SPECIFICATION 904 NOISE WALLS Copyright MAIN ROADS Western Australia MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 1 of 18 SPECIFICATION 904 NOISE WALLS REVISION REGISTER Date 8 Jan 2010 Clause Number 904.2 Description of Revision Reference to Specification Authorised By SBDE 908 ANTI-GRAFFITI added EARTHWORKS deleted OPERATIONS added before Clause 904.31 904.36 Paragraph 3 amended Clause numbering and references corrected 904.91 Contract specific clause 904.91 amended 6 Dec 08 904.34 Replaced reference to Perth falling weight penetrometer with Perth sand penetrometer test SDE 1 Aug 06 Whole document Complete revision of Issue 1.1 to new format MCP MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 2 of 18 CONTENTS Clause Page No GENERAL ...................................................................................................................... 4 904.01 SCOPE ........................................................................................................ 4 904.02 REFERENCES ............................................................................................. 4 904.03 – 904.05 NOT USED........................................................................................ 5 PRODUCTS AND MATERIALS ..................................................................................... 5 904.06 904.07 904.08 904.09 CONCRETE FOOTINGS, POSTS AND WALL PANELS .......................... 5 BRICKS WALL PANELS AND PIERS .......................................................... 5 MORTAR...................................................................................................... 5 REINFORCING STEEL FOR CONCRETE FOOTINGS, POSTS AND WALL PANELS ............................................................................................ 6 904.10 LIMESTONE BLOCKS ................................................................................. 6 904.11 – 904.20 NOT USED........................................................................................ 6 SAMPLING AND TESTING ............................................................................................ 7 904.21 CONCRETE NOISE WALLS – SAMPLE PANEL ......................................... 7 904.22 BRICK NOISE WALLS – BRICKWORK UNITS ........................................... 7 904.23 BRICK NOISE WALLS - MORTAR .............................................................. 7 904.24 BRICK NOISE WALLS - SAMPLE PANEL ................................................... 8 904.25 LIMESTONE NOISE WALLS – LIMESTONE BLOCKS ............................. 8 904.26 LIMESTONE NOISE WALLS – MORTAR .................................................... 8 904.27 LIMESTONE NOISE WALLS – SAMPLE PANEL......................................... 8 904.28 – 904.30 NOT USED........................................................................................ 9 OPERATIONS ................................................................................................................ 9 904.31 EARTHWORKS ........................................................................................... 9 904.32 CLEARING AND TOPSOIL REMOVAL ........................................................ 9 904.33 EXCAVATION .............................................................................................. 9 904.34 ACCEPTANCE OF BEARING SURFACES TO CARRY LOADS................ 9 904.35 FOUNDATION IMPROVEMENT ................................................................ 10 904.36 PROTECTION OF BEARING SURFACES................................................. 10 904.37 BACKFILLING ............................................................................................ 11 904.38 UNSUITABLE AND EXCESS MATERIAL .................................................. 11 904.39 CONCRETE WORKS ................................................................................ 11 904.40 FOOTING TOLERANCES……………………………………………………. 12 904.41 STRIP FOOTING CONTROL JOINTS ……………………………………….12 904.42 CONCRETE NOISE WALL PANELS AND POSTS .................................... 12 904.43 CONCRETE WALL TOLERANCES ........................................................... 12 904.44 CONCRETE WALL PANEL SURFACE FINISH ......................................... 12 904.45 BRICKWORK ............................................................................................. 13 904.46 LIMESTONE BLOCKS ............................................................................... 