONSTRUCTION
To be compiled for each project.
2.
MAJOR CONSTRAINTS
To be compiled for each project ("Major Constraints" should list only the constraints not covered elsewhere in the
Specification, refer Clause 110P.2).
3.
PRE-COMMENCEMENT MEETING
The following information shall be submitted at the pre-commencement meeting:
ITEM
RECEIVED
Program of Works *
Daily Diary form
Manufacturer’s Instructions
Amenities Details
Scaffolding Plan *
Pedestrian Movement and Screening Plan
Security Plan
Traffic Management Plan *
Clearance from Landowners
Traffic Provision Details including “Notification of
Works Impacting DPTI roads form.
Approval from EPA
Environmental Considerations
APAS Records
Abrasive Sample 2 kg
Surface Preparation Procedures
Lighting Plan
Bunding details
*
DPTI XXCxxx
These items are not required if they have been previously presented at the Post Tender
Meeting, unless further information has been requested by the Superintendent.
Page 7
Revision 0
4.
Specification: Contract Specific Requirements 110P
CONTRACTOR’S PERSONNEL
The Contractor’s personnel shall meet the following minimum requirements:
TITLE
QUALIFICATIONS
Contractor’s
Representative
Site Supervisor
Quality Management
Representative
Demonstrated
understanding of the
principles and practices of
Quality Management or
have completed a course in
Quality Management
EXPERIENCE
REQUIRED
5 years of on-site work of a
similar magnitude and
complexity.
3 years of on-site work of a
similar magnitude and
complexity.
3 years of on-site work of a
similar magnitude and
complexity.
TIME REQUIRED ON
SITE
During customary working
hours.
During customary working
hours.
The QMR is not required to
be based permanently on
site when works are in
progress but shall be on site
when critical activities are
being undertaken.
or
The QMR is required to be
based permanently on site
when works are in progress.
Environmental
Management
Representative
Demonstrated
understanding of the
principles and practices of
Environmental Management
or have completed a course
in Environmental
Management
3 years of on-site work of a
similar magnitude and
complexity.
Refer Part 150 of these
Contract Specific
Requirements.
The Contractor’s Representative may / shall not be the Quality Management Representative. Other positions shall be
filled by separate individuals.
5.
CONTRACTOR'S COMPOUND AND SUPERINTENDENT'S REQUIREMENTS
Information to be included in this section:
Sketch of location(s) of land available to Contractor if Principal making land available for use by the
Contractor.
Planning requirements (approvals in Hills Face Zone, etc.)
Examples:
The area shown on Sketch CS110P is available for the Contractor's use during the Contract. The tenderer shall
submit as post tender information the proposed usage of the allocated area.
The Contractor shall obtain a written agreement with the landholder and Local Council to establish a compound or
any area used for the storage of plant or materials. Copies of these agreements shall be submitted to the
Superintendent prior to establishment of the compound. A written release shall be obtained from the landholder
after de-establishment.
6.
SPECIAL REQUIREMENTS AND CONTACT PERSONS OF EMERGENCY SERVICES
6.1
Special Requirements
DPTI XXCxxx
Page 8
Revision 0
Specification: Contract Specific Requirements 110P
Any special conditions/requirements must be identified with the emergency service authority during development of
the specification and be included in this area
6.2
Contact Persons
(A)
Metropolitan Fire Service:
Mr / Ms .....................................
.....................................
.....................................
Telephone: ....................
(B)
Country Fire Service:
Mr / Ms .....................................
.........................................
.........................................
Telephone: ...........................
(C)
South Australia Police (SAPOL):
Mr / Ms .....................................
........................................
........................................
Telephone: ..........................
(D)
Marine Authority:
Mr / Ms .....................................
.........................................
.........................................
Telephone: ..........................
7.
SUPPLY OF WATER
Details for rural projects to be included.
8.
TEST PROCEDURES
Notwithstanding the Test Procedures (TP) listed in the Clause "Test Procedures" in each Part the following test
procedures are applicable to this Contract:
TP 765 Determination of Total Dissolved Salts of Abrasive Blast Medium
TP 913 The Measurement of Dry Film Thickness of Coatings on Steelwork (Abrasive Blast Cleaned)
TP 911 Water Sediment Testing – Lead Abatement Projects
TP 912 Air Monitoring-Lead Abatement Projects
TP 914 Soil Testing – Lead Abatement Projects
9.
ACCESS FOR PRINCIPAL TO INSPECT AND UNDERTAKE REPAIRS
The Principal will require access to the scaffolding to carry out various maintenance, concrete and electrical wiring
repairs.
____________
DPTI XXCxxx
Page 9
Revision 0
Specification: Contract Specific Requirements 112
112
UTILITY SERVICES
1.
SPECIAL REQUIREMENTS AND CONTACT PERSONS OF SERVICE AUTHORITIES
1.1
Special Requirements
Any special conditions/requirements must be identified with the service authority during development of the
specification and be included in this area. Removal of hazardous items or substances, such as asbestos
conduits/pipes and pits require a special payment item in the Schedule.
1.2
Contact Persons
(A)
Telecommunications:
Mr / Ms .....................................
.....................................
.....................................
Telephone: ....................
(B)
Water Supply Authority:
Mr / Ms .....................................
.........................................
.........................................
Telephone: ...........................
(C)
Electricity Authority:
Mr / Ms .....................................
........................................
........................................
Telephone: ..........................
(D)
Gas Authority:
Mr / Ms .....................................
.........................................
.........................................
Telephone: ..........................
A Gas Authority representative shall be on site during excavation near gas mains and any damage to the protective
coating of the gas main shall be reported immediately.
___________
DPTI XXCxxx
Page 10
Revision 0
Specification: Contract Specific Requirements 120
120
1.
PROVISION FOR TRAFFIC
GENERAL
The amount submitted for the item for traffic provisions and control in the Schedule of Quantities and Prices /
Schedule of Rates shall not be less than 3% of the Contract Sum.
2.
ADDITIONAL TRAFFIC PROVISIONS
3.
CONSTRAINTS
The Contractor shall not detour traffic without the written approval of the Superintendent.
The Contractor shall not detour traffic along council roads without the written approval of the relevant council. The
Contractor shall submit to the Superintendent a copy of the council approval for the detour no later than 24 hours prior
to operation of the detour.
Example for urban contracts
Lane restrictions and speed limits less than 60 kph are not permitted on Port Wakefield Road during the following
peak hour times:

6.30 a.m. - 9.00 a.m. Monday - Friday

3.30 p.m. – 7.00 p.m. Monday - Friday
General
Provision for traffic movements on roads affected by the Works shall be maintained at all times.
Traffic restrictions will not be allowed on Cross Road-, Unley Road, Belair Road and Goodwood Road Intersection
during the following "peak" hours:
6.30 a.m. - 9.30 a.m. Monday - Friday
3.00 p.m. - 6.30 p.m. Monday - Thursday
3.00 p.m. - 7.00 p.m. Friday
9.00 a.m. - 12 noon Saturday (at intersections with Goodwood Road and Unley/Belair Roads, excluding
for installation of Main Drain).
At all other times, the Contractor shall allow a minimum of:
Belair Road / Unley Road / Cross Road Intersection
(a) One 3.2 m wide sealed through lane, one right turn lane and one left turn lane on Cross Road.
(b) Two 3.2 m wide sealed through lanes in each direction on Unley Road and Belair Road. (The Contractor
may only close the left turn lane on Belair Road during the construction of the Main Drain at the
intersection).
(c) One 3.2 m wide sealed right turn lane on Unley Road and Belair Road.
Goodwood Road / Cross Road Intersection
(d) One 3.2 m wide sealed through lane, one right turn lane and one left turn lane on Cross Road.
(e) Two 3.2 m wide sealed through lanes on Goodwood Road.
(f) One 3.2 m wide sealed right turn lane in each direction on Goodwood Road.
Other Locations
(g) One 3.2 m wide sealed lane in each direction on Cross Road.
DPTI XXCxxx
Page 11
Revision 0
Specification: Contract Specific Requirements 120
(h) Two 3.2 m wide sealed lanes in each direction on Unley Road and Belair Road.
(i) Two 3.2 m wide sealed lanes in each direction on Goodwood Road.
(j) One 3.5 m wide lane in side streets.
4.
LANE OCCUPANCY
The Contractor must not work or otherwise disrupt traffic at the times and locations specified in the following table:
LOCATION
PROHIBITED WORK TIMES
Main Road, Chainage 250 – 570, northbound
4.30 pm to 6.00 pm
Main Road, Chainage 150 – 570, northbound
7.30 am to 9.00 am
If the Contractor works or otherwise disrupts traffic at the times specified above, the Contractor agrees that the
payment due to the Contractor will be reduced by the applicable amount specified in the following table:
PAYMENT REDUCTION
$200.00 for increments of 15 minutes within 30 minutes that the traffic does not have lane
availability.
$500.00 for increments of 15 minutes within 30 to 60 minutes that the traffic does not have lane
availability.
