Division 2 – Sitework Sitework 02200 Refer to Samet Corporation

advertisement
Division 2 – Sitework
Sitework 02200
Refer to Samet Corporation standard details and standards
PHASE
DATE
COMPLETE
DESCRIPTION
INITIAL
Dig Safely 1-800-632-4949
Soils Report has been reviewed on and water tables evaluated accordingly.
Job survey is reviewed; monuments and stakes are located. Limits of work are
established
Mandatory photo shoot of all existing conditions including adjoining properties and
existing erosion problems was done.
Existing vegetation to remain is protected.
Existing utility lines to remain are located, staked, and protected. Observe conditions
of uncovered lines. Verify utility companies have been notified. All lines to be
removed or abandoned are properly capped. If unknown lines are encountered, notify
appropriate parties. All contractors digging have obtained their own permit and each
permit number with effective dates has been recorded and put into _________________
file. Private locater has been used for private property
And his name and number are _____________________________________________?
Adjacent property is protected. Verify whether adjacent property owner is notified as
required by work or code.
Import or export haul routes have been approved by local agencies, if required.
Backfill materials are from approved source. They are installed in specified layers and
adequate compaction equipment is used. Relative density of backfill is checked. Walls
are properly cured before backfilling.
EROSION/ENV. CONTROL
Check to see if a National Pollution Discharge Efficiency System (NPDES) Notice of
Intention plan has been filed, if required and is being complied with.
Samet Corporation | Building Structures. Building Relationships.
Division 2 – Sitework
Sitework 02200
What are the temporary entrance requirements prior to starting work?
Erosion control maintenance has been assigned. DWQ logs are on site and are being
maintained every rain period and at least weekly.
Dust control is provided during all grading operations. Water truck should be on site
during all these operations. This was confirmed on date noted, with Project manager
and sub contractors
Stripping of site, preservation and depth of removal of top-soil, and location of
stockpile are performed and established. Location of stock pile has been passed on to
engineer and is on DENR approved dwg dated____________.
Drainage is provided continuously as excavation progresses, other dewatering methods
such as well points are provided, drainage ditches are maintained, and ponding does
not occur.
Seeding has been done by excavation contractor on date noted and ________________
seeding mixture [winter, summer, spring, and fall] was used as prescribed in approved
DENR plans.
Review erosion control plan and ensure that appropriate measures are undertaken
during the wet season. Make sure erosion control devices are replaced at the end of
each day’s work.
Verify that the construction sequence on the approved DENR plans is being followed.
Verify that there are no stream/wetland buffer zones or tree protection areas that need
to flagged and noted for protection.
See “COMPLETION” Section to verify that DENR has approved completed project.
Samet Corporation | Building Structures. Building Relationships.
Division 2 – Sitework
Sitework 02200
SITEWORK AND EXISTING VEGETATION
Refer to Samet Corporation standard details and standards.
PHASE
DATE
DESCRIPTION
COMPLETE
INITIAL
Existing trees and other vegetation to remain are protected as required. Barricades
and fencing are provided if required. Signage was posted on _______________________date
by ____________________________[contractor]
No traffic, parking, storage of materials, or debris allowed within drip line of trees.
Paints, solvents, oils, old plaster, and other debris is not placed in areas to receive
planting. Do not allow maintenance of construction equipment to be performed in
areas to receive planting.
In general, all deep utility work is to be done before soil preparation, all shallow utilities
such as irrigation laterals are done after soil preparation.
INSTALLATION
Observe excavation adjacent to existing trees. Unless otherwise required, do not allow
exposing of root systems; keep equipment beyond drip line.
Depth of cuts and other conditions required are met for retainage and/or reuse of onsite topsoil. Observe required stockpiling and that topsoil is not intermixed with
deleterious materials.
Subgrade is carried sufficiently below finish grade to provide depth of topsoil required.
Do not allow in subgrade debris that is detrimental to landscaping.
Existing vegetation not to be saved is removed as required.
Elevations of manholes, catch basins, valves, boxes, etc., are coordinated to finished
grades required on landscaping plans. Verify coordination to other drawings.
Backfill against foundation walls that receive planting is clean and free of rocks,
concrete, and debris.
COMPLETION
Existing trees and other vegetation are maintained by regular feeding and watering
during construction, if required.
Pruning of branches is performed only by qualified persons.
Ponding around base of existing trees does not occur.
Samet Corporation | Building Structures. Building Relationships.
Download