15 904.47 – 904.80 NOT USED...................................................................................... 16 AS BUILT AND HANDOVER REQUIREMENTS .......................................................... 16 904.81 – 904.90 NOT USED...................................................................................... 16 CONTRACT SPECIFIC REQUIREMENTS ................................................................... 16 904.91 – 904.99 NOT USED...................................................................................... 16 MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 3 of 18 SPECIFICATION 904 NOISE WALLS GENERAL 904.01 SCOPE 1. The work under this specification consists of all operations in the supply and construction of noise walls including earthworks, concrete footings and columns, and materials for brick and limestone noise wall infill panels. 904.02 REFERENCES 1. Australian Standards, MAIN ROADS Western Australia Standards and MAIN ROADS Western Australia Test Methods are referred to in abbreviated form (e.g. AS 1234, MRS 67-08-43 or WA 123). For convenience, the full titles are given below: Australian Standards AS 1289 AS 1379 AS 3600 AS 3700 AS 3972 Methods of testing soils for engineering purposes The specification and supply of concrete Concrete structures Masonry structures Portland cement Australian/New Zealand Standards AS/NZS 2699.1 Built-in components for masonry construction AS/NZS 4455 Masonry Units and Segmental Pavers AS/NZS 4671 Steel Reinforcing Materials MAIN ROADS Test Methods MRWA 134.1 Dry Density Ratio MRWA 910.1 Chlorides and Total Soluble Salts in Soil and Water MRWA 915.1 Calcium Carbonate Content MAIN ROADS Specifications Specification 201 Specification 302 Specification 801 Specification 819 QUALITY SYSTEMS EARTHWORKS EXCAVATION AND BACKFILL FOR STRUCTURES FALSEWORK MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 4 of 18 Specification 820 Specification 821 Specification 822 Specification 901 Specification 905 Specification 908 CONCRETE FOR STRUCTURES FORMWORK STEEL REINFORCEMENT CONCRETE – GENERAL WORKS LIMESTONE RETAINING WALLS ANTI-GRAFFITI 904.03 – 904.05 NOT USED PRODUCTS AND MATERIALS 904.06 CONCRETE FOOTINGS, POSTS AND WALL PANELS 1. Concrete used in the construction of footings and any other concrete elements of noise walls shall be in accordance with the Drawings and Specification 901 CONCRETE - GENERAL WORKS. 2. Concrete used in the construction of posts wall panels and any other major structural concrete elements of noise walls shall be in accordance with the Drawings and Specification 820 CONCRETE FOR STRUCTURES. 904.07 BRICKS WALL PANELS AND PIERS 1. Bricks used in the construction of panels, piers and any other brick elements of noise walls shall be clay bricks, uniform in shape, texture, colour and size, with sharp arises, free from distortion and other defects. Bricks shall have a minimum compressive strength of 17MPa. Brick Properties 2. Bricks shall be in accordance with the dimensions and colours as shown on the Drawings. Dimensions and Colours 904.08 MORTAR 1. Mortar shall comply with AS 3700. Mortar shall consist of 1 part of Portland Cement, 1 part of building lime, 6 parts of fine aggregate and colouring pigments as required. The measured parts in mixes shall be mixed mechanically to an even colour and consistency with the minimum amount of water for workability. Admixtures, only when specified, shall be used as specified and in accordance with the manufacturer’s recommendations. Mortar colour shall be in accordance with the Drawings. Colouring pigments shall be thoroughly mixed with the cement before adding other components. Components and Proportions 2. Mortar mixed on site shall be used within 20 minutes of mixing. Retempering of mortar shall not be permitted. Any mortar which has begun to set prior to use shall be rejected. MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 5 of 18 904.09 REINFORCING STEEL FOR CONCRETE FOOTINGS, POSTS AND WALL PANELS 1. Reinforcing steel used in the construction of reinforced concrete footings, posts and wall panels and any other reinforced concrete elements of noise walls shall be in accordance with AS/NZS 4671 and Specification 822 STEEL REINFORCEMENT. Reinforcement 2. The Contractor shall store reinforcing steel above ground level and shall protect it from damage and deterioration. 3. Reinforcement placed in the Works shall be clean and free from all loose rust, mill-scale, dirt, grease, and other foreign substances which would impair the bond between steel and concrete. 4. After being placed in position, all reinforcement shall be maintained by the Contractor in a clean condition until it is embedded in the concrete. 