Response 15-02-11 Future funding for flood and coastal erosion risk management: consultation on the future capital grant-in-aid allocation process in England Cornwall Council’s response to the public consultation, 24th November 2010-16th February 2011 1 Do you think that the existing funding prioritisation and allocation system should continue, in which Government focuses on funding the most cost-beneficial projects? We welcome the debate on changing the funding system. The existing system tends to benefit the most cost-effective schemes, which tend to be in more densely populated urban areas. Whilst this is understandable, the present system excludes many rural schemes that do not qualify under the present arrangements but nonetheless deserve consideration and a way forward. 2 Do you have any other comments or anything to add to the analysis in Section 1? We particularly welcome the inclusion of funding for surface water projects. We hope that the proposed arrangements will encourage joint funding partnerships, such as between LLFAs and private water companies where there are multiple benefits such as reduced highway flooding and reduced combined sewer overflows, for example. We also hope that it eases the way for private developers to part-fund wider schemes that provide benefits on a wider catchment scale and also unlock part-funding from central government. However, the inclusion of private funding requires a much faster response time for the central funding element than is achieved at present. We assume that the new arrangements will allow the local levy to be applied to local schemes, such as surface water management and ordinary watercourses and also to catchment-approach schemes, which can result in large downstream benefits for relatively minor upstream interventions. In all, a wider range of schemes should attract at least part funding than at present. The analysis does, however, assume that a similar level of central government funds will be available overall and if this is not the case then the advantages referred to will be lost. Funding formulae should take into account all flooding and erosion source risks including area/region specific such as wave induced high water which is 1 Response 15-02-11 less of an issue elsewhere in the country but a significant factor in the SW generally and specifically Cornwall and IOS. 3 Do you agree with the objectives in Section 2? If not, which would you change, or what others would you add? In order to achieve objective (i), the operating authorities will need to have some funds to invest, in the first place. This Section should not lose sight of the aspiration to provide the greatest support to the most deprived. The statement that ‘levels of activity will become based on people’s willingness to pay’, does not provide the correct message. There also needs to be recognition that the beneficiaries of flood management activities are not necessarily those who created the risk or are in a situation to pay for its management. The receptor is not necessarily the cause. 4 Do you agree with the guiding principles outlined in Section 3? If not, which would you change, or what others would you add? In general the principles appear to be right. However there may need to be some flexibility in the cost-benefit analysis in order to unlock match-funding. Some outcomes may be difficult to measure, such as scenic beauty and accessibility, particularly in relation to the coast which is enjoyed by far more people than live there. The provision for surface water management schemes to access part-funding for Grant-in-Aid is a big step forward as it may help to realise some of the actions identified within Surface Water Management Plans. We would like to see a clearer definition of property level resilience. Does this refer to grants for moveable flood gates, raising electric sockets, etc, or does it apply to community sand-bag schemes or small scale surface water schemes such as retro-fitting SUDS? Local Levy via the RFCC could be a useful way of “seed” funding potential FDGiA schemes to provide initial justification. This in turn can then help prioritise schemes/larger studies on the MTP which might otherwise have been below the consideration level. 5 In particular, do you agree that the costs of protecting new development should not fall to the general taxpayer, now or over the long term? We agree that new development should bear the costs of flood protection for that development if flood protection is required, and the construction of that 2 Response 15-02-11 development is justified within the context of PPS25. Where integrated flood risk management is required that crosses the boundaries of multiple developers the LLFA and the EA will need to take a coordinating role. We further feel that S.106 agreements may be justified to provide the partfunding element of flood protection measures that benefit the whole community within which a new development is situated. The retrospective date of January 2009 for excluding new developments from the funding formula may be unfair as it predates the Flood and Water Management Act. Also new development may have a long lead-in time from design and planning through to construction. We feel that there should be a period of notice provided rather than a retrospective cut-off date so that developers can take these issues on board and plan accordingly. Alignment with the SUDS approval and adoption timescale would seem appropriate. 6 Do you agree with the rationale for the ‘payment for outcomes’ approach? We would generally agree with the rationale as stated. Whilst focussing on households may be sensible, for the reasons provided in the document, there may be cases whereby they do not reflect the costbenefit implications. This is particularly so for coastal erosion whereby very few, if any, households may be directly affected but infrastructure, access and amenity are. Cost savings achieved are likely to result in a reduction in the level of protection provided. This then creates a circular reference in the calculations. If an initial proposal specifies protection for a 100 year event but this is scaled down to a 50 year event with, say, 30% cost savings, the cost-benefit calculations need to be repeated for the 50 year event, but are the 30% savings included in the final assessment? The proposal seems to indicate if an overall scheme cost can be reduced where it is for instance eligible for 80% FDGiA (20% from other source) the amount of other source money will also reduce. This seems rather unfair as a scheme that originally had effective approval for say £80k for a £100k scheme would have to be funded another £20k from elsewhere. If the overall scheme cost was reduced to say £80k the FDGiA does not cover the whole amount but still 80% (i.e.