$750.00 for increments of 15 minutes in within 60 to 120 minutes that the traffic does not have lane
availability.
$1 000.00 for increments of 15 minutes in excess of 120 minutes that the traffic does not have lane
availability.
Reduction in payments will not apply where the Superintendent has directed work during the times specified above.
5.
ROAD SAFETY AUDITOR
Endorsement of the Traffic Management Plan by a Road Safety Auditor (Clause 120.2.1) is required.
6.
NOTIFICATION OF ROAD WORKS
The Contractor shall erect advance notice signs (TES 13004-1) at the locations listed below.
Specify: location and number of signs required, dates applicable and whether the Principal will supply the signs.
Detailed TES drawings for inclusion in contract documents are available from Statewide Operational Coordination
Group,
The Contractor shall remove the signs upon completion of the Works.
7.
COUNCIL LIAISON
The Contractor shall arrange a meeting with the Superintendent and relevant Council Contract Person (refer to
Part 110).
8.
NIGHT WORK
The Contractor shall undertake work at night only with the approval of the Superintendent. All night work shall
DPTI XXCxxx
Page 12
Revision 0
Specification: Contract Specific Requirements 120
be in accordance with DPTI Operational Instruction No. 21.7 “Management of Noise and Vibration: Construction
and Maintenance Activities”.
Constraints
Specify Restrictions / limitations
Hours proximity to dwellings
Noise
Machinery
Specify
Approvals required
Specify
Notification requirements. To locals.
9.
DPTI PUBLIC TRANSPORT DIVISION REQUIREMENTS AND CONTACT PERSON
Example for urban contracts which affect Bus Stops
a)
General
Bus stop poles shall be relocated and temporary bus stops established as required. Relocation of bus stops shall be
appropriate to the traffic movements at that time.
The Contractor shall ensure that pedestrian access to bus stops is maintained at all times.
The Contractor shall not remove or move bus stops without the written consent of the DPTI Public Transport
Division and then not until it is necessary to carry out the Works. Seven days notice shall be given to the
Superintendent and the DPTI Public Transport Division prior to the removal of any bus stop shelter.
Bus stop shelters shall be removed by the Contractor and delivered to/stored by the Contractor.
Bus stop shelters shall be reinstated by the Contractor.
Delivery and repair of any damage caused by the removal shall be at the Contractor's expense.
Bus stop poles shall be set in concrete. Existing concrete surrounding bus stop poles and shelter footings shall be
removed and disposed of off site.
The DPTI Public Transport Division contact person is:
Mr ...................................
DPTI Public Transport Division
136 North Terrace
ADELAIDE 5000
Telephone: ........................
Example for urban contracts which affect access to Bus Routes or Bus Stops
The Contractor shall ensure that pedestrian access to bus stops is maintained at all times.
The Contractor shall liaise with the DPTI Public Transport Division prior to commencing work when access to bus
stops is impacted by the Works. Seven days notice shall be given to the Superintendent and the DPTI Public
Transport Division.
The DPTI Public Transport Division contact person is:
Mr ...................................
Telephone: ........................
DPTI Public Transport Division
136 North Terrace
DPTI XXCxxx
Page 13
Revision 0
Specification: Contract Specific Requirements 120
ADELAIDE 5000
10.
TEMPORARILY TRAFFICKED AREAS
Earthworks
Earthworks shall be constructed in accordance with the requirements of Part 210 "Construction of Earthworks".
All fill shall have a Plasticity Index less than 18 when tested in accordance with TP 141. Batter slopes shall be no
steeper than 2 horizontal to 1 vertical.
When no longer required, temporarily trafficked areas shall be rehabilitated and suitable excavated material
incorporated in the permanent work.
Pavement
a)
Subbase
200 mm minimum compacted thickness of PM2/20 20 mm Class 2 Pavement Material placed in one layer and
compacted to not less than 96%.
b)
Base
150 mm minimum compacted thickness of PM1/20 20 mm Class 1 Pavement Material placed in one layer and
compacted to not less than 98%.
The minimum frequency of compaction testing shall be one test per 300 square metres per layer.
c)
Ramps
Shall be shaped and span the access or egress point to allow restricted traffic movement.
Ramps to side streets shall be constructed, from materials capable of meeting all traffic loadings, shaped and
compacted to not less than 90%.
Ramps to residential or commercial premises shall be from local fill or quarry rubble.
Drainage
The Contractor shall adequately drain temporarily trafficked areas. This shall include the installation of temporary
culverts where necessary.
Surface Treatment
All temporarily trafficked areas shall be sealed prior to opening to traffic.
The surface treatment shall be a primerseal and a surface course of a minimum thickness of 30 mm of AC10
asphalt. (spray seal for rural jobs)
The constraints on asphalt work with respect to weather conditions (detailed in Clause 228.4 "Constraints to the
Placement of Asphalt") do not apply to temporarily trafficked areas. All other aspects of sealing work shall comply
with Part 226 "Application of Sprayed Bituminous Surfacing" and Part 228 "Construction of Asphalt Pavements".
Pavement Marking
Temporary pavement marking shall be applied to sealed temporarily trafficked areas prior to opening to traffic.
Temporary pavement marking shall consist of a minimum of 100 mm wide continuous separation line applied in
accordance with Part 246 "Application of Pavement Marking".
Removal
The temporary pavement marking and temporarily trafficked areas shall be removed when no longer required.
DPTI XXCxxx
Page 14
Revision 0
Specification: Contract Specific Requirements 120
Where the shoulder has been sealed for the purpose of traffic management, the Contractor shall remove the seal
when no longer required and rehabilitate the shoulder to the standard specified.
Standard of Construction Of Temporarily Trafficked Areas
The standard of construction shall be:
Width
12 m
Crossfall
3%
Minimum radius on a curve
300 m
Maximum grade
5%
Maximum change in grade without a vertical curve
1%
Minimum length of vertical curve shall be calculated using the formula L = KA
where
11.
L = length of vertical curve,
K = length required for each 1% change in grade = 15 m,
A = change in grade %.
TEMPORARY PAVEMENT MARKINGS
All temporary road markings shall be in accordance with Part 245 “Supply of Materials for Pavement Marking”.
The Contractor shall supply and install temporary road markers where any pavement marking is completely
removed. Temporary road markers shall be placed on all separation lines, on the outlines of painted medians and
on the edgelines of overtaking lines and intersections to assist with lane delineation, unless otherwise directed by
the Superintendent.
For centreline delineation, temporary road markers shall be installed at
(a) 24 metre spacing where the posted speed limit is 80 km/h; and
(b) 12 metre spacing where the posted speed limit is less than 80 km/h.
For the edge line delineation the temporary road markers shall be installed at 24 metre spacing.
Stop bars and give way bars which require removal or will be covered shall have their locations marked prior to
commencing work. All stop bars and give way bars shall be reinstated prior to opening to traffic as follows:
(c) White road marking paint or similar product approved by the Superintendent.
(d) Bar width to be 150 mm.
12.
TEMPORARY BARRIERS
e.g. Ex Bakewell Bridge
Temporary longitudinal barriers shall comply with AS/NZS 3845 “Road safety barrier systems” and be approved
for use by the Principal.
The DPTI register of temporary longitudinal barrier systems that have been approved for use is available on
request. The use of the barrier system selected by the Contractor must conform to the conditions imposed as part of
the approval.
Specify:
 location
 extent
 type of temporary longitudinal barrier required for traffic separation,
From known
DPTI XXCxxx
Construction risks.
Page 15
Revision 0
Specification: Contract Specific Requirements 120
Opposing traffic movement. (high-speed and/or high traffic volumes are involved)
Hazardous locations
Work zone protection
(OHS& W risks)
Pedestrian movements.
DPTI XXCxxx
Page 16
Revision 0
Specification: Contract Specific Requirements 120
Example for a sealing contract
2.
GENERAL
Traffic control shall be such as to protect the safety of the public and ensure that traffic does not damage the work
during the period the binder requires to develop sufficient adhesion and strength.
In addition to Clause 2 "Traffic Management", the Contractor shall prepare Traffic Management Plans while work
activities are being undertaken and plans for the period when no activities are being undertaken. Some jobs within
Appendix 1 “Work Summary” may also require unique and different plans. For the plans when no activities are
being undertaken, at a minimum the plans shall address issues such as "Road Works Ahead" signs, 80 km/h signs,
repeater signs, signage on side roads, spacing of temporary raised pavement markers and "No Lines" signs.
If linemarking work is being undertaken using a ‘mobile work site’, the Contractor shall undertake the work within
the designated worksite using 60 km/hr signs or with the use of a crash cushion on the pilot vehicle.
The Contractor shall not delay traffic for longer than 20 minutes.
The Contractor shall supply and place "Road Under Repair Expect Long Delay" signs as directed by the
Superintendent’s Representative prior to commencement of sealing operations. The Contractor shall remove these
signs at the end of sealing operations on each day.
Restriction to traffic shall only occur when work is in progress.