904.10 LIMESTONE BLOCKS 1. The stone used for the retaining walls shall be natural or reconstituted limestone with individual blocks being free from any foreign matter, shakes, pockets, veins or other defects and generally sound and clean and of uniform colour and texture. Limestone Properties 2. Limestone blocks shall also be in accordance with the dimensions and colours as shown on the Drawings and conform to the following requirements: Quality a) Calcium Carbonate Content; 60% minimum by weight in accordance with WA 915.1 Dimensions b) Dry Density; 1500 kg/m3 minimum tested by direct measurement, the weight of a known size cube/core after oven drying at 45 degrees Celsius for 12 hours c) Unconfined Compression Strength; 1.7MPa for natural limestone and 2.5MPa for reconstituted limestone tested using a core/cube sample cut to normal test size to be tested for crushing strength. d) Dimensions; As indicated on the Drawings with a tolerance of + 15mm. 904.11 – 904.20 NOT USED MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 6 of 18 SAMPLING AND TESTING 904.21 CONCRETE NOISE WALLS – SAMPLE PANEL 1. The Contractor shall construct an 8 m long, full height sample panel of wall as part of the Works for the consideration of the Superintendent to become the approved sample panel. Further fabrication or installation of noise walls shall not commence until the sample panel has been approved by the Superintendent. HOLD POINT 2. Concrete testing shall be in accordance with Specification 820 CONCRETE FOR STRUCTURES. 904.22 BRICK NOISE WALLS – BRICKWORK UNITS 1. The Contractor shall submit samples of brickwork units, with the manufacturer’s certificate for approval, to the Superintendent before placing orders. The manufacturer’s certificate shall show compressive strength, tensile strength and absorption values of the bricks. The samples shall indicate the full range of texture and colour and consist of at least six units. Test certificates for compliance shall be 1 per 2000 bricks. Units built into the Works shall conform to and fall within the range of appearance properties of the approved samples. 904.23 HOLD POINT BRICK NOISE WALLS - MORTAR 1. The Contractor shall prepare samples of mortar for brickwork for the approval of the Superintendent. Mortar used in the Works shall conform to the approved mix and samples as specified on the Drawings. Samples 2. Mortar shall be prepared in accordance with Clause 904.05. Mortar shall be classification M3 and when tested in accordance with AS 3700 shall achieve sufficient compressive strength to meet requirements of Table 3.1 of AS3700 for characteristic compression strength of masonry. Preparation and Test Results 3. The Contractor shall undertake a mortar compression test at the laboratory at the beginning of the Works to establish the compressive strength as required by the Specification. The Contactor shall undertake mortar compression tests using site mixes on regular bases to maintain the required compressive strength results. Frequency of testing on site shall be one test every 200m of wall. Method of sampling and testing shall be in accordance with AS 3700. Sampling MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 7 of 18 904.24 BRICK NOISE WALLS - SAMPLE PANEL 1. The Contractor shall construct an 8m long, full height sample panel of wall as part of the Works and for the approval of the Superintendent. Joints shall be finished in accordance with the Drawings. The Works shall conform to the approved sample panel. Further brickwork associated with the Works shall not commence until the sample panel has been approved by the Superintendent. The sample panel may be used as a section of the noise wall. 904.25 LIMESTONE NOISE WALLS – LIMESTONE BLOCKS 1. The Contractor shall submit samples of limestone blocks, with the manufacturer’s certificate for approval, to the Superintendent before placing orders. Testing certificates for compliance to be 1 per 200 blocks for natural limestone and 1 per 500 for reconstituted limestone. The manufacturer’s certificate shall show compressive strength, dry density and calcium carbonate content values of the blocks. The samples shall indicate the full range of texture and colour and consist of at least 6 units. Units built into the Works shall conform to and fall within the range of appearance properties of the approved samples. 