£64k) the remaining £16k to be found still from elsewhere. Whilst we would not necessarily say the whole scheme should be funded 100% (though if it still provides the same degree of protection etc. then perhaps it should) but we would have thought the FDGiA element should perhaps be re-evaluated to reflect the benefit from overall scheme savings slightly more in favour of the “other source” proportion to be found.e.g. saving of 20% overall shared evenly between FDGiA and other source. This would make the £80k reduced cost scheme £72k = FDGiA and £8k = other source. 3 Response 15-02-11 7 Do you agree that a ‘payment for outcomes’ system would be more likely to deliver the objectives stated in Section2, in comparison with the current prioritisation and allocation approach? An accompanying impact assessment provides a more detailed comparison. We believe that the proposed system is more likely to achieve the objectives than the existing system, not withstanding any reduction in total central funding available. In the case studies provided, the local input of funds is obtained from community groups, local chamber of commerce, local flood risk partners and “other community interest”. The case studies assume that this local input is easily forthcoming. There will need to be a degree of public awareness raising as the local taxpayer, private or business, will not readily accept responsibility to pay for rectifying problems generally seen as being not of their making. The EA and LLFA will need to coordinate funding partnerships. One way of increasing incentives to invest in flood risk management schemes would be for insurance companies to guarantee a reduction in premiums to those affected. Insurance companies may need to take a more active role in planning and investing in flood risk management along with the EA and LLFA. Revenue Support Grant (RSG) or whatever it now might be called? Is allocated to LA’s to provide funding source for ongoing maintenance etc. but in the past hasn’t been ring-fenced for this sort of work and consequently has often been “redirected” to other seemingly more pressing areas of Council business. In the future this money will be important to provide that ongoing provision for maintenance without which funding may not be supportive through FDGiA as this is not intended to replace years of underinvestment in day to day repair. 8 Do you have any comments or suggestions on the role of RFCCs and the local levy? The RFCCs have a role to play in coordinating the allocation of funds across a region, particularly with respect to schemes that cross LLFA boundaries. The new coastal role is a challenging one and the RFCCs will need to take account of the Shoreline Management Plans along with the Catchment Flood Management Plans, Surface Water Management Plans and Local Flood Risk Management Plans in addition to Outcomes of Measures. There may be a case for the LLFAs to have a greater say in the allocation of local levy funds, as it is the LLFA that is responsible for local flood risk management strategies, plans and actions. Local Levy via the RFCC could be a useful way of “seed” funding potential FDGiA schemes to provide initial justification. This in turn can then help prioritise schemes/larger studies on the MTP which might otherwise have 4 Response 15-02-11 been below the consideration level. 9 Do you have any comments on the analysis in Section 6, or your own views of the potential benefits and risks of the ‘payment for outcomes’ approach? We are unsure of the statement: “In every case, projects would only be deferred if the local area, local flood risk partnership and the RFCC between them all decide that the benefits are not sufficient to warrant the remaining costs involved, in lieu of other priorities at that time”. Surely a scheme can still be deferred by the RFCC, even though the local area/community believe it should go forward but are unable to secure the necessary match-funding or cost efficiencies to meet the formula requirements and so anticipate the local levy being used to support the scheme. The RFCC will need to consider how proposed schemes fit in with local strategies, as well as the other factors mentioned when deciding how to allocate top-up funds from the local levy or recommend deferment. The priorities for a LLFA may not fit entirely with the payment for outcomes formula. Whilst the inclusion of infrastructure and businesses in the OM is welcome, the fund ratio of 18:1 does not reflect the importance of some assets to isolated communities where the road link for instance effectively acts as the only means of access and would impact the community functioning capacity and economy disproportionately to one where several roads could act as alternatives. Likewise, where a business below may be flooded, this in itself might reflect the 18:1 inclusion but often in these coastal villages, the lower floor is also the only access to the upper floor which may be residential but unusable/inaccessible due to damage to the lower floor. Whilst we accept the principle of the lower rate for infrastructure and business premises generally, it would be useful to have some flexibility to enable a special case to be made in certain circumstances (this may be achievable through Moderation but not clear as my interpretation of this is that is strengthens the overall case but would not improve scoring). 10 Do you have any suggestions for improving the way a payment for outcomes systems might work? Ultimately, the goals are only achievable if the funding is available. The LLFAs are charged with determining Local Flood Risk Management Strategies. These then need to be turned into Actions. The inclusion of local flood risk issues, such as surface water and property level resilience within the FDGiA system is welcome, but will lead to an increase in the number of applications for funding. Central government funding for FDGiA should actually be increased in order to provide the same level of commitment across a wider remit. 5 Response 15-02-11 To provide economy of scale it would be useful to be able to combine schemes/studies where works of a similar repetitive nature allow e.g. a condition survey of multiple harbour sites. Overall, we agree that the proposed system should lead to a larger number of schemes becoming realised, but the ability to raise other sources of funding and efficiency savings may be over-optimistic. LLFAs will need to put extra resources into the preparation of funding bids and the coordination of local groups and funding streams. 6