The length of road closure shall not exceed 500 metres. All lanes shall be open to traffic when the Contractor is not
on site.
Due to the need to maintain a high standard of safety for road users, the placement of pavement markings soon as
practicable after the completion of the bituminous works.
The Contractor shall be responsible for traffic management and safety for the road users until installation of the
pavement marking and the installation of the raised pavement markers. Immediately following the application of
paint and the installation of the raised pavement markers, and the removal of all temporary raised pavement markers,
all aftercare signage shall be removed, unless a fault with the seal is evident or otherwise directed by the
Superintendent. All temporary raised pavement markers must be cut off at ground level.
Access to schools, commercial businesses etc. sited adjacent to the works shall be maintained at all times.
Parked vehicles maybe encountered on some AE’S, in particular AE237, 242 and 262. The Contractor shall liaise with
the relevant Council to arrange temporary parking restrictions.
_________
DPTI XXCxxx
Page 17
Revision 0
Specification: Contract Specific Requirements 130
130
SURVEY
1.
SURVEY SETTING OUT AND VERIFICATION CERTIFICATES - ROADWORKS
2.1
Setting Out
The Surveyor shall set out the following works:
(a) Drains and drainage structures other than the culverts at property accesses.
(b) Light pole footings.
(c) Levels for asphalt overlay, refer Clause 227.10 "Setting Out".
(d) ................
2.2
Verification Certificates
The Contractor shall provide the following verification certificates vide Clause 8 "Verification Certificates":
String label
chainage at
interval of
reference
string
Offset from
reference
string
Design
level
Actual
level
Difference
between actual
and design
levels
Displacement
from horizontal
position
Stripping
Topsoil
yes
yes
-
-
-
-
Fills
yes
yes
-
?
?
-
Subgrade
yes
yes
yes
yes
yes
-
Subbase
yes
yes
yes
yes
yes
-
Base
yes
yes
yes
yes
yes
-
Earth Drains
yes
yes
yes
yes
yes
yes
Kerb and
Gutter
yes
yes
yes
yes
yes
yes
Median Kerb
type 2, 3, 4,
4A
yes
yes
yes
yes
yes
yes
Median Kerb
type 1, 5, 6,
7, 8
yes
yes
-
-
-
yes
Pipes and
box culverts
-
-
yes
yes
yes
yes
Drainage
structures
-
-
yes
yes
yes
yes
yes
yes
yes
yes
yes
yes
Lighting
Additional information provided for:
Stripping Topsoil
The verification certificate shall confirm that stripping of topsoil was confined to the chainages set out in the
Geometric Details applicable to the Reference String, top of batter and batter interface string.
Additional strings shall be taken as necessary to define the stripped surface, but shall not be spaced at distances
exceeding 20 m.
DPTI XXCxxx
Page 18
Revision 0
Specification: Contract Specific Requirements 130
Cuts / Fills
The verification certificate shall confirm that fills are located within the horizontal tolerances specified in
accordance with the chainages set out in the Geometric Details applicable to the Reference String, top of batter and
batter interface string.
Where the length of batter exceeds 15 m additional data shall be obtained at the batter mid-point.
Verification certificates shall be accompanied by cross section plots on transparent or translucent film. The plots
shall be to the same scale and shall reference the same datum and chainages as those shown on the Drawings. In
each case the reference string locations shall be indicated.
Subgrade, Subbase, Base and Earth Drains
The verification certificate shall confirm that pavement layers are located within the horizontal tolerances specified
in accordance with the chainages set out in the Geometric Details for the applicable reference string and:
Edge of shoulder strings for subgrade and subbase,
Edge of bitumen strings for base, except for unsealed roads where the edge of shoulder string shall be
referenced.
Drainage string for earth drains. This shall be verified every 10 m.
Kerb, Kerb and Gutter, Side Drains, Property Crossovers and Dish Drains
The verification certificate shall confirm that kerb, kerb and gutter, side drains, property crossovers and dish drains
are set out at the chainages listed in the Geometric Details in accordance with the applicable strings indicated on
the Drawings for those elements of work.
Culverts and Drainage Structures
The verification certificate shall confirm that culverts and drainage structures are located within the horizontal
tolerances specified in accordance with the chainages set out in the Geometric Details applicable with the strings
indicated on the drawings for those elements of work.
For culverts, levels shall be taken at the inlet and outlet and at intervals not exceeding ... m (e.g. 50 m) along the
length of the culvert. For drainage structures, an invert level is required.
2.
SURVEY SETTING OUT AND VERIFICATION CERTIFICATES - STRUCTURAL
2.1
Setting Out
The Surveyor shall provide the following:
(a) Prior to commencement of construction, a certificate showing details of setting out points for the
construction of the bridge.
(b) Certification for the following items:
(i) Setting out of pile locations prior to pre-drilling and/or driving.
(ii) Setting out and levels of footings prior to placing concrete.
(iii) Setting out and levels of piers prior to placing concrete.
(iv) Setting out and levels of abutment sill prior to placing concrete.
(v) Setting out and levels of deck prior to placing of concrete.
(vi) Setting out and levels of kerb and gutter prior to placing concrete.
(vii) Setting out and levels of bearing pedestals.
For (v) the following shall apply:
DPTI XXCxxx
Page 19
Revision 0
Specification: Contract Specific Requirements 130
(hogs in beams, allowance for deflections, adjustment of design levels??? - to be followed up with
Structural Services).
2.2
Verification Certificates
The Surveyor shall provide the following verification certificates:
(a) Alignment and spacing of piles on completion of driving.
(b) Span lengths and location and levels of bearing pedestals.
(c) Alignment and levels of deck after placing concrete.
(d) Alignment and levels of kerb and gutter after placing of concrete.
(e) Alignment and position of Reinforced Soil Structures (vide Clause 420.5.4).
These verifications shall be accompanied by sketches showing relevant details. For items (c) and (d), the sketches
shall show design levels (amended as necessary to compensate for hogs in beams) and actual levels.
__________
DPTI XXCxxx
Page 20
Revision 0
Specification: Contract Specific Requirements 140
140
1.
QUALITY SYSTEMS
SPECIFIC PROCEDURES
Procedures shall be submitted with the Quality Plan as part of the Post Tender Submission except for bituminous
work and .......... .......... which shall be submitted at least 4 weeks prior to such work commencing.
The Contractor's Procedures shall at a minimum address the following:
(a) The location of services, vide Clause 110.11 "Utility Services"
(b) The procedures listed in Clause 2 "Quality Requirements" of the following Parts:
Part 215
Supply of Pavement Materials
Part 220
Pavement
Part 221
Unstabilised Granular Pavement
Part 222
Plant Mixed Cement Stabilised Pavement
Part 223
Construction of Insitu Stabilised Pavement
Part 224
Construction of Insitu Foam Bitumen Stabilisation
Part 226
Application of Sprayed Bituminous Surfacing
Part 227
Supply of Asphalt
Part 228
Construction of Asphalt Pavements
Part 229
Slurry Surfacing
Part 232
Thin Asphalt Surfacing
Part 237
Pavement Crack Sealing
Part 243
Supply and Installation of Wire Rope Safety Barrier Systems
Part 244
Construction of Concrete Safety Barrier Systems
Part 246
Application of Pavement Marking
Part 247
Application of Audio Tactile Profiled Edge Lining
Part 280
Supply of Guide Posts and Delineators
Part 305
Steel Reinforcement
Part 310
Formwork
Part 320
Concrete
Part 330
Precast Concrete Units
Part 336
Heat Accelerated (Hot Water) Curing of Precast Units
Part 410
Earthworks for Structures
Part 415
Driven Piles
Part 416
Cast-in-Place Concrete Piles
Part 422
Soil Nailing
Part 425
Prestressed Concrete Work
Part 426
Incrementally Launched Superstructure (Prestressed Concrete)
Part 428
Fibre Reinforced Polymer Composite Strengthening of Concrete Structures
Part 430
Fabrication and Erection of Structural Steelwork
Part 435
Protective Treatment of Structural Steelwork
Part 436
Protective Treatment of Structural Steelwork – Previously Coated
Part 437
Galvanizing
Part 440
Bearings
Part 445
Deck Expansion Joints
2.
ADDITIONAL QUALITY SYSTEM REQUIREMENTS
If the Superintendent does not release Hold Points (e.g. Contractor or Independent Verifier releases them, details
must be included here. Note that Clause 140.7 defaults to the Superintendent releasing hold points.
DPTI XXCxxx
Page 21
Revision 0
Specification: Contract Specific Requirements 140
Change the number of controlled copies of accepted Quality Plan in Clause 3.1 if not 2.
3.
LOT MANAGEMENT SYSTEM
3.1
General
The Contractor shall supply, maintain and utilise either of the following for the Lot Management System:
(a) "QC Project" proprietary software licensed to SpectraQest Pty. Ltd. (Contact: Mr. Dirk Janek, telephone:
(08) 8212 0700).
(b) An electronic system using Microsoft software.
The details of the Lot Management System shall be submitted as the Post Tender Submission. The information shall
be submitted within 7 days of written request.