904.26 HOLD POINT HOLD POINT LIMESTONE NOISE WALLS – MORTAR 1. The Contractor shall prepare samples of mortar for limestone jointing for the approval of the Superintendent. Mortar used in the Works shall conform to the approved mix and samples as specified on the Drawings. Samples 2. When tested in accordance with AS 3700 mortar shall achieve a compressive strength of at least 2.8MPa for samples taken from site mixes and 4.2MPa for samples taken from laboratory mixes. Test Results 3. The Contractor shall undertake a mortar compression test at the laboratory at the beginning of the Works to establish the compressive strength as required by the Specification. The Contactor shall undertake mortar compression tests using site mixes on regular bases to maintain the required compressive strength results. Frequency of testing on site shall be one test every 200m of wall. Method of sampling and testing shall be in accordance with AS 3700. Sampling 904.27 LIMESTONE NOISE WALLS – SAMPLE PANEL 1. The Contractor shall construct an 8m long, full height sample panel of wall as part of the Works and for the approval of the Superintendent. Joints shall be finished in accordance with the Drawings. The Works shall conform to the approved sample panel. Further Works shall not commence until the sample panel has been approved by the Superintendent. The sample panel may be a section of the retaining wall. MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 HOLD POINT Page 8 of 18 904.28 – 904.30 NOT USED OPERATIONS 904.31EARTHWORKS 1. This Section of the Specification covers earthworks for the construction of the noise wall strip footings and includes excavation, foundation improvement and backfilling. Earthworks item shall be carried out as specified hereafter and as detailed on the Drawings. 904.32 CLEARING AND TOPSOIL REMOVAL 1. The Contractor shall clear a sufficient width of the work site at the wall location prior to starting excavation. Topsoil in the cleared area shall be removed to a minimum depth of 100mm by the Contractor and stockpiled for reuse at a location approved by the Superintendent. The stockpiled topsoil shall be respread by the Contractor over the cleared area to a minimum depth of 70mm and surplus removed from site. 904.33 EXCAVATION 1. The Contractor shall excavate to the lines and grades shown on the Drawings. The actual dimensions for excavation shall in all cases be no more than that required for the placement of protective works if necessary and any working space required. 2. back-fill. The Contractor shall stockpile excavated material for use as 3. Any excavated material considered unsuitable by the Superintendent shall be removed to the nominated spoil site. 4. If excavation below the footing is required, it shall be backfilled and compacted with embankment quality material in accordance with Specification 302 EARTHWORKS. The back-fill shall be compacted to at least the density of the surrounding material if not specified on the Drawings. 904.34 ACCEPTANCE OF BEARING SURFACES TO CARRY LOADS 1. When foundations have been excavated, all the soil below the strip footings shall be compacted by the Contractor. MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Bearing Surface Page 9 of 18 2. Undisturbed soil below footings shall be proof compacted by the Contractor with a plate compactor, and disturbed soil below foundations shall be compacted to a minimum dry density of 96 % to the minimum depth as given on the Drawings and tested in accordance with WA 134.1. 3. When foundations in Perth sands have been excavated, the Contractor shall compact the bearing surface and test the compaction in accordance with Soil strength and consolidation tests – Determination of the penetration resistance of a soil – Perth sand penetrometer test, as set out in AS1289.6.3.3. The minimum acceptable blow count is 10 blows per 300 mm for the whole depth as shown on the Drawings. 4. Testing frequency shall be 1 test per 10m of wall length, or 1 test per wall panel, whichever is the greater frequency. 5. If the soil does not meet the requirements of this Clause, it shall be compacted by the Contractor until it complies, unless otherwise directed by the Superintendent. 904.35 FOUNDATION IMPROVEMENT 1. If directed by the Superintendent, the soil shall be excavated and either re-compacted by the Contractor if it meets the requirements of Clause 904.33 or replaced by compacted layers of suitable fill satisfying the requirements of Clause 904.33. The excavation shall be carried out to a depth as directed by the Superintendent. 2. The thickness of each layer of backfill material shall be limited to enable the specified compaction to be obtained for the full depth of the layer for the equipment being used and in any case shall not exceed 300mm before compaction. 3. The backfilled material shall be re-tested by the Contractor to ensure compliance with Clause 904.34. 904.36 PROTECTION OF BEARING SURFACES 1. The exposed bearing surface at the bottom of each excavation shall be adequately protected from disturbance by the Contractor's operations or by the action of stormwater or ground water. Protection 2. Any material at the bottom of an excavation which becomes unsuitable shall be removed and replaced with fill complying with Clause 904.33 and compacted in accordance with Clause 904.34 or replaced by additional blinding concrete. 3. Alternatively, the disturbed surface may be lightly watered and compacted with a hand operated mechanical compactor until it complies with Clause 904.34. MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 10 of 18 904.37 904.37.01 BACKFILLING GENERAL 1. The Contractor shall backfill around foundations and noise walls as shown on the Drawings using suitable material excavated from the foundations unless otherwise approved by the Superintendent. 2. The fill shall be placed carefully by the Contractor so as not to damage the wall and concrete foundations. 3. The Contractor shall place fill in continuous horizontal layers of not more than 300mm uncompacted thickness and shall separately compact each layer to a similar density to the surrounding material. 904.37.02 SUITABLE FILL MATERIAL 1. Suitable fill material shall meet the requirements of Specification 302 EARTHWORKS. 904.38 UNSUITABLE AND EXCESS MATERIAL 1. All unsuitable and excess material shall be removed from site and disposed of by the Contractor. 904.39 CONCRETE WORKS 1. The Contractor shall carry out the construction of concrete footings to the dimensions shown on the Drawings. Concrete Classes used for the construction of the concrete footings shall be as shown on the Drawings, and conform to AS 1379. The concrete construction requirements shall comply with Specification 901 CONCRETE GENERAL WORKS. 2. The Contractor shall advise the Superintendent of the time and date of concrete placement not less than 24 hours prior to any proposed placement. 904.40 HOLD POINT FOOTING – TOLERANCES a) Variation of dimensions in plan and elevation ± 15mm b) Misplacement of eccentricity of centreline ± 10mm c) Variation in specified level ± 10mm MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 11 of 18 904.41 STRIP FOOTING CONTROL JOINTS 1. The Contractor shall construct construction joints at maximum intervals of 16m and at the locations shown on the Drawings. 2. Materials used for the joints (such as dowels, grease, caps and Fortecon layers) and installation details shall be in accordance with the Drawings. 904.42 CONCRETE NOISE WALL PANELS AND POSTS 1. The Contractor shall carry out the construction of major concrete noise wall elements such as panels and posts to the dimensions shown on the Drawings. Concrete Classes used for the construction of the concrete elements shall be as shown on the Drawings, and conform to AS 1379. The concrete construction requirements shall comply with Specification 820 CONCRETE FOR STRUCTURES. 904.43 CONCRETE WALL TOLERANCES 1. Concrete noise walls shall be constructed to the following tolerances: a) Variation from vertical or specified batter ± 10mm b) Misplacement or eccentricity of centreline ± 10mm c) Variation from specified level of surfaces ± 10mm d) Horizontal deviation (bow) edge 904.44 + 10mm over a 2m straight CONCRETE WALL PANEL SURFACE FINISH 1. Concrete wall panel surface shall be Class 2 grey finish in accordance with AS 3610 in the first instance unless specified otherwise on the Drawings. Initial Surface Finish 2. Further surface treatment such as painting shall be preceded by cleaning by water blasting. 3. Further surface treatment such as painting system, patterns, textures etc. shall be specified in detail by the designer to the specific individual requirements of the Project. MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Further Surface Treatment Page 12 of 18 904.45 904.45.01 BRICKWORK GENERAL 1. The Contractor shall stack bricks on supports clear of the ground and keep them dry and free from dust, dirt and staining and shall cover them with tarpaulins or plastic sheeting. 2. Bricks shall not be laid in wet weather. 3. The Contractor shall set out the Works according to the Drawings with no part rising more than 1000mm above the adjacent unfinished brickwork. Corners and other advanced rising work shall be racked by the Contractor. Setting Out 4. Bricks moved after initial laying shall be re-laid in fresh mortar by the Contractor. 