3.2
Minimum Requirements for Lot Management System using Microsoft Software
The Contractor’s Lot Management System shall provide the Superintendent with the ability to concurrently view
and down load via an Ethernet link the following information at all times:
(a) Lot Register Report, providing for each lot (see attached sample detailing the minimum requirements):
(i) description and location of lot
(ii) lot measurement
(iii) lot conformance status and the disposition and status of non-conformances.
(b) Non-conformance Report Register (see attached sample detailing the minimum requirements).
(c) Corrective Action Report Register (see attached sample detailing the minimum requirements).
(d) Separate Report Registers for asphalt, bituminous products and concrete used in structures, (with a span
greater than 1.8 m) detailing all test reports including the specification limits. This shall be electronically
forwarded fortnightly to a person nominated by the Superintendent (see attached sample detailing the
minimum requirements).
(e) Survey certificates with accompanying data in Microsoft Excel format.
Within the above constraints, the Contractor shall determine the design and layout of the system. Information shall
be displayed in a logical manner with sort capabilities.
The Contractor shall ensure that the Superintendent has access to any NATA certificate or test result at all times.
3.3
Requirements for Hardware and Software
The Contractor shall provide and install in the Superintendent’s office the following minimum hardware and
software for the exclusive use of the Superintendent’s site staff for the duration of the Contract:
(a) A Pentium 4 personal computer (including keyboard and 17" screen) with Windows 2000 or Windows XP
and the current version of Microsoft Office.
(b) VET Anti-Virus software with continuous upgrades.
(c) 3COM Fast Etherlink 10/100 network card or similar that will permit the effective operation of data
viewing between the Contractor and the Superintendent’s site staff.
(d) Ethernet link socket.
(e) A digital camera with minimum 3 times optical zoom and 2.0 megapixels, using AA batteries, and
accessories including spare memory card, Universal AC adaptor to suit, 2 sets of AA size Nickel Cadmium
batteries, battery charger to take 4 AA size Nicad batteries, cables and software.
The Contractor shall install the Etherlink and associated software between the Superintendent’s and the
Contractor’s computer and shall be responsible for insurance and maintenance of equipment provided to the
Superintendent’s site staff.
DPTI XXCxxx
Page 22
Revision 0
Specification: Contract Specific Requirements 140
The Contractor’s responsibility for maintaining its computer equipment and that provided to the Superintendent’s
site staff shall be extended to cover the following instances:
(a) In the event of failure of the Contractor’s hardware, the costs associated with the reinstallation of the
operating system shall be borne by the Contractor.
(b) In the event a virus infects the system, the Contractor shall immediately arrange for its removal and
bringing the system back to fully operational status and all associated costs shall be borne by the
Contractor.
3.4
Backup of Data
The Lot Management System shall be backed up. A set of disks (or tapes) shall be cycled to ensure recovery is
possible in the case of lot or damaged data. The following process shall be adopted:
DISK/TAPE
1
2
3
4
5
6
3.5
USED ON
Monday
Tuesday
Wednesday
Thursday
First and third Friday of every month
Second and last Friday of every month
Payment
Separate payment will not be made for the Lot Management System and supply of equipment to the Superintendent.
4.
PERIODIC CERTIFICATION OF QUALITY SYSTEM
The QMR shall prepare a certificate at intervals not greater than 3 months and immediately prior to Practical
Completion which certifies that the Contractor has:
(a) established, implemented and maintained a Quality System in accordance with AS 9001 "Quality
Management Systems – Requirements", which includes Clause 7.3 of the Standard;
(b) recorded and submitted all records necessary to demonstrate conformance with the requirements of the
Contract; and
(c) complied with and satisfied the requirements of Part 140 “Quality System Requirements” and Part 705
“Quality Management Requirements for Design”
The certificates shall be forwarded to the Superintendent and signed by the QMR and the Contractor’s
Representative
(A sample of the proposed certificate should be requested at Tender time and examined prior to Contract award).
DPTI XXCxxx
Page 23
Revision 0
Specification: Contract Specific Requirements 140
SAMPLE OF LOT REGISTER REPORT
LOT
NO.
DESCRIPTION
C/WAY
LOCATION
DATE
OPENED
DATE
SUBMITTED
DATE
CLOSED
CONTRACTOR
QUANTITY
DPTI
QUANTITY
____________
DPTI XXCxxx
Page 24
UNIT
AGREED
QUANTITY
CUMULATIVE
AGREED
QUANTITY
PP No.
COMMENT
NCR
No.
S
O
C
Revision 0
Specification: Contract Specific Requirements 150
150
1
ENVIRONMENTAL MANAGEMENT REQUIREMENTS
ENVIRONMENTAL MANAGEMENT REPRESENTATIVE
The Environmental Management Representative (EMR) shall:
(a) be ‘on call’ when works are in progress,
(b) shall not be the Contractor's Site Representative (refer Special Conditions of Contract, Clause 3
"Contractor's Personnel"),
(c) possess a recognised tertiary environmental qualification and have recent relevant experience to the
position in environmental management of similar projects.
(d) possess an appropriate knowledge and ability to identify weed species outlined in the Weed Management
Plan,
(e) have authority to:
(i) enforce the implementation of all measures to mitigate, avoid or minimise adverse environmental
impacts,
(ii) stop the progress of any part or element of the Contractor’s Work that does not comply with the
environmental documents, until such time as the non-compliance has been rectified,
(f) be engaged in the Contractor’s work exclusively for environmental management and environmental issues
and,
(g) not allow any other duties to take precedence over duties related to the operation of the Contractor’s
Environmental Management System.
2
PERIODIC CERTIFICATION OF ENVIRONMENTAL SYSTEM
The Environmental Management Representative shall prepare a certificate at intervals not greater than 3 months
and immediately prior to Practical Completion which certifies that:
(a) the Contractor's Environmental Management System is in accordance with AS/NZS ISO 14000;
(b) Subcontractors' Environmental Management Systems which form a part of the Contractor's Environmental
Management System were in accordance with AS/NZS ISO 14000;
(c) the Contractor complied with and satisfied the requirements of the Contractor’s Environmental
Management Plan; and
(d) documentation was recorded and submitted to the Superintendent in accordance with the Specification.
The certificates shall be forwarded to the Superintendent and signed by the Environmental Management
Representative and the Contractor’s Representative.
(A sample of the proposed certificate should be requested at Tender time and examined prior to Contract award).
__________
DPTI XXCxxx
Page 25
Revision 0
Specification: Contract Specific Requirements 150
150
3
ENVIRONMENTAL MANAGEMENT REQUIREMENTS
ENVIRONMENTAL MANAGEMENT REPRESENTATIVE
The Environmental Management Representative (EMR) shall:
(h) be ‘on call’ when works are in progress,
(i) not be the Contractor's Site Representative (refer Special Conditions of Contract, Clause 3 "Contractor's
Personnel"),
(j) possess a recognised tertiary environmental qualification and have recent relevant experience to the
position in environmental management of similar projects.
(k) possess the qualifications and experience as stated in the Contract Specific Requirements Part 110,
Clause 5 “Contractor's Personnel”,
(l) possess an appropriate knowledge and ability to identify weed species outlined in the Weed Management
Plan,
(m) possess the skills to facilitate an induction and training program for all persons involved in construction
activities,
(n) have authority to:
(i) enforce the implementation of all measures to mitigate, avoid or minimise adverse environmental
impacts,
(ii) stop the progress of any part or element of the Contractor’s Work that does not comply with the
environmental documents, until such time as the non-compliance has been rectified,
(o) be engaged in the Contractor’s work exclusively for environmental management and environmental issues,
(p) not allow any other duties to take precedence over duties related to the implementation of the Contractor’s
Environmental Management Plan, and
(q) attend the work site a minimum of two days per week until the Date of Practical Completion, with
responsibility to develop and implement the Contractor’s Environmental Management Plan. The EMR may
be required to attend the site more than two days per week, subject to environmental performance as
determined by the Superintendent.
4
REPORTING ON ENVIRONMENTAL MANAGEMENT SYSTEM
The Environmental Management Representative shall prepare a report at intervals not greater than 3 months and
immediately prior to Practical Completion, which identifies that:
(e) the Contractor's Environmental Management System is in accordance with AS/NZS ISO 14000;
(f) Subcontractors' Environmental Management Systems, which form a part of the Contractor's Environmental
Management System, were in accordance with AS/NZS ISO 14000;
(g) the Contractor complied with and satisfied the requirements of the Contractor’s Environmental
Management Plan; and
(h) documentation was recorded and submitted to the Superintendent in accordance with the Specification.
The report shall be forwarded to the Superintendent and signed by the Environmental Management Representative
and the Contractor’s Representative.
3.
ENVIRONMENTAL AUTHORISATIONS
The Contractor shall obtain a project specific authorisation under the Environment Protection Act 1993 for any
'prescribed activity of environmental significance' as defined in Schedule 1 that may be undertaken as part of the
works. This includes but is not limited to Earthworks Drainage, Hotmix Asphalt Plant and Concrete Batching
Works.