5. New brickwork shall be temporarily braced by the Contractor to withstand lateral loads. 6. The Contractor shall build brickwork having 76mm bricks to a gauge of 7 courses to 600mm. 7. The Contractor shall build all walls in stretcher bond unless otherwise shown on the Drawings. Brickwork Bond 8. The Contractor shall lay the first bed joint on footings, and solid blocks on a full bed of mortar. 904.45.02 JOINTS 1. The Contractor shall lay bricks on a full bed of mortar with frogs (if any) uppermost and shall fill perp ends solidly with mortar. 2. The Contractor shall form joints uniformly in external facework to suit gauge and to match existing, unless otherwise specified, and shall work joints with the jointing tool to a dense, smooth finish. 3. The Contractor shall cut off joints flush in walls that are not exposed to view and will not be rendered or plastered. The Contractor shall rake out joints to 5mm depth in brickwork to be rendered or plastered. The Contractor shall roll joints in facing bricks or walls exposed to view. 904.45.03 Joint Finishes FACEWORK 1. The Contractor shall set out face work to suit bends and to avoid cutting of bricks. MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Facework Page 13 of 18 2. The Contractor shall start face work approximately two courses below adjacent finished ground level. 3. The Contractor shall lay face brick to avoid changes of colour beyond the range of bricks in the approved sample panel. 4. The Contractor shall keep perp ends in alternate courses in vertical alignment. 904.45.04 DAMP - PROOF COURSE 1. The Contractor shall use Cementaid Everdure Caltite additive to provide a damp-proof course. 2. The Contractor shall mix the additive with the mortar and apply it from the footing to the top joint of the first course immediately above ground. 904.45.05 Location BRICKWORK CLEANING 1. The Contractor shall clean brickwork on completion, and shall take care to protect adjacent surfaces from cleaning solutions. 2. The Contractor shall not apply cleaning solutions to joints, and shall not scrub joints. 3. The Contractor shall consult the brick manufacturer before attempting to remove unusual stains and shall obtain approval from the Superintendent before commencing cleaning. Brick Stains 4. The Contractor shall wash brickwork with water after cleaning and shall mop off surplus water with a clean sponge. 5. To remove mortar droppings from clay brickwork, the Contractor shall drench the brickwork with water before applying the cleaning solution. 904.45.06 BRICK MASONRY CONTROL JOINTS 1. The Contractor shall install control joints at a maximum distance of 16m or at the locations shown on the Drawings. 2. Control joints shall consist of galvanised expansion ties, backing material and sealant as specified on the Drawings. 3. Materials used for masonry control joints and installation details shall be in accordance with the Drawings. MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 14 of 18 904.46 904.46.01 LIMESTONE BLOCKS GENERAL 1. The Contractor shall stack limestone blocks on supports clear of the ground and keep them dry and free from dust, dirt and staining and shall cover them with tarpaulins or plastic sheeting. 2. Limestone blocks shall not be laid in wet weather. 3. The Contractor shall set out the Works according to the Drawings. 4. The first course of units shall be laid on top of the prepared bedding sand and be levelled and checked for alignment. 5. Additional courses shall be laid in squared work with joints fully mortared and levelled and checked for alignment. 6. 904.46.02 The walls shall be laid with a front face batter of 1H:50V. JOINTS 1. The Contractor shall lay blocks on a full bed of mortar and shall fill perp ends solidly with mortar. 2. Wall Joints Mortar joints shall be nominally 20mm in width. 3. The joint shall be raked back from the block face so that the joint can be faced at a later date with cream coloured mortar to match the limestone colour. 904.46.03 FACING 1. The Contractor shall prepare trial mortar mixes for facing to match the limestone colour. Trial mortar mixes shall be prepared until a suitable match is obtained as approved by the Superintendent. 2. The facing shall occur in a single operation after the wall has been completed and all movement has been taken up. 3. The exposed face shall be cleaned of all excess mortar as the work progresses. 