Any sub contractors undertaking works associated with any of the above mentioned activities of 'environmental
significance' shall obtain an exemption from obtaining a licence under Section 37 of the Environment Protection
Act 1993.
DPTI XXCxxx
Page 26
Revision 0
Specification: Contract Specific Requirements 150
__________
DPTI XXCxxx
Page 27
Revision 0
Specification: Contract Specific Requirements 155
155
1
ENVIRONMENTAL PROTECTION ISSUES
INDUCTION
The Contractor shall provide an environmental induction for all persons involved in construction activities, which
shall be delivered by the Environmental Management Representative.
The environmental induction is to include, but is not limited to [select from list below the issues that are applicable
to the project]]
(a) Purpose, objectives and key issues of the Contractor’s Environmental Management Plan
(b) Conditions of environmental licences, permits and approvals
(c) Emergency response procedures and reporting process for environmental incidents
(d) Site specific issues such as boundaries for vegetation clearing, location of refuse bins, refuelling and
maintenance of vehicles, plant and equipment
(e) Weed identification and practices to minimise the spread of weeds
(f) Practices to avoid the spread of phytophthora
(g) Aboriginal heritage issues including identification of Aboriginal heritage sites and procedures to be
followed in the event of discovery of Aboriginal heritage sites
(h) Location and management of non-Aboriginal heritage places
(i) Management of dust from construction activities
(j) Greenhouse gas emission reduction techniques
(k) Management of construction noise and approvals required, especially during night works
(l) Contamination management procedures
(m) Protection of specific flora and/or fauna including management requirements
(n) Soil erosion and drainage management measures.
2
CARE OF REMAINING VEGETATION
The following trees have been identified as [insert special characteristic of trees, eg, having local heritage
significance, Regulated Trees]:
(a) [identify trees]
The Contractor shall contact the Superintendent 5 working days prior to works occurring within the vicinity of these
trees, to allow for agreement on the work activity zone and methods.
The Contractor shall determine the Tree Protection Zone (TPZ) for these trees in accordance with AS4970, and
shall comply with the tree protection measures set out in AS4970, including: [select from the following as relevant]
(a) Installing protective fencing to prevent machinery accessing the TPZ
(b) Installing signage identifying the TPZ
(c) Installing protection to the trunk and branches of the tree(s)
(d) Installing ground protection measures within the TPZ to prevent root damage and soil compaction.
[Insert any revegetation requirements]
3
FAUNA PROTECTION
The Contractor shall provide 5 working days notice prior to removing the hollows:
(a) [identify hollows]
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
The Contractor shall remove these hollows with the supervision of the Superintendent or DPTI Environment Officer,
and store them in an approved secure storage area until required. Additional hollows discovered during the tree
removal works shall also be retained and stored within the secure storage area.
The Contractor shall place the hollows in agreed locations as directed by the Superintendent or DPTI Environment
Officer.
In the event that hollows are discovered during the tree removal works, the Contractor shall remove the hollows
carefully and notify the Superintendent. The Contractor shall store the hollows within a secure storage area until
instructed by the Superintendent or DPTI Environment officer.
Should any fauna be found injured on the site, Fauna Rescue SA on Ph: (08) 8289 0896, the RSPCA or a
veterinarian shall be contacted to provide advice and treatment. Any fauna found on site that is not injured but
needs to be relocated due to the construction works, should be relocated by a suitably qualified person to a similar
habitat to where it was found.
4
WEED, PEST AND DISEASE CONTROL
4.1 Weed management and control
The Contractor shall be responsible for removing and destroying all proclaimed weed species within the
Contractor’s Activity Zone prior to construction, and undertaking monitoring and control after construction to
control the re-establishment of these species. See details below / attached weed management plan.
The following species, which are known to exist at the project site, are declared weeds under the Natural Resources
Management Act 2004:
(a) [list species]
(b) [list species]
(c) [list species]
All weeds at a height greater than 400 mm must be slashed and weed control must be carried out in accordance
with Part 548 “Herbaceous and Woody Weed Control”.
All declared and environmental weed species shall be disposed of at a licensed waste depot or a suitable recycling
facility in line with Natural Resource Management Board guidelines.
Weed identification material shall be made available on site, to all the Contractor’s employees. Weed identification
shall be included in the Contractor’s induction procedure.
Any feral/pest fauna species found on the site that need to be removed due to construction works shall be taken to
the RSPCA or the Animal Welfare League for action at the Contractor’s cost.
The Contractor must obtain authorisation from the Natural Resources Management Board prior to transporting
these plants on a public road.
4.2 Phytophthora
4.2.1
General
Phytophthora has been identified as being present within or adjacent to the project site.
OR
The project site has been identified as being within or adjacent to a high risk Phytophthora site as defined in the
DPTI Operational Instruction 21.3 Phytophthora (Dieback) Control.
Phytophthora is a root rot fungus that kills many native and exotic plant species. The fungus can be spread through
the movement of infected soil, plant material and water. The amount of moisture in the soil, the soil type and
vegetation type combined with the location and extent of works are considered when determining low, medium and
high risk Phytophthora sites.
The DPTI Operational Instruction 21.3 Phytophthora (Dieback) Control classifies the site or zones within the site
as:
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
(a) “High risk site” - occur within high or moderate potential threat areas, typically low lying, high soil
moisture, adjacent to large areas of remnant vegetation and either infested or showing symptoms at
the site, or within 5km from a known infestation.
(b) “Medium risk site” – occur within high or moderate potential threat areas. The site is within or
adjacent to remnant vegetation, known susceptible species are present in or adjacent to the site and
the site uninfested but is more than 5 but less than 10km from a known infested site.
(c) “Low risk site” - occur within low potential threat areas where there is no remnant vegetation, in
urban/residential/developed/agricultural/industrial areas, greater than 10km from an infested and
contain non conductive soil types (limestone and sandy soils)
The overall management of Phytophthora shall comply with the Phytophthora control principles outlined in the
DPTI Operational Instruction 21.3 Phytophthora (Dieback) Control.
4.2.2
Responsibilities
A Phytophthora Hygiene Plan shall be included in the Contractor’s Environmental Management Plan (CEMP) for
high and medium risk sites The Phytophthora Hygiene Plan shall include;
(a) …
(b) …
(c) …
4.2.3
Training
All staff and subcontractors shall receive an Environmental Induction prior to starting work on the project that
includes relevant information and procedures to minimise the risk of spreading Phytophthora.
This will occur at
4.2.4
Known sites containing and adjacent to Phytophthora infestations
(a) The following sites have been identified as containing Phytophthora within the project area and must
be avoided during construction.
Between ……..roads and ………………road
Ch……… to Ch…… (or MM…… to MM…..)
(b) The following sites have been identified directly adjacent to the project area and must be bunted to
avoid vehicles and workers entering the area.
Between ……..roads and ………………road
Ch……… to Ch…… (or MM…… to MM…..)
4.2.5
Works Program
To minimise the potential spread of Phytophthora the following requirements for the works program are
required;
(a) …
(b) …
(c) …
4.2.6
Hygiene
Hygiene requirements shall be undertaken in accordance with the Hygiene guidelines for vehicles, equipment and
footwear in Appendix 2 of the DPTI Operational Instruction 21.3 Phytophthora (Dieback) Control.
For this project these are:
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
(a) …
(b) …
(c) …
4.2.7
Topsoil Removal
Topsoil shall be contained within the infected area or disposed of to a licensed waste depot in consultation with the
Superintendent. If off site disposal is required the material must be secured and contained to prevent any potential
to spread Phytophthora further.
4.2.8
Vegetation Management
The following measures are required:
(a) Use methods that do not disturb the soil such as mowing, slashing, hand-pruning or herbicide
application should be used in preference to grading
(b) Work outside the formation should be carried out in dry conditions only. Avoid drains where ever
possible
(c) Clearly mark on site the areas which have been identified as Phytophthora-infested
4.2.1
Vegetation Disposal
Trees for removal shall be cut a minimum of 1.5m above the ground. The vegetative material above this point
(upper trunk and canopy) can be considered Phytophthora free as long as it has not been in contact with soil, and
shall be mulched and retained on site.
OR
... shall be disposed of at the discretion of the Contractor. Vegetative material from weed species cut a minimum of
1.5m above the ground shall be disposed of in accordance with Part 155 Environmental Protection Issues – 3. Weed
Pest and Disease Control, and with Contract Specific Requirements 155 – 4.1 Weed Management and Control.
All vegetation under 1.5m, including tree stumps, shall be excavated, stockpiled at [insert secure location] (to
prevent unauthorised collection for firewood) and burnt once dry..
OR
Tree stumps shall be ground out in accordance with Part 540 Tree Pruning and Removal and Contract Specific
Requirements 540. The ground vegetative material is to be retained and spread on site. All other vegetation (native
and exotic) under 1.5m in height requiring clearance from within the Phytophthora infected area, shall be mulched
and retained on site.
If mulch and cleared vegetative material cannot be contained within the infected area, it must be disposed of at a
licensed waste depot in consultation with the Superintendent. If off site disposal is required, the material must be
contained to prevent any potential to spread Phytophthora.
4.2.9
Vehicle Movement
The following measures are required to minimise the risk of spreading of Phytophthora by vehicles:
(a) Contain movement of vehicles to formed areas wherever possible particularly in wet conditions
(b) All plant shall be cleaned prior to:

arriving at a site

moving to another high or medium priority site

transporting gravel and other construction materials
(c) Plant shall be cleaned or washed down in designated clean down areas
(d) Where possible, work should proceed from un-infested (Phytophthora-free) or status unknown sites to
known infested sites
4.2.10
Earthworks
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
The following measures are required to minimise the risk of spreading of Phytophthora during earthworks:
(a) Avoid leaving the road except under dry soil conditions.
(b) Avoid using tracked vehicles where possible as they are difficult to clean effectively
(c) Avoid grading beyond the areas previously graded (e.g. patrol grading)
(d) Conduct routine activities (e.g. grading) in “bounds” of several kilometres (e.g. 3-4 km), each
interrupted by a clean-down to minimise the exposure of vegetation to risk down-slope of the operation
The Contractor shall contain the movement of construction traffic to specific construction related areas, i.e.
road formation. Movement of trucks and light vehicles shall be limited to roads and access tracks
4.2.11
Clean Down Site - location and construction
Prior to the establishment of any "Dieback" clean-down site and the commencement of works, the Contractor shall
nominate the location of such site to the Superintendent. A HOLD POINT shall apply.
The contractor must comply with the requirements for clean down sites identified in the DPTI Operational
Instruction 21.3 Phytophthora (Dieback) Control.
Additional requirements for this project have been identified. These are:
(a)
(b)
(c)
4.2.12
Drains
To minimise the risk of spreading of Phytophthora when working in drains and/or culverts the following measures
are required:
(a)
(b)
(c)
(d)
Clean out or repair drains in dry conditions only
Avoid grading in watercourses or areas prone to flooding
Drain construction to avoid ponding of discharge water
Clean or wash down plant and equipment before moving away from a culvert or drain if working outside
formed areas
4.2.13
Kangaroo Island requirements
Phytophthora is known at a number of locations on Kangaroo Island and additional hygiene measures
apply. These measures are outlined in the DPTI Operational Instruction 21.3 Phytophthora (Dieback)
Control and include:
(a) Before leaving the mainland for Kangaroo Island clean (wash-down) all mobile plant and machinery.
(b) Avoid if possible any works off the seal (particularly grading of unsealed shoulders, drain maintenance and
sourcing of materials), particularly during the high-risk months of August to December.
(c) Gravel pits should be assessed to be Phytophthora-free prior to use to ensure that Phytophthora is not
introduced to Phytophthora-free or Phytophthora status-unknown areas
(d) A power wash-down unit shall be used for cleaning mobile plant and equipment. This is available for hire
from the District Council of Kangaroo Island.
(e) Before leaving Kangaroo Island for the mainland, clean (wash-down) all mobile plant and machinery.
(f) Specific requirements for the Playford Highway when undertaking off the seal works from Kingscote towards
Parndana.
Knet #3221569
Revision 0
5
Specification: Contract Specific Requirements 155
WATER QUALITY PROTECTION, EROSION AND SEDIMENT CONTROL
5.1 Water Quality Monitoring
The Contractor shall prepare and implement a Level [insert appropriate level] Water Quality Monitoring Program
(WQMP), in accordance with DPTI’s Water Quality Monitoring Manual for Construction Sites. The WQMP shall be
submitted with the SEDMP.
Stormwater retained in any basin or storage device shall be treated prior to discharge (including discharge to
groundwater) to the following standard:
(a) [insert desired standard]
The WQMP will detail proposed treatment methods.
Works undertaken within a watercourse shall comply with the following requirements:
(a) works shall not cause destabilisation of the bed and banks of the watercourse
(b) all excavated material must be removed from the watercourse and securely stored away from the watercourse
to ensure that it does not return to the watercourse
(c) any material placed in and around the bed and banks of the watercourse must be compacted to prevent the
movement of loose material and downstream sedimentation.
Should the proposed construction methodology involve dredging or earthworks drainage, the Contractor is
responsible for obtaining any licences required under the Environmental Protection Act 1993.
5.2 Soil Erosion and Drainage Management Plan
The SEDMP will specifically detail how intercepted groundwater collected during the course of the construction
activities will be managed and treated prior to release.
Detailed / Medium level / Simple SEDMP
A detailed SEDMP for the project shall be developed and include:
(a) North point and plan scale.
(b) Site and easement boundaries and adjoining roadways.
(c)
Construction access points.
(d) Site office, car park and location of stockpiles.
(e)
Proposed construction activities and limits of disturbance.
(f)
Retained vegetation including protected trees.
(g) General soil information and location of problem soils.
(h) Location of critical environmental values (where appropriate).
(i)
Existing site contours (unless the provision of these contours adversely impacts the clarity of the SEDMP).
(j)
Final site contours including locations of cut and fill.
(k)
Construction Drainage Plans for each stage of earthworks, including land contours for that stage of
construction, sub-catchment boundaries and location of watercourses.
(l)
General layout and staging of proposed works.
(m) Location of all drainage, erosion and sediment control measures.
(n) Full design and construction details (e.g. cross-sections, minimum channel grades, channel linings,) for all
drainage and sediment control devices, including Diversion Channels and Sediment Basins.
(o) Construction specifications for adopted Soil Erosion Drainage Management (SEDM) measures (as
appropriate).
(p) Site revegetation requirements (if not contained within separate plans).
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
(q) Site Monitoring and Maintenance Program, including the location of proposed water quality monitoring
stations.
(r)
Technical notes relating to:

site preparation and land clearing;

extent, timing and application of erosion control measures;

temporary SEDM measures installed at end of working day;

temporary SEDM measure in case of impending storms, or emergency situations;

installation sequence for SEDM measures;

site revegetation and rehabilitation requirements;

application rates (or at least the minimum application rates) for mulching and revegetation
measures;

legend of standard symbols used within the plans.
(s)
Calculation sheets for the sizing of SEDM measures.
(t)
A completed SEDMP checklist, such as presented in Appendix 155.1.
OR
A Medium level Soil Erosion and Drainage Management Plan shall be developed and include:
(i)
North point and plan scale.
(ii)
Site and easement boundaries and adjoining roadways.
(iii)
Construction access points.
(iv)
Site office, car park and location of stockpiles.
(v)
Proposed construction activities and limits of disturbance.
(vi)
Retained vegetation including protected trees.
(vii)
General soil information and location of problem soils.
(viii)
Location of critical environmental values (where appropriate).
(ix)
Existing site contours (unless the provision of these contours adversely impacts the clarity of the SEDMP).
(x)
Final site contours including locations of cut and fill.
(xi)
Construction Drainage Plans for each stage of earthworks, including land contours for that stage of
construction, sub-catchment boundaries and location of watercourses.
(xii)
General layout and staging of proposed works.
(xiii)
Location of all drainage, erosion and sediment control measures.
(xiv)
Site revegetation requirements (if not contained within separate plans).
(xv)
Site Monitoring and Maintenance Program, including the location of proposed water quality monitoring
stations.
(xvi)
Calculation sheets for the sizing of any SEDM measures.
(xvii)
A completed Soil Erosion and Drainage Management Plan checklist such as presented in Appendix 155.1
(xviii)
Any other relevant information the Regulatory authority may require to properly assess the SEDMP.
OR
A Simple Soil Erosion and Drainage Management Plan shall be developed and include:
(i)
North point and plan scale.
Knet #3221569
Revision 0
(ii)
Site and easement boundaries and adjoining roadways.
(iii)
Construction access points.
(iv)
Site office, car park and location of stockpiles.
(v)
Proposed construction activities and limits of disturbance.
(vi)
Retained vegetation including protected trees.
(vii)
General soil information and location of problem soils.
(viii)
Location of critical environmental values (where appropriate).
Specification: Contract Specific Requirements 155
(ix)
Existing site contours (unless the provision of these contours adversely impacts the clarity of the SEDMP).
(x)
Final site contours including locations of cut and fill.
(xi)
General layout and staging of proposed works.
(xii)
Location of all drainage, erosion and sediment control measures.
(xiii)
Site revegetation requirements (if not contained within separate plans).
(xiv)
Any other relevant information the Regulatory authority may require to properly assess the SEDMP.
6
CONSTRUCTION NOISE AND VIBRATION
The Contractor shall prepare and implement a Construction Noise and Vibration Management Plan (CNVMP) in
accordance with Operational Instruction 21.7 “Management of Construction Noise and Vibration”.
Select from the following additional clauses, as applicable to the project:
The Construction Noise and Vibration Management Plan shall be prepared by an appropriately qualified acoustic
engineer (defined as a Member of the Australian Institute of Engineers and eligible for membership in the
Australian Acoustical Society).