904.46.03 FINISHING TOLERANCES 1. Limestone retaining walls shall be laid to the following tolerances: a) Horizontal position of any element in plan b) Maximum deviation from plumb MAIN ROADS Western Australia Contract xxx/xx + 25mm + 15mm per 3m height Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 15 of 18 c) Maximum horizontal deviation (AS 3700 App H) + 10mm over a 2m edge d) Deviation in any bed joint from horizontal in any 10m or + 15mm total + 10mm e) Deviation in thickness of bed joint or perp end + 10mm f) Maximum step between blocks block to block + 10mm 904.47 – 904.80 NOT USED AS BUILT AND HANDOVER REQUIREMENTS 904.81 – 904.90 NOT USED CONTRACT SPECIFIC REQUIREMENTS 904.91 – 904.99 NOT USED MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 16 of 18 SPECIFICATION 904 GUIDANCE NOTES DELETE THESE GUIDANCE NOTES FROM FINAL DOCUMENT AFTER USING FOR REFERENCE All edits to downloaded TDP documents shall be tracked (most word processing software allows this to be done automatically). Deletions shall be struck through e.g. example. Insertions shall be in italics e.g. example. If all information relating to a clause is deleted then the clause number should be retained and the words "NOT USED" should be inserted. The proposed documents with tracked changes shall be submitted to the Project Manager for review, prior to printing the final batch of documents. When this final printing is carried out, the tracked changes option is to be turned off. The Custodian of this specification is the Senior Design Engineer. -------------------------------------------------------------------------------------------------------------1. GENERAL This Specification has been written to cover concrete, brick and limestone noise walls. If only one type is specified in the Works, delete other clauses relating to the other wall types. 2. LOADS: CLAUSE 904.34 ACCEPTANCE OF BEARING SURFACES TO CARRY NOTE: This is for granular materials. Alternative Specification may be required for other materials 3. CLAUSE 904.44 CONCRETE WALL PANEL SURFACE FINISH: Need to insert the detailed surface finish treatment based on the contract specific requirements at 904.44.3 or delete sub-clause 904.44.3. 4. CLAUSE 904.91 ANTI-GRAFFITI PAINT Insert clause 904.91 under CONTRACT SPECIFIC REQUIREMENTS if required. CONTRACT SPECIFIC REQUIREMENTS TO ADD OR DELETE The following clauses are to be placed under the CONTRACT SPECIFIC REQUIREMENTS as required. 904.91 ANTI-GRAFFITI COATING SYSTEMS 1. Anti-graffiti paint coating systems shall be non-sacrificial (except where the coating is to be installed on a limestone substrate) clear or pigmented coating to a specified colour and comply with the requirements of Specification 908 ANTI-GRAFFITI. 2. The Contractor shall apply anti-graffiti paint only to the roadside face of the noise wall or as specified on the Drawings. MAIN ROADS Western Australia Contract xxx/xx Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 17 of 18 SPECIFICATION AMENDMENT CHECKLIST Specification Name: No: 904 Revision No: ______Title: NOISE WALLS Project Manager: Name: _______________Signature: _____________Date:______ Checked By: Name: _______________Signature: _______________Date:______ Contract No: ______Contract Description: __________________________________ ITEM DESCRIPTION Note: approved. SIGN OFF All changes/amendments must be shown in Tracked Change mode until 1. Project Manager has reviewed Specification and identified Additions and Amendments. 2. CONTRACT SPECIFIC REQUIREMENTS addressed? – Contract specific materials/products/clauses added? (Refer Specification Guidance Notes for guidance). 3. Any unlisted Materials/Products proposed and approved by the Project Manager? – if “Yes” provide details at 15. 4. Standard Clauses amended? – MUST SEEK approval from MCP. 5. Clause deletions shown as ‘NOT USED’. 6. Appropriate INSPECTION & TESTING parameters included in Spec 201 (Test Methods, Minimum Testing Frequencies verified). 7. ANNEXURES completed (Refer Specification Guidance Notes). 8. HANDOVER and AS BUILT requirements addressed. 9. Main Roads QS has approved changes to SMM. 10. Project Manager certifies completed Specification reflects intent of the design. 11. Completed Specification – independent verification arranged by Project Manager 12. Project Manager’s review completed. 13. SPECIFICATION GUIDANCE NOTES deleted. 14. TABLE OF CONTENTS updated. 15 Supporting information prepared and submitted to Project Manager. Further action necessary: Signed: MAIN ROADS Western Australia Contract xxx/xx (Project Manager) Date: _______________ Specification 904 Noise Walls Document 04/10151 Issue 13/01/10 Page 18 of 18