Heritage-listed items are located at [insert locations of heritage items or attach a schedule]. Heritage-listed items
shall be considered ‘sensitive structures’ for the purposes of determining upper vibration limits for damage to
structures.
DPTI will undertake pre-construction dilapidation surveys of [insert structures] and will arrange follow-up surveys
post-construction, if necessary, to ascertain whether the structures have sustained any damage as a result of
construction activities.
OR
The Contractor shall ensure that pre- and post-construction dilapidation surveys of [insert structures] are
undertaken by an appropriately qualified consultant, to ascertain whether the structures have sustained any damage
as a result of construction activities.
The Contractor shall ensure that short-term vibration levels at properties are less than or equal to the velocity limits
in DIN 4150, Part 3, Table 1 (or a similar approved Standard of guideline) for “Dwellings and buildings of similar
design and/or occupancy”. The Contractor shall implement a monitoring regime to enable post construction
verification that the limits in DIN 4150 were not exceeded at all sensitive locations, including State Heritage listed
places. This may include Building Condition Inspections and on ground vibration monitoring.
If the Contractor has caused structural damage to a building or structure of heritage significance, the Contractor
shall arrange for the repairs of damage required in a manner that is consistent with the character and fabric of the
item. Where approval under the Development Act is required, this shall be obtained by the Contractor prior to any
rectification or repairs of damage being undertaken. Repairs shall be determined and documented by a suitably
qualified heritage architect.
The Contractor shall undertake appropriate community consultation regarding construction noise in areas where
sensitive receptors are present as outlined in the TSD Operational Instruction 21.7 or as required by the regulatory
authority.
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
The Contractor shall prepare a Blast Management Plan in accordance with AS 2187.2 – 2006 Explosives – Storage
and Use of Explosives, where blasting activities are to occur within the project area. Submission of the Blast
Management Plan shall constitute a HOLD POINT.
7
AIR QUALITY AND DUST SUPPRESSION
In addition to those measures outlined in clause 2.6 of Part 155, the Contractor shall employ the following
construction methods to minimise the disturbance caused by dust and other airborne pollutants to persons on and in
the vicinity of the site (select from the list below):
(a) establishing appropriate dust-screen fencing to minimise the transfer of airborne pollutants from within the
site to adjacent areas
(b) limiting on-site vehicle speeds
(c) selecting appropriate surface materials for haul roads to minimise dust generation, eg gravel, bitumen seal
(d) spraying stockpiles with suitable stabilising agents and/or erecting dust screens around stockpiles
(e) removing dirt and mud from construction equipment before it leaves the Site (this can be achieved through the
use of shaker ramps, truck wash downs and wheel washes)
(f) locating stockpiles away from areas susceptible to disturbance by wind
(g) covering loads carried by trucks
(h) promptly removing any material that is spilt on to public roads or other sealed pavements
(i) progressively stabilising batter slopes and construction areas with a temporary cover crop or other soil
stabilising material/technique
(j) immediately establishing suitable cover crops over topsoil stockpiles or providing suitable alternative
covering
Continuous particulate matter monitoring (PM10) shall be undertaken by the Contractor to ensure the Site does not
compromise public health, nor cause an environmental nuisance. Monitoring shall be undertaken in accordance
with the requirements of any of the following Australian Standards (depending on equipment selected):
(d) AS 3580.9.6 (high volume sampler)
(e) AS 3580.9.7 (dichotomous sampler)
(f) AS 3580.9.8 (TEOM analyser)
(g) AS 3580.9.9 (low volume sampler
(h) AS 3580.9.11 (beta attenuation monitor)
Monitoring equipment shall be located in accordance with the requirements of AS 3580.1.1, and shall be positioned
in areas where air quality is likely to have the greatest impact on adjacent properties or create nuisance/
inconvenience to the public. PM10 concentrations should not exceed 60g/m3 for a 24hr average. Where the PM10
method selected does not provide continuous readings, the monitoring program shall be supplemented with
equipment that provides measurements for 1hr average concentrations. The Contractor’s site manager shall be
notified as soon as possible when PM10 1hr average concentrations are such that the 60 g/m3 24hr average limit
may not be achieved (e.g. by programming the equipment to provide notice), to enable the Contractor to modify
working methods or cease work if necessary.
The sampling frequency shall be a minimum of once per week for a 24 hour period during construction activities. If
a dust complaint is received, or if significant nuisance dust is visible, additional dust monitoring is recommended to
provide evidence of the Contractor’s general environmental duty under the Environment Protection Act 1993.
In addition to PM10 monitoring, the Contractor shall monitor Total Suspended Particulate Matter (TSP) in
accordance with the following requirements:
(a) TSP sampling shall be in conducted in accordance with Australian Standard 3580.9.3.
(b) The concentration of TSP shall be determined as a 24 hour average
(c) TSP monitoring shall be undertaken not less than every 3 days.
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
Results of Air Quality monitoring shall be made available to the Principal and SA EPA upon request. Monitoring
results shall be compared to background levels at [insert closest BOM monitoring station] (available from
www.bom.gov.au). Any corrective action measures taken as a result of dust monitoring shall be included in the
weekly report.
The Contractor will be provided access to DPTI-owned High Volume Air Quality samplers for sampling dust and
particulate matter and will be required to liaise with the DPTI environmental representative to ensure availability
of the sampling equipment. The Contractor will be responsible for the maintenance and calibration of this
equipment for the duration of their use.
8
RESOURCE USE
8.1 Water
The Contractor shall keep a record of water use and shall submit this record with each status report required under
Part 150, Clause 3.3, or upon request.
8.2 Energy and Greenhouse emissions
The Contractor shall implement fuel efficiency measures including, but not limited to:
(a) adequately maintaining vehicles so they are operating efficiently
(b) reducing idling time of construction vehicles and plant
(c) using alternative or low emission fuels, such as LPG or biodiesel/biodiesel blends for construction vehicles
and plant (e.g. 20% biodiesel – B20)
(d) using efficient equipment including vehicles, plant and office equipment
Where practicable, the Contractor shall use energy efficient office equipment and adopt energy efficient practices
within the on-site project offices.
The Contractor shall consider purchasing electricity from a renewable energy source (e.g. GreenPower) for electricity
to be used at all on-site project offices.
8.3 Recycled materials
The Contractor shall maintain a record of the use of recycled materials on the project, including steel, concrete, fill
and pavement material. The record shall be provided to the Principal upon completion of work, or at any other time
upon request.
The risk assessment referred to in clause 155.8.2 shall be undertaken by a qualified environmental consultant.
9
CONTAMINATION
If a Remediation Management Plan has been prepared, reference it here and place in an appendix.
The Contractor shall adhere to the Remediation Management Plan provided by the Principal for the
remediation/removal/disposal of contaminated material.
The Contractor shall engage a contamination specialist eligible for membership of DPTI’s Panel to develop a
Remediation Management Plan (RMP) to address contaminated material within the project area, in accordance
with the EPA Guidelines for Environmental Management of On-site Remediation (March 2006). The RMP shall
detail the nature, type and location of known contaminated material and describe the proposed method of
remediation/removal/disposal (including verification) for each. Remediation should start with the preparation of a
Remediation Action Plan (RAP) and an Environmental Management Plan (EMP) specific to site contamination. The
RAP should detail the methods, processes and controls of the remediation activities. The EMP should address all
the environmental management issues relating to contamination. These two plans combine to form the RMP.
Where soil will be removed from the project site, further sampling and analysis may be required (depending on the
requirements of the end user) and the RMP must include details of disposal options, end use and appropriate
classification of this material.
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
The Contractor shall implement the approved RMP during the course of the project.
10 ACID SULPHATE SOILS
The uncovering of acid sulphate soils is likely if the existing ground profile is to be excavated below the water table,
with or without dewatering. Where avoidance is not possible and some disturbance of acid sulphate soils occurs,
measures to manage the associated risks are required.. Investigations into the presence of acid sulphate soils are to
be completed in accordance with EPA Guideline: Site Contamination - Acid Sulphate Soils issued 2007. Detailed
management measures shall be incorporated into a Acid Sulphate Soils Management Plan as part of the overall
Contractor’s Environmental Management Plan (CEMP) in consultation with the EPA and in accordance with EPA
Guideline: Site Contamination - Acid Sulphate Soils and EPA Guideline: Environmental Management of On-site
Remediation.
The acid sulphate soils management plan should include as a minimum, proposed management strategies,
monitoring requirements and verification testing requirements for both the short and long term.
11 GROUNDWATER WELLS
The Contractor shall maintain an accurate register of the location of all groundwater wells within the Site.
Where well decommissioning is required, the Contractor shall decommission any operational, disused, abandoned
or uncovered groundwater wells, known or discovered, within the Site in accordance with the Natural Resources
Management Act 2004 unless these wells will be used for construction water or irrigation. Any appropriate
approvals for groundwater use for construction water or irrigation will need to be obtained by the Contractor.
12 ASBESTOS REMOVAL
All buildings to be demolished will be subject to an asbestos audit. The contractor undertaking the removal of
asbestos shall be licensed by SafeWork SA and have an approval (from SafeWork SA) to undertake the removal
activities. All asbestos removal shall be undertaken in accordance with the current Code of Practice for the Safe
Removal of Asbestos (2nd Edition) [NOSC: 2002(2005)].
All asbestos removed from buildings shall be transported by an appropriately EPA licensed transporter and
disposed of at an EPA licensed facility.
13 STORAGE AND HANDLING OF HYDROCARBONS AND HAZARDOUS LIQUIDS
Refuelling or maintenance of plant and equipment, mixing of cutting oil with bitumen or any other mobile or
stationary activity which may result in the spillage of a chemical, fuel or lubricant at any location with direct
drainage to a waterway, is not permitted without appropriate temporary bunding being provided. Refuelling
operations shall not be left unattended while in progress.
The Contractor shall ensure that chemical, fuel and lubricant storage areas are not located within 20 metres of
natural or built drainage lines, or on slopes steeper than 1:10.
14 WASTE MANAGEMENT
The Contractor shall be responsible for ensuring that the site is kept clear of litter. Sealed waste and recycling bins
shall be available on site for the collection and storage of wastes.
15 PROTECTION OF SITES OF CULTURAL AND NATURAL HERITAGE SIGNIFICANCE
Insert here any appropriate conditions from the Aboriginal Heritage Survey report, for example:
The Contractor shall not undertake any ground disturbing works within the Aboriginal Heritage Monitoring Areas until
Heritage Monitoring Area Clearance has been provided by the Superintendent.
The Contractor is required to carry out Aboriginal monitoring at the locations identified as Aboriginal Heritage
Monitoring Areas (AHMA) in the Aboriginal Cultural Heritage Management Plan. The Contractor shall be responsible
for arranging and ensuring the appropriate number and presence of Aboriginal Heritage Monitors for all ground
disturbing works within the AHMA. There are to be two Aboriginal Heritage Monitors per worksite while ground
disturbing works are conducted.
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 155
The Contractor shall be responsible for payment and arrangement of Aboriginal heritage monitors and to ensure
the appropriate number and presence of monitors for all ground disturbing works within the identified monitoring
areas. There are to be two Aboriginal heritage monitors per worksite while ground disturbing works are conducted.
The Contractor shall provide [specify desired frequency, eg bi-monthly, monthly etc] updates of the project to the
Aboriginal group representatives identified by the Principal.
The Contractor shall bunt off the site from [specify location of sensitive area] and shall ensure that no disturbance
occurs within the bunted area.
Heritage items are located at [insert locations of heritage items or attach a schedule]. If the Contractor has caused
structural damage to a building or structure of heritage significance, the Contractor shall arrange for the repairs of
damage required in a manner that is consistent with the character and fabric of the item. Where approval under the
Development Act is required, this shall be obtained by the Contractor prior to any rectification or repairs of
damage being undertaken.
When undertaking work that may affect a heritage site, the Contractor shall comply with the requirements of the
Conservation Plan for the site.
16 SUSTAINABILITY
The Contractor shall, as a minimum, implement sustainability activities and actions identified in the Sustainability
Implementation Plan. During the construction phase, the Contractor shall provide the Principal with quarterly
status/progress reports on the implementation of the actions/activities Sustainability Implementation Plan. Data
shall be made available at any time when requested by the Principal.
17 HOLD POINTS
The following is a summary of Hold Points referenced in this Part:
CLAUSE
REF.
HOLD POINT
RESPONSE TIME
2
Establishment of work zone around identified trees
5 working days
3
Removal of hollows
5 working days
4
Weed, Pest and Disease Control
5 working days
6
Submission of Blast Management Plan
10 working days
____________
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 160
160
OCCUPATIONAL HEALTH, SAFETY AND WELFARE
RISKS AND HAZARDS
List here any information the DPTI has in relation to hazards and risks at or in the vicinity of the workplace where
the construction work is to be carried out
__________
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 170
161
OCCUPATIONAL HEALTH, SAFETY AND WELFARE
RISKS AND HAZARDS
List here any information the DPTI has in relation to hazards and risks at or in the vicinity of the workplace where
the construction work is to be carried out
SENIOR SAFETY COORDINATOR, RAIL PROJECTS)
The Senior Safety Coordinator, Rail Projects is:
Mr Mitchell McDonald
..........................................
..........................................
__________
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 170
170
1.
ADDITIONAL RAILWAY REQUIREMENTS AND INFORMATION
CONTACT PERSONS
The appropriate Rail Authority for this Contract is ARTC / ASR / TransAdelaide.
..........................................................................
..........................................................................
..........................................................................
telephone .........................................................
2.
CLEARANCES FOR PASSAGE OF RAILWAY VEHICLES
The clearances for passage of railway vehicles are as follows:…
3.
SITE ACCESS LICENCE
Insert Site Access Licence here where appropriate
___________
Knet #3221569
Revision 0
1.
Specification: Contract Specific Requirements 175
DPTI PUBLIC TRANSPORT SERVICES OPERATIONS AND MAINTENANCE DIVISION
The majority of activities previously undertaken by TransAdelaide (TA) are now being undertaken by the staff of the
Public Transport Services Operations and Maintenance Division (PTSOM) of the Department for Transport, Energy
and Infrastructure for and on behalf of the Rail Commissioner.
Any reference in this Agreement to TransAdelaide (or TA) shall mean a reference to PTSOM.
Whilst transition arrangements are completed, TransAdelaide documents shall be used where an equivalent PTSOM
document does not exist.
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 180
180
1.
COMMUNITY CONSULTATION
COMMUNITY RELATIONS REPRESENTATIVE
The Contractor shall provide a Community Relations Representative until the Date of Practical Completion.
The Community Relations Representative shall:
(a) ensure the Superintendent is provided with accurate and timely information;
(b) be available for contact by local residents, businesses and community representatives at all reasonable
times to answer any questions and to address any concerns in relation to the Contract, in particular:
(c) provide information on planned traffic arrangements, including any temporary traffic switches, being
sought by users of the Contract and adjacent road and rail network; and
(d) provide information on planned construction operations being sought by affected and concerned residents,
businesses and occupants.
The Community Relations Representative shall refer all questions and issues concerning the road network outside
the Contractor’s Works to the Superintendent.
2.
TELEPHONE SERVICE
The Principal has established a 1300 project information telephone line for members of the community and broader
public to seek information, register complaints or concerns.
The Contractor shall establish a site-based telephone service with 24-hour answering machine for members of the
community to register complaints or concerns. The telephone service shall be connected prior to the
commencement of construction, and remain operational until 3 months after the Date of Construction Completion.
The telephone number shall be quoted on all correspondence applicable to the Contract, including letter drops and
other information issued to the community.
3.
PROJECT WEBSITE
A project website has been setup at www.infrastructure.sa.gov.au and the Contractor shall provide information and
data to the Superintendent for publication on the website including general project information, project plans,
reports, submissions, photographs, local traffic management information and other communications material.
Any plans, drawings, photographs, submissions or reports provided by the Contractor for this purpose shall be in a
format which is suitable for direct incorporation into the website.
Information shall be made available for the duration of the Contractor’s work and for up to 12 months after the
Date of Practical Completion.
4.
MEDIA EVENTS
The Superintendent will manage any media events associated with the commencement of construction or opening of
the project. The Contractor shall coordinate site logistics associated with media events and provide reasonable
cooperation with organising the event. The Contractor shall not erect or display promotional banners during such
media events.
The Contractor shall provide 3 weeks written notice to the Superintendent of the date for opening.
Other opportunities for media events, including the achievement of project milestones shall be notified to the
Superintendent at least 3 weeks prior to the expected event.
5.
HANDLING OF COMPLAINTS AND ENQUIRIES
The Contractor shall provide an information/complaints hotline to be available 24 hours a day as required by the
Superintendent, which may take the form of a dedicated mobile number. The person receiving complaints shall be
appropriately trained in community engagement and/or customer service and should have the ability to action the
complaint. This may include modification of the work site or a review of night activities.
Knet #3221569
Revision 0
Specification: Contract Specific Requirements 180
A complaint management procedure shall be developed for handling complaints in accordance with Clause 180.3.2
"Inquiries Received by the Contractor". At a minimum the procedure shall contain the following steps:
(a) Receive complaint and record details in a complaint register;
(b) Provide or prepare a response to the complaint made including confirmation of the consultation and / or
notification undertaken for the activity; and
(c) Advise complainant of actions undertaken as required.
The Superintendent or persons nominated by the Superintendent has the discretion to contact members of the
community to ascertain the level of satisfaction with the resolution of a dispute. Draft responses shall be provided
to the Superintendent in accordance with Clause 180.3.1 "General".
6.
SIGNS
The Contractor shall erect and maintain the accuracy of advisory signposting that is required to provide
information to Stakeholders.
____________
Knet